23 USC 326 Categorical Exclusions Six Month Report to FHWA
January 1, 2014 – June 30, 2014
Summary This report has been prepared pursuant to the Caltrans/FHWA Memorandum of Understanding (MOU) authorizing State assumption of responsibilities under Section 326 of Chapter 3, title 23, United States Code (23U.S.C. 326), as amended by the Moving Ahead for Progress in the 21st Century Act (MAP-21). MOU Section IV, State Performance Requirement F.1 requires Caltrans to provide a list of Categorical Exclusion (CE) determinations that it approves semi-annually. This report provides a list of all 23 USC 326 CE determinations reported between January 1 and June 30, 2014 (Quarter 27 and Quarter 28). Additionally, newly identified approvals from previous quarters are also included on this report. A total of 531 CE determinations were reported for the six month reporting period, including 203 State Highway System Projects and 328 Local Assistance Projects.
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
District-EA County Route Post MileDate
Signed
01-0B030_ HUM 96 008.3/ 6/24/2014
01-0B270_ DN 101 015.1/ 6/2/2014
01-0B340_ HUM 36 022.8/027.7 6/26/2014
01-0B450_ HUM 299 R010.7/R02 4/1/2014
01-0E430_ MEN 1 92.85/92.85 5/14/2014
01-0E600_ HUM 101 10.9 6/13/2014
01-26201_ MEN 101 052.2/052.4 6/4/2014
01-49370_ HUM 96 011.0/ 6/25/2014
02-0E090_ SHA 5 045.5/ 5/28/2014
02-4E890_ SHA 299 047.5/ 4/22/2014
02-4F610_ TRI 3 Mar-82 5/7/2014
02-4F710_ TEH 5 24.8/26.7 5/1/2014
02-4F720_ TRI 299 3.7/4.2 6/2/2014
03-0G160_ YOL 16 31.7/40.6 5/13/2014
03-0G170_ PLA 28 0/11 6/26/2014
03-1E760_ YUB 20 000.6/ 4/17/2014
03-1F400_ PLA 80 035.1/ 4/10/2014
03-3F790_ SUT 20 16.52/16.52 4/24/2014
03-4M860_ NEV 80 14.8/16.4 6/19/2014
04-1SS59_ VAR VAR 2.7/2.7 6/20/2014
04-23552_ SM 92/8211/11.5,
10.3/10.75/5/2014
04-2A331_ ALA 84 13.6/18 5/23/2014
04-2G940_ NAP 128 017.9/017.9 6/9/2014
04-3E790_ SM 101 23.66/23.66 5/13/2014
04-3G080_ SON 1 003.4/030.5 6/26/2014
04-4C200_ SCL 152 9.9/21.9 4/1/2014
04-4H900_ SF 280 R0.143 and 5/28/2014
04-4S920_ SON 1 19.6/0 5/6/2014
05-0R830_ VAR 1 0/0 5/1/2014
05-0S030_ SB, SB, SB1, 101,
150, 2460.0, 0.0, 0.0 4/24/2014
05-1A870_ SCR 1 16.95/17.17 6/16/2014
05-1C080_ SLO 101 12.1/29.9 5/6/2014
05-1C110_ SLO 101 12.1/29.9 5/6/2014
05-1C130_ VAR 1 R0/0 4/25/2014
05-1C170_ SLO 1 5.3 / 5.8 4/23/2014
05-1F890_ MON 1 28/28.6 5/29/2014
06-0L340_ FRE 168 T30.2 5/27/2014
06-0M370_ KIN 43 1.4 4/11/2014
06-0N180_ KIN 198 R8.8 / R10.5 5/30/2014
06-0P290_ KER 155 1.5 6/9/2014
06-0P670_ TUL 245 7.0 / 7.2 4/8/2014
06-0R070_ MAD 99 R1.0/9.5 4/8/2014
06-0S350_ VAR 5 0/26.72 6/9/2014
07-1W140_ LA 1 21.9/23.9 6/6/2014
07-28920_ LA 710 18.7/21.0 6/11/2014
Hennessy Ridge Shoulder Widening
RAC Overlay
Microsurfacing
Marysville Operational Improvement
Sut-20 Signal Poles
I-5 Cable Barrier
Repair cracked and deteriorating AC pavement
Source Control, Install irrigation system, plants, &
pavement
Auberry Road Intersection
Whitley Avenue Roundabout
Latache Median Barrier
Delano Roundabout
Woodlake Intersection Improvement
Pavement rehab (CAPM)
Construct Soldier Pile Wall - 0.1 mile south of
Russian River Bridge
SB/SLO County Curb Ramps
SB Curb Ramps
Santa Cruz 1/17 Shoulder Widening
North SLO 101 Roadside Safety
South SLO Roadside Safety
Orcutt ADA (1 Location)
Add Left Turn Channelization
Cow Cliffs Viaduct
Niles 2 short term
Knoxville storm damage - construct roadway
Paint Bridge at Sierra Pt Parkway
Construct soil nail walls
CAPM Pavement preservation
Install Concrete Barrier
Repair slide
Partial Cloverleaf to be widened at 2 diagonal off-
ramps & 2 signalized I/S will be created
299 Slip / Slides
Rockport Slipout
Sinkhole/culverts repair / District Director's Order
Hoopa Safety
Dog Creek - Sidehill Viaduct - Seismic
McCandless Gulch Curve Improvement
TRI-3 Deck Rehab
Red Bluff Ramps
State Highway System Projects
Project Description
Hoopa Vista Point Curve Correction
Last Chance Slips
Larabe 3 Slip Repair
Replace Damaged Fence
Coho Mitigation @ Ryan Creek
I-80 3 Mile Truck Climbing Lane
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
1
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
07-29080_ LA 1 2.75/12.17 6/19/2014
07-29340_ LA 5 25.2/25.9 6/30/2014
07-29770_ LA 110 23.7/25.5 5/12/2014
07-1W700_ LA 066 0.0/3.0 6/3/2014
07-2W640_ LA 10 20.2/23.6 5/6/2014
07-2W650_ LA 57 Various 5/6/2014
07-2W660_ LA 10 26.8/30.8 6/12/2014
07-2W670_ LA 010 23.9/26.4 6/24/2014
07-2W680_ LA 110 24.53/29.28 6/19/2014
07-2W690_ LA 5 13.89/28.7 6/16/2014
07-2W700_ LA 10 0.0/0.0 6/11/2014
07-2W710_ VEN 33 Various 4/29/2014
07-2W730_ LA 110 07.0/16.7 6/13/2014
07-2W740_ LA 110 16.98/23.69 6/12/2014
