4 KSC Motor Integration
Transcript of 4 KSC Motor Integration
-
7/29/2019 4 KSC Motor Integration
1/37
ATK THIOKOL
286
Motor Integration Team
Presented by:
KSC MotorIntegration
-
7/29/2019 4 KSC Motor Integration
2/37
ATK THIOKOL
287
Motor Integration at KSC and CCAFS
-
7/29/2019 4 KSC Motor Integration
3/37
ATK THIOKOL
288
Russ Bakes
Integration ProgramManager
SteveSchmieder
IntegrationSub-systemManager
Paul Teehan
MSFC ResidentOffice
Ted Shaffner
KSC OperationsManager
Bruce Tams
Integration DesignEngineering Manager
Mike Evans
Quality Manager
Integration Leadership Team
-
7/29/2019 4 KSC Motor Integration
4/37
ATK THIOKOL
289
Interfaces
The integration teams function is to assure ATK and MSFCrequirements are incorporated into the motor processing at KSC
The hands on work, i.e., build up, stack, close out, integrate,
launch and disassemble the boosters is done by USA
Because we work with an integrated vehicle and operate in a
multi contractor environment our communication is with multipleelements
-
7/29/2019 4 KSC Motor Integration
5/37
ATK THIOKOL
290
Recovery
and PostflightEvaluation
Launch
SRB Stacking
KSC Operations
KSC Operations
CCAFS Operations
RSRM Processing
-
7/29/2019 4 KSC Motor Integration
6/37
ATK THIOKOL
291
Jay Jay
Siding
LMF
Segment
Onload
Port
Canaveral
Hangar AF and
Hangar N
VAB/ RPSF/
OSB Area
Pads
SuspectSiding
-
7/29/2019 4 KSC Motor Integration
7/37
ATK THIOKOL
292
SHUTTLELANDING
SRB RETRIEVALSHIP
HANGAR AF
RPSF
SRB STACKING
ET/SRBOPERATIONS
ETSTANDALONE
LCC
INTEGRATEDVEHICLE OPS/VAB
OffloadBuildup
HORIZONTALPAYLOAD INT
PAYLOAD FACILITIESHYPERGOLIC
FACILITY
ORBITER PROCESSING
FACILITY
Pad Ops
VERTICAL
PAYLOAD
INSTALLATION
Design Centers
Element Refurbishment and Manufacturing
Logistics and Shipping
Delivery
Offload and
Inspect
Aft Booster
Build
Field Joint Mate
Leak Test
Field Joint
Protection
System
S&A
SRB Integration
Launch
Recovery
Disassembly andAssessment
Shuttle Vehicle Processing Operations
-
7/29/2019 4 KSC Motor Integration
8/37
ATK THIOKOL
293
Delivery
Segments arrive at Jay Jaysiding via railcar
Cars are 200-ton railcars
with fiberglass covers
-
7/29/2019 4 KSC Motor Integration
9/37
ATK THIOKOL
294
Offload and Inspect
Segments and exit cones are rotated to vertical (flightorientation) in the rotation building at the Rotation, Processingand Surge Facility (RPSF)
-
7/29/2019 4 KSC Motor Integration
10/37
ATK THIOKOL
295
Aft Booster Build-up
Aft skirt mate Exit cone mate
Leak test
Backfill
Nozzle severance connection,
checkout, and close out GEI and heater power cable
installation and test
Stiffener ring installation andclose out
Froth-Pak Application Systems tunnel installation
and close out
Storage until ready to stack
-
7/29/2019 4 KSC Motor Integration
11/37
ATK THIOKOL
296
Aft Skirt Mate
The aft skirt (USA supplied) isplaced in the build up stand and
the segment is mated
177 pins are installed and secured
with a steel retainer strap
The joint is closed out with a pinband and cork
Cork
Pin Retainer Strap
Aft skit clevis
-
7/29/2019 4 KSC Motor Integration
12/37
ATK THIOKOL
297
Exit Cone Mate
Aft exit cone is assembled to theforward exit cone at KSC
(Joint No.1)
Phenolic mating surfaces are
primed with DC1220 primer
prior to assembly
Primary and secondary O-rings
are installed
Exit cone is raised on an
elevator and floated on an air
bearing for mating
The joint is bolted with 96fasteners
Leak test is performed at 83
and 30 psig with the Mass Flow
Meter prior to joint backfill
Backfill
O-rings
-
7/29/2019 4 KSC Motor Integration
13/37
ATK THIOKOL
298
Exit Cone Backfill
Joint gap is backfilled (injected) with RTV sealant Spatulas are used to support the tape and aid in a
deep fill of the joint
Backfill is part of thermal barrier system
Joint 1 is a static joint (opens less than 0.0005 in.)
