Soil-gas monitoring: soil-gas well designs and soil-gas sampling
4 Soil Sampling and Analysis Plan Site
Transcript of 4 Soil Sampling and Analysis Plan Site
Phase 4 ‐ Soil Sampling and Analysis Plan
Sigma‐Aldrich Fort Mims Site
Maryland Heights, Missouri
U.S. Nuclear Regulatory Commission Radioactive Materials License No. 24‐16276‐01
Sigma‐Aldrich Company PO Box 14508 St. Louis, MO 63178
Prepared by:
DDES LLC 345 North Avenue, 2nd Floor Wakefield, MA 01880 February 26, 2015
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
ii
Table of Contents 1.0 Introduction ......................................................................................................................... 1
1.1 Background .......................................................................................................................... 1
1.2 Contaminants of Concern .................................................................................................... 2
1.3 Date Quality Objectives ....................................................................................................... 2
1.3.1 Statement of the Problem ............................................................................................ 2
1.3.2 Sample Design Summary .............................................................................................. 2
1.4 Characterization Design for Soil Areas................................................................................. 2
1.4.1 Site Screening Levels ........................................................................................................ 4
2.0 Quality Assurance Project Plan ............................................................................................ 5
2.1 Project Management ........................................................................................................... 5
2.1.1 Project/Task Organization ............................................................................................ 5
2.1.2 Special Training Requirements/Certification ............................................................... 6
2.1.3 Documentation and Records ........................................................................................ 7
2.1.4 Nonconformance Control and Corrective Action ......................................................... 8
2.2 Measurement/Data Acquisition .......................................................................................... 8
2.2.1 Sampling Process Design .............................................................................................. 8
2.2.2 Analytical Methods Requirements ............................................................................... 8
2.2.3 Instrument/Equipment Testing, Inspection, Maintenance .......................................... 8
2.2.4 Instrument Calibration Frequency ............................................................................... 8
2.2.5 Data Acquisition Requirements (Non‐Direct Measurements) ..................................... 9
2.3 Data Validation and Usability .............................................................................................. 9
2.3.1 Data Review, Validation, and Verification Requirements ............................................ 9
2.3.2 Data Analysis ............................................................................................................... 10
3.0 Field Sampling Plan ............................................................................................................ 11
3.1 Sampling Objectives ........................................................................................................... 11
3.2 Sampling and On‐Site Environmental Measurement Procedures ..................................... 11
3.2.1 Surface Soil Sampling ..................................................................................................... 11
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
iii
3.2.2 Subsurface Soil Sampling ............................................................................................... 11
3.2.3 Soil Sampling Procedure ................................................................................................. 11
3.3.4 Sample Identification ........................................................................................................... 12
3.2.4 Sample Labeling ............................................................................................................. 12
3.2.5 Sample Packaging and Shipment ................................................................................... 13
3.2.6 Sample Handling and Mixing .......................................................................................... 13
3.2.7 Decontamination Procedure .......................................................................................... 13
3.3 Field Records, Sample and Document Control .................................................................. 14
3.4 Chain of Custody ................................................................................................................ 14
3.5 Custody Seals ..................................................................................................................... 15
3.6 Field Logbook ..................................................................................................................... 15
3.7 Document Corrections ....................................................................................................... 15
3.8 Management of Investigation‐Derived Waste .................................................................. 16
4.0 Conclusions ........................................................................................................................ 17
5.0 References ......................................................................................................................... 18
Attachment A: ....................................................................................................................... A‐1
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
A‐1
1.0 Introduction
The Fort Mims Site occupies approximately one‐acre open land area with no structures. This site
was once occupied by Sigma‐Aldrich’s radiochemistry facility that was previously
decommissioned and demolished in compliance with in NUREG 1757 Volume 2, Consolidated
NMSS Decommissioning Guidance and NUREG 1575, Multi‐Agency Radiation Survey and Site
Investigation Manual (MARSSIM). The document describes the approach, methods and
techniques for the design and performance of characterization and final status surveys. This
parcel of land is located in a commercial/light industrial park in Maryland Height, Missouri. The
Fort Mims facility currently operates under U.S. Nuclear Regulatory Commission (NRC)
Radioactive Materials License Number 24‐16273‐01.
This soil‐sampling plan is designed to define the lateral and vertical extent of carbon‐14 (14C) and
tritium (3H) contamination in soils at the site by using the United States Environmental Protection
Agency (EPA) Triad approach for site assessment and cleanup. The original approved soil
sampling plan was designed to evaluate the upper six inches of surface soil following the
guidance of MARSSIM. The soil sample results indicate detectible concentrations of
contaminants present well below the surface (>6 inches).
As such, the Phase 4 soil sampling approach uses the previous soil sampling data to identify areas
of concern which require further characterization to define the vertical and horizontal extent of
contamination. The goal of this sampling event is to define the extent of contamination at the
site so that site‐specific Derived Concentration Guidance Levels (DCGLs) can be developed and
groundwater monitoring locations can be selected. All soil sampling activities shall be carried
out in accordance with the Sigma Aldrich Fort Mims Decommissioning Health and Safety Plan.
1.1 Background
There have been three phases of soil sampling that have occurred to date. A total of two
hundred fourteen (214) discrete soil samples have been obtained from the site from three
previous soil sampling events. The first two soil sampling events were performed in compliance
with the approved Open Land Soil Sampling Plan dated October 20th, 2008. The third round of
soil sampling used biased sampling to evaluate the former building footprint and former septic
system at the site. The soil sampling results from each round of sampling indicated
contamination exceeded the approved default screening value of 12 picoCuries/Gram (pCi/g)
for 14C in both surface and subsurface soils.
Past site characterization events have failed to bound the extent of horizontal and vertical
contamination in soils at the site.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
2
1.2 Contaminants of Concern
Through interviews, characterization and historical site data it has been determined that the
Nuclides of Concern (NOC) for this facility decommissioning are Carbon‐14 (14C) and Tritium
(3H). Through the first three phases of soil sampling only one soil sampling location near the
former septic tank location exceeded the approved default screening value for tritium (3H) of
110 pCi/g.
1.3 Data Quality Objectives
1.3.1 Statement of the Problem
A number of soil contamination data gaps exist from the three previous soil sampling
events. The Fort Mims facility requires further soils characterization in order to bound
the vertical and horizontal extent of contamination. This data is necessary to help in the
development of site‐specific DCGLs.