07-2W750_ LA 405 Various 6/13/2014
07-2W760_ LA 5 34.2/56.1 6/12/2014
07-2W770_ LA 118 Various 6/5/2014
07-2W840_ LA 101 27.63/32.08 6/23/2014
07-30060_ LA 405 20.5/28 6/5/2014
07-30070_ LA 5 13.8/19.2 6/17/2014
07-30170_ LA 210 33.7/39.8 4/9/2014
07-30260_ LA 57 4.45/12.12 6/2/2014
07-30290_ LA 5 43.9C/46.3C 6/4/2014
07-30570_ LA 110 25.48/25.8 4/1/2014
07-30620_ LA 91 R11.32/R20. 6/2/2014
07-30640_ LA 210 24.7/44.92 6/10/2014
07-30800_ LA 5 19.2/28.9 6/12/2014
07-30850_ VEN 23 11.4/11.4 6/12/2014
07-30860_ LA 10R2.15/R14.8
36/13/2014
07-3P890_ LA 91 17.6/20.5 5/2/2014
07-3P900_ LA 210 34.6/34.6 5/27/2014
07-3P930_ LA 110 27.063 5/28/2014
07-3X820_ LA 39 21.6/21.9 6/5/2014
07-4X230_ LA 39 41.0/44.0 4/24/2014
08-0N56U_ SBE 40 R94.7/R99.7 4/25/2014
08-0Q790_ SBD 40 93.60/93.65 4/25/2014
08-0R003_ SBD 138 / 5/5/2014
08-0R710_ SBD 15 87.26/91.81 6/24/2014
08-1C370_ RIV 95 0.0/36.2 5/12/2014
08-1E480_ RIV 79 12.6/12.9 5/5/2014
09-35880_ MNO 395 44.1-51.2 6/27/2014
10-0K140_ STA 120 0.0 / 4.3 5/23/2014
10-0W140_ MER, SCL 152, 152 R0.0 / R2.4, 4/10/2014
10-0Y900_ SJ 99 18.5/22.9 4/8/2014RHMA overlay
Non-Capacity Increasing Operational Improv, Install
Flashing Beacon & Signs
Repair Slope Failure
D.O. - Roadway Sideslope Damage
Bridge Replacement (Haller, Rojo, Clipper)
SR152 Median Barrier Near Pacheco Pass Summit
Install double thrie beam barrier - Coyote Lake
Mill and overlay pavement w/digouts
Install metal beam rail
Rush Creek Thin Blanket
Oakdale pavement repairs
Paint girders & beams, replace appr slabs, etc
0714000151 - LA-091 Roadway rehab
Hoff Bridge Replacement (BR #54 0889L&R)
Various Locations / Pefection of Title
0714000165 - LA-210 Install upgrade transportation
management system
0714000224 - LA-005-Ramp/ADA Ramp Repair
0714000245 - VEN-23, Upgrade Ramp Metering
0714000246 - LA-10, Upgrade Ramp Metering
Systems & convert Field Element
Const slope paving at bridge abutments
Foothill Maint. Station L5743, Install CNG fuel
0714000162 - LA-101, Line Ditch, Repair & Replace
Culverts
0713000485 - LA-405, Pavement rehab
0713000492 - LA-5 Pavement rehab
Repair Irrigation Systems & Planting
0713000483 - LA-057, Slab Replacement and Grind
Roadway Rehabilitation
Patch bridge deck spalls, pier walls, AC overlay, &
seal deck cracks
Meth Deck, Spall Repair, Joint Seal
0713000437 - Deck METH, Joint Seal, Approach
slab and spall repair
Meth Deck, Joint Spall Repair, Joint Seals
Bridge Preservation
Repair Joint Seal, Spalls, Methcrylate Deck
Replace bridge joints, meth deck, spalls
Bridge Rehabilitation
Various bridge maintenance work
Bridge Preservation
Bridge Preservation fr Eastern Ave to Allen Ave,
Repair deck & joint seals
0713000438 - Joint Seal, etc.
LA 1 ADA - Upgrade Pedestrian Facilities
Meadian Barrier
Install Safety Lighting
0713000050 - Microsurfacing
Replace joint seals, repair spalls, AC rdwy, etc.
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
2
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
10-0Y910_ MER 59 23.3/33.7 4/9/2014
10-1C030_ TUO 108 2-Feb 5/12/2014
10-1C090_ SJ 4 R16.6 6/25/2014
10-3A750_ SJ 4 0.0 / 8.2 6/11/2014
11-2M640_ SD 8 R5.8-R18.5 4/3/2014
11-2M740_ IMP 111 23.9/40.5 5/7/2014
11-2M780_ IMP 8 R28/R40.9 6/23/2014
11-2T190_ SD 15 5.6/6.0 5/12/2014
11-41470_ SD 67 9.3/11.2 4/23/2014
12-0H234_ ORA 5 23.8/23.8 6/19/2014
12-0M520_ ORA 39 20.17/20.17 6/5/2014
12-0N130_ ORA 57 21.59/22.09 6/17/2014
12-0N220_ ORA 5 23.8/23.8 4/10/2014
District-EA County Route Post Mile Project Description TypeDate
Signed
01-0B270_ DN 101 015.1/
015.3Last Chance Slips De minimis only 06/02/14
District-EA County Route Post MileDate
Signed
01-0C480_ HUM 101 69.9/75.1 08/03/2013
01-0C900_ MEN 101 50.7/51.2 12/06/2013
01-41540_ MEN 101 074.8/
081.412/15/2013
02-4E850_ SIS 005 45.7 02/14/2014
03-4M840_ NEV 80 21.2/28.1 07/13/2013
04-4H570_ SON 112 01/21/2014
05-1E060_ MON 101 47.6 / 53.8 11/05/2013
06-0Q630_ FRE 41 R29.3 / 33.4 09/03/2013
06-0R150_ KER 58 R88.5/R99.8 02/05/2014
06-0R230_ FRE VAR 24.5/31.37 12/19/2013Install High Friction Surface Treatment2
Yreka Storm Drain & Paving1
Resurfacing (grind existing bonded wearing course
overlay, profile grind PCC surface, apply concrete
hardener)2
Replace pavement and overlay1
Concrete median barrier, inside shoulder widening
and rumble strip2
Roadside safety improvements2
Pavement Preservation (CAPM)1
NB 57 Brea Safety Improvement
1213000182 - I-5 Upgrade existing A/V & Video Wall
in D12 TMC
1114000092 - Mill & Replace with RHMA Overlay -
HM1 - 124
Construct Class I bike path in San Diego County
(Route 15 from Adams Avenue overcrossing to
Camino Del Rio South undercrossing)
Drainage improvements and high friction surface
