4 Soil Sampling and Analysis Plan Site

25
Phase 4 Soil Sampling and Analysis Plan SigmaAldrich Fort Mims Site Maryland Heights, Missouri U.S. Nuclear Regulatory Commission Radioactive Materials License No. 241627601 SigmaAldrich Company PO Box 14508 St. Louis, MO 63178 Prepared by: DDES LLC 345 North Avenue, 2 nd Floor Wakefield, MA 01880 February 26, 2015

Transcript of 4 Soil Sampling and Analysis Plan Site

Page 1: 4 Soil Sampling and Analysis Plan Site

Phase 4 ‐ Soil Sampling and Analysis Plan 

Sigma‐Aldrich Fort Mims Site 

Maryland Heights, Missouri  

 U.S. Nuclear Regulatory Commission  Radioactive Materials License No. 24‐16276‐01 

 

 Sigma‐Aldrich Company PO Box 14508 St. Louis, MO 63178 

   

Prepared by:   

  

DDES LLC 345 North Avenue, 2nd Floor Wakefield, MA 01880    February 26, 2015 

Page 2: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

ii  

Table of Contents 1.0  Introduction ......................................................................................................................... 1 

1.1  Background .......................................................................................................................... 1 

1.2  Contaminants of Concern .................................................................................................... 2 

1.3  Date Quality Objectives ....................................................................................................... 2 

1.3.1  Statement of the Problem ............................................................................................ 2 

1.3.2  Sample Design Summary .............................................................................................. 2 

1.4  Characterization Design for Soil Areas................................................................................. 2 

1.4.1  Site Screening Levels ........................................................................................................ 4 

2.0  Quality Assurance Project Plan ............................................................................................ 5 

2.1  Project Management ........................................................................................................... 5 

2.1.1  Project/Task Organization ............................................................................................ 5 

2.1.2  Special Training Requirements/Certification ............................................................... 6 

2.1.3  Documentation and Records ........................................................................................ 7 

2.1.4  Nonconformance Control and Corrective Action ......................................................... 8 

2.2  Measurement/Data Acquisition .......................................................................................... 8 

2.2.1  Sampling Process Design .............................................................................................. 8 

2.2.2  Analytical Methods Requirements ............................................................................... 8 

2.2.3  Instrument/Equipment Testing, Inspection, Maintenance .......................................... 8 

2.2.4  Instrument Calibration Frequency ............................................................................... 8 

2.2.5  Data Acquisition Requirements (Non‐Direct Measurements) ..................................... 9 

2.3  Data Validation and Usability .............................................................................................. 9 

2.3.1  Data Review, Validation, and Verification Requirements ............................................ 9 

2.3.2  Data Analysis ............................................................................................................... 10 

3.0  Field Sampling Plan ............................................................................................................ 11 

3.1  Sampling Objectives ........................................................................................................... 11 

3.2  Sampling and On‐Site Environmental Measurement Procedures ..................................... 11 

3.2.1  Surface Soil Sampling ..................................................................................................... 11 

Page 3: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

iii  

3.2.2  Subsurface Soil Sampling ............................................................................................... 11 

3.2.3  Soil Sampling Procedure ................................................................................................. 11 

3.3.4 Sample Identification ........................................................................................................... 12 

3.2.4  Sample Labeling ............................................................................................................. 12 

3.2.5  Sample Packaging and Shipment ................................................................................... 13 

3.2.6  Sample Handling and Mixing .......................................................................................... 13 

3.2.7  Decontamination Procedure .......................................................................................... 13 

3.3  Field Records, Sample and Document Control .................................................................. 14 

3.4  Chain of Custody ................................................................................................................ 14 

3.5  Custody Seals ..................................................................................................................... 15 

3.6  Field Logbook ..................................................................................................................... 15 

3.7  Document Corrections ....................................................................................................... 15 

3.8  Management of Investigation‐Derived Waste .................................................................. 16 

4.0  Conclusions ........................................................................................................................ 17 

5.0  References ......................................................................................................................... 18 

Attachment A: ....................................................................................................................... A‐1 

 

 

Page 4: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

A‐1  

1.0 Introduction 

The Fort Mims Site occupies approximately one‐acre open land area with no structures.  This site 

was  once  occupied  by  Sigma‐Aldrich’s  radiochemistry  facility  that  was  previously 

decommissioned  and  demolished  in  compliance with  in NUREG  1757  Volume  2,  Consolidated 

NMSS  Decommissioning  Guidance  and  NUREG  1575, Multi‐Agency  Radiation  Survey  and  Site 

Investigation  Manual  (MARSSIM).    The  document  describes  the  approach,  methods  and 

techniques  for  the  design  and  performance  of  characterization  and  final  status  surveys.    This 

parcel of land is located in a commercial/light industrial park in Maryland Height, Missouri.   The 

Fort  Mims  facility  currently  operates  under  U.S.  Nuclear  Regulatory  Commission  (NRC) 

Radioactive Materials License Number 24‐16273‐01.  

This soil‐sampling plan is designed to define the lateral and vertical extent of carbon‐14 (14C) and 

tritium (3H) contamination in soils at the site by using the United States Environmental Protection 

Agency  (EPA)  Triad  approach  for  site  assessment  and  cleanup.    The  original  approved  soil 

sampling  plan  was  designed  to  evaluate  the  upper  six  inches  of  surface  soil  following  the 

guidance  of  MARSSIM.    The  soil  sample  results  indicate  detectible  concentrations  of 

contaminants present well below the surface (>6 inches).   

As such, the Phase 4 soil sampling approach uses the previous soil sampling data to identify areas 

of concern which require further characterization to define the vertical and horizontal extent of 

contamination.   The goal of this sampling event  is to define the extent of contamination at the 

site  so  that  site‐specific Derived Concentration Guidance Levels  (DCGLs) can be developed and 

groundwater monitoring  locations can be selected.     All soil sampling activities shall be carried 

out in accordance with the Sigma Aldrich Fort Mims Decommissioning Health and Safety Plan. 

1.1 Background 

There  have  been  three  phases  of  soil  sampling  that  have  occurred  to  date.   A  total  of  two 

hundred  fourteen  (214)  discrete  soil  samples  have  been  obtained  from  the  site  from  three 

previous soil sampling events.  The first two soil sampling events were performed in compliance 

with the approved Open Land Soil Sampling Plan dated October 20th, 2008.  The third round of 

soil sampling used biased sampling to evaluate the former building footprint and former septic 

system  at  the  site.    The  soil  sampling  results  from  each  round  of  sampling  indicated 

contamination exceeded  the approved default  screening value of 12 picoCuries/Gram  (pCi/g) 

for 14C in both surface and subsurface soils.               

Past  site  characterization  events  have  failed  to  bound  the  extent  of  horizontal  and  vertical 

contamination in soils at the site.   

Page 5: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

2  

1.2 Contaminants of Concern 

Through  interviews, characterization and historical  site data  it has been determined  that  the 

Nuclides of Concern  (NOC)  for  this  facility decommissioning  are Carbon‐14  (14C)  and  Tritium 

(3H). Through  the  first  three phases of  soil  sampling only one soil sampling  location near  the 

former septic tank  location exceeded the approved default screening value  for tritium  (3H) of 

110 pCi/g.   

