Cork19/jan/2016
Project SLOPE1
WP 3 – Integration of novel intelligent harvesting systems operating in mountain
areas (hardware development)
![Page 2: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/2.jpg)
Project SLOPE
Greifenberg Presentation
CORK, JANUARY 2016
![Page 3: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/3.jpg)
Foreword
Wp 3 is focused on the set up of machines and tools required to create anintelligent interaction from rfid tag reader to black box back up withinnovative machinery covering the complete supply chain in harvestingoperations on steep terrains. The aim is to improve forestry workers safety,productivity together with terrain sustainability.
![Page 4: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/4.jpg)
Foreword
Technical innovation required will be implemented in machines which willbe ready to function to perform real forestry operations on difficult areas.
![Page 5: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/5.jpg)
Foreword
The critical part of the wp 3 is to be able to manage interaction amongdifferent machines and components keeping functionality also with relevantchanges carried out on the machines.
We do believe that we will be able to successfully manage the wp with themost suitable components able to collect and transmit perfect data alongthe supply chain
![Page 6: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/6.jpg)
Mitigating action undertaken
New partner in the project for the processor head part.
Dow amendmentTask 3.2 changed with the purchase of a new processorhead and the analysis required
Start of wp 3 in month 6 affected by amendment andmitigating action as reported previously
Suitable components choice and their availability
![Page 7: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/7.jpg)
We will implement information with the other partners tohave the suitable components (antenna, reader andinterface pc and its programming) to proceed with thedeliverable to be submitted in month 26.
What we will be doing to finalisedeliverable 3.3
![Page 8: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/8.jpg)
Let's see what we have been doing sincelast January
![Page 9: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/9.jpg)
![Page 10: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/10.jpg)
Time plan
![Page 11: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/11.jpg)
Task 3.3 parts
Tecno carriageChockersRope launcher
![Page 12: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/12.jpg)
Tecno carriage work status
The carriage is ready. We still need toimplement the interface pc with itssoftware, the modification on existingsoftware with laboratory test to verifyinteraction.
A mechanical part is being installed nowfor the antenna. It will be a movable partto be lifted upward and downward toprotect the component from the logsWe have planned testing activities withGraphitech and CNR at the end ofJanuary, beginning of February.
http://youtu.be/ihXUCTBtoVU
![Page 13: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/13.jpg)
Chockers work statusChokers are ready. The mechanical part is ready. We still need to manageinteraction between them and the new software
Testing activities will be carried out also between Tecno carriage and theChockers
![Page 14: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/14.jpg)
Synthetic rope launcher EASER status
The prototype is ready. We have carried out testing activities up to 500mt. We met difficulties due to the unwrapping of the textile rope. Wehave newly re-designed the system and currently we are working ontesting activities with a new component tailored to our needsThe new project will consider the launch of the rope without the needon unwrapping from the winches.
![Page 15: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/15.jpg)
Synthetic rope launcher EASER status
![Page 16: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/16.jpg)
Synthetic rope launcher EASER status
![Page 17: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/17.jpg)
Synthetic rope launcher EASER status
![Page 18: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/18.jpg)
Wp3 needs testing in machines andcomponent interactions. We will proceedwith the interface activities between thecarriage and the processor head first inlaboratory and then on field
3.3 - 3.4
![Page 20: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/20.jpg)
ProjectSLOPE
Mid termreviewmeeting19th-21st January2016
![Page 21: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/21.jpg)
Mid termreviewmeeting19th-21st January2016
Overview
• Status: ongoing(70%)• Duration: 17 months (from M9 to M25)• Involved partners
‐ leader: Compolab‐ participants:CNR, BOKU, Greifenberg
• Aim: add to a commercial processorhead grading and markingcapabilities while preservingthe existingones
• Output: D3.04 (P type deliverable, due to M25)
![Page 22: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/22.jpg)
Previous status ofactivities
Mid termreviewmeeting19th-21st January2016
![Page 23: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/23.jpg)
Performed activitiesReverse engineering activities (Task3.2) completed
Deliverable D.3.09submitted inSeptember 2015
Mid termreviewmeeting19th-21st January2016
![Page 24: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/24.jpg)
Performedactivities
Designof thenovel intelligent processor head
Mid termreviewmeeting19th-21st January2016
![Page 25: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/25.jpg)
SWquality index – Described inD4.05