treatment
1214000037 - Advanced reports to support the TMS
and CHP
1212000096 - Modify signal add lighting refresh
pavement marking
Repair Hinges and Bearing Pads
Hwy. 4 Rehab & Old and Middle River Bridges
Replacement
Pavement Rehab
Imp-111 , AR Chip Seal
RHMA overlay
Tuolumne 108/49 intersection improvements
State Highway System Projects - Section 4(f)
Approvals from Quarters 24 - 27 State Highway System Projects
Project Description
Men 101 OGAC Overlay near Willits2
Laytonville North Rehab2
RHMA overlay2
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
3
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
06-0S330_ KER 046 29.9/30.5 03/05/2014
07-4X110_ LA 2 15.1 08/30/2013
08-0R250_ RIV 010 154.6/156.1 05/13/2013
08-0R850_ SBD 5718 05/01/2013
08-1C410_ SBD VAR 0/0 05/23/2013
11-2E003_ SD 5 34.8/35.1 06/20/2013
11-2M650_ IMP 86 67.8/43.1 06/28/2013
12-0H007_ VAR VAR / 08/06/2013
12-0N070_ ORA 005 19.7/20 03/17/2014
District-EA County Route Post Mile Project Description TypeDate
Signed
None
Federal Aid Project
NumberDistrict
Date
Signed
BHLO-5914(070) 01 LAK 04/08/14
BPMP-5904(120) 01 HUM 06/10/14
BPMP-5904(121) 01 HUM 06/10/14
BRLO-5914(067) 01 LAK 04/08/14
BRLO-5914(068) 01 LAK 04/09/14
BRLO-5914(071) 01 LAK 04/08/14
HRRRL-5904(136) 01 HUM 06/24/14
HSIPL-5017(040) 01 HUM 06/12/14
RPSTPLE-5904(128) 01 HUM 04/22/14
BPMP-5903(056) 02 MOD 06/27/14
BRLO-5909(029) 02 PLU 05/13/14
Relocate East Hobson Way Westbound Ramps
Inspection Station2
Construct sandhouse at the Mountain Pass
Maintenance Station (SBD 15 PM 170.6)2
Methacrylate and/or Polyester Concrete Overlay and
Replace Joint Seals2
Dean Mitigation Site: Purchase and restore
environmental mitigatin parcels2
Apply Asphalt Rubber Chip Seal2
Provide CCTV in Orange County Freeways2
Rte 5, 55, 73 Grooving, OGAC, polyester concrete,
restriping1
Pedestrian and ADA improvements - CA Aqueduct
Lost Hills1
D.O. Bridge Repair from Truck Fire2
Bridge Rehabilitation - Harbin Springs Road over
Harbin Creek (Br. No. 14C-0111)
Local Assistance Projects
Project DescriptionCounty
Bridge Replacement - Foard Road Bridge over
Anderson Creek (Br. No. 14C-0076)
Bridge Replacement - Highland Springs Road Bridge
over Highland Creek (Br. No. 14C-0085)
Install Striping - Countywide, various locations
Install pedestrian countdown heads and ADA push
buttons - 25 Intersections throught the City of Eureka
Approvals from Quarters 24 - 27 State Highway System Projects - Section 4(f)
Bridge Rehabilitation - Various Bridges in Humboldt
County
Bridge Rehabilitation - Various Bridges in Humboldt
County
Bridge Replacement - Ackley Road Bridge over
Manning Creek (Br. No. 14C-0083)
Pedestrian and Bike Path - Red Cap Road Bike and
Pedestrian Improvements
Bridge Related - Other - Develop Bridge Preventive
Maintenance Plan
Bridge Replacement - In Plumas County - Blarsden
Gragle Rd. @ Middle Fork Feather River 0.5 mi N of
SH 89 - Br. #09C0134
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
4
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
RPSTPL-5903(044) 02 MOD 04/30/14
RPSTPL-5909(106) 02 PLU 05/02/14
SRTSL-5068(048) 02 SHA 05/13/14
BRLO-5918(076) 03 SUT 06/26/14
BRLO-5924(184) 03 SAC 05/12/14
BRLS-5925(126) 03 ED 06/25/14
CML-5163(032) 03 SUT 05/28/14
CML-6158(066) 03 PLA 04/14/14
CMLFSP15-
6158(067)03 PLA 05/22/14
HSIPL-5142(034) 03 BUT 04/08/14
HSIPL-5425(026) 03 BUT 06/11/14
HSIPL-5479(042) 03 SAC 06/09/14
HSIPL-5917(086) 03 NEV 04/14/14
HSIPL-5917(087) 03 NEV 04/23/14
HSIPL-5919(112) 03 PLA 04/14/14
HSIPL-5919(118) 03 PLA 06/03/14
HSIPL-5922(094) 03 YOL 04/18/14
RPSTPL-5062(018) 03 GLE 05/14/14
RPSTPL-5062(019) 03 GLE 05/14/14
Road Rehabilitation - from Cedarville to Fort Bidwell
on County Road 1: Surprise Valley Road.
Road Rehabilitation - Bucks Lake Road Pavement
Rehabilitiation (Snake Lake Road to Slate Creek
Road) Near Meadow Valley west of Quincy, on
Bucks Lake Road between Snake Lake Road adn
Slate Creek Road.
Pedestrian and Bike Path - On west side Bidwell
Road from Bonnyview Elem School south to N
Bonnyview Rd; then east on north side North
Bonnyview Rd to East Bonnyview Road.
Bridge Replacement - Pennington Rd at Sutter Butte
Canal bridge ~0.5 mile East Sheldon Rd
Replace existing 2-lane functionally obsolete bridge
with a new 2-lane bridge - Apple Rd over Fruit
Channel 0.65 miles southeast of Dillard Rd
Bridge Related - Long Term Mitigation - Green
Valley Road at Tennessee Creek Bridge
Pedestrian and Bike Path - Garden Hwy, from
Lincoln Rd to Winship Rd
Planning,Programming and Monitoring - Congestion
Management Program
Freeway Service Patrol - SR65 and I80 within Placer
County
New Signals - Oro Dam Blvd./Orange Ave./Acacia
Ave.
