4 KSC Motor Integration

download 4 KSC Motor Integration

of 37

Transcript of 4 KSC Motor Integration

  • 7/29/2019 4 KSC Motor Integration

    1/37

    ATK THIOKOL

    286

    Motor Integration Team

    Presented by:

    KSC MotorIntegration

  • 7/29/2019 4 KSC Motor Integration

    2/37

    ATK THIOKOL

    287

    Motor Integration at KSC and CCAFS

  • 7/29/2019 4 KSC Motor Integration

    3/37

    ATK THIOKOL

    288

    Russ Bakes

    Integration ProgramManager

    SteveSchmieder

    IntegrationSub-systemManager

    Paul Teehan

    MSFC ResidentOffice

    Ted Shaffner

    KSC OperationsManager

    Bruce Tams

    Integration DesignEngineering Manager

    Mike Evans

    Quality Manager

    Integration Leadership Team

  • 7/29/2019 4 KSC Motor Integration

    4/37

    ATK THIOKOL

    289

    Interfaces

    The integration teams function is to assure ATK and MSFCrequirements are incorporated into the motor processing at KSC

    The hands on work, i.e., build up, stack, close out, integrate,

    launch and disassemble the boosters is done by USA

    Because we work with an integrated vehicle and operate in a

    multi contractor environment our communication is with multipleelements

  • 7/29/2019 4 KSC Motor Integration

    5/37

    ATK THIOKOL

    290

    Recovery

    and PostflightEvaluation

    Launch

    SRB Stacking

    KSC Operations

    KSC Operations

    CCAFS Operations

    RSRM Processing

  • 7/29/2019 4 KSC Motor Integration

    6/37

    ATK THIOKOL

    291

    Jay Jay

    Siding

    LMF

    Segment

    Onload

    Port

    Canaveral

    Hangar AF and

    Hangar N

    VAB/ RPSF/

    OSB Area

    Pads

    SuspectSiding

  • 7/29/2019 4 KSC Motor Integration

    7/37

    ATK THIOKOL

    292

    SHUTTLELANDING

    SRB RETRIEVALSHIP

    HANGAR AF

    RPSF

    SRB STACKING

    ET/SRBOPERATIONS

    ETSTANDALONE

    LCC

    INTEGRATEDVEHICLE OPS/VAB

    OffloadBuildup

    HORIZONTALPAYLOAD INT

    PAYLOAD FACILITIESHYPERGOLIC

    FACILITY

    ORBITER PROCESSING

    FACILITY

    Pad Ops

    VERTICAL

    PAYLOAD

    INSTALLATION

    Design Centers

    Element Refurbishment and Manufacturing

    Logistics and Shipping

    Delivery

    Offload and

    Inspect

    Aft Booster

    Build

    Field Joint Mate

    Leak Test

    Field Joint

    Protection

    System

    S&A

    SRB Integration

    Launch

    Recovery

    Disassembly andAssessment

    Shuttle Vehicle Processing Operations

  • 7/29/2019 4 KSC Motor Integration

    8/37

    ATK THIOKOL

    293

    Delivery

    Segments arrive at Jay Jaysiding via railcar

    Cars are 200-ton railcars

    with fiberglass covers

  • 7/29/2019 4 KSC Motor Integration

    9/37

    ATK THIOKOL

    294

    Offload and Inspect

    Segments and exit cones are rotated to vertical (flightorientation) in the rotation building at the Rotation, Processingand Surge Facility (RPSF)

  • 7/29/2019 4 KSC Motor Integration

    10/37

    ATK THIOKOL

    295

    Aft Booster Build-up

    Aft skirt mate Exit cone mate

    Leak test

    Backfill

    Nozzle severance connection,

    checkout, and close out GEI and heater power cable

    installation and test

    Stiffener ring installation andclose out

    Froth-Pak Application Systems tunnel installation

    and close out

    Storage until ready to stack

  • 7/29/2019 4 KSC Motor Integration

    11/37

    ATK THIOKOL

    296

    Aft Skirt Mate

    The aft skirt (USA supplied) isplaced in the build up stand and

    the segment is mated

    177 pins are installed and secured

    with a steel retainer strap

    The joint is closed out with a pinband and cork

    Cork

    Pin Retainer Strap

    Aft skit clevis

  • 7/29/2019 4 KSC Motor Integration

    12/37

    ATK THIOKOL

    297

    Exit Cone Mate

    Aft exit cone is assembled to theforward exit cone at KSC

    (Joint No.1)

