31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2...

17
Name Designation Affiliation Date Signature Submitted by: W. Turner Signal Processing Domain Specialist SPDO 20110406 Approved by: K.Cloete Project Manager SPDO 20110406 SIGNAL PROCESSING CODR REVIEW PLAN Document number ................................................................. WP2040.020.011PLA001 Revision ........................................................................................................................... 2 Author ............................................................................................................... W. Turner Date ................................................................................................................. 20110406 Status............................................................................................... Approved for release

Transcript of 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2...

Page 1: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

 

 

 

Name  Designation  Affiliation  Date  Signature 

Submitted by: 

W. Turner  Signal Processing Domain Specialist

SPDO  2011‐04‐06   

Approved by: 

K.Cloete  Project Manager  SPDO  2011‐04‐06 

 

 

   

 SIGNAL PROCESSING CODR  

REVIEW PLAN 

Document number ................................................................. WP2‐040.020.011‐PLA‐001

Revision ........................................................................................................................... 2

Author ............................................................................................................... W. Turner

Date ................................................................................................................. 2011‐04‐06

Status ............................................................................................... Approved for release

Page 2: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 2 of 17 

 

DOCUMENT HISTORY 

Revision  Date Of Issue  Engineering Change  

Number 

Comments 

C  26th March 2011  ‐  First draft release for internal review 

1  29th March 2011    First Issue 

2  06th April 2011  ‐  Front  sheet  changed  K  Cloete’s  function  to 

Project Manager 

Updated Distribution list 

Section  4.1  Corrected  Andre  Jongeling’s  e‐

mail address 

Section  5  Numbered  items  6  to  9  changed 

from Mar to April 

Section  4.1  added  Aris  Karastergiou,  Roy 

Smits,  Ralph  Eatough,  Richard  Schilizzi  to 

presenters list 

Section 7 Changed key for Roy Smits from RS 

to RSm. Corrected spelling of Karastergiou. 

 

 

DOCUMENT SOFTWARE 

  Package  Version  Filename 

Wordprocessor  MsWord  Word 2007  31‐WP2‐040.020.011‐PLA‐001‐2_CoDR_Review_Plan 

Block diagrams       

Other       

 

 

ORGANISATION DETAILS 

Name  SKA Program Development Office 

Physical/Postal 

 Address 

Jodrell Bank Centre for Astrophysics 

Alan Turing Building 

The University of Manchester 

Oxford Road 

Manchester, UK 

M13 9PL 

Fax.  +44 (0)161 275 4049 

Website  www.skatelescope.org 

 

   

Page 3: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 3 of 17 

 

DISTRIBUTION LIST 

 

Review Panel   

Robin Sharpe (External advisor UK) (chair) 

Peter Dewdney (SPDO UK)      

Andre Jongeling (JPL USA)        

Phillip Stanley‐Marbell (IBM research CH)    

Lou Morales (iSine USA)  

Tim Hankins (NRAO USA)        

SPDO     

Richard  Schilizzi,  Peter  Dewdney,  Joe  Lazio,  Minh  Huynh,  Kobus  Cloete,  Tim 

Stevenson, Neil Roddis, Andre Gunst, Roshene McCool, Wallace Turner, Duncan Hall, 

Georgina Harris, Rob Millenaar, Billy Adams, Lisa Bell, Colin Greenwood, Jo Bowler, 

Phil Crosby, Greta Collins. 

WP2 Management Team 

Andrew Faulkner (AAVP), Jan Geralt bij de Vaate (ASTRON), Carole Jackson (CSIRO), 

Gary Hovey  (DRAO),  Steve  Torchinsky  (OBSPAR), Athol  Kemball  (TDP),  Lynn Baker 

(TDP), Paul Alexander (UK).  

Liaison Engineers 

  Jan Geralt bij de Vaate  (ASTRON),  John Bunton  (CSIRO), Gary Hovey  (DRAO), Peter 

Hall  (ICRAR),  Stelio Montebugnoli  (INAF),  Domingos  Barbosa  (IT),  Leonid  Gurvits 

(JIVE), Arpad Szomoru  (JIVE),  Jongsoo Kim (KASI), Reinhard Keller (MPG), Yashwant 

Gupta  (NCRA‐TIFR),  Anita  Loots  (NRF),  Steve  Torchinsky  (OBSPAR),  Thijs  van  der 

Hulst  (RUG),  Athol  Kemball  (TDP),  Lynn  Baker  (TDP),  Len  Bruton  (UCAL),  Paul 

Alexander (UCAM), Andy Faulkner (UCAM), Chris Shenton (UMAN), Rodolphe Weber 

(UORL), Kristian Zarb Adami (UOXF), Mike Jones (UOXF). 