Upgrade Signals - 15 intersections throughout
Paradise
Signal Synchronization - Franklin Blvd. between Elk
Grove Blvd. and Big Horn Blvd.; Bruceville Rd.
between Elk Grove Blvd. and Big Horn Blvd.
New Signals - Brunswick Rd/Loma Rica Dr
Install striping and pavement markers - Various
locations throughout Nevada County
Install Pavement Raised/Reflective Markers -
Various locations throughout Placer County
Install High Friction Surface Treatment - 18 various
locations throughout Placer County (See Field
Review Form)
Install left-Turning Lanes - County Road 31/County
Road 95
Reconstruct roadway - Sacramento St from
Sycamore St to Wood St
Reconstruction of roadway, curb, gutter, and
sidewalk. - Butte St South from Willow St to Wood
St
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
5
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
STPL-5046(040) 03 YOL 06/25/14
STPL-6085(059) 03 SAC 06/04/14
CML-5005(126) 04 SCL 04/22/14
CML-5934(173) 04 SF 05/07/14
CML-5937(200) 04 SCL 06/03/14
CML-6084(188) 04 MULT 06/05/14
CML-6429(008) 04 NAP 06/30/14
DEM06L-5933(122) 04 ALA 06/19/14
HPLUL-5273(024) 04 SM 05/29/14
HSIP-5005(135) 04 SCL 06/03/14
HSIPL-5177(031) 04 SM 06/06/14
HSIPL-5306(027) 04 SCL 06/03/14
IPSTPLE-6000(055) 04 MULT 06/02/14
NMTPL-5043(027) 04 MRN 05/21/14
RSTP-5034(023) 04 SCL 06/26/14
SR2SNI-5438(016) 04 SM 05/12/14
SRTSL-5005(124) 04 SCL 04/22/14
STPL-5114(017) 04 SON 06/05/14
STPL-5123(015) 04 SON 05/12/14
Pedestrian Walkway - Downtown Streetscape (Main
St)
Bicycle Related - Other - SACOG Region - Regional
Bicycle and Pedestrian Data Collection
Install low cost engineering enhancements to
improve safety along SRTS routes - 35 Schools in
San Jose.
Pedestrian Walkway - Vicinity of ER Taylor
Elementary School
Pedestrian Walkway - Non-Infrastructure Safe
Routes to School
Implement a pilot bikesharing program. - San Mateo
and Santa Clara Counties
Bike Path - NCTPA Napa Valley Vine Trail - Various
locations
Pedestrian and Bike Path - East Avenue from E. St.
to Camino Vosta
Upgrade Signals - Willow Rd between Middlefield
and Hamilton
Install Traffic signals; Construct sidewalk and raised
median. - On Ocala Ave: Daytona Dr to E Capitol
Expressway
Install Traffic Signals - Mission Rd./Evergreen Dr.
Install Traffic Signals.Signs, Pavement Markers -
Harriet Avenue (McCoy Ave to San Tomas Aquino
Rd)
Bicycle Related - Other - Capitol Corridor locations
between Roseville (Placer County) and San Jose
Bicycle Related - Other - Francisco Blvd. East from
Bellem to Grand.
Bike Path - Western Ronan Channels & Lions Creek
Safe Route to Schools - Fordham Bay Pulgas, Non
Infrastructure
Install sidewalk, curb/gutter, drainage modification
and new street lights - On Bucknall Rd Between
Mayfield Ave. to Woodglen Dr.
Road Rehabilitation - Napa Road from west of
Broadway Avenue to Jones Street
Reconstruct existing street: grind out existing
asphalt, recompact baserock, repave with HMA. -
Keating Avenue from North Main Street to Pitt
Avenue
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
6
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
STPL-5127(028) 04 CC 05/12/14
STPL-5261(008) 04 SM 04/04/14
STPL-5314(010) 04 SCL 05/07/14
STPL-5322(055) 04 ALA 06/04/14
STPL-5350(020) 04 SM 05/12/14
STPL-6249(037) 04 SOL 05/19/14
BRLO-5943(054) 05 SBT 04/18/14
CASB12RP-
5391(013)05 SLO 04/07/14
ER-20E0(011) 05 SCR 06/03/14
HPLUL-6090(072) 05 SB 06/12/14
HRRRL-5951(150) 05 SB 04/28/14
HSIPL-5045(027) 05 MON 05/15/14
RPSTPLE-5359(018) 05 SLO 04/07/14
SRTSL-5080(029) 05 SB 05/15/14
BR-NBIL(523) 06 TUL 06/09/14
CML-5060(180) 06 FRE 05/29/14
CML-5060(216) 06 FRE 06/04/14
CML-5060(267) 06 FRE 06/16/14
CML-5109(209) 06 KER 04/01/14
Asphalt Concrete Overlay - Railroad Ave from north
of Linscheid Driver to south of State Rte 4
Road Reconstruction - Atherton Ave, Fair Oaks
Lane, Middlefield Rd.
Repair Failed AC pavement, Resurface Road,
reconstruct ADA curb Ramps, Repair sidewalk and
curbs, - Various Locations
Multi-Modal Improvements, Bicycle and Pedestrian
Improvements. - Capital Ave. - Fremont Blvd. to
State St., Fremont City Center
Pavement Rehabilitation - Linda Mar Blvd Blvd
between De Solo Dr and Adobe Dr
Priority Conservation Area (PCA) Program - Solano
County
Bridge Replacement - San Benito County Rocks
Road Bridge #43C0053 over Pinacate Rock Creek
Bike/Pedestrian Structure - Morro Bay from Hwy 1 to
Morro Rock
Emergency Opening and Restoration-Slipout - In the
Co of SCR on Felton-Empire Road (PM2.58) DAF#
DDM-SCRCO-005-0
Equipment Purchase - In Santa Barbara County
Pavement Markings: Install rumble strips and
flashing beacons - W. Betteravia Rd (Simas Rd.)
Between Black Rd and W. Main St
Upgrade Signals - Sanborn Road Signal
Improvements
PHASE 3: Grover Beach on West Grand Avenue
from the western city limits to 5th Street. Landscape
medians and parkways, install bike lanes, decorative
sidewalks, and crosswalks.