Joint
Interface
Backfill
Nozzle
-
7/29/2019 4 KSC Motor Integration
14/37
ATK THIOKOL
299
Stiffener Ring Installation and Close-out
The function of the stiffenerrings is to prevent case
damage from splashdown due
to cavity collapse
Stiffener rings have no flight
function
Three sections are bolted to the
integral stub and joined
together by splice plates
RT-455 is used to protect
fasteners and the paintedhardware from heat loads
The foam ramp helps deflect
the water geyser at splashdown
3 Stiffener
Rings
Foam
RT-455
Ablative
Stiffener
Ring
-
7/29/2019 4 KSC Motor Integration
15/37
ATK THIOKOL
300
Systems Tunnel
The aft segment systems tunnel iscompleted at the RPSF up to the ETA
ring prior to transfer to storage
Cables are run and secured
Connections are checked
Covers are installed and closed out
Systems
Tunnel
Stiffener Ring
-
7/29/2019 4 KSC Motor Integration
16/37
ATK THIOKOL
301
Segment Storage
All segments remainvertical on their pallets
until they are transferred
to the VAB for stack
A KAMAG is used to pick
up and transport thepallet
Surges protect the
hardware from rain, wind,
etc.
Not climate controlled.
Segments have weather
proof covers on top
-
7/29/2019 4 KSC Motor Integration
17/37
ATK THIOKOL
302
SHUTTLELANDING
SRB RETRIEVALSHIP
HANGAR AF
RPSF
SRB STACKING
ET/SRBOPERATIONS
ETSTANDALONE
LCC
INTEGRATEDVEHICLE OPS/VAB
OffloadBuildup
HORIZONTALPAYLOAD INT
PAYLOAD FACILITIESHYPERGOLIC
FACILITY
ORBITER PROCESSINGFACILITY
Pad Ops
VERTICAL
PAYLOAD
INSTALLATION
Design Centers
Element Refurbishment and Manufacturing
Logistics and Shipping
Delivery
Offload and
Inspect
Aft Booster
Build
Field Joint Mate
Leak Test
Field Joint
Protection
System
S&A
SRB Integration
Launch
Recovery
Disassembly andAssessment
Shuttle Vehicle Processing Operations
-
7/29/2019 4 KSC Motor Integration
18/37
ATK THIOKOL
303
RSRM Field Joint Mate
Current joint mate process wasdeveloped through testingduring the RSRM redesignprogram
Joint assembly objective is toprevent tang/clevis flat-on-flatand protect the o-rings frombeing cut or damaged: capturefeature O-ring is mostsusceptible
Calculations are performedbased on case diameter data todetermine proper Field Joint
Assembly Fixture (FJAF)configuration for each joint mate
Interference Fit
Maintains O-ring
Squeeze and Restricts
Joint RotationClevis
Tang
-
7/29/2019 4 KSC Motor Integration
19/37
ATK THIOKOL
304
Joint Mate Preparations
Pressure Sensitive Adhesive(PSA) is applied to the
insulation interfaces
Metal parts are inspected and
greased
O-rings are installed
FJAF configured and
installed
Cases are measured to
determine the relative shapes
Requirement is for shapes to
be within +/-0.210 in. fornominal mate
Shape can be improved by
adjusting the 4 point beam
load distribution
Tang
Clevis
J-Joint
-
7/29/2019 4 KSC Motor Integration
20/37
ATK THIOKOL
305
RSRM Field Joint Mate
Crane lowering rate iscontrolled to 0.060 in./minute
maximum
Levelness and rate of
engagement are continually
monitored during segmentlowering
FJAF contact with the case is
monitored during maximum
engagement
Leak test of the joint and thevent port plug are the final
acceptance of a successful
joint mate
Field Joint Assembly
Fixture Acts to
Shoehorn the
Segments Together
Temposonics to Measure
Rate of Engagement,
Parallelism, and DistanceFrom Mate
-
7/29/2019 4 KSC Motor Integration
