MEMORANDUM
ITEM: MASTERTON TOWN HALL
Date:
Subject:
To:
11 June 2019
Strengthening Options
PROJECT STEERING GROUP
ITEM:
EXECUTIVE SUMMARY
This memo serves as an optioneering report on several strengthening and refurbishment options to assist
the Steering Group with making an informed recommendation to the Masterton District Council. The next
Councillors meeting is on 26 June 2019.
BACKGROUND
Scope - Stage One:
In order to gain robust cost estimating on several demolition and strengthening options the Steering Group
committed to engaging a consultant team and progressing conceptual designs in order better inform the
Quantity Surveyors estimations.
Xigo prepared Requests for Proposal (RFP) documents for several design consultants to price and
undertake Concept Design services for the following options;
• Option A - Demolition of All Buildings
o Complete demolition of existing buildings on the site.
• Option B - Complete Demolition with Façade Retainment/Propping
o The building’s façade (Perry Street and Chapel Street), are listed within the MDC District
Plan as having heritage value. Façades to be retained with propping.
o Remaining buildings demolished.
o Identification and documentation of salvageable items as desired by Masterton District
Council.
• Option C - Façade Propping, Strengthening of Municipal and Civil Defence Buildings (100%NBS),
and Demolition of Town Hall building
o Maintain both heritage façades and strengthen Municipal and Civil Defence buildings.
o Demolish main Auditorium (Town Hall) space.
o Design internal layout for replacement/alternative use i.e. open plan office
o Structural Engineer design options targeting 100%NBS.
The successful respondents to the RFP were; Silverwoods Architects (Architecture), LGE Consulting
(Structural Engineering), Stevenson and Turner (Building Services) and Rawlinsons (Quantity Surveyor).
ATTACHMENT 2404
MEMORANDUM
2
DESIGN CRITERIA AND ASSUMPTIONS
Option A:
The cost estimate assumes the full removal of the existing Town Hall structure, Municipal and Civil
Defence buildings and that the vacant lot to be returned to flat ground. Existing services are to be
terminated and covered.
Option B:
LGE have designed a propping solution based on an expected lifespan of 5 years. This design has been
considered with the demolition of the other structures. It relies on a temporary support structure, not one
that utilises existing structure, nor does it consider a new structure to be built behind.
Option C:
The scope of works provided to the Consultants were to provide a generic, open plan office space for a
single occupant to occupy the existing Municipal building footprint.
The QS advised early on in the process that the construction required to strengthening the existing
Municipal building structure could well be more expensive than to build a new structure altogether. It was
decided to conduct an exercise to be run in parallel to provide comparison for the;
Option C - Strengthening of existing MOB structure, and
Option C1 - Build new structure.
Rawlinsons used a square metre rate basis to calculate the new structure estimates.
Due to the change in the structural design target from 80% to 100%nbs, additional design work and
calculations were completed by LGE Consulting. This has resulted in higher degree of design quality to
that which would usually be undertaken for conceptual design. The design for the structural design
element of Option C is considered at Preliminary Stage level. This has provided for a more robust
estimate.
LGE has advised that the Council should be aware of the difference between how a strengthened building
compares to that of a new build in terms of NBS ratings. New buildings designed to be 100%nbs would
actually rate higher, in the range of 130-150%NBS, if they were to be evaluated post construction. A
strengthened building to 100%NBS will only ever be 100%NBS. The reasoning is complex and are to do
with several assumptions and factors of safety that are applied during the assessment of existing
structures that differ to newly designed elements that meet modern day standards. LGE are happy to
advise further on this should there be a need. For refurbished projects, like the proposed Option C, where
existing structural elements are proposed to be kept, the robustness and resilience of these are lesser
than that built to the current code and therefore can reduce the buildings performance during an
earthquake event.
405
MEMORANDUM
3
COST ESTIMATES
The funding available for the development was identified within Masterton’s Long-Term Plan with an
allocation of $15.5 million in Years 1-3.
See below summary table identifying the costs associated with each option:-
All options investigated can be achieved within the budget available.
Option C, is considered the more economical option available for retainment of the existing MOB structure
and historic façade when compared against option C1 with the new structure. The concept designs for
both two options have been tailored towards a high-end specification i.e. we have allowed for some ‘nice
to have’ elements and therefore, the design could be value engineered should there be a need to reduce
cost.
Should the project wish to take on ‘Green Building’ type initiatives such as GreenStar or NABORS ratings
then it is suggested an additional 5% be added to the overall estimates.