1.3.2 Sample Design Summary
The sample design and DQOs were based on the USEPA Soil Screening Guidance
(EPA/540/R‐96/018), the USEPA Guidance for the Data Quality Objectives Process and
the USEPA Using the Triad Approach to Streamline Brownfields Site Assessment and
Cleanup.
1.4 Characterization Design for Soil Areas
A Conceptual Site Model (CSM) was developed based on review of the existing data obtained
during prior sampling events combined with the historic operations onsite. The existing soils
data and survey maps were combined into a single CSM using Geographic Information System
(GIS) to provide location and depth of sampling. This data was imported into Spatial Analysis
Decision Assistance (SADA) 5.0.7800.0 software to create a 3D model of existing contamination
levels at the site.
Review of this data and operational history indicate there are two potential sources of soils
contamination onsite:
Soil deposition from exhaust stack emissions to the west of the former building
Deposition from exhaust stack emissions on the roof in which rain runoff drained to the
south and southwest corner of the former building
Septic disposal of contaminants under the former foundation of the building
While the potential contaminant source for two of these areas may be linked to exhaust stack
emissions, the mechanisms for fate and transport are very different. The current soil data for
the open land area west of the former building indicate surficial deposition over a wide area
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
3
has occurred with little vertical movement of contaminants in soil. The data from the runoff
area south and southwest of the former building indicate that contaminants may have been
transported deeper in soils by runoff. This will require sampling at greater depths to define the
vertical extent of contamination.
The former septic system has the highest potential for migration of contaminants due to the
volume of water passing though this contaminated area. Soil samples will be required at the
greatest depth in this location and down gradient of the water pathway.
It will also be necessary to expand the survey units to include additional areas south of the
property boundary of the site. This will encompass the parcel of land to the south and east of
the former building location. The highest contamination levels were located between the
former building and south property boundary, thus resulting in further investigation.
Therefore, samples will be heavily focused on the areas where contamination is likely to be
present in order to quantify the boundaries of contamination. This will be done to verify and
help bound the known areas of contamination.
This sampling design covers both the data gaps identified from the previous sampling events as
well as extend sampling to new areas of concern. Samples will be obtained from previous
sample coordinates where contamination levels exceed 50 pCi/g for 14C at the deepest interval
sampled. In these locations, one additional sample will be collected from 1 meter below the
last recorded sample depth. Table 1.4‐1 lists the locations and depths where the data gap
samples will be obtained. Attachment A – Data Gap Samples depicts the locations of each
proposed data gap sample.
Table 1.4‐1 Data Gap Sample Locations
Location Depth (Meters)
29‐015 3
29‐018 1
29‐019 1
29‐045 1, 2, 3
29‐049 3
29‐051 3
29‐061 3
In addition to the data gap sample locations described above, Additional samples shall be
obtained from Survey Unit 29 in order to properly characterize the former exhaust stack and
steric systems areas. Survey Unit 30 will evaluate the open land area to the south and east of
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
4
the former building footprint. This land area slopes towards the south and surface
contamination may have migrated following the surface water runoff pathway. These sample
locations are depicted in Attachment A.
The Phase 4 sample locations were based off the previously established triangular sampling
grids to evaluate adjacent areas where sampling results exceeded 50 pCi/g. For the purpose of
this investigation, the lateral spacing between these additional locations will match the Phase 3
sampling event which was approximately 9.1 meters. A field technician will verify the location
of each sample using a Trimble GPS tracker unit. At each of the new locations, one surface
sample will be collected from 0 ‐ 6 inches below the ground surface. Additional samples shall
be collected at these locations at 1 meter, 2 meter and 3 meter depths. These sample locations
are depicted in Attachment A.
1.4.1 Site Screening Levels
Site screening levels (SSL) have been set at 50 pCi/g for 14C and 220 pCi/g for 3H based
off the previous soil sampling results. The SSL’s do not correspond to a specific annual
dose limit but are to be used as a decision point to determine when additional data
should be obtained.
Site‐specific DCGLs for subsurface soils will be developed once the horizontal and
vertical extent of contamination has been determined.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
5
2.0 Quality Assurance Project Plan
2.1 Project Management
2.1.1 Project/Task Organization
The project organization described in this section shall be responsible for achieving
quality on this project. Verification personnel, whether in line or organizationally
independent, have sufficient freedom, authority, access, and responsibility to:
Identify quality problems, deficiencies in hardware and documentation, and
noncompliance with performance objectives.
Initiate, recommend, or provide solutions through designated channels
Verify implementation of the solutions
Assure that deficient work is stopped or is proceeding under controlled
conditions until proper disposition of the unsatisfactory condition is
accomplished.
The quality related responsibilities for the management positions of the Sigma‐Aldrich
Fort Mims Decommissioning are provided in Table 2‐1. Where titles are used to
designate responsibility the named position has the authority to designate another
qualified position within the organization to perform an assigned task. The incumbent,
however, retains the responsibility for implementing the requirements. Project
organizations operate directly in accordance with this QAPP.
The Project Manager (PM) is responsible for the overall safe, timely and cost
effective completion of the project. The individual is responsible for all project
activities and directly supervises the Sr. Health Physics Technicians and
subcontractors; approve all project expenditures; provide interface between the
client and company resources; and maintain project budget and schedules. In
addition, the PM is responsible for ensuring the elements of this QAPP are
successfully implemented.
The Quality Assurance Representative is responsible for the development and
issuance of this QAPP and reviewing and concurring with project plans and
procedures affecting quality. The Quality Assurance Representative is also
responsible for the following:
o Advising management of quality achievement and recommending means
of improving quality performance.
o Establishing generic project management/quality assurance procedures
and instructions. Verifying the quality of work by audit or surveillance.
o Investigating quality issues.
o Furnishing quality assurance expertise to support project assessments.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
6
The Senior Health Physics Manger is responsible for survey planning,
implementation and documentation. This individual is responsible for
implementation of the D&D Plan and meeting all data quality objectives.
The Health and Safety Officer is responsible for implementing project health and
safety and the DDES Health and Safety Program. The Health and Safety Officer
reports directly to the Corporate Safety and Health Manager.
The Senior Health Physics Technician is responsible for implementing all aspects
of radiation safety and data collection.
All personnel have the responsibility for executing their work and ensuring that quality‐
affecting activities within their purview are performed in conformance with this QAPP
and the applicable approved plans and procedures.
All project personnel have the authority and responsibility to stop their own work when
continuation will produce or conceal results that are not in accordance with prescribed
requirements of this QAPP, and the responsibility to report such conditions to line
management.