Replace Low Water Crossing / Br. No. 00L0057 -
Road 224 at Deer Creek
Interconnect Signals and Installation of signal
coordination - Willow Avenue from Ashlan to
International Avenue.
Safe Route to Schools - Infrastructure Project - In
the City of Lompoc various locations throughout the
City - Infrastructure Project
Install wireless networking cummunication
equipment, cotrollers, cameras and update signals -
West Avenue from Herndon to Olive Avenues
Install New Signals - Clinton and Valentine Avenues
Intersection
New Signals - Buena Vista Road At Harris Road &
Buena Vista Road from White to Panama Lanes
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
7
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
CML-5143(027) 06 TUL 06/12/14
CML-5143(028) 06 TUL 06/12/14
CMLNI-5044(100) 06 TUL 05/06/14
CMLNI-5143(025) 06 TUL 04/24/14
CMLNI-5287(037) 06 KER 06/02/14
HSIPL-5060(274) 06 FRE 05/28/14
HSIPL-5060(275) 06 FRE 05/28/14
HSIPL-5060(276) 06 FRE 06/16/14
HSIPL-5060(277) 06 FRE 05/28/14
HSIPL-5060(282) 06 FRE 06/16/14
HSIPL-5109(211) 06 KER 05/03/14
HSIPL-5122(080) 06 TUL 04/28/14
HSIPL-5252(018) 06 FRE 05/22/14
HSIPL-5942(231) 06 FRE 04/28/14
RSTPL-5950(373) 06 KER 04/03/14
STPL-5044(102) 06 TUL 06/17/14
STPL-5060(244) 06 FRE 05/01/14
STPL-5060(254) 06 FRE 04/16/14
STPL-5060(262) 06 FRE 06/16/14
STPL-5224(020) 06 FRE 06/04/14
STPL-5291(021) 06 FRE 05/28/14
STPL-5301(015) 06 FRE 05/21/14
STPL-5370(024) 06 KER 04/24/14
STPL-5942(235) 06 FRE 05/27/14
Road Related - Shoulder Stabilization on Road 72
from Nebraska Avenue to Saginaw Avenue.
Road Related - Other / Shoulder Stabilization - West
Sierra Way from Rd 70 to Rd 72.
Equipment Purchase - Visalia
Equipment Purchase - Purchase One CNG Street
Sweeper.
Equipment Purchase - City of Wasco
Install Left Turn Phasing - McKinley and Palm
Avenues Intersection
Install left turn phasing - Cedar Avenue and Bulldog
Avenues Intersection
Install New Signals - Clinton and Vassar Avenues
Install Left turn phasing - Tulare and 'R' Streets
Intersection
New Signals - Shields and Weber Avenues
Intersection
Install pedestrian countdown signal heads - 60
Intersections throughout the City
Upgrade Signal to install protected left-turn phasing. -
Intersection of Putnam Street and D Street
Intersection Improvements and provideing LT turns
& RT Turns and Modifying Signal. - Intersection at
Manning Ave and Zediker Ave
Install New Signals,left turn pocket and road
widening - Grantland Ave and Shaw Ave
Asphalt Concrete Overlay - Elk hills road from
Skyline road to SR 58
Asphalt Concrete Overlay - North Avenue btwn.
Cedar and Maple Avenues
New Signals - SH99 NB Off-ramp at Ventura Street
Asphalt Concrete Overlay - Herndon Avenue
between Blackstone and West Avenues
Road Rehabilitation - Pavement resurfacing - 16th
St, O St, & Q St., City of Firebaugh
Roadway Widening, curb, gutter, sidewalk. - On
Vineland Ave from Kearny Blvd to Sunset Ave.
Road Reconstruction - Anchor Ave. from Adams
Ave. to Park Blvd.
Road Reconstruction - Campus Dr: Grapevine Dr to
approximately 800' North of Varsity Rd
Asphalt Concrete Overlay - Manning from 1.379
miles west of Lassen Alignment to Placer.
Road Rehabilitation - Visalia
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
8
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
STPLE-5950(383) 06 KER 06/19/14
BHLS-5450(080) 07 LA 05/07/14
BPMPL-5953(679) 07 LA 04/09/14
CML-5006(647) 07 LA 06/04/14
CML-5026(054) 07 VEN 06/10/14
CML-5200(046) 07 LA 04/30/14
CML-5393(033) 07 VEN 06/05/14
CML-5952(171) 07 VEN 05/08/14
CML-5952(172) 07 VEN 06/04/14
CMLGNI-6155(086) 07 VEN 05/08/14
HPLUL-5455(016) 07 LA 05/08/14
HSIPL-5006(769) 07 LA 04/30/14
HSIPL-5006(773) 07 LA 04/16/14
HSIPL-5108(164) 07 LA 06/12/14
HSIPL-5403(022) 07 LA 06/06/14
Construct Class I Bike Path and pedestrian walkway.
- Tehachapi Cummings Valley Water District
Property : Highline Road to Valley Blvd.
PM000024 BRIDGE PREVENTIVE MAINTENANCE
PROGRAM - FIVE (5) VARIOUS BRIDGES IN THE
CITY OF SANTA CLARITA.
Bridge Preventative Maintenance Program - Various
Locations within Los Angeles County -Group 5 (18
Bridges)
Planning,Programming and Monitoring - Angels
Walk Crenshaw. To promote pedestrian activity
within the project limits with a guidebook and 15 on-
street information markers (historic stanchions) at
strategic locations.
Construction of bike path - Bike Path on property
along HWY 126
Burbank Channel Bikeway Regional Gap Closure -
Burbank Western Channel: Downtown Burbank
Metrolink-Alameda Ave, within the city limit
Signalize 4-way stop intersection of Dunnigan St.
and Arneill Rd. - Arneill Rd. from Las Posas Rd. to
Ponderosa Dr., Dunning St. from Mobil Ave. to
Bordeaux Ave.
Construction of ClassII Bike Lanes on both sides of
Las Posas Road. - Las Posas Road Bike lanes
Upgrade 3 berths with electrical shoreside power
units at wharf 1 - In the city of Port Hueneme on
ponoma St. 3 miles southeast of HWY 1
Rideshare activities within the County of ventura -
Within Ventura County
Grand Avenue Enchancement/Rehabilitation.
Beautification,Streetscape/Hardscape & Pedestrian
improvement - Grand Avenue
Enchancement/Rehabilitation.