1.3 Data Quality Objectives 

1.3.1 Statement of the Problem 

A number of soil contamination data gaps exist  from  the  three previous soil sampling 

events. The Fort Mims facility requires further soils characterization  in order to bound 

the vertical and horizontal extent of contamination.  This data is necessary to help in the 

development of site‐specific DCGLs.   

1.3.2 Sample Design Summary 

The  sample  design  and  DQOs  were  based  on  the  USEPA  Soil  Screening  Guidance 

(EPA/540/R‐96/018),  the USEPA Guidance  for  the Data Quality Objectives Process and 

the USEPA  Using  the  Triad  Approach  to  Streamline  Brownfields  Site  Assessment  and 

Cleanup.   

1.4 Characterization Design for Soil Areas 

A Conceptual Site Model (CSM) was developed based on review of the existing data obtained 

during prior sampling events combined with  the historic operations onsite.   The existing soils 

data and survey maps were combined into a single CSM using Geographic Information System 

(GIS) to provide  location and depth of sampling.   This data was  imported  into Spatial Analysis 

Decision Assistance (SADA) 5.0.7800.0 software to create a 3D model of existing contamination 

levels at the site.   

Review of  this data and operational history  indicate  there are  two potential  sources of  soils 

contamination onsite:  

Soil deposition from exhaust stack emissions to the west of the former building  

Deposition from exhaust stack emissions on the roof in which rain runoff drained to the 

south and southwest corner of the former building 

Septic disposal of contaminants under the former foundation of the building   

While the potential contaminant source for two of these areas may be linked to exhaust stack 

emissions, the mechanisms for fate and transport are very different.   The current soil data for 

the open  land area west of  the  former building  indicate surficial deposition over a wide area 

Page 6: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

3  

has occurred with  little vertical movement of contaminants  in soil.   The data  from the runoff 

area  south and  southwest of  the  former building  indicate  that  contaminants may have been 

transported deeper in soils by runoff.  This will require sampling at greater depths to define the 

vertical extent of contamination. 

The  former septic system has  the highest potential  for migration of contaminants due  to  the 

volume of water passing though this contaminated area.   Soil samples will be required at the 

greatest depth in this location and down gradient of the water pathway.     

It will also be necessary  to expand  the  survey units  to  include additional areas  south of  the 

property boundary of the site.  This will encompass the parcel of land to the south and east of 

the  former  building  location.    The  highest  contamination  levels  were  located  between  the 

former  building  and  south  property  boundary,  thus  resulting  in  further  investigation.  

Therefore,  samples will be heavily  focused on  the  areas where  contamination  is  likely  to be 

present  in order to quantify the boundaries of contamination.   This will be done to verify and 

help bound the known areas of contamination.  

This sampling design covers both the data gaps identified from the previous sampling events as 

well  as  extend  sampling  to  new  areas  of  concern.    Samples will  be  obtained  from  previous 

sample coordinates where contamination levels exceed 50 pCi/g for 14C at the deepest interval 

sampled.    In these  locations, one additional sample will be collected  from 1 meter below the 

last  recorded  sample  depth.    Table  1.4‐1  lists  the  locations  and  depths where  the  data  gap 

samples will  be  obtained.   Attachment A  – Data Gap  Samples  depicts  the  locations  of  each 

proposed data gap sample.      

Table 1.4‐1 Data Gap Sample Locations 

Location Depth (Meters) 

29‐015  3 

29‐018  1 

29‐019  1 

29‐045  1, 2, 3 

29‐049  3 

29‐051  3 

29‐061  3 

 

In  addition  to  the  data  gap  sample  locations  described  above,  Additional  samples  shall  be 

obtained  from Survey Unit 29  in order  to properly characterize the  former exhaust stack and 

steric systems areas.  Survey Unit 30 will evaluate the open land area to the south and east of 

Page 7: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

4  

the  former  building  footprint.    This  land  area  slopes  towards  the  south  and  surface 

contamination may have migrated following the surface water runoff pathway.   These sample 

locations are depicted in Attachment A.   

The Phase  4  sample  locations were based off  the previously  established  triangular  sampling 

grids to evaluate adjacent areas where sampling results exceeded 50 pCi/g.  For the purpose of 

this investigation, the lateral spacing between these additional locations will match the Phase 3 

sampling event which was approximately 9.1 meters.  A field technician will verify the location 

of each  sample using a Trimble GPS  tracker unit.   At each of  the new  locations, one  surface 

sample will be collected from 0 ‐ 6  inches below the ground surface.   Additional samples shall 

be collected at these locations at 1 meter, 2 meter and 3 meter depths.  These sample locations 

are depicted in Attachment A.     

1.4.1 Site Screening Levels 

Site screening levels (SSL) have been set at 50 pCi/g for 14C and 220 pCi/g for 3H based 

off the previous soil sampling results.  The SSL’s do not correspond to a specific annual 

dose  limit but  are  to be used  as  a decision point  to determine when  additional data 

should be obtained. 

Site‐specific  DCGLs  for  subsurface  soils  will  be  developed  once  the  horizontal  and 

vertical extent of contamination has been determined.   

   

Page 8: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

5  

2.0 Quality Assurance Project Plan 

2.1 Project Management 

2.1.1 Project/Task Organization 

The  project  organization  described  in  this  section  shall  be  responsible  for  achieving 

quality  on  this  project.    Verification  personnel,  whether  in  line  or  organizationally 

independent, have sufficient freedom, authority, access, and responsibility to: 

Identify  quality  problems,  deficiencies  in  hardware  and  documentation,  and 

noncompliance with performance objectives. 

Initiate, recommend, or provide solutions through designated channels 

Verify implementation of the solutions 

Assure  that  deficient  work  is  stopped  or  is  proceeding  under  controlled 

conditions  until  proper  disposition  of  the  unsatisfactory  condition  is 

accomplished. 

The quality related responsibilities  for the management positions of the Sigma‐Aldrich 

Fort  Mims  Decommissioning  are  provided  in  Table  2‐1.    Where  titles  are  used  to 

designate  responsibility  the  named  position  has  the  authority  to  designate  another 

qualified position within the organization to perform an assigned task.  The incumbent, 

however,  retains  the  responsibility  for  implementing  the  requirements.    Project 

organizations operate directly in accordance with this QAPP. 

The  Project Manager  (PM)  is  responsible  for  the  overall  safe,  timely  and  cost 

effective completion of the project.   The  individual  is responsible for all project 

activities  and  directly  supervises  the  Sr.  Health  Physics  Technicians  and 

subcontractors; approve all project expenditures; provide interface between the 

client and company  resources; and maintain project budget and  schedules.    In 

addition,  the  PM  is  responsible  for  ensuring  the  elements  of  this  QAPP  are 

successfully implemented. 

The Quality Assurance Representative  is  responsible  for  the  development  and 

issuance  of  this  QAPP  and  reviewing  and  concurring  with  project  plans  and 

procedures  affecting  quality.    The  Quality  Assurance  Representative  is  also 

responsible for the following: 

o Advising management of quality achievement and recommending means 

of improving quality performance. 

o Establishing  generic  project management/quality  assurance  procedures 

and instructions. Verifying the quality of work by audit or surveillance. 

o Investigating quality issues. 

o Furnishing quality assurance expertise to support project assessments.  

