3 Economics Gas Generation Cris

download 3 Economics Gas Generation Cris

of 11

Transcript of 3 Economics Gas Generation Cris

  • 7/27/2019 3 Economics Gas Generation Cris

    1/11

    Economics of Gas Based PowerGeneration

    May 2010

  • 7/27/2019 3 Economics Gas Generation Cris

    2/11

    2.

    Given the right price, Natural Gas can play a large role in Indias Power SupplyBasket

    Fuel Diversification

    Fuel Diversification

    Indias Power Generation mix is considerably gravitated towards coal based power generation

    The current capacity addition underway accentuates this dependence on coal as a generation source

    Indias Power Generation mix is considerably gravitated towards coal based power generation

    The current capacity addition underway accentuates this dependence on coal as a generation source

    Expected Coal Shortages

    Expected Coal Shortages

    CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this

    decade

    The Production from captive coal blocks is slow to take off

    CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this

    decade

    The Production from captive coal blocks is slow to take off

    Smaller Gestation Period leading to Faster Capacity Additions

    Smaller Gestation Period leading to Faster Capacity Additions

    Greenfield LNG Based Power Plants can be set up in a period of 28-30 months

    Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months

    Greenfield LNG Based Power Plants can be set up in a period of 28-30 months

    Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months

    Peaking Ability

    Peaking Ability

    Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand

    Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand

    Comparatively Clean and Lean Source of Power

    Comparatively Clean and Lean Source of Power

    About 50% lesser emissions than a coal based station

    Land and Water Requirement is also substantially lower

    About 50% lesser emissions than a coal based station

    Land and Water Requirement is also substantially lower

  • 7/27/2019 3 Economics Gas Generation Cris

    3/11

    3.

    Current Trends in Capital and Operating Costs

    The Capital Cost for a Natural Gas based station in Combined Cycle are in therange of INR 3.5 Crore/ MW

    CERC has notified the Tariff Regulations for control period 2009-14:

    The O&M expenses have been fixed as: INR 15.65 Lakh/ MW/ year escalated at 5.72% perannum

    Auxiliary Consumption for Combined Cycle stations has been stipulated as 3% of Energy

    Generated and 1% for Open Cycle units

    The Station Heat Rate for Advance class turbines range from 1700- 1800 Kcal/

    KWh

    LNG based Power Stations at Terminals can achieve better operational andcost parameters due to Cold Energy Utilization

  • 7/27/2019 3 Economics Gas Generation Cris

    4/11

    4.

    Fixed Cost of Gas based stations are considerably lower than coal basedstations

    The Fixed Cost per unit ranges from ~85 paise to 120 paise/ unit and compares

    quite favourably to coal based supercritical stations

    The levellized fixed cost is ~99 paise per unit vis--vis a levellized fixed cost of nearly 150paise/ unit for a coal based supercritical station

    Fixed Cost/ KWh

    0.00

    0.20

    0.40

    0.60

    0.80

    1.00

    1.20

    1.40

    2011

    2013

    2015

    2017

    2019

    2021

    2023

    2025

    2027

    2029

    2031

    2033

    2035

  • 7/27/2019 3 Economics Gas Generation Cris

    5/11

    5.

    Long Term Tariffs benchmarked with Case-I Winning Bids

    2.722.88 2.89 2.9

    3.27 3.29

    0

    1

    2

    3

    4

    Maharashtra Maharashtra Haryana Haryana Maharashtra Maharashtra

    Lanco Emco Adani GMR Indiabulls Adani

    Rs./

    kWh(Levelized)

    For Natural Gas to be competitive in the Long Term Markets, a levellized Gas Priceof USD 7- USD 8 per MMBTU (Delivered) is sustainable for achieving a 16% RoE

    The Developer shall also realize incremental revenues from CER benefits

    Case-I bids won inthe last 3 years arein the range of Rs.2.72/ kWh to Rs.3.29/ kWh

    FY 08 FY 08 FY 08 FY 08 FY 09 FY 09

  • 7/27/2019 3 Economics Gas Generation Cris

    6/11

    6.

    Merchant Sale Economics

    The Short Term tariffs have seen wide fluctuations in their yearly, seasonal and

    intra-day patterns

    Although a short term window exists for pure merchant operations, in the longer

    term an appropriate mix shall have to be evolved by generators to hedge against

    demand and price risks

    The approx. delivered gas price at various merchant prices can be:

    INR 4/ Unit: USD 9/ MMBTU

    INR 4.5/ Unit: USD 11.5/ MMBTU

    INR 5/ Unit: USD 12/ MMBTU

    3.37

    4.53

    5.61

    7.07

    6.37

    4.7

    5.19

    7.89

    6.91

    7.24

    4.64

    4.69

    4.84

    3

    4

    5

    6

    7

    8

    2007Q3

    2007Q4

    2008Q1

    2008Q2

    2008Q3

    2008Q4

    2009Q1

    2009Q2

    2009Q3

    2009Q4

    2010Q1

    2010Q2

    2010Q3

    Rs.perunit

  • 7/27/2019 3 Economics Gas Generation Cris

    7/11

    7.

