25mw hfo power station1
-
Upload
david-adouglui -
Category
Documents
-
view
236 -
download
0
description
Transcript of 25mw hfo power station1
Compressed air cylinder, Turning gear, Jacket water pre-heater unit,
11kV outlet cable rack have been mounted on the engines
Main engine works completed, sensors/meters
checked and replaced, instrument cabling checked-
Engine 1 and 2’s exhaust piping insulation finished,
now working on engine 3 and 4.
Water pump motors tested and
ready, LO separators’ heating
module installed, LO separator and
booster unit connecting to the fuel
pipes.
Separator room: HFO separator in
position, incoming power ready, now
working on all piping and wiring
connections. Also waiting for the 2
transfer pumps in air-flight and 1
sludge pump
Radiator cooling system: Mainly completed. Just need to do painting of the support
structure, final run connection to the motors and meters in front of the heat
exchangers
11kV and LV switchgear panels:
Commission tests done with satisfactory
results. Most CB’s have been put back into
panel, termination work for the 11kV cable
to the switchyard completed
Engine monitoring panels: Commission
tests completed – no major defects except
some meters to be changed.
System control panel: To be
commission
Fire fighting pump room – Both diesel and
electrical pumps in position. Diesel pump
was tested to be ok -
Switchyard -
11kV cable laying between power plant
and switchyard completed –
Termination on the transformer side to
be completed in this week -