-3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical...

150
? M S C - PA -3 -6 9 - 2 SUPPLEMENT 2 l/i" NATIONAL AERONAUTICS AND SPACE ADMINISTRATION ...................... APOLLO 9 MISSION REPORT SUPPLEMENT 2 ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... .......... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ............. .~.-.*.'.-.~.'.~.~.'.~. ............ ........... GUIDANCE, NAVIGATION, AND CONTROL SYSTEM PERFORMANCE ANALYSIS ........... ............ ........... ............ ........... ............ ........... ............ ........... ..... ..... , ..... ..... ..... ~.'.~_~_'_ ..__. ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... .... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... .:.:.:.. ... (NASA-TH-X-72261) APOLLC 9 MISSION N75-704 SUIDANCE, .......... .......... .......... NAVIGATICN, AND CCNTROL SYSTEH PEEFOBHANCE .......... .......... ~... .......... .......... .......... .......... .......... .......... .......... ........... ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ .......... B .~.'.~.'.~.~.~.~.~.~.~. ........... NALYSIS (NASA) 162 p Unclas 00/98 17335 MANNED SPACECRAFT CENTER

Transcript of -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical...

Page 1: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

?

M S C - PA -3 -6 9 - 2 SUPPLEMENT 2 l/i"

N A T I O N A L AERONAUTICS A N D SPACE ADMINISTRATION

...................... APOLLO 9 MISSION REPORT

SUPPLEMENT 2

........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... .......... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............

.............

.~.-.*.'.-.~.'.~.~.'.~. ............ ........... GUIDANCE, NAVIGATION, AND CONTROL

SYSTEM PERFORMANCE ANALYSIS ........... ............ ........... ............ ........... ............ ........... ............ ........... ..... ..... ,..... ..... ..... ~.'.~_~_'_ . . _ _ . ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ....

..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... ..... .:.:.:.. ... ( N A S A - T H - X - 7 2 2 6 1 ) APOLLC 9 M I S S I O N N75-704

S U I D A N C E , .......... .......... .......... NAVIGATICN, A N D C C N T R O L SYSTEH P E E F O B H A N C E .......... .......... ~ . . . .......... .......... .......... .......... .......... .......... .......... ........... ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............ ........... ............

.......... B

.~.'.~.'.~.~.~.~.~.~.~.

...........

N A L Y S I S (NASA) 162 p U n c l a s 00/98 17335

M A N N E D S P A C E C R A F T C E N T E R

Page 2: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

NATIONAL AERONAUTICS AND S P A C E A D M I N I S T R A T I O N

MANNED SPACECRAFT CENTER

HOUSTON, TEXAS

N o v e m b e r 1969

MSC-PA-R-69-2 Supplement 2

APOLLO 9 M I S S I O N RF2OEfT

SUPPLEMENT 2

GUIDANCE, NAVIGATI0P.T , AND CONTROL

S Y S T E M PERFORMANCE ANALYSIS

PREPARFD B Y

TRW S y s t e m s G r o u p

APPROVED BY

James A. M c D i v i t t ager , A p o l l o Spacecrart Program

Page 3: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

1 1 l76-H232-RO-W

P R O J E C T T E C H N I C A L R E P O R T TASK E - 3 8 B

A 2 0 L L O I X G U I D A N C E , N A V I G A T I O N A N D C O N T R O L S Y S T E M P E R F O R M A N C E A N A L Y S I S

R E P O R T

NAS 9-8166 15 M A Y 1969

Prepared for NATIONAL AERONAUTICS A N D SPACE ADMINISTRATION

MANNED SPACECRAFT CENTER HOUSTON, TEXAS

Approved by 9 7 W d I .

' J . 'E. Alexander, Manager Guidance and Control Systems De par tm e nt

Page 4: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

-’

~ -

TABLE OF CONTENTS

1.0 INTRODUCTION

1.1 General

1.2 Background

2.0 SUMMARY

3.0 CSM I M U PERFORMANCE

3.1 Ascent Vel o c i t y Comparison

4.0 CSM DIGITAL AUTOPILOT

4.1 T V C DAP Performance

4.1.1 A t t i tude E r r o r s

4.1.2 I g n i t i o n Transients

4.1.3 Manual Takeover

4.1.4 R o l l TVC DAP

4.1.5 S t r o k i n g Tests

4.2 RCS DAP Performance

4.2.1 RCS DAP Automatic Maneuvers

4.2.2 RCS DAP A t t i t u d e Hold

4.3 E n t r y DAP Performance

4.3.1 R o l l DAP Performance

4.3.2 P i t c h and Yaw Rate Damping

5.0 LM I M U PERFORMANCE

5.1 DPS 1 V e l o c i t y Comparison

Page

1-1

1-1

1-1

2-1

3-1

3-1

4-1

4-1

4-2

4-3

4-4

4-5

4-5

4-6

4-6

4-7

4-7

4-7

4-a

5-1

5-1

iii

Page 5: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

TABLE OF CONTENTS (Continued)

6.0 LM D I G I T A L AUTOPILOT

6.1 LM/CSM Docked Con f igu ra t i on

6.1.1 Docked DPS Burn

6.1.2 Slosh

6.1.3 Compliance

6.2 Descent Con f igu ra t i on

6.2.1 DPS I n s e r t i o n Burn

6.2.2 A t t i t u d e Hold

6.3 Ascent Con f igu ra t i on

6.3.1 Automatic Maneuver

6.3.2 A t t i t u d e Hold

6.3.3 Manual Contro l

6.3.4 C S I Burn

6.3.5 APS Burn t o Dep le t ion

7.0 LM/AGS/CES CONTROLLABILITY

7.1 DPS Phasing Burn (AGS)

7.1.1 Telemetry Q u a n t i z a t i o n Versus t h e Rate A t t i t u d e Phase Plane

7.1 .2 GTS Performance

i v

Page

6-1

6-1

6-1

6-3

6-5

6-5

6-6

6-7

6-7

6-7

6-8

6-8

6-9

6-9

7-1

7-1

7-1

7-4

Page 6: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

TABLE OF CONTENTS (Continued)

7.1.3 CG O f f s e t s

7.2 Descent Stage A t t i t u d e Hold (AGS)

7.2.1 Propel 1 an t Consumption

8.0 RENDEZVOUS

8.1 Onboard Nav iga t i ov

8.2 Rendezvous T a r g e t i n g

8.2.1 C S I Maneuver Eva lua t ion

8.2.2 T P I Maneuver Eva lua t ion

REFERENCES

V

Page

7-4

7-5

7-5

8-1

8-1

8-1

8-2

8-2

R- 1

Page 7: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

~ ~ ~~

LIST OF ILLUSTRATIONS

F igure

3-1 DELVX G&N Minus F i n a l S - I V B OMPT, W/O Compensation - Ascent

3-2 DELVY G&N Minus F i n a l S - I V B OMPT, W/O Compensation - Ascent

3-3 DELVZ G&N Minus F i n a l S - I V B OMPT, W/O Compensation - Ascent

3-4 DELVX G&N Minus S-IVB IU/TM, W/O Compensation - Ascent

3-5 DELVY G&N Minus S - I V B IU/TM, W/O Compensation - Ascent

3-6 DELVZ G&N Minus S- IVB IU/TM W/O Compensation - Ascent

3-7 DELVX G&N Minus S- IVB IU/TM, With Compensation - Ascent

3-8 DELVY G&N Minus S - I V B IU/TM, With Compensation - Ascent

3-9 DELVZ G&N Minus S- IVB IU/TM, With Compensation - Ascent

4-1 SPS 2 - A t t i t u d e E r r o r s

4-2 SPS 2 - Gimbal Commands and Gimbal P o s i t i o n s I

4-2a SPS 2 - Gimbal P o s i t i o n During I g n i t i o n T r a n s i e n t and 40% S t r o k i n g Tests

4-3 SPS 2 - Tr im Angles

4-4 SPS 3 - A t t i t u d e E r r o r s

4-5 SPS 3 - P i t c h Rates and A t t i t u d e E r r o r s Dur ing Rate MTVC

4-6 SPS 3 - Yaw Rates and A t t i t u d e E r r o r s Dur ing Rate MTVC

4-7 SPS 3 - Gimbal Commands and Gimbal P o s i t i o n s

Page

3-3

3-5

3-7

3-9

3-1 1

3-1 3

3-1 5

3-17

3-1 9

4-1 5

4-1 6

4-17’

4-18

4-1 9

4-20

4-21

4-22

v i i

Page 8: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

LIST OF ILLUSTRATIONS (Continued)

F igure Page

4-8 SPS 3 - Trim Angles

4-9 SPS 4 . - A t t i t u d e Errors

4-10 SPS 4 - Gimbal Commands and Gimbal P o s i t i o n s

4-11

4-12 SPS 5 - A t t i t u d e Er ro r s

4-13 SPS 5 - Gimbal Commands and Gimbal P o s i t i o n s

4-14

SPS 4 - Trim Angles

SPS 5 - Trim Angles

4-15 SPS 5 - Comparison o f Measured F i l te r Output and Computed F i l t e r Output

4-16 SPS 5 - Measured Gimbal P o s i t i o n s

4-17 Automatic Maneuversto SPS 2 A t t i t u d e - Body Rates

4-18 Automatic Maneuver t o SPS 2 A t t i t u d e - CDU Angles

4-19 Automatic Maneuver t o Docked DPS Burn A t t i t u d e - Body Rates

4-20 Automatic Maneuver t o Docked DPS Burn A t t i t u d e - CDU Angles

4-21 O r b i t Rate Automatic Maneuver - Body Rates

4-22 O r b i t Rate Automatic Maneuver - CDU Angles

4-23 A t t i t u d e Hold P r i o r t o SPS 3 - Roll Phase Plan

4-24 A t t i t u d e Hold P r i o r t o SPS 3 - Pitch Phase Plan

4-25 A t t i t u d e Hold P r i o r t o SPS 3 - Yaw Phase P lan

4-26 A t t i t u d e Hold P r i o r t o SPS 4 - Roll Phase Plan

4-27 A t t i t u d e Hold P r i o r t o SPS 4 - Pi tch Phase Plan

4-28 A t t i t u d e Hold P r i o r t o SPS 4 - Yaw Phase Plan

4-24

4-25

4-26

4-27

4-28

4-29

4-30

4-31

4-32

4-33

4-34

4-35

4-36

4-37

4-38

4-39

4-40

4-41

4-42

4-43

4-44

v i i i

Page 9: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

LIST OF ILLUSTRATIONS (Cont inued)

4-29

4-30

4-31

5- 1

5-2

5-3

5-4

5-5

5-6

6-1

6-2

6-3

6-4

6-5

6-6

6-7

6-8

6-9

6-1 0

F i g u r e

Commanded and Actual R o l l Angles Dur ing Entry

Yaw Thrus ter A c t i v i t y During Bank Angle Reversal

Yaw Thrus ter A c t i v i t y During Bank Angle Reversal

DELVX LM Minus CSM W/O Compensation - DPS 1

DELVY LM Minus CSM W/O Compensation - DPS 1

DELVZ LM Minus CSM W / O Compensation - DPS 1

DELVX LM Minus CSM With Compensation - DPS 1

DELVY LM Minus CSM With Compensation - DPS 1

DELVZ LM Minus CSM With Compensation - DPS 1

Docked DPS Burn P Ax is Phase Plane

LGC Angular Rates Versus Time Dur ing Manual T h r o t t l e P r o f i l e

Docked DPS Burn - CSM BMAG Rates

Docked DPS Burn - Vel o c i ty - to-be-gai ned

Docked DPS Burn - Time H i s t o r y o f GDA's and T h r o t t l e S e t t i n g

DPS I n s e r t i o n Burn - U Axis A t t i t u d e E r r o r s and J e t F i r i n g s

DPS I n s e r t i o n Burn - P Axis Phase Plane

DPS I n s e r t i o n Burn - V Axis Phase Plane

DPS I n s e r t i o n Burn - Veloc i ty- to-be-gained

DPS I n s e r t i o n Burn - GDA Time H i s t o r y

Page

4-45

4-46

4-47

5-5

5-7

5-9

5-1 1

5-1 3

5-1 5

6-1 2

6-1 3

6-14

6-1 5

6-1 6

6-1 7

6-18

6-1 9

6-20

6-21

i x

Page 10: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

LIST OF ILLUSTRATIONS (Continued)

Figure

6-11 Descent Con f igu ra t i on - A t t i t u d e Hold - P Ax is Phase Plane

6-12 Descent Con f igu ra t i on - A t t i t u d e Hold - U A x i s Phase Plane

6-13 Descent Con f igu ra t i on - A t t i t u d e Hold - V Axis Phase Plane

6-14 Ascent Con f igu ra t i on Automatic Maneuver - Rates

6-15 Ascent Con f igu ra t i on Automatic Maneuver - Gimbal Angles

6-16 Ascent Con f igu ra t i on - A t t i t u d e Hold - P Ax i s Phase Plane

6-17 Ascent Con f igu ra t i on - A t t i t u d e Hold - U Axis Phase Plane

6-18 Ascent Con f igu ra t i on - A t t i t u d e Hold - V A x i s Phase Plane

6-19 Ascent Con f igu ra t i on - P Ax is Phase Plane

6-20 Ascent Con f igu ra t i on - U Axis Phase Plane

6-21 Ascent Con f igu ra t i on - V Ax is Phase Plane

6-22 C S I Burn - P Axis Phase Plane

6-23 C S I Burn - U Ax is Phase Plane

6-24 C S I Burn - V Ax is Phase Plane

6-25 C S I Burn - Veloci ty- to-be-gained

6-26 APS Burn t o Dep le t i on - U Axis Phase Plane

6-27 APS Burn t o Dep le t i on - U Axis A t t i t u d e E r r o r s and J e t F i r i n g s

Page

6-22

6-23

6-24

6-25

6-26

6-27

6-28

6-29

6-30

6-31

6-32

6-33

6-34

6-35

6-36

6-37

-

6-38

X

Page 11: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

L I S T OF 1LLUSTRAT.IONS (Continued)

.