Install 1 new & upgrade 7 existing traffic signal -
Corbin Ave./Roscoe Blvd.; Glenoaks Blvd./Hubbard
St.; Mason Ave./Roscoe Blvd.; Saticoy St./Winnetka
Ave.; Sepulveda Blvd./Vose St.;
Install new traffic signals - Pico Blvd./Wooster St.;
Pico Blvd./Bedford St.
Realign Intersection, Install Traffic Signal and Install
Bike Path - Intersection of Walnut Avenue and 20th
Street
Construct two right turns, modify traffic signal and
install pedestrian heads. - Avalon Blvd and Carson
Sreet Intersection
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
9
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
HSIPL-5419(041) 07 LA 04/21/14
RPSTPLE-5064(080) 07 LA 05/02/14
RPSTPLE-5953(685) 07 LA 04/28/14
RPSTPLE-5953(686) 07 LA 04/24/14
SRTSL-5006(732) 07 LA 05/14/14
STPL-5006(774) 07 LA 06/12/14
STPL-5006(783) 07 LA 06/12/14
STPL-5064(077) 07 LA 05/19/14
STPL-5064(081) 07 LA 05/07/14
STPL-5315(013) 07 LA 06/09/14
STPL-5325(016) 07 LA 04/15/14
STPL-5334(047) 07 LA 04/22/14
STPL-5351(029) 07 LA 06/06/14
STPL-5405(081) 07 VEN 04/08/14
CML-6053(117) 08 SBD 06/19/14
CML-6053(118) 08 SBD 06/19/14
HSIPL-5188(020) 08 SBD 05/27/14
Modify Traffic signals; upgrade crosswalks; install
pedestrian countdown heads.pedestrian refuge -
Ave.I/10th St. West, Ave K/30th St. West
Install ped-scale street lights,trees,bus
benches,trash receptacles and bike racks - North
Fair Oaks Ave between North City Limit and Cedar
street in the City of Pasadena
Design & Construct class II bike lanes on Vermont
Ave - Vermont Ave-Manchester Bl to El Segundo Bl
Improve bicycle access to the Florence Avenue Blue
Line station. - Florence Metro Blue Line Station
Construct road diet with bike lanes, crosswalks, and
median refuge islands and bulb - The area
bordered/bounded by Martin Luther King Jr. Blvd.,
Hoover St., Vernon Ave., and Vermont Ave.
Asphalt Concrete Overlay - STP-L Force Account
Resurfacing Project XIII. Citywide resurfacing and
construction of ADA compliant access ramps
Road Rehabilitation, Force Account Resurfacing
Projec - Citywide, STP-L Force Account Resurfacing
Project XIV.
Install ped scale street lights, decorative
crosswalks, bus benches & trash receptacles on
street - East Colorado blvd between Hill ave and
Allen ave
Asphalt Concrete Overlay - Del Mar, Foothill, Lake,
Sierra Madre Villa.
Road Rehabilitation and other works - Del Amo Blvd:
Clark Aveenue to Downey Avenue
Road Rehabilitation - STUDEBAKER ROAD:
SOUTH ST TO ARTESIA BLVD
Road Rehabilitation - GARDENDALE ST:
GARFIELD AVE TO LAKEWOOD BLVD
Road Rehabilitation . - Whittier Blvd : Paramount
Blvd. to West City Limit
Widening the road to accommodate Northbound
Right Turn Lane. Construction and relocation of
curb/gutter - Madera Road From Simi Village Drive
To Los Angeles Avenue
Rideshare - Througout Mojave Desert within San
Bernardino County.
Rideshare - Within the South Coast Air Basin in San
Bernardino County
Upgrade Signals - Chino Ave at Ramona Ave.
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
10
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
RPSTPLE-6054(074) 08 RIV 06/04/14
STPL-5430(032) 08 RIV 06/19/14
STPL-5486(002) 08 RIV 04/10/14
STPLER-5380(013) 08 SBD 05/01/14
BPMPL-5947(048) 09 MNO 06/06/14
CML-5385(053) 09 KER 06/06/14
CML-5399(022) 09 KER 04/22/14
RPSTPLE-5184(022) 09 KER 04/03/14
BPMP-5929(223) 10 SJ 05/19/14
BPMP-5929(224) 10 SJ 06/13/14
BPMP-5929(226) 10 SJ 04/15/14
BRLO-5926(031) 10 AMA 04/24/14
BRLS-5939(078) 10 MER 04/09/14
CML-5059(203) 10 STA 05/30/14
CML-5085(028) 10 MER 05/15/14
CML-5085(035) 10 MER 04/08/14
TEA - Other - Downtown Riverside and Pedley
Transit Station Improvements
Road rehabilitation - East Palm Canyon Drive from
Golf Club Drive to 550 feet west of Canyon Plaza
Drive and from Melrose Street to the east city limits
east of Date Palm Drive
Pedestrian and bike path - Riverwalk Trail in Mojave
Narrows Regional Park
Repair bridge railing and mitigate scour - Topaz
Lane over the Walker River, Br. No. 47C-0005
Signal Synchronization - On China Lake Blvd. from
Ridgecrest Blvd. to College Heights Blvd.
Park and ride facility - Northwest quadrant of the
intersection of California City Boulevard and Harvard
Avenue
Sidewalk, ADA-compliant curb ramps, pedestrian
lighting, and landscaping - East Tehachapi
Boulevard from Snyder Avenue to Dennison Road
Bridge Preventive Maintenance Program - Scour
Mitigation - Austin Road over North Fork of South
Little Johns Creek, Bridge 29C0259.
Bridge Preventive Maintenance Program - Scour
Mitigation - Stanley Road over Little Johns Creek,
Bridge 29C0112
Bridge Preventive Maintenance Program - Scour
Mitigation - Van Allen Road over South Little Johns
Creek, Bridge 29C0115
Replace existing 2-lane bridge with a standard t2-
lane bridge - Bunker Hill Rd @ Rancheria Creek, Br.
26C0043. In Amador County 0.6 miles north of
Amador City/School Street
Replace existing 2-lane timber bridge with a
standard 2-lane reinforced concrete bridge -
Dickenson Ferry Road over Bear Creek, Bridge
39C0095.
Rideshare - Stanislaus County
Bike Path - From Yosemite Ave to McKee Road
along Black Rascal Creek Corridor
Traffic Signal Synchronization and Traffic Operation
Center in the City of Merced. - Along G street From
16th St to Yosemite Ave and Along 16th St from R St
to G St. of the existing Traffic Signals and Develop a
Traffic Operation Center.