2.1.2 Special Training Requirements/Certification
Project personnel shall be indoctrinated and trained in accordance with this QAPP,
project specific documents, applicable DDES corporate procedures and applicable Sigma
Aldrich procedures.
Indoctrination to the project scope of work shall be provided to all project
personnel
Project Personnel shall be provided sufficient training prior to commencement of
the individuals assigned task(s). The extent of training shall be determined by
the Project Manager. The extent of training shall be based on scope, complexity,
and nature of the assigned task(s), education, experience, previous training, and
proficiency of the individual.
The training method employed may be one or all of the following:
o Classroom instruction;
o Reading assignments;
o On‐the‐job;
o Practical demonstration
Education and experience qualifications shall be documented by resume with
relevant formal educational training certificates enclosed with the resume.
All forms of personnel indoctrination and training shall be documented and
maintained.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
7
All employees exposed to hazardous substances, safety hazards or health hazards shall
be thoroughly trained as prescribed by 29 CFR 1910.120. Training of project employees
shall include:
Safety, Health and other site hazards
Proper use of PPE
Work practices that can minimize risks from hazards
Engineering controls
Equipment use
Medical surveillance requirements
At a minimum all project employees shall be required to be trained in a 40 hour
Hazardous Waste Operations and Emergency Response (HAZWOPER) training course.
This training requires an initial 40‐hour session of off‐site instruction and three days of
field experience. There are additional requirements for occasional site workers,
managers and supervisors. 29 CFR 1910.120(e)(8) addresses refresher training for 40‐
hour site worker certified employees; this refresher training is eight hours in length.
2.1.3 Documentation and Records
Project documents and records that shall be considered Quality Assurance Records
include but are not limited to the following:
Decommissioning Plan
Health and Safety Plan
Soil Sampling Plan
Project‐Specific Procedures
Supporting Quality Assurance Procedures
Project documents shall be reviewed for adequacy and approved by authorized
personnel. Document control shall insure that only the most current documents are in
use during the performance of project activities. Project‐specific and supporting quality
assurance procedures, work instructions, quality plans and other documents which
specify quality requirements or prescribe activities affecting quality shall define the
required documents or data to be maintained as Quality Assurance Records. Additional
documents such as quality‐related procurements for items and sub‐contracted services,
personnel training records and qualification documentation shall also be maintained as
Quality Assurance Records. Records shall be protected against damage, deterioration or
loss.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
8
2.1.4 Nonconformance Control and Corrective Action
All project personnel shall be responsible for notifying their supervisor, the Project
Manager, or the Quality Assurance Manager of conditions or items that do not meet
specified requirements. All project personnel are encouraged to identify any activity,
process, or procedure that could lead to a potential nonconformance or a condition
adverse to quality. All nonconformance’s, corrective actions, and preventative actions
shall be documented and maintained.
2.2 Measurement/Data Acquisition
2.2.1 Sampling Process Design
This soil sampling procedure is designed to describe the use of equipment and the
handling and processing of the sample after the retrieval of material. The collection of
samples may be done using hand augers, a Geoprobe or similar drilling rig.
2.2.2 Analytical Methods Requirements
Test America in Earth City, Missouri will be used for radiochemical analysis of the soil
samples. All samples shall be analyzed for 3H and 14C. Both 3H and 14C analysis will be
performed by oxidation of the sample to vaporize and capture volatile 3H and 14C. Both
the volatile and non‐volatile samples will be analyzed using a liquid scintillation counter.
The Test America analytical methods are LCS and EERF C‐01‐1, respectively.
2.2.3 Instrument/Equipment Testing, Inspection, Maintenance
Instrumentation and Equipment shall be used in accordance with DDES procedures and
policies. All instrumentation shall be calibrated in accordance with manufacturer’s
instruction or by a subcontracted laboratory calibration procedure.
2.2.4 Instrument Calibration Frequency
Calibration checks of laboratory counting equipment and field instruments shall be
performed per manufacturers or NIST specifications and periodicities. Some field
instruments do not require periodic calibration; these will be marked as such. NIST
traceable sources shall be used where applicable. Data sheets of calibration checks of
fixed laboratory counting equipment will be maintained for both source and background
during the course of the project to evaluate trends in counting data.
When field instruments are in use, daily response checks using radioactive sources with
similar energies shall be used to verify the functionality of field instruments.
Background readings will be taken as part of the daily response check.
When instruments and equipment are found out of calibration or not functioning as
expected, evaluations shall be made to assess the validity of the data obtained since the
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
9
last performance test. This evaluation shall be documented and if required, processed
as a nonconforming condition.
The following documentation shall be maintained:
Calibration Procedures
Calibration Certificates
Instrument and Equipment Inventory
Nonconformance and Corrective Action Reports
2.2.5 Data Acquisition Requirements (Non‐Direct Measurements)
The data collection process will be defined, controlled, verified, and documented. The
following activities shall be addressed in the applicable final status survey procedures:
Scanning and direct measurements
Field sampling methods
Sample handling and custody
Analytical operations for bench top laboratory equipment
Procedures shall be reviewed and approved. Procedures shall include, but are not
limited to the following:
A design which assures data is traceable to the survey and analytical procedures,
performance standards, data collectors, analysts and measuring and test
equipment.
Noting deviations from planned data‐collection operations on the survey forms
or in field logbooks.
2.3 Data Validation and Usability
2.3.1 Data Review, Validation, and Verification Requirements
Laboratory analysis shall be evaluated as follows:
External analytical laboratories will be required to provide their own data
validation package for review. As appropriate, this package may include gamma
spectrum identification information such as calibration and peak identification
measurements, isotopic quantification calculations and, if radiochemical analysis
is used, percent sample recovery.
The Project Manager will review the sample data to ensure chain of custody has
been preserved, all samples taken having corresponding sample results
provided, limits of detection are at or below criteria specified in the D&D Plan,
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
10
peak identification is correct (i.e. the radionuclide identified is associated with
the energy line in the spectrum), and calculations for peak quantification are
accurate.
Field data shall be reviewed to ensure that:
All DQOs are met as defined in the D&D Plan and Soil Sampling Plan
Forms are accurate and complete and the type of survey has correctly been
assigned to the survey unit.
The Minimum Detectable Concentration (MDC) for measurements meets the
criteria specified in the D&D Plan and Soil Sampling Plan
Instrumentation calibrations and functional checks have been performed
accurately and at the specified frequency.
2.3.2 Data Analysis
The statistical guidance contained in the Soil Sampling Plan will be used to determine if
additional surveys or sample measurements are needed.
