28th September-sirsa Report
Transcript of 28th September-sirsa Report
-
7/29/2019 28th September-sirsa Report
1/5
Solar Street lighting systems under the Jawaharlal Nehru National Solar Mission in Sirsa,
Haryana
Although the entire state of Haryana is connected to the grid, the state (especially rural areas)experiences frequent and sustained power cuts due to the power deficit scenario. Besides, the district of
Sirsa had no street lights until April, 2011. Even if street lights were proposed through conventional
power, the power cuts would affect the utility of such lights.
Therefore, after detailed surveys 6660 solar street lighting systems were sanctioned to 333
villages in Sirsa district. The systems comprise of a 74 W solar panel, 11W CFL and 12V battery. Theproject falls under the Off-grid solar photo voltaic applications scheme which is a part of the
Jawaharlal Nehru National Solar Mission. Each system costs Rs 18900 along with a 2 year warranty
period. With an additional Rs 100 the manufacturers have included a maintainance contract for 3 years.The sum of Rs 100 would only be paid after the 5 year period. The overall project cost comes upto
Rs 12.65 crores. Under the scheme, the Ministry of New & Renewable Energy has funded 30% of the
project cost (Rs 3.80 crore). The remaining 70% (Rs 8.85 crore) was shared between the beneficiaries
(villages) and the state.
Financing:
The MNRE has allotted for subsidies to cover 30% of the price of the system. According to theinitial project report, it was found that people in Sirsa were not capable of raising funds on their own.
Hence, in villages where self-financing was not possible, financial interventions were committed by the
state as explained below:
1. Self-financing
10 villages have borne the entire 70% of the cost (Rs 2.66 lac per village) out of the available
Gram Panchayat funds. The Gram Panchayats own most of the land in these villages. They leaseout land to farmers and farmers make payments on the leased land annually. In this manner, the
funds available with each of these villages has amounted to more Rs 10 lac per annum which
has allowed them to be capable of financing this project on their own.
2. Partly funded by the state
98 villages have gram panchayat funds anywhere between Rs 5-10 lacs per annum. Suchvillages were capable of pooling Rs 2.2 lacs each which is Rs 215.6 lac out of the required Rs
260.6 lacs for those villages. The Community Organisation head of the Hariyali Scheme met out
the remaining Rs 45.08 lacs. The Hariyali/District Development Plan's Watershed project is ascheme that aims to promote the economic development of the village community which is
directly or indirectly dependent on the watershed and to encourage restoration of ecological
balance in the village.
3. Fully supported by the State and Centre
The remaining 225 villages were completely incapable of funding themselves. Hence, the
entire sum of Rs 598.50 lacs was pooled out from the Backward Regional Grant Fund
(BRGF). The BRGF is developmental scheme under the Ministry of Panchayati Raj. The funds
aim to finance local infrastructural projects besides professional support on infrastructure in
selected rural districts.
-
7/29/2019 28th September-sirsa Report
2/5
Monitoring & Maintainance:
A Village Energy Committee was meant to be constituted in every village.The committee
would be headed by the village Sarpanch, the Gram Sachiv would be the secretary and another memberof the Gram Panchayat. The committee would also include an ITI passed youth who will be trained by
the supplier before the end of the 5 year maintenance period. HAREDA also monitors projects through
monitoring committee setup.In the first year of installation, every village has resolved to deposit a sum of Rs 2500 per
system in VEC accounts from the gram panchayat funds. Between the second to fifth year a sum of Rs
1000 per system has to be deposited in the VEC account annually. This leads to a sum of Rs 1,30,000per village in the VEC funds. This amount will be used to maintain the systems after the 5 year contract
with the suppliers. In reality, the VECs are yet to be constituted in these villages.
Report on villages visited:
1. Farwain Khurd
This village received financial support from the District Development Plan and CEL had supplied
systems here. All systems were found to be working. The village Sarpanch(Ramjas) and the villagers
expressed satisfaction with the street lighting systems. There were roughly about 120 BPL householdsin this village. Some lights have intentionally been placed within BPL household premises tomaintain equitable distribution. The villagers are now aware of solar energy and the Sarpanch
expressed interest in solar water pumps for the village due to unreliable power cuts. But the rest of thepanchayat members showed no interest since the population could not afford it in the and besides these
farmers have been receiving electricity for water pumps at a subsidized price of 0.25p/unit.