The estimated construction escalation costs are based on the construction phase commencing from June
2020. If the works are delayed until June 2021, or further, then the escalation costs provided would need
to be taken into account year on year.
Consultant fees are currently based on the project budget allocation of $15.5M. If the project value
changes then the consultants fee can be adjusted accordingly.
Within Horwath HTL’s demand and analysis report, their projections were based on assumptions that the
Municipal and Civil Defence Buildings were to remain, with a 1,500m2 Civic Centre development attached
to the buildings. The total construction value estimated by Howarth HTL was $20,000,000.00.
406
MEMORANDUM
4
Rawlinsons have provided a rough order of cost at $13,500,000.00 for an Event Centre development
based on their experience with other facilities within New Zealand.
Should the Council wish to proceed with an approach that an Event Centre is built behind the
strengthened MOB and existing façade we would need to revisit the concept design and prepare new
estimates.
407
MEMORANDUM
5
PROJECT PROGRAMME (Indicative)
We have prepared the attached programme with input on design timeframes from the design team. A
summary of this programme is shown below:
PROJECT RISKS
With any construction project comes an element of risk that needs to be evaluated and understood. At
this early stage in the project we have identified the following risks that could impact on cost and time
should they eventuate; this is not an exhaustive list;
Hazardous Materials (All Options):
FibreSafe NZ have completed a Demolition/Refurbishment Survey of the all the buildings that has
identified several areas of asbestos containing materials (ACM’s) and some minor areas of lead-based
paint. Removal of identified asbestos has been captured within the QS estimates. However, there may
well be areas that have not been identified that can only be uncovered during construction works;
unforeseen asbestos elements can place huge strain on project contingencies.
Programme (All Options):
The project programme is indicative only. Input on design timeframes has been made by all consultants
however, if the project were to proceed with an Event Centre additional design time may well be required.
The construction period is indicative and we have estimated 18months to be sufficient, the QS has used
this period as a guide to inform the P&G costs for a Main Contractor.
Structural Strengthening, 100NBS% (Options C & C1):
Destructive investigations of the existing structures are required to assertion its condition for refurbishment
under option C. Our estimates have assumed that they are of good condition.
Site Ground Conditions (Options B, C & C1):
Geotechnical ground assessments are required to confirm structural assumptions made at this Concept
Design stage. The project team are aware that there is contamination in the soils in at least three
locations. The QS have made allowances in the estimates to remove 700m3 of contaminated soils.
408
MEMORANDUM
6
Water Main Pressure Test (Option C & C1)
The water mains pressure is to be tested in future stages to confirm if it has enough capacity to supply fire
sprinklers without an onsite sprinkler pump. The costs for tests and installation of pump have been
captured within the Concept Design cost estimates.
Heightened Industry Activity
There is a considered boom within the industry at present and we have encountered projects whereby
estimates have been exceeded once tenders have returned from the market. The following need to be
considered;
• It is imperative that the design briefing from the Client is robust and unaltered ahead of the design
team commencing
• It is imperative that there are no scope changes made by the client and any stage post design
brief
• It is important that sufficient time is allowed for the design period as all too often we see designers
under-deliver on documentation because of impossible deadlines to meet client driven milestones.
Poor quality equals poor pricing and greater variations.
409
MEMORANDUM
7
SUMMATION – NEXT STEPS
We believe the options presented and the conceptual designs undertaken are of a good standard and the
estimates provided by the QS to be robust. There has been a good level of review and critique by all
members of the design team to test the estimates provided.
We intend to conduct a presentation for discussion at the next Steering Group meeting on 18 June 2019,
where it is proposed that the Steering Group make a decision to recommend either 1 or 2 options to the
MDC.
ATTACHMENTS
Silverwood Architects - Concept Design Report
Rawlinsons - Concept Design Estimate Report
Concept Design Documentation -
Silverwood Architects
LGE Consulting
Stevenson and Turner
410
CONCEPT DESIGN REPORT
PROJECT: Seismic Strengthening and
Office Fit-Out to MDC
Municipal Building
ADDRESS: 64 Chapel Street, Masterton
CLIENT: Masterton District Council
JOB NO: W1918
REV N0: Concept Design
DATE: 05/06/2019
411
CONTENTS
1 PREAMBLE .......................................................................................................................................... 3
2 DESIGN PROCESS SUMMARY ......................................................................................................... 3
3 DESIGN OUTCOMES .......................................................................................................................... 4
4 NEXT STEPS & PROJECT RISKS ...................................................................................................... 9
5 APPENDIX ......................................................................................................................................... 10
Prepared by:
Stephen Geuze
BAS, March (prof), NZRAB 5241
Registered Architect
412
1 PREAMBLE
The Masterton Town Hall facility located at 64 Chapel Street, Masterton includes the following
buildings; the 1915 Town Hall auditorium, 1915 Municipal building and 1985 Civil Defence building.