6-28

7- 1

7-2

7-3

7-4

7-5

7-6

7-7

7-8

8- 1

8- 2

8-3

8-4

8- 5

8-6

F igu re

APS Burn t o Dep le t ion - V A x i s A t t i t u d e E r r o r s and J e t F i r i n g s

Phase Plane o f A t t i t u d e & Rate Versus Log ic Vol t . P o l a r i t y

Log ic I n p u t Vo l t s as Generated by A t t i t u d e E r r o r s & Body Rates

LM 3 /Apo l lo 9 Time H i s t o r y P l o t o f Log ic I n p u t V o l t s Dur ing DPS 2 Burn

I

LM 3 /Apo l lo 9 Time H i s t o r y P l o t o f Ca lcu la ted Rates Dur ing DPS 2 Burn

LM 3 /Apo l lo 9 Time H i s t o r y P l o t o f P i t c h Rate as Tel emetered

LM 3 j A p o l l o 9 Time H i s t o r y P l o t o f A t t i t u d e E r r o r s Dur ing DPS 2 Burn

LM 3 /Apo l lo 9 Time H i s t o r y P l o t o f R o l l Rate Recorded I n f l i g h t

LM 3/Apol l o 9 Time H i s t o r y P l o t o f DPS Engine P o s i t i o n Dur ing DPS 2 Burn

S ta te Vector Comparison Versus Rendezvous Radar Marks - P x

S ta te Vector Comparison Versus Rendezvous Radar Marks - Py

S ta te Vector Comparison Versus Rendezvous Radar Marks - Pz

S ta te Vector Comparison Versus Rendezvous Radar Marks - V x

S ta te Vector Comparison Versus Rendezvous Radar Marks - V y

S ta te Vector Comparison Versus Rendezvous Radar Marks - V z

x i

Page

6-39

7-8

7-9

7-10

7-1 1

7-1 2

7-1 3

7-1 4

7-1 5

8-4

8-5

8-6

8-7

8-8

8-9

Page 12: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

LIST OF ILLUSTRATIONS (Continued)

Figure

Comparison o f CMC and BET R e l a t i v e P o s i t i o n Vector - X Component (NBY Coordinates)

Comparison o f CMC and BET R e l a t i v e P o s i t i o n Vector - Y Component (NBY Coordinates)

Comparison o f CMC and BET R e l a t i v e P o s i t i o n Vector - Z Component (NBY Coordinates)

8-7

8-8

8-9

Page

8-10

8-1 1

8-1 2

x i i

Page 13: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

LIST OF TABLES

3.1

4.1

4.2

4 .3

4 .4

4.5

5.1

8.1

8.2

8.3

8 . 4

8 .5

IMU Er ro r Sources , CSM Ascent

SPS Burn Data

P re - Ign i t ion Data

Rates and Attitude Errors During SPS Burns

Engine Gimbal Trim

Veloci ty-to-be-gained and Veloci ty Residua; s f o r SPS Burns $

Rendezvous Ta rge t ing Sumnary

Rendezvous Ta rge t ing Solu t ions

CDH Maneuver Eva1 u a t i on

Comparison o f TPI Solu t ions

PGNCS TPI Maneuver Evaluation

Page

3-21

4-10

4-1 1

4-12

4-13

4-14

8-1 3

8-14

8-1 5

8-1 5

8-16

x i i i

Page 14: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

1 .O INTRODUCTION

1.1 GENERAL

Th is r e p o r t presents t h e conclusions o f t h e analyses of t h e i n -

f l i g h t performance o f t h e Apo l l o 9 m iss ion (AS-504/CSM-l04/LM-3)

onboard guidance and nav iga t i on equipment and i s in tended as a supple-

ment t o the MSC Miss ion Report f o r Apo l l o 9. The r e p o r t was prepared

and submi t ted under MSC/TRW Task E-388 (G&C Test Ana lys is ) . The work repo r ted r e f l e c t s a working i n t e r f a c e between Task E-38B, MSC/TRW

Task A-50 ( T r a j e c t o r y Reconstruct ion) and MSC/TRW Task E-72A (Guidance

and Contro l System Ana lys is ) . The r e s u l t s o f these tasks a re h i g h l y in terdependent and the cooperat ion and suppor t o f t h e A-50 and E-72A task personnel are g r a t e f u l l y acknowledged.

1.2 BACKGROUND

The Apo l l o 9 miss ion was the f i r s t manned Lunar Module (LM) f l i g h t t e s t . The pr imary purpose o f the miss ion was t o eva lua te t h e LM systems

performance and per form se lec ted Command and Serv ice Module and Lunar Module (CSM/LM) Operations. Th is was the f i r s t f l i g h t f o r t h e opera t i on and checkout of t h e Abor t Guidance System (AGS). The most s i g n i f i c a n t GN&C a c t i v i t y occurred dur ing the f i f t h day o f the miss ion when t h e LM undocked from t h e CSM, performed burns s imu la t i ng the l u n a r miss ion and

concluded w i t h a rendezvous and docking w i t h t h e CSM. Overa l l , space-

c r a f t performance data and miss ion event t imes are presented i n t h e MSC

M iss ion Report f o r Apo l l o 9.

.

1-1

Page 15: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

2.0 SUMMARY

The i n e r t i a l subsystem performance was e x c e l l e n t d u r i n g the mission.

The c a p a b i l i t y o f a docked LM/CSM IMU al ignment was s u c c e s s f u l l y demon-

s t r a t e d .

Performance o f t he LM and CSM DAP was very good and complete ly nominal.

a t t i t u d e h o l d inves t iga ted , except t h e torque due t o the cg o f f s e t s

d u r i n g t h e u l lages .

preceding the docked DPS burn, the crew repor ted the presence o f apparent aerodynamic to rqu ing .

t o e i t h e r s u b s t a n t i a t e o r r e f u t e the cause o f the experienced to rqu ing .

P r i o r t o t h e LM DPS I n s e r t i o n burn, an ex terna l d i s t u r b i n g torque about the V-axis was ev ident .

No externa l torques were apparent d u r i n g the per iods o f CSM

During the per iod o f CSM-LM docked a t t i t u d e h o l d

Inadequate da ta were a v a i l a b l e d u r i n g t h a t p e r i o d

CES opera t ion d u r i n g t h e AGS DPS Phasing burn was nominal.

Performance o f t he spacecraf t n a v i g a t i o n systems d u r i n g the ren- dezvous p e r i o d was e x c e l l e n t . A l l updates suppl ied t o t h e LM guidance computer d u r i n g the rendezvous were from the rendezvous radar . A l l Concentr ic F l i g h t Plan burn s o l u t i o n s used were generated by the LGC.

2-1

Page 16: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

3.0 CSM IMU PERFORMANCE

3.1 ASCENT VELOCITY COMPARISON

Ana lys is o f the CM and LM IMU's were based on separate s tud ies . The

ana lys i s of t h e CM system was based on the S - I V B as a standard. Analys is o f t he LM I M U i s presented i n Sect ion 5.0 and i s based on the DPS docked burn.

Two f i n a l t r a j e c t o r i e s were generated by MSFC as a bas i s f o r

comparison f o r t he ascent phase, these being the "Edi ted S- IVB I U TM" t r a j e c t o r y and the "F ina l S - I V B Observed P o i n t Mass Tra jec to ry , "

(OPMT). Reasons f o r r e j e c t i o n o f t he l a t t e r a r e shown i n comparisons

o f F igures 3-1 through 3-3 w i t h F igures 3-4 through 3-6 which present

t h e uncompensated v e l o c i t y res idua ls f o r the ascent phase. As i n the

pas t , the OPMT was r e j e c t e d because o f more e r r a t i c t rends, and reasonable e r r o r se ts which e f f e c t e d a good boost comparison were

unachievable.

I n the ana lys i s o f Apo l l o 9, f l i g h t l oad values were used i n

p lace o f the data means as a basis of comparison w i t h the der ived

e r r o r s because the number o f p r e f l i g h t da ta p o i n t s were smal l and because some o f t he inst ruments were showing s t rong t rends immediately

p r i o r t o f l i g h t . The i n f l i g h t ( f r e e f a l l ) measured values were used

as comparisons t o the der ived data values f o r P I P A and I R I G b iases.

The CM e r r o r sources a re presented i n Table 3.1. None o f the e r r o r

sources exceeded the one-sigma bounds f rom the expected e r ro rs .

Comparison w i t h the p r e f l i g h t data t rends lends conf idence t o the de r i ved e r r o r se t . The compensated r e s i d u a l s f o r t h e ascent phase

a r e presented i n Figures 3-7 through 3-9.

Due t o the e x c e p t i o n a l l y good f i t t o t h e der ived da ta w i t h respec t t o the expected e r r o r s , no d iscuss ion o f the i n d i v i d u a l e r r o r sources i s necessary. One problem un re la ted t o A p o l l o i s ev iden t f rom

3-1

Page 17: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Figures 3-2 and 3-9. corrected by using the standard technique o f applying an offset velocity t o the Apollo data equivalent t o the time zero velocity difference between Apollo and Saturn data. acceleration domain where i t was observed tha t the Saturn S-IVB Y accelerometer sensed o u t p u t was approximately 1 f t /sec2 higher for the f i r s t four seconds o f f l i g h t than the Apollo sensed acceleration. has subsequently been established t h a t Saturn accelerometers are susceptible t o the l i f t -of f vibration environment and the f i rs t few seconds of Saturn data are suspect.

The f irst few seconds of velocity error could not be

The problem i s more apparent i n the

I t

3-2

Page 18: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

u)

I

L

-

8 9

3 3 rr)

3 3 -t

3 9 5

0 0 N

8 7

0

m I

Cr)

4

Page 19: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

- u) I 2

I

. 9

f

W r - I-

O 0 hl

0 0 -

0

Page 20: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

u) I

Page 21: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

rr)

- '.

-

* - -

0 0 9

8 v)

8 *

I I

Page 22: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

z I

v) hl

I

Page 23: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

v) I

rr)

I c

0 0 9

8 v)

0 0 *

0 0 c3

0 0 N

0 0 7

0

U I = - s

m I

m F

Page 24: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Y

I Z m o

Page 25: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

0 0 I c

L L

w - x I-

O 0 hl

0 0 c

0

h

I m F

Page 26: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

0 0 I c

v) cy I

Page 27: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Q

.: .! .! 5 5 5

N L \ D m m - r - m a < < 4 < " O N "

Z Z Z Z j O O o o o o o o o 4 0 4 o o o o o o o o o I O I , ,

u

f E

2 3 a

2 f

3

4 1

u

u m

h 0 W

Y

c

z m Y

V . Y U al C C 0 U

0

9 m ld TI

m m m

$

%

f

2

P m A

+

... cl 0

al

4 ..-I

rd

c h 0

4

2 In fi

V

7

.r(

m

m ... V

m m d

.- a x Y

VI

E al m

M . 2 E 3

0 c

c

... c

... m > V V

V m

m Y m

L

I

w

n tu I-

3-21

Page 28: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4.0 CSM DIGITAL AUTOPILOT

The major p o r t i o n o f t h e CSM and CSM/LM c o n t r o l a c t i v i t y du r ing the m iss ion was c a r r i e d o u t under SCS c o n t r o l . Per iods o f G&N c o n t r o l were

genera l l y l i m i t e d t o the automatic maneuvers t o t h e SPS and docked DPS burn a t t i t u d e s , the a t t i t u d e ho ld mode f o l l o w i n g these automat ic

maneuvers, and a l l o f t he SPS burns. A f t e r t he SPS 6 burn,the DAP

was i n c o n t r o l du r ing t h e o r b i t r a t e automat ic maneuver. A l l o f t he SPS burns and most o f t he automatic maneuvers and pe r iods o f a t t i t u d e

h o l d were analyzed; however, most o f t he a n a l y s i s focused on the RCS

and TVC DAP ope ra t i on w i t h t h e CSM/LM i n the docked c o n f i g u r a t i o n .

An except ion t o t h i s was the o r b i t r a t e automat ic maneuver which was

performed by the CSM alone.

Periods o f DAP c o n t r o l analyzed were:

TVC DAP

SPS burns 1 t o 8. Burns 1, 6 and 8 were n o t examined i n as much d e t a i l as the o the rs because o f t h e i r s h o r t d u r a t i o n . DAP Automatic Maneuvers

o Maneuvers t o a l l o f the SPS burns except SPS burns 5, 6 and 8 ( d e o r b i t ) . these maneuvers.

No data was a v a i l a b l e du r ing

o The maneuver t o the docked DPS burn a t t i t u d e .

o The o r b i t r a t e automatic maneuver.

DAP A t t i t u d e Hold

u l l a g e . preceding burn 5 ( l a s t 10 seconds) and d i d n o t a l l o w com- p l e t e phase plane swi tch ing v e r i f i c a t i o n .

A t t i t u d e ho ld preceding each o f t he burns and i n c l u d i n q Only l i m i t e d data were a v a i l a b l e du r ing the u l l a g e

4.1 TVC DAP PERFORMANCE

Data summarizing t h e TVC DAP performance and SPS burn charac ter - i s t i c s f o r each of t he SPS burnsare prov ided i n Tables 4.1 t o 4.5.

4- 1

Page 29: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Plots of a t t i t u d e errors , gimbal trim angles, gimbal commands and mea- sured gimbal positions are given in Figures 4-1 t o 4-14. the measured gimbal positions, Ground Elapsed Time ( G E T ) relating t o the burns and peak body rates , the above d a t a were obtained from computer words. Ignition times, ullage on-times, and burn durations are based on RCS and SPS solenoid bilevel s ta tes . Measured gimbal positions and peak bcdy rates were cbtained from time history tabulations. Autopilot performance was satisfactory d u r i n g a l l of the SPS burns dur ing th i s mission.