Quality Control (QC) measurements, samples, and direct measurements are technical
activities performed to measure the residual radioactive contamination from licensed
activities. The measurement results will be compared to the criteria listed in the Soil
Sampling Plan.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
11
3.0 Field Sampling Plan
3.1 Sampling Objectives
This soil sampling plan has been designed to both complete the site soils characterization.
During the characterization phase of the sampling the goal is to fill in the existing data
gaps and bound the areas of contamination. The data will be imported into GIS based
mapping software to allow for easy identification during remediation or future sampling
campaigns.
3.2 Sampling and On‐Site Environmental Measurement Procedures
Subsurface and surface soil sampling shall be conducted using hand augers, a Geoprobe
or equivalent drilling equipment. Surface soil samples may be collected by using manual
or hand operated devices when access to sampling locations with a Geoprobe may be
impeded due to overgrowth of vegetation.
3.2.1 Surface Soil Sampling
Surface soils are classified as soils between ground surface and 6 inches below ground
surface. As these samples are obtained, they will be homogenized in stainless steel
mixing bowls.
3.2.2 Subsurface Soil Sampling
Subsurface samples are classified as those samples that are below six inches of ground
surface. These samples shall be obtained using a Geoprobe or similar using push tubes,
split spoons, etc. Subsurface soil samples will be collected from 6 inches below ground
surface to 1 meter. Sample intervals will continue in 1 meter intervals based on the
designated boring depth defined in the soil sampling plan. Each sampling interval will
be homogenized in stainless steel mixing bowls.
3.2.3 Soil Sampling Procedure
The soil sampling will be performed as follows:
Sampling personnel will don a new pair of disposable gloves immediately before
collecting soil samples at each location;
A hand‐auger or push probe will be used to collect soil at accessible locations
from 0” to 6” below ground surface;
If the hand auger or push probe is unable to access the sampling location a
Geoprobe will be used to collect soil samples;
A minimum of 500 grams of material will be collected from each sampling
location before homogenization. In the case of deep sample locations, multiple
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
12
samples will be collected in proximity to each other to obtain the necessary
sample volume;
Homogenized soil will be placed into sample containers;
A completed sample label will be affixed to each sample container and clear
packing tape used to secure the sample label to the container. Note: It may be
practical to write the applicable information directly on the containers;
A custody seal will be affixed over the lid of the sample container;
The sample number, date, time and description of the sample will be recorded
on the chain‐of‐custody (COC) record and in the field logbook. All entries will be
written in permanent black ink;
Each sample will be numbered, labeled and packaged in accordance with the
Sample Number and Sampling Packaging & Shipment sections;
Field documentation, including field logbooks and COC records, will be filled out
in accordance to the Field Records, Sample and Document Control;
The hand auger, push probe and Geoprobe shall be decontaminated in
accordance to the decontamination procedure.
3.3.4 Sample Identification
Each sample will be identified as follows:
WW: Up to 2‐character designation of the survey unit (for example, “29”)
YYY: 3‐character designation of the sample number (for example, “002”)
ZZZZ: 1‐character designation of the sample depth (for example, “3”)
For example, in the sample identification number 29‐002‐3, “29” represents the survey
unit, sample, “002” represents the sample collected at location 002, “3” represents the
depth in meters of which the sample was obtained. The sample number will be
recorded in the field logbook, on the labels or containers and chain‐of‐custody record at
the time of sample collection. A complete description of the sample and sampling
conditions will be recorded in the field logbook and referenced using the unique sample
identification number.
3.2.4 Sample Labeling
Sample labels are necessary to prevent misidentification of samples. Sample labels will
be filled out in permanent ink and affixed to sample containers at the time of sample
collection. Each sample container will be labeled with the following, at a minimum.
Sample identification number
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
13
Sample collection date (month/day/year)
Time of collection (24‐hour clock)
Samplers initials
3.2.5 Sample Packaging and Shipment
Sample packaging and shipment procedures for this project will be in accordance with
Department of Transportation (DOT) and International Air Transportation Association
(IATA) procedures as applicable for packaging and shipping of samples. Samples for
radiological will be packaged in an insulated cooler with sufficient packing material if
samples are transported by a commercial carrier.
3.2.6 Sample Handling and Mixing
Precautions will be taken to prevent sample contamination. Clean gloves, sampling and
mixing equipment will be used for each sample taken and will be decontaminated prior
to subsequent use. One member of the sampling team will be responsible for taking
field notes, filling out labels, COC’s, etc., while other members of the team shall obtain
soil samples. Collection activities will take place from the least suspect contamination
locations to the most suspect contamination locations to prevent cross contamination
between sampling locations. A minimum of 500 grams of soil shall be collected at each
sampling location.
After collection, all soil samples shall be mixed thoroughly to ensure sample uniformity.
As the required volume of soil is collected it will be transferred into stainless steel
mixing bowls to be homogenized using stainless steel mixing spoons. Once the soil has
been properly mixed, samples will be removed and placed into the sample containers
for analysis. Mixing in the bowls will consist of breaking down any clumps of material
with stainless steel spoons and stirring in a circular fashion, reversing direction and
occasionally turning the material over from the bottom of the bowl to the top to
prevent settling of the finer materials. Any rocks or debris will be removed from the
sample. After mixing is complete, the soil will be divided into two sample sets and
placed into sample containers.
3.2.7 Decontamination Procedure
Decontamination of non‐disposable sampling equipment will be performed to prevent
introduction of extraneous material into samples and to prevent cross contamination
between samples. This cleaning process will be done in a series of wash bins to assure
that contamination is not spread and enhance the probability of being able to release
the equipment from the site.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
14
The following steps will be utilized for general decontamination of non‐disposable
sampling equipment:
Clean with appropriate non‐phosphorus decontamination solution to remove
gross contamination from the equipment within a wash bin.
Rinse and perform a 2nd cleaning in the 2nd wash bin.
Rinse and wipe equipment using a water from a clean water wash bin.
Final wipe and cleaning with a dry clean cloth to remove remaining solution and
contamination from the equipment.
Radiological screening of equipment to verify effectiveness of the
decontamination for equipment that is to be taken off site at the completion of
work activities. This process will be completed using hand held survey meters
and wipes that will be analyzed using a liquid scintillation counter.
3.3 Field Records, Sample and Document Control
In order to maintain the integrity and traceability of samples, all information pertinent to field
sampling will be recorded in a field logbook. All samples will be properly labeled and custody
sealed prior to being transported to the laboratory. All samples will be accompanied by a
completed COC. All documentation will be recorded in a bound field logbook with permanent
ink.
