Prepare the following tools before the installation:
Installing the Cabinet�Installing the Cabinet on the Rack of Storage Batteries
According to actual conditions, use one of the following modes to install the cabinet: installing the cabinet on the rack of storage batteries, installing the cabinet on the ground, installing the cabinet on the 19-inch open rack, installing the cabinet on the BTS cabinet. The cabinet must be installed at the place which no more than 3m distance from the DC load.
Move the cabinet to the installation position on the rack of storage batteries.1
Align the expansion bolt holes on the base in the front of the cabinet with the installation holes for the bolt holes on the rack of storage batteries.
23
Install the rack-mounting ears to the cabinet.
Socket wrench Torque wrench
Installing the Cabinet on the Rack of Storage Batteries Directly
According to actual conditions, use one of the following modes to install the cabinet: installing the cabinet on the rack of storage batteries directly, installing the cabinet on the rack of storage batteries using conversion board.
Ф12 drill bitFlat-head screwdriver
(M3M4) Adjustable wrench
Key to cabinet
Percussion drill
Wire stripper Ratchet crimp tool Diagonal pliers Paint brush
Nylon tie
Multimeter
Insulating tape Marking pen Vacuum cleaner Hydraulic pliers Insulating handle Electric knife
Heat gun
Phillips screwdriver (M3M4)
A-shaped ladder (2 m)
Rack-mounting ears
Operation side
1
�
Fix the bolts into the holes and fasten the bolts.4
Installing the Cabinet on the Conversion Board
Install the conversion board on the rack of storage batteries.
1
2
Install the rack-mounting ears to the cabinet.
NOTE The layout of installation holes on the rack of storage bat-teries varies with the rack model. Align the first bolt hole on the base with the bolt hole on the storage rack, and then install other bolts in the proper holes.
Ф8×20 mm (4pcs)
1 2
Ф10×25 mm (4pcs)
Rack-mounting ears
Operation side
�
Installing the Cabinet on the Ground
单位:mm确认机柜安装位置,用粉笔标出打孔位置。
Determine the installation position of the cabinet, and then mark the positions of the holes to be drilled with a marking pen.1
Ф8×20 mm (4pcs)
Align the expansion bolt holes on the base in the front of the cabinet with the installation holes for the bolt holes on the conversion board.
3
Fix the bolts into the holes and fasten the bolts.4
Unit: mm
Cabinet outline
316
450
Installation hole4- 10
1 2
Ф10×25 mm (4pcs)
Rack-mounting ears
Operation side
�
单位:mm确认机柜安装位置,用粉笔标出打孔位置。
Drill holes at the hole positions, feed expansion bolts into the holes, and then secure (hammer and then tighten) the expansion bolts.
2
Install the rack-mounting ears to the cabinet. Place the cabinet on the expansion bolts, and then tighten the bolts.3
Unit:mm
52-60
12
Ф8×60 mm (4pcs)
NutSpring washer
Flat washer
Expansion tubeExpansion trough
Cone-head bolt
Installation hole
Rack-mounting ears
�
Installing the Cabinet on the 19-inch Open Rack (IMU)
单位:mm确认机柜安装位置,用粉笔标出打孔位置。
Fix the rack-mounting ears into the bolt holes at both sides of the cabinet. Ensure that the base of the rack-mounting ears. install direction faces the front of the cabinet
1
Determine the installation position of the cabinet on the 19-inch open rack, and then install the Ф6 floating nuts at the holes for bolts. The recommended installation height of the cabinet is 1.5 m. The actual installation height of the cabinet must be determined according to the stature of installation personnel and installation requirements.
2
Floating nut
3
Side of the cabinet
2
�
单位:mm确认机柜安装位置,用粉笔标出打孔位置。
Move the cabinet to the installation position of the 19-inch open rack, and then install the cabinet on the open rack.4
CAUTIONA minimum of three persons are required for safe installation on the 19-inch open rack.Otherwise, the cabinet may fall and cause injury.
Ф6×12 mm (4pcs)
3
�
Installing the Cabinet on the BTS Cabinet1
Install the conversion board on BTS cabinet.2Install the rack-mounting ears to the cabinet.
Align the expansion bolt holes on the base in the front of the cabinet with the installation holes for the bolt holes on the conversion board.