4.1.1 Attitude Errors

Except for

Peak att i tude errors in pitch and yaw fo r a l l of the burns during G&N control ( the only period of SCS control during a b u r n were during the manual takeover near the end of burn 3 ) except SPS b u r n 5 were less t h a n 2.5 degrees. of 7 .2 degrees; the peak pitch at t i tude error for th i s b u r n was 3.2 degrees. t ive t o i n i t i a l condition errors and mistrims t h a n the other burns. In i t ia l condition errors in yaw for th i s burn included a 0.5 degree at t i tude error, a 0.3 deg/sec rate error and -0.19 degrees of yaw engine mistrim. The resultant yaw at t i tude deviation (Figure 4-5) was consistent with preflight analysis.

SPS b u r n 5 experienced a peak yaw at t i tude error

Preflight simulations indicated t h a t th i s b u r n was more sensi-

During the preliminary analysis of t h i s b u r n , i t was n o t entirely clear t h a t the yaw gimbal actuator command was responding correctly t o null the increasing yaw at t i tude error . For example, i t can be seen from Figures 4-12 and 4-13 t h a t there was a period of 8 seconds (54:26:39.9 to 54:26:47.9 G E T ) in which the at t i tude error increased monotonically from 5 degrees t o 7 degrees and the engine command remained constant. A d igi ta l simulation of the CSM/LM DAP f i l t e r , including the switchover logic, was solved for the f i l t e r response to the measured yaw at t i tude error shown in Figure 4-12. were then compared with the measured f i l t e r response from the f l i gh t d a t a . Actuator Command ( Y C M D ) and the Yaw Trim Angle (YACTOFF).

The results

The measured f i l t e r response i s the difference between the Yaw

4-2

Page 30: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

r i g c r e 4-15 presents the comparison o f t h e measured and computed f i l t e r

response t o the measured a t t i t u d e e r r o r . The maximum d e v i a t i o n between computed and measured f i l t e r output was 0.05 degrees.

i s t o be expected because constant mass p r o p e r t i e s (used i n t h e ca lcu- l a t i o n o f t h e ga in VARK) were assumed i n t h e s imu la t i on .

Some d e v i a t i o n

The reason f o r t he sudden change i n the a t t i t u d e e r r o r , and conse- quent engine response, d u r i n g t h e l a s t 4 seconds of t h e burn i s due t o

t h e guidance commands be ing s e t t o zero a t t h i s t ime.

r e s u l t s i t i s apparent t h a t t he engine response t o the yaw a t t i t u d e e r r o r du r ing SPS 5 was e n t i r e l y nominal.

From these

4.1.2 I g n i t i o n Trans ien ts

The gimbal i g n i t i o n t rans ien ts appeared nominal i n a l l cases. The

measured gimbal command du r ing the f i r s t 5 seconds a f t e r i g n i t i o n i s p l o t t e d on an expanded sca le f o r SPS 2 i n F igure 4-2a.

t he peak-to-peak ampl i tude o f t h e i n i t i a l gimbal excurs ion caused by

gimbal compliance du r ing the f i r s t 1/2 second o f t h r u s t i n g was l e s s than 0.45 degrees f o r both p i t c h and yaw.

For a l l burns

Gimbal o s c i l l a t i o n s r e f l e c t i n g p r o p e l l a n t s l o s h were observed du r ing the SPS 5 and SPS 7 burns. SPS 5 was a docked burn and fo l l owed the

docked DPS burn. observed i n bo th p i t c h and yaw and were w e l l damped w i t h i n 10 seconds

a f t e r i g n i t i o n . due t o the LM p r o p e l l a n t du r ing t h i s burn. The t h e o r e t i c a l frequency o f the LM p r o p e l l a n t i s approximately equal t o t h a t o f the

CSM a t t h i s time. Comparisons o f the LM and CCM s losh dynamics i n the v i c i n i t y o f SPS 5 i g n i t i o n are discussed i n Sec t ion 6.1.2.

gimbal o s c i l l a t i o n s du r ing burn 7 were a l s o damped o u t i n about 10

seconds. t h e o r e t i c a l values. Slosh induced peak-to-peak engine d e f l e c t i o n s were l e s s than 0.25 degrees f o r burn 5 and 0 .6 degrees f o r burn 7 .

O s c i l l a t i o n s dur ing burn 5 o f about 0.5 HZ were

It i s be l i eved t h a t the s losh torques were predominately

s losh

The

For bo th burns the measured s losh frequencies agreed w i t h the

4- 3

Page 31: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4.1 .3 Manual Takeover

The rate comnand MTVC mode was exercised during the l a s t 45 seconds of burn 8 and tested ra te damped manual control with the LM attached. Transfer from CMC TVC t o SCS MTVC occurred a t 25:21:34.8 GET. Manual control i s accomplished in th i s mode w i t h the Rotational Hand Controller ( R H C ) . Body rates are commanded proportional t o the RHC deflection, with the p i lo t attempting t o null the Flight Director Attitude Indicator (FDAI) displayed at t i tude errors . The FDAI displays the o u t p u t of the at t i tude BMAG's which are uncaged a t ignition. Roll control was accomplished using the at t i tude hold mode. deadband was selected for rol l phase plane switching during MTVC. Figures 4-5 and 4-6 present plots of pitch and yaw at t i tude errors and

rates during MTVC. I n general , satisfactory control was maintained th roughou t the manual control. Pitch and yaw at t i tude errors peaked a t 3.2 degrees and -4.3 degrees respectively, approximately 1 2 t o 15 sec a f te r manual takeover. remained a t burn termination. appeared t o be excited dur ing manual control. Considerably more RHC commands were issued in pitch t h a n yaw, par t ia l ly because of an i n i t i a l 0 .2 deg/sec body ra te which was present in pitch compared t o practically zero r a t e in yaw.

The minimum ra t e , narrow

A residual cross axis velocity of -2.5 f t / sec Neither slosh nor bending oscil lations

One roll RHC correction was made about 1 . 2 seconds a f te r Manual Thrust Vector Control (MTVC) in i t ia t ion . This command was issued t o remove a rol l rate which had bui l t u p t o abou t 2 .5 deg/sec by the time the RHC action was taken. A continuous 1 . 2 second 2- je t rol l f i r ing from the time o f transfer t o SCS was responsible for the ra te build-up. The long j e t f ir ing was caused by the roll deadband being contracted from 5.0 degrees during G&N TVC t o 0.2 degrees a t SCS in i t ia t ion . The rol l a t t i tude error which was present a t the time of transfer t o SCS was almost -4 degrees. This i n i t i a l roll transient and the resulting correctiveaction could have been avoided had the SCS rol l a t t i tude deadband n o t been i n i t i a l l y s e t a t 0 .2 degrees. I t i s recommended for future f l ights t h a t preceding G&N controlled SPS burns, the SCS

4-4

Page 32: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

J i jdband be s e t a t maximum deadband (+ 4 degrees o r 2 4.2 degrees, depend- i n g on whether the RATE SWITCH i s se t i n t h e MAX o r M I N p o s i t i o n ) .

Estimated mis t r ims are presented i n Table 4.4. These values were computed by comparing the i n i t i a l t r i m a t i g n i t i o n w i t h thes ing le -sho t t r i m values a t switchover ( i g n i t i o n t ime + 6.42 seconds f o r LM ON, + 3.7 seconds f o r LM OFF).

switchover, m is t r ims were n o t ca lcu la ted . m i s t r i m us ing the above method occurred on burn 7 i n which the yaw

m i s t r i m was -0.486 degrees. Due t o t h e s losh torques which had n o t

subsided a t t h e t ime of switchover, a va lue o f YACTOFF a t a l a t e r t ime

would probably g i v e a b e t t e r t r i m t o compare w i t h t h e i n i t i a l value. Four seconds a f t e r switchover, YACTOFF has a va lue o f -0.802 and does

n o t change f o r another 4 seconds. Comparing t h i s va lue w i t h the i n i t i a l t r i m y i e l d s an est imated yaw m is t r im o f 0.316 degrees. I n a d d i t i o n t o i n i t i a l m is t r im , Table 4.4 a l s o l i s t s values o f t he MCC t ime updates

which were communicated by vo i ce p r i o r t o the burns, values o f PACTOFF and YACTOFF a t i g n i t i o n , switchover, and c u t o f f , and measured engine

p o s i t i o n a t i g n i t i o n . Figures 4-3, 4-8, 4-11 and 4-14 present p l o t s o f PACTOFF and YACTOFF f o r SPS burns 2, 3, 4 and 5, r e s p e c t i v e l y .

I t i s c l e a r from t h e p l o t s t h a t the cg t r a c k e r i s f o l l o w i n g the m i g r a t i n g

cg *

4.1.4 R o l l TVC DAP

For shor t SPS burns i n which t h e r e was no

The l a r g e s t va lue o f est imated

R o l l c o n t r o l was nominal throughout a l l o f the burns. There were

v e r y few r o l l f i r i n g s du r ing any o f t h e burns and i n o n l y one case an

e x t e r n a l r o l l torque was d i s t i n c l y evident. Dur ing burn 4 a r o l l 1 a t t i t u d e e r r o r was

was s a t i s f a c t o r y . t o rque o f about 1.25 f t - l b was observed. The r o d r i v e n t o the negat ive deadband ,but r o l l c o n t r o l

Three r o l l f i r i n g s were observed dur ing the burn

4.1.5 S t r o k i n g Tests

The two s t r o k i n g t e s t s which

o f SPS burns 2 and 3 were n o t ana

were c a r r i e d yzed i n deta

o u t d u r i n g t h e e a r l y p a r t s

1 f o r t h i s r e p o r t , b u t

4- 5

Page 33: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

a f a i r ly detailed tiiiie history of the gimbal a c t u a t o r response during each t e s t was included f o r reference. t o the 40';) stroking t e s t i n b u r n 2 and Figure 4-7a shows the 100% stroking t e s t which was performed in b u r n 3 .

Figure 4-2a presents the response

4 .2 RCS DAP PERFORMANCE

No anomalies were identified d u r i n g the periods of RCS DAP control which were analysed. RCS DAP performance appeared nominal t h r o u g h - o u t the mission.

4.2.1 RCS DAP Automatic Maneuvers -

Figures 4-17 t o 4-22 present plots relating t o three automatic maneuvers: The maneuver t o b u r n 2 a t t i tude ; the maneuver t o the docked DPS b u r n ; and the Orbit Rate Automatic maneuver. I n each case, plots o f body rates and CDU angles are given with the desired body rates a n d desired final CDU angles dashed in. Only the l a s t 40 seconds of data during the maneuver t o b u r n 2 was available, as i s indicated in Figures 4-17 and 4-18. However, about 160 seconds of a t t i tude hold data following the maneuver was available and i s included in the plots.

Wide deadband was used during the maneuver t o b u r n 2 and the docked DPS burn. The orb i t ra te maneuver was carried o u t in the narrow deadband. All o f the maneuvers were successfully executed, with att i tude errors a t the termination within the DAP deadband. The command and actual body rates were in agreement w i t h i n %he l imits of the phase plane deadzone. No a t t i tude overshoot was observed d u r i n g any of the maneuvers. Atti tude hold was properly ini t ia ted a t the termination of a l l of the maneuvers. determine t h e frequency of RCS j e t f i r ings during the Orbit Rate Maneuver, b u t data were n o t available during t h a t time period. of the estimated body rates (Figure 4-20) indicate t h a t an excessive number o f f i r ings d i d no t occur. impulse.

Bilevel d a t a were searched t o

Plots

The majority of f i r ings were minimum

4-6

Page 34: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4.2.2 RCS DAP Attitude Hold

Figures 4-23 t o 4-28 present phase plane plots of the periods of a t t i tude hold preceding burns 3 and 4. i n a l l cases. No external torques were apparent i n any of the periods of a t t i t ude hold investigated except the torque due t o the cg of fse t s during the ullages. The e f f ec t of the 20 second 4- je t +X ullage prior

t o b u r n 4 i s seen in these figures. The cg of f se t i n pitch which was present during this ullage was about 3 .4 inches and resulted in a pitch disturbing acceleration o f about 0.024 deg/sec2 forcing the pitch phase plane t ra jectory t o an a t t i tude e r ror of about -0.62 degrees. Figures 4-26 to 4-28 include the ullage maneuver as well as about 200 seconds of p r i o r coasting f l igh t . Predictably, there were a large number of s ingle j e t f i r ings during th i s ullage to bring the phase plane t ra jectory back into the deadzone.

Nominal performance was indicated

4.3 ENTRY DAP PERFORMANCE

During the extra-atmosphere portion of entry, the SCS was i n control of the spacecraft. Sensing of 0.059 occurred a t 240:42:25 GET and the Entry DAP was placed in control of the spacecraft a t 240:46:47 GET. T h u s , the only portions of the Entry DAP which were exercised were the 2-sec, predictive Roll D A P , and the pitch and yaw ra t e dampers.

Entry Roll DAP performance was found t o be en t r ie ly nominal t o the extent t ha t TM data allowed analysis. On the basis of data obtained, r a t e damping in the pitch and yaw axes appeared nominal although com- plete verification was n o t possible due t o low frequency of these data.

4.3

the a t

1 Roll DAP Performance

Entry Roll DAP performance was en t i re ly nominal. The a b i l i t y of R ~ l l DAP t o maintain the desired ro l l angle i s shown by Figure 4-29, me history of commanded and actual ro l l angles d u r i n g entry.

4-7

Page 35: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

A number o f large angle, a t t i tude maneuvers were executed d u r i n g entry w i t h l i t t l e or no overshoot, supporting the assumption t h a t j e t on-times were calculated correctly. Actual verification of the j e t on-time calculation could n o t be done due to the lack of necessary quantit ies on TM and the coarseness of the d a t a .

4.3.2 Pitch and Yaw Rate Damping

Every pitch f i r ing d u r i n g entry was verified to have been i n accordance w i t h the pitch ra te damper design which limits pitch ra te t o less than two degrees per second.

Yaw damper f i r ings are commanded by the yaw DAP t o execute co- ordinated turns according t o r = p sin a with sin O. held a t a constant -0.34202 (a = - 20" ) . yaw j e t s are fired to damp the rates.

