461-sl5

download 461-sl5

of 28

Transcript of 461-sl5

  • 8/11/2019 461-sl5

    1/28

    Thisimagecannotcurrently bedisplayed.

    ENCE4610

    Foundation

    Analysis

    and

    DesignShallow FoundationsTotal and Differential Settlement

    Schmertmanns Method

  • 8/11/2019 461-sl5

    2/28

    Strength

    Requirements Geotechnical Strength

    Requirements Design to prevent failure bysoil shear failure

    Geotechnical strength forshear failure is referred to asthe bearing capacity of the

    soil Analysis usually performed by

    ASD analysis; LRFD becomingmore common

    Structural StrengthRequirements

    Design to avoid structuralfailure of foundationcomponents

    Similar to other structuralanalyses

    Most common strengthrequirement: avoid bearingcapacity failure

    Thisimagecannotcurrently bedisplayed.

  • 8/11/2019 461-sl5

    3/28

    Serviceability

    Considerations Most common issue

    in serviceability:settlement

    Thisimagecannotcurrently bedisplayed.

    Thisimagecannotcurrently bedisplayed.

  • 8/11/2019 461-sl5

    4/28

    TypesofSettlement Definitions of

    Settlemento Absolute settlement,

    usually associatedwith uniform/totalsettlement

    o Angular distortionsettlement, usuallyassociated withdifferential settlement(ratio of settlement todistance betweenfoundations andstructures)

  • 8/11/2019 461-sl5

    5/28

    FactorstoDetermine

    Acceptable

    Settlement Connections with existing

    structures Utility Lines

    Total settlement ofpermanent facilities canharm or sever connectionsto outside utilities such as

    water, natural gas, andsewer lines. Water and sewer lines may

    leak contributing tolocalised wetting of the soilprofile and aggravating

    differential displacement. Leaking gas from breaks

    caused by settlement canlead to explosions.

    Surface Drainage

    Access

    Aesthetics Material of structure (steel,

    concrete)

    Usage Requirements

    Settlement ofbridges/overpasses vs.settlement of embankments,the bump in the bridge

  • 8/11/2019 461-sl5

    6/28

    Typical

    Values

    of

    Acceptable

    SettlementThisimagecannotcurrently bedisplayed.

    Thisimagecannotcurrently bedisplayed.

    Thisimagecannotcurrently bedisplayed.

  • 8/11/2019 461-sl5

    7/28

    Example

    of

    Settlement

    Calculations Given Steel framed office building, 20' column spacing Supported on spread footings founded on clayey

    soil

    Find Allowable total settlement

    Allowable differential settlement

    Solution Typical total settlement specification = 4 (Frames

    structure)

    Use = 1/500 (Steel and concrete frame); du

    =(1/500)(20') = 0.04' = 0.5

  • 8/11/2019 461-sl5

    8/28

    Schmertmanns

    Method:

    Procedure

    and

    Example Given

    o 6 x 24 footing, shown below

    o 2 ksf applied bearing pressureo Soil Profile and foundation

    depth as shown below

    Note that N160 arecorrected for both

    overburden and hammerefficiency

    Findo Settlement in inches at the

    end of constructiono Settlement in inches one (1)

    year after the end ofconstruction

  • 8/11/2019 461-sl5

    9/28

    Schmertmanns MethodStep1:DrawtheStrainInfluenceDiagram,

    Compute

    IzbatSurface Strain influence

    diagrams for squareand continuousfoundations areshown at the right

    Compute Lf/Bf(Equivalent Footing)o Uniform loading, so Lf/Bf

    = L/B = 24/6 = 4

    o For L/B = 1, Iz|z = 0 = 0.1

    o For L/B = 10, Iz|z = 0 = 0.2

    o By linear interpolation, forL/B = 4, Iz|z = 0 = 0.133

  • 8/11/2019 461-sl5

    10/28

    Schmertmanns MethodStep

    2:

    Draw

    the

    Strain

    Influence

    Diagram,

    Compute

    Maximum

    Depth

    of

    Influence

    Compute DI

    o Uniform loading, so Lf/Bf =

    L/B = 24/6 = 4

    o For L/B = 1, DI = 2Bfo For L/B = 10, DI = 4Bfo By linear interpolation, for

    L/B = 4, DI = 8Bf/3

    o For B = 6, DI = (8)(6)/(3) =16

  • 8/11/2019 461-sl5

    11/28

    Schmertmanns MethodStep

    3:

    Draw

    the

    Strain

    Influence

    Diagram,

    Determine

    Depth

    of

    Peak

    Strain

    Influence

    Factor

    Compute DIP

    o Uniform loading, so Lf/Bf =

    L/B = 24/6 = 4

    o For L/B = 1, DIP = Bf/2

    o For L/B = 10, DIP = Bfo By linear interpolation, for

    L/B = 4, DIP = 2Bf/3

    o For B = 6, DIP = (2)(6)/(3) =4

    o Alternate: DIP = DI/4

  • 8/11/2019 461-sl5

    12/28

    Schmertmanns MethodStep

    4:

    Draw

    the

    Strain

    Influence

    Diagram,

    Determine

    Peak

    Strain

    Influence

    Factor

    Compute IZPo DIP = (2)(6)/(3) = 4o This is 4 below the foundation;

    since the foundation is 3below the surface, the depthof the peak strain influence

    factor is 3 + 4 = 7 below thesoil surface (important foreffective stress computations)

    o IZP=0.5 + 0.1(p/pop)0.5

    o Increase in stress at depth of

    footing

    p = 2 ksf (3)(0.115kcf) = 1.655 ksfo pop = (3)(0.115) + (3)(0.125) +

    (1)(120) = 0.840 ksfo IZP = 0.5 + 0.1(1.665/0.840)

    0.5 =0.64

  • 8/11/2019 461-sl5

    13/28

    SchmertmansMethod

    Step

    5:

    Draw

    the

    Strain

    Influence

    Diagram

    Helpful Guidelines:o The depth of the peak value

    of the strain influence isfixed. To aid in thecomputation, develop thelayering such that one ofthe layer boundaries occursat this depth even though itrequires that an actual soil

    layer be sub-divided.o Limit the top layer as well as

    the layer immediately belowthe peak value of influencefactor, Izp, to 2/3Bf or less toadequately represent thevariation of the influencefactor within DIP.

    o Limit maximum layerthickness to 10 ft (3 m) orless.

    o Match the layer boundarywith the subsurface profile

    layering.

    Layer Boundaries are SOLID

    Layer Mid-Points are DASHED

  • 8/11/2019 461-sl5

    14/28

    Schmertmanns MethodStep

    6:

    Determine

    the

    Values

    of

    Elastic

    Modulus

    Estimate from SPT Value

    o Layer 1: Sandy Silt, Es =4(N160) = (4)(25) = 100 tsf =200 ksf

    o Layer 2: Coarse Sand, Es =10(N160) = (10)(30) = 300 tsf =

    600 ksfo Layer 3: Coarse Sand, Es =

    10(N160) = (10)(30) = 300 tsf =600 ksf

    o Layer 4: Sandy Gravel, Es =12(N1

    60) = (12)(68) = 816 tsf =

    1632 ksf

    Values computed in thisfashion must be correctedby a factor X

  • 8/11/2019 461-sl5

    15/28

    Schmertmanns MethodStep

    6:

    Determine

    the

    Values

    of

    Elastic

    Modulus

    Modulus of Elasticity

    Correction Factor Xo X = 1.25 for Lf/Bf = 1

    o X = 1.75 for Lf/Bf > 10

    o

    By linear interpolation, forLf/Bf = 4, X = 1.42

    Corrected Values of Eso 1: (100)(1.42) = 142 tsf

    o 2: (300)(1.42) = 426 tsfo 3: (300)(1.42) = 426 tsf

    o 4: (816)(1.42) = 1159 tsf

  • 8/11/2019 461-sl5

    16/28

    Schmertmanns MethodStep7:ComputeBasicTotalSettlement

    Basic Formula for

    Schmertmanns Methodo We first concentrate on

    computing thesummation, which willrepresent the settlement

    divided by the appliedbearing pressure

    =

    = =

    s

    zci

    n

    iii

    XE

    IHH

    HpCCS1

    21

  • 8/11/2019 461-sl5

    17/28

    Schmertmanns MethodStep8:DetermineEmbedmentandCreepFactors

    896.01655

    115'35.01

    5.01

    1

    1

    =

    =

    =

    pcf

    pcfC

    p

    pC o

    Embedment Factor Creep Factor

    2.11.0

    1log2.01

    year,oneofendAt

    1on,constructiofendFor

    1.0log2.01

    102

    2

    102

    =+=

    =

    +=

    C

    C

    tC

    years

  • 8/11/2019 461-sl5

    18/28

    Schmertmanns Method

    Step

    9:

    Determine

    Settlement

    at

    End

    of

    ConstructionStep10:DetermineSettlementatEndofOneYear

    End of Construction

    End of One Year

    "130.0

    )ksf2tsf1)(in/tsf1760.0)(ksf1.655)(1)(896.0(

    1

    21

    =

    =

    = =

    i

    i

    n

    i

    ii

    S

    /S

    HpCCS

    "156.0

    )ksf2tsf1)(in/tsf1760.0)(ksf1.655)(2.1)(896.0(

    1

    21

    =

    =

    = =

    i

    i

    n

    i

    ii

    S

    /S

    HpCCS

  • 8/11/2019 461-sl5

    19/28

    Chartfor

    Interpolated

    Values

    S ttl t B i

  • 8/11/2019 461-sl5

    20/28

    Settlement

    vs.

