CECE 4270 & CEQS 3230 Miss Samira Said Al Esry DEP ARTMENT OF ENGINEERING 1

Transcript of 3-Project Organisation 2

Page 1: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 1/34

CECE 4270 & CEQS 3230

Miss Samira Said Al Esry

DEPARTMENT OF ENGINEERING

1

Page 2: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 2/34

 

ConceptionFeasibility &

Selection

Design &

PlanningDevelopment

CloseoutOperationsDe-

commissioning

2

Page 3: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 3/34

Fundamentals: Risk

Payment Methods

Lump Sum / fixed price

Time & materials - Unit Prices

Cost Plus Percentage

Cost Plus Fixed Fee

Guaranteed Maximum Price

Incentive

3

Page 4: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 4/34

Involves identifying, analysing and respondingto risks throughout the project life cycle, in thebest interest of meeting project objectives

Can improve project success

Help in project selection, scope determinationand realistic development of schedules and cost

estimates

Schwalbe, 2006

4

Page 5: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 5/34

Uncertainty inherent in plans and the possibility

of something happening that can affect the

prospects of achieving business or project goalsBS6079-3:2000

Risk is the likelihood of an event or hazard

impacting the project

5

Page 6: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 6/34

In commerce, a ‘high risk venture’ implies a

potential for large gains as well as potential for

large losses

Where there are opportunities there are risks

All projects require risk management, risk

monitoring and risk control

6

Page 7: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 7/34

Table 3-1: Potential negative risk conditions associated with each knowledge area

Knowledge Area Risk Conditions

IntegrationInadequate planning; poor resource allocation; poor integration management;

lack of post-project review

Scope Poor definition of scope or work packages; incomplete definition

Time

Errors in estimating time or resource availability; errors in determining the

critical path; poor allocation and management of float; early release of

competitive products

Cost Estimating errors; inadequate productivity, cost, change, or contingency

QualityPoor attitude toward quality; substandard design/materials/workmanship;

inadequate quality assurance program

Human ResourcesPoor conflict management; poor project organisation and definition of

responsibilities; absence of leadership

CommunicationsCarelessness in planning or communicating; lack of consultation with key

stakeholders

Risk Ignoring risk; unclear analysis of risk; poor insurance management

Procurement Unenforceable conditions or contracts clauses; adversarial relations

Source: Wideman, R. Max, “Project and Program Risk Management: A Guide to Managing Project Risks & Opportunities”, Upper Darby,PA: Project Management Institute, 1992, II  – 4.

Page 8: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 8/34

Technical / quality/ performance risks: include risksassociated with unproven technology, complextechnology, changes to technology, unrealisticperformance goals, etc.

Project management risks: includes improperschedule and resource planning, poor project planning,improper project management methodologies.

Organisational risks: include resource conflicts due to

multiple projects; unrealistic scope, time and costobjectives; lack of funding.

External risks: include new laws or regulations, labourissues, weather, changes in ownership, etc.

Page 9: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 9/34

Records and other sources of historical data

Relevant experience

Reviews of research into project success and

failure

Market testing and research

Application of behavioural, financial, economic,

engineering and/or other relevant modelsUse of specialist and/or external expertise

9

Page 10: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 10/34

Medium

Small risk Medium

Big risk

Likelihood/

probability

Severity of impact

Impact can be in terms of cost, time, quality, reputation,

safety

1010

Figure 3-1: Risk classification

based on likelihood of occurrence

and impact on project

Page 11: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 11/34

Cost(OMR) Delay Quality Reputation

Major

ImpactExtra

100,000s

Several

months

Severe

impairment or loss

of a function

Negative publicity in

major news channels

Loss of public trust

Significant impact onGoodwill

Medium

impact

Extra 10,000s A few

weeks

Some impairment

of a major

function

Some impact on

Goodwill

Low

Impact

Extra 1,000s A few

days

Some impairment

of a minor

function

Minor impact on

Goodwill

11

Table 3-2: Sample Impact / Effect for risk assessment

Page 12: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 12/34

Response: Negative risks

Response/ treatment Summary

Accept Continue without altering the project goals or approach

Eliminating or avoiding Changing or abandoning goals specifically associated with

the risk in question, or choosing alternative approaches/processes that make the risk no longer relevant