3.4 Chain of Custody
To establish the documentation necessary to trace sample possession from the time of
collection through analysis and disposal, a COC record will be completely filled out and will
accompany every sample obtained. Samples will be delivered to the laboratory as soon as
practical. At a minimum, the following items will be on the COC record:
Project name
Sample ID
Sampler Name
Sampler Signature
Date of sample collection
Sample matrix
Sample location codes
Number of sample containers
Comments
Relinquish signature
Laboratory representative signature
Date of custody transfer
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
15
3.5 Custody Seals
Sample custody seals are used to detect unauthorized tampering of samples from the time of
sample collection to the time of analysis. The applicable seals will be signed or initialed and
dated by the sampler. The seals will be placed on the sample containers and shipping
containers in such a way that they must be broken in order to open the containers. Seals will
be affixed to containers before the samples leave the custody of the sampling personnel.
3.6 Field Logbook
A permanently bound field logbook with consecutively numbered pages, used for sampling
activity only, will be assigned to this project. All entries will be recorded in permanent ink. At
the end of each work day, the logbook pages will be signed by the responsible party and any
unused portion of the page will be crossed out, signed and dated. If it is necessary to transfer
the logbook to another person, the person relinquishing the logbook shall sign and date the last
page used, and the person receiving the logbook shall sign and date the next page to be used.
At a minimum, the logbook will contain the following information:
Project name and site location
Date and Time
Personnel in attendance
General weather information
Work performed
Field observations
Sampling performed, including specifics such as location, type of sample, type of
analyses, and sample identification numbers
Problems encountered and corrective action taken
Verbal or written instructions
Any other events that may affect the samples
3.7 Document Corrections
Changes or corrections on any project document will be made by crossing out the erroneous
item with a single line and initialing (by the person performing the correction) and dating the
correction. The original item, although erroneous, must remain legible beneath the cross‐out
line. The new information should be written clearly above the crossed‐out item.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
16
3.8 Management of Investigation‐Derived Waste
It is anticipated that Investigation‐Derived Waste (IDW) will be generated during the
characterization and final status survey soil sampling events. Anticipated waste materials that
will be generated as part of the soil sampling scopes include:
Well development and purge water
Waste soil, sediment and water
Used personal protective equipment
Decontamination liquids
Used sampling equipment
Paper towels
Sampling bottles
All wash water from the cleaning of soil samples shall be collected into 55‐gallon polyethylene
drums and held on site. 55‐gallon steel drums shall be used to collect any dry wastes
associated with this scope of work. Once the sampling event is complete, the drum(s) will be
analyzed for radiological contamination and waste profiling. IDW does not include wastes that
are generated from the displacement or removal of environmental media as a result of
remediation activities.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
17
4.0 Conclusions
The Phase 4 Soil Sampling Plan has been designed to fill the existing data gaps in the soils data
previously obtained and evaluate the area of concern south of the former building footprint. The
results of the Phase 4 sampling will be used to help calculate site‐specific DCGLs and help in the
development of a ground water monitoring strategy.
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
18
5.0 References
USEPA Soil Screening Guidance User’s Guide, Second Edition 9355.4‐23 (July 1996).
USEPA Using the Triad Apporach to Streamline Brownfields Site Cleanup (June 2003).
USEPA Guidance for the Data Quality Objectives Process EPA/240/B‐06/001 (February 1996).
NUREG 1505 A Nonparametric Statistical Methodolgy for the Analysis of Final Status
Decommissioning Surveys. (1995).
NUREG 1506, Measurement Methods for Radiological Surveys in Support of New
