400kV Overhead Line Construction
-
Upload
kalpanaadhi -
Category
Documents
-
view
238 -
download
2
Transcript of 400kV Overhead Line Construction
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 1/15
Place your chosenimage here. The four
corners must justcover the arrow tips.For covers, the threepictures should be thesame size and in astraight line.
400kV Overhead Line Construction
Tim Inglehearn
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 2/15
2
Contents
Overhead line components
Typical tower types
Overhead line construction
Reinstatement
Inspection and maintenance
Substations
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 3/15
3
Overhead Line Components
Support
Conductors
Insulators
Spacers
Dampers
Earth wire
Jumpers (on tension
towers)
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 4/15
4
Typical Tower Types
Suspension TowerTension Tower
(angled or deviation towers)
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 5/15
5
Typical Tower Types
Termination Tower at aSealing End Compound or Substation
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 6/15
6
Typical Tower Types
Short support: lower height;more supports per kilometre
Tall support: greater height;
fewer supports Clearance and ‘sag’; higher
voltages require greaterclearance/increased insulation
Sum of adjacent ‘spans’
Typical tower height: around50m
Typical tower span: 360m
Span Lengths and Tower Heights
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 7/15
7
Overhead Line Construction
Temporary metal trackways orstone tracks dependent onlandowners requirements
Localised vegetation clearanceand excavation where towerfoundations needed, minor soilstorage as a result
Drainage/dewatering works
might be required depending onground conditions/watertable
Every tower requires its ownworking area – protected by
temporary Heras fencing
Access, Working Areas and Ground Preparation
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 8/15
8
Overhead Line Construction
Excavator for foundations andany drainage works
Delivery of materials to site
Crane to assemble towers
Winch and tensioner
Machinery Required
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 9/15
9
Overhead Line Construction
Tower Foundations –Excavated or Piled
Foundation type dependenton ground conditions
Excavated foundationsencased in mass concrete
Piled foundations also useconcrete
Stub legs installed andremainder of tower built up bycrane
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 10/15
10
Overhead Line Construction
Fabricated from rolled steelangles and delivered to site innumbered parts (similar to flat-pack furniture)
Most parts are bolted together
Sections e.g. crossarmsassembled at ground leveland raised into position usinga crane
All steelwork is galvanised forprotection (will last approx. 20years)
Installation of insulators and
fittings
Tower Construction and Cranage
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 11/15
11
Draw wires winched through
Conductors are winched intoposition
Conductors pulled throughsuspension towers
Winch and tensioner placed
at tension towers
Additional fittings (spacersetc.) installed
Overhead Line Construction
Stringing conductors
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 12/15
12
Reinstatement
At end of construction, temporaryaccess tracks and working areas areremoved (unless otherwise agreedwith the landowner)
Land returned to original condition
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 13/15
13
Inspection and Maintenance
Inspection is carried out everyyear
Towers are repainted approx.every 18 years depending oncondition
Replacement fittings duringroutine inspection, if required
Reconductoring takes place
approx. every 40 years
7/28/2019 400kV Overhead Line Construction
http://slidepdf.com/reader/full/400kv-overhead-line-construction 14/15
14
Substations
Transform voltages (400/132 kV)
Switch connections in and out ofthe network
Manage power flows
Connection points
Switches, transformers,compensation equipment
Permanent land-take and vehicle
access required Transformers delivered as
abnormal loads - existing roadsmay need widening etc.