Masterton District Council have sought feasibility investigation into the following options for re
developing the existing Masterton Town Hall facility;
Option A: Demolish all buildings - Auditorium, Municipal & Civil Defence buildings.
Option B: Retain and prop the Municipal building façade, demolish all buildings.
Option C Strengthen: Seismic strengthen and refurbish the Municipal and Civil Defence
buildings, demolish the Auditorium building.
Option C1 Rebuild: Retaining and propping the Municipal building façade, demolition of all
the buildings behind, and rebuilding the equivalent area of the civil defence and municipal
buildings as a new building.
The following Concept Design Report has been prepared by Silverwood Architects for Option C;
including the proposed structural strengthening and refurbishment of the Municipal & Civil Defence
buildings together with the demolition of the Town Hall Auditorium.
The following Design Report must be read in conjunction with Silverwood Architects; Concept Design
Drawings and Outline Specification.
The following consultants have also provided documentation in support of Option C:
Stephenson & Turner: HVAC, Electrical, Hydraulic, Fire Design.
LEG Consulting Structural & Civil Engineers: Structural Strengthening Scheme 100% NBS.
Rawlinsons Quality Surveyors: Elemental Cost Estimate.
2 DESIGN PROCESS SUMMARY
2.1 Concept Design Brief – Option C:
Demolition of Auditorium – Complete demolition.
Seismic Strengthening - 100% NBS IL2 Seismic Strengthening to Municipal and Civil Defence
Buildings.
Refurbish Municipal and Civil Defence Base Buildings – refurbish existing municipal and civil
defence base buildings including exterior envelope, existing services & facilities.
New Generic ‘Open Plan’ Office Fit Out – new office fit-out to be designed on the
assumption that MDC will reoccupy the building(s) as a large single tenancy.
New Asphalt Carpark to Auditorium Footprint – new carpark to foot print of demolished
Auditorium.
413
2.2 Design Brief Assumptions – Option C:
Acoustic Performance – Upgrade building’s exterior glazing to double glazed units to reduce
road noise within building. New office fit-out to meet acoustic standards for open-plan office
space, including meeting spaces.
Thermal Performance – Insulate all existing exterior walls, install new insulated warm roof,
upgrade building’s exterior glazing to double glazed units, upgrade solar control to work
spaces (civil defence building).
Blank Rear External Walls - The new exterior walls along Grid 4 & Grid B have been designed
as blank two-way fire rated walls without glazing to provide MDC with flexibility in respect of
future project development on the site. These walls could be partially glazed with access to
natural light and view subject to further discussion with the MDC Project Team during the
preliminary design stage.
New Fire Protection System – New fire alarm system together with fire sprinkler protection.
Provision of Single Lift – A large single lift has been provided to meet accessible
requirements of NZ Building Code, option for an additional lift is feasible within Stair 2 if
required.
Asbestos-containing Material (ACM)- Presence and extent of ACM present on site has been
confirmed on site by Fibresafe NZ Ltd.
Lead Paint - Limited presence of lead based paint has been confirmed on site by Fibresafe
NZ Ltd.
Contaminated Site - Site contamination listed on SLUR register. Site investigation has been
differed to the preliminary design stage.
3 DESIGN OUTCOMES
3.1 Concept Design Outcomes
Concept Design - The design team has prepared the concept design based upon the concept
design brief and assumptions above including;
o Seismic strengthening scheme for upgrade to 100% NBS IL2.
o Architects base-build and fit-out design.
o Services Engineers preliminary HVAC and electrical design.
o Fire Engineers fire safety input.
Concept Design Cost Review - Rawlinson’s Quantity Surveyors have prepared a concept
design elemental estimate providing detail on project costs.