    Bearing

    Capacity

    (Shear

    Failure)

  • 8/11/2019 461-sl5

    21/28

    Bearing

    Capacity

    ChartsExample

  • 8/11/2019 461-sl5

    22/28

    C t B i

  • 8/11/2019 461-sl5

    23/28

    Comments

    on

    Bearing

    Capacity

    Chart

    Example

    Li h l L d d F i d

  • 8/11/2019 461-sl5

    24/28

    LightlyLoadedFootingsand

    Presumptive

    Bearing

    Pressures Lightly loaded footings are

    those which meet thefollowing criteria:o Square, circular, or rectangular

    footings subjected to vertical loadsless than 200 kN (45 kips)

    o Continuous footings subjected tovertical loads less than 60 kN/m (4kips/ft)

    Include typical one andtwo-story wood framebuildings and other similarstructures

    A conservative approach;

    normally easier in thesecases to design aconservative structure thanto perform the analysis

    The use of presumptive bearingcapacities for shallow foundationsbearing in soils is not recommended forfinal design of shallow foundations for

    transportation structures, especiallybridges. Guesses about the geologyand nature of a site and theapplication of a presumptive valuefrom generalizations in codes or in thetechnical literature are not a substitutefor an adequate site-specific

    subsurface investigation andlaboratory testing program. As anexception, presumptive bearing valuesare sometimes used for the preliminaryevaluation of shallow foundationfeasibility and estimation of footingdimensions for preliminary

    constructability or cost evaluations.

    Presumpti e Bearing Pressures

  • 8/11/2019 461-sl5

    25/28

    PresumptiveBearingPressures

    SandsAllowable Bearing Pressure

    Tons Per sq ft

    Type of Bearing Material Consistency In Place Range RecommendedValue for Use

    Well graded mixture of fine and coarse-grained soil: glacial till, hardpan, boulder clay(GW-GC, GC, SC)

    Very compact 8 to 12 10.0

    Gravel, gravel-sand mixtures, boulder gravelmixtures (SW, SP, SW, SP)

    Very compact 6 to 10 7.0

    Medium to compact 4 to 7 5.0

    Loose 2 to 6 3.0

    Coarse to medium sand, sand with littlegravel (SW, SP)

    Very compact 4 to 6 4.0

    Medium to compact 2 to 4 3.0

    Loose 1 to 3 1.5

    Fine to medium sand, silty or clayey mediumto coarse sand (SW, SM, SC)

    Very compact 3 to 5 3.0

    Medium to compact 2 to 4 2.5

    Loose 1 to 2 1.5

  • 8/11/2019 461-sl5

    26/28

    PresumptiveBearingPressures

    Clays

    and

    Silts

    Allowable Bearing Pressure TonsPer sq ft

    Type of Bearing Material Consistency InPlace

    Range RecommendedValue for Use

    Homogeneous inorganic clay,

    sandy or silty clay (CL, CH)

    Very stiff to hard 3 to 6 4.0

    Medium to stiff 1 to 3 2.0

    Soft .5 to 1 0.5

    Inorganic silt, sandy or clayey silt,varved silt-clay-fine Sand

    Very stiff to hard 2 to 4 3.0

    Medium to stiff 1 to 3 1.5

    Soft .5 to 1 0.5

  • 8/11/2019 461-sl5

    27/28

    PresumptiveBearingPressures

    Noteso Compacted fill, placed with control of moisture, density, and lift

    thickness, has allowable bearing pressure of equivalent natural soil.

    o Allowable bearing pressure on compressible fine grained soils isgenerally limited by considerations of overall settlement of structure.

    o Allowable bearing pressure on organic soils or uncompacted fills isdetermined by investigation of individual case.

    o If tabulated recommended value for rock exceeds unconfinedcompressive strength of intact specimen, allowable pressures equals

    unconfined compressive strength.

  • 8/11/2019 461-sl5

    28/28

    Questions?