HIqualityindex – Described in D4.04
NIR qualityindex –Described in D4.03
Stress wave system
Hyperspectralimaging system
Near infraredimaging system
RFIDlabeller
Performedactivities
Envisaged sub-system
Cutting forces evaluation system CPqualityindex – Described inD4.06
Mid termreviewmeeting19th-21st January2016
![Page 26: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/26.jpg)
Performedactivities
Cutting forces evaluation system
![Page 27: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/27.jpg)
Mid termreviewmeeting19th-21st January2016
Performedactivities
Cutting forces evaluation system
![Page 28: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/28.jpg)
Performedactivities
Stress wave evaluation system
Lasermeasurementsystem
Longitudinalaxial modes analysis withtheresonancemethod
Lasertriangulationsensorableto detectandmeasuretheinducedfreevibrationof thetree
Mid termreviewmeeting19th-21st January2016
Accelerometersmeasurementsystem
Wavepressuretimeof flightmeasurementsinthe processedlogs
Composedbytwoaccelerometersand asensorized hammerthat providesthemechanicalstimulusandtriggersignal
![Page 29: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/29.jpg)
Performedactivities
Stress wave evaluation system
Mid termreviewmeeting19th-21st January2016
![Page 30: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/30.jpg)
Performedactivities
Stress wave evaluation system
Mid termreviewmeeting19th-21st January2016
![Page 31: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/31.jpg)
Mid termreviewmeeting19th-21st January2016
Performedactivities
Hyperspectral imagingsystem + NIR imagingsystem
HyperspectralandNIRsensorswill bepositionedonalifting/loweringbar(socalled scanbar)paralleltothechainsawbar
and placedin aseparated carterforprotectionfromdirty,lubricatingoil andchipping
Sensorsneed specificand verysmalldistance(~3mm)fromlogsurface
Velocityprofileof scanbarneed tobedefined
![Page 32: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/32.jpg)
Performedactivities
Hyperspectral imagingsystem + NIR imagingsystem
Mid termreviewmeeting19th-21st January2016
![Page 33: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/33.jpg)
Performedactivities
RFIDlabeller
RFIDtagswill beplaced onthe
Systemwill beplaced ona movablebarand will becomposedby:
• RFIDtagroll• RFIDloading andcutting
systemsystem• Staplersystem• RFIDantenna• RFIDreader
Mid termreviewmeeting19th-21st January2016
crosssection ofeach log
RFIDtagwill befixed onlogs bystaple(mostreliablesystem)
RFIDtags
Minimumlogdiameter(~20cm)
Logcrosssection
![Page 34: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/34.jpg)
Performedactivities
RFIDlabeller
Mid termreviewmeeting19th-21st January2016
![Page 35: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/35.jpg)
Performedactivities
RFIDlabeller
Mid termreviewmeeting19th-21st January2016
![Page 36: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/36.jpg)
Performedactivities
RFIDlabeller
Mid termreviewmeeting19th-21st January2016
![Page 37: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/37.jpg)
Actual activities status
Mid termreviewmeeting19th-21st January2016
Designofthenovelintelligentprocessorheadiscompleted
Sensorshavebeen selected, purchasedand arrived
NationalInstrumentscomponentsforsensorsacquisition havebeen selected, purchasedand arrived
NationalInstrumentscomponentsforthenewmachinecontrolhavebeen selected andpurchased
IndustrialPChavebeen selected, purchasedand arrived
Actuators:hydrauliccylindersforstress wavesystemand RFIDlabeller designed andordered
electrical actuatorsforscan barandRFIDlabeller selected andpurchased
![Page 38: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/38.jpg)
Mid termreviewmeeting19th-21st January2016
Ongoing activities
Designofharnesswiring
Designofaddedhydrauliccircuit
Electricalpowersupplysystem
Productionofthedesignedcustomparts
Assemblyofthenovelprocessorhead
D.3.04isplannedtobecompletedbytheendofMarch2016
![Page 39: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/39.jpg)
Contact info
GaspareL’Episcopia:[email protected]: [email protected]
Thank you for your attention
Mid termreviewmeeting19th-21st January2016
![Page 40: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/40.jpg)
Cork19/jan/2016
Project SLOPE40
T 3.5 ‐ Intelligent transport truck
Cork, January 19th, 2016
![Page 41: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/41.jpg)
Cork19/jan/2016
Scope41
Status: 100%
Length: 12 months (M12 to M24)
Partners involved: ITENE (leader), CNR, MHG, BOKU
Aim: Track trucks and loaded logs and send the information into the SLOPE system
Output: Deliverable D3.05 (finished)
![Page 42: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/42.jpg)
Cork19/jan/2016
General Architecture42
![Page 43: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/43.jpg)
Cork19/jan/2016
43
Use case
![Page 44: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/44.jpg)
Cork19/jan/2016
Hardware44
![Page 45: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/45.jpg)
Cork19/jan/2016
Hardware45
Raspberry Pi 2 Model B 900MHz Quad core ARM V7 processor 1GB of RAM
GlobalSat BU‐353‐S4 USB GPS ‐ GPS data acquisition
Huawei E3256 USB GPRS – GPRS connection
Belkin F8T013‐1 – Bluetooth USB adapter
Edimax EW‐7811Un – Wireless USB adapter
CAEN R1240I – qID – portable RFID reader
![Page 46: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/46.jpg)
Cork19/jan/2016
Software46
Raspbian Linux distribution as an operative system. Raspbian is a free operating system based on Debian and optimized for the rpi hardware.