3.2 Concept Design Description
The concept design for the new office fit-out includes the provision of;
414
o Main public entry, foyer and reception spaces (entered from the primary town
square entrance).
o Public meeting spaces in close proximity to public entry (formal & informal).
o Accessible public toilet and parenting room.
o Accessible lift in close proximity to public entrance. Lift car size large enough to use
for trolleys for catering or accommodate a group of dignitaries using the lift
together.
o Separate staff entrances in close proximity to staff facilities (Chapel Street and
Lincoln Road entrances).
o Provision of amenities for staff to foster active lifestyle options including bike
storage, e-bike charging, showers & lockers.
o Provision of staff break, kitchen and toilet facilities at both levels located centrally
for all staff.
o Provision of separate cubicles for toilet facilities.
o Generic open plan offices spaces broken into large team spaces each with
supporting meeting rooms of various sizes, quiet refuge spaces, collaboration
spaces, resource and store areas.
o Provision of separate reception and offices for senior staff including the Mayor and
Chief Executive Officer.
o Provision of two key internal stairs.
o Provision of wet and dry services spaces for the buildings key environmental and
electrical services equipment.
o Provision of roof level services platform for new HVAC exterior units.
3.3 Concept Design Features
Town Square Entry – The town square main entry formally serving the Town Hall Auditorium
is to form the main public entry for the MDC offices. This improves the sense of arrival to the
building and encourages further pedestrian use of the town square.
Two main Vertical Circulation Spaces – the existing stairs and lift were all deemed
impractical/not viable to re-use. In their place two new double height spaces have been
proposed; one to the main public entry off the town square and the second to the proposed
staff entry off Chapel Street.
These double height spaces (floors, walls and ceilings) are to be refurbished consistent with
the original mosaic tiling, fret work, plaster ceilings, moulded cornices and architraves as
recorded within the original building plans. The new inserted feature stairs, mezzanine floors
and an exposed lift shaft are to be carefully designed as contemporary additions contrasting
the original architecture.
These spaces are designed as neutral places outside of the team office environments for
staff from different teams to greet one another as they pass, stand and chat or sit together
in casual seating spaces on the first floor mezzanine level.
415
These spaces also provide opportunities for reference to the Wairarapa’s cultural identity to
be developed in consultation with Rangitane and Ngati Kahungunu iwi groups.
It is also proposed to salvage the last known original 1915 steel framed window and look to
reinstate this in its original location back lit on the rear wall of Stair 2.
New CLT Stairs and Exposed Lift Shaft – The proposed new stairs are to be constructed of
Cross Laminated Timber with transparent glass balustrades. The CLT Air Stair is an innovative
NZ based engineered timber product providing a cost effective solution to creating an open
free spanning stair case. The new stair case is of a similar proportion to the original building,
however it will have a contemporary aesthetic.
The proposed lift is to be enclosed within a frameless steel & glass lift shaft, allowing the
inner workings of the new lift to be exposed to view.
416
New Solar Shading to Civil Defence Building - Existing civil defence building has roof hoods
over all exterior windows which have reached the end of their life span. Replacement with
aluminium louvers for solar shading is considered to be a practical and cost effective option
to avoid replacing the roof hoods.
Removal of secondary external entrance on Chapel Street – It is proposed to remove the
smaller secondary entrance on the Chapel Street elevation. This entrance was originally used
to access the council chambers, which are no longer used.
No provision for Council Chamber’s – It was deemed by the architect that it is not practical
to provide a new council chambers space within the existing municipal or civil defence
buildings. This is due to the existing buildings being too narrow to provide a council
chambers space of sufficient capacity for large council meetings with provision for public
seating.
Generic Open Plan Office Spaces – The proposed office spaces are to provide a balance of
open-plan and private spaces to create a range of working environments. The architect’s
concept design plans describe areas for team meetings, social & wellbeing spaces, staff
community spaces and spaces of refuge each contributing to creating a flexible, and modern
work environment.
Staff Facilities – Kitchen break rooms are designed to reflect ‘café hub’ type spaces, typical
of both modern government and private open-plan office spaces.
Weathertightness Resilience – Existing internal gutters are to be widened with new
overflows and new down pipes for increased capacity in extreme weather events. New
roofing to be installed with the quantity of roof penetrations to be reduced and consolidated
within plant room area. Existing low-pitch membrane roofs to be repitched as a minimum to
comply with NZ Building Code.
Ground Floor Separate Office Space – The current concept design provides a separate office
on the ground floor to the west end of the building. This space could be used by satellite
teams requiring temporary office space. Alternatively, this space with input from MDC in the
preliminary design phase can be redesigned to be incorporated within the larger facility.
