3 Economics Gas Generation Cris
-
Upload
sajjanmishra -
Category
Documents
-
view
216 -
download
0
Transcript of 3 Economics Gas Generation Cris
-
7/27/2019 3 Economics Gas Generation Cris
1/11
Economics of Gas Based PowerGeneration
May 2010
-
7/27/2019 3 Economics Gas Generation Cris
2/11
2.
Given the right price, Natural Gas can play a large role in Indias Power SupplyBasket
Fuel Diversification
Fuel Diversification
Indias Power Generation mix is considerably gravitated towards coal based power generation
The current capacity addition underway accentuates this dependence on coal as a generation source
Indias Power Generation mix is considerably gravitated towards coal based power generation
The current capacity addition underway accentuates this dependence on coal as a generation source
Expected Coal Shortages
Expected Coal Shortages
CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this
decade
The Production from captive coal blocks is slow to take off
CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this
decade
The Production from captive coal blocks is slow to take off
Smaller Gestation Period leading to Faster Capacity Additions
Smaller Gestation Period leading to Faster Capacity Additions
Greenfield LNG Based Power Plants can be set up in a period of 28-30 months
Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months
Greenfield LNG Based Power Plants can be set up in a period of 28-30 months
Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months
Peaking Ability
Peaking Ability
Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand
Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand
Comparatively Clean and Lean Source of Power
Comparatively Clean and Lean Source of Power
About 50% lesser emissions than a coal based station
Land and Water Requirement is also substantially lower
About 50% lesser emissions than a coal based station
Land and Water Requirement is also substantially lower
-
7/27/2019 3 Economics Gas Generation Cris
3/11
3.
Current Trends in Capital and Operating Costs
The Capital Cost for a Natural Gas based station in Combined Cycle are in therange of INR 3.5 Crore/ MW
CERC has notified the Tariff Regulations for control period 2009-14:
The O&M expenses have been fixed as: INR 15.65 Lakh/ MW/ year escalated at 5.72% perannum
Auxiliary Consumption for Combined Cycle stations has been stipulated as 3% of Energy
Generated and 1% for Open Cycle units
The Station Heat Rate for Advance class turbines range from 1700- 1800 Kcal/
KWh
LNG based Power Stations at Terminals can achieve better operational andcost parameters due to Cold Energy Utilization
-
7/27/2019 3 Economics Gas Generation Cris
4/11
4.
Fixed Cost of Gas based stations are considerably lower than coal basedstations
The Fixed Cost per unit ranges from ~85 paise to 120 paise/ unit and compares
quite favourably to coal based supercritical stations
The levellized fixed cost is ~99 paise per unit vis--vis a levellized fixed cost of nearly 150paise/ unit for a coal based supercritical station
Fixed Cost/ KWh
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
2011
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
-
7/27/2019 3 Economics Gas Generation Cris
5/11
5.
Long Term Tariffs benchmarked with Case-I Winning Bids
2.722.88 2.89 2.9
3.27 3.29
0
1
2
3
4
Maharashtra Maharashtra Haryana Haryana Maharashtra Maharashtra
Lanco Emco Adani GMR Indiabulls Adani
Rs./
kWh(Levelized)
For Natural Gas to be competitive in the Long Term Markets, a levellized Gas Priceof USD 7- USD 8 per MMBTU (Delivered) is sustainable for achieving a 16% RoE
The Developer shall also realize incremental revenues from CER benefits
Case-I bids won inthe last 3 years arein the range of Rs.2.72/ kWh to Rs.3.29/ kWh
FY 08 FY 08 FY 08 FY 08 FY 09 FY 09
-
7/27/2019 3 Economics Gas Generation Cris
6/11
6.
Merchant Sale Economics
The Short Term tariffs have seen wide fluctuations in their yearly, seasonal and
intra-day patterns
Although a short term window exists for pure merchant operations, in the longer
term an appropriate mix shall have to be evolved by generators to hedge against
demand and price risks
The approx. delivered gas price at various merchant prices can be:
INR 4/ Unit: USD 9/ MMBTU
INR 4.5/ Unit: USD 11.5/ MMBTU
INR 5/ Unit: USD 12/ MMBTU
3.37
4.53
5.61
7.07
6.37
4.7
5.19
7.89
6.91
7.24
4.64
4.69
4.84
3
4
5
6
7
8
2007Q3
2007Q4
2008Q1
2008Q2
2008Q3
2008Q4
2009Q1
2009Q2
2009Q3
2009Q4
2010Q1
2010Q2
2010Q3
Rs.perunit
-
7/27/2019 3 Economics Gas Generation Cris
7/11
7.