SSEC Chairman 

    M Garret (ASTRON). 

IEAC 

Jaap Baars  (Arcor), Marco de Vos  (ASTRON), Wolfgang  von Rueden  (CERN),  Peter 

Hall  (Curtin  University),  Tony  Beasley  (National  Ecological  Observatory  Network), 

Noriyuki  Kawaguchi  (National  Astronomical  Observatory),  Peter  Napier  (Chair) 

(NRAO), André Hoogstrate (TNO). 

Page 4: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 4 of 17 

 

  

TABLE OF CONTENTS 

1  INTRODUCTION ............................................................................................. 7 

1.1  Purpose of the document ....................................................................................................... 7 

1.2  Scope of the document ........................................................................................................... 7 

1.3  Date and Place ........................................................................................................................ 7 

2  REFERENCES ................................................................................................ 7 

3  PURPOSE AND EXPECTED OUTCOME OF THE SYSTEM CODR ..................................... 7 

4  ORGANISATION ............................................................................................ 8 

4.1  Participants ............................................................................................................................. 8 

4.2  Review Process ...................................................................................................................... 10 

4.3  Roles and Responsibilities ..................................................................................................... 10 

5  REVIEW SCHEDULE ...................................................................................... 11 

6  REVIEW DOCUMENTATION ............................................................................ 12 

7  AGENDA (DRAFT) ....................................................................................... 13 

8  LOGISTICS ................................................................................................. 14 

8.1  Location ................................................................................................................................. 14 

8.2  Contact Persons .................................................................................................................... 14 

9  CAMPUS MAP ............................................................................................ 15 

 

 

LIST OF FIGURES 

Figure 1 Manchester University Campus Map ...................................................................................... 16 

 

 

LIST OF TABLES 

Table 1 Signal Processing Review Documents ...................................................................................... 12 

Table 2 Signal Processing CoDR Agenda (Draft) .................................................................................... 13 

 

 

Page 5: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 5 of 17 

 

LIST OF ABREVIATIONS 

AA .................................. Aperture Array

ASIC .............................. Application-Specific Integrated Circuit

ASKAP .......................... Australian SKA Pathfinder

ASTRON ....................... Netherlands Foundation for Research in Astronomy

CAD ............................... Computer Aided Design

CDR ............................... Critical Design Review

CISRO ........................... (Australian) Commonwealth Scientific and Research Organisation

COAR ............................ Consolidated Observation and Action Register

CoDR ............................. Conceptual Design Review

DRM .............................. Design Reference Mission

EMC .............................. Electro Magnetic Compatibility

EX .................................. Example

FFT ................................ Fast Fourier Transform

FoV ................................ Field of View

FPGA ............................. Field Programmable Gate Array

GNU .............................. GNU’s Not Unix

INAF .............................. National Institute for Astrophysics

IP ................................... Intellectual Property

JIVE ............................... Joint Institute for VLBI in Europe

JPL ................................ Jet Propulsion Labs

KASI .............................. Korea Astronomy Space-Science Institute

LEMP ............................. Logistic Engineering Management Plan

MPIfR ............................ Max Planck Institute for Radio Astronomy

MTBF ............................. Mean Time Before Failure

MTTR ............................ Mean Time To Replacement

NCRA ............................ National Centre for Radio Astrophysics

NRC-HIA ....................... National Research Council Herzberg Institute of Astrophysics

NRF ............................... National Research Foundation

OPAR ............................ Observatorie de Paris

OS ................................. Operating System

PAF ............................... Phased Array Feed

PDR ............................... Preliminary Design Phase

PSU ............................... Power Supply Voltages

RFI ................................. Radio Frequency Interference

RMON ........................... Remote Monitoring

RMP .............................. Risk Management Plan

SEMP ............................ System Engineering Management Plan

Page 6: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 6 of 17 

 