Page 9: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

6  

The  Senior  Health  Physics  Manger  is  responsible  for  survey  planning, 

implementation  and  documentation.    This  individual  is  responsible  for 

implementation of the D&D Plan and meeting all data quality objectives.  

The Health and Safety Officer is responsible for implementing project health and 

safety and the DDES Health and Safety Program.   The Health and Safety Officer 

reports directly to the Corporate Safety and Health Manager.  

The Senior Health Physics Technician is responsible for implementing all aspects 

of radiation safety and data collection.  

All personnel have the responsibility for executing their work and ensuring that quality‐

affecting activities within  their purview are performed  in conformance with  this QAPP 

and the applicable approved plans and procedures. 

All project personnel have the authority and responsibility to stop their own work when 

continuation will produce or conceal results that are not in accordance with prescribed 

requirements  of  this  QAPP,  and  the  responsibility  to  report  such  conditions  to  line 

management.  

2.1.2 Special Training Requirements/Certification 

Project  personnel  shall  be  indoctrinated  and  trained  in  accordance  with  this  QAPP, 

project specific documents, applicable DDES corporate procedures and applicable Sigma 

Aldrich procedures. 

Indoctrination  to  the  project  scope  of  work  shall  be  provided  to  all  project 

personnel 

Project Personnel shall be provided sufficient training prior to commencement of 

the  individuals assigned  task(s).   The extent of  training  shall be determined by 

the Project Manager.  The extent of training shall be based on scope, complexity, 

and nature of the assigned task(s), education, experience, previous training, and 

proficiency of the individual. 

The training method employed may be one or all of the following: 

o Classroom instruction; 

o Reading assignments; 

o On‐the‐job; 

o Practical demonstration 

Education  and  experience  qualifications  shall  be  documented  by  resume with 

relevant formal educational training certificates enclosed with the resume. 

All  forms  of  personnel  indoctrination  and  training  shall  be  documented  and 

maintained. 

Page 10: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

7  

All employees exposed to hazardous substances, safety hazards or health hazards shall 

be thoroughly trained as prescribed by 29 CFR 1910.120.  Training of project employees 

shall include: 

Safety, Health and other site hazards 

Proper use of PPE 

Work practices that can minimize risks from hazards 

Engineering controls 

Equipment use 

Medical surveillance requirements 

At  a  minimum  all  project  employees  shall  be  required  to  be  trained  in  a  40  hour 

Hazardous Waste Operations  and  Emergency  Response  (HAZWOPER)  training  course. 

This training requires an  initial 40‐hour session of off‐site  instruction and three days of 

field  experience.   There  are  additional  requirements  for  occasional  site  workers, 

managers and supervisors.  29 CFR 1910.120(e)(8) addresses  refresher  training  for 40‐

hour site worker certified employees; this refresher training is eight hours in length. 

2.1.3 Documentation and Records 

Project  documents  and  records  that  shall  be  considered  Quality  Assurance  Records 

include but are not limited to the following: 

Decommissioning Plan 

Health and Safety Plan 

Soil Sampling Plan 

Project‐Specific Procedures 

Supporting Quality Assurance Procedures 

Project  documents  shall  be  reviewed  for  adequacy  and  approved  by  authorized 

personnel.  Document control shall insure that only the most current documents are in 

use during the performance of project activities.  Project‐specific and supporting quality 

assurance  procedures,  work  instructions,  quality  plans  and  other  documents  which 

specify  quality  requirements  or  prescribe  activities  affecting  quality  shall  define  the 

required documents or data to be maintained as Quality Assurance Records.  Additional 

documents such as quality‐related procurements for items and sub‐contracted services, 

personnel training records and qualification documentation shall also be maintained as 

Quality Assurance Records. Records shall be protected against damage, deterioration or 

loss.  

Page 11: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

8  

2.1.4 Nonconformance Control and Corrective Action 

All  project  personnel  shall  be  responsible  for  notifying  their  supervisor,  the  Project 

Manager, or  the Quality Assurance Manager of  conditions or  items  that do not meet 

specified  requirements. All  project personnel  are  encouraged  to  identify  any  activity, 

process,  or  procedure  that  could  lead  to  a  potential  nonconformance  or  a  condition 

adverse to quality.   All nonconformance’s, corrective actions, and preventative actions 

shall be documented and maintained. 

2.2 Measurement/Data Acquisition 

2.2.1 Sampling Process Design 

This  soil  sampling  procedure  is  designed  to  describe  the  use  of  equipment  and  the 

handling and processing of the sample after the retrieval of material.  The collection of 

samples may be done using hand augers, a Geoprobe or similar drilling rig.   

2.2.2 Analytical Methods Requirements 

Test America  in Earth City, Missouri will be used  for  radiochemical analysis of  the soil 

samples.  All samples shall be analyzed for 3H and 14C.   Both 3H and 14C analysis will be 

performed by oxidation of the sample to vaporize and capture volatile 3H and 14C.  Both 

the volatile and non‐volatile samples will be analyzed using a liquid scintillation counter. 

The Test America analytical methods are LCS and EERF C‐01‐1, respectively.    

2.2.3 Instrument/Equipment Testing, Inspection, Maintenance 

Instrumentation and Equipment shall be used in accordance with DDES procedures and 

policies.    All  instrumentation  shall  be  calibrated  in  accordance  with  manufacturer’s 

instruction or by a subcontracted laboratory calibration procedure.  

2.2.4 Instrument Calibration Frequency 

Calibration  checks  of  laboratory  counting  equipment  and  field  instruments  shall  be 

performed  per  manufacturers  or  NIST  specifications  and  periodicities.    Some  field 

instruments  do  not  require  periodic  calibration;  these will  be marked  as  such.   NIST 

traceable sources shall be used where applicable.   Data sheets of calibration checks of 

fixed laboratory counting equipment will be maintained for both source and background 

during the course of the project to evaluate trends in counting data.  

When field instruments are in use, daily response checks using radioactive sources with 

similar  energies  shall  be  used  to  verify  the  functionality  of  field  instruments.  

Background readings will be taken as part of the daily response check.  

When  instruments  and  equipment  are  found  out  of  calibration  or  not  functioning  as 

expected, evaluations shall be made to assess the validity of the data obtained since the 

Page 12: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

9  

last performance test.   This evaluation shall be documented and  if required, processed 

as a nonconforming condition.  

The following documentation shall be maintained: 

Calibration Procedures  

Calibration Certificates 

Instrument and Equipment Inventory 

Nonconformance and Corrective Action Reports 

2.2.5 Data Acquisition Requirements (Non‐Direct Measurements) 

The data collection process will be defined, controlled, verified, and documented.   The 

following activities shall be addressed in the applicable final status survey procedures: 

Scanning and direct measurements 

Field sampling methods 

Sample handling and custody 

Analytical operations for bench top laboratory equipment 

Procedures  shall  be  reviewed  and  approved.    Procedures  shall  include,  but  are  not 

limited to the following: 

A design which assures data is traceable to the survey and analytical procedures, 

performance  standards,  data  collectors,  analysts  and  measuring  and  test 

equipment. 

Noting deviations  from planned data‐collection operations on the survey  forms 

or in field logbooks. 