    Phenolic mating surfaces are

    primed with DC1220 primer

    prior to assembly

    Primary and secondary O-rings

    are installed

    Exit cone is raised on an

    elevator and floated on an air

    bearing for mating

    The joint is bolted with 96fasteners

    Leak test is performed at 83

    and 30 psig with the Mass Flow

    Meter prior to joint backfill

    Backfill

    O-rings

  • 7/29/2019 4 KSC Motor Integration

    13/37

    ATK THIOKOL

    298

    Exit Cone Backfill

    Joint gap is backfilled (injected) with RTV sealant Spatulas are used to support the tape and aid in a

    deep fill of the joint

    Backfill is part of thermal barrier system

    Joint 1 is a static joint (opens less than 0.0005 in.)

    Joint

    Interface

    Backfill

    Nozzle

  • 7/29/2019 4 KSC Motor Integration

    14/37

    ATK THIOKOL

    299

    Stiffener Ring Installation and Close-out

    The function of the stiffenerrings is to prevent case

    damage from splashdown due

    to cavity collapse

    Stiffener rings have no flight

    function

    Three sections are bolted to the

    integral stub and joined

    together by splice plates

    RT-455 is used to protect

    fasteners and the paintedhardware from heat loads

    The foam ramp helps deflect

    the water geyser at splashdown

    3 Stiffener

    Rings

    Foam

    RT-455

    Ablative

    Stiffener

    Ring

  • 7/29/2019 4 KSC Motor Integration

    15/37

    ATK THIOKOL

    300

    Systems Tunnel

    The aft segment systems tunnel iscompleted at the RPSF up to the ETA

    ring prior to transfer to storage

    Cables are run and secured

    Connections are checked

    Covers are installed and closed out

    Systems

    Tunnel

    Stiffener Ring

  • 7/29/2019 4 KSC Motor Integration

    16/37

    ATK THIOKOL

    301

    Segment Storage

    All segments remainvertical on their pallets

    until they are transferred

    to the VAB for stack

    A KAMAG is used to pick

    up and transport thepallet

    Surges protect the

    hardware from rain, wind,

    etc.

    Not climate controlled.

    Segments have weather

    proof covers on top

  • 7/29/2019 4 KSC Motor Integration

    17/37

    ATK THIOKOL

    302

    SHUTTLELANDING

    SRB RETRIEVALSHIP

    HANGAR AF

    RPSF

    SRB STACKING

    ET/SRBOPERATIONS

    ETSTANDALONE

    LCC

    INTEGRATEDVEHICLE OPS/VAB

    OffloadBuildup

    HORIZONTALPAYLOAD INT

    PAYLOAD FACILITIESHYPERGOLIC

    FACILITY

    ORBITER PROCESSINGFACILITY

    Pad Ops

    VERTICAL

    PAYLOAD

    INSTALLATION

    Design Centers

    Element Refurbishment and Manufacturing

    Logistics and Shipping

    Delivery

    Offload and

    Inspect

    Aft Booster

    Build

    Field Joint Mate

    Leak Test

    Field Joint

    Protection

    System

    S&A

    SRB Integration

    Launch

    Recovery

    Disassembly andAssessment

    Shuttle Vehicle Processing Operations

  • 7/29/2019 4 KSC Motor Integration

    18/37

    ATK THIOKOL

    303

    RSRM Field Joint Mate

    Current joint mate process wasdeveloped through testingduring the RSRM redesignprogram

    Joint assembly objective is toprevent tang/clevis flat-on-flatand protect the o-rings frombeing cut or damaged: capturefeature O-ring is mostsusceptible

    Calculations are performedbased on case diameter data todetermine proper Field Joint