When stabi 1 i ty-axi s yaw rates exceed 2"/sec,

D u r i n g two bank angle reversals, a number o f consecutive yaw axis f i r ings occurred when the yaw ra te from the SCS data was apparently well below 2"lsec. However, since the f i r ings are based on the CMC

ra te estimates instead o f the SCS data, the ra te estimator d a t a were examined i n detail d u r i n g these periods. thruster act ivi ty are shown i n Figures 4-30 and 4-31. SCS s t a b i l i t y ax i s yaw ra te , CMC yaw ra te calculated from PREL and RREL data, and yaw axis thruster ac t iv i ty are shown i n these figures.

The periods of h i g h yaw

PREL and RREL were available a t 200 m sec intervals (every other DAP cycle) on the TM downlist, accounting for the gaps i n the p l o t s of CMC estimated rates. data were available. Those firings which occurred when PREL and RREL data were available on T M were according t o the yaw DAP design; t h a t i s , the yaw rate had exceeded the 2"/sec ra te deadband a t the time of the firings. yaw ra te was w i t h i n the deadbands.

Some thruster f i r ings occurred when no ra te estimator

In some instances, the rate gyro data indicated that the

4-8

I

Page 36: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

The above ana lys i s i n d i c a t e s t h a t s u f f i c i e n t d i f f e r e n c e s e x i s t between the SCS data and r a t e es t imator da ta t o p rec lude use o f t h e SCS

data as a c r i t e r i o n f o r v a l i d a t i n g the yaw j e t f i r i n g s d u r i n g per iods

where r a t e es t ima to r da ta i s unava i lab le . Several f a c t o r s can c o n t r i b u t e t o t h i s var iance between the analog and CMC r a t e es t ima to r data.

t h e i n t e r v a l s o f i n t e r e s t occurred dur ing pe r iods o f h igh r o l l r a t e s ( > 10°/sec), t he most probable cause i s t h e CDU sw i t ch ing between h igh

and l o w r a t e sampling f requencies. Th is s w i t c h i n g occurs f o r r o l l

r a t e s i n excess o f 4"/sec and can c rea te r a t e e r r o r s as h igh as l " / sec .

Since

Also, f, the r a t e o f change o f t he angle between t h e l o c a l h o r i z o n t a l

and t h e r e l a t i v e v e l o c i t y vec tor , i s i nco rpo ra ted i n t o the r a t e es t ima to r

c a l c u l a t i o n s when +0.5"/sec. Another p o t e n t i a l source o f e r r o r i s

s t r u c t u r a l v i b r a t i o n s . Although the r a t e gyros and t h e IMU a re sub jec ted

t o the same v i b r a t i o n du r ing reent ry , t h e i r l o c a t i o n s w i t h i n the CM

s t r u c t u r e cause some d i f f e rences i n the ampli tudes and frequencies o f the v i b r a t i o n s app l i ed t o the i n d i v i d u a l p ieces o f equipment.

4-9

Page 37: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

..................... ...-.. ----- . - -- . - u

, .

E 1 m

a C 0

r c -

s J

I 2 d N

m m 2 d Q

4 N

ca N

... ..

s c3 w k CQ U cn

0 0, d 0 m VI

In

..

..

m 0

* 0 N d

N N

d

..

..

0 0

Q m h 4

VI N

? .. ..

0 0 o m 0 0 o m

N h 4 0

a m N ( v

e m r n N

. . . .

. . . . d

... ... _-._._.._._.-.____.-_.-I_ ..- .........

m aD Q: ,-I

. . . .

0 \D

? m 4

. -. . N N VI

m rv e (v

Q hl

..

..

0 0 0 z z z s 0

. . . . . . . . . . -_.. .- ..>. ..... n L,

..

-. .

. . . -. .. __ . . . . . . ----

s W

a l a M M ( O m

al M m

1 0 z

4 4

..-

c 0 -4 U m

. 2 0 0 z z

v1

.A U

a U LE E -4

. _...- ... ....... _ _ ...............

w w CJ U Ll m U v)

..

v1 U al c,

0 z '. _. .

a l a l o ) M O O M m m r d d d d

X 0 b a P. rD

-k

0 0 0 % Z %

......... ___-_ _..__..._C__.__ _-

'I

4-10

Page 38: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

a U

0"

-4 U -4 E M H I 0) h P.4

I I

.-- .... _...--,... ............ _- ................. __,_- -

i .-..... ._-.. ......... ............ i

i I I I I 1

................ 1 1 r ...-- - _..-.-.- .. .- ............ - ..

Y v a m

P . 4 4

0 e: d

0) 00 4

3 0 z 0) 00 4

3

0 z

74 4

.......

d .-I

I I I

I I

.. .....-..-. I.._ ..........

. . 0 0 0 1 I l l z z z

Page 39: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

v)

C k 7 la m & v3

M E

'A

2 m k 0 k I.r W a a 7 U 'I4 U U -4 a C a m al U 0 t%

Pl)

d w -4

=c I-

rn

d r

--.. . . . . . 1, .. ....- .- .. ..... ............... _.. ........ . ..:

.. ........ . .._ ....___... . _ . . _ _ C _ . _ _ _ _ _ . . -..- . . - .

.. ____ ....... .__.._ ...... _--.- ..

..... ~ .... ..-.. _.. ..... - & - . . .

c o o -

d U * ? ? z *

I * . _._.-_. * -.._ ..- - - - ..

I 1

N d

rl I

c 0

VI

. -.

m ... __-.. .

0

rl ?

. .

a0

. n V al m

d r(

C 0

.I4 U a k 1 rn C k 7 D U k 0 '5 a .c U

0 L)

a 'D

a P 0 d -A (d

7 '

4

5 $ m

&I C 4 0 a (d U a a a C 0

h C 0

* d

* .

4-1 7

Page 40: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I \

I

I

i

!

I

! i

I 1

I I

!

1

i I i

f

t ! i

I

I I

P- O ? I

- ._

cc 0 9. I

I- 0 9

(0 C '9 I

a -s a

1

8 -

r. C'

I

3

c 9. I

-3

it 0' 4

I

3 2 I

a s 3

N n '9 I

N P- I-

I

?! - N '1)

I

- v n 0 I

lr

'0 m 4

1

m N

0. I

\c W U

N c? \o

I

z N

9 4 I

m ,- i

A

I

C .- .A

I

I-

9 s I

0 m m

I

9 U i

.D N P

1

X

C J r. 3

1

.3 m

0 I

ID

E .A

b U I m

' r ( . , E !

W 02 .j

0 c.

\f a- ? 3

W m a 9 I

a- r 0

9 i

r? 9 9 I'

m r. 3 c

4

0 c

c

m

1

N N

I

I

I

lr r. 3

I

.s i

I

c=

0 I

N

-.

I

9 9 4

4 I

I

I

P-

9 4

I

C C d

-- I

n i

-- I

.c

I

n N

0: I

I

I

2 ?

1

m N CT

I

U

0 9 I

\D

0

. ...

N m 9. 4

0) C %.

ri

r. 3

- k

1

U- I- .- I

- .2 P- ,-

I

r-

0

c

I

?-l

0 N I-

Q: 9 N

'9 I

N m N

1 '

m U m I

\o aY * 9 I

P4 P-

j: I

\f

W

I

3

n hl 0.

I

C J r-

0 1

r .

'. m ls.

c . & I

c a M

U C o m I c , .c 'L c; I '

. I

m ' U

a -3

U ' 0 m z I ' I

x

a I

!

5 'U

I

.- E 0 iz I

I ,

l i

I

4-1 3

Page 41: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

1 - .. ...

. . ..-.- .... -.-

i I 1 i !

i

!

!

1 I I I

i

I

i

1 I I

i i

i i

I I

I I

i j 1 I I I

I i i I i

i i

t -1

!

I !

I ,

!

i 1

I i t i i

i

1

L

6 i

i I t i

i

I

, I

i I i

9 , m

- .

I

N

I

N

(A C 8-l 1 la

. . . ..- . . . . . . . . . .

ln N

I

I l l I I

. . ....... -_ - ......... .- - . . . . . . . . . ... ..

...

" . ? I N

I

I-

* N N I

N ? . P- '? Z 1

_. ._ .___._. I . ._~. - ..... -

W a J > > P- I l l I I I l

a Z

. .

I

Lo

cf

............ . - . . . . . . ...

d u 3

d I .4

. . . . . . . . . . . . . . . . . . -

9

d I

1 1 1 1 I I

. . . . . . . . . -1 i I i ? " 1 I I

Z r - I

. .̂ ..... "____.. ....... .---- ............

Q\ .-I

4 4

9 . ? " . " i Z O N

...... -. . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . J

4-1 4

. . . . . . . . . . . . . _._- ... _. . . - -.. . _- -

Page 42: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-1 5

Page 43: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-1 6

Page 44: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-1 7

Page 45: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

. .

4-1 8

Page 46: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-1 9

Page 47: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-20

Page 48: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-21

Page 49: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-22

Page 50: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-23

Page 51: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis
Page 52: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-25

Page 53: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-26

Page 54: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-27

Page 55: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-28

Page 56: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-29

Page 57: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-30

Page 58: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-31

Page 59: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-32

Page 60: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-33

Page 61: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-34

Page 62: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-35

Page 63: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4- 36

Page 64: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-37

Page 65: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-38

Page 66: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

m N I

w W CT 3 u U

LL

4-39

Page 67: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-40

Page 68: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

4-41

Page 69: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-42

Page 70: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

4-43

Page 71: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

A t t i t u d e Error

4-44

Page 72: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

5.0 LM IMU PERFORMANCE

5.1 DPS 1 VELOCITY COMPARISON

Ana lys is of the LM system was based on t h e CSM as a standard.

The LM e r r o r s were n o t co r rec ted f o r CSM e r r o r s as determined from t h e ascent da ta for two reasons. F i r s t , i n t h e CM/S- IVB comparison,

t h e S- IVB e r r o r s a re unknown and are thereby a t t r i b u t e d t o the CSM.

Second, f o r t he DPS burn, t he average a c c e l e r a t i o n over t h e burn was

o n l y 0.13 g ' s on the LM X-axis. These two cond i t i ons l end t o low conf idence l e v e l s i n the der ived LM s o l u t i o n , s ince combinations o f

ext remely smal l e r r o r sources could g i v e a reasonable s o l u t i o n t o the

smal l res idua ls invo lved. Table 5.1 l i s t s what a re be l i eved t o be t h e

major LM e r r o r s w i t h respec t t o the CM f o r t h i s burn. s e t i s des i red, i t can be obtained by mere ly s u b t r a c t i n g the CM e r r o r s f rom t h e LM e r r o r s . The except ion t o the above i s t h a t between ascent

and DPS 1 , ACBX was changed from -1.214 cm/sec t o zero due t o an updated

compensation l oad between the t w o f l i g h t phases.

I f a CSM co r rec ted

2

The uncompensated v e l o c i t y comparisons f o r DPS-1 a re shown i n

F igures 5-1 through 5-3 and the compensated r e s i d u a l s a re shown i n

F igures 5-4 through 5-6, respec t ive ly .

Due t o the e x c e p t i o n a l l y good f i t o f t he der ived data w i t h respec t t o the expected e r r o r s , no discuss on o f t h e i n d i v i d u a l e r r o r s i s

necessary.

5 -1

Page 73: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.5 .5 .!I

m N 9

< e u e o o Z Z Z Z q 0 o o o o o

- 0

Z Z Z Z o O o w o Z Z q e u e y - e t \o 0.

P- m m 4 e u e m o u e u u Z Z Z Z 0 O o Z Z Z Z

5-2

Y

Page 74: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

0 . c

v! 0

0 v! 0 I

Page 75: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I U m 0 0 .

c 0 C I

m I

m

Page 76: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

0 . c-

u)

0

-

- .

-

0

Page 77: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

."..

0 In

0 I

*

n

m h ?

In N 0 m h c

In h m co h ?

Ln N 0, co h ?

In h 03 co h ?

m I In

Page 78: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

0

n u

n N 3

r- m -

v) h Q, 00 h

I

v) N Q, 00 h c

h 00 00 h .

I

Page 79: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

( 3 3 S / l j )

- . .

- - -

0

L

-

. * . .

* . .

ZA w m a

In h (u cn h c

In cu (u ui h -

E v, V I

f u3 I In

aJ L 3 0,

c3

I L n

F

In h

0, h

c -

v) (u 0 0, h c

In h cn a3 h -

In cu cn a3 h 7

m h co a3 h -

Page 80: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6.0 LM DIGITAL AUTOPILOT

The degree o f d e t a i l and accuracy o f t he pos t f l i g h t ana lys i s o f t he

LM DAP was dependent on the ava i l ab le te lemet ry (TM) data. An accurate ana lys i s was n o t always obtained s ince the m a j o r i t y o f the LGC downl ink

parameters used were sampled once pe r two second TM cyc le . I n some cases, maneuvers and burns were performed over areas where coverage

was n o t ava i l ab le . Th is sec t ion discusses the t h r e e d i s t i n c t con-

f i g u r a t i o n s which the LM DAP m u s t c o n t r o l , i . e .

a) LM/CSM Docked Conf igura t ion

b ) Descent Conf igura t ion

c ) Ascent Conf igura t ion .

Automatic maneuvers, PGNCS c o n t r o l l e d burns and per iods o f a t t i tude

h o l d were i n v e s t i g a t e d f o r each c o n f i g u r a t i o n .

which were analyzed were: The var ious modes

a ) A t t i t u d e Hold (coast ing and powered f l i g h t )

b ) Manual Rate Command

c ) Automatic Maneuvers

d) Autornati c S teer ing . 6.1 LM/CSM DOCKED CONFIGURATION

The data used i n the ana lys is o f t h i s c o n f i g u r a t i o n were taken from

t h e computer words down1 inked and the associated osc i 11 ograph records.

The maneuver t o the burn a t t i t u d e and t h e a t t i t u d e h o l d be fo re and a f t e r

t h e burn were performed by the CSM and are n o t inc luded under t h e LM ana lys i s .