417
3.4 Option C1 Rebuild - Retain and Prop Municipal Building Façade with new build behind.
Given the extent of demolition, propping and reconstruction of the Municipal Building’s
structure required to carry out ‘Option C Strengthening’. The design team recommended that
the cost of ‘Option C1 Rebuild’ was also investigated in order to assess against the ‘Option C
Strengthening’ scheme. This provides MCD with a cost comparison of rebuilding office space
new versus seismic strengthening with both options retaining the Municipal building façade and
providing the same area of office space.
Option C1 Rebuild – includes retaining and propping the Municipal building façade, demolition
of all the buildings behind, and rebuilding the equivalent area of the civil defence and municipal
buildings as a new building.
Rebuilding the Municipal & Civil Defence buildings (Option C1 Rebuild) provides a number of
opportunity’s & advantages over seismic strengthening to the existing structures as outlined
below;
A new building footprint can be redesigned to more efficient proportions which are better
suited to modern open plan office spaces. The existing building proportion limits the
opportunity for large open plan spaces due to its narrow building width.
Subject to site planning the building can be redesigned to access natural light and view to
the North & West in an efficient manner if the overall building width was increased.
New building construction has a higher level of acoustic and thermal performance.
New building construction has a higher level of durability with all elements specified
meeting current NZBC durability requirements. Existing buildings re-use existing structure
such as steel beams, timber joists and roof rafters which vary in condition.
New building structures generally have a higher capacity to withstand seismic events. Please
refer to the Structural Engineers documentation for comments in respect of the two options
with respect to how a strengthen building versus a new building performs in an earthquake.
New buildings typically has a lower risk profile for unforeseen items as they avoid making
good unforeseen damage or deterioration such as rotten timber, borer damaged timber,
corroded steel or concrete repairs. Please refer to the Quantity Surveyors documentation for
comment in respect of the two options and comparative costings and allowances.
While the Municipal building façade is of significant heritage value the remainder of the
building has little to no heritage value including the Civil Defence building.
418
4 NEXT STEPS & PROJECT RISKS
4.1 Next Steps – Preliminary Design Phase
Present the Concept Design to the Client Team – To date the concept design has been
prepared based on the design brief provided. Should Option C be selected as the viable
option the design team is to present the current concept design to the MDC project team
and receive feedback from MDC prior to proceeding with the preliminary design phase.
Occupation Strategy Review – MDC to confirm how they wish to re-occupy the building and
for what services and use. MDC project team to confirm staff numbers and teams to
reoccupy the facility.
Workplace Strategy Review – MDC to confirm their ‘work place’ strategy. Project team to
meet to assess existing concept design for proposed office fit-out and develop to suit MDC
occupation requirements.
Energy Efficiency Review – MDC to confirm ‘energy use’ strategy. Project team to meet and
confirm which strategies will be integrated within the building and allow the design team to
design accordingly.
Preliminary Design Refinement and Coordination – The building design including office
fitout is to be developed to reflect feedback from MDC.
Co-ordination Workshops – Design team workshops on-going through preliminary design
phase.
4.2 Project Risks – For Review, Monitoring and Mitigation
Site Ground Conditions – Geotechnical Investigation to be carried out as required for
structural & civil design certainty.
Site Contamination Investigation - Environmental Engineer to carryout site investigation
into extent of site contamination (listed on SLUR register) and quantify scope to
decontaminate the site.
Building Condition Investigation – Further destructive investigation to test the structural
integrity and condition of existing building fabric including structure (concrete, masonry,
reinforcing, timber framing, steel beams).
Water Main Pressure Test – Water main pressure to be tested to confirm if it has sufficient
capacity to supply fire sprinklers without an onsite sprinkler pump.