3
Fix the bolts into the holes and fasten the bolts.4
1
Rack-mounting ears
Operation side
2
Ф10×25 mm (2pcs)
Ф6×12 mm (4pcs)
Ф6×12 mm (4pcs)
�
Installing Sensor � Installing indoor temperature and humidity sensor.1
Indoor temperature and humidity sensor
Indoor temperature and humidity sensor
Main equipment
60 m
m
M4 X 35Expansion Bolt Shelter
Installing battery temperature sensor.2
Connect to battery
Connect to TP48300A
�
Installing the PGND Cables� Unlock and open the cabinet door, and then remove the cover plate of the cable window on the top of the cabinet.1
Lead the PGND cables into the cabinet through the cable window, and then route the cables along the panels of the cabinet.2
DC output positive wiring busbar
Load power-off MCB Transfer copper bar
Monitoring module
Negative pole of the battery
The protection MCB on the battery
AC input MCB
Rectifier module Earthing busbar of the cabinetAC surge protector
DC output positive wiring busbar
Load power-off fuse Transfer copper bar
Monitoring module
Negative pole of the battery
The protection MCB on the battery
AC input MCB
Rectifier module Earthing busbar of the cabinetAC surge protector
Cover plate
NOTE Please installing the cabinet according to actual conditions: load power-off tributary using fuse, load power-off tributary using MCB.
Load power-off tributary using fuse
Load power-off tributary using MCB
�0
Connect the PGND cables to the earthing busbar.3
Bind the PGND cables.4
4
4
33
The earthing busbar
Use an insulating handle to remove battery fuses and load power-off fuses.5
Use an insulating handle to remove battery fuses and set the load power-off MCB to OFF .
CAUTIONThe PGND cables, AC cables, DC cables, signal cables, and communication cables must be bound separately.
4
4
33
The earthing busbar
Load power-off tributary using fuse
Load power-off tributary using MCB
Load power-off tributary using fuse
Load power-off tributary using MCB
��
Lead the dry contact signal cables and communication cables into the cabinet through the cable window, and then route the cables along the panels of the cabinet.
1
According to the actual installation requirements, use a flat-head screwdriver to prop up the white contact plates to have the metal dome sheets in the ports spring up. Insert the dry contact signal cable into the dry contact points, and pull out the screwdriver to fasten the signal cable.
2
Installing the Dry Contact Signal Cables and Communication Cables (Optional)�
NOTE1. The use of the dry contact signal cables and communication cables is scenario-specific.According to actual requirements, determine the dry contact signal cables and communication cables to be installed before installation.2. Functions of dry contact points.
J13, J14, J4-J10 are nine dry contact sockets on the monitoring back plane. Status, Status1, Status2 are three circuits for the input of the detection signals of the diesel generator. Ctrl1 and Ctrl2 are two circuits for the output of the control signals of the diesel generator. ALM1-ALM7 are seven circuits for the output of the alarm signals of the diesel generator. Each circle represents the corresponding wiring terminal. The black circles are the common terminals of the constant-enabled ports and constant-disabled ports on the relays.NC represents constant-disabled port and NO represents constant-enabled port.By default, the output of the dry contact is set to OFF.
White contact plate
Dry contact point
1 2
Alarm Type Default Function DescriptionAC power-off alarm
DC input overvoltage and undervoltage
Power supply system fault alarm
Surge protector failure alarm
Fuse disconnection alarm
Battery protection
Standby dry contact output 1
Control for the diesel generator 1
Control for the diesel generator 2Detection for the runningstatus of the diesel generatorDetection for the start/stopcontrol signals of diesel generator 1Detection for the start/stopcontrol signals of diesel generator 2
AC input power-cut alarm port (AC Fail)
DC input undervoltage alarm port (DC Low)
Rectifier module fault alarm port (PSU Fail)
Surge protector alarm port (SPD Fail)
Fuse disconnection alarm port (Fuse Alarm)
Battery low-voltage isolation disconnection alarm port (Batt.LVD)
Reserved dry contact 1 (Reserve 1)
Port for starting and stopping the Generator 1
Port for detecting the running status of the diesel generator
Port for starting and stopping the Generator 2
Port for detecting the start.stop signals of diesel generator 1
Port for detecting the start.stop signals of diesel generator 2
ALM1
ALM2
ALM3
ALM4
ALM5
ALM6
ALM7
Ctrl1
Ctrl2
Status
Status1
Status2
12
��
According to the actual installation requirements, insert the communication cables into the RJ45 ports on the monitoring backplane.
3
Bind the dry contact signal cables and communication cables on the cable window separately, and then route all the cables to the distribution frame.
