3D Engineered Models for Construction Part I - Introduction September 2012 Part 1 Introduction1.
-
Upload
skyla-perren -
Category
Documents
-
view
216 -
download
0
Transcript of 3D Engineered Models for Construction Part I - Introduction September 2012 Part 1 Introduction1.
1
3D Engineered Models for Construction
Part I - Introduction
September 2012
Part 1 Introduction
2
What is 3D Modeling?
• Using a collection of intelligent computer objects that represent an original surface, in our case the design surface of a highway segment.
• The objects know their position in space and in some cases what they represent.
Part 1 Introduction
3
To better understand the design and locate possible conflicts and/or errors in the design.
Why 3D Modeling?
Part 1 Introduction
4Part 1 Introduction
Courtesy of Iowa DOT
3D Transportation Model
5Part 1 Introduction
Another 3D Model
Courtesy of Iowa DOT
Courtesy of Iowa DOT
3D Cartesian Coordinates
Part 1 Introduction Graphic courtesy of Curtis Clabaugh, WYDOT
Mapping Capabilities
Part 1 Introduction Graphic courtesy of Curtis Clabaugh ,WYDOT
8
A High Level Benefit of 3D Modeling• Improves communication between the owner,
consultant, contractor, prefabricators, and materials suppliers
Part 1 IntroductionImage courtesy of FHWA
9
• Easier to get stakeholder buy in• Identify possible errors before construction• Visualize subgrade and potential utility conflicts• Benefits to highway construction are similar to
those realized in Building Information Modeling (BIM)
Part 1 Introduction
What are Some General Benefits?
10
Virtual construction to assess issues and improve communication prior to breaking ground!
Part 1 Introduction
Top Benefits for Owners
• Grade check 100% of constructed surface
• Locate as-built utilities on the fly• Improved industry perception• Material cost savings
Photo courtesy of FHWA
11Part 1 Introduction
Top Benefits for Contractors• Save labor of setting string
line (paving) or stakes (grading)
• Stringless paving may limit need for traffic closures
• Increased productivity• Increased efficiency• Reduced labor costs
Photo courtesy of FHWA
12Part 1 Introduction
Top Benefits for A/E Firms
• Identification of potential constructability issues earlier in the design process
• Better value to clients• Improved accuracy in design• Visual model verification
provides design QC
Image courtesy of FHWA
13Part 1 Introduction
Leaders in the Use of 3D Modeling
• Wisconsin DOT• Iowa DOT• North Carolina DOT• Caltrans• Land developers• Design-builders
14
3D Engineered Models are a Building Block of the Digital Jobsite
Part 1 Introduction
Other Functions 3D Models Support
• Public outreach/marketing for projects• Utilities – coordination and early issue
identification• 3D mapping and data storage• Clash detection• Earthwork quantities
15Part 1 Introduction
Challenges to Implementation
• Time investment from 2D to 3D
• Project selection – what characteristics to look for
• Coordination across key stakeholders (contractor, owner, designers, suppliers, etc.)
16
• Where does “designing” stop and where does “detailing” begin?
• What becomes the legal record of the design?• Can a 3D model be part of the contract documents?• Can electronic plans legally represent the design?
Part 1 Introduction
What Challenges Need Consideration?
17
Project Development Considerations
Part 1 Introduction
18
3D modeling allows the existing and proposed features to be seen geospatially.
Part 1 Introduction
Plans and Evolution
• 2D plans with profile andcross-section
• 3D plans, electronic data files, and digital terrain models
19
Using a 3D model, we now have the capability to design and build accurately everywhere.
Part 1 Introduction
Limitations of 2D Plans in Construction
• Human error in reading plans• Conflicts are not readily apparent• No surfaces, just cross-sections• We traditionally design and build accurately
only at cross-sections
20
Who
Complete Designin 3D from
Road Owner
2D DrawingsDOT Generates
2D drawings
Designin 2D from
Road Owner2D Drawings
ContractorCreation of3D Modelfor AMG
Surveying
StructuralRoad
Requirements(size, location,
ESAL, etc)& Prioritization
3D Model
Contractor Utilizes3D Model for AMG
DOT / Government Contractor
2D DataTransfer
3D DataTransfer
Several years old,
sometimes
Key Stakeholders and Process Elements
Part 1 Introduction
21
• Develop incremental detail of a virtual model by working continuously in a 3D environment
• Extract the traditional 2D contract plans and bid item quantities from the 3D design model
• Export 3D data files for construction and use of technology applications in the field
Part 1 Introduction
How is the Workflow Different from 2D to 3D?