    Assembly Fixture (FJAF)configuration for each joint mate

    Interference Fit

    Maintains O-ring

    Squeeze and Restricts

    Joint RotationClevis

    Tang

  • 7/29/2019 4 KSC Motor Integration

    19/37

    ATK THIOKOL

    304

    Joint Mate Preparations

    Pressure Sensitive Adhesive(PSA) is applied to the

    insulation interfaces

    Metal parts are inspected and

    greased

    O-rings are installed

    FJAF configured and

    installed

    Cases are measured to

    determine the relative shapes

    Requirement is for shapes to

    be within +/-0.210 in. fornominal mate

    Shape can be improved by

    adjusting the 4 point beam

    load distribution

    Tang

    Clevis

    J-Joint

  • 7/29/2019 4 KSC Motor Integration

    20/37

    ATK THIOKOL

    305

    RSRM Field Joint Mate

    Crane lowering rate iscontrolled to 0.060 in./minute

    maximum

    Levelness and rate of

    engagement are continually

    monitored during segmentlowering

    FJAF contact with the case is

    monitored during maximum

    engagement

    Leak test of the joint and thevent port plug are the final

    acceptance of a successful

    joint mate

    Field Joint Assembly

    Fixture Acts to

    Shoehorn the

    Segments Together

    Temposonics to Measure

    Rate of Engagement,

    Parallelism, and DistanceFrom Mate

  • 7/29/2019 4 KSC Motor Integration

    21/37

    ATK THIOKOL

    306

    Field Joint Protection System (FJPS)

    The purposes of the FJPS are: Maintain an optimal temperature for

    O-ring tracking

    Prevent environmental

    contaminants such as rainwater

    from entering the joint area

    Final product is painted with white

    Acrymax paint

    Cork

    Heater Retainer

    Strap and ThermalBarrier

    JointTemperature

    Sensor

    JointHeater

    Pin RetainerBand

    RT-455Ablative

    RT-455Ablative

    Cork

  • 7/29/2019 4 KSC Motor Integration

    22/37

    ATK THIOKOL

    307

    Skirt Joint Protection System (JPS)

    Forward and aft skirt JPS isprimarily to provide thermal

    protection, weather protection and

    to retain the pins

    A flat steel strap is installed over the

    pin heads

    Cork is bonded with EA934 andpainted with Acrymax paint

    A grease bead is applied to the

    clevis/tang exterior interface of the

    joint

    GreaseBead

    Steel Retainer

    Strap

    Cork

  • 7/29/2019 4 KSC Motor Integration

    23/37

    ATK THIOKOL

    308

    S&A Installation

    The ignition Safe and Arm (S&A)devices are installed after the

    RSRM is stacked and the forward

    skirt is installed

    Fluorocarbon seals contained

    within a steel retainer gasket are

    placed between the S&A and theigniter adapter surface

    Crushable preload measuring

    washers are used to control bolt

    preload

    Leak test is performed with thebolts partially torqued to prevent

    false positive due to a metal to

    metal seal

    Final torque and cable

    connections are then performed

    S&A

    Gasket

    S&A

  • 7/29/2019 4 KSC Motor Integration

    24/37

    ATK THIOKOL

    309

    Vehicle Integration

    SRB integration Joint heater and temperature sensor connections

    Thrust Vector Control (TVC) actuator to nozzle connections

    Chamber pressure and ignition S&A connections

    Systems tunnel cable runs

    Systems tunnel cove close outs

    Extensive checkouts of ground and flight electrical systems

    The tank is mated to the SRB

    The orbiter is mated to the tank

    The assembled vehicle is rolled to the pad

  • 7/29/2019 4 KSC Motor Integration

    25/37

    ATK THIOKOL

    310

    SHUTTLELANDING

    SRB RETRIEVALSHIP

    HANGAR AF

    RPSF

    SRB STACKING

    ET/SRBOPERATIONS

    ETSTANDALONE

    LCC

    INTEGRATEDVEHICLE OPS/VAB

    OffloadBuildup

    HORIZONTALPAYLOAD INT

    PAYLOAD FACILITIESHYPERGOLIC

    FACILITY

    ORBITER PROCESSINGFACILITY

    Pad Ops

    VERTICAL

    PAYLOAD

    INSTALLATION

    Design Centers

    Element Refurbishment and Manufacturing

    Logistics and Shipping

    Delivery

    Offload and

    Inspect

    Aft Booster

    Build

    Field Joint Mate

    Leak Test

    Field Joint

    Protection

    System

    S&A

    SRB Integration

    Launch

    Recovery

    Disassembly andAssessment

    Shuttle Vehicle Processing Operations

  • 7/29/2019 4 KSC Motor Integration

    26/37

    ATK THIOKOL

    311

    Launch

    Launch countdown begins about 3days prior to launch

    RSRM systems begin to activateapproximately 18 hours prior tolaunch S&A rotation test at Launch (L)-60

