3rd Steinmüller Engineering Conference 2019€¦ · 600MW boiler damaged by a significant...
Transcript of 3rd Steinmüller Engineering Conference 2019€¦ · 600MW boiler damaged by a significant...
Version: xx/201x/Tel
Rely on good experience with
The Engineers Company
3rd Steinmüller Engineering Conference 2019
Replacement of a damaged 600MW boiler:
A review of the design activities and
technical challenges
Speaker : Armin Martz
Co-Speaker : Thomas Will
2
Introduction
The 600MW coal-fired boiler (Main steam design temperature 545°C, design pressure 19.4
MPA) was designed by L&C Steinmueller GmbH in the 1970ies
600MW boiler damaged by a significant over-pressurisation incident in 2014
Require demolition and rebuild of boiler within existing structure
Recovery project has many challenges, this papier focus on:
Demolition activities
Design approach and challenges
Source: publications from ESKOM
3
Contents
Part 1 Part 2
Project Scope
Demolition
HP Pipe Demolition
Structure Assessment
Boiler Demolition
Lessons Learnt
Design Activities
Design Team Setup
Design Approach
Boiler Re-engineering
Lessons Learnt
Conclusion
Source: publications from ESKOM
4
Project Scope
Source: publications from ESKOM
Boiler structure retained
Damaged Plant
Undamaged Plant
Air
Heater
Fabric Filter
Plant
Main Steel
Structure
Boiler
MillsFans
Ducting
HP
Piping
Turbine
Plant
Boiler structure retained
Damaged Plant
Undamaged Plant
5
HP Pipe Demolition
Aux Bay
Turbine Hall
• HP piping followed a cutting and dismantling approach
• Installed blocking frames to minimize pipe movement
(cold pull gradually released)
• Installed temporary restraints and supports for rigging
• Salvaged components capped and preserved
Source: publications from ESKOM
6
Pre-demolition Structural Assessment & Repair
• Condition of structure assessed prior to
demolition
• Visual inspections
• 3D laser surveying
• Structural modelling
• NDT of welds
• Bolt removal & inspection
• Assessment concluded that structure
maintained original load bearing capacity,
only required minor repair.
• Performed temporary repairs prior to
demolition
• Permanent repairs will follow post demolition
Source: publications from ESKOM
7
Boiler Demolition
• Boiler internals
• “cut-and-drop” approach
• Removed bottom ash hopper
• Cut evaporator bottom slope
• Erected “cushion” on 0m level
• Installed demolition curtain from 0-16m
• Used evaporator walls as chute
• Drop test
• Concerns over impact forces transferring to
boiler supports
• Installed strain gauges & performed drop test
• Determined safe cut sizes
• Boiler external equipment & water walls
• Controlled cut, dismantle & rigging
Source: publications from ESKOM
8
Boiler Demolition
“Cushion” at 0m level
Evaporator walls used as chute Windows
cut out in
evaporator
Demolition
curtains
Super heater
bundle
dropped onto
cushion
Source: publications from ESKOM
9
Demolition Challenges & Lessons Learnt
• Demolish boiler in between operating units, may not
impact operation & maintenance of adjacent units
• Reuse of main steel structure require continuous
structural assessment
• Rigging studies develop progressively as areas
become accessible
• Full time resources to review rigging studies while
being developed to limit standing time
• Demolition period: 13 months
• 7600 ton of steel removed from site to date
Source: publications from ESKOM
10
Empty Structure Post-demolition
Source: publications from ESKOM
Version: xx/201x/Tel
Rely on good experience with
The Engineers Company
Part 2
Design Activities
Design Team Setup
Design Approach
Boiler Re-engineering
Lessons Learnt
Conclusion
12
Design Team Setup
Source: publications from ESKOM
Eskom – Steinmüller Cooperation before project
• Acquisition of IP (manuals, tools)
• Training (classroom, on-the-job)
• Cooperation in various Eskom projects, e.g.
• Coal studies incl. thermodynamic modelling
• Low-NOx retrofit studies & design
• Boiler over-pressurisation root cause analysis and damage assessment
Architect Engineer
Design Authority
Pressure Parts &
Combustion Systems
Steam piping & LPS
Steel Structures
DimBo thermodynamic model
13
Design Approach
Source: publications from ESKOM
• Reuse of the main steel structure resulted in
requirement for “like-for-like” replacement.
