40 MW CPP Chanda -...
-
Upload
phungnguyet -
Category
Documents
-
view
216 -
download
2
Transcript of 40 MW CPP Chanda -...
2017 Chanda Cement Works
Energy Leadership
Welcome to CII
17th National Award for Excellence in Energy Management 2017
30, 31 August & 01 September 2017
Presenter : Sandeep Kumar Garg
40 MW CPP Chanda
2017 Chanda Cement Works
Contents…
1. Company Profile
2. Process flow diagram & configuration
3. Plant Performance over the year
4. Innovative Projects with No investments
5. Innovative Projects with investments
6. Best practices
7. Energy Saving Projects – Way forward
2017 Chanda Cement Works
CPP - 1X15MW + 1X25MW - Commissioned in 2002 (15MW) & 2010 (25MW).
Chanda is the first cement plant set up in the state of Maharashtra.
Located at Ghugus Taluka-27 KM from Chandrapur and 165 KM from Nagpur.
Company Profile - Chanda Cement Works
Maharastra
Chanda
2017 Chanda Cement Works
Process Flow Diagram…
2017 Chanda Cement Works
Plant Performance Over the Years
13.21 12.79 12.55
10.41 10
Year 2014 Year 2015 Year 2016 Till July
2017
Aspiration
2017
APC %
3287 3265
3212
3110 3100
Year 2014 Year 2015 Year 2016 Till July 2017 Aspiration2017
SHR (Kcal/Kwh)
2017 Chanda Cement Works
Auxiliary Power Consumption Vs PLF - 2017
11.07
10.12 10.04 10.05
10.39
10.98
10.43
9.50
10.00
10.50
11.00
11.50
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
60
.12
77
.74
73
.07
77
.17
72
.57
61
.65
71
.61
2017 Chanda Cement Works
SN Energy Saving Projects
Saving Achieved
Electrical Energy (MWH)
Thermal Energy
(Ton/Year)
Rs. Lac
01 Implementation of DP logic in BPF of Unit#1 201 - 8.10
02 Implementation of DP logic in BPF of Unit#2 252 - 10.10
03 Optimisation of CEP discharge pressure form 10 to 6.0 Kg/cm2 for Unit#1
101 - 4.04
04 Optimisation of CEP discharge pressure form 10 to 6.0 Kg/cm2 for Unit#2
98 - 3.92
Total savings 652 26.16
Energy Saving Projects with zero investment…2017
2017 Chanda Cement Works
SN Energy Saving Projects
Saving Achieved
Electrical Energy (MWH)
Thermal Energy
(Ton/Year)
Rs. Lac
01 Improved TG vacuum by arresting leakages in exhaust path through Helium leak detect test
- 80.75 2.66
02 CBD vent line connected to deareator. - 210 6.93
03
CHP power optimization by increasing through crusher out put & reducing idle running hours through keen observation at coal feeding grizzly hopper.
300 - 12.0
04 Impeller trimming of Raw Water Pump for reduction of APC.
25 - 1.0
05 Recycle & reuse of BAC cyclone trapped material. - - 2.40
Total savings 325 290.75 24.99
Energy Savings Projects with zero investment…2015 - 16
2017 Chanda Cement Works
SN Energy Saving project
Saving Achieved/Year Investments
(Rs. Lac)
Pay Back
Months Year Electrical
Energy (MWH)
Thermal Energy (Ton)
Rs. Lac
01
P&V pump replaced with low capacity pump, by modification of water spray system existing louvers replaced with cellulose pad.
43.50 - 1.74 0.50 3 2017
02
Unit=1 condenser tube assembly replacement to improve vacuum from -0.80 to .91 Kg/cm2.
- 700 23.45 61 2.60 2016
03 HT VVFD installed in BFP of unit#1
294 - 11.76 30 2.5 2016
04 HT VVFD installed in BFP of units#2
798 - 31.92 75 2.3 2016
05 VVFD installed in IAC of both units.
100 - 4.03 3 8 2016
Energy Savings Projects with investment…2015-17
Continued..