Risk sharing Sharing risks in part or in full with another stakeholder who

could be involved solely to facilitate risk treatment, e.g. an

insurer

Reducing thelikelihood Changing project approach, identifying causal links betweenthreat and impact, or causes of threats, and intervening to

mitigate occurrence, acting to reduce the threat

Reducing the impacts Developing contingency plans for responding to the threat if

it occurs, even if other steps have been taken to minimize the

risk

12

Table 3-3: Basic response strategies for risks

Page 13: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 13/34

Contractors are risk averse

Risks that can be controlled by contractor,contractor will manage them rather than reduce

chargesRisks that cannot be controlled by contractor,contractor will typically reduce charges so

owner assumes themHigh contractor risks: higher price, morechances for delays

13

Page 14: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 14/34

14

Likelihood

(L) 

Severity

(S) 

1  Very unlikely  1  No impact or harm 

2  Unlikely  2  Low Impact  –  minor injury – no lost time 

3  Likely  3  Medium impact  – injury or ill health OVER 3 days lost time 

4  Very Likely  4  High impact  – major injury or possible loss, including death 

5  Probable  5  Very high impact  –  multiple casualties or loss of more than one

life 

5 10 15 20 25

4 8 12 16 20

3 6 9 12 15

2 4 6 8 10

1 2 3 4 5

HIGH

MEDIUM

LOW

Page 15: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 15/34

Fundamentals

Payment Methods

Fixed price or Lump Sum

Time and Materials (T&M) -Unit Prices

Cost reimbursableCost Plus Percentage

Cost Plus Fixed FeeGuaranteed Maximum Price

Incentive

15

Page 16: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 16/34

Set a specific, firm price for the goods andservices.

Owner and contractor agree on a well-defined

deliverable.Lower owner risks, biggest risk borne by thecontractor.

Typically used with traditional design/bid/build

Typically results in a desire to finish the projectin minimum time, with minimizes cost andquality uncertainty.

16

Page 17: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 17/34

Example:

Owner and contractor enter into a Lump Sum

agreement, OMR 20,000. The actual costsincurred by the contractor are OMR 18,500.

Price charged to owner:

Contractor profit:

17

Page 18: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 18/34

Fundamentals

Payment Method

Lump SumUnit Prices

Cost Plus Percentage

Cost Plus Fixed FeeGuaranteed Maximum Price

Incentive

18

Page 19: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 19/34

Time and materials contracts are a crossbetween fixed price and cost-reimbursable.

The full amount of material costs is not knownat the time of contract awarding: the costs willcontinue to grow during the contract’s life.

Unit rates (agreement of charges per unit ofwork) may be used to preset certain portions of

the project.The owner bears the biggest risk.

19

Page 20: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 20/34

Fundamentals

Payment Method

Lump Sum

Unit Prices

Cost Plus Percentage

Cost Plus Fixed Fee

Guaranteed Maximum Price

Incentive

20

Page 21: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 21/34

Owner pays actual cost plus a percentage fee

Used if price cannot be determined in another

way and for urgency (e.g. ill-defined risky scope)

Maximum flexibility for owner (change orders)

High risk for owner

Little incentives for contractor to improve

efficiencyNo consideration of quality in payment

Permits collaboration at early stages – minimum

negotiation time, fear of commitment21

Page 22: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 22/34

Example:Your company has entered into a Cost plusPercentage contract with contractor X. At the endof the project the contractor’s actual costs are

OMR10,000. The contract percentage is 2%. Whatis the price charged to the owner? What is thecontractor’s profit? 