SRS ............................... (Sub) Systems Requirement Specification

SRR ............................... (Sub) Systems Requirement Review

SKA ............................... Square Kilometre Array

SNMP ............................ Simple Network Management Protocol

SPDO ............................ SKA Program Development Office

TDP ............................... Technology Development Program

TIFR .............................. Tata Institute of Fundamental Research

UCAM ............................ University of Cambridge

UMAN ............................ University of Manchester

UORL ............................ University of Orleans

UOXF ............................ University of Oxford

VLBI ............................... Very Long Baseline Interferometry

WBSPF .......................... Wide Band Single Pixel Feed

 

   

Page 7: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 7 of 17 

 

1 Introduction 

1.1 Purpose of the document 

This document describes  the plan  for  the Signal Processing Concept Design Review  (CoDR)  for  the 

Square Kilometre Array (SKA) project. 

1.2 Scope of the document 

This  document  will  describe  all  matters  related  to  the  review  itself.  It  will  include  logistics 

surrounding the review as well as a preliminary agenda. 

1.3 Date and Place 

The Signal Processing CoDR will be held on 14th and 15th April 2011 at the University of Manchester, 

Manchester, UK. 

 

2 References 

[1]  T Stevenson, System Engineering Management Plan, document WP2‐005.010.030‐MP‐001. 

 

3 Purpose and Expected Outcome of the System CoDR 

The signal processing CoDR is the review of the work conducted at element level during the Concept 

Phase. The phase, as well as the design review requirements, are described in more detail in [1]. 

During the Concept Phase of the project, the signal processing engineering process will be  initiated 

by  conducting  investigations  into,  amongst  others,  the  particular  technologies  being  utilised, 

technology  trends,  technology  options, work  already  done  and  being  done  by  precursors,  design 

studies and other pathfinder arrays, and results obtained from this work. Preliminary investigations 

into the signal processing set of requirements, the interfaces and the risks will also be conducted. 

The CoDR will be conducted to evaluate: 

The overall progress, 

Whether the technical adequacy obtained during the concept phase is at a sufficient level of 

maturity to allow the Signal Processing Element to move into the next phase, 

Whether all Signal Processing Element aspects of the project have been covered and where 

gaps exist, whether adequate measures have been identified to address the shortcomings.  

The expected outcome of the review is the establishment of the signal processing concept baseline 

by conclusion of  the  signal processing  level concept phase. Following  the  successful conclusion of 

the review the next phase, the Signal Processing Element definition phase, will be initiated. 

   

Page 8: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 8 of 17 

 

More specifically the Review Panel is requested to consider the following questions: 

1. Are the requirements complete, and sufficiently defined for this stage of the project? 

2. At  the  concept  level,  is  the  element/subsystem  presented  capable  of  meeting  the 

requirements? 

3. Have  interfaces  to other aspects of  the  system been adequately  identified and defined at 

this stage of the program? 

4. Are  the options proposed  to be  carried  forward  credible and are  the presented data and 

information in support of each option credible? 

5. Have  all  the  necessary  aspects  of  the  specific  element/subsystem  been  considered  and 

addressed during the review or are there gaps and/or shortcomings? 

6. Does the risk profile appear reasonably detailed and assessed for this stage of the program? 

7. Do the stated risk controls and proposed mitigations appear reasonable and executable? 

8. Is the overall plan (including the identification of the tasks, effort, resources, costs, schedule 

and risk mitigation needed) to complete the subsequent project phases credible? 

These questions are  to be within  the context of SKA1 but with consideration of extensibility  to 

SKA2 

4 Organisation 

4.1 Participants 

The following groups of review participants have been identified: 

Review Panel : Four external members of the review panel + Peter Dewdney (SPDO) 

Presenters : SKA Contributing Institutions + SPDO 

Observers : Any other attendee (see below) 

 

The Review Panel is composed of the following members: 

Peter Dewdney (SPDO UK)       [email protected]  

Andre Jongeling (JPL USA)      [email protected]  

Phillip Stanley‐Marbell (IBM research CH)  [email protected]  

Lou Morales (iSine USA)       [email protected]  

Robin Sharpe (External advisor UK) (chair)  [email protected] 

Page 9: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 9 of 17 

 