PostgreSQL as a database software. PostgreSQL is cross platform, open source and free to use.
Python 3 as programming language. Python is a general‐purpose, object‐oriented, high‐level programming language defined for code readability. Python is free and open source.
![Page 47: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/47.jpg)
Cork19/jan/2016
Main Screen47
Main screen to engage the systemand monitor status
![Page 48: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/48.jpg)
Cork19/jan/2016
Test Screen48
Test screen to try thedifferent parts of thesystem and checkfunctionalities.
![Page 49: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/49.jpg)
Cork19/jan/2016
Configuration Screen49
Configuration screento set differentoptions of thesolution.
![Page 50: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/50.jpg)
Cork19/jan/2016
Manual RFID Reader Screen50
Manual RFID Screento control and monitor the activity of the portable RFID reader.
![Page 51: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/51.jpg)
Cork19/jan/2016
Next steps51
Optimize software and functioning ‐ T7.2, T7.3
Prepare participation in SLOPE pilots – T7.3
![Page 52: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/52.jpg)
Cork19/jan/2016
Contact info52
Juan de Dios Díaz ([email protected])
Emilio Gonzalez ([email protected])
Thanks for your attention!!
![Page 53: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/53.jpg)
Cork19/jan/2016
Task 3.6: data management backupObjectives
The goals of this task are:• to develop system for data exchange between hardware in field and central computer of FIS• to provide a data backup strategy
![Page 54: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/54.jpg)
Cork19/jan/2016
Task 3.6: data management backup
Task Leader: CNR
Task Partecipants: Compolab, Greifenberg, Graphitech, Itene, (Treemetrics)
March 2015 to February 2016
Status: 50%
D.3.07 Black‐box for backup and data transmissionPrototype: portable and internal powered black box for daily/weekly data back up and for data transmission in areas without GPRS coverage (M.25)
![Page 55: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/55.jpg)
Cork19/jan/2016
the “black box” solution is a portable storage (SSHD or similar)
the external storage will be connected with USB to the industrial PC hosted by the excavator
it is used for storing critical data (backup)
the dedicated GPRS module (USB) is installed in industrial PC and is used for communication with the central server in a case of the network coverage
the portable storage is transferred to the office / operator house and after connecting to internet, automatically synchronizing data with the database in a case of no network coverage in forest
Task 3.6: data management backupdetailed concept
![Page 56: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/56.jpg)
industrial PC
Database
banana PI computer
FRID
wei
ght
fuel
???
Data storage
CP NIR HI SW
cam
era
kine
ct
![Page 57: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/57.jpg)
banana PI
CAN-bus
RFID antena
RFID controler
load cell
A/D converterWIFI antena
PC processor
CAN-bus CAN-bus
USB
Fuel consumptionPositionTime of installing logTime of cycleRFID of logsTotal weight of logs
TECHNO PLC
![Page 58: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/58.jpg)
banana PI
SSD “black box”
cRIO - control
PC processorUSB
SWsensors
Fuel consumptionPositionTime of installing logTime of cycleRFID of logsTotal weight of logs
WIFI antena
GPRS/UMTS
USBLAN
cDAQ - sensors
LAN
Data from FIS:quality indexes for
RFID trees, suggested cutting plan
Data for FIS:logs quality, quantity,
suitability for each RFID log Backup of all data,
including WP4 quality indexed
pressuresensors
NIRsensors
HIsensors
CFsensors
termometer
actuators guages
encoders
![Page 59: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/59.jpg)
Cork19/jan/2016
Banana PI Pro
![Page 60: 3rd Technical Meeting - WP3](https://reader031.fdocuments.us/reader031/viewer/2022011721/58a30b981a28abea508b6b73/html5/thumbnails/60.jpg)
Cork19/jan/2016
select and purchase optimal hardware (CNR, Graphitech and COMPOLAB) integrate the hardware modules with PC chassis (CNR and COMPOLAB) define structures of data (both; to be transmitted via 3G and stored for further use in FIS (Graphitech + Treemetrics) to develop the software for communication of the cable crane and central computer (Greifenberg, CNR and COMPOLAB) to develop the software for field instruments and GPRS communication (CNR and COMPOLAB) to develop software tools for merging the data with FIS (Graphitech) to extensively test the solution both in lab and in field (all partners)
Task 3.6: data management backupwork plan