6.1 . I Docked DPS Burn

A 2 - j e t u l l a g e ( j e t s 6 and 14) was s t a r t e d a t 49:41:25.6 and con-

t i n u e d u n t i l 49:41:35.2. I g n i t i o n occurred a t 49:41:33.0 w i th t h e manual

t h r o t t l e s e t a t 11.37% o f maximum t h r o t t l e s e t t i n g . A t 49:41:45 the manual

6-1

Page 81: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

t h r o t t l e had been placed a t 38% maximum s e t t i n g and the automat ic

t h r o t t l e s t a r t e d b u i l d i n g up t o the f i x e d t h r o t t l e p o i n t a t 49:42:0.75.

V65E was keyed i n p r i o r t o i g n i t i o n t o i n h i b i t t h e X-axis RCS j e t s f r o m f i r i n g dur ing t h e Docked DPS Burn.

d u r i n g r e a l t i m e mon i to r i ng t h e appearance of 8 o r 9 r a p i d RCS pulses a t

i g n i t i o n . A review o f t h e o s c i l l o g r a p h records and b i l e v e l t a b u l a t i o n s d i d n o t subs tan t i a te t h i s observat ion. r e a l t ime te lemet ry noise. was du r ing the pe r iod o f ' u l l age .

f o r 0.1 sec t o p rov ide +V r o t a t i o n . Th is f i r i n g was i n accordance

w i t h t h e phase plane l o g i c .

were f i r e d throughout t h e burn. The o n l y RCS a c t i v i t y was balanced coupled 2 - j e t f i r i n g s which produced r o t a t i o n s about t h e P-axis.

f i r i n g s were 0.1 sec i n d u r a t i o n which i s a minimum impulse f o r t h e LM/CSM docked con f igu ra t i on . A sample o f t he P-axis phase plane i s

shown i n F igure 6-1 and i n d i c a t e s t h a t t he f i r i n g s occurred a t t h e

sw i t ch ing 1 i nes as planned.

The f l i g h t d i r e c t o r s r e p o r t e d

The observed f i r i n g s must have been

J e t s 1 and 10 (4U and 1D) came on

One f i r i n g d i d occur a t 59:41:31.3 which

Exc lus ive of u l l a g e , no X-axis RCS j e t s

A l l

Peak angular r a t e s f o l l o w i n g t h e t h r o t t l e - u p t o t h e f i x e d t h r o t t l e

p o s i t i o n were q u i t e low (0.14 deg/sec about t h e Q-ax is and 0.2 deg/sec

about t h e R-axis) . The angular r a t e s and a t t i tude excursions ob ta ined du r ing the steady-state p o r t i o n o f t he burn were low and l e s s than t h e

values pred ic ted by p r e f l i g h t s imu la t ions . The peak angu lar r a t e s

which occur red du r ing the t h r o t t l i n g p r o f i l e near t h e end o f the burn were -0.35 deg/sec f o r t h e Q-ax is and 0.53 deg/sec f o r t he R-axis.

Both peaks occurred a t 49:47:12. 0.5 t o 0.6 deglsec which was p r e d i c t e d by p r e f l i g h t s imu la t i on .

p l o t o f t he LGC es t imated r a t e s d u r i n g the t h r o t t l i n g p r o f i l e i s con- t a i n e d i n Figure 6-2.

BMAG's a re shown i n F igure 6-3.

t he curves i s very good i n the two f i g u r e s .

w i l l be discussed i n Sec t ion 6.1.2, very e v i d e n t i n F igure 6-3. Th is e f f e c t i s n o t as pronounced i n the es t imated r a t e s because o f t he

f i l t e r i n g ac t i on o f t h e r a t e es t ima to r and t h e low v i s i b i l i t y a f f o r d e d

These r a t e s were w i t h i n t h e range of A

For comparison, t h e r a t e s ob ta ined from t h e CSM

The general agreement o f t h e shape of

The e f fec t o f s losh, which

6-2

Page 82: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

by t he 1 sec TM data. be-gained i n body coord inates f o r t h i s burn. a t 49:47:45, the v e l o c i t y e r r o r i n the Y-axis was 3.5 f t / sec and the

v e l o c i t y e r r o r i n the Z-axis was -1.9 f t / s e c a t c u t o f f .

F igure 6-4 conta ins the p l o t s o f v e l o c i t i e s - t o - The burn was terminated

6.1.2 Slosh

s losh, or an e f f e c t which appeared t o be s losh, was q u i t e ev iden t d u r i n g the docked DPS burn. The P i t c h , R o l l and Yaw Log ic E r r o r t races (Channels GH1248, GH1249 and GH1247) osc i 11 a ted q u i t e n o t i c e a b l y du r ing

var ious p o r t i o n s of t h e burn. The o s c i l l a t i o n s were n o t always sus ta ined

and would appear and disappear a t var ious t imes du r ing the burn. The f o l l o w i n g t a b l e summarizes some o f t he more no t i ceab le o s c i l l a t i o n s .

TIME - A X I S VEHICLE WEIGHT FREQUENCY

49: 44: 29 R o l l 57579 l b 0.39 HZ

49 : 44 : 40 Yaw 57227 l b 0.37 H,

49 : 46 : 7.5 P i t c h 5441 1

49: 46: 7.5 R o l l 5441 1

49: 46 :20.0 P i t c h 53990

49:46:20.0 R o l l 53990

L

b 0.41 HZ

b 0.40 HZ

b 0.41 HZ

b 0.41 HZ

49:46:20.0 Yaw 53990 l b 0.40 HZ

The above mentioned o s c i l l a t i o n s d i d n o t show up i n the LM analog r a t e t raced on the o s c i l l o g r a p h records, b u t t h i s i s probably due t o the

sca l i ng .

conta ined i n F igure 6-3. i s 0.4 HZ be fore the t h r o t t l i n g p r o f i l e was s t a r t e d . Very s l i g h t

o s c i l l a t i o n s were observed i n the Gimbal D r i ve Actuators (Channels

GH1313 - P i t c h and GH1314 - R o l l ) du r ing the per iods i n which the l o g i c e r r o r t races o s c i l l a t e d . For instance, t h e frequency o f o s c i l - l a t i o n of t h e R o l l GDA a t 49:46:7.5 was 0.4 HZ.

R o l l GDA were i n phase w i t h t h e p i t c h l o g i c o s c i l l a t i o n s and were 180 degrees ou t of phase w i t h the r o l l l o g i c o s c i l l a t i o n s .

The o s c i l l a t i o n s are very no t i ceab le i n the CSM r a t e t races The frequency o f the o s c i l l a t i o n s i n F igure 6-3

The o s c i l l a t i o n s o f the

6-3

Page 83: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Theore t ica l c a l c u l a t i o n s were made i n an at tempt t o i d e n t i f y t h e presence o f slosh.

percentage o f f u e l l e f t , t he c a l c u l a t e d frequency o f s losh f o r the DPS tanks v a r i e d between 0.355 HZ and 0.358 HZ. The t h e o r e t i c a l frequency

o f s losh f o r the APS tanks was 0.6 HZ,but a t t h i s t ime the APS tanks

were f u l l and would n o t cause the o s c i l l a t i o n s . The t h e o r e t i c a l

s losh frequency f o r the CSM f u e l and o x i d i z e r tanks was 0.36 HZ based on the amount o f f u e l remaining a f t e r SPS 4 and the a c c e l e r a t i o n obtained du r ing the Docked DPS burn. The t h e o r e t i c a l s losh masses

were ca l cu la ted and are tabu la ted below.

Based on t h e a c c e l e r a t i o n o f t he v e h i c l e arid t h e

Fuel Ox id i ze r

CSM a f t e r SPS 4 150.0 kg 237.0 kg

LM w i t h 0.714% f u e l l e f t 336.9 kg 536.2 kg LM w i t h 0.690% f u e l l e f t 336.9 kg 536.2 kg LM w i t h 0.53% f u e l l e f t 331.3 kg 527.3 kg

LM w i t h 0.509% f u e l l e f t 328.9 kg 523.4 kg

A rev iew o f t h e f i r s t f o u r SPS burns d i d n o t show any s t rong evidence

o f s losh.

d i d show evidence o f an o s c i l l a t i o n o f 0.5 H Z . t h e t h e o r e t i c a l s losh frequency o f t h e DPS tanks a t t h i s t ime.

However, the SPS 5 burn which fo l l owed the Docked DPS burn

Th is tu rns o u t t o be

I n the SUNDANCE p r e f l i g h t so f tware v e r i f i c a t i o n t e s t i n g , runs

were made f o r the docked DPS burn w i t h and w i t h o u t s losh modeling.

For the cases i n which s losh was modeled, t h e gimbals were observed t o o s c i l l a t e w i t h a frequency o f 0.357 H Z . o f the gimbals f o r t h e cases w i t h o u t s losh were rough ly 0.22HZ. Thus,

i t seems s a f e t o assume t h a t t he o s c i l l a t i o n s o f t he r a t e and l o g i c e r r o r t races were caused by s losh and n o t by the Gimbal T r im System.

The maximum peak-to-peak ampl i tude o f 0.4 deg/sec of the r a t e o s c i l -

l a t i o n s i n Figure 6-3 agreed w i t h p r e f l i g h t s i m u l a t i o n r e s u l t s .

The frequency o f o s c i l l a t i o n

6-4

Page 84: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6.?.3 Compliance

The Pitch and Roll Gimbal Drive Actuator positions (Channels GH1313 and GH1314) along with the engine throt t le profile are plotted i n Figure 6-5 for the beginning and end o f the docked DPS burn . A t a b o u t 49 : 42 : 09 the GDA ' s appeared t o have reached s teady-s t a t e posi t i ons . Using the formulas in Reference 1 t o equivalent engine bell rotation, one obtains the following steady- s t a t e trim positions:

which relates GDA position in inches

Pitch = -0.0276 deg Roll = -1.525 deg

The theoretical trim values based on the mass property data contained i n Reference 2 are:

Pitch = -0.421 deg Roll = -1.218 deg

This amounts t o an average difference between actual and theoretical trim of about 0.35 deg.

I t was very noticeable that the gimbal drive actuators d i d not show signif icant act ivi ty following the automatic throttle-up t o the fixed thro t t le position ( F T P ) , i . e . , the majority of compliance effects occurred between zero and 40% of FTP. Compliance i s presently being modeled as a l inear thrust misalignment and the above mentioned fac t does n o t correlate with this model. Also, the peak-to-peak excursions of the GDA's, obtained during the thrott l ing prof i le a t the end of the b u r n , were approximately midway between the corresponding values obtained from preflight simulations in which compliance was and was n o t modeled. Further investigations should be conducted t o determine the exact nature of cornpl i ance.

6 . 2 DESCENT CONFIGURATION

Two burns were performed in the descent configuration during the Apollo 9 mission. AGS control and i s discussed in Section 7. The second b u r n which was the

The f i r s t , the DPS Phasing B u r n , was performed under

6-5

Page 85: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

DPS I n s e r t i o n Burn i s discussed below.

f o r the automatic maneuvers t o the burn a t t i t u d e s .

6.2.1 DPS I n s e r t i o n Burn

No TM coverage was a v a i l a b l e

U l lage was i n i t i a t e d a t 95:39:0.628 f o r the i n s e r t i o n burn and cont inued u n t i l 95:39:9.138.

f i r i n g s occurred f o r a t t i t u d e c o n t r o l as requ i red by the phase p lane

l o g i c . were r e q u i r e d f o r a t t i t u d e c o n t r o l . The angular r a t e s and a t t i t u d e

e r r o r s throughout the burn were o f the o rde r expected based on pre-

f l i g h t s imu la t ions . were 1.18 deg/sec and -0.67 deg/sec, r e s p e c t i v e l y . The peak a t t i t u d e e r r o r s f o r both axes were l ess than 11.7 degrees. F igu re 6-6 conta ins

a p l o t o f t h e U-axis a t t i t u d e e r r o r and t h e associated U-axis RCS j e t f i r i n g s . The deadband f o r the I n s e r t i o n Burn i s one degree and i t can

be observed t h a t the f i r i n g s genera l l y occur dur ing the per iods i n which t h e a t t i t u d e e r r o r exceeds 5 1 degree. The l a c k o f h igh frequency

da ta prevents an exact i n v e s t i g a t i o n o f the P and V-axes r e s p e c t i v e l y .

The t ime pe r iod covered by p l o t s 6-7 and 6-8 inc ludes u l l age , the . I n s e r t i o n Burn and a p o r t i o n o f the n u l l i n g o f t he r e s i d u a l v e l o c i t i e s .

A p l o t o f t he ve loc i ty - to -be-ga ined from t h e I n s e r t i o n Burn i s conta ined i n F igure 6-9.

Dur ing t h i s per iod , severa l U, V j e t

Numerous 1 and 2 - j e t f i r i n g s occurred throughout the burn which

The peak angular r a t e s about the U and V axes

F igu re 6-10 presents a t i m e h i s t o r y o f t h e gimbal d r i v e ac tua to rs

f o r t he I n s e r t i o n Burn. GDA's i s 0.2 HZ.

e x i s t i n g dur ing t h i s burn i s 0.18 HZ. on the osc i l l og raph records revealed o s c i l l a t i o n s i n the p i t c h and r o l l

axes o f 0.2HZ. As before, there seems t o be a good c o r r e l a t i o n between

the ca l cu la ted s losh frequency and the observed r a t e osc i 1 l a t i o n s .