Decommissioning Criteria. (1995).
NUREG 1507, Minimum Detectable Concentrations with Typical Radiation Survey Instruments
for Various Contaminants and Field Conditions. (1997).
NUREG 1575, Multi‐Agency Radiation Survey and Site Investigation Manual (MARSSIM),
Revision 2. (2001).
NUREG 1727, NMSS Decommissioning Standard Review Plan, Final. (2000).
NUREG 1757, Vol. 2. Consolidated NMSS Decommissioning Guidance, Final Report. (2003).
Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01
A‐1
Attachment A:
Soil Sampling Maps
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
29-004Depth 0.15 m C-14 38
29-003Depth 0.15 m C-14 37
28-005Depth 0.15 m C-14 34
28-019Depth 0.15 m C-14 30
28-041Depth 0.15 m C-14 11
29-019Depth 0.15 m C-14 162
28-010Depth 0.15 m C-14 4.2
28-025Depth 0.15 m C-14 1.1
29-014Depth 0.15 m C-14 43.7
29-006Depth 0.15 m C-14 28.8
28-006Depth 0.15 m C-14 35.5 28-007
Depth 0.15 m C-14 15.3 28-008
Depth 0.15 m C-14 23.8
28-009Depth 0.15 m C-14 23.7
29-039Depth 0.15 m C-14 30.2
29-007Depth 0.15 m C-14 29.7
29-005Depth 0.15 m C-14 49.3
29-002Depth 0.15 m C-14 41.9
29-001Depth 0.15 m C-14 34.7
29-008Depth 0.15 m C-14 27.3
29-009Depth 0.15 m C-14 27.8
29-017Depth 0.15 m C-14 48.4
29-018Depth 0.15 m C-14 57.4
29-045Depth 0.15 m C-14 1290
29-029Depth 0.15 m C-14 15.9
29-025Depth 0.15 m C-14 49.6
29-028Depth 0.15 m C-14 40.3
29-033Depth 0.15 m C-14 25.1
29-034Depth 0.15 m C-14 10.2
29-035Depth 0.15 m C-14 27.5
28-001Depth 0.15 m C-14 0.83
28-011Depth 0.15 m C-14 11.2
28-043Depth 0.15 m C-14 2.01 28-042
Depth 0.15 m C-14 4.81
28-044Depth 0.15 m C-14 0.68 28-045
Depth 0.15 m C-14 5.05
28-004Depth 0.15 m C-14 23.2
28-023Depth 0.15 m C-14 8.92
28-022Depth 0.15 m C-14 26.7
28-021Depth 0.15 m C-14 8.08
28-020Depth 0.15 m C-14 16.9
28-018Depth 0.15 m C-14 25.5
28-016Depth 0.15 m C-14 13.9
28-015Depth 0.15 m C-14 12.6
28-014Depth 0.15 m C-14 10.5
28-013Depth 0.15 m C-14 5.14
28-012Depth 0.15 m C-14 3.97
28-029Depth 0.15 m C-14 1.07
28-030Depth 0.15 m C-14 5.56
28-031Depth 0.15 m C-14 15.7
28-032Depth 0.15 m C-14 29.3
28-033Depth 0.15 m C-14 31.3
28-034Depth 0.15 m C-14 8.69
28-035Depth 0.15 m C-14 2.29
28-036Depth 0.15 m C-14 1.95
28-037Depth 0.15 m C-14 6.22
28-038Depth 0.15 m C-14 1.64
28-039Depth 0.15 m C-14 10.2
28-040Depth 0.15 m C-14 10.8
28-059Depth 0.15 m C-14 19.5
28-058Depth 0.15 m C-14 3.62
28-057Depth 0.15 m C-14 6.72
28-056Depth 0.15 m C-14 4.96
28-055Depth 0.15 m C-14 4.28
28-054Depth 0.15 m C-14 2.62
28-053Depth 0.15 m C-14 2.62
28-052Depth 0.15 m C-14 6.55
28-051Depth 0.15 m C-14 3.79
28-050Depth 0.15 m C-14 7.92
28-049Depth 0.15 m C-14 3.65
28-048Depth 0.15 m C-14 4.22
28-047Depth 0.15 m C-14 42.5
28-046Depth 0.15 m C-14 9.36
28-027Depth 0.15 m C-14 1.065
28-026Depth 0.15 m C-14 0.795
28-024Depth 0.15 m C-14 0.945
28-017Depth 0.15 m C-14 0.995
28-028Depth 0.15 m C-14 0.915
28-060Depth 0.15 m C-14 0.925
ST-009Depth 0.15 m C-14 136Depth 1 m C-14 43.8
29-016Depth 0.15 m C-14 109Depth 1 m C-14 0.66
ST-008Depth 0.15 m C-14 22.9Depth 1 m C-14 9.54
29-048Depth 0.15 m C-14 71.8Depth 1 m C-14 96.9
29-038Depth 0.15 m C-14 95.4Depth 1 m C-14 3.01
29-013Depth 0.15 m C-14 63.7Depth 1 m C-14 4.38
29-012Depth 0.15 m C-14 104Depth 1 m C-14 0.755
29-010Depth 0.15 m C-14 93.8Depth 1 m C-14 3.55
29-011Depth 0.15 m C-14 85.8Depth 1 m C-14 17.2
29-021Depth 0.15 m C-14 65.1Depth 1 m C-14 3.86
29-026Depth 0.15 m C-14 95.8Depth 1 m C-14 9.71
29-027Depth 0.15 m C-14 99.2Depth 1 m C-14 25.2
29-031Depth 0.15 m C-14 96.1Depth 1 m C-14 6.31
ST-010Depth 0.15 m C-14 21.1Depth 1 m C-14 0.735
29-020Depth 0.15 m C-14 59.9Depth 1 m C-14 0.725
29-032Depth 0.15 m C-14 81.4Depth 1 m C-14 0.795
29-041Depth 0.15 m C-14 0.825Depth 1 m C-14 0.78
29-051Depth 0.15 m C-14 95Depth 1 m C-14 145Depth 2 m C-14 74.3
29-061Depth 0.15 m C-14 483Depth 1 m C-14 128Depth 2 m C-14 398
29-049Depth 0.15 m C-14 38.4Depth 1 m C-14 978Depth 2 m C-14 189
29-040Depth 0.15 m C-14 159Depth 1 m C-14 120Depth 2 m C-14 27.5
29-056Depth 0.15 m C-14 34Depth 1 m C-14 0.78Depth 2 m C-14 3.35
29-015Depth 0.15 m C-14 305Depth 1 m C-14 4.14Depth 2 m C-14 175
29-047Depth 0.15 m C-14 12.1Depth 1 m C-14 422Depth 2 m C-14 30.8
29-050Depth 0.15 m C-14 122Depth 1 m C-14 5.35Depth 2 m C-14 14.6
29-058Depth 0.15 m C-14 12.7Depth 1 m C-14 3.7Depth 2 m C-14 2.83
29-068Depth 0.15 m C-14 5.3Depth 1 m C-14 2.7Depth 2 m C-14 0.735
29-055Depth 0.15 m C-14 108Depth 1 m C-14 3.47Depth 2 m C-14 16.6
29-046Depth 0.15 m C-14 52.3Depth 1 m C-14 11.8Depth 2 m C-14 1.8