2.3 Data Validation and Usability 

2.3.1 Data Review, Validation, and Verification Requirements 

Laboratory analysis shall be evaluated as follows: 

External  analytical  laboratories  will  be  required  to  provide  their  own  data 

validation package for review.  As appropriate, this package may include gamma 

spectrum  identification  information  such  as  calibration  and peak  identification 

measurements, isotopic quantification calculations and, if radiochemical analysis 

is used, percent sample recovery. 

 

The Project Manager will review the sample data to ensure chain of custody has 

been  preserved,  all  samples  taken  having  corresponding  sample  results 

provided,  limits of detection are at or below criteria specified  in the D&D Plan, 

Page 13: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

10  

peak  identification  is  correct  (i.e.  the  radionuclide  identified  is associated with 

the  energy  line  in  the  spectrum),  and  calculations  for  peak  quantification  are 

accurate.  

Field data shall be reviewed to ensure that: 

All DQOs are met as defined in the D&D Plan and Soil Sampling Plan 

Forms are accurate and complete and the type of survey has correctly been 

assigned to the survey unit. 

The Minimum Detectable Concentration (MDC) for measurements meets the 

criteria specified in the D&D Plan and Soil Sampling Plan 

Instrumentation  calibrations  and  functional  checks  have  been  performed 

accurately and at the specified frequency. 

2.3.2 Data Analysis 

The statistical guidance contained in the Soil Sampling Plan will be used to determine if 

additional surveys or sample measurements are needed. 

Quality Control  (QC) measurements,  samples,  and direct measurements  are  technical 

activities performed  to measure  the  residual  radioactive  contamination  from  licensed 

activities.   The measurement  results will be compared  to  the criteria  listed  in  the Soil 

Sampling Plan. 

   

Page 14: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

11  

3.0 Field Sampling Plan 

3.1 Sampling Objectives 

This soil sampling plan has been designed to both complete the site soils characterization.  

During  the characterization phase of  the  sampling  the goal  is  to  fill  in  the existing data 

gaps and bound  the areas of contamination.   The data will be  imported  into GIS based 

mapping software to allow for easy  identification during remediation or future sampling 

campaigns.   

3.2 Sampling and On‐Site Environmental Measurement Procedures 

Subsurface and surface soil sampling shall be conducted using hand augers, a Geoprobe 

or equivalent drilling equipment.  Surface soil samples may be collected by using manual 

or hand operated devices when  access  to  sampling  locations with  a Geoprobe may be 

impeded due to overgrowth of vegetation.   

3.2.1 Surface Soil Sampling 

Surface soils are classified as soils between ground surface and 6  inches below ground 

surface.   As  these  samples  are  obtained,  they will  be  homogenized  in  stainless  steel 

mixing bowls.   

3.2.2 Subsurface Soil Sampling 

Subsurface samples are classified as those samples that are below six inches of ground 

surface.  These samples shall be obtained using a Geoprobe or similar using push tubes, 

split spoons, etc.  Subsurface soil samples will be collected from 6 inches below ground 

surface  to 1 meter.   Sample  intervals will  continue  in 1 meter  intervals based on  the 

designated boring depth defined  in the soil sampling plan.   Each sampling  interval will 

be homogenized in stainless steel mixing bowls.      

3.2.3 Soil Sampling Procedure 

The soil sampling will be performed as follows: 

Sampling personnel will don a new pair of disposable gloves immediately before 

collecting soil samples at each location; 

A hand‐auger or push probe will be used  to  collect  soil at accessible  locations 

from 0” to 6” below ground surface; 

If  the  hand  auger  or  push  probe  is  unable  to  access  the  sampling  location  a 

Geoprobe will be used to collect soil samples;  

A  minimum  of  500  grams  of  material  will  be  collected  from  each  sampling 

location before homogenization.  In the case of deep sample locations, multiple 

Page 15: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

12  

samples will  be  collected  in  proximity  to  each  other  to  obtain  the  necessary 

sample volume; 

Homogenized soil will be placed into sample containers; 

A  completed  sample  label will  be  affixed  to  each  sample  container  and  clear 

packing tape used to secure the sample label to the container.  Note: It may be 

practical to write the applicable information directly on the containers; 

A custody seal will be affixed over the lid of the sample container; 

The sample number, date, time and description of the sample will be recorded 

on the chain‐of‐custody (COC) record and in the field logbook.  All entries will be 

written in permanent black ink; 

Each  sample will  be  numbered,  labeled  and  packaged  in  accordance with  the 

Sample Number and Sampling Packaging & Shipment sections; 

Field documentation, including field logbooks and COC records, will be filled out 

in accordance to the Field Records, Sample and Document Control; 

The  hand  auger,  push  probe  and  Geoprobe  shall  be  decontaminated  in 

accordance to the decontamination procedure. 

3.3.4  Sample Identification 

    Each sample will be identified as follows: 

    WW:  Up to 2‐character designation of the survey unit (for example, “29”) 

    YYY:  3‐character designation of the sample number (for example, “002”) 

    ZZZZ:  1‐character designation of the sample depth (for example, “3”) 

For example, in the sample identification number 29‐002‐3, “29” represents the survey 

unit, sample, “002” represents the sample collected at location 002, “3” represents the 

depth  in  meters  of  which  the  sample  was  obtained.    The  sample  number  will  be 

recorded in the field logbook, on the labels or containers and chain‐of‐custody record at 

the  time  of  sample  collection.    A  complete  description  of  the  sample  and  sampling 

conditions will be recorded in the field logbook and referenced using the unique sample 

identification number. 

3.2.4 Sample Labeling 

Sample labels are necessary to prevent misidentification of samples.  Sample labels will 

be  filled out  in permanent  ink and affixed to sample containers at the  time of sample 

collection.  Each sample container will be labeled with the following, at a minimum. 

Sample identification number 

Page 16: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

13  

Sample collection date (month/day/year) 

Time of collection (24‐hour clock) 

Samplers initials 

3.2.5 Sample Packaging and Shipment 

Sample packaging and shipment procedures for this project will be  in accordance with 

Department  of  Transportation  (DOT)  and  International Air  Transportation Association 

(IATA)  procedures  as  applicable  for  packaging  and  shipping  of  samples.    Samples  for 

radiological will be packaged  in an  insulated  cooler with  sufficient packing material  if 

samples are transported by a commercial carrier.  

3.2.6 Sample Handling and Mixing 

Precautions will be taken to prevent sample contamination. Clean gloves, sampling and 

mixing equipment will be used for each sample taken and will be decontaminated prior 

to  subsequent use.   One member of  the  sampling  team will be  responsible  for  taking 

field notes, filling out labels, COC’s, etc., while other members of the team shall obtain 

soil samples.   Collection activities will take place from the  least suspect contamination 

locations  to  the most suspect contamination  locations  to prevent cross contamination 

between sampling locations.  A minimum of 500 grams of soil shall be collected at each 

sampling location.   

After collection, all soil samples shall be mixed thoroughly to ensure sample uniformity.  