5
Installing the DC Output Cables� Insert the –48 V DC output cable into the output port on the battery protection MCB.1
Loosen the bolt on the top of the load power-off fuse, connect the –48 V output cable to the bolt, use torque wrench to tighten the bolt, force moment as 10 Nm.
2
Connect the 0 V output cable to the DC output positive wiring busbar.3
Bind the DC output cables on the cable window. Ensure that the DC output cables are separated from other cables.4
Load power-off tributary using fuse
DC output distribution can be customized.
Load power-off tributary using fuse
Communication cable
12
According to the actual installation requirements, Insert the temperature and humidity sensor signal cable and battery temperature sensor signal cable.
4
Indoor temperature and humidity sensor
Battery temperature sensor
��
Insert the –48 V DC output cable into the output port on the battery protection MCB.1
Connect the 0 V output cable to the DC output positive wiring busbar.2
Bind the DC output cables on the cable window. Ensure that the DC output cables are separated from other cables.3
Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using MCB
1
2
CAUTION1. The force moment of tightening the bolt must less than 10 Nm.2. The signal cables must be installed in the front of the –48 V cables.
1
2
3
��
Loosen the bolt on the top of the base of the battery negative-pole access fuse, connect the –48 V input cables to the bolt, and use torque wrench to tighten the bolt, force moment as 10 Nm.
2
Connect the of the storage battery to the DC output positive wiring busbar.1
Arrange the output cables, and then use a nylon bundling tape to bind the cables to the bundling tie at the rear of the cable window.
3
Installing the Power Cables of the Storage Battery� Load power-off tributary using fuse
Loosen the bolt on the top of the base of the battery negative-pole access fuse, connect the –48 V input cables to the bolt, and use torque wrench to tighten the bolt, force moment as 10 Nm.
2
Connect the of the storage battery to the DC output positive wiring busbar.1
Arrange the output cables, and then use a nylon bundling tape to bind the cables to the bundling tie at the rear of the cable window.
3
Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using fuse
Load power-off tributary using fuse机柜负载下电支路采用熔丝Load power-off tributary using MCB
1 2
BF1- BF2-
Battery negative-pole
Battery positive-pole
CAUTION1. Ensure that the signal cables are installed in the front of the battery negative-pole input cable and that the battery protection MCB is set to OFF.2. When installing a fuse for the load storage batteries, ensure that the bare metal part of the screwdriver does not touch the positive bus and the fuse wiring terminal, otherwise a short circuit may be caused.3. The force moment of tightening the bolt must less than 10 Nm.4. If only one group of batteries is connected ,it should be connected to BF1.
CAUTION1. Ensure that the signal cables are installed in the front of the battery negative-pole input cable and that the battery protection MCB is set to OFF.2. When installing a fuse for the load storage batteries, ensure that the bare metal part of the screwdriver does not touch the positive bus and the fuse wiring terminal, otherwise a short circuit may be caused.3.The force moment of tightening the bolt must less than 10 Nm4. If only one group of batteries is connected ,it should be connected to BF1.
1 2
BF1 BF2BF1- BF2-
Battery negative-pole
Battery positive-pole
��
The cabinet supports the single-phase and three-phase AC input cables, which must be installed in different ways.Mode 1: To install the single-phase AC input lines, perform the following steps:a) Connect the neutral line to the N-terminal.b) Install the copper bar on the AC input MCB. c) Connect live line to the copper bar.
1
Mode 2: To install the three-phase AC input lines, perform the following steps:a) Connect the neutral line to the N-terminal.b) Connect the U-phase, V-phase, and W-phase lines to the AC input MCB.
机柜负载下电支路采用熔丝AC input MCB using 3-pole MCB
机柜负载下电支路采用熔丝AC input MCB using 4-pole MCBTo install the three-phase AC input lines, perform the following steps: Connect the N-phase, U-phase, V-phase, and W-phase lines to the AC input MCB.
U V W N
a cb
Input copper bar Live lineNeutral line
N-terminal
ba
Neutral line
N-terminal
Installing the AC Input Cables�
��
Checks After the Installation� Ensure that the cabinet and cables are secure.1
According to the connecting diagram, ensure that the cables are installed properly by sight or with a multimeter and that the live line, earth line, and neutral line are not short-circuited.Ensure that the 0 V cable and –48 V cable are not short-circuited.
2
Insert the removed fuses into the corresponding positions.3
1 2
电池正极
电池负极
BF1 BF2BF1- BF2-
Scenario1: load power-off tributary using fuse.
