3rd Quarter Contractor Business Meeting

September 13, 2013

Yesika L. Castro-HernandezPlant Engineering

Facilities Session

Page 2: 3rd  Quarter  Contractor Business Meeting

2

Agenda

• Road Closures

• Vehicle Parking on Crane Travel Path

• Contractor Lifting & Handling Operations

• Storm Drain Protection

• Excavation Permits

• Foreign Exclusion Devices (FMEDs)

• Fuel Gas Hoses in Confined Spaces

• Ladder Safety

• Driving around JLGs and Forklifts

• Hot Work & High Visibility Vests

• Genie Boom Lift Recall

• Background Investigations

• Standard T&M Sheet

Page 3: 3rd  Quarter  Contractor Business Meeting

3

Road Closures

• Prior to closing a road you must notify your contractor coordinator. – This includes both full or partial road closures

• The Communication Center (757-380-4031) has to be notified prior to any road closure.

– They notify the fire department and security (O15)

• Base One (757-380-2461) must also be notified. – They notify emergency personnel such as:

• Water Tender, Emergency Electrician, and Spill Response Teams

• Attempt to always leave a lane or enough space open for emergency vehicles when performing a road closure.

Page 4: 3rd  Quarter  Contractor Business Meeting

4

Vehicle Parking on Crane Travel Path

• Do not park vehicles on the yellow travel path of cranes

• Material should not be delivered or stored on the travel path of the crane.

• Always be aware of the crane envelop.

Page 5: 3rd  Quarter  Contractor Business Meeting

Contractor L&H Operations - General Overview

Approved Safety Plan• L&H Section in Approved Safety Plan

Crane Operations• X36 Notification

• Certificate of Compliance -3rd Party Certification

• Operator Qualification – 29CFR1926.1427(a)

• AD Director

Rigger Qualification• 29CFR1926– “Qualified" means one who, by possession of a recognized degree,

certificate, or professional standing, or who by extensive knowledge, training, and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project

• Applies to both crane L&H operation and non-crane L&H operations

Page 6: 3rd  Quarter  Contractor Business Meeting

Lift Plans• Lift plans are required at NNS for all L&H operations, not just crane L&H operations.• Where can you get help with lift plans?

Rigging Gear

• 29CFR1926.251 - Rigging equipment for material handling shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe. Defective rigging equipment shall be removed from service.

• "Inspections." Each day before being used, the sling and all fastenings and attachments shall be inspected for damage or defects by a “competent person” designated by the employer.

• “Competent person" means one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.

• For Steel Erection - A qualified rigger (a rigger who is also a qualified person) shall inspect the rigging prior to each shift in accordance with § 1926.251.

Contractor L&H Operations

Page 7: 3rd  Quarter  Contractor Business Meeting

7

Contractor L&H Operations

• Hoisting Personnel – 29CFR1926.1431

• Only permitted when conventional methods for personnel access is more hazardous or  not possible.

– Total load on the lifting equipment must be 50% or less of the rated WLL of the lifting equipment crane in the radius and configuration to be used except for proof testing.

– Lifting equipment must have controlled load lowering.  No free fall permitted.

– Lifting equipment pre-lift operational check of required devices

– Personnel Platform requirements

– Rigging gear requirements

– Proof Testing

– Trail Lift and inspections

– “Competent” person responsibilities

• Working Under Suspended Loads– NNS does not allow personnel under suspended loads except where an hazard evaluation has determined that the

work cannot be performed in another manner or the alternate methods poses a greater hazard to personnel.  This non-allowance includes the exceptions noted in 29CFR1926.735.

– The evaluation, lift plan and a detailed rigging sketch for the lift must be reviewed and approved by both the responsible Field Engineer or Contract Coordinator and X36 L&H Engineering is required.  All information shall be at the lift site during the lift.

Page 8: 3rd  Quarter  Contractor Business Meeting

8

Contractor L&H Operations

L&H Accidents• Your responsibilities when a possible L&H accident occurs:

• Make the site safe (emergency response, etc). Do not disturb the site any more than necessary to make the site safe.

• Contact the Service Desk at 688-9888 and provide the requested information.

• Wait for the Accident Prevention Team (APT) to arrive on site.

• Follow the APT instructions.