2017 Chanda Cement Works
Energy Savings Projects with investment…2015-17
SN Energy Saving project
Saving Achieved Investment (Rs. Lac)
Pay Back
Months Year Electrical
Energy Thermal Energy
Rs. Lac
06 Replacement of Cooling tower fan blades with hollow blades of Unit#1
156 - 6.24 7.68 14 2016
07 VVFD installed in condensate extraction pump no.1 of unit#1
67 - 2.68 2.5 10 2016
08 VVFD installed in condensate extraction pump no.1 of unit#2
93 - 3.70 3 8 2015
09 Boiler No. 01 & 02 APH tube replacement
84 - 6.72 40 7 2015
10 Replacement of Cooling tower fan blades with hollow blades of Unit#2
597 - 23.90 7.32 4 2015
11
Improve MDC air slider reliability to replacement of slider sintered sheet to ceramic cloth. Reduce maintenance cost.
- 24 7.90 0.95 2 2017
Total savings 2232.5 724 124.04 230.95
2017 Chanda Cement Works
Concept # 1 DP Logic implementation in BFP…
Concept..
• DP LOGIC for Boiler Feed Pump to reduction of auxiliary power consumption.
Background..
• HT VFDs ware installed for Boiler Feed Pumps (BFP) -1 in both units which was operating at reduced fixed RPM as per requirement. However most of the time even on reduced pump loading, discharge pressure of BFP is more than the requirement on varying loads.
Approach..
• After studying the system it was observed that even if discharge pressure is maintained 5 to 6 kg/cm2 above the drum pressure, system behaves stable.
• Logic was developed in-house & incorporated in DCS so that PID will automatically take set point of 5 kg/cm2 higher than drum pressure. (Differential pressure of 5 kg/cm2 is maintained between drum pressure & BFP Discharge Pressure).
Continued..
2017 Chanda Cement Works
Concept # 1 DP Logic implementation in BFP…
Investment ..
• Financial investment is ZERO.
• Technical skill & Experience - To prepare & implement DP logic on DCS through own team with keen & vigilant observation during operation.
Benefits & Economic impact..
• Improvement in APC (Auxiliary Power Consumption).
For Unit-1
KW consumed before DP Logic = 211 KW
KW consumed after DP Logic = 187 KW
Total saving in KW = 24 KW
Saving per day in 15 MW = 24 KW X 24 Hrs= 576
Units
Saving per year @ Rs 4 /unit = 576*350*4
= 8.1 Lac / Year
For Unit No.2
KW consumed before DP Logic = 285 KW
KW consumed after DP Logic = 255 KW
Total saving in KW = 30 KW
Saving per day in 25 MW = 30 KW X 24 Hrs= 720
Units
Saving per year @ Rs 4 /unit = 720*350*4
= 10.1 Lac/ Year
Total Saving per year = 18.2 Lac / year
2017 Chanda Cement Works
Concept..
• Replacement of CT fan GRP solid blades assembly with FRP type to reduce in Auxiliary Power Consumption.
Background..
• In both units, Cooling tower fans were installed with VFDs which ware operated at reduced fixed RPM as per requirement.
• Originally, Fans were supplied with GRP type solid blades fan assembly, resulting in high Auxiliary power consumption due heavy weight of blades.
Approach..
• Idea is suggested by O&M team to replace GRP type blade assembly to FRP
Continued..
Concept # 2 Replacement of Cooling Tower Blades…
** Glass Reinforced Polypropylene
** Fiber Reinforced Plastic
2017 Chanda Cement Works
Investment ..
• Financial investment was 16 Lac.
Benefits & Economics impact..