0.11Financing Cost (Rs perunit of Consumption)
0.46
Operations Cost (Rsper unit ofConsumption)
3%
Escalation in per unit
power purchase cost
2.96Power Purchase Cost(Rs/Unit)
Cost Details Projected ARR of Gujarat
0
10000
20000
30000
40000
50000
60000
70000
80000
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Year
Rs.
Crores
Power Purchase Cost Operating Cost Financing Cost
3.583.553.543.573.603.623.653.683.713.75Tariff Under Group CaptiveScheme (Rs/kWh)
3.583.513.453.423.393.363.333.293.263.24
Industrial Tariff (Under
Open access) (Rs/kWh)
2019201820172016201520142013201220112010Particular
Projected HT tariffs at 10% discountProjected HT tariffs at 10% discount
Note: Cross Subsidy surcharge is not applicable in case of a Group Captive Power Plant.Accordingly realizations under the Group Captive Scheme are better
Sale to Industrial Consumers Tariffs based on 10% discount to projected HTTariffs
-
7/27/2019 3 Economics Gas Generation Cris
8/11
8.
Sale to Industrial Consumers Netbacks
9.61
9.953.70
3.80
9.40
9.50
9.60
9.70
9.80
9.90
10.00
Sale to Industrial Consumer Captive Sale
3.64
3.66
3.68
3.70
3.72
3.74
3.76
3.78
3.80
3.82
Gas (USD per MMBtu) Power Tariff (Rs. Per kWh)
-
7/27/2019 3 Economics Gas Generation Cris
9/11
9.
Comparison with other fuels
1.00
1.47
1.90
1.47
1.98
1.47
0.00
3.70
2.03
0.99
2.37
0.99
2.71
0.99
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.504.00
Rs/ KWh
Pithead
Coal
Station
Coal
Station-
1000 KM
from Mine
Imported
Coal-
Coast
Hydro Natural
Gas @ $6
Per
MMBTU
Natural
Gas @ $7
Per
MMBTU
Natural
Gas @ $8
Per
MMBTU
Variable Charge Fixed Charge
Natural Gas compares favourably with competing fuels till a price of USD 7- USD 8
per MMBTU delivered
However long term pricing certainty shall be an imperative as the Indian PowerMarkets are coal dominated
-
7/27/2019 3 Economics Gas Generation Cris
10/11
10.
Given the right price, Natural Gas can play a large role in Indias Power SupplyBasket
Fuel DiversificationFuel Diversification
Indias Power Generation mix is considerably gravitated towards coal based power generation
The current capacity addition underway accentuates this dependence on coal as a generation source
Indias Power Generation mix is considerably gravitated towards coal based power generation
The current capacity addition underway accentuates this dependence on coal as a generation source
Expected Coal ShortagesExpected Coal Shortages
CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this
decade
The Production from captive coal blocks is slow to take off
CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this
decade
The Production from captive coal blocks is slow to take off
Smaller Gestation Period leading to Faster Capacity AdditionsSmaller Gestation Period leading to Faster Capacity Additions
Greenfield LNG Based Power Plants can be set up in a period of 28-30 months
Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months
Greenfield LNG Based Power Plants can be set up in a period of 28-30 months
Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months
Peaking AbilityPeaking Ability
Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand
Comparatively Clean and Lean Source of PowerComparatively Clean and Lean Source of Power
About 50% lesser emissions than a coal based station
Land and Water Requirement is also substantially lower
About 50% lesser emissions than a coal based station
Land and Water Requirement is also substantially lower
-
7/27/2019 3 Economics Gas Generation Cris
11/11
11.
CRISIL Risk and Infrastructure Solutions Limited
A Subsidiary of CRISIL Limited, a Standard & Poors company
www.crisil.com