• As close to original design as practical
• Maintain boiler load & load distribution
• Designed using TRD (original code) for the
boiler
• Modifications required due to
• Material availability
• Current emissions legislation
• Current fabrication & construction techniques
• Design methodology
• Redraw original drawings
• Compare to site as-built information
• Validate through calculations
• 3D modelling for clash detection
14
Boiler Re-engineering
Example for design modification data sheet
• A modification register was established and is
managed throughout design process.
• Modifications are evaluated based on
• Technical
• Financial
• Safety
• Environmental
• Operating
• Timing
• Number of modifications per system:
Source: publications from ESKOM
• The only plant changes are related to the
low NOx coal burners
30 Boiler pressure parts 16 Air and flue gas ducts
7 Boiler non-pressure parts 3 Oil and gas burners
7 Boiler process design 4 Coal burners
12 Structural elements
15
Boiler Re-engineering – Pressure Parts
Source: publications from ESKOM
Modification A3 Transition pieces helical wall - vertical
wall
Old design Transition was designed using individual
tube bends
Motivation Easier manufacturing and construction;
minimization of shrinkage and welds
New design Transition designed by forgings (1 helical
tube connects to 6 vertical tubes)
Modification A1 Flat ends of various headers
Old design Flat ends with relief groove
Motivation Negative experiences with this design.
New design regulations no longer allow
for high temperature services.
New design Flat ends without relief groove A1: Old flat
end designA1: New flat
end design
A3: Old transition piece
A3: New transition piece
16
Boiler Re-engineering – Ducting
3D model of air supply system
• 3D CAD model for duct design
• 2D drawings derived from 3D model
and detailed
• Old drawings used as reference
documents
Design modification of flue gas duct
(Attemporation no longer required) Source: publications from ESKOM
17
Boiler Re-engineering – Firing System
• New emissions limit: 750mg/Nm3 (10% O2)
by 2020
• Implementation of low-NOx firing system
• Replace old burners with SM V® Burners
• Burner designed to enable retrofit to remaining units at station
• Arrangement on furnace wall unchanged
• Burner internals incl. mixing elements changed
Source: publications from ESKOM
18
Boiler Re-engineering – PF Piping
• PF routing currently designed as “like-for-like”
• PF distribution not ideal for low-NOx burners
• PF modification proposed:
Dynamic classifier with 4 individual PF pipes
Source: publications from ESKOM
Old design New design
19
Boiler Re-engineering
• Main steel structure & primary steel
structure
• Repaired & reused
• New boiler loads evaluated in structure
design model
• Minor strengthening required due to new
loads
• Designed primarily using BS
• Secondary steel structure
• Complete replacement within 8 columns of
MSS
• Designed according to SANS
• Design for local material & profile sizes
• BS 4360 Grade 43A replaced with S355JR
Source: publications from ESKOM
20
Boiler Re-engineering – Steam Piping & LPS
• Steam piping (Eskom)
• Main steam, hot reheat, cold reheat,
sootblower piping & drains/vents
• Full detail design
• X20CrMoV 121 replaced with P92
(X10CrWMoVNb9-2)
• P92 results in reduced wall thickness
• Pipe stress analyses performed including
dynamic analyses.
• Higher flexibility required introduction of
additional shock absorbers
• Low Pressure Service (Eskom)
• Compressed air, fire protection, auxiliary
cooling
• Functional design
Source: publications from ESKOM
21
Design Challenges & Lessons Learnt
• Limited availability, accuracy & quality of
original drawings
• Differences between original design and as
built
• Incorporate operational lessons learnt
• Draughting in parallel to design calculations
expedited re-engineering, but calculations
often required drawing revisions
• Design rules well documented in Project
Design Manual
• “Like-for-like” approach agreed up front with
AIA, but still requires regular discussion to
agree on level of design verification and
assurance
• Original plan was to design on a like-for-like
approach. Together with the design
standards, material changes on a damaged
plant it turned out to a very challenging
brown-field project
Source: publications from ESKOM
Version: xx/201x/Tel
Rely on good experience with
The Engineers Company
Speaker : Armin Martz
Co-Speaker : Thomas Will
Questions