    hours

    The igniter heater is activated at L-18hours

    Operational Pressure Transducers(OPTs) are powered up at L-9 hours

    Joint heaters are powered up at L-8hours

    OPTs are checked out at L-1.5 hours

    The igniter heater is deactiviated andthe S&A armed at L-5 minutes

    Main engine start is at L-6 sec

    SRB ignition and hold-down post-firingat L-0

  • 7/29/2019 4 KSC Motor Integration

    27/37

    ATK THIOKOL

    312

    SHUTTLELANDING

    SRB RETRIEVALSHIP

    HANGAR AF

    RPSF

    SRB STACKING

    ET/SRBOPERATIONS

    ETSTANDALONE

    LCC

    INTEGRATEDVEHICLE OPS/VAB

    OffloadBuildup

    HORIZONTAL

    PAYLOAD INT

    PAYLOAD FACILITIESHYPERGOLIC

    FACILITY

    ORBITER PROCESSINGFACILITY

    Pad Ops

    VERTICAL

    PAYLOAD

    INSTALLATION

    Design Centers

    Element Refurbishment and Manufacturing

    Logistics and Shipping

    Delivery

    Offload and

    Inspect

    Aft Booster

    Build

    Field Joint Mate

    Leak Test

    Field Joint

    Protection

    System

    S&A

    SRB Integration

    Launch

    Recovery

    Disassembly andAssessment

    Shuttle Vehicle Processing Operations

  • 7/29/2019 4 KSC Motor Integration

    28/37

    ATK THIOKOL

    313

    Recovery

    Ships crew gatherparachutes and the frustum

    Divers install the Diver

    Operated Plug into the

    nozzle

    The DOP system pumpswater from the interior to get

    the booster into log mode

    Recovery ships tow the

    SRBs back to Hangar AF

  • 7/29/2019 4 KSC Motor Integration

    29/37

    ATK THIOKOL

    314

    Post Flight Disassembly and Assessment

    SRBs are floated into awharf and lifted onto the

    disassembly dolly with a

    straddle lift

    SRB and RSRM

    components aredisassembled by USA

    Assessments of the flown

    hardware are performed

    by ATK, USA SRB and

    MSFC representatives

  • 7/29/2019 4 KSC Motor Integration

    30/37

    ATK THIOKOL

    315

    RSRM Postfire Evaluation Process

    Purpose of RSRM Postfire Evaluation

    The objective of postfire evaluation (disassembly and assessment)

    is to verify integrity of recovered RSRM hardware and identify any

    anomalous conditions in a timely manner

    Did the hardware perform as expected? What is it telling us?

    Were engineering requirements violated, and if so how does this effectperformance?

    Is the condition in family with past observations?

    Does the condition affect subsequent launches or tests?

    Impact on future launches is addressed in flight/test readiness review

    (FRR/TRR) process

  • 7/29/2019 4 KSC Motor Integration

    31/37

    ATK THIOKOL

    316

    RSRM Postfire Evaluation Process

    Postfire Evaluation Requirements Postfire Hardware Evaluation System Operating Plan

    Defines system requirements for:

    Disassembling, evaluating, documenting, reporting, and databasing the

    condition of postfired RSRM hardware

    Identifying, reviewing, tracking, and resolving observed abnormal/anomalous

    conditions or trends

    Postfire Engineering Evaluation Plans

    Defines requirements for:

    Engineering evaluation, hardware observation limits (allowable and

    reportable), and photo/video documentation

    Approved by NASA MSFC

  • 7/29/2019 4 KSC Motor Integration

    32/37

    ATK THIOKOL

    317

    RSRM Postfire Evaluation Process

    Postflight Evaluation Process and Timeline Launch + 2-21 days, CCAFS Hangar AF (Florida)

    Recovered solid rocket boosters initially assessed, including assessment for missing

    external insulation

    Forward and aft skirts, S&A devices, igniters, nozzles, and exit cones removed and

    assessed

    Case field joints demated and internal insulation assessed Launch + 8-14 days, ATK Thiokol M-66A Facility (Utah)

    S&As disassembled and assessed

    Launch + 15-30 days, VACCO vendor facility (California)

    Arming-Monitor and Barrier-Booster disassembled and assessed

    Launch + 12-18 days, ATK Thiokol Refurbishment Center (Utah)

    Internal nozzle joints demated and assessed

    Launch + 20-160 days, Thiokol Refurbishment Center (Utah)

    Nozzle bondlines, nozzle liner char/erosion measurements, case and igniter insulation

    measurements, and factory joints demated and assessed

  • 7/29/2019 4 KSC Motor Integration

    33/37

    ATK THIOKOL

    318

    Barrier-Booster Housing

    A041627a1

    SAFETY AND ARMING DEVICE

    Barrier-BoosterRotor Shaft Seals

    Safing Pin

    A-M Backfill Port

    Visual Indicator

    Window

    A-M Switch Deck

    Motor Field Windings

    Motor Armature

    A-M Electrical ConnectorGear Reduction (625:1)