The frequency o f o s c i l l a t i o n o f bo th o f the The t h e o r e t i c a l s losh frequency f o r the cond i t i ons

A rev iew o f t he LM r a t e t races

6-6

Page 86: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Pre l im ina ry ana lys i s i nd i ca ted t h a t the t h r u s t b u i l d u p fo r the I n - s e r t i o n Burn had been very slow and t h a t the change i n v e l o c i t y over a two

second per iod j u s t managed t o exceed the th resho ld va lue on the l a s t pass through the AV Mon i to r . A d e t a i l e d rev iew o f the TM da ta revealed t h a t the AV f o r the f i r s t pass through the AV Mon i to r was 11 cm/sec, 12

crn/sec f o r t he second pass, and 105 cm/sec f o r the f o u r t h pass. Due t o a da ta dropout, the i n fo rma t ion on the t h i r d pass was n o t a v a i l a b l e . The r e q u i r e d th resho ld of 36 cm/sec a f te r f o u r passes was t h e r e f o r e c e r t a i n l y

exceeded w i t h ease a f t e r the f o u r t h pass.

was exceeded on the t h i r d pass cannot be determined due t o the l a c k o f data.

Whether o r n o t t he th resho ld

6.2.2 A t t i t u d e Hold

U and V-axes f o r a pe r iod o f a t t i t u d e h o l d f o r the unstaged c o n f i g u r a t i o n j u s t p r i o r t o the DPS I n s e r t i o n Burn.

s e t t o one degree which i s the powered f l i g h t deadband.

a u t o p i l o t func t ioned p roper l y i n the a t t i t u d e h o l d mode and the phase planes were as expected.

about the V-axis i s ev ident i n Figure 6-13. The exac t na ture o f the

d i s t u r b i n g torque i s n o t known a t t h i s t ime.

w i l l be c a r r i e d ou t i n t h i s area.

Figures 6-11, 6-12 and 6-13 conta in phase plane p l o t s f o r the P,

A t t h i s p o i n t , the deadband was The d i g i t a l

The presence o f an ex te rna l d i s t u r b i n g torque

Fur ther i n v e s t i g a t i o n s

6.3 ASCENT CONFIGURATION

The LM was staged a t the beginning o f the C S I Burn and the remaining

rendezvous sequence was performed w i th the ascent con f igu ra t i on . A f t e r

docking w i t h the CSM, the crew t rans fe r red t o the CSM and an unmanned

APS Burn t o d e p l e t i o n was performed. The ana lys i s o f the ascent con-

f i g u r a t i o n inc ludes two burns, an automatic maneuver, a pe r iod o f a t t i t u d e ho ld and a pe r iod du r ing which manual c o n t r o l was exerc ised.

6.3.1 Automatic Maneuver

Data cover ing the automat ic maneuver t o the CDH Burn a t t i t u d e was

rece ived by the HTV S t a t i o n on Rev 61. 2.0 deg/sec w i t h commanded r a t e s about the Q and R axes. F igure 6-14 i s a p l o t of the commanded and LGC veh ic le r a t e s about the P, Q and R-axes.

The maneuver was performed a t

6 -7

Page 87: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

The f i g u r e shows a s l i g h t r a t e overshoot i n the Q and R-axes, b u t t h e

o v e r a l l r a t e performance was s a t i s f a c t o r y . The r a t e overshoot i s

c h a r a c t e r i s t i c o f t he r a t e es t ima to r and was a n t i c i p a t e d based on

p r e f l i g h t s imu la t ions . maneuver. The CDUXD, CDUYD and CDUZD a r e the f i n a l d e s i r e d b a l l angles and t h e p l o t s i n d i c a t e t h a t t h e automatic maneuver p rov ided t h e

approp r ia te veh ic le r c t a t i o n .

F igure 6-1 5 i 1 l u s t r a t e s t h e CDU angles d u r i n g t h e

6.3.2 A t t i t u d e Hold

F igures 6-16, 6-17 and 6-18 con ta in phase plane p l o t s o f a pe r iod

o f a t t i t u d e hold f o r t he ascent c o n f i g u r a t i o n immediately f o l l o w i n g the APS Burn t o deplet ion. The APS Burn was te rmina ted by t h e AV Mon i to r when low t h r u s t was detected. The programmed guidance equat ions r e s e t

t he deadband t o t h e as t ronaut s p e c i f i e d value (5 degrees i n t h i s case) and dutomati ca l l y requested an u l l age.

back t o t h e TIG-5 program and remained t h e r e i n a 5 degree deadband u n t i l

an "ENTER" was rece ived ( i . e . , u l l a g e was te rmina ted and r e - i g n i t i o n

was n o t requested). were zeroed and t h e deadband was s e t t o 0.3 deg by t h e APS burn program

P42. p r o p e r l y dur ing t h i s p e r i o d and t h e phase planes were as expected. The

t r a n s i t i o n f r o m the 5 deg deadband t o the 0.3 deg deadband was very smooth and can be observed i n t h e above mentioned f i g u r e s .

6.3.3 Manual Control

The burr! proyrams were recyc led

A f t e r r e c e i v i n g a "PROCEED", t h e a t t i t u d e e r r o r s

E x i t from P42 placed t h e deadband back a t 5 deg. The DAP func t ioned

I

E i g h t minutes o f da ta rece ived by BDA Rev 63 were analyzed du r ing a p e r i o d j u s t p r i o r t o docking. The DAP was i n a 0.3 degree deadband

a t t i t u d e h o l d mode,but t h e r e was a p ro fus ion o f RHC and TTCA a c t i v i t y a t t h i s t ime. Figures 6-19, 6-20 and 6-21 present phase p lane p l o t s

d u r i n g t h i s per iod of t h e docking sequence. the DAP was n u l l i n g the r a t e s and ma in ta in ing a 0.3 degree a t t i t u d e

deadband a f t e r t h e re lease o f t he RHC o r TTCA. The dashed l i n e s i n the f i g u r e s i n d i c a t e r a t e and a t t i t u d e e r r o r s induced by RHC a c t i v i t y .

The f i gu res i n d i c a t e t h a t

Page 88: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I .

i -

The o the r a t t i t u d e excurs ions were caused by TTCA a c t i v i t y . r a t e changes f o r each a x i s (P, U, V) dur ing a minimum impulse l i m i t cyc le a re 0.1 deg/sec f o r t h i s con f igu ra t i on . of t h i s o rder of magnitude whenever the re was no RHC o r TTCA a c t i v i t y .

The t h e o r e t i c a l

The observed r a t e changes were

6.3.4 C S I Burn -

The data f o r t he C S I Burn was rece ived by TAN on Rev 61. Th is was a + j e t RCS PGNCS c o n t r o l l e d burn. The 4 - j e t s ( j e t s 2 , 6, 10 and 14)

were tu rned on a t 96:16:6.5 and the burn was te rmina ted a t 96:16:38.2.

The phase planes presented i n Figures 6-22, 6-23 and 6-24 i nc lude the per iods o f a t t i t u d e ho ld p r i o r t o t h e C S I burn, t h e burn, and the n u l l i n g

o f r e s i d u a l Vg's f o l l o w i n g t h e burn. The phase planes show t h a t , i n

genera l , t he DAP was ho ld ing the appropr ia te deadband (1.1 deg = 0.3

narrow deadband + 0.8 deg "FLAT"). The spikes i n r a t e s are a r e s u l t

o f t he X and Z axes t r a n s l a t i o n s f o l l o w i n g the burn. t h e burn s t a r t e d , j e t s 6 and 10 began t o g g l i n g on and o f f t o p rov ide

a t t i t u d e c o n t r o l about the U and V-axes ( j e t 6 t u r n i n g o f f produced a +U r o t a t i o n and j e t 10 t u r n i n g o f f produced a - V r o t a t i o n ) .

p o s i t i o n o f the cg, the angular e r r o r s remained a t t h e deadband 1 i m i t s

f o r the d u r a t i o n o f the burn.

S h o r t l y a f t e r

Due t o the

F igure 6-25 presents a t i m e h i s t o r y o f t h e ve loc i ty - to -be-ga ined

f o r the C S I burn. were 1.003, 0.04 and -1.361 f t / s e c r e s p e c t i v e l y .

The v e l o c i t y e r r o r s a t c u t o f f i n t h e X, Y and Z-axes

6.3.5 APS Burn t o Dep le t ion

The APS Burn t o d e p l e t i o n was i n v e s t i g a t e d based on downlinked computer words rece ived by Texas on Rev 64.

ve ry much as expected based on p r e f l i g h t s imu la t ions . be fo re t h i s burn was about 32 sec long.

u l l a g e t o come on 3.5 sec be fore i g n i t i o n . The crew, a f t e r observ ing

Once again, the burn was

The u l l a g e

The normal sequence i s f o r

6-9

Page 89: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

a buildup of velocity, would key in "Proceed" sometime during th i s 3.5 sec period and ignition would occur as planned. In t h i s case, the "Proceed" (V33E) had t o be keyed in by telemetry and was somewhat delayed, proceeded as pl anned.

Once the V33E was received, ignition occurred and the b u r n

During the b u r n , the peak a n g u l a r rates abou t the Q and R-axes were of the order of predicted rates of 5.0 t o 6.0 deg/sec. cursions were o f the order of 5 2.5 deg which a g a i n agrees with preflight simulations. The l imit cycle frequency was calculated during a steady s t a t e portion o f the burn (101:57:43). frequency was 0.37 HZ for the pitch axis (Q-axis) and 0.375 H Z for the ro l l axis (R-axis). Theoretical calculations based on the existing offset accelerations predict a l imit cycle frequency of 0.35 H for the Q-axis and 0.38 HZ for the R-axis. the l imit cycle frequency was 0.36 H Z fo r the pitch axis and 0.75 H Z for the rol l axis .

5.0 deg/sec. This compares favorably with the The larger angular error ex-

The observed l imit cycle

Z Early i n the f l i gh t (101:53:30),

Figure 6-26 i s a phase plane plot of a steady s t a t e p o r t i o n o f

the APS b u r n . The original intent of the plot was t o trace o u t the shape of the limit cycle trajectory by plotting a suff ic ient number of points. sampling frequency, a good outline of the l imit cycle shape could n o t be obtained. cycle trajectory. results l i e within a range consistent with preflight simulation resul ts .

Figures 6-27 and 6-38 are plots o f short segments of the UERROR

However, due t o the l imit cycle frequency and low d a t a

The dashed l ine o f th i s figure shows an approximate l imit The plot does show t h a t , on a qual i ta t ive basis, the

and V E R R O R , respectively, during the APS b u r n t o depletion. Also plotted are t h e U-jet and V-jet f i r ings . The je t - f i r ing history i s

available a t 10 msec intervals while the LGC a t t i tude error d a t a i s available only a t one-second intervals. I n general, the a t t i tude errors corroborate the j e t f i r ings. a t t i tude deadband (one degree) i s n o t a constant, b u t i s a function of angular rate (see the switching curves i n Figure 6-26) .

I t should be noted t h a t the

6-1 0

Page 90: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

-0.5

The cross-coupl ing between t h e c o n t r o l axes descr ibed i n Sec t ion

2.1.1 o f Reference 3 was ev ident du r ing t h i s burn. A l ong f i r i n g o f j e t 10 would be fo l lowed by a f i r i n g o f j e t 6, d u r i n g which the re

would be another s h o r t f i r i n g of j e t 10. Th is e x t r a f i r i n g o f j e t 10 r e s u l t e d from the acce le ra t i on coupled i n t o the V-axis f rom j e t 6 (which produces a U-axis torque) du r ing the p e r i o d when the V-axis

l i m i t cyc le was i n i t s "coast" phase.

e x t r a f i r i n g s were aga ins t the o f f s e t acce le ra t i on and d i d n o t represent an i n e f f i c i e n t use o f f u e l .

I t should be noted t h a t these

The te rm ina t ion o f t he burn and subsequent coas t ing phase o f t h i s

burn were covered i n Sect ion 6.3.2 o f t h i s r e p o r t .

6-1 1

Page 91: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I

!

I

!

i j

I

i

i

; !

6-12,

Page 92: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

7 r : o

. (3as/Bap)

0 0 - -- I "

. I.. I

, I I

. ,

!

I

. .

I . . i

W ) _ ' 4

. .

* J

i I _. t

i ' 2 7 '

, . ..

-1 . - .i . : . - . L - . - . . . . . .

6-1 3

Page 93: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

-0.51,

Figure 6-3 Docked DPS Burn CSN BMAG Rates

CSN Roll Axis +OS5 T

49 : 46 : 56.6 49:47:26.6 -0.5- 1

Time

6 1 4

Page 94: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I , .

- . ..

- . . .

--.

.. . .. .

-, .

.. .

. . .

. .

- -

I . I -

1: i ! I :

/ - 1 ! i

1

.. . . . . . . ... . . i . ' t , . I: !

. . -

6-1 5

Page 95: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-16

I

.

Page 96: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

. , 1 - .. . . . .L ' I

F 4 +

!

- 1 I

. .

6-1 7

Page 97: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-1 8

Page 98: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

- : . . .. . 1.- --..I . : :. ..: ..

_., ! '

I

. .

6-19

Page 99: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-20

Page 100: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

' - ; I

, . !

I . . ._: -I : , . . . . . .+ .

-: , ..I .

. .

' . , ..I: . .

I

I . . . ,

. . 0 . _ _ _ _ . _ _ ..... - 0

....... . I

:* . ! . .

. . . .

. I .

L.. I ...

t

' ,

. . .

. .

, . .

_. .

6-2 1

Page 101: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I

I _ ' I

! ... ! - . .

i . ...

I .

: . ! . .

1.

vl I

0 9

--- I !

6-22

Page 102: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-23

Page 103: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

i .I

...I :

- .

I . -

. i

; I

' I

i -

I ' :-- c . - .. I C

! I

. . .~

!

I I I '

. .. .. . . I

.. -1. . , I ' I

,

6-24

I ' I

! , -

L .. . . . . . ' .

I

i

Page 104: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

!

I

I !

. I. I !

I

i

i ! I

I

! I

- . ,

. -.

i

! I

I .

I J

I 1 I i I

i

I 1.

j

! I

I

I

!

I

,

! !

I i

. - . - . . . - I !

. .

I

I I

I

'1 I ' I I I I I I I I

Y I

Q I .. .

-- I

6-25

Page 105: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

. - . . -.

. . . .- .. . . ~ . - ~- . . : . . . . . -. 1 1

' I . . ' ! ; , ,

I . . - ' _ . . ! . ,

' : I , ; I

, .. . , _. . - . . .