Road Rehabilitation - Schleisman Avenue pavement
Rehabilitation: Schleisman Ave from to Sumner Ave.
to W/O Harrison Ave.
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
11
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
CML-5085(036) 10 MER 05/22/14
CML-5085(037) 10 MER 04/01/14
CML-5085(038) 10 MER 06/06/14
CML-5085(039) 10 MER 05/22/14
CML-5153(036) 10 STA 05/15/14
CML-5938(218) 10 STA 04/02/14
STPL-5059(170) 10 STA 04/02/14
STPL-5153(035) 10 STA 05/15/14
STPL-5929(268) 10 SJ 05/07/14
STPL-5929(269) 10 SJ 05/06/14
STPL-5938(216) 10 STA 05/16/14
STPL-5938(220) 10 STA 05/09/14
STPL-5938(221) 10 STA 05/09/14
HSIPL-5066(021) 11 SD 04/24/14
HSIPL-5211(030) 11 SD 04/16/14
HSIPL-5429(025) 11 SD 06/24/14
Asphalt Concrete Overlay - Phase G 1-Keyes
Rd(Hickman Rd to Hall Rd) 2- Keyes Rd& Sperry Rd
Intersection 3-Keyes Rd & Gratton Rd Intersection
50ft each direction 4- Fath Home Rd (Kaiser Rd to
West Main St)
Asphalt Concrete Overlay (Roadway Resurfacing
Phase I ) - 1-Emerald ave(Kansas ave to Woodland
ave)2-Rosemore ave(Kansas ave to SR132 3-Geer
rd( SR132 to Tuolumne river)4- Geer rd(Tuolumne
river to Hatch rd)5-Finch rd (Garner rd to Modest
Asphalt Concrete Overlay (roadway Resurfacing
Phase H ) - Rogers Rd. (SR 33 to Zacharias Rd).
Highland Avenue between Division Street and E 8th.
Street
Purchase and Install 3 Bike Shelters - 1) N Street
and 4th Street. 2) M Street across from Cornell
Court. 3) M Street and W 26th Street.
Purchase and Install 50 bike racks. - Main Street,
18th Street, and Canal Street
Sidewalk Infill on El Redondo Dr, Campass Pointe
Ave, Collins Dr, & R Street - Install sidewalk on El
Redondo Dr, Campass Pointe Ave, & R Street just
North of Yosemite Ave, and Collins Drive just North
of Olive Ave all within the city limits of Merced.
Sidewalk Infill on Carol Ave between HWY140 &
Motel Drive - Install sidewalk Infill on Carol Ave
between HWY140 & Motel Drive
Pedestrian Improvements - Yosemite Ave (H Street
to J Street), J Street (Yosemite to Sierra)
Upgrade signs - Various locations throughout the
City
Transit Related - Other(Stanislaus Co. Ridershare
Program) - Stanislaus County
Intersection Improvements on Oakdale Road from
Scenic Drive and extending approx. 1000 north -
Oakdale Road and Scenic Drive
Road Rehabilitation - South Yosemite Avenue - F
Street to Warnerville Road
Asphalt Concrete Overlay - Thornton Rd (Eight Mile
Rd. to De Vries Rd.)
Asphalt Concrete Overlay - Walnut Grove
Rd.(Sacramento Co. Line to Hope Bridge)
Upgrade Traffic Signals - 57 Intersections
throughout the City of El Cajon
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
12
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
SRTS-5381(037) 11 SD 04/14/14
STPL-5169(042) 11 IMP 05/12/14
STPL-5174(024) 11 IMP 04/16/14
HSIPL-5073(073) 12 ORA 06/11/14
HSIPL-5073(075) 12 ORA 06/09/14
HSIPL-5073(076) 12 ORA 06/11/14
HSIPL-5181(177) 12 ORA 06/30/14
HSIPL-5181(178) 12 ORA 06/25/14
HSIPL-5312(094) 12 ORA 06/09/14
Federa Aid
Project NumberDistrict Project Description Type
Date
Signed
CASB12RP-
5391(013)05 SLO Bike/Pedestrian Structure De Minimis 04/07/14
STPLER-5380(013) 08 SBD
Pedestrian and bike paths -
Riverwalk Trail in Mojave
Narrows Regional Park
De Minimis 05/01/14
Federal Aid Project
NumberDistrict County Project Description
Date
Signed
ER-18D0(002) 05 SLO 03/27/2014
HSIPL-5007(064) 05 SB 01/07/2014
RPSTPLE-5423(028) 05 SLO 03/04/2014
BPMPL-5953(678) 07 LA 03/27/2014
HSIPL-5108(151) 07 LA 03/28/2014
ER-24M0(001) 09 INY 03/19/2014
County
Local Assistance Projects - Section 4(f)
Approvals from Quarters 24 - 27 Local Assistance Projects1
Safe Route to Schools - Borden/Richland Rd/Rose
Ranch
Install Curb & Gutter, Sidewalk, and - SR115/5th
Street at Grape Ave Intersection (North Side)
REF Project: STPL 5174(017) - SR115/5th Str.