21/37
ATK THIOKOL
306
Field Joint Protection System (FJPS)
The purposes of the FJPS are: Maintain an optimal temperature for
O-ring tracking
Prevent environmental
contaminants such as rainwater
from entering the joint area
Final product is painted with white
Acrymax paint
Cork
Heater Retainer
Strap and ThermalBarrier
JointTemperature
Sensor
JointHeater
Pin RetainerBand
RT-455Ablative
RT-455Ablative
Cork
-
7/29/2019 4 KSC Motor Integration
22/37
ATK THIOKOL
307
Skirt Joint Protection System (JPS)
Forward and aft skirt JPS isprimarily to provide thermal
protection, weather protection and
to retain the pins
A flat steel strap is installed over the
pin heads
Cork is bonded with EA934 andpainted with Acrymax paint
A grease bead is applied to the
clevis/tang exterior interface of the
joint
GreaseBead
Steel Retainer
Strap
Cork
-
7/29/2019 4 KSC Motor Integration
23/37
ATK THIOKOL
308
S&A Installation
The ignition Safe and Arm (S&A)devices are installed after the
RSRM is stacked and the forward
skirt is installed
Fluorocarbon seals contained
within a steel retainer gasket are
placed between the S&A and theigniter adapter surface
Crushable preload measuring
washers are used to control bolt
preload
Leak test is performed with thebolts partially torqued to prevent
false positive due to a metal to
metal seal
Final torque and cable
connections are then performed
S&A
Gasket
S&A
-
7/29/2019 4 KSC Motor Integration
24/37
ATK THIOKOL
309
Vehicle Integration
SRB integration Joint heater and temperature sensor connections
Thrust Vector Control (TVC) actuator to nozzle connections
Chamber pressure and ignition S&A connections
Systems tunnel cable runs
Systems tunnel cove close outs
Extensive checkouts of ground and flight electrical systems
The tank is mated to the SRB
The orbiter is mated to the tank
The assembled vehicle is rolled to the pad
-
7/29/2019 4 KSC Motor Integration
25/37
ATK THIOKOL
310
SHUTTLELANDING
SRB RETRIEVALSHIP
HANGAR AF
RPSF
SRB STACKING
ET/SRBOPERATIONS
ETSTANDALONE
LCC
INTEGRATEDVEHICLE OPS/VAB
OffloadBuildup
HORIZONTALPAYLOAD INT
PAYLOAD FACILITIESHYPERGOLIC
FACILITY
ORBITER PROCESSINGFACILITY
Pad Ops
VERTICAL
PAYLOAD
INSTALLATION
Design Centers
Element Refurbishment and Manufacturing
Logistics and Shipping
Delivery
Offload and
Inspect
Aft Booster
Build
Field Joint Mate
Leak Test
Field Joint
Protection
System
S&A
SRB Integration
Launch
Recovery
Disassembly andAssessment
Shuttle Vehicle Processing Operations
-
7/29/2019 4 KSC Motor Integration
26/37
ATK THIOKOL
311
Launch
Launch countdown begins about 3days prior to launch
RSRM systems begin to activateapproximately 18 hours prior tolaunch S&A rotation test at Launch (L)-60
hours
The igniter heater is activated at L-18hours
Operational Pressure Transducers(OPTs) are powered up at L-9 hours
Joint heaters are powered up at L-8hours
OPTs are checked out at L-1.5 hours
The igniter heater is deactiviated andthe S&A armed at L-5 minutes
Main engine start is at L-6 sec
SRB ignition and hold-down post-firingat L-0
-
7/29/2019 4 KSC Motor Integration
27/37
ATK THIOKOL
312
SHUTTLELANDING
SRB RETRIEVALSHIP
HANGAR AF
RPSF
SRB STACKING
ET/SRBOPERATIONS
ETSTANDALONE
LCC
INTEGRATEDVEHICLE OPS/VAB
OffloadBuildup
HORIZONTAL
PAYLOAD INT
PAYLOAD FACILITIESHYPERGOLIC
FACILITY
ORBITER PROCESSINGFACILITY
Pad Ops
VERTICAL
PAYLOAD
INSTALLATION