0 0'

6-26

Page 106: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-2 7

!

x:

Page 107: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I : I . I "

i ,- * I N

. . 0 0 0

' I

. .

I I :. 1

. I

I

. . . -..

. . _ . I

! . . I

.i . . .. . . . ! ... . -

i

! '

I I I I , .

. .

I

_. ' 8 . , .

. ...

I !

-.

I I

. ._

6-28

Page 108: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

: '. I_- - . , .

. ' I . .... . I

' 1 -

, . - ' I

. . I ! . ' ' .

!

. . . ~ . -

. . . . . . - I '

. I

I I . . I ' . , . . . - - . .-. . . .- . - -. ..

6-29

Page 109: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

. ..

. -

.. _-_

II . . . . .

I I .

. . J.

6-30

.

.. ' 1 . - .

I - - -

Page 110: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

!

6-31

Page 111: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-32

Page 112: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-33

Page 113: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

. . . . . - I I

I ' I

- 1

I

6-34

Page 114: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

! U '

. -

! i !

... . , .

. .

I -- .

, .- -..--

I

6-35

Page 115: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-36

Page 116: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

c

6-37

Page 117: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

r l ' + . .I

- . , .

I -

1

I

6-38

Page 118: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

6-39

Page 119: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

7 .O LM/AGS/CES CONTROLLABILITY

7 . 1 DPS PHASING B U R N (AGS)

7 1 . 1 Telemetry Quantization Versus the Rate-Attitude Phase Plane

The inf l igh t telemetry data quantization was such tha t i t made i t impossible t o determine w i t h accuracy the Phase Plane about which the RCS system was operating. The telemetry encoder caused the ra te channels i n - crement t o be 0.107 deg/sec* and the a t t i t ude channels increment t o be 0.092 deg*. Figure 7-1 shows the theoretical phase plane. The cross-hatched areas i s a typical deadband area of the a t t i tude and r a t e telemetry resulting from the quantization employed. and shows the logic volts generated by changes i n ra te and a t t i t ude commands. The cross-hatched area resul ts from a typical telemetry quantization e r ror and demonstrates how much the logic volts can change without an a t t i tude or ra te change being shown on telemetry.

Figure 7-2 i s based on theory

The CES telemetry channels were sampled a t a 0.1 second rate. This sample r a t e did not permit the accurate measurement of changes f a s t e r t h a n about 2 . 5 HZ to be recorded.

The logic volt d a t a was o f greater value because the increment This error was 20% of (because o f the quantization) was 0.1 vol ts .

the theoretical 0.5 volt required to turn on a thruster pa i r , b u t l ess t h a n 10% of the logic volts generally present when the thrusters were on, and less than 1% of the maximum logic vol ts . q u a n t i z a t i o n error of 0.197 deg/sec was about 40% o f the maximum ra t e shown by telemetry, and a much greater percentage of the "average" r a t e . For these reasons, i t was decided t o generate the ra te from

The r a t e data

* 7.0 volts ( r a t e and a t t i t u d e scaling) = .02756 volts/TLM increment 254 (TLM increments)

= O.l97"/S/TLM increment .02756 volts .140 vol ts/deg/S

"its = 0.092 deg/TLM increment .30 vol ts/deg

7-1

Page 120: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

the logic volts in order t o better determine the maximum rates present during the ullage and DPS-2 b u r n . r a te , the resul t o f the exercise was s t i l l only an approximation. Also, because o f these inherent errors , approximations of angular accelerations were n o t considered.

However, because of the sampling

Figure 7-3 shows the logic volts generated during the ullage a n < DPS-2 b u r n . from the f l i gh t d a t a by the TRW 1800 computer.) rates generated by solving ‘the following expression.

(This figure and a l l subsequent figures were drawn Figure 7-4 shows the

-t e* - logic volts + 2,63 n - + e L

( P i t c h & Roll = - typical ) 9.597

1.5

- logic volts + 3.59 t J , - - + e 2

(yaw) 9.597 - 1 . 5

The (+) - i s dependent upon the recorded polar i t ies . e was taken from the recorded d a t a and was assumed t o be correct. This assumption was based on the fac t that a t t i tude error i s a slow moving function compared t o ra te . comprised only 1 /3 o f the phase plane deadband in pitch and roll ( 1 / 4 in yaw), while the rate quantization error comprised the ent i re phase plane deadband i n pitch and roll ( and 752 of the yaw deadband).

The value of

Also, the at t i tude quantization error

The pitch and roll rates recorded inf l ight are shown in Figures 7-5 and 7-7 (yaw rate no% shown). rates shown in Figure 7-4.

These may be compared t o the generated The quantization caused a bias in b o t h

* Derived from the ATCA expression: . Logic volts = ([+ ( e ) (0.3) ( 7 ) 2 ( e ) ( .140) (22 .5) ] - 4.57 - + 2.63) - 2

7-2

Page 121: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

:~c, .?s; t h e r e f o r e , t h e zeros were loca ted manually.

f i g u r e s revea ls t h a t t h e generated ra tes are s i g n i f i c a n t l y l a r g e r than the recorded r a t e s .

apparent by t h i s exerc ise, i .e. , s t r u c t u r a l resonance o r l i m i t cyc les , t h a t w r e c o t apparent i n t h e recorded data. However, i n r o l l a s i g n i - f i c a n t d i f f e r e n c e e x i s t s . Theore t ica l deadbands of 0.2 deg/sec, p i t c h

Comparison o f t h e

I n p i t c h , no other data o f s i g n i f i c a n c e became

ana r o i l , and 3.4 deg/sec f o r yaw are shown i n F igures 7-4 and 7-5. T h e o r e t i c a l l y , any r a t e s g r e a t e r than these, w i t h zero a t t i t u d e

e r r o r , would cause the t h r u s t e r s t o f i r e . S i m i l a r l y , t h e a t t i t u d e

e r r o r s recorded d u r i n g t h e u l l a g e and burn are shown i n F i g u r e 7-6

(zeros were loca ted manual ly) .

e r r o r deadbands i n d i c a t e d .

Th is f i g u r e has t h e t h e o r e t i c a l a t t i tude

By means o f t h e maximum r a t e s and a t t i t u d e gure 7-1) u t i 1 i zed

e r r o r s shown

was marked t o

i n p i t c h , yaw

n F igures 7-4 and 7-6, t h e phase p lane p l o t ( F

show the extremes o f a t t i t u d e and r a t e c o n t r o l

and r o l l d u r i n g t h e u l l a g e and burn.

O f i n t e r e s t i n the r a t e and a t t i t u d e data i s t h e apparent one-sided

r o l l i n s t a b i l i t y beginn ing a t 93:47:46.6 and ending a t 93:47:53.0 (see

F igures 7-4 and 7-6). w i t h engine c u t o f f . However, Figure 7-3 i n d i c a t e s (+) and ( - ) r o l l

l o g i c v o l t s generated d u r i n g t h i s i n t e r v a l w h i l e t h e a t t i t u d e and r a t e

f i g u r e s do n o t show an out-of-deadband s igna l t h a t would generate a

( + ) l o g i c vo l tage. q u a n t i z a t i o n e r r o r i s causing a f a l s e gyro n u l l and t h e zeros were

The end o f the apparent divergence i s c o i n c i d e n t

This leads one t o conclude t h a t t h e te lemet ry

n o t loca ted c o r r e c t l y . That i s , the discrepancy i s based on a mis-

l o c a t i o n o f t h e a t t i t u d e o r r a t e zero p o i n t . c a l c u l a t e d from l o g i c v o l t s (F igure 7-4) i s compared w i t h t h e r o l l

r a t e s recorded i n f l i g h t shown i n Figure 7-7, one may observe t h a t t h e r o l l r a t e from f l i g h t data does not show t h e r a t e peaks a f t e r 45 seconds

t h a t are shown on t h e c a l c u l a t e d r a t e data. The disagreement o f t h e

p l o t s i s a t t r i b u t e d t o the te lemetry q u a n t i z a t i o n e r r o r . Therefore,

t h e divergence d i d n o t e x i s t .

Fur ther , when t h e r a t e

7-3

Page 122: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

O f o ther i n t e r e s t i s t h e cont inued p i t c h down command, w i t h a few r o l l l e f t commands,

cou ld be explained by the p o s i t i o n of t h e cg a long (+) Y and ( + ) Z

p lus the hypothesis t h a t t h e t h r u s t of D3 was g r e a t e r than t h a t o f D1.

However, t h i s must remain a hypothesis i n t h i s a n a l y s i s s ince angular acce le ra t ions , necessary t o t h e proo f , cou ld n o t be obta ined f rom t h e

data because o f t h e te lemet ry q u a n t i z a t i o n e r r o r .

7.1 . 2 GTS Performance

throughout t h e u l l a g e (see F igure 7-3). Th is

F igure 7-8 shows t h e mot ion o f t h e DPS Engine through t h e DPS-2 burn.

of 0.198 deg/sec.

mot ion i s so descr ibed on t h e f i g u r e . t ime and p o l a r i t y w i t h t h e l o g i c v o l t s shown i n F igure 7-3.

The slopes drawn on t h e f i g u r e are drawn t o t h e nominal GDA r a t e

The LM body a c c e l e r a t i o n produced by t h e engine

The engine motions agree i n

The f i r s t mot ion o f t h e p i t c h GDA i s observed a t Gimbal Enable, 93:47:32.45 (32.45 on f i g u r e ) . t o t h i s t i m e i s a r e s u l t o f t h e te lemet ry sample r a t e and i s n o t an

anomaly a t t r i b u t a b l e t o t h e GDA. The GDA t h r e s h o l d was j u s t overcome p e r i o d i c a l l y a t t ime increments much longer than t h e te lemet ry sample r a t e o f 0.1 sample/second. As a r e s u l t , t h e apparent slow GDA mot ion was recorded.

The apparent slow engine mot ion subsequent

The GTS performance was s a t i s f a c t o r y throughout t h e DPS-2 burn.

7.1.3 CG O f f s e t s

From Figure 7-8, i t may be observed t h a t s t a t i c p o s i t i o n of t h e

engine moved ( - ) 0.234 degrees i n p i t c h and (+) 0.641 degrees i n r o l l between DPS-2 S t a r t and DPS-2 O f f .

above mentioned engine motions stem from t h e f o l l o w i n g f a c t s :

a ) P i t c h engine b e l l mot ion towards ( - ) Z causes body p i t c h up and p o s i t i v e go ing te lemet ry vo l tage.

b ) R o l l engine b e l l mot ion towards ( - ) Y causes body r o l l r i g h t and p o s i t i v e go ing t e l e m e t r y vo l tage.

c ) P i t c h engine b e l l mot ion towards ( - ) Z i s de f ined as (+) 6

The p o l a r i t i e s assigned t o t h e

P ' 7-4

Page 123: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8 ) R o l l engine b e l l motion towards (+) Y i s def ined

The engine t h r u s t i s app l ied t o the LM a t s t a t i o n X = 154".

as ('1 6R

P r i o r

t o the burn the cg i s t h e o r e t i c a l l y l oca ted near the X a x i s a t X =

192.49" (Ref.1).

was a t (-) 1.97 degrees i n the r o l l p lane and (+) 1.49 degrees i n

t h e p i t c h p lane p r i o r t o the burn. ( - ) 1.33 degrees i n r o l l and (+) 1.26 degrees i n p i t c h .

From F igure 7-8 i t may be observed t h a t t he engine

A f t e r t h e burn, t he engine was a t By t r igonometry ,

P r i o r DPS-2, cg Y = +1.32" cg z = +I .OO"

Post DPS-2, Cg Y = +0.90" cg Z = +0.85".

Resu l t i ng cg mot ion f rom s t a r t t o end o f burn:

Y cg motion, ( - ) 0.42" a long (+) Y Z cg motion, ( - ) 0.15" a long (+) Z

Th is i s t he opposi te d i r e c t i o n f rom t h a t p red ic ted . There i s no ex- p l a n a t i o n f o r t h i s discrepancy a t t h i s t ime. However, the change i s smal l and cou ld be the r e s u l t o f a cg m i s t r i m a t t h e s t a r t o f the burn s ince the prev ious burn (DPS 1 ) was w i t h the docked con f igu ra t i on .

7.2

7.2.1

DESCENT STAGE ATTITUDE HOLD (AGS)

Propel 1 a n t Consumpti on

The telemetered data ( rece ived by Ship Mercury i n the P a c i f i c )

was extremely no isy . As a r e s u l t , t he re were many f a l s e t h r u s t e r f i r i n g s i nd i ca ted . The fo l low ing l i s t i n g was der ived from a count

o f i n d i c a t e d f i r i n g s vs. du ra t i on i n the recorded 4-minute and

45-second a t t i tude ho ld per iod p r i o r t o DPS-2.

Number o f I nd i ca ted F i r i n g s

478 55

2 1 7 7-5

I n d i c a t e d F i r i n g Dura t ion (Seconds)

0.014 0.020 0.030 0.050

0.070

Page 124: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Number o f I nd i ca ted F i r i n g s

8 1 4

7 2 2 2

1 1 1

I n d i c a t e d F i r i n g Durat ion (Seconds)

0.080 0.100 0.150

0.200 0.250 0.300 0.400

0.500 0.600

0.800

However, a f t e r t h e data w e screened o f t h e o r e t i c a l l y impossib le

t h r u s t combinations p l u s t h r u s t on i n d i c a t i o n s when l o g i c v o l t s were n o t g r e a t e r than 0.5 v o l t s , t h e above t a b u l a t i o n was reduced t o t h e

f o l l o w i n g one.

Number o f I nd i ca ted F i r i n g s

24 30 1 1

I n d i cated F i r i n g D u r a t i o n - (Seconds)

0.014 0.020

0.050 0.080

P r o p e l l a n t usage p e r t h r u s t e r on t ime was e x t r a c t e d from t h e

Spacecraf t Operat ional Data Book, Volume 11. f o l l o w i n g t a b u l a t i o n was devised.