• Improvements in APC (Auxiliary Power Consumption)
• Improved Cooling effect due to air velocity increase by 27.72% & 31.64% respectively of both units
• Electrical Energy Saving on each fan of Unit#1 – 8.85+9.73 KWH (38.62%)
Saving per year @ 4Rs/Unit = (8.85+9.73)*24*350*4=6.24 Lac per year
• Electrical Energy Saving on each fan of Unit#2 – 37.44+33.67 KWH (42.15%)
Saving per year @4Rs/Unit = (37.44+33.67)*24*350*4=23.90 Lac per year
Concept # 2 Replacement of Cooling Tower Blades…
2017 Chanda Cement Works
Concept # 3 Reduction of secondary air in CFBC Boiler…
Concept..
• Reduction in secondary air & focus on primary combustion for reduction of Station Heat Rate & Auxiliary Power Consumption
Background..
• Earlier CFBC boiler was operated with 1350 mmwc wind box pressure as per OEM recommendations, resulting in higher loading operation of PA fan, even at partial loading of boiler.
Approach..
• Idea is generated by our O&M team.
• In CFBC Boiler, PA fan header pressure reduced from 1350 to 1150 mmwc through improving the Mechanical Dust Collector efficiency by reducing slider jamming tendency.
• Secondary air reduced and more focus was given to primary combustion. This improved the recycle inventory.
Continued..
2017 Chanda Cement Works
Investment ..
• Financial investment was negligible.
Benefits & Economics impact..
• Improvement in SHR by avoiding frequent leakages through air sliders(Station Heat Rate)
• Reduction in LOI by recycling.
• Reduction in boiler excess air O2% by reduction in secondary air.
• Improved boiler efficiency.
• Improvement in APC (Auxiliary Power Consumption) -
One SA fan (250KW) always maintained as hot standby.
Concept # 3 Reduction of secondary air in CFBC Boiler…
2017 Chanda Cement Works
Concept # 3 Reduction of secondary air in CFBC Boiler…
2017 Chanda Cement Works
Concept # 4 Recycling of Cyclone material…
Concept..
• Recycling of drained Bed ash pneumatically to bed as bunker and optimize the use of fresh bed material.
• Reduction in manual interference for charging of bed material at bed bunker
Background..
• Earlier in CFBC boiler, the bed material bunkers which are located at almost 25 mtrs above ground, had to be filled manually for meeting light up or any other emergency requirements. This activity required manpower involvement & safety hazards. The bed ash used, was either sieved or fresh one. Now, after the system implementation, use of fresh bed material is drastically reduced.
Approach..
• Idea was suggested by our O&M team.
• In CFBC Boiler, Bed material drained & cooled in BAC. During cooling process fine material is trapped in cyclone & collected in a vessel. These fine bed material is pneumatically conveyed to bed material bunker
Continued..
2017 Chanda Cement Works
Investment ..
• Financial investment is ZERO.
Benefits & Economic impact..
• Elimination of manual interference & associated safety hazards.
• Reduced fresh bed material consumption.
• All employee satisfaction
Concept # 4 Recycling of Cyclone material…
2017 Chanda Cement Works
Best practices on safety front…
Display of SOPs/SMPs & JSAs Group Isolation & Lock out provision
PPE adherence while electrical energy isolation
2017 Chanda Cement Works
Energy Saving Projects – way forward…
Major Overhauling of TG # 1 & 2 to improve STG cycle efficiency & Heat Rate
CFBC boiler, APH tube assembly replacement for reduction of Auxiliary power consumption & improvement of boiler efficiency.
Elimination of raw water pump use by providing interconnecting line between Mines & River water pump.
Modification of existing coal handling circuit for reduction of Auxiliary Power Consumption as well as increasing throughput rate.
Installation of energy efficient Cooling water pumps in both units.
Existing inefficient reciprocating compressors replacement with screw compressors for reduction of APC.
2017 Chanda Cement Works
Achieve ZERO Harm consistently with Lowest Power
Generation Cost by using the Innovative practices and
Corporate ethics.