Ensure that the AC input MCB and battery power-off MCB is set to ON.Check whether the MCBs and fuses are not dam-aged with a multimeter and replace the damaged MCBs or fuses.
4
Ensure that the cabinet door is closed and locked.6
Check whether paint on the surface of the cabinet is improper and repaint the surface of the cabinet where paint falls off.7
Cut the cover plate of the cable window on the top of the cabinet according to the cabling conditions, and then place the cover plate back to its original position.
5
1 2
电池正极
电池负极
BF1- BF2-
Scenario2: load power-off tributary using MCB.
Install the plastic protection plate.2
Bind the AC input cable to the nearest bundling tie.3
2 3
Plastic protection plate
��
Cabling guide�
-
-
+
+
-
+
-
+
-
+
-
-
+
-
+
The power cable of the storage batteryDC output cablePGND cableAC input cableDry contact signal cable
1
2
34
5
Battery temperature sensor6 Temperature and humidity sensor signal cable7
3
76
3
4
4 5
62
5
1
2
The scenario with Cabling Rack
NOTEThe AC input cables and signal cables must be bound and routed separately.
1
a
a
b
c
cCutaway view:
CableRack Rack Rack
Cable Cable Cable
b
1
7
��
The scenario without Cabling Rack
-
-
+
+
-
+
-
+
- +
- 1
2
2
34
34
5
76
561
2
34
5
6
7
The power cable of the storage batteryDC output cablePGND cableAC input cableDry contact signal cable
Battery temperature sensorTemperature and humidity sensor signal cable
-
+
-
+
NOTEThe AC input cables and signal cables must be bound and routed separately.
1
a
a
b
c
cCutaway view:
b
17
CableRack Rack Rack
Cable Cable Cable
��
Power-on Testing�0
Set the parameters:
a Conducting a power-on test
b Setting the monitoring system
Power on TP48300/A power system.
Group and capacity of batteries.1
Temp Alarm.2
time and date.3
NOTE1. The position of the CPMU01 monitoring module, operating keyboard, and status indicator are shown in the following figure.2. When the TP48300/A power system is working properly and communicate with the main equipment, the ALM indicator on the CPMU01 does not light and the RUN flash slowly. When the TP48300/A power system is working properly and the TP48300/A power system does not communicate with the main equipment, the ALM indicator on the CPMU01 does not work and the RUN indicator is ON.When the TP48300/A power system has serious alarms, the ALM indicator on the CPMU01 is ON and the buzzer sounds. For details, see the TP48300/A power system Maintenance Guide.3. When the system is in standby mode, press "↓" and "Enter" at the same time to reduce the contrast of the LCD or press "↑" and "Enter" at the same time to increase the contrast of the LCD.4. Before setting the CPMU01 menu, press "↓" or "↑" to select options and configure values.Press "Enter" to enter the main menu when the system is standby. On the main menu, press "Enter" to view the submenu, and save the configuration by pressing "Enter" on the submenu.Press Cancel to undo the operation and return to the upper menu without saving the configuration.5. The PMU does not generate any alarm. When the current interface is not the main menu, the LCD goes dark five minutes later if you do not press any button, and the main menu is displayed eight minutes later if you do not press any button.6. -On the System Control interface, you can access the system with the user password, engineer password, or administrator password.3. On the Engineer Ad-vanced Setting interface, you can access the system with the engineer password or administrator password.The user password and engineer password are 0# and 11# respectively and can be reset on the menu.The administrator password is provided by Huawei.
CAUTIONDo not power on the DC load before the storage batteries parameter is correctly set on the CPMU01 , otherwise, it will cause damage to storage batteries.
NOTEThe number of the battery group can be set as 0, 1 or 2. Please set the number of the battery group and capacity according to actual configuration. If you face to the door, the fuse at the leftside is BF1- and the fuse at the rightside is BF2- .1. If only one group of batteries is connected, please connect to BF1- , set the number of the battery group as 1, and set "battery capacity 1" according to actual configuration. 2. If two groups of batteries are connected, please separately connect to BF1- and BF2- , set the number of the battery group as 2, and set "battery capacity 1", "battery capacity 2" according to actual configuration. 3. If four groups of batteries are connected, two battery groups connect to BF1- and the other two battery groups connect to BF2- , set the number of the battery group as 2, and set "battery capacity 1", "battery capacity 2" according to total actual capacity of every two battery groups. 4. This guide take two groups of 300Ah batteries as an example.
