30 mei 2016 Welcome N329 Road of the Future Patrick Megens · Royal Haskoning Architecten....
Transcript of 30 mei 2016 Welcome N329 Road of the Future Patrick Megens · Royal Haskoning Architecten....
30 mei 2016Welcome
N329 Road of the FuturePatrick Megens
Content Introduction
• Reasons for reconstruction N329• Why Road of the Future?• Tendering Process• What makes the road special?
. OssPopulation: 85000Surface 15.993 ha
EconomyJobs %
Industry 9588 23,8 %Retail 7268 18 %Construction 3547 8,8 %Logistics 3021 7,5 %
Reasons for reconstruction / Road of the Future
Reasons for reconstruction N329• Important highway for Oss and industrial areas• One of the mainstays of transport by boat, train and truck• Capacity completely insufficient
• Poor physical condition
6,5 km long2x2 lanes
Lots of trucks2 car tunnels
3 bicycle tunnelsWildlife crossings
Road of the Future
2003 : started as a conventional reconstruction
2008: decision Province Noord-Brabant and Municipality Oss: N329 became testing ground for sustainability and innovation
title “Road of the Future”
Ideas for Road of the Future
Book containing all 200 ideas
Concrete ideas:
• LED lighting• Energy Neutral in operation• Intelligent Transport System • CO2 neutral construction
Guidelines for design (tunnels, road and landscape)
Impressions made by Royal Haskoning Architecten
Impressions made by
Royal Haskoning Architecten
Impressions made by Royal Haskoning Architecten
Impressions made by Royal Haskoning Architecten
Tendering process
Call for tenders
• Design & Construct contract
• Chance for contractor for own ideas with regard tosustainability and innovation
• The idea was : the contractor with the best design within the aivalable budget gets the job
Price ceiling € 45,000,000
• Energy neutral road• LED lighting• Intelligent TransportSystem
• Accessibility• Built CO2 neutral
• Design Road and tunnels
• Landscaping
Additional ideas
Functional requirements
Detailed requirements
Offers recieved were assessed on two criteria
• Visible innovation
• Sustainability
3 november 2010: publish bonuses and
Opening bid envelopes
Inschrijving2
What makes the road special?
General •Cooperation Province of Noord Brabant and Municipality of Oss
•Tendering process
•Many aspects sustainability and innovation
Energy neutral in operation
Energy used for
• Lighting
• Traffic lights and Intelligent Transport
System
• Pumps in tunnels
Energy generated by
• Solar trees / solar flowers
• Solar panels
Solar tree
CO2 emission in construction
Built CO2 neutral
• Unique in the
Netherlands
Production of materials
Construction site
Transport
CO2 Compensation
• 100% in city of Oss
• In businesses in the area
• Energy saving measures
• Green gas
• Green elctricity
Design for Re-use
• Complete re-use of materials old road
• All new materials (> 99 %) suitable for re-use
or recycling
Intelligent Transport System
System selects automatically optimal traffic light switching
• Heavy traffic on N329 :“Green wave”• Less traffic on N329 : “Green on demand”
Intention• Best possible traffic flow• Less energy consumpsion by vehicles• Lower CO2 emissions• Less noise
Added by contractor : Flowman
Flowman
• Continuous guidance for the driver
Flowman
• http://www.n329wegvandetoekomst.nl/actueel/videofragmenten/hoe_werkt_de_flowman
Pleasant Pass
• http://publicpasses.nl/
For informationwww.n329wegvandetoekomst.nl