Tim Hankins (NRAO USA)      [email protected]  

As Presenters, the following people have been identified: 

Aris Karastergiou        [email protected]  

Arpad Szomoru (JIVE)        [email protected] 

Ben Stappers (UMAN)        [email protected] 

Brent Carlson (nrc‐cnrc)       brent.carlson@nrc‐cnrc.gc.ca 

Dominic Ford (UCAM)        [email protected] 

Francois Kapp (NRF)        [email protected] 

Guenter Knittel (MPiFR)       gknittel@mpifr‐bonn.mpg.de 

John Bunton (CSIRO)        [email protected] 

Kobus Cloete (SPDO)        [email protected] 

Kris Zarb Adami (UOXF)        [email protected] 

Larry D’Addario  (JPL)        [email protected] 

Ralph Eatough          reatough@mpifr‐bonn.mpg.de  

Richard Schilizzi         [email protected]  

Roshene McCool (SPDO)      [email protected]  

Roy Smits          [email protected]  

Tim Stevenson (SPDO)        [email protected]  

Wallace Turner (SPDO)        [email protected] 

Note that the presenters will be doing the presentations on behalf of the international collaboration 

and contributors. 

As Observers, the following people have been invited: 

Liaison engineers 

WP2 Management Team members 

Members of the SSEC (exact numbers and attendance still to be confirmed) 

Members of the International Engineering Advisory Committee (IEAC)  

SPDO staff members  

Page 10: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 10 of 17 

 

4.2 Review Process 

The External Review Panel is expected to review the CoDR documentation prior to the actual review. 

Any questions, comments or queries sent to the SPDO SP domain specialist (W.Turner)  in advance 

will be recorded and be dealt with during the review. Questions, comments or queries posed during 

the review will be recorded and will be attempted to be addressed during the review. In the event 

that any issue cannot be dealt with during the review, it will be recorded as such and the SPDO will 

address these outstanding issues as soon as possible after the review. 

4.3 Roles and Responsibilities 

The SPDO shall 

• Distribute the last of the documentation to the External Reviewers no later than two weeks 

before the review date;  

• Record all questions, comments and queries raised before and during the review; 

• Respond to questions, comments and queries before, during and after the review; 

• Record the responses to the questions, comments and queries; 

• Organise and support the review meeting: 

• Provide the necessary facilities for the meeting; 

• Respond to agreed Actions within the agreed due dates; 

• Compile an overview report to the PrepSKA Board and the SSEC after the review.  

 

The External Review Panel Chairman shall 

Organise and lead the External Review Panel; 

Review the documentation;  

Raise questions, comments and queries before and during the review related to any part or 

aspect of the project; 

Prepare  and  issue  the  External  Review  Panel  Report,  together with  a  list  of  the  agreed 

Actions; 

 

Page 11: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 11 of 17 

 

The External Review Panel Members shall 

• Review the documentation;  

• Raise questions, comments and queries before and during the review related to any part 

or aspect of the project; 

• Support the Chairman in the preparation of the External Review Panel Report;  

Observers: 

Observers are deemed to have more than a passing familiarity with the work being reviewed and 

to have had some opportunity to pass comment prior to the Review. In order to capture views 

that develop during the Review process, but to allow the formal procedure to complete  in the 

time allocated, COARs may be drafted by Observers and an opportunity to present them to the 

SPDO  immediately  following  the  Review  is  envisaged.  As  this  right  is  available  to Observers, 

questions or statements  from the  floor of the Review will be discouraged. Questions  from  the 

panel will be handled by the presenter which may, at his/her discretion, call on members of the 

audience to assist with answering the question.  

The Observers are therefore invited to: 

•  Attend the review; 

•  Provide  written  feedback  with  regards  to  any  aspects  of  the  review,  including  the 

documentation, in COAR format after the review; 

•  Assist  with  answering  questions  from  the  review  panel  if  requested  to  do  so  by  the 

presenter. 

5 Review Schedule 

 

1. Weeks  3  to  31  Jan  2011  –  Finalise  scope  of  CoDR  and  contents  of  documents,  identify 

participants, arrange short telecons, start work on documents. 

2. Weeks 31 Jan to 4 Mar 2011 – Produce first drafts of documents, read and update, finalise 

as many of the smaller documents during this period. 