�0
English
中 文
English
中 文
English
中 文
2008-08-0653.6VDC 227VACLoad:0.2ABatt:0.0A
2008-08-0653.6VDC 227VACLoad:0.2ABatt:0.0A
2008-08-0653.6VDC 227VACLoad:0.2ABatt:0.0A
SettingsDC SettingsBatt SettingsAMB. Settings
SettingsDC SettingsBatt SettingsAMB. Settings
Batt SettingsBatt SelectionLVD SettingCharge
Batt SelectionBatt String:1Cap.1:400AhCap.2:0Ah
Batt SelectionBatt String:2Cap.1:400AhCap.2:0Ah
Batt SelectionBatt String:2Cap.1:400AhCap.2:0Ah
Batt SelectionBatt String:2Cap.1:300AhCap.2:0Ah
Batt SelectionBatt String:2Cap.1:300AhCap.2:0Ah
Batt SelectionBatt String:2Cap.1:300AhCap.2:300Ah
MAIN MENUStatusMaintenanceSettings
MAIN MENUStatusMaintenanceSettings
MAIN MENUStatusMaintenanceSettings
Batt SettingsBatt TestTemp coeff
Temp Comp Basis:Batt 1Temp Comp:80mV/ ℃
Low Temp Alarm:0℃High Temp Alarm:50℃
Low Temp Alarm:0℃High Temp Alarm:50℃
SettingSystem SettingsAlarm SettingsAC Settings
Address:0Text:EnglishComm Mode:ModemBand:9600
Date:2008-08-08Time:09:10
Date:2008-08-08Time:09:10
English
中 文
2008-08-0653.6VDC 227VACLoad:0.2ABatt:0.0A
MAIN MENUStatusMaintenanceSettings
SettingSystem SettingsAlarm SettingsAC Settings
Address:0Text:EnglishComm Mode:ModemBand:9600
ENT▼
ENT▼
ENT▼
ENT ENTor▼▼
ENTor▼▼
ENTor▼▼
ENT ▼
ENT ▼
ENT▼
ENT▼
ENTor▼▼
ENT▼
ENTor▼▼
ENT▼
ENTor▼▼
ENT▼
ENT ▼
ENT ▼
ENT▼
ENT ▼
ENT ▼
ENT
ENT▼
ENT ▼
ENT ▼
ENT ENT ▼
ENT
ENT
ENT
ENTor▼▼
Load Shunt:YesPisp Contrast:3System Type: TP48300/A
▼
ENT
Load Shunt:YesPisp Contrast:3System Type: TP48300/A
��
c Monitoring Menu Structure
Appendix 1
Main menu
Running information System control Parameter setting
Module information
Current alarm
History alarm
Battery test result
Version disply
Module ID
Output voltage
Output current
Current limit
Status
Major alarm
Minor alarm
Alarm SN
Alarm severity
Alarm name
Generation time
Alarm SN
Alarm severity
Alarm name
Generation time
Alarm SN
Alarm severity
Alarm name
Generation time
End time
ControlMode
Start
Modules 1-6
Automatic
Manual
Floatingcharging
Passwordmodification
Parameterinitialize
Standard test
Quick test
End test
Equalizedcharging
On
Off
Systemparameter
setting
Address
Language
Communication on mode
Baud rate
Date
Time
Load current divider
Display contrast
Engineeradvancedsetting
System type
Dormant permit
Alarmparameter
setting
Alarm severity Alarm type
Severity
Alarm controlparameter
Alarm sound
Clearing ofhistory alarms
Relay relate
Digital alarm
Alarm type
Relate relay
AC parametersetting
Overvoltage
Undervoltage
DC parametersetting
Overvoltage
UndervoltageBattery
parametersetting
Environmentparameter
setting
High limit
Low limit
High temperature
Low temperature
DG parametersetting
Generator enable
Output power
DOD
High-TEMP switch-off
DG switch-on temperature
DG switch-off temperature
Air-conditionerparameter
setting
Type
Power
Appendix 2
��
d CPMU01 Menu Reference
Appendix 2
Main Menu Second-LevelMenu
third-LevelMenu
Fourth-LevelMenu Paremeter Value
Address 0
Text English
Comm Mode Modem
Band 9600
Date 2001-01-01
Time 00:00
Load Shunt Yes
Disp Contrast 3
Modify PWD None
Init Para No
System Type TP48300/A
SystemSetting
Eng Setting
Rect Sleep No
Setting
Charging parameter
Battery parameter
Power-off parameter