Design Centers
Element Refurbishment and Manufacturing
Logistics and Shipping
Delivery
Offload and
Inspect
Aft Booster
Build
Field Joint Mate
Leak Test
Field Joint
Protection
System
S&A
SRB Integration
Launch
Recovery
Disassembly andAssessment
Shuttle Vehicle Processing Operations
-
7/29/2019 4 KSC Motor Integration
28/37
ATK THIOKOL
313
Recovery
Ships crew gatherparachutes and the frustum
Divers install the Diver
Operated Plug into the
nozzle
The DOP system pumpswater from the interior to get
the booster into log mode
Recovery ships tow the
SRBs back to Hangar AF
-
7/29/2019 4 KSC Motor Integration
29/37
ATK THIOKOL
314
Post Flight Disassembly and Assessment
SRBs are floated into awharf and lifted onto the
disassembly dolly with a
straddle lift
SRB and RSRM
components aredisassembled by USA
Assessments of the flown
hardware are performed
by ATK, USA SRB and
MSFC representatives
-
7/29/2019 4 KSC Motor Integration
30/37
ATK THIOKOL
315
RSRM Postfire Evaluation Process
Purpose of RSRM Postfire Evaluation
The objective of postfire evaluation (disassembly and assessment)
is to verify integrity of recovered RSRM hardware and identify any
anomalous conditions in a timely manner
Did the hardware perform as expected? What is it telling us?
Were engineering requirements violated, and if so how does this effectperformance?
Is the condition in family with past observations?
Does the condition affect subsequent launches or tests?
Impact on future launches is addressed in flight/test readiness review
(FRR/TRR) process
-
7/29/2019 4 KSC Motor Integration
31/37
ATK THIOKOL
316
RSRM Postfire Evaluation Process
Postfire Evaluation Requirements Postfire Hardware Evaluation System Operating Plan
Defines system requirements for:
Disassembling, evaluating, documenting, reporting, and databasing the
condition of postfired RSRM hardware
Identifying, reviewing, tracking, and resolving observed abnormal/anomalous
conditions or trends
Postfire Engineering Evaluation Plans
Defines requirements for:
Engineering evaluation, hardware observation limits (allowable and
reportable), and photo/video documentation
Approved by NASA MSFC
-
7/29/2019 4 KSC Motor Integration
32/37
ATK THIOKOL
317
RSRM Postfire Evaluation Process
Postflight Evaluation Process and Timeline Launch + 2-21 days, CCAFS Hangar AF (Florida)
Recovered solid rocket boosters initially assessed, including assessment for missing
external insulation
Forward and aft skirts, S&A devices, igniters, nozzles, and exit cones removed and
assessed
Case field joints demated and internal insulation assessed Launch + 8-14 days, ATK Thiokol M-66A Facility (Utah)
S&As disassembled and assessed
Launch + 15-30 days, VACCO vendor facility (California)
Arming-Monitor and Barrier-Booster disassembled and assessed
Launch + 12-18 days, ATK Thiokol Refurbishment Center (Utah)
Internal nozzle joints demated and assessed
Launch + 20-160 days, Thiokol Refurbishment Center (Utah)
Nozzle bondlines, nozzle liner char/erosion measurements, case and igniter insulation
measurements, and factory joints demated and assessed
-
7/29/2019 4 KSC Motor Integration
33/37
ATK THIOKOL
318
Barrier-Booster Housing
A041627a1
SAFETY AND ARMING DEVICE
Barrier-BoosterRotor Shaft Seals
Safing Pin
A-M Backfill Port
Visual Indicator
Window
A-M Switch Deck
Motor Field Windings
Motor Armature
