3rd Brazilian Congress on Tunnels and Underground ... · International Seminar "South American...
-
Upload
nguyenhanh -
Category
Documents
-
view
219 -
download
6
Transcript of 3rd Brazilian Congress on Tunnels and Underground ... · International Seminar "South American...
3rd Brazilian Congress on Tunnels and Underground Structures
International Seminar "South
American Tunnelling - SAT 2012“
Júlio César Bueno
The general rule: contractor’s liability If a contractor has promised - in unqualified terms - to construct a building or other structure for a lump sum price, no excuse for late performance or non-performance that the site conditions were worse than anticipated
– Agreed price is all that the contractor is entitled to
be paid for doing so
– The risk of adverse site conditions, whether they be known or latent, is with the contractor
The general rule: contractor’s liability US case law – United States v Spearin (1918), 248 U.S. 132 “Where one agrees to do, for a fixed sum, a thing
possible to be performed, he will not be excused or become entitled to additional compensation, because unforeseen difficulties are encountered. Thus, one who undertakes to erect a structure upon a particular site, ordinarily assumes the risk of subsidence of soil.”
UK case law – Bottoms v York Corporation (1892), Hudson Fourth
Edition, Vol 2 Table of Cases; Workshop Tarmacadam Co Ltd v Hannaby (1995) 66 Con LR 105, CA
The general rule: contractor’s liability If otherwise expected, contract should have an specific contractual release for the contractor
– Unless a contract makes specific provision for a
contractor to be entitled to an extension of time for completion, additional compensation, or both, in the event of adverse conditions being encountered, the risk of those conditions will remain with the contractor
– Clauses dealing with “force majeure” or
“exceptionally weather conditions” ARE NOT sufficiente as they ARE NOT to be considered the same as “unforeseen bad ground”
The general rule: contractor’s liability Enhancing the general rule’s application?
– Contractor has knowledge of the site – Contractor has inspected the site or “shall be
deemed to have inspected it” – Contractor has satisfied itself on the form and nature
of the site, including the soil and subsurface How far can these provisions go?
– Need to qualify reasonable knowledge or inspection – Was the contractor really able to get to know the
site, inspected it and to be satisfied?
A contract rule: risk with the owner
Many standard forms give contractors extension of time and price increase in case of unforeseen ground conditions
– ICE - Institute of Civil Engineers (clause 12)
– NEC - Engineering and Construction Contract (clause 60.1)
– FIDIC - International Federation of Consulting Engineers (clause 4.12, of the “new Red Book”)
A contract rule: risk with the owner In those standard forms, owner may be excluded from
liability when contractor “ought to have anticipated such conditions”
Such forms apply the concept of “imputed knowledge” in
opposition to “actual knowledge”
– What site investigations an experienced contractor ought to have conducted?
– What information an experienced contractor would have gleaned?
– How an experienced contractor ought to have interpreted the information?
A contract rule: risk with the owner
In contrast, some US State legislatures provides a baseline of expected ground conditions and seek potential distinctions only
– A “differing site condition” clause entitles the
contractor to additional time for completion and compensation
– No need for inquiry on what site conditions the contractor ought to have anticipated
1) Owner does not provide any information to contractor - “No Information System” 2) Owner provides information to contractor but does not
warrant the accuracy of such information – “Disclaimer System”
3) Owner provides information to contractor and warrants
the accuracy and/or the completeness of such information – “DSC System”
Disclaimer System
Some special considerations for public owners
– Stenerson v City of Kalispell, (1981) 629 P.2d 773 Mont.
“Public entity either knew or should have known that the information would be relied on by bidders”
Is it fair to make such distinction?
DSC System
The owner may find that shifting risk to the contractor is not in the owner’s best interest – In such a case, the owner may choose to accept the
risk of unforeseen site and subsurface conditions The owner may be taken to warranty contractually, either
expressly or by necessary implication, that the information provided to the contractor is accurate and should be followed – Bacal Construction (Midlands) Ltd v Northampton
Development Corporation (1975), 8 BLR 88, CA
DSC System
Type I DSC – Requires that there be an actual physical condition
encountered at the site that differs materially from the conditions indicated in the contract document
Type II DSC
– Requires a variance between the site condition actually encountered and that which would be reasonably expected at the time the contract was made
DSC System
The applicability of the Spearin Doctrine in the USA
– United States v Spearin (1918), 248 U.S. 132 “If the contractor is bound to build according to
plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. (...) This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work.”
DSC System
Confront with UK case law
– Under English law, an owner who provides plans or specifications to a contractor does not warrant that the work described in the plans and specifications is capable of being performed at all, or that is capable of being performed in a particular manner
– Thorn v The Mayor and Commonalty of London (1876), LR 1 HL 120
DSC System
Misrepresentation
– When erroneous information is provided to a tenderer, and the tenderer, in reliance upon it, enters into a building or engineering contract, there may be an actionable misrepresentation, sounding in damages
– Possible distinction between innocent misrepresentation (an erroneuous statment) and a fraudulentmisrepresentation
Ground’s elements and related risk types
Information
Interpretation (subjective)
Information (objective)
Incorrect Incomplete
Specific issues in Brazil
Importance of the management of the contract The day-by-day in opposition to the pacta sunt
servanda principle – Possible change in the allocation of
responsibility
Specific issues in Brazil The “theory of unpredictability” or “rebus sic stantibus clause” in the new Civil Code
– The absolute unpredictability concept
– Complete change in the conditions of the contract
– Extreme burdensome
– A clear benefit to the other party
Specific issues in Brazil
Continuous obligation of the parties to mitigate the risks during the contract
Simply allocation of risk does not prevent the
application of good-faith rules
Alianza
VALE
Contratado
Engineering
Procurement
Construction
VALE
Contratado2
Procurement
Engineering
Construction
Contratado1
VALE
Contratado2
Procurement
Engineering
Construction
Contratado1
VALE EPCMProcurement
Engineering
Construction
VALE Contratado Procurement
Engineering
Construction
DBB
EPCM
Split EPC EPC
O QUE É UMA ALIANÇA?
Conclusions
Ground Risks, in the form of unforeseen geological and/or geotechnical conditions, are a serious factor in cost and schedule control on all major civil engineering projects
The amounts of money, involved in claims arising from
these geotechnical problems, is enormous and needs to be taken very seriously by financing agencies and all players in the construction industry
Conclusions
Inadequate site investigations rank as one of the major contributors to ground risk.
More realistic allocations of time and money have to be
made to these site investigation programs It is also important that geologists and geotechnical
engineers make more efficient use of the resources allocated for site investigation
Júlio César Bueno LL.M (Cantab) Ph.D (USP) Pinheiro Neto Advogados Rua Hungria, 1.100 São Paulo - SP 01455-000 Brazil Tel: +55 (11) 3247-8667 Fax: +55 (11) 3247-8600 E-mail: [email protected]
Contact information