36th Safety Committee Meeting - draft 28-3-13 new
-
Upload
emad-salem -
Category
Documents
-
view
433 -
download
0
Transcript of 36th Safety Committee Meeting - draft 28-3-13 new
![Page 1: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/1.jpg)
Safety Talk : ACCESS SHAFT Climbing shutter
By: Emad Salem
![Page 2: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/2.jpg)
Items to be discussed1.Introduction
2.Sequence of the works
3.Safety precautions/Risk Assessments
4.Method Statement
5.Lesson learned from T02
![Page 3: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/3.jpg)
Introduction :- This presentation is to present the sequence of
Constructing SIX meter diameter climbing support
structure (used on all the blocks but Block 1): this will
consist of a frame with a system of 8Nos. “klik-klak”
brackets to anchor the formwork to the wall and support
it. The structure will be completed with two platforms
(top and bottom platform) at two different levels. The use
and lifting of the formwork will be one of the key aspects
to be managed and strictly controlled during construction
as it could potentially create severe Health and Safety
Hazards.
In particular, the structural failure of a single component
of the formwork might trigger the collapse of the entire
system with significant falls from height and serious
consequences.
![Page 4: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/4.jpg)
Sequence of the works:-
1.Surface preparation for construction joints between base slab and block n0.1.
2.Shaft survey as built and chipping SCL if necessary.
3.Geo textiles installations as separation later between CPL and Diagram wall
4.Block No.1 Rebar works.
5.RMD shutter panels preparation with the platform and inspections,
Lowering/Aligned in the passions by inclined jacks and anchor with the base slab.
6.Lowering Membrane and tightening
7.Installing the water stop between Block 1 and Block 2
8.Survey and QC inspection, then casting
9.Installed the injection hose between Block number No.1 AND No. 2
![Page 5: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/5.jpg)
Sequence of the works:-
10.Installed the rebar for block number 2
11.Dismantling Block No 1 shutter and lifting up to surface
12.Lowering frame structure with “klik-klak” resting on block 1 , 8 no shear pockets.
13. Lowering shutter panels fixed with the frame structure .
14. Setting out the shutter to the pouring position using turn buckle jacks and pouring.
15.Repeat point Item no. 6 to 9 with filler board between movement joints.
16.After concrete strength reach 20 mpa, close the shutter to the lifting position .
17.Lift up the shutter to the next block and repeat the same sequence each block.
18.After lifting each block ,grouting injection hoses ,casting previous shear pockets
and membrane joints welding.
![Page 6: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/6.jpg)
Surface preparation for construction joints between base slab and block n0.1.
![Page 7: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/7.jpg)
Shaft survey as built
![Page 8: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/8.jpg)
Geo textiles installations as separation later between CPL and Diagram wall
![Page 9: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/9.jpg)
Block No.1 Rebar works
![Page 10: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/10.jpg)
RMD shutter panels preparation with the platform and inspections, Lowering/Aligned in the passions by inclined jacks and anchor with
the base slab .
![Page 11: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/11.jpg)
Lowering Membrane and tightening
![Page 12: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/12.jpg)
Survey and QC inspection, then casting
![Page 13: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/13.jpg)
Installed the injection hose between Blocks
![Page 14: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/14.jpg)
Install the rebar for block number 2
![Page 15: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/15.jpg)
Lowering frame structure with “klik-klak” resting on block 1 , 8 no shear pockets.
![Page 16: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/16.jpg)
Setting out the shutter to the pouring position using turn buckle jacks and pouring .
![Page 17: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/17.jpg)
Lift up the shutter to the next block and repeat the same sequence each block.
![Page 18: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/18.jpg)
After lifting each block ,grouting injection hoses ,casting previous shear pockets and membrane joints welding.
![Page 19: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/19.jpg)
Safety precautions/Risk Assessments
![Page 20: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/20.jpg)
Safety precautions/Risk Assessments
![Page 21: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/21.jpg)
Safety precautions/Risk Assessments
![Page 22: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/22.jpg)
Safety precautions/Risk Assessments
![Page 23: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/23.jpg)
Safety precautions/Risk Assessments
![Page 24: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/24.jpg)
Safety precautions/Risk Assessments
![Page 25: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/25.jpg)
Safety precautions/Risk Assessments
![Page 26: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/26.jpg)
Safety precautions/Risk Assessments
![Page 27: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/27.jpg)
Safety precautions/Risk Assessments
![Page 28: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/28.jpg)
Safety precautions/Risk Assessments
![Page 29: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/29.jpg)
Lesson learned from T02
1.Full body harness must be used all the times while working on the shutter.
Setting out the climbing
2.Shutter must be surveyed before and after casting from minimum 8 points
from the centres.
3.All jacks must be proper tightening and secured .
4.Membrane sheets must be tensioned equally and checked from all the sides
and ensure for not air pockets.
![Page 30: 36th Safety Committee Meeting - draft 28-3-13 new](https://reader035.fdocuments.us/reader035/viewer/2022070512/589df1661a28ab773b8b70e1/html5/thumbnails/30.jpg)
AnyQuestions..?
Thank you