3 Week Schedule
-
Upload
tori-small -
Category
Documents
-
view
217 -
download
3
description
Transcript of 3 Week Schedule
-
Customer : SEC - EOA
Contractor : SIEMENS Sub Contractor: KUC
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
Total
Cum %age
completed
18.10.2014.
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
15% P
15% A
0% P
0% A
0% P
0% A
0% P 0
0% A
SIEMENS
FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)
Sl. No. Unit
QUANTITY
Remarks ACTIVITY
Control Building works
Base coarse in all SVC area
03.00
02.01
Trenches/duct banks
02.00 Base coarse in all SVC area
01.02
01.03
Remaining Corridor finsihing works
Toilet works
Grade slab Ramp and loading platform control
building west side
01.01
01.00
Activity start depend on clearance from
Electomechanical teams
Activity start depend on clearance from
Electomechanical teams
Dec-14
Page 1 of 3
-
Customer : SEC - EOA
Contractor : SIEMENS Sub Contractor: KUC
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
Total
Cum %age
completed
18.10.2014.
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
SIEMENS
FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)
Sl. No. Unit
QUANTITY
Remarks ACTIVITY
Control Building works 01.00
Dec-14
P
A
100% P
100% A
50% P
60% A
50%P
60% A
25% P
25% A
100% P
90% A
0% P
0% A ;
0% P
0% A
Valve cooler Pipe support foundation pedestals
west side
Valve Cooler foundations
03.01
Readiness of 230 kV cable trench/duct bank03.03
Readiness of control cable trench Filter area
03.04Readiness of Control cable trench/ duct bank
North Side
04.00
03.00
04.01
03.02 Readiness of control cable trench East side
Trenches/duct banks
Activity completeion depend on clearance from
Electrical installation teams
04.03 Remaining valve cooler trench
04.02Valve cooler pipe support foundation pedestals
East side
Page 2 of 3
-
Customer : SEC - EOA
Contractor : SIEMENS Sub Contractor: KUC
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
Total
Cum %age
completed
18.10.2014.
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
Sat
Su
n
Mo
n
Tu
e
Wed
Th
u
Fri
SIEMENS
FOUR WEEK CONSTRUCTION SCHEDULE (CIVIL WORKS)
Sl. No. Unit
QUANTITY
Remarks ACTIVITY
Control Building works 01.00
Dec-14
20% P
10% A
0% P
0% A
0% P
0% A
25% P
20% A
0% P
0% A
0% P
0% A
0% P
0% A
Muhammad Faisal Jelani
Siemens
05.01 Trench pad works
05.00
07.00
06.01 PACU foundation Finsihing
05.02 Trench wall works
06.00 PACU foundation
Lighting mast and lighting pole foundation
08.00 Septic tank
Auxilary tansformer foundation/ trench
09.00Installation of all direct buried pipes for
outdoor equipment
10.00Installation of all direct buried pipes for
lighting pole/lighting mast foundation
Page 3 of 3