419
5 APPENDIX
1. Architects Proposed L1 Fit-Out Plans– MDC Municipal & CD Building.
2. Architects Proposed L2 Fit-Out Plans– MDC Municipal & CD Building.
420
7 7
A
A
B
B
6 6
5 5
1 1
3 3
2 2
4 4
D
D
C
C
E
E
F
F
G
G
H
H
I
I
J
J
K
K
L
L
M
M
N
N
O
O
P
P
36-031
36-031
36-061
36-061
PUBLIC FOYER
WIND LOBBY
PU
BLIC
T
OIL
ET
S
PARENTS ROOM
PLANNING &
ENVIRONMENTAL
SPRINKLER VALVE/PUMP
ROOM
RECEPTION
ADMIN SUPPORT
WAITING
LIFT
STAIR 2
STAIR 3
WIND LOBBY
ST
AIR
1
DRY SERVICES
ROOM
SEPARATE OFFICE
STAND ALONE TEAM OR PUBLIC MEETING ROOM
STORE ROOM
MEETING ROOM
MEETING ROOM
MEETING ROOM
STORE ROOM
MEETING
ROOM
MEETING ROOMU
P
UP
AREA LEGEND
L1. GROSS FLOOR AREA: 884m2
SITE AREA: 2,655m2
L2. GROSS FLOOR AREA: 886m2
L1. SUSPENDED CEILING HEIGHT
3.2m
L2. SUSPENDED CEILING HEIGHT
3.1m
36-041
36-041
36-051
36-051
NEW ENTRANCE STEPS
DIS
PL
AY
DIS
PL
AY
MA
LE
S
HO
WE
RS
LOCKERROOM
2000W x 1500D
FE
MA
LE
S
HO
WE
RS
QUIETROOM
QUIET ROOM
STAFF BREAK AREA
WET SERVICES
ROOM
MALE
UNI-SEX ACCESSIBLE
TOILET
FEMALE
LOCKERS LOCKERS
RESOURCE
RE
SO
UR
CE
ST
AT
ION
PUBLIC MEETING SPACE STAFF COMMUNITY SPACETEAM MEETING SPACE (6+ PEOPLE)SOCIAL / WELLBEING SPACE REFUGE SPACE (1-3 PEOPLE)ENCLAVE SPACE (3-6 PEOPLE)
SHEET:
STATUS:
(HALF SCALE at A3)
JOB NO:
DATE:
SCALE:
REV:
PROJECT:
CLIENT:
ADDRESS:
SHEET:
MASTERTON: 06 378 6332 WELLINGTON: 04 972 1906
24 Church Street, Masterton, P.O
Box 120
Suite 3, L2, 182 Vivian Street,
Wellington
www.silverwoodarchitects.co.nz [email protected]
1 : 100 at A1
20-06L0. Proposed Floor Plan - Fitout
M1918
15/05/2019
64 Chapel Street, Masterton
Seismic Strengthening and Office
Fit-Out to MDC Municiple & CD
Building
Masterton District Council
Concept Design
REVISION SCHEDULEREF. DESCRIPTION DATE
421
7
A B
6
5
1
3
2
4
DC E F G H IJ K L M N O P
36-031
36-031
36-061
36-061
CHIEF EXECUTIVE TEAM OPERATIONS TEAM
MAYOR OFFICE
CEO OFFICE
RECEPTION
STAFF BREAK AREA
ST
AIR
1
ST
AIR
3
STORE ROOM
MEETING ROOM
DRY SERVICES
ROOM
VOID VOID
MEZZANINE
MEETING ROOM
MEETING ROOM
VOID
OFFICE
OFFICE
STAIR 2
QUIETROOM
QUIET ROOM
DOWN
DO
WN
36-041
36-041
WET SERVICES
ROOM
36-051
36-051
SE
RV
ICE
S
ST
AIR
MALE
UNI-SEX ACCESSIBLE
TOILET
FEMALE
LOCKERS LOCKERS
STORE ROOM
MEETING ROOM
MEETING ROOM
RE
SO
UR
CE
VOID
LIFT
2000W x 1500D
PUBLIC MEETING SPACE STAFF COMMUNITY SPACETEAM MEETING SPACE (6+ PEOPLE)SOCIAL / WELLBEING SPACE REFUGE SPACE (1-3 PEOPLE)ENCLAVE SPACE (3-6 PEOPLE)
AREA LEGEND
L1. GROSS FLOOR AREA: 884m2
SITE AREA: 2,655m2
L2. GROSS FLOOR AREA: 886m2
L1. SUSPENDED CEILING HEIGHT
3.2m
L2. SUSPENDED CEILING HEIGHT
3.1m
SHEET:
STATUS:
(HALF SCALE at A3)
JOB NO:
DATE:
SCALE:
REV:
PROJECT:
CLIENT:
ADDRESS:
SHEET:
MASTERTON: 06 378 6332 WELLINGTON: 04 972 1906
24 Church Street, Masterton, P.O
Box 120
Suite 3, L2, 182 Vivian Street,
Wellington
www.silverwoodarchitects.co.nz [email protected]
1 : 100 at A1
20-07L1. Proposed Floor Plan - Fitout
M1918
15/05/2019
64 Chapel Street, Masterton
Seismic Strengthening and Office
Fit-Out to MDC Municiple & CD
Building
Masterton District Council
Concept Design
REVISION SCHEDULEREF. DESCRIPTION DATE
422