    Rotor(mechanical barrier)

    Perforated PlateFoam Cushion

    B-KNO3Granules

    B-KNO3Pellets

    SII

    Safing Arm

    Clutch Ass embly

    Locking Shaft

    EnvironmentalSeals

    Booster Basket

    Attach Bolt

    PLI NestedWasher

    Aft Exit Cone Assembly

    Cowl Housing

    Cowl

    A038797aDDB

    Vented PositiveStop Set Screw

    FlexibleBoot Assembly

    Cowl Insulation Segment

    Nose InletAssembly

    Throat Inlet AssemblyForward Exit Cone Assembly

    Fixed HousingAssembly

    Snubber Detail:

    Ring, Segment,Retainer

    Flex Bearing

    Flex Bearing Protector

    Vented Positive Stop Set Screw

    Vented Positive Stop Set Screw

    RSRM Postfire Evaluation Process

  • 7/29/2019 4 KSC Motor Integration

    34/37

    ATK THIOKOL

    319

    RSRM Postfire Evaluation Process

    Postfire Anomaly Record (PFAR) System Any observation that falls outside of established limits or is

    unexpected is reported on a Squawk (Florida) or Preliminary PFAR

    (Utah, California)

    Each Squawk/Preliminary PFAR is presented to SRB/RSRM

    Postflight Assessment Team (SPAT Board) for review

    SPAT Board consists of NASA, senior contractor management, and

    engineering

    SPAT Board determines if violation should be elevated to PFAR which

    requires corrective actions and further reviews

    PFAR corrective actions worked by component teams

    PFAR closure rationale approved by ATK Thiokol and MSFC

    All PFARs presented in FRR/TRR process including impact and

    rationale for upcoming flights/tests

  • 7/29/2019 4 KSC Motor Integration

    35/37

    ATK THIOKOL

    320

    RSRM Postfire Evaluation Process

    Postfire

    HardwareEvaluationSystem

    TWR-16899

    Postfire

    HardwareEvaluationSystem

    TWR-16899

    RSRM-XXSpecialIssues

    RSRM-XXSpecialIssues

    Hardware Disassembly

    and Evaluation

    Postflight

    Observation

    Records(PFORS)

    Hardware Disassembly

    and Evaluation

    Postfire

    Observation

    Records(PFORS)

    Squawk

    (KSC)

    Squawk

    (KSC)

    Preliminary

    Postflight

    Anomaly

    Record

    (Utah)

    Preliminary

    Postfire

    Anomaly

    Record

    (Utah)

    Postflight

    Anomaly

    Record

    (PFAR)

    Postfire

    Anomaly

    Record

    (PFAR)

    RSRM-XXPostflight

    Report

    RSRM-XXPostfireReport

    Review,Cause,

    CorrectiveAction &

    DispositionDefines overall

    postfire system

    Defines motor-set

    unique evaluationsbased on specific

    changes & issues

    PEEP limit

    violation or

    unexpected condition

    Observation

    checklist and

    recording form

    SRB/RSRM

    Postfire

    Assessment Team

    (SPAT) Board

    Elevateto PFAR

    Dispositionand Close

    PostflightEngineeringEvaluation

    Plan

    (PEEP)

    TWR-50051/2

    PostfireEngineeringEvaluation

    Plans

    (PEEPs)

    Defines standard

    hardware

    evaluation

    requirements,

    observation limits

    and photographic

    /video coverage

    requirements

  • 7/29/2019 4 KSC Motor Integration

    36/37

    ATK THIOKOL

    321

    RSRM Postfire Evaluation Process

    Postfire Database, Trending, and Documentation

    RSRM postfire data is entered into historical database

    Data is trended with historical data to verify performance within

    approved limits

    Violations of trending limits are reported and investigated asnecessary

    Closure of violations is approved by ATK Thiokol management

    (and MSFC for significant trends)

    Postfire observations and trend data included in final report(s)

  • 7/29/2019 4 KSC Motor Integration

    37/37

    ATK THIOKOL

    Return to Utah

    Segments are loaded ontothe same type railcars as

    they were delivered

    Nozzle components, igniters,

    stiffener rings and other

    smaller components areshipped by truck

    The joint pins remain at KSC

    and are refurbished by ATK

    personnel