22
• A data package can be developed from the 3D model to support Automated Machine Guidance/Automated Machine Control“Plug and Play” equivalent once package is input to machine
Part 1 Introduction
What Activities Can the Model Support?
23
• A process where design software and construction equipment are linked to direct the operation of machinery with a high level of precision, improving the speed and accuracy of the construction process.
Part 1 Introduction
What is Automated Machine Guidance (AMG)?
24Part 1 Introduction
Bulldozer Using AMG
Photo courtesy of David White , Iowa State University
25Part 1 Introduction
Courtesy of Iowa DOT
What the Machine Sees
26
• Stakes
• String Lines
• String Lines with Sensors
• Lasers
• GPS
• Total Stations
Types of Guidance Systems(Guidance Systems Evolution)
Part 1 IntroductionPhotos courtesy of FHWA
27
• Provides visual guide/grade information
• Stakes set by surveyor
• Field personnel read stakes and guide machine operator
Using Stakes – Traditional Method
Part 1 Introduction
Photo courtesy of FHWA
28
• Allows for machine control along a non-level surface
• Line represents a design surface at a particular elevation
Using String Lines – Traditional Method
Part 1 Introduction
Photo courtesy of FHWA
29
• Lasers are used for elevations
• A light bar on the cutting edge of a grader allows for up/down positioning
• GPS can be used to determine X-Y coordinates and pinpoint a location
• Users need different accuracies (we need “survey” level accuracy for highway projects compared with lower accuracy for recreational use or mapping)
Using Lasers/GPS
Part 1 Introduction
30
Scrapers, dozers, excavators, motor graders, milling machines, pavers
Automated Machine Control Applications
Part 1 IntroductionPhotos courtesy of David White, Iowa State University
31
Earthworks
Part 1 Introduction
Photo courtesy of David White, Iowa State University
32Courtesy of Ed Jaselskis
Typical Concrete Paving Using AMG
Part 1 Introduction
33Part 1 Introduction
Typical Asphalt Paving Using AMG
Photo courtesy of David White, Iowa State University
34
Grading
Part 1 Introduction
Photo courtesy of David White, Iowa State University
35
Case Study Colorado I-70 Project
Part 1 Introduction
36
Colorado DOT I-70: The Problem
• Expansive Soils Severe longitudinal undulations, rough ride, cracking
• Widely varying asphalt depths – average 15”
• Traditional mill/fill: consistent mill depth would maintain existing profile
Part 1 Introduction
Photo courtesy of FHWA
37
CDOT I-70: The Process
• No initial CDOT survey Contractor survey
• Specs allowed for AMG for milling
• Short timeline GPS survey – 5 passes at 25’ EB/WB
• CDOT used MicroStation InRoads optimization to create 3D model with milling depths to balance humps and dips
Part 1 Introduction
Photo courtesy of FHWA
38
CDOT I-70: The Project
• Concrete “Whitetopping” pavement design required 8” minimum asphalt for 6” concrete
• Full depth 9 ¼” concrete where < 8” asphalt remains after milling
Part 1 Introduction
Photo courtesy of FHWA
39
CDOT I-70: AMG Milling
• Robotic Total Station – 600’ intervals• Milling machine – automatically directed mill depth• Contractor’s surveyor performed independent check on original
and milled surface
Part 1 IntroductionPhoto courtesy of FHWA
40
CDOT I-70: AMG Milling (cont’d)
• Operation manually monitored
• Screen reports deviation from pre-set milled elevation
• Track height adjusted automatically to meet milled surface profile
Part 1 Introduction Photos courtesy of FHWA
41
CDOT I-70: AMG Milling (cont’d)
• Greatly variable milling depths
Part 1 IntroductionPhoto courtesy of FHWA
Image courtesy of FHWA
42
CDOT I-70: Lessons Learned
• Colorado DOT– Better knowledge of technology prior to plan
preparation– Need survey control by owner during construction– More accurate initial survey – tie in boundaries