Page 9: 3rd  Quarter  Contractor Business Meeting

9

Storm Drain Protection

• Straw bales cannot be used on construction sites at NNSB.

– A bundle of straw bales caught fire recently at DD12.

– The bundle of straw bales was being used to protect storm drains/sumps during construction operations.

• Alternate methods must be used:– Silt bags– Filter cloth

Page 10: 3rd  Quarter  Contractor Business Meeting

10

Excavation Permits

• Recent Excavation Permit Issues:– No signature for RadCon or O27.

• No E-mail confirmation.• E-mail must be placed with

excavation permit.– No Project Coordinator signature

approving work to commence.– No General Contractor signature. – No worker signatures on permits.

Page 11: 3rd  Quarter  Contractor Business Meeting

11

Foreign Exclusion Devices (FMEDs)

• FMEDs are available at the O46 conex box located east of the Leyte Boiler platform (North of B4613).

• Your coordinator must send a charge number to Steven Thomas [email protected] or 757-534-4093

• All piping shall come fromthe supplier with FMEDs.

• If supplier did not provideFMEDs then the contractormust place FMEDs on the material before it comes into the yard.

Page 12: 3rd  Quarter  Contractor Business Meeting

12

Fuel Gas Hoses in Confined Spaces

• Fuel gas and oxygen supply lines and torches. – Fuel and oxygen gas cylinders and distribution manifold systems can not be

located in enclosed or confined spaces. Maintain them in open areas. – All fuel gas and oxygen hose lines must be disconnected from the source at the

end of each shift.– All fuel gas and oxygen hose lines shall be rolled back to the supply manifold or to

open air prior to disconnecting the torch.– Fuel gas and oxygen hose lines shall not be used unless they have been drop

tested to ensure the integrity of the hoses. • Drop test needs to be preformed for at least sixty (60) seconds.

Page 13: 3rd  Quarter  Contractor Business Meeting

13

Fuel Gas Hoses in Confined Spaces

• Fuel gas and oxygen supply lines and torches. – No unattended fuel gas and oxygen hose lines or torches are to be located in

confined spaces.– H&SM, Vol II, Ch. 5

• A qualified Fire Watch, who has been fully instructed in emergency procedures, shall be stationed at the entrance to the confined space.

• The fire watch shall have a hose clamp loosely placed around the torch lines to be able to rapidly shut off the gases in an emergency.

• The fire watch shall not leave his/her station while the operator or his/her equipment remain inside the confined space.

• The Fire Watch shall be positioned to be able to observe or converse with torch operator.

Page 14: 3rd  Quarter  Contractor Business Meeting

14

Ladder Safety

• Inspect ladders prior to use. – Ensure rungs, and steps are in good condition and free of grease, oil, and dirt. – Ensure locking devices and non-skid safety feet are in place.

• Place ladders on a firm footing. Do not use or place a ladder on a slippery surface. • Maintain a 3-point contact. When ascending or descending a ladder, face the ladder and

maintain a 3-point contact.– Two hands and one foot or one hand and two feet.

• Ladders shall be secured by both side rails at the top to prevent displacement. • Ladders shall extend 3 feet above the landing surface. • Ladders shall be placed with a one to four ladder slope.

– The bottom of the ladder should be one foot away from the wall for every four feet that the ladder rises. When a ladder slope of one to four cannot be attained for ladders up to 12 feet in length, the bottom shall be secured.

• Do not stretch beyond the side rails. Doing so could cause the ladder to tip and fall. • Only one person is allowed on the ladder at one time. • Be observant for electrical wiring and third rails in the vicinity of where the ladder will be used.• A step ladder is a work platform:

– Never stand or sit on the top of a stepladder. Stepladders have a label that states, “do not stand above this step.”

Page 15: 3rd  Quarter  Contractor Business Meeting

15

Sound Horn Before Passing Equipment

• Recent near misses involving vehicles passing JLGs and forklifts with out warning.

• EH&S Manual Vol II, CH 13– Operators of vehicles must sound their horn

and pass on the left around JLGs, forklifts, scissor lifts, etc.

• O43 has begun installing decals on mobile equipment for drivers to sound their horn before passing.

Page 16: 3rd  Quarter  Contractor Business Meeting

16

Hot Work & High Visibility Vests

• Recently there have been observations of personnel performing hot work while wearing high visibility vests.