By t h i s means t h e

7-6

L

Page 125: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

Length of Th rus te r Pounds o f Number o f T o t a l Pounds F i r i n g (Seconds) Propel 1 a n t Used F i r i n g s Used

0.014 0.0075 24 0.180 0.020 0.0097 30 0.290 0.050 0.0203 1 0.020 0.080 0.0295 1 c =

l b = 0.109 min .520 l b 60 sec 285 sec m i n

0.030 0.520

The Spacecraf t Operat ional D a t a Book Volume I I p r e d i c t e d 0.11 4

l b /m in . Therefore, i t i s concluded t h a t t h e p r o p e l l a n t consumption was s a t i s f a c t o r y as a r e s u l t o f a s a t i s f a c t o r y CES. a t t i t u d e h o l d

performance.

7-7

Page 126: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis
Page 127: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

7-9

Page 128: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

I

7-10

Page 129: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

7-1 1

Page 130: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

7-1 2

I

I

,

Page 131: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

..

7-1 3

Page 132: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

! I i FIGURE 7-7 ' L - ... ' I !

!

7-1 4

Page 133: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

, i i . . . . . . . . . . . . . . . . . . . . . . . . . . ! . , . . . . . . . . . . . . . . . . , I , . . . . . . . - . . . . 1 . , . . .

. . 4 . . . . . . . . . . . . . . . . . . .

I 1 1 I

FIGURE 7-8

;,. l ~ . I $ y ; . ! ; . y f ~ ; . $ : , j . . . f , 3" . . . . . . . . . . . . . . .... c- .... . . . . . . . . . . . . I . , -.

A ..*. -.., . . . . . , . . . "t-'.:

7-1 5

Page 134: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8.0 RENDEZVOUS

8.1 ONBOARD NAVIGATION

Performance o f t he spacecra f t nav iga t i on systems du r ing t h e ren-

dezvous p e r i o d was e x c e l l e n t . A l l updates supp l i ed t o t h e LM Guidance

Computer (LGC) du r ing t h e rendezvous were from t h e onboard rendezvous

radar. F igure 8-1 t o 8-6 present a comparison of LM s t a t e vec to r

components a f t e r C S I w i t h the TRW HOPE Program and the i n t e g r a t e d s t a t e

vec to r components.

s t a t e s would have propagated i n the absence o f rendezvous rada r ob-

se rva t i ons .

converge on t h e BET s t a t e vec tors as radar marks were incorpora ted .

The i n t e g r a t e d s t a t e vec tors show h o i t h e onboard

From the data, t he tendency was f o r t h e s t a t e vec to rs t o

Dur ing t h e LM separa t ion per iod , t h e command-module p i l o t was

making sex tan t s i g h t i n g s when the LM was v i s i b l e and updat ing t h e LM s t a t e v e c t o r i n t h e Command Module Computer (CMC). p resent t h e CMC r e l a t i v e (CSM/LM) s t a t e v e c t o r components and t h e

p r e l i m i n a r y BET r e l a t i v e vec to r components d u r i n g the rendezvous

per iod . Although minimal CMC da ta were a v a i l a b l e du r ing the rendezvous

period,those which were ob ta ined show c lose agreement w i t h t h e BET

re1 a t i v e s t a t e vec tors .

8.2 RENDEZVOUS TARGETING

Figures 8-7 t o 8-9

Comparisons o f a l l executed nV s o l u t i o n s . d u r i n g the rendezvous w i t h

t h e pre-mission nominal A V ' S are shown i n Table 8.1. The t o t a l crV

r e q u i r e d t o perform the LM maneuvers was w i t h i n 4 percent o f t h e

nominal A V .

Dur ing the rendezvous sequence, var ious maneuver s o l u t i o n s were

a v a i l a b l e t o the LM crew. These a d d i t i o n a l s o l u t i o n s were a v a i l a b l e

as a comparison f o r eva lua t i ng t h e pr imary s o l u t i o n and f o r backup

purposes.

t r a j e c t o r y , onboard c h a r t s o l u t i o n s were ca l cu la ted , and t h e CSM had

a c a p a b i l i t y t o so l ve f o r TPI and midcourse maneuvers. near p e r f e c t r e l a t i v e t r a j e c t o r y and t h e accurate onboard n a v i g a t i o n , a l l s o l u t i o n s were e q u a l l y good and any one would have produced

approximately t h e same r e s u l t s . A l l of t he a v a i l a b l e s o l u t i o n s a r e presented i n Table 8.2.

The RTCC was c a l c u l a t i n g a s o l u t i o n based on the RTCC

Due t o t h e

8- 1

Page 135: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8.2.1 CSI Maneuver Evaluation

Three CSI solutions were available; the LGC solution, the RTCC solution and the charts. Each of these solutions impulsively sumned w i t h the LGC LM s ta tes and then propagating bo th LM and CSM orbi ts t o the time of CDH yields nearly identical AH resul ts as shown i n Table 8.3.

8.2.2 TPI Maneuver Evalution

For TPI , four solutions were available; the L G C , CMC, RTCC and

chart solution. i n Table 8.4.

All would. have produced equally good resul ts as shown S t a r t i n g from the TPI maneuver, the LGC s t a t e vectors

(obtained by integrating forward from the l a s t available LGC s t a t e vectors) were propagated out t o the Distance of Closest Approach ( D C A ) based on precision integration of the CSM orbi t and by incorporating separately i n t o the LM trajectory each of the available TPI solutions as impulsive maneuvers. Also determined was the time a t which the DCA occurred and theaV required to match orbi ts a t t h a t same time. The AV required is equivalent t o the b r a k i n g I V . i n the form of a s h i f t from the expected time fo r braking (TTPF) since time sh i f t s from nominal are c r i t i ca l due t o l i g h t i n g constraints d u r i n g the braking period. actually used) i s further substantiated by the smal 1 midcourse corrections ( < 4 f t j s ec ) actually required a f t e r T P I .

The DCA time was p u t

Accuracy of the LGC solution ( the burn

The CSM would have performed the TPI maneuver as a mirror image b u r n had the LM become incapacitated or had the LM primary and backup solutions f a i l e d GO/NO-GO t e s t s . To evaluate the CSM T P I solution, the mirror image burn was simulated one minute a f t e r the actual TPI time using the CSM A V solution and using the CSM onboard s t a t e vectors. The r u n indicated the CSM trajectory distance of closest approach to the LM would have been 4200 f t and the required b r a k i n g would have been 29 f t / s ec (nominal 30 f t / s ec ) . within one minute of predicted intercept time. and are expected due to the imperfections i n the targeting scheme.

The time o f intercept would have been These errors are reasonable

8- 2

Page 136: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

A C S I t o i n t e r c e p t e v a l u a t i o n - o f t h e LGC t a r g e t i n g was eva lua ted

S t a r t i n g w i t h

through s i m u l a t i o n by r e - f l y i n g each o f t h e a c t u a l rendezvous s o l u t i o n s

and by i n t e g r a t i n g o u t the passive v e h i c l e t r a j e c t o r y . t he LGC onboard s t a t e vec tors imned ia te ly p r i o r t o C S I , t he C S I AV was a p p l i e d as an impulse t o the LM v e l o c i t y s t a t e and the t r a j e c t o r y was

propagated t o CDH t ime. As shown i n Table 8.3, t he e r r o r between the

nominal d i f f e r e n t i a l a l t i t u d e a t CDH t ime and Ah from the C S I t a r g e t i n g i s 0.90 n.m., a reasonable e r r o r cons ider ing the imper fec t i ons i n t h e

t a r g e t i n g scheme and p r e f l i g h t s i m u l a t i o n e r r o r p r e d i c t i o n s . A t CDH t ime, the CDH AV was i m p u l s i v e l y app l i ed and the s t a t e s were propagated

t o the t ime o f TPI.

accomplished between CSI and TPI, i t was considered u n r e a l i s t i c t o use

the progagated s ta tes . Therefore, t h e LM s t a t e s were updated t o the

onboard values. (10 minutes p r i o r t o TPI) before loss o f s t a t i o n coverage. o f TPI, t h e T P I AV s o l u t i o n was impu ls i ve l y a p p l i e d and t h e d i s tance

of c l o s e s t approach t o the t a r q e t v e h i c l e determined (Table 8.5). t h e T P I s o l u t i o n and the f i r s t midcourse s o l u t i o n t r a j e c t o r y was

determined. Also, the T P I and both TPM s o l u t i o n s were used t o so l ve

f o r a t r a j e c t o r y propagated t o i n t e r c e p t . Resu l ts o f bo th cases a re

a l s o shown i n the tab le . The rendezvous t a r g e t i n g e r r o r s a r e w i t h i n

p r e f l i g h t s i m u l a t i o n e r r o r p red ic t i ons .

Since considerable rendezvous rada r updat ing was

The values used were the l a s t a v a i l a b l e onboard s t a t e s

A t t h e t ime

Next

8-3

Page 137: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8-4

Page 138: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

c

8-5

Page 139: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

s

8-6

N a I

v, Y

2

Page 140: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

.

8-7

Page 141: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8-8

Page 142: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

8

5

N > I

s VI 0 8

w

ci

s 2 VI

0.

v) 3 v) e W > z 0 v)

e 0 t- o W w W s t;;

8-9

Page 143: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

f

8-10

Page 144: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

3 % E 3 0 0

P 0

8 ??

0 t N

$01 X 14) 5 3 1 V N I O Y 0 0 3 ABN 'lN3NOdWO3-A Y 0 1 3 3 A 3AIlV13Y

8-1 1

Page 145: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

\

2 L 3 I

Page 146: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

c

TABLE 8.1. RENDEZVOUS TARGETING SUMMARY

S o l u t i o n Executed Maneuver A V Non;inal*(Ft/Sec) AV Ac tua l (Ft /Sec)

CSM Separat ion 5.0 5.0 RTCC

Phasing 88.8 90.5 RTCC

I n s e r t i o n 41.8 43.1 RTCC

C S I 38.9 40.0 LGC

CDH

TP I

MCC 1

39.1

22.9

0

41.5

22.3

1.4

LGC

L GC

LGC

MCC 2 0 2.0 LGC

Brak ing 28.7 27.8

TOTAL 266.2 273.2

Percent Above Nominal = 3.2

* A p o l l o 9 Spacecraf t Operat ional T ra jec to ry , Rev is ion 2, 20 February 1969

f

8-13

Page 147: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

s AVx--O

A V Y 4 hVz-* 5 .o

AV =+ 0.9 X AVy" AV =-90.7 z

AV --20.2 AVy-+ 0.4

X

RSS

+5.0

RSS

90.7oL

RSS

2 0 . 2 5 c

AV =-40 X

p,Vy-O AVz--14

RSS

42.37

TABLE 8.2 RENDEZVOUS T ~ C E T I N C

SOhITION

\ Maneuver ICC AEA CHARTS cm:

Separation

Phaatng

AV =19.6

hVy= 0.6 X

A V p - 3 . 3

ss 9.8W

AV --20. X AVy- 0 AVZ- 1.1

:ss !O. 180 TPI

AVx--40 . I

.3Vz-0 AVy=O

I S S

to.0

AV =-40.7 X

'V -0 Y

sv -1) 2

R S S

40.7 No Solutlon

ISS

i l .S25

- RSS

21.69:

- RSS

I . 38

RSS

42.011

I

AV, --19.! hVy-'- 0.1

AVz 9.1

AVx 19.4 AVy 0 .4

A d z -9.7

F 20.0

D 1.0

A h.0

D 0.0

AVx -4.6

AVy 0.5 EVZ 1-2.3

? F 1.0

u 0.0 hVx- 0.2 AV =-n.9

Y AVz=-l .8

RSS

2.022

2 7 .A 29 29.3

8-14

Page 148: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

C S I M TABLE 8.3

NEUVER EVAL

SOLUTION AH AT CDH T I G (349094 SEC)

LGC 9.9 n . m .

RTCC 9.5 n . m .

CHARTS 10.4 n . m .

Postf 1 i g h t 10.5 n . m . BET

NOTE: Nominal ah = 10.8 n .m.

TABLE 8.4

COMPARISON OF T P I SOLUTIONS

DISTANCE OF REQUIRED INTERCEPT T I M E SoLUT1oN CLOSEST APPROACH (FT) BRAKING AV (FT/SEC) S L I P (SEC)

LGC 2081 31.2 72 e a r l y

CMC 657 29.5 32 e a r l y

3973 34.8 140 e a r l y RTCC

CHARTS 1291 21.2 267 l a t e

NOTE 1 - LGC predicted i n t e r c e p t time:

NOTE 2 - Actual A V braking was 27 .8 f t / s e c .

TTPF = 354587.67 secs

8-15

Page 149: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

TABLE 8.5

PGNCS TPI MANEUVER EVALUATION

Maneuver Distance o f Required Brakin I n t erce p t T i me Closest Approach ( f t ) A v ( f t /sec3 S l i p (sec)

TPI Only 3585 33.0 94 e a r l y

TPI & TPM 3050 27.9 1 l a t e

TP I , TPM 1 & 2 2926 30.5 37 e a r l y

NOTE 1 - LGC predicted in tercept time: TTPF = 354587.67 sec.

8-16

Page 150: -3 2 SUPPLEMENT 2 l/i NATIONAL AERONAUTICS AND SPACE ... · 1 1 l76-h232-ro-w project technical report task e-38b a20llo ix guidance, navigation and control system performance analysis

REFERENCES

1. NASA SNA-B-D-027 (I I ) Rev. 1 "CSM/LM Spacecraft Opera t iona l

Data Book, Vol 1 1 LM Data Book P a r t 1, Rev is ion 1, 15 March

1969

2. NASA SNA-8-D-027 (11) Rev 1 CSM/LM Spacecraf t Operat ional

Data Book, Vol I 1 1 Mass Proper t ies , Rev is ion 1, November 7968.

3. M I T I L E-2377, LM D i g i t a l A u t o p i l o t S imu la t ion Resul ts Using

Program SUNDANCE January 1969.

R- 1 NASA - MSC