• Contractor– There should only be one 3D model– Boundaries were a problem – even in rural setting– 8% allowable concrete overrun is very tight– CDOT survey (pre-bid) more competitive bids
Part 1 Introduction
43
Benefits – Quality Assurance, Cost Savings, and Schedule Savings
Part 1 Introduction
44
Quality Assurance Without 3D Modeling
Part 1 Introduction
Photo courtesy of FHWA
45
Quality Assurance With 3D Modeling
Part 1 Introduction
Photo courtesy of David White, Iowa State University
46
Who
Complete Designin 3D from
Road Owner
2D DrawingsDOT Generates
2D drawings
Designin 2D from
Road Owner2D Drawings
ContractorCreation of3D Modelfor AMG
Surveying
StructuralRoad
Requirements(size, location,
ESAL, etc)& Prioritization
3D Model
Contractor Utilizes3D Model for AMG
DOT / Government Contractor
2D DataTransfer
3D DataTransfer
Several years old,
sometimes
Data Transfer: Benefits, Procedures, and Challenges
Part 1 Introduction
47
Trans XML
Autodesk
Bentley
Carlson
Trimble
Topcon
Leica
Preferred Import/Export Capabilities
Part 1 Introduction
48
Leica
Trimble
Topcon
Autodesk
Bentley
Carlson
Another Import/Export Scheme
Part 1 Introduction
49
Perceived AMG Benefits – Phase I Survey
Perceived AMG Benefits* Contractor Agency P/C Equipment Vendors
Labor savings (direct cost on projects) 96% 76% 80%
Environmental-Fuel savings N/A 36% 60%
Project schedule compression 86% 57% 93%
Avoidance of re-work (re-grading) 93% 60% 87%
As-built documentation 58% 57% 80%
Ease of constructability review 44% 49% 73%Jobsite safety 68% 44% 60%Safety of the traveling public N/A 31% 40%* Percentage of respondents choosing the benefit at the two highest risk levels
Part 1 Introduction
Source: NCHRP 10-77
50
Productivity Impacts
Productivity Gain Using AMG (%)
10 20 30 40 50
Fre
quen
cy
0
2
4
6
8
10
12
ContractorsVendors
Cost Savings Using AMG (%)
10 20 30 40 50
Fre
quen
cy
0
2
4
6
8
10
12
ContractorsVendors
>50
Ultrasonic12D Laser1
3D Laser1/GPS1 (89 to
101%)
Ultrasonic1 2D Laser1 3D Laser1
GPS1
GPS2
Notes: 1Fine-grading using CAT 140H motor grader (Jonasson et al., 2002) 2Trench excavation using CAT 330DL hydraulic excavator (Aðalsteinsson, 2008) 3Earth moving and fine grading (general values; not project specific) (Forrestel, 2007) 4Earth moving and fine grading project - Port of Brisbane (Higgins, 2009)
Notes: 1Fine-grading using CAT 140H motor grader - Overall unit cost (Jonasson et al., 2002) 2Earth moving and fine grading project - Port of Brisbane (overal cost savings) (Higgins, 2009)
GPS3GPS4
GPS2
GPS7
(265%)
5Bulk earth moving and subgrade fine grading using CAT D6N dozer (gain in the number of passes; Caterpillar, 2006)6Bulk earth moving using CAT 330D excavator (Caterpillar, 2006)7Base course fine grading using CAT 140H motorgrader (gain the number of passes; Caterpillar, 2006)
GPS6
GPS3
3Bulk earth moving using CAT 330D excavator - fuel cost savings (Caterpillar, 2006)4Bulk earth moving and fine grading using CAT D6N dozer - fuel cost savings (Caterpillar, 2006)5Fine grading using 140H motorgrader - fuel cost savings (Caterpillar, 2006)
GPS4
GPS5 (68%)
>50
GPS5
(107%)
Part 1 IntroductionSource: NCHRP 10-77
51
McGraw Hill Smart Market Report – The Business Value of BIMImplementation of GPS Controlled Highway Construction Equipment
(Vonderohe, University of Wisconsin)AASHTO AMG Quick Reference GuideNCHRP 10-77
Part 1 Introduction
Additional Resources
52
• 3D Modeling can provide for increased efficiencies in projects by providing an intuitive user interface, identifying potential issues early on, and linking to cost effective construction methods such as AMG.
• Session II will focus on the application of these practices and components, along with challenges and project selection criteria.
Part 1 Introduction
Summary
53
Charles Jahren, [email protected]
Douglas Townes, [email protected]
Chris Schneider, [email protected]
Questions?
Part 1 Introduction