    0.11Financing Cost (Rs perunit of Consumption)

    0.46

    Operations Cost (Rsper unit ofConsumption)

    3%

    Escalation in per unit

    power purchase cost

    2.96Power Purchase Cost(Rs/Unit)

    Cost Details Projected ARR of Gujarat

    0

    10000

    20000

    30000

    40000

    50000

    60000

    70000

    80000

    2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

    Year

    Rs.

    Crores

    Power Purchase Cost Operating Cost Financing Cost

    3.583.553.543.573.603.623.653.683.713.75Tariff Under Group CaptiveScheme (Rs/kWh)

    3.583.513.453.423.393.363.333.293.263.24

    Industrial Tariff (Under

    Open access) (Rs/kWh)

    2019201820172016201520142013201220112010Particular

    Projected HT tariffs at 10% discountProjected HT tariffs at 10% discount

    Note: Cross Subsidy surcharge is not applicable in case of a Group Captive Power Plant.Accordingly realizations under the Group Captive Scheme are better

    Sale to Industrial Consumers Tariffs based on 10% discount to projected HTTariffs

  • 7/27/2019 3 Economics Gas Generation Cris

    8/11

    8.

    Sale to Industrial Consumers Netbacks

    9.61

    9.953.70

    3.80

    9.40

    9.50

    9.60

    9.70

    9.80

    9.90

    10.00

    Sale to Industrial Consumer Captive Sale

    3.64

    3.66

    3.68

    3.70

    3.72

    3.74

    3.76

    3.78

    3.80

    3.82

    Gas (USD per MMBtu) Power Tariff (Rs. Per kWh)

  • 7/27/2019 3 Economics Gas Generation Cris

    9/11

    9.

    Comparison with other fuels

    1.00

    1.47

    1.90

    1.47

    1.98

    1.47

    0.00

    3.70

    2.03

    0.99

    2.37

    0.99

    2.71

    0.99

    0.00

    0.50

    1.00

    1.50

    2.00

    2.50

    3.00

    3.504.00

    Rs/ KWh

    Pithead

    Coal

    Station

    Coal

    Station-

    1000 KM

    from Mine

    Imported

    Coal-

    Coast

    Hydro Natural

    Gas @ $6

    Per

    MMBTU

    Natural

    Gas @ $7

    Per

    MMBTU

    Natural

    Gas @ $8

    Per

    MMBTU

    Variable Charge Fixed Charge

    Natural Gas compares favourably with competing fuels till a price of USD 7- USD 8

    per MMBTU delivered

    However long term pricing certainty shall be an imperative as the Indian PowerMarkets are coal dominated

  • 7/27/2019 3 Economics Gas Generation Cris

    10/11

    10.

    Given the right price, Natural Gas can play a large role in Indias Power SupplyBasket

    Fuel DiversificationFuel Diversification

    Indias Power Generation mix is considerably gravitated towards coal based power generation

    The current capacity addition underway accentuates this dependence on coal as a generation source

    Indias Power Generation mix is considerably gravitated towards coal based power generation

    The current capacity addition underway accentuates this dependence on coal as a generation source

    Expected Coal ShortagesExpected Coal Shortages

    CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this

    decade

    The Production from captive coal blocks is slow to take off

    CIL predicts a substantial shortfall in the quantum of its coal production and committed linkages during this

    decade

    The Production from captive coal blocks is slow to take off

    Smaller Gestation Period leading to Faster Capacity AdditionsSmaller Gestation Period leading to Faster Capacity Additions

    Greenfield LNG Based Power Plants can be set up in a period of 28-30 months

    Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months

    Greenfield LNG Based Power Plants can be set up in a period of 28-30 months

    Whereas, other conventional sources of have gestation periods ranging from 48 months-84 months

    Peaking AbilityPeaking Ability

    Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand Dedicated Plants operating in Open Cycle in proximity to Load Centers can meet Peak Demand

    Comparatively Clean and Lean Source of PowerComparatively Clean and Lean Source of Power

    About 50% lesser emissions than a coal based station

    Land and Water Requirement is also substantially lower

    About 50% lesser emissions than a coal based station

    Land and Water Requirement is also substantially lower

  • 7/27/2019 3 Economics Gas Generation Cris

    11/11

    11.

    CRISIL Risk and Infrastructure Solutions Limited

    A Subsidiary of CRISIL Limited, a Standard & Poors company

    www.crisil.com