29 August 2013
AMD DebateTechnical solutions and funding models for theAcid Mine Drainage problems of South Africa
![Page 2: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/2.jpg)
![Page 3: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/3.jpg)
“Sophistication creates Simplicity”
![Page 4: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/4.jpg)
The Challenge
• Active mining and dewatering of the mines along the East, Central and West Rand mining basins declined and essentially ceased in 2010
• The underground voids have been filling with water which interacts with the exposed rock (pyrite) to form AMD
• In 2002 – AMD from the Western Basin started decanting into surface streams
• Decanting is expected to occur in 2013 in the Central Basin and 2014 in the Eastern Basin
• AMD is of poor quality and poses a definite threat to the environment and to the water resources of the Crocodile West and Vaal River Systems
![Page 5: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/5.jpg)
Current Short Term Solution
• Upgrading and construction of HDS (lime neutralisation) plants in the Western, Central & Eastern Basin
• pH increases & metals precipitate as insoluble metal oxides and hydroxides
• Precipitates are removed from the water via large clarifiers and deposited on waste storage facilities
• Advantages:– Proven, established process
– Can be adapted to variable water qualities and quantities
– Process is relatively stable and relatively easy to control
• Disadvantages:– Large volumes of mixed hydroxide and gypsum sludge
– Large plant footprints with associated CAPITAL costs
– Excessive “scaling” potential in down stream pipelines & processes
– DOES NOT remove the salts (desalinate) the water
– Long term de-stabilisation of waste residues unknown!!
![Page 6: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/6.jpg)
Alternative Short Term Solution
• Neutralization of & metals removal from AMD – using waste water from existing gold recovery processing
• pH increases & metals precipitate as insoluble metal oxides and hydroxides
• Precipitates are deposited with the gold tailings onto tailings storage facilities (TSF) and water is recovered from the TSF
• Advantages:– Combines two waste streams to solve both problems
– Disposal of solid waste is simplified
• Disadvantages:– Not yet fully developed process
– Long term de-stabilisation of waste residues unknown!!
– Effects of low density gold tailings onto conventional gold TSF’s not fully understood
– DOES NOT remove the salts (desalinate) the water
– Can only be operated in areas where there are operational gold processing plants
![Page 7: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/7.jpg)
The Challenge
• Should AMD, which has not been desalinated, be discharged into the Vaal River System, the salt load will require large dilution-releases to be made from the Vaal Dam to achieve fit-for-use objectives
• This will result in unusable surpluses developing in the Lower Vaal River
• In addition, should the dilution releases still be required after 2015, the acceptable levels of assurance of water supply from the Vaal dam will be threatened
• This means that there will be an increasing risk of water restrictions in the Vaal River Supply area
![Page 8: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/8.jpg)
Medium & Long Term Solutions
• PHYSICAL Processes– HDS followed by conventional RO– MIWATEK Process– Electrocoagulation & Precipitation
• CHEMICAL Processes– Alkali-Barium-Calcium (ABC) Process– Ettringite Process (SAVMIN)
• BIOLOGICAL Processes– Biological Sulphate Reduction (Biosure) Process– Biological Sulphate Reduction (Paques) Process
![Page 9: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/9.jpg)
HDS & Conventional RO
• HDS for neutralisation & metals precipitation and multi stage RO for desalination
• Advantages:– “Proven” process
– Only process that has been installed at scale required for treatment of Wits AMD
• Disadvantages:– Process has not yet been “proven” on gold AMD
– Large volumes of mixed hydroxide and gypsum sludge to dispose of
– Large plant footprints with associated CAPITAL costs
– Excessive “scaling” potential in down stream pipelines & processes
– Long term de-stabilisation of waste residues unknown!!
– Large volumes of lime required
– Energy intensive
– Final “brine” difficult to treat
![Page 10: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/10.jpg)
MIWATEK
• Multi stage chemical pre-treatment, metals precipitation & RO
• Advantages:– Analysis driven design, flexible and modular
– Does not use lime for neutralisation and therefore does not have any of the negative downstream effects
– Chemicals used in the pre-treatment/neutralisation can be recovered from the final “brine”
– Final “brine” stream can be processed to produce industrial quality reagents
– Dramatically reduced solid waste production
– Majority/total solid waste can be used by large industry as feed stock
– Unique & exclusive South African developed equipment producing rapid and complete chemical reactions resulting in dramatically reduced plant footprint and Capital costs
– Unique & exclusive low pressure first stage RO
– Process already piloted and demonstrated on Western Basin gold AMD water
• Disadvantages:– Not yet at “Proven” status
![Page 11: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/11.jpg)
Funding Models
• DBOOM – Design, Build, Own, Operate & Maintain• DBOM – Design, Build, Operate & Maintain
![Page 12: 29 August 2013 AMD Debate Technical solutions and funding models for the Acid Mine Drainage problems of South Africa.](https://reader036.fdocuments.us/reader036/viewer/2022062515/56649d155503460f949ea1a3/html5/thumbnails/12.jpg)