As  the  required  volume  of  soil  is  collected  it will  be  transferred  into  stainless  steel 

mixing bowls to be homogenized using stainless steel mixing spoons.  Once the soil has 

been properly mixed, samples will be removed and placed  into  the sample containers 

for analysis.   Mixing  in the bowls will consist of breaking down any clumps of material 

with  stainless  steel  spoons  and  stirring  in  a  circular  fashion,  reversing  direction  and 

occasionally  turning  the  material  over  from  the  bottom  of  the  bowl  to  the  top  to 

prevent  settling of  the  finer materials.   Any  rocks or debris will be  removed  from  the 

sample.   After mixing  is  complete,  the  soil will  be  divided  into  two  sample  sets  and 

placed into sample containers.   

3.2.7 Decontamination Procedure 

Decontamination of non‐disposable sampling equipment will be performed to prevent 

introduction of extraneous material  into  samples and  to prevent  cross  contamination 

between samples.  This cleaning process will be done in a series of wash bins to assure 

that contamination  is not spread and enhance the probability of being able to release 

the equipment from the site. 

Page 17: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

14  

The  following  steps  will  be  utilized  for  general  decontamination  of  non‐disposable 

sampling equipment: 

Clean  with  appropriate  non‐phosphorus  decontamination  solution  to  remove 

gross contamination from the equipment within a wash bin. 

Rinse and perform a 2nd cleaning in the 2nd wash bin. 

Rinse and wipe equipment using a water from a clean water wash bin.    

Final wipe and cleaning with a dry clean cloth to remove remaining solution and 

contamination from the equipment. 

Radiological  screening  of  equipment  to  verify  effectiveness  of  the 

decontamination for equipment that is to be taken off site at the completion of 

work activities.   This process will be completed using hand held survey meters 

and wipes that will be analyzed using a liquid scintillation counter.  

3.3 Field Records, Sample and Document Control 

In order to maintain the integrity and traceability of samples, all information pertinent to field 

sampling will be recorded  in a field  logbook.   All samples will be properly  labeled and custody 

sealed  prior  to  being  transported  to  the  laboratory.    All  samples will  be  accompanied  by  a 

completed COC.  All documentation will be recorded in a bound field logbook with permanent 

ink.  

3.4 Chain of Custody 

To  establish  the  documentation  necessary  to  trace  sample  possession  from  the  time  of 

collection  through  analysis  and  disposal,  a COC  record will  be  completely  filled out  and will 

accompany  every  sample  obtained.    Samples will  be  delivered  to  the  laboratory  as  soon  as 

practical.  At a minimum, the following items will be on the COC record: 

Project name 

Sample ID 

Sampler Name 

Sampler Signature 

Date of sample collection 

Sample matrix 

Sample location codes 

Number of sample containers 

Comments 

Relinquish signature 

Laboratory representative signature 

Date of custody transfer 

Page 18: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

15  

3.5 Custody Seals 

Sample custody seals are used to detect unauthorized tampering of samples from the time of 

sample  collection  to  the  time of analysis. The applicable  seals will be  signed or  initialed and 

dated  by  the  sampler.    The  seals  will  be  placed  on  the  sample  containers  and  shipping 

containers in such a way that they must be broken in order to open the containers.  Seals will 

be affixed to containers before the samples leave the custody of the sampling personnel. 

3.6 Field Logbook 

A  permanently  bound  field  logbook with  consecutively  numbered  pages,  used  for  sampling 

activity only, will be assigned to this project.  All entries will be recorded in permanent ink.  At 

the end of each work day, the  logbook pages will be signed by the responsible party and any 

unused portion of the page will be crossed out, signed and dated.  If it is necessary to transfer 

the logbook to another person, the person relinquishing the logbook shall sign and date the last 

page used, and the person receiving the logbook shall sign and date the next page to be used.  

At a minimum, the logbook will contain the following information: 

Project name and site location 

Date and Time 

Personnel in attendance 

General weather information 

Work performed 

Field observations 

Sampling  performed,  including  specifics  such  as  location,  type  of  sample,  type  of 

analyses, and sample identification numbers 

Problems encountered and corrective action taken 

Verbal or written instructions  

Any other events that may affect the samples 

3.7 Document Corrections 

Changes or corrections on any project document will be made by crossing out  the erroneous 

item with a single  line and  initialing (by the person performing the correction) and dating the 

correction.   The original  item, although erroneous, must remain  legible beneath the cross‐out 

line.  The new information should be written clearly above the crossed‐out item.  

Page 19: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

16  

3.8 Management of Investigation‐Derived Waste 

It  is  anticipated  that  Investigation‐Derived  Waste  (IDW)  will  be  generated  during  the 

characterization and final status survey soil sampling events. Anticipated waste materials that 

will be generated as part of the soil sampling scopes include: 

Well development and purge water 

Waste soil, sediment and water 

Used personal protective equipment  

Decontamination liquids 

Used sampling equipment 

Paper towels  

Sampling bottles 

All wash water from the cleaning of soil samples shall be collected into 55‐gallon polyethylene 

drums  and  held  on  site.    55‐gallon  steel  drums  shall  be  used  to  collect  any  dry  wastes 

associated with this scope of work.   Once the sampling event  is complete, the drum(s) will be 

analyzed for radiological contamination and waste profiling.  IDW does not include wastes that 

are  generated  from  the  displacement  or  removal  of  environmental  media  as  a  result  of 

remediation activities.    

Page 20: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

17  

4.0 Conclusions  

The Phase 4 Soil Sampling Plan has been designed to fill the existing data gaps  in the soils data 

previously obtained and evaluate the area of concern south of the former building footprint.  The 

results of the Phase 4 sampling will be used to help calculate site‐specific DCGLs and help in the 

development of a ground water monitoring strategy.   

   

Page 21: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

18  

5.0 References 

  USEPA Soil Screening Guidance User’s Guide, Second Edition 9355.4‐23 (July 1996). 

USEPA Using the Triad Apporach to Streamline Brownfields Site Cleanup (June 2003). 

USEPA Guidance for the Data Quality Objectives Process EPA/240/B‐06/001 (February 1996). 

  NUREG 1505 A Nonparametric Statistical Methodolgy for the Analysis of Final Status 

Decommissioning Surveys. (1995). 

NUREG 1506, Measurement Methods for Radiological Surveys in Support of New 

Decommissioning Criteria. (1995). 

NUREG 1507, Minimum Detectable Concentrations with Typical Radiation Survey Instruments 

for Various Contaminants and Field Conditions. (1997). 

NUREG 1575, Multi‐Agency Radiation Survey and Site Investigation Manual (MARSSIM), 

Revision 2. (2001). 

NUREG 1727, NMSS Decommissioning Standard Review Plan, Final. (2000). 

NUREG 1757, Vol. 2. Consolidated NMSS Decommissioning Guidance, Final Report. (2003). 