Price charged:

Contractor profit:

22

Page 23: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 23/34

Fundamentals

Payment Method

Lump SumUnit Prices

Cost Plus Percentage

Cost Plus Fixed FeeGuaranteed Maximum Price

Incentive

23

Page 24: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 24/34

Owner agrees to pay the cost of workplus a fixed fee

Unknown cost up-front

Used if the price cannot be determinedin another manner

Fee is independent of project duration

Little incentive to reduce costHigh incentive to finish early

24

Page 25: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 25/34

Example:

Owner and contractor enter into Cost plus fixedfee agreement with the owner agreeing to pay

the contractor his costs plus an additionalOMR500. The actual costs were OMR3000.What is..

The price charged to the owner:Contractor profit:

25

Page 26: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 26/34

100%

100%

0%

0%

Lump Sum

CPFF

CP%

Contractor’s risk  Owner’s risk 

26

Figure 3-2: Risk sharing meter; comparing between lump sum, CPFF &

CPPC

Page 27: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 27/34

FundamentalsPayment Method

Lump Sum

Unit Prices

Cost Plus Percentage

Cost Plus Fixed Fee

Guaranteed Maximum Price

Incentive

27

Page 28: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 28/34

Same as Cost Plus Fixed Fee (CPFF), but with a

Guaranteed Maximum Price (GMP)

Contractor assumes any risks of cost goingbeyond GMP

Quality may be sacrificed to remain below GMP

28

Page 29: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 29/34

Fundamentals

Payment Method

Lump Sum

Unit Prices

Cost Plus Percentage

Cost Plus Fixed Fee

Guaranteed Maximum Price

Incentive

29

Page 30: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 30/34

Owner and contractor agreeing to a ratio forsharing savings and overruns (e.g. 80/20)

If savings of 1000, owner’s cost is reduced by800 and contractor’s profit is increased by 200 

If overrun of 1000, owner shoulders 800 andcontractor shoulders 200

Can have limitations on price or profit

30

Page 31: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 31/34

Target Estimate contract2% basic markup

70/30 O/C sharing arrangement

Original estimate: 10,000,000 OMROwner’s payment?= Actual cost + [markup*estimate] +

[contractor’s share*(estimate-actual cost)]

Contractors Profit/loss?= Price charged to owner – 

Contractor actual cost

Owner’s savings/losses= Estimate + [markup*Estimate] – 

owner’s payment 

31

Page 32: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 32/34

Estimate 10000000Mark-up 2%

Contractor share 30%

Owner Share 70%

Actual cost Owner's PaymentContractor's Gross

Profit

Owner's

Savings/Losses8000000

8500000

9000000

9500000

10000000

10500000

11000000

11500000

12000000

32

Page 33: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 33/34

Estimate 10000000Mark-up 2%

Contractor share 30%

Owner Share 70%

Actual cost Owner's PaymentContractor's Gross

Profit

Owner's

Savings/Losses8000000 8800000 800000 1400000

8500000 9150000 650000 1050000

9000000 9500000 500000 700000

9500000 9850000 350000 350000

10000000 10200000 200000 0

10500000 10550000 50000 -350000

11000000 10900000 -100000 -700000

11500000 11250000 -250000 -1050000

12000000 11600000 -400000 -1400000

33

R f

Page 34: 3-Project Organisation 2

8/10/2019 3-Project Organisation 2

http://slidepdf.com/reader/full/3-project-organisation-2 34/34

ReferencesDr. Lee, S. (2007). Presentation to Project Management course in

MIT.

“Project Management for Construction” by Chris Hendrickson

available at http://pmbook.ce.cmu.edu/ 

Schwalbe, K., Information Technology Project management, 4th 

Edition, 2006, Thomson Course Technology

Harold Kerzner, Ph.D., Project Management A systems approach

to planning, scheduling & controlling, 9th ed., 2006, John Wiley

& Sons, Inc.

Heldman, Kim, PMP: Project Management Professional, Study

Guide, 3rd edition, 2005, Wiley Publishing