2. Farwain Kala
On talking to the villagers, it was apparent that the VEC had not yet been setup and none
from the village was yet trained to maintain the systems. The members of the houses in whichthe street lights were placed dusted the panels occasionally.
3. BharoKhan Dhani
26 systems were installed in the village. On visiting the Sarpanch's (Khajan Chand) house, we
found that the street light within his premises was not from the companies listed in the proposal.On inquiry, we discovered that the sarpanch had purchased 6 more solar street lights (6 watt,
LED bulb) out of funds, that was released by the Panchayat Samiti under the authority of the
13th Finance Commission, for the purpose of operating and maintaining water supply, street
lights and sanitation. The village was not eligible for any subsidies for these extra 6 street lights.The systems were working.
4. Sikanderpur
According to villagers, 4 systems were not working. On checking the defunct lights, the panels
had apparently never been dusted as the member of the house in which the light was erectedwas not asked to dust the systems. She did not seem aware of the fact that the panels needed to
dusted frequently. The VEC had not been set up here as well. The sarpanch claimed that more
than 4 sytems were not working in Sikanderpur. He had not written to the District level project
-
7/29/2019 28th September-sirsa Report
3/5
officer and he was asked to do so in order to take action.
5. Ganganpur
The next set of villages were visited at night. All systems were working. It was clear that the
lights were not enough. Some houses had fixed their incandescent bulbs in front of their houses
which helped a great deal in lighting up the street. An interesting case existed here where thestreetlight was erected literally under a tree. Although the light was working then, it is absurd to
locate it in such places. Besides the shadow of the tree, bird droppings could reduce panel
efficiency.
6. Shahpur Begu
The utility of the street lights is definitely the lowest here among the villages visited. The
village is heavily populated. The villagers stated that the lighting systems didn't do much good
except for the people living around it which was an absolute minority compared to the actualpopulation of the village which is roughly around 7500.
7. Odhan
Another populated village very similar to the case of Shahpur Begu. Besides the street lighting
systems Odhan and Ellenabad have been accepted proposals for 10 kw solar power plants by theMNRE under the same scheme for the current year (2011 12). The plants will be set up at the
Block Development & Panchayat Offices. The reason for setting up power plants here is to
increase the speed in filing reports by the officers to the central government on a daily basis
with regard to Mahatma Gandhi National Rural Employment Guarantee Act. The plants are yetto be commissioned.
8. Dharampura and Sant Nagar were the other two villages that were visited. Sant Nagar isagain a large village that did not benefit much from the 20 street lights that have been proposed.
Key Findings:
Theft of panels and batteries have been completely reduced by installing the systems within the
premises of the houses. Only the light bulbs have been made to stand out from the polesextending into the street. The batteries remain inside locked boxes which was extended inside
the rooms of houses in most cases. The keys remain with the members of the houses in which
the lights have been put up. There were no cases of theft yet under the scheme according to the
project officer and the villages visited.
Only 20 street lights per village seems inadequate for many villages where population is high.
The MNRE has withdrawn financial support for the project since their initial proposed target
has been achieved. In large villages, the beneficiaries are in such small proportions that the
utility of such expensive equipment is very low. Although people could become aware of solarenergy through just 20 systems per village the benefits would remain low unless demographic
conditions are taken into account.
The Village Energy Committees need to be constituted as soon as possible. There is no trained
person in these villages to repair and maintain the equipment although such measures have been
-
7/29/2019 28th September-sirsa Report
4/5
proposed in paper. There needs be regular dusting that needs to be done. In almost every
village, there were many panels that were not faced towards the sun. This could lead to
inefficient charging of the batteries. The villagers need to be educated on these issues evidently.
If a system turned out to be defunct or needed service, the process to ensure this is strenuous.
The village sarpanch would first be informed. He would then have to turn this in during a gram
panchayat meeting. From here, a letter including all the details of the failed systems will have to
be prepared and sent to the Project Officer. Then, the PO would inform the relevant supplier anda service is supposed to arrive within a short notice. Obviously, a lot of time could be saved if
the villagers could directly inform the manufacturers.
The Project officer noted that the state level Green Energy Funds have not been utilized for this
project at all by HAREDA which could probably have helped in implementing more systems.
-
7/29/2019 28th September-sirsa Report
5/5