Battery string
Capacity
Installation date
Load power-off permit
Load power-off voltage
Battery power-off permit
Battery power-off voltage
Floating charging
Equalized charging
equalized charing period
Charging current limitBattery parameter setting
Battery test
Auto test
Short test
Auto test permit
Start test period
Test end voltage
Test time
Test delay
Test end voltage
Test time
Battery temperature factor
TEMP compensate basis
TEMP compensate factor
High-TEMP power-off permit
High-TEMP power TEMP
TEMP alarm lower limit
TEMP alarm upper limit
Upper limit
Lower limit
��
Main Menu Second-LevelMenu
third-LevelMenu
Fourth-LevelMenu Paremeter Value
AC ON/OFF Serious
Serious
Serious
Serious
Serious
Serious
SeriousSerious
Serious
SeriousSerious
AC Volt Low/High Common
Common
CommonCommon
CommonCommonCommonCommon
Common
CommonCommonCommonCommonCommon
DC Volt Low/High
Load Off Alarm
Batt Off Alarm
Batt Fuse AlarmTemp1 Alarm
Humidity Alarm No Alarm
Batt Temp Alarm
Door Alarm
Water Alarm
Smoke Alarm
Rect Fail
Rect Protect
Rect Comm Fail
Charge Curr High
DC SPD Alarm
AC SPD Alarm
Wire Alarm
Generator Fail
Alarm Level
Load Fuse Alarm
Alarm Type HighDigital Alarm Digital 1
Set Alarm Name Switch 1
Switch 1
Switch 2
Switch 5
Switch 6
Switch 7
Setting
Alarm Setting
Alarm ControlAudible Alarm YesClr Hist Alarm No
AC OFF1
Relay Relate
280VAC Setting
180V58.0V
DC Setting 45.0V1400Ah0AhBatt Setting
Batt Setting 2001-01-01
AlarmRelate RelayOver Volt
Over VoltUnder Volt
Under VoltBatt StringCap 1Cap 2
Install DateYesYes44.0VLVD Setting
43.0V
LLVD EnableBLVD Enable
LLVD
BLVD53.5V56.5V
60 daysCharge
0.10C10
FloatBoost
Cyc BC Duration
Curr Limit
��
Setting
Generator
No
12.5kW
30%
Yes45℃
29℃Type Single-Phase
Power 1.0kW
Status
Maintance
Air-condition
Major Alarm
Common Alarm
AutoMgmt Mode
Manual
FC
Std Test
Quick Test
End Test
Start
BC
ON
Rect1
Rect1Rect2
Rect3
Rect4Rect5Rect6
Batt Test Result
Version Disply
No Record
V100R001C01********
*
*
Rectifiers
History Alarm
Active Alarm
Disch Test120 days
1.9VAuto Test
—10 hours
45.0V
Batt Test
Short Test60 minBatt 180mV/℃
No53℃
0℃
50℃
Batt Setting
Temp Coeff
AMB Setting
80℃
-20℃
80℃
-20℃
50℃
Generator Enable
Output Power
Discharge Depth
High Temp OFF
Start Temp
OFF Temp
Auto Test Enable
Cycle
Test End Volt
Test DlayDuration
Test End Volt
Duration
Temp Comp Basis
Temp Comp
BHTD Enable
BHTD Temp
Low Temp Alarm
High Temp Alarm
Upper Limit
Lower Limit
Upper Limit
Lower Limit
High Alarm
Low Alarm 0℃
Main Menu Second-LevelMenu
third-LevelMenu
Fourth-LevelMenu Paremeter Value
��
1st Rev Date Sign 2st Rev Date SignItem Setting Bound FactorySetting
0~2 1
30~1000 400Ah
30~1000 0Ah
44.0V
43.0V
43.2V~57.6V 53.5V
43.2V~57.6V 56.5V
0.05~0.25 0.1
Battery String
Battery Cap 1
Battery Cap 2
LLVD
BLVD
Battery Float
Battery Boost
Rect Sleep
LLVD Enable
BLVD EnableCurrent Limit Coefficient
35V~LLVD
YES/NO
YES/NO
YES/NO
NO
YES
YES
BLVD~DC Under volt
-50℃~100℃ 50℃
50℃-50℃~100℃
Battery High TempAlarmEnvironment High Alarm
TP48300/A Mini Power System Parameter List
Appendix 3
CAUTIONPlease set the number of the battery group, battery capacity, battery temperature and environment temperature according to actual configuration.