• These high visibility vests are made of 100% polyester.– Polyester when heated can melt and can adhere to the skin. – Use non-synthetic fabrics when performing hot work.

• Use proper PPE when performing hot work:– Based on your company’s PPE hazard assessment.

Page 17: 3rd  Quarter  Contractor Business Meeting

17

Genie Boom Lift Recall

• Z-135/70– The secondary boom angle sensor calibration was performed improperly.– An improperly calibrated machine can lead to machine instability resulting in a

machine tip over.– It is required the immediate removal of all Genie Z-135/70 Boom lifts from service.– Machines may only be returned to service after the inspection listed below is

performed.

Page 18: 3rd  Quarter  Contractor Business Meeting

O15 Security Background Investigations

• Huntington Ingalls Industries has recently awarded a contract for performing background investigations (BI) on our employees and visitors to General Information Services, Inc. (GIS), trading as “backgroundchecks.com”. With that award, GIS immediately becomes our preferred background investigation (BI) provider.

• O15 Security Contacts– Gabe Watlington – Security Manager: 757-688-5396– Natalie Joyner – Security Manager: 757-534-2308– Daryl Hagwood – Island of Security Officer: 757-688-2464

18

Page 19: 3rd  Quarter  Contractor Business Meeting

O15 Security Badge Process

The 9327 Process Is The Same:

• Visiting company (Contractors) conducts background investigation (BI) on their employee who will be badged to work at NNS

• Visiting company completes 9327 and delivers to NNS Sponsor in the same manner they have done in the past

• NNS Sponsor or NNS VMS user enters visit into VMS in the same manner they have done in the past

• NNS Sponsor or VMS user maintains 9327 (for the required period of time) as they have done in the past

• Visiting company maintain file of complete background investigation on employees as they have done in the past

19

Page 20: 3rd  Quarter  Contractor Business Meeting

O15 Security Badge Process

What’s New:

• Visiting company prints “certificate of BI completion” and turns in with 9327 (Rev 11) to NNS Sponsor  

• Visiting company employee brings copy of certificate of BI completion to Access Center when he/she is ready for NNS Contractors Badge. This is a one page document

NOTE: Visiting Company Employee Does Not Bring 9327 To Access CenterNOTE: Visiting Company Employee Does Not Bring Background Investigation To Access

Center

In order for the Access Center to process a visit and issue a badge: The visiting employee must have a current visit in VMS. The visiting employee must produce picture ID. The visiting employee must produce proof of citizenship. The visiting employee must produce the a copy of the certification of BI completion

20

Page 21: 3rd  Quarter  Contractor Business Meeting

21

Donor Information

SSN Date Ordered 08/31/2013

Last Name Who Ordered HAGWOODR01

First Name Date Completed 09/03/2013

Status Complete DOB

Control Number 48861555 Location DESIGN ENG SVCS PC

Action Services Ordered – Panel 12671

2905 – Education Verification Complete

2000 – Basic Employment Reference Complete ***

QUEST/QIS FIRST PAGE

Page 22: 3rd  Quarter  Contractor Business Meeting

VENDOR SAFE CERTIFICATE

22

Page 23: 3rd  Quarter  Contractor Business Meeting

23

Security Badge Process

• All BIs must be performed by the Huntington Ingalls Industries corporate award supplier, which is currently General Information Services, Inc., trading as backgroundchecks.com.

• A new BI is required for all unescorted badge visitors every three (3) years, and following any break in service in excess of 90 days, to re-verify criminal and DMV checks

Page 24: 3rd  Quarter  Contractor Business Meeting

24

NNS Standard Time-and-Material TicketOverview

• The NNS Standard Time-and-Material Ticket shall be used to document all T&M work performed on NNS contracts.

• A fully completed T&M ticket shall be submitted daily to the NNS Field Engineer daily.

• A blank Microsoft Excel 2007 formatted version will be provided to the Contractor by the coordinators.

• All fields must be completed prior to submittal to NNS.

• All subcontractor back-up must be attached to the T&M ticket.

Page 25: 3rd  Quarter  Contractor Business Meeting

25

QUESTIONS?

• If you have questions regarding this presentation, please contact your Contract Coordinator or:

Yesika Castro-Hernandez

O41 – Plant Engineering

757-353-2772

[email protected]