3 Week Schedule

3
Customer : SEC - EOA Contractor : SIEMENS Sub Contractor: KUC 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 Total Cum %age completed 18.10.2014. Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri 15% P 15% A 0% P 0% A 0% P 0% A 0% P 0 0% A SIEMENS FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS) Sl. No. Unit QUANTITY Remarks ACTIVITY Control Building works Base coarse in all SVC area 02.01 02.00 Base coarse in all SVC area 01.02 01.03 Remaining Corridor finsihing works Toilet works Grade slab Ramp and loading platform control building west side 01.01 01.00 Activity start depend on clearance from Electomechanical teams Activity start depend on clearance from Electomechanical teams Dec-14 Page 1 of 3

description

3 week

Transcript of 3 Week Schedule

  • Customer : SEC - EOA

    Contractor : SIEMENS Sub Contractor: KUC

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2

    Total

    Cum %age

    completed

    18.10.2014.

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    15% P

    15% A

    0% P

    0% A

    0% P

    0% A

    0% P 0

    0% A

    SIEMENS

    FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)

    Sl. No. Unit

    QUANTITY

    Remarks ACTIVITY

    Control Building works

    Base coarse in all SVC area

    03.00

    02.01

    Trenches/duct banks

    02.00 Base coarse in all SVC area

    01.02

    01.03

    Remaining Corridor finsihing works

    Toilet works

    Grade slab Ramp and loading platform control

    building west side

    01.01

    01.00

    Activity start depend on clearance from

    Electomechanical teams

    Activity start depend on clearance from

    Electomechanical teams

    Dec-14

    Page 1 of 3

  • Customer : SEC - EOA

    Contractor : SIEMENS Sub Contractor: KUC

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2

    Total

    Cum %age

    completed

    18.10.2014.

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    SIEMENS

    FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)

    Sl. No. Unit

    QUANTITY

    Remarks ACTIVITY

    Control Building works 01.00

    Dec-14

    P

    A

    100% P

    100% A

    50% P

    60% A

    50%P

    60% A

    25% P

    25% A

    100% P

    90% A

    0% P

    0% A ;

    0% P

    0% A

    Valve cooler Pipe support foundation pedestals

    west side

    Valve Cooler foundations

    03.01

    Readiness of 230 kV cable trench/duct bank03.03

    Readiness of control cable trench Filter area

    03.04Readiness of Control cable trench/ duct bank

    North Side

    04.00

    03.00

    04.01

    03.02 Readiness of control cable trench East side

    Trenches/duct banks

    Activity completeion depend on clearance from

    Electrical installation teams

    04.03 Remaining valve cooler trench

    04.02Valve cooler pipe support foundation pedestals

    East side

    Page 2 of 3

  • Customer : SEC - EOA

    Contractor : SIEMENS Sub Contractor: KUC

    12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2

    Total

    Cum %age

    completed

    18.10.2014.

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    Sat

    Su

    n

    Mo

    n

    Tu

    e

    Wed

    Th

    u

    Fri

    SIEMENS

    FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)

    Sl. No. Unit

    QUANTITY

    Remarks ACTIVITY

    Control Building works 01.00

    Dec-14

    20% P

    10% A

    0% P

    0% A

    0% P

    0% A

    25% P

    20% A

    0% P

    0% A

    0% P

    0% A

    0% P

    0% A

    Muhammad Faisal Jelani

    Siemens

    05.01 Trench pad works

    05.00

    07.00

    06.01 PACU foundation Finsihing

    05.02 Trench wall works

    06.00 PACU foundation

    Lighting mast and lighting pole foundation

    08.00 Septic tank

    Auxilary tansformer foundation/ trench

    09.00Installation of all direct buried pipes for

    outdoor equipment

    10.00Installation of all direct buried pipes for

    lighting pole/lighting mast foundation

    Page 3 of 3