3. Week 7 Mar to 18 Mar 2011 –Distribute documents to community for document review and 

finalisation. 

4. Week 21 Mar to 25 Mar 2011 –  Internal review. Gather comments and  identify remaining 

issues. Update documents following internal review. 

5. 31 Mar 2011 ‐ Distribute documents to the external reviewers. 

6. 13 April 2011 – Review panel members arrive in Manchester 

7. 14 and 15 April 2011 – Conduct design review 

Page 12: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 12 of 17 

 

8. 15 April 2011 – Review panel to start drafting report and provide initial feedback 

9. Week 26 April to 28 April – Internal follow‐up review, determine and action follow up items. 

6 Review Documentation 

The CoDR Documentation Package consists of the following documents: 

Doc No  Title 

1a  Signal Processing High Level Description 

1b  Searching  For Fast Transients with SKA PHASE 1* 

1c  Pulsar survey with SKA phase 1 

2  Technology Roadmap 

3a1  Software Correlator Concept Description 001 

3a2  Software Correlator Concept Description 002 

3b  GSA Correlator Concept Description 

3c1  ASKAP Correlator Concept Description SKA2 

3c2  ASKAP Correlator Concept Description SKA1 

3d  A UNIBOARD  Based PHASE 1 SKA Correlator and  Beamformer Concept Description 

3e  CASPER Correlator Concept Description 

3f1  SKA1 ASIC‐Based Correlator for Minimum Power Consumption—Concept Description 

3f2  SKA2 ASIC‐Based Correlator for Minimum Power Consumption—Concept Description 

3g  AA CORRELATOR SYSTEM CONCEPT DESCRIPTION 

3h  Central Beamformer Concept Description 

3i  Station Beamformer Concept Description 

3j1  GPU Processing for Real Time Isolated Radio Pulse Detection 

3j2  GPU Processing for Pulsar Search 

3k  PAF Beamformer Concept Description 

3l  FPGA DeDispersion Concept 

3m  FPGA based pulsar searching 

3n  Benchmarking pulsar search backends 

7**  SKA Signal Processing Requirements 

8  SKA Signal Processing Costs 

9  SKA Signal Processing Risk Register 

10  Signal Processing Strategy to Proceed to the Next Phase 

32***  Software & Firmware Strategy 

  Relevant reference documents 

Table 1 Signal Processing Review Documents 

Note:  *Transients  are  not  currently  an  SKA1  requirement  but  are  presented  in  the  context  of 

extensibility to SKA2 

** Documents Numbers 4,5 and 6 not part of the CoDR  

Page 13: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 13 of 17 

 

***Document Numbers 11 through 31 and 33 through 37 are reference documents 

7 Agenda (Draft) 

Please note that all times are reflected in UT. 

Session    Presenter  Starting time  Time allocated 

  Thursday, 14 April 2011   Room 3.225, Alan Turing Building 

1  Review panel (closed meeting)  Reviewers  9:00 – 9:30  30 minutes 

  Welcome and general overview of the SKA   KC/RS  9:30 – 10:00  30 minutes 

  Purpose and context of the Signal Processing CoDR 

KC  10:00 – 10:15  15 minutes 

  Signal Processing Requirements   TS  10:15 – 10:45  30 minutes 

  Coffee break    10:45 – 11 :15  30 minutes 

2  Technology Roadmap  WT  11:15 – 11:30  15 minutes 

  Station Beamforming  KZ  11:30 – 12:00  30 minutes 

  Central Beamforming  BC  12:00 – 12:30  30 minutes 

  PAF Beamforming  JB  12:30 ‐ 13:00  30 minutes 

  Lunch break    13:00 – 13:45  45 minutes 

3  Non‐Imaging Processing  BS  13:45 – 14:15  30 minutes 

  GPU Processing for Real Time Isolated Radio Pulse Detection 

AK  14:15 – 14:30  15 minutes 

  GPU Non‐Imaging Concept  GK  14:30 – 14:45  15 minutes 

  Acceleration Processing  RE/RSm  14:45 – 15:00  15 minutes 

  Other Instruments  BS  15:00 – 15:15  15 minutes 

  Coffee break    15:15 – 15:45  30 minutes 

4  Software Correlator Concept  DF  15:45 – 16:15  30 minutes 

  Review panel (closed meeting)  Reviewers  16:15 – 17:15  1 hour 

  Dinner (Novotel)  All  18:30   

         