 

 

Page 22: 4 Soil Sampling and Analysis Plan Site

 

Phase 4‐ Soil Sampling PlanSigma‐Aldrich Fort Mims SiteUS NRC License: 24‐16276‐01

 

A‐1  

Attachment A:  

Soil Sampling Maps 

Page 23: 4 Soil Sampling and Analysis Plan Site

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

29-004Depth 0.15 m C-14 38

29-003Depth 0.15 m C-14 37

28-005Depth 0.15 m C-14 34

28-019Depth 0.15 m C-14 30

28-041Depth 0.15 m C-14 11

29-019Depth 0.15 m C-14 162

28-010Depth 0.15 m C-14 4.2

28-025Depth 0.15 m C-14 1.1

29-014Depth 0.15 m C-14 43.7

29-006Depth 0.15 m C-14 28.8

28-006Depth 0.15 m C-14 35.5 28-007

Depth 0.15 m C-14 15.3 28-008

Depth 0.15 m C-14 23.8

28-009Depth 0.15 m C-14 23.7

29-039Depth 0.15 m C-14 30.2

29-007Depth 0.15 m C-14 29.7

29-005Depth 0.15 m C-14 49.3

29-002Depth 0.15 m C-14 41.9

29-001Depth 0.15 m C-14 34.7

29-008Depth 0.15 m C-14 27.3

29-009Depth 0.15 m C-14 27.8

29-017Depth 0.15 m C-14 48.4

29-018Depth 0.15 m C-14 57.4

29-045Depth 0.15 m C-14 1290

29-029Depth 0.15 m C-14 15.9

29-025Depth 0.15 m C-14 49.6

29-028Depth 0.15 m C-14 40.3

29-033Depth 0.15 m C-14 25.1

29-034Depth 0.15 m C-14 10.2

29-035Depth 0.15 m C-14 27.5

28-001Depth 0.15 m C-14 0.83

28-011Depth 0.15 m C-14 11.2

28-043Depth 0.15 m C-14 2.01 28-042

Depth 0.15 m C-14 4.81

28-044Depth 0.15 m C-14 0.68 28-045

Depth 0.15 m C-14 5.05

28-004Depth 0.15 m C-14 23.2

28-023Depth 0.15 m C-14 8.92

28-022Depth 0.15 m C-14 26.7

28-021Depth 0.15 m C-14 8.08

28-020Depth 0.15 m C-14 16.9

28-018Depth 0.15 m C-14 25.5

28-016Depth 0.15 m C-14 13.9

28-015Depth 0.15 m C-14 12.6

28-014Depth 0.15 m C-14 10.5

28-013Depth 0.15 m C-14 5.14

28-012Depth 0.15 m C-14 3.97

28-029Depth 0.15 m C-14 1.07

28-030Depth 0.15 m C-14 5.56

28-031Depth 0.15 m C-14 15.7

28-032Depth 0.15 m C-14 29.3

28-033Depth 0.15 m C-14 31.3

28-034Depth 0.15 m C-14 8.69

28-035Depth 0.15 m C-14 2.29

28-036Depth 0.15 m C-14 1.95

28-037Depth 0.15 m C-14 6.22

28-038Depth 0.15 m C-14 1.64

28-039Depth 0.15 m C-14 10.2

28-040Depth 0.15 m C-14 10.8

28-059Depth 0.15 m C-14 19.5

28-058Depth 0.15 m C-14 3.62

28-057Depth 0.15 m C-14 6.72

28-056Depth 0.15 m C-14 4.96

28-055Depth 0.15 m C-14 4.28

28-054Depth 0.15 m C-14 2.62

28-053Depth 0.15 m C-14 2.62

28-052Depth 0.15 m C-14 6.55

28-051Depth 0.15 m C-14 3.79

28-050Depth 0.15 m C-14 7.92

28-049Depth 0.15 m C-14 3.65

28-048Depth 0.15 m C-14 4.22

28-047Depth 0.15 m C-14 42.5

28-046Depth 0.15 m C-14 9.36

28-027Depth 0.15 m C-14 1.065

28-026Depth 0.15 m C-14 0.795

28-024Depth 0.15 m C-14 0.945

28-017Depth 0.15 m C-14 0.995

28-028Depth 0.15 m C-14 0.915

28-060Depth 0.15 m C-14 0.925

ST-009Depth 0.15 m C-14 136Depth 1 m C-14 43.8

29-016Depth 0.15 m C-14 109Depth 1 m C-14 0.66

ST-008Depth 0.15 m C-14 22.9Depth 1 m C-14 9.54

29-048Depth 0.15 m C-14 71.8Depth 1 m C-14 96.9

29-038Depth 0.15 m C-14 95.4Depth 1 m C-14 3.01

29-013Depth 0.15 m C-14 63.7Depth 1 m C-14 4.38

29-012Depth 0.15 m C-14 104Depth 1 m C-14 0.755

29-010Depth 0.15 m C-14 93.8Depth 1 m C-14 3.55

29-011Depth 0.15 m C-14 85.8Depth 1 m C-14 17.2

29-021Depth 0.15 m C-14 65.1Depth 1 m C-14 3.86

29-026Depth 0.15 m C-14 95.8Depth 1 m C-14 9.71

29-027Depth 0.15 m C-14 99.2Depth 1 m C-14 25.2

29-031Depth 0.15 m C-14 96.1Depth 1 m C-14 6.31

ST-010Depth 0.15 m C-14 21.1Depth 1 m C-14 0.735

29-020Depth 0.15 m C-14 59.9Depth 1 m C-14 0.725

29-032Depth 0.15 m C-14 81.4Depth 1 m C-14 0.795

29-041Depth 0.15 m C-14 0.825Depth 1 m C-14 0.78

29-051Depth 0.15 m C-14 95Depth 1 m C-14 145Depth 2 m C-14 74.3

29-061Depth 0.15 m C-14 483Depth 1 m C-14 128Depth 2 m C-14 398

29-049Depth 0.15 m C-14 38.4Depth 1 m C-14 978Depth 2 m C-14 189

29-040Depth 0.15 m C-14 159Depth 1 m C-14 120Depth 2 m C-14 27.5

29-056Depth 0.15 m C-14 34Depth 1 m C-14 0.78Depth 2 m C-14 3.35

29-015Depth 0.15 m C-14 305Depth 1 m C-14 4.14Depth 2 m C-14 175

29-047Depth 0.15 m C-14 12.1Depth 1 m C-14 422Depth 2 m C-14 30.8

29-050Depth 0.15 m C-14 122Depth 1 m C-14 5.35Depth 2 m C-14 14.6

29-058Depth 0.15 m C-14 12.7Depth 1 m C-14 3.7Depth 2 m C-14 2.83

29-068Depth 0.15 m C-14 5.3Depth 1 m C-14 2.7Depth 2 m C-14 0.735

29-055Depth 0.15 m C-14 108Depth 1 m C-14 3.47Depth 2 m C-14 16.6

29-046Depth 0.15 m C-14 52.3Depth 1 m C-14 11.8Depth 2 m C-14 1.8

29-022Depth 0.15 m C-14 200Depth 1 m C-14 59.9Depth 2 m C-14 6.07

29-030Depth 0.15 m C-14 257Depth 1 m C-14 9.74Depth 2 m C-14 6.78

29-023Depth 0.15 m C-14 163Depth 1 m C-14 38.2Depth 2 m C-14 8.75

29-024Depth 0.15 m C-14 125Depth 1 m C-14 1.92Depth 2 m C-14 1.85

29-053Depth 0.15 m C-14 25.3Depth 1 m C-14 5.43Depth 2 m C-14 12.6

29-059Depth 0.15 m C-14 2.14Depth 1 m C-14 10.5Depth 2 m C-14 4.58

29-060Depth 0.15 m C-14 3.95Depth 1 m C-14 0.76Depth 2 m C-14 2.53

29-057Depth 0.15 m C-14 24.9Depth 1 m C-14 0.89Depth 2 m C-14 11.1

29-054Depth 0.15 m C-14 35.2Depth 1 m C-14 6.47Depth 2 m C-14 14.5

29-043Depth 0.15 m C-14 7.61Depth 1 m C-14 0.785Depth 2 m C-14 5.8

29-044Depth 0.15 m C-14 43.2Depth 1 m C-14 31.7Depth 2 m C-14 12.4

29-042Depth 0.15 m C-14 17.5Depth 1 m C-14 8.39Depth 2 m C-14 2.32

29-064Depth 0.15 m C-14 0.72Depth 1 m C-14 0.685Depth 2 m C-14 0.71

29-063Depth 0.15 m C-14 3.32Depth 1 m C-14 0.885Depth 2 m C-14 0.81 29-065

Depth 0.15 m C-14 5.03Depth 1 m C-14 0.745Depth 2 m C-14 0.735

28-003Depth 0.15 m C-14 35.7

28-002Depth 0.15 m C-14 11.4

29-036Depth 0.15 m C-14 62.8Depth 1 m C-14 0.795

29-037Depth 0.15 m C-14 191Depth 1 m C-14 2.94Depth 2 m C-14 2.44

29-052Depth 0.15 m C-14 11.5Depth 1 m C-14 18.6Depth 2 m C-14 5.77

29-066Depth 0.15 m C-14 0.74Depth 1 m C-14 0.785Depth 2 m C-14 15.4

29-067Depth 0.15 m C-14 12.3Depth 1 m C-14 3.81Depth 2 m C-14 0.83529-062

Depth 0.15 m C-14 3.3Depth 1 m C-14 5.35Depth 2 m C-14 3.71

±X:\

DDES

\SiteM

ap_H

3_C1

4.mxd

0 10 20 30 40 50Feet

Sigman Aldrich Soil ResultsC-14

Sigman Aldrich Fort Mims Facility11542 Fort Mims drive

Maryland Heights, MissouriM. NortonREQUESTED BY:

DATE: 3/12/2015MA-15-028-02PROJECT NO:

M. SenneDRAWN BY:

Legend!? Soil Sample Location

FMF-28FMF-29

Googe Earth Pro Imagery: 10/21/2014

Note:- All Sample Units are in pCi/g

Page 24: 4 Soil Sampling and Analysis Plan Site

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

28-008Depth 0.15 m H-3 21

29-003Depth 0.15 m H-3 11

29-009Depth 0.15 m H-3 1.7

29-034Depth 0.15 m H-3 5.9

28-010Depth 0.15 m H-3 5.7

28-044Depth 0.15 m H-3 6.7

28-025Depth 0.15 m H-3 3.1

29-014Depth 0.15 m H-3 2.92

29-006Depth 0.15 m H-3 3.32

28-027Depth 0.15 m H-3 2.71

28-006Depth 0.15 m H-3 12.3 28-007

Depth 0.15 m H-3 18.6 28-009

Depth 0.15 m H-3 16.9

29-039Depth 0.15 m H-3 7.35

29-007Depth 0.15 m H-3 9.57

29-005Depth 0.15 m H-3 8.74

29-004Depth 0.15 m H-3 9.55

29-002Depth 0.15 m H-3 6.82

29-001Depth 0.15 m H-3 2.78

29-008Depth 0.15 m H-3 5.34

29-017Depth 0.15 m H-3 3.42

29-018Depth 0.15 m H-3 9.06

29-019Depth 0.15 m H-3 29.4

29-045Depth 0.15 m H-3 10.5

29-029Depth 0.15 m H-3 2.14

29-025Depth 0.15 m H-3 2.62

29-028Depth 0.15 m H-3 5.24

29-035Depth 0.15 m H-3 3.13

28-005Depth 0.15 m H-3 3.45

28-001Depth 0.15 m H-3 8.88

28-011Depth 0.15 m H-3 13.6

28-043Depth 0.15 m H-3 6.95 28-042

Depth 0.15 m H-3 14.2

28-045Depth 0.15 m H-3 9.92

28-004Depth 0.15 m H-3 6.81

28-003Depth 0.15 m H-3 19.2

28-002Depth 0.15 m H-3 17.9

28-026Depth 0.15 m H-3 2.76

28-024Depth 0.15 m H-3 2.05

28-023Depth 0.15 m H-3 5.52

28-022Depth 0.15 m H-3 7.27

28-021Depth 0.15 m H-3 9.26

28-020Depth 0.15 m H-3 21.8

28-019Depth 0.15 m H-3 15.8

28-018Depth 0.15 m H-3 8.25

28-017Depth 0.15 m H-3 4.72

28-016Depth 0.15 m H-3 5.39

28-015Depth 0.15 m H-3 14.9

28-014Depth 0.15 m H-3 11.2

28-013Depth 0.15 m H-3 6.52

28-012Depth 0.15 m H-3 4.86

28-028Depth 0.15 m H-3 4.18

28-029Depth 0.15 m H-3 2.23

28-030Depth 0.15 m H-3 3.05

28-031Depth 0.15 m H-3 3.37

28-032Depth 0.15 m H-3 4.57

28-033Depth 0.15 m H-3 4.56

28-034Depth 0.15 m H-3 6.47

28-035Depth 0.15 m H-3 4.97

28-036Depth 0.15 m H-3 3.41

28-037Depth 0.15 m H-3 4.41

28-038Depth 0.15 m H-3 1.65

28-039Depth 0.15 m H-3 8.24

28-040Depth 0.15 m H-3 6.31

28-041Depth 0.15 m H-3 8.11

28-060Depth 0.15 m H-3 6.44

28-059Depth 0.15 m H-3 4.03

28-058Depth 0.15 m H-3 6.16

28-057Depth 0.15 m H-3 15.4

28-056Depth 0.15 m H-3 15.9

28-055Depth 0.15 m H-3 13.1

28-054Depth 0.15 m H-3 3.54

28-053Depth 0.15 m H-3 9.56

28-052Depth 0.15 m H-3 4.63

28-051Depth 0.15 m H-3 3.88

28-050Depth 0.15 m H-3 7.98

28-049Depth 0.15 m H-3 10.7

28-048Depth 0.15 m H-3 10.2

28-047Depth 0.15 m H-3 28.2

28-046Depth 0.15 m H-3 11.1

29-033Depth 0.15 m H-3 0.745

29-011Depth 0.15 m H-3 13Depth 1 m H-3 2

29-010Depth 0.15 m H-3 14Depth 1 m H-3 2.39

ST-008Depth 0.15 m H-3 3.98Depth 1 m H-3 0.9

29-048Depth 0.15 m H-3 2.27Depth 1 m H-3 3.6

29-016Depth 0.15 m H-3 5.6Depth 1 m H-3 1.86

29-038Depth 0.15 m H-3 18.5Depth 1 m H-3 2.33

29-012Depth 0.15 m H-3 9.88Depth 1 m H-3 4.19

29-020Depth 0.15 m H-3 5.83Depth 1 m H-3 0.51

29-021Depth 0.15 m H-3 4.13Depth 1 m H-3 1.75

29-026Depth 0.15 m H-3 22.3Depth 1 m H-3 1.54

29-027Depth 0.15 m H-3 8.88Depth 1 m H-3 2.21

29-032Depth 0.15 m H-3 5.28Depth 1 m H-3 0.56

29-031Depth 0.15 m H-3 4.46Depth 1 m H-3 1.99

29-041Depth 0.15 m H-3 0.58Depth 1 m H-3 2.48

29-036Depth 0.15 m H-3 5.65Depth 1 m H-3 0.56

ST-009Depth 0.15 m H-3 0.945Depth 1 m H-3 2.41

29-013Depth 0.15 m H-3 17.5Depth 1 m H-3 0.555

ST-010Depth 0.15 m H-3 1.015Depth 1 m H-3 1.005

29-047Depth 0.15 m H-3 0.595Depth 1 m H-3 6Depth 2 m H-3 6.92

29-066Depth 0.15 m H-3 1Depth 1 m H-3 1.03Depth 2 m H-3 0.895

29-049Depth 0.15 m H-3 13.1Depth 1 m H-3 11.6Depth 2 m H-3 7.9

29-040Depth 0.15 m H-3 42.5Depth 1 m H-3 3.32Depth 2 m H-3 3.61

29-059Depth 0.15 m H-3 1.07Depth 1 m H-3 0.9Depth 2 m H-3 0.965

29-061Depth 0.15 m H-3 6.83Depth 1 m H-3 2.88Depth 2 m H-3 7.39