29-022Depth 0.15 m C-14 200Depth 1 m C-14 59.9Depth 2 m C-14 6.07
29-030Depth 0.15 m C-14 257Depth 1 m C-14 9.74Depth 2 m C-14 6.78
29-023Depth 0.15 m C-14 163Depth 1 m C-14 38.2Depth 2 m C-14 8.75
29-024Depth 0.15 m C-14 125Depth 1 m C-14 1.92Depth 2 m C-14 1.85
29-053Depth 0.15 m C-14 25.3Depth 1 m C-14 5.43Depth 2 m C-14 12.6
29-059Depth 0.15 m C-14 2.14Depth 1 m C-14 10.5Depth 2 m C-14 4.58
29-060Depth 0.15 m C-14 3.95Depth 1 m C-14 0.76Depth 2 m C-14 2.53
29-057Depth 0.15 m C-14 24.9Depth 1 m C-14 0.89Depth 2 m C-14 11.1
29-054Depth 0.15 m C-14 35.2Depth 1 m C-14 6.47Depth 2 m C-14 14.5
29-043Depth 0.15 m C-14 7.61Depth 1 m C-14 0.785Depth 2 m C-14 5.8
29-044Depth 0.15 m C-14 43.2Depth 1 m C-14 31.7Depth 2 m C-14 12.4
29-042Depth 0.15 m C-14 17.5Depth 1 m C-14 8.39Depth 2 m C-14 2.32
29-064Depth 0.15 m C-14 0.72Depth 1 m C-14 0.685Depth 2 m C-14 0.71
29-063Depth 0.15 m C-14 3.32Depth 1 m C-14 0.885Depth 2 m C-14 0.81 29-065
Depth 0.15 m C-14 5.03Depth 1 m C-14 0.745Depth 2 m C-14 0.735
28-003Depth 0.15 m C-14 35.7
28-002Depth 0.15 m C-14 11.4
29-036Depth 0.15 m C-14 62.8Depth 1 m C-14 0.795
29-037Depth 0.15 m C-14 191Depth 1 m C-14 2.94Depth 2 m C-14 2.44
29-052Depth 0.15 m C-14 11.5Depth 1 m C-14 18.6Depth 2 m C-14 5.77
29-066Depth 0.15 m C-14 0.74Depth 1 m C-14 0.785Depth 2 m C-14 15.4
29-067Depth 0.15 m C-14 12.3Depth 1 m C-14 3.81Depth 2 m C-14 0.83529-062
Depth 0.15 m C-14 3.3Depth 1 m C-14 5.35Depth 2 m C-14 3.71
±X:\
DDES
\SiteM
ap_H
3_C1
4.mxd
0 10 20 30 40 50Feet
Sigman Aldrich Soil ResultsC-14
Sigman Aldrich Fort Mims Facility11542 Fort Mims drive
Maryland Heights, MissouriM. NortonREQUESTED BY:
DATE: 3/12/2015MA-15-028-02PROJECT NO:
M. SenneDRAWN BY:
Legend!? Soil Sample Location
FMF-28FMF-29
Googe Earth Pro Imagery: 10/21/2014
Note:- All Sample Units are in pCi/g
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
28-008Depth 0.15 m H-3 21
29-003Depth 0.15 m H-3 11
29-009Depth 0.15 m H-3 1.7
29-034Depth 0.15 m H-3 5.9
28-010Depth 0.15 m H-3 5.7
28-044Depth 0.15 m H-3 6.7
28-025Depth 0.15 m H-3 3.1
29-014Depth 0.15 m H-3 2.92
29-006Depth 0.15 m H-3 3.32
28-027Depth 0.15 m H-3 2.71
28-006Depth 0.15 m H-3 12.3 28-007
Depth 0.15 m H-3 18.6 28-009
Depth 0.15 m H-3 16.9
29-039Depth 0.15 m H-3 7.35
29-007Depth 0.15 m H-3 9.57
29-005Depth 0.15 m H-3 8.74
29-004Depth 0.15 m H-3 9.55
29-002Depth 0.15 m H-3 6.82
29-001Depth 0.15 m H-3 2.78
29-008Depth 0.15 m H-3 5.34
29-017Depth 0.15 m H-3 3.42
29-018Depth 0.15 m H-3 9.06
29-019Depth 0.15 m H-3 29.4
29-045Depth 0.15 m H-3 10.5
29-029Depth 0.15 m H-3 2.14
29-025Depth 0.15 m H-3 2.62
29-028Depth 0.15 m H-3 5.24
29-035Depth 0.15 m H-3 3.13
28-005Depth 0.15 m H-3 3.45
28-001Depth 0.15 m H-3 8.88
28-011Depth 0.15 m H-3 13.6
28-043Depth 0.15 m H-3 6.95 28-042
Depth 0.15 m H-3 14.2
28-045Depth 0.15 m H-3 9.92
28-004Depth 0.15 m H-3 6.81
28-003Depth 0.15 m H-3 19.2
28-002Depth 0.15 m H-3 17.9
28-026Depth 0.15 m H-3 2.76
28-024Depth 0.15 m H-3 2.05
28-023Depth 0.15 m H-3 5.52
28-022Depth 0.15 m H-3 7.27
28-021Depth 0.15 m H-3 9.26
28-020Depth 0.15 m H-3 21.8
28-019Depth 0.15 m H-3 15.8
28-018Depth 0.15 m H-3 8.25
28-017Depth 0.15 m H-3 4.72
28-016Depth 0.15 m H-3 5.39
28-015Depth 0.15 m H-3 14.9
28-014Depth 0.15 m H-3 11.2
28-013Depth 0.15 m H-3 6.52
28-012Depth 0.15 m H-3 4.86
28-028Depth 0.15 m H-3 4.18
28-029Depth 0.15 m H-3 2.23
28-030Depth 0.15 m H-3 3.05
28-031Depth 0.15 m H-3 3.37
28-032Depth 0.15 m H-3 4.57
28-033Depth 0.15 m H-3 4.56
28-034Depth 0.15 m H-3 6.47
28-035Depth 0.15 m H-3 4.97
28-036Depth 0.15 m H-3 3.41
28-037Depth 0.15 m H-3 4.41
28-038Depth 0.15 m H-3 1.65
28-039Depth 0.15 m H-3 8.24
28-040Depth 0.15 m H-3 6.31
28-041Depth 0.15 m H-3 8.11
28-060Depth 0.15 m H-3 6.44
28-059Depth 0.15 m H-3 4.03
28-058Depth 0.15 m H-3 6.16
28-057Depth 0.15 m H-3 15.4
28-056Depth 0.15 m H-3 15.9
28-055Depth 0.15 m H-3 13.1
28-054Depth 0.15 m H-3 3.54
28-053Depth 0.15 m H-3 9.56
28-052Depth 0.15 m H-3 4.63
28-051Depth 0.15 m H-3 3.88
28-050Depth 0.15 m H-3 7.98
28-049Depth 0.15 m H-3 10.7
28-048Depth 0.15 m H-3 10.2
28-047Depth 0.15 m H-3 28.2
28-046Depth 0.15 m H-3 11.1
29-033Depth 0.15 m H-3 0.745
29-011Depth 0.15 m H-3 13Depth 1 m H-3 2
29-010Depth 0.15 m H-3 14Depth 1 m H-3 2.39
ST-008Depth 0.15 m H-3 3.98Depth 1 m H-3 0.9
29-048Depth 0.15 m H-3 2.27Depth 1 m H-3 3.6
29-016Depth 0.15 m H-3 5.6Depth 1 m H-3 1.86
29-038Depth 0.15 m H-3 18.5Depth 1 m H-3 2.33
29-012Depth 0.15 m H-3 9.88Depth 1 m H-3 4.19