  Friday, 15 April 2011   Room 3.225, Alan Turing Building 

5  GSA Correlator Concept  BC  9:00 – 9:30  30 minutes 

  Low Power ASIC concept  LD  9:30 – 10:00  30 minutes 

  ASKAP style Correlator Concept  JB  10:00 – 10:30   30 minutes 

  Coffee break    10:30 – 11:00  30 minutes 

6  UNIBOARD SKA correlator concept  AS  11:00 – 11:30  30 minutes 

  CASPER Correlator  FK  11:30 – 12:00  30 minutes 

  Costs & Costing Strategy  RM  12:00 – 12:15   15 minutes 

  Signal Processing Element level Risks  WT  12:15 – 12:30  15 minutes 

  Strategy to proceed to the next phase  WT  12:30 – 12:45  15 minutes 

  Lunch break    12:45 – 13:30  45 minutes 

7  Review panel (closed meeting)  Reviewers  13:30 – 15:15  95 minutes 

  Coffee break    15:15 – 15:45  30 minutes 

8  Review Panel initial comments  All  15:45 – 16:45  1 hour Table 2 Signal Processing CoDR Agenda (Draft) 

 AS – Arpad Szomoru  BS – Ben Stappers  BC – Brent Carlson DF – Dominic Ford  FK – Francois Kapp  GK – Guenter Knittel 

Page 14: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 14 of 17 

 

JB ‐ John Bunton  KC – Kobus Cloete  KZ – Kris Zarb Adami LD – Larry D’Addario  RS – Richard Schilizzi  RM – Roshene McCool TS – Tim Stevenson  WT – Wallace Turner  AK – Aris Karastergiou RE – Ralph Eatough  RSm – Roy Smits  Note  that  representatives  for documents 1b, 3a1, 3g and 3l are not able  to attend  the  review but questions can be forwarded either prior to or as a result of the review.  

8 Logistics 

8.1 Location 

The SPDO office is located at: 

Jodrell Bank Centre for Astrophysics (Room 3.136) 

Alan Turing Building (Building 46) (53°28'4.58"N  2°13'53.27"W) 

University of Manchester 

Manchester 

M13 9PL 

UK 

The meeting rooms for the review are: 

Thursday 14th  : Lovell Seminar Room, Room 3.225, Alan Turing Building (Building 46) 

   (53°28'4.58"N  2°13'53.27"W) 

Friday 15th  : Lovell Seminar Room, Room 3.225, Alan Turing Building (Building 46) 

   (53°28'4.58"N  2°13'53.27"W) 

 

8.2 Contact Persons 

For support please contact any of the following SPDO representatives: 

Name    Peter Dewdney (Project Engineer) 

Email    [email protected] 

Phone    +44 (0)161 275 4294 

 

  Name    Kobus Cloete (Project Manager) 

Email    [email protected] 

Page 15: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

    WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06   Page 15 of 17 

 

Phone    +44 161 275 4081 

 

Name    Wallace Turner (Domain Specialist) 

Email    [email protected]  

Phone    +44 161 306 6470 

 

Name    Lisa Bell (Office Manager) 

Email    [email protected] 

Phone    +44 (0)161 275 4239 

Fax    +44 (0)161 275 4049 

 

9 Campus Map 

Campus map attached on next page.  

For more maps of the campus please see http://www.manchester.ac.uk/visitors/travel/maps/. 

 

 

Page 16: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

      WP2‐040.020.011‐PLA‐001     Revision : 2 

 

  2011‐04‐06     Page 16 of 17 

   

 

Figure 1 Manchester University Campus Map 

Page 17: 31-WP2-040.020.011-PLA-001-2 CoDR Review Plan · WP2‐040.020.011‐PLA‐001 Revision : 2 2011‐04‐06 Page 2 of 17 DOCUMENT HISTORY Revision Date Of Issue Engineering Change

      WP2‐040.020.011‐PLA‐001     Revision : 2 

  2011‐04‐06     Page 17 of 17 

 

 

 

 

 

 

 

 

Intentionally Blank