A-M Electrical ConnectorGear Reduction (625:1)
Rotor(mechanical barrier)
Perforated PlateFoam Cushion
B-KNO3Granules
B-KNO3Pellets
SII
Safing Arm
Clutch Ass embly
Locking Shaft
EnvironmentalSeals
Booster Basket
Attach Bolt
PLI NestedWasher
Aft Exit Cone Assembly
Cowl Housing
Cowl
A038797aDDB
Vented PositiveStop Set Screw
FlexibleBoot Assembly
Cowl Insulation Segment
Nose InletAssembly
Throat Inlet AssemblyForward Exit Cone Assembly
Fixed HousingAssembly
Snubber Detail:
Ring, Segment,Retainer
Flex Bearing
Flex Bearing Protector
Vented Positive Stop Set Screw
Vented Positive Stop Set Screw
RSRM Postfire Evaluation Process
-
7/29/2019 4 KSC Motor Integration
34/37
ATK THIOKOL
319
RSRM Postfire Evaluation Process
Postfire Anomaly Record (PFAR) System Any observation that falls outside of established limits or is
unexpected is reported on a Squawk (Florida) or Preliminary PFAR
(Utah, California)
Each Squawk/Preliminary PFAR is presented to SRB/RSRM
Postflight Assessment Team (SPAT Board) for review
SPAT Board consists of NASA, senior contractor management, and
engineering
SPAT Board determines if violation should be elevated to PFAR which
requires corrective actions and further reviews
PFAR corrective actions worked by component teams
PFAR closure rationale approved by ATK Thiokol and MSFC
All PFARs presented in FRR/TRR process including impact and
rationale for upcoming flights/tests
-
7/29/2019 4 KSC Motor Integration
35/37
ATK THIOKOL
320
RSRM Postfire Evaluation Process
Postfire
HardwareEvaluationSystem
TWR-16899
Postfire
HardwareEvaluationSystem
TWR-16899
RSRM-XXSpecialIssues
RSRM-XXSpecialIssues
Hardware Disassembly
and Evaluation
Postflight
Observation
Records(PFORS)
Hardware Disassembly
and Evaluation
Postfire
Observation
Records(PFORS)
Squawk
(KSC)
Squawk
(KSC)
Preliminary
Postflight
Anomaly
Record
(Utah)
Preliminary
Postfire
Anomaly
Record
(Utah)
Postflight
Anomaly
Record
(PFAR)
Postfire
Anomaly
Record
(PFAR)
RSRM-XXPostflight
Report
RSRM-XXPostfireReport
Review,Cause,
CorrectiveAction &
DispositionDefines overall
postfire system
Defines motor-set
unique evaluationsbased on specific
changes & issues
PEEP limit
violation or
unexpected condition
Observation
checklist and
recording form
SRB/RSRM
Postfire
Assessment Team
(SPAT) Board
Elevateto PFAR
Dispositionand Close
PostflightEngineeringEvaluation
Plan
(PEEP)
TWR-50051/2
PostfireEngineeringEvaluation
Plans
(PEEPs)
Defines standard
hardware
evaluation
requirements,
observation limits
and photographic
/video coverage
requirements
-
7/29/2019 4 KSC Motor Integration
36/37
ATK THIOKOL
321
RSRM Postfire Evaluation Process
Postfire Database, Trending, and Documentation
RSRM postfire data is entered into historical database
Data is trended with historical data to verify performance within
approved limits
Violations of trending limits are reported and investigated asnecessary
Closure of violations is approved by ATK Thiokol management
(and MSFC for significant trends)
Postfire observations and trend data included in final report(s)
-
7/29/2019 4 KSC Motor Integration
37/37
ATK THIOKOL
Return to Utah
Segments are loaded ontothe same type railcars as
they were delivered
Nozzle components, igniters,
stiffener rings and other
smaller components areshipped by truck
The joint pins remain at KSC
and are refurbished by ATK
personnel