29-020Depth 0.15 m H-3 5.83Depth 1 m H-3 0.51
29-021Depth 0.15 m H-3 4.13Depth 1 m H-3 1.75
29-026Depth 0.15 m H-3 22.3Depth 1 m H-3 1.54
29-027Depth 0.15 m H-3 8.88Depth 1 m H-3 2.21
29-032Depth 0.15 m H-3 5.28Depth 1 m H-3 0.56
29-031Depth 0.15 m H-3 4.46Depth 1 m H-3 1.99
29-041Depth 0.15 m H-3 0.58Depth 1 m H-3 2.48
29-036Depth 0.15 m H-3 5.65Depth 1 m H-3 0.56
ST-009Depth 0.15 m H-3 0.945Depth 1 m H-3 2.41
29-013Depth 0.15 m H-3 17.5Depth 1 m H-3 0.555
ST-010Depth 0.15 m H-3 1.015Depth 1 m H-3 1.005
29-047Depth 0.15 m H-3 0.595Depth 1 m H-3 6Depth 2 m H-3 6.92
29-066Depth 0.15 m H-3 1Depth 1 m H-3 1.03Depth 2 m H-3 0.895
29-049Depth 0.15 m H-3 13.1Depth 1 m H-3 11.6Depth 2 m H-3 7.9
29-040Depth 0.15 m H-3 42.5Depth 1 m H-3 3.32Depth 2 m H-3 3.61
29-059Depth 0.15 m H-3 1.07Depth 1 m H-3 0.9Depth 2 m H-3 0.965
29-061Depth 0.15 m H-3 6.83Depth 1 m H-3 2.88Depth 2 m H-3 7.39
29-057Depth 0.15 m H-3 1.09Depth 1 m H-3 1.12Depth 2 m H-3 1.08
29-015Depth 0.15 m H-3 7.91Depth 1 m H-3 1.61Depth 2 m H-3 3.52
29-043Depth 0.15 m H-3 0.59Depth 1 m H-3 0.55Depth 2 m H-3 0.52
29-030Depth 0.15 m H-3 4.01Depth 1 m H-3 1.74Depth 2 m H-3 1.56
29-023Depth 0.15 m H-3 7.02Depth 1 m H-3 2.23Depth 2 m H-3 0.52
29-042Depth 0.15 m H-3 3.13Depth 1 m H-3 1.71Depth 2 m H-3 1.64
29-051Depth 0.15 m H-3 4.42Depth 1 m H-3 4.48Depth 2 m H-3 1.115
29-067Depth 0.15 m H-3 2.21Depth 1 m H-3 3.12Depth 2 m H-3 1.095
29-068Depth 0.15 m H-3 0.925Depth 1 m H-3 3.96Depth 2 m H-3 0.96
29-060Depth 0.15 m H-3 3.21Depth 1 m H-3 0.96Depth 2 m H-3 0.905
29-056Depth 0.15 m H-3 1.05Depth 1 m H-3 0.985Depth 2 m H-3 0.84
29-055Depth 0.15 m H-3 3.22Depth 1 m H-3 0.985Depth 2 m H-3 0.94
29-022Depth 0.15 m H-3 6.88Depth 1 m H-3 3.06Depth 2 m H-3 0.438
29-050Depth 0.15 m H-3 0.575Depth 1 m H-3 0.59Depth 2 m H-3 0.585
29-064Depth 0.15 m H-3 0.905Depth 1 m H-3 0.865Depth 2 m H-3 1.99
29-063Depth 0.15 m H-3 0.885Depth 1 m H-3 1.115Depth 2 m H-3 1.02
29-053Depth 0.15 m H-3 1.09Depth 1 m H-3 1.115Depth 2 m H-3 0.935
29-052Depth 0.15 m H-3 1.045Depth 1 m H-3 1.02Depth 2 m H-3 1.045
29-058Depth 0.15 m H-3 0.86Depth 1 m H-3 0.945Depth 2 m H-3 1.005
29-065Depth 0.15 m H-3 0.915Depth 1 m H-3 0.935Depth 2 m H-3 0.93
29-054Depth 0.15 m H-3 1.005Depth 1 m H-3 0.98Depth 2 m H-3 0.845
29-024Depth 0.15 m H-3 6.58Depth 1 m H-3 0.473Depth 2 m H-3 0.535
29-037Depth 0.15 m H-3 10.6Depth 1 m H-3 1.72Depth 2 m H-3 0.4925
29-046Depth 0.15 m H-3 0.535Depth 1 m H-3 0.505Depth 2 m H-3 0.423
29-044Depth 0.15 m H-3 0.545Depth 1 m H-3 0.4195Depth 2 m H-3 0.477
29-062Depth 0.15 m H-3 0.83Depth 1 m H-3 1.08Depth 2 m H-3 0.9
±X:\
DDES
\SiteM
ap_H
3_C1
4.mxd
0 10 20 30 40 50Feet
Sigman Aldrich Soil ResultsH-3
Sigman Aldrich Fort Mims Facility11542 Fort Mims drive
Maryland Heights, MissouriM. NortonREQUESTED BY:
DATE: 3/12/2015MA-15-028-02PROJECT NO:
M. SenneDRAWN BY:
Legend!? Soil Sample Location
FMF-28FMF-29
Googe Earth Pro Imagery: 10/21/2014
Note:- All Sample Units are in pCi/g
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
!?
29-00429-003
28-00528-019
28-041
29-019
28-010
28-025
29-014
29-006
28-00628-007
28-008 28-009
29-039
29-007
29-005
29-00229-001
29-00829-009
29-01729-018
29-045
29-029
29-025
29-028
29-033
29-034 29-035
28-001
28-011
28-04328-042
28-04428-045
28-004
28-02328-022
28-02128-020
28-018
28-01628-015
28-01428-013
28-012
28-02928-030
28-03128-032
28-03328-034
28-03528-036
28-03728-038
28-03928-040
28-05928-058
28-05728-056
28-05528-054
28-05328-052
28-05128-050
28-04928-048
28-04728-046
28-027
28-026
28-024
28-017 28-028
28-060
ST-009
29-016
ST-008
29-048
29-038
29-01329-012
29-01029-011
29-021
29-026
29-027
29-031
ST-010
29-020
29-032
29-041
29-051
29-061
29-049
29-040
29-056
29-015
29-047
29-050
29-058
29-068
29-055
29-046
29-022
29-030
29-023
29-024
29-053
29-059
29-060
29-057
29-054
29-043
29-044
29-042
29-064
29-063
29-065
28-00328-002 29-036
29-037
29-052
29-066
29-067
29-062
29-73
29-8129-82
29-7429-75
29-76
29-7129-72
29-7730-78
29-7929-80
29-83 29-8430-85
30-9030-91
30-89
30-9230-93
30-9430-95
30-8730-88
30-86
309630-97
30-98
±X:\
DDES
\SiteM
ap_H
3_C1
4_Pr
opos
ed.m
xd
0 10 20 30 40 50Feet
Phase 4 Soil Sampling LocationsSigman Aldrich Fort Mims Facility
11542 Fort Mims driveMaryland Heights, Missouri
M. NortonREQUESTED BY:
DATE: 3/12/2015MA-15-028-02PROJECT NO:
M. SenneDRAWN BY:
Legend!? Existing Soil Sample Location
Proposed Soil Sample LocationFMF-28FMF-29
Googe Earth Pro Imagery: 10/21/2014
29-6929-70
29-99
29-10029-100