29-057Depth 0.15 m H-3 1.09Depth 1 m H-3 1.12Depth 2 m H-3 1.08

29-015Depth 0.15 m H-3 7.91Depth 1 m H-3 1.61Depth 2 m H-3 3.52

29-043Depth 0.15 m H-3 0.59Depth 1 m H-3 0.55Depth 2 m H-3 0.52

29-030Depth 0.15 m H-3 4.01Depth 1 m H-3 1.74Depth 2 m H-3 1.56

29-023Depth 0.15 m H-3 7.02Depth 1 m H-3 2.23Depth 2 m H-3 0.52

29-042Depth 0.15 m H-3 3.13Depth 1 m H-3 1.71Depth 2 m H-3 1.64

29-051Depth 0.15 m H-3 4.42Depth 1 m H-3 4.48Depth 2 m H-3 1.115

29-067Depth 0.15 m H-3 2.21Depth 1 m H-3 3.12Depth 2 m H-3 1.095

29-068Depth 0.15 m H-3 0.925Depth 1 m H-3 3.96Depth 2 m H-3 0.96

29-060Depth 0.15 m H-3 3.21Depth 1 m H-3 0.96Depth 2 m H-3 0.905

29-056Depth 0.15 m H-3 1.05Depth 1 m H-3 0.985Depth 2 m H-3 0.84

29-055Depth 0.15 m H-3 3.22Depth 1 m H-3 0.985Depth 2 m H-3 0.94

29-022Depth 0.15 m H-3 6.88Depth 1 m H-3 3.06Depth 2 m H-3 0.438

29-050Depth 0.15 m H-3 0.575Depth 1 m H-3 0.59Depth 2 m H-3 0.585

29-064Depth 0.15 m H-3 0.905Depth 1 m H-3 0.865Depth 2 m H-3 1.99

29-063Depth 0.15 m H-3 0.885Depth 1 m H-3 1.115Depth 2 m H-3 1.02

29-053Depth 0.15 m H-3 1.09Depth 1 m H-3 1.115Depth 2 m H-3 0.935

29-052Depth 0.15 m H-3 1.045Depth 1 m H-3 1.02Depth 2 m H-3 1.045

29-058Depth 0.15 m H-3 0.86Depth 1 m H-3 0.945Depth 2 m H-3 1.005

29-065Depth 0.15 m H-3 0.915Depth 1 m H-3 0.935Depth 2 m H-3 0.93

29-054Depth 0.15 m H-3 1.005Depth 1 m H-3 0.98Depth 2 m H-3 0.845

29-024Depth 0.15 m H-3 6.58Depth 1 m H-3 0.473Depth 2 m H-3 0.535

29-037Depth 0.15 m H-3 10.6Depth 1 m H-3 1.72Depth 2 m H-3 0.4925

29-046Depth 0.15 m H-3 0.535Depth 1 m H-3 0.505Depth 2 m H-3 0.423

29-044Depth 0.15 m H-3 0.545Depth 1 m H-3 0.4195Depth 2 m H-3 0.477

29-062Depth 0.15 m H-3 0.83Depth 1 m H-3 1.08Depth 2 m H-3 0.9

±X:\

DDES

\SiteM

ap_H

3_C1

4.mxd

0 10 20 30 40 50Feet

Sigman Aldrich Soil ResultsH-3

Sigman Aldrich Fort Mims Facility11542 Fort Mims drive

Maryland Heights, MissouriM. NortonREQUESTED BY:

DATE: 3/12/2015MA-15-028-02PROJECT NO:

M. SenneDRAWN BY:

Legend!? Soil Sample Location

FMF-28FMF-29

Googe Earth Pro Imagery: 10/21/2014

Note:- All Sample Units are in pCi/g

Page 25: 4 Soil Sampling and Analysis Plan Site

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

!?

29-00429-003

28-00528-019

28-041

29-019

28-010

28-025

29-014

29-006

28-00628-007

28-008 28-009

29-039

29-007

29-005

29-00229-001

29-00829-009

29-01729-018

29-045

29-029

29-025

29-028

29-033

29-034 29-035

28-001

28-011

28-04328-042

28-04428-045

28-004

28-02328-022

28-02128-020

28-018

28-01628-015

28-01428-013

28-012

28-02928-030

28-03128-032

28-03328-034

28-03528-036

28-03728-038

28-03928-040

28-05928-058

28-05728-056

28-05528-054

28-05328-052

28-05128-050

28-04928-048

28-04728-046

28-027

28-026

28-024

28-017 28-028

28-060

ST-009

29-016

ST-008

29-048

29-038

29-01329-012

29-01029-011

29-021

29-026

29-027

29-031

ST-010

29-020

29-032

29-041

29-051

29-061

29-049

29-040

29-056

29-015

29-047

29-050

29-058

29-068

29-055

29-046

29-022

29-030

29-023

29-024

29-053

29-059

29-060

29-057

29-054

29-043

29-044

29-042

29-064

29-063

29-065

28-00328-002 29-036

29-037

29-052

29-066

29-067

29-062

29-73

29-8129-82

29-7429-75

29-76

29-7129-72

29-7730-78

29-7929-80

29-83 29-8430-85

30-9030-91

30-89

30-9230-93

30-9430-95

30-8730-88

30-86

30­9630-97

30-98

±X:\

DDES

\SiteM

ap_H

3_C1

4_Pr

opos

ed.m

xd

0 10 20 30 40 50Feet

Phase 4 Soil Sampling LocationsSigman Aldrich Fort Mims Facility

11542 Fort Mims driveMaryland Heights, Missouri

M. NortonREQUESTED BY:

DATE: 3/12/2015MA-15-028-02PROJECT NO:

M. SenneDRAWN BY:

Legend!? Existing Soil Sample Location

Proposed Soil Sample LocationFMF-28FMF-29

Googe Earth Pro Imagery: 10/21/2014

29-6929-70

29-99

29-10029-100