(South Side)
Left turn channelization and signal phasing -
Intersection of Chapman Avenue and Hewes Street
Road Rehabilitation -Street Improvements
(reconditioning of pavement, curb, gutter, and
sidewalk.) - Adams Avenue from La Brucherie
Avenue to Lotus Drain
Emergency Opening and Restoration, PR-CON, PR-
CE
New Signals
Pedestrian and Bike Path between San Gabriel Rd
and Pismo Ave
Bridge Preventative Maintenance Program
Left turn channelization and signal phasing -
Intersection of Tustin Street and MayfairAvenue
Left turn channelization and signal phasing -
Intersection of Chapman Avenue and Esplanade
Street
Left-turn signal phasing and interconnect -
Intersections of Adams Avenue at Bushard Street
amd Magnolia Street at Yorktown Avenue
Left-turn signal phasing - Intersections of Gothard
Street at Talbert Avenue, Gothard Street at Heil
Avenue, and Springdale Street at McFadden Avenue
Roadway and Traffic Improvements
Emergency Opening
Raised landscaped median islands - Red Hill
Avenue from Bristol Street to McCormick Avenue
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
13
23 USC 326 Categorical Exclusions
Quarterly Report #28
April 1, 2014 - June 30, 2014Report Date: July 22, 2014
Federal Aid Project
NumberDistrict County Project Description Type
Date
Signed
None
2Erroneously omitted from previous reporting periods (January 1, 2013 - June 30, 2013 and July 1, 2013 - December 31, 2013)
Approvals Quarters 24 - 27 Local Assistance Projects - Section 4(f)
1Approval from Quarter 27 not included in Caltrans' quarterly report dated April 21, 2014; however, the approval falls within the current 6 month
reporting period as outlined under the NEPA Assignment MOU (Jan. 1, 2014 - June 30, 2014)
23 USC 326 Quarterly Report #28: April 1, 2014 - June 30, 2014
7/21/2014
14
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
District-EA County Route Post MileDate
Signed
01-0A520_ HUM 299 R021.1/R0 03/14/14
01-0B370_ HUM 36 044.4/ 03/27/14
01-0B380_ HUM 96 004.1/ 03/26/14
01-0B460_ HUM 299 032.0/ 01/13/14
01-0B470_ MEN 1 035.7/ 03/26/14
01-0C350_ LAK 29 0.2/9.9 03/11/14
01-0C460_ HUM 299 / 01/06/14
01-36291_ MEN 101 9.2/ 01/31/14
01-45930_ MEN 101 064.7/ 01/13/14
02-3E730_ SIS 5 68.33 03/20/14
02-3E770_ TRI 299 036.9/053. 02/14/14
02-4E812_ VAR VAR / 01/15/14
03-0F370_ GLE 024.8/ 024.8/ 01/13/14
03-1F990_ BUT 32 006.0/ 02/04/14
03-2F290_ PLA 267 000.0/ 02/27/14
03-4F120_ SAC 5 12.9/13.1 01/24/14
03-4F130_ SAC VAR 0/0 02/21/14
03-4F340_ VAR 80 0/0 02/19/14
04-1A340_ SCL 9 3.6/11.4 03/21/14
04-1G830_ SM 280 0.3/27.1 03/24/14
04-1SS42_ ALA 680 20.2/20.2 01/10/14
04-1SS48_ SCL 87 4.8/4.8 01/17/14
04-2G830_ ALA 13009.1/009.
102/19/14
04-2L730_ MRN 580 2.5/3.0 01/15/14
04-3G110_ SON 116039.0/040.
002/10/14
04-3G650_ SOL 680 000.0/013. 03/10/14
04-3G750_ SM 92 2.5/2.5 01/27/14
04-3S900_ MRN 1 6.6 02/24/14
04-44500_ SCL 17 7.7/7.7 01/22/14
04-4S190_ SON 116 015.0/ 01/17/14
05-0S790_ SLO 101 R21.6 / 01/10/14
05-0T760_ MON 1 R77.6 03/25/14
05-1A390_ SB 101 84.1 / 90.9 01/24/14
05-1A730_ MON 101 49.8 / 55.3 01/08/14
05-1C120_ SB 101 0.0 / 12.7 02/28/14
05-1C130_ VAR 1 R0/0 02/19/14
06-0K810_ KER, KER 99, 178 26.7, R1.9 02/06/14
06-0Q860_ TUL 245 7.3/7.4 01/28/14
06-32551_ KIN 198 8.6/9.7 02/04/14
07-1W240_ LA 5 20.31/20.3 01/06/14
07-27540_ LA 1 Feb-00 01/09/14
07-2838U_ LA 2 Various 03/18/14
Pilarcitos Creek Wash Out - construct RSP and install
drainage
SON-116 Mays Canyon - Construct soldier pile wall
South San Luis Obispo Rehab
Pavement preservation (CAP M)
Roadside Safety Improvements
Oceano & Orcutt ADA (2 Locations)
Kern County Seismic Restoration
Woodlake Downtown Sidewalks Phase 4
19th Ave Landscape
Paint Elysian Viaduct Bridge
Project Description
Lupton Curve
Cobb Slide
Pipeline Slide
Willow Creek Wall
Satori Gulch Slip
LAK 29 CAPM
HUM 299 CAPM
Men 101 CAPM
Laytonville Pavement
Hilt Deck Replacement
West Weaverville CAPM
Phase 2 Workers Safety
3 Bridges Vertical Clearance Upgrades on Glenn 5.
BUT 32 ADA Compliance
PLA 267 Rehab. Pavement & Widen Shoulder
Beach Lake Bridge HFST
Sac Various Locations High Friction Surface
Treatment
Replace AC ditch with PCC, Kingvale & Soda Springs
Upgrade metal beam guardrails
Bridge Rail Replacement
DAF - Rock Slope Protection
Install midwest guardrail on MRN 580
Muir Beach 0 Construct Tie Back Wall
SCL-17 WIM
Aquajito Ramp Overlay
Asphalt Overlay
Pavement repair -- install permeable blanket, etc
Repair slope slide with soldier beam, tie back retaining
wall
Lakeville Hwy RSP
CAPM 680 - Rehabilitate pavement
Test Boring for GeoTech Study
Transp. Enhancement for Rtes 2, 134, 101 & 210
State Highway System Projects
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
1
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
07-28730_ LA 210 39.8/41 03/18/14
07-28820_ LA 60 0.2/3.2 02/19/14
07-29450_ LA 5 R45.1/R55. 03/21/14
07-2W600_ LA 5 Various 02/27/14
07-30130_ LA 5 28.9/29.4 02/06/14
07-30450_ LA 57 R0.0/R4.45 03/17/14
07-3P790_ LA 1 41.7 01/17/14
07-3P830_ LA 213 3.2 01/17/14
07-3P840_ LA 405 23.3/24.66 02/03/14
07-3P850_ LA 105 7.7/8.9 01/13/14
07-3P870_ LA 105 R6.0/R6.5 01/31/14
07-3X710_ LA 60 007.7/008. 01/06/14
07-4X150_ LA 27 1.5 03/25/14
08-33630_ SBD 38 26.3/26.8 01/24/14
09-34090_ MNO 395 72.5 / 78.9 03/13/14
09-35990_ INY 127 35.8/41.8 02/04/14
10-0U520_ MER 59 12.8 / 13.5 01/02/14
10-0V620_ CAL 26 8.4 01/06/14
10-0V660_ STA 5 0.0 / 28.1 02/10/14
10-0W110_ SJ 4 R16.2 01/07/14
10-0X300_ MER 140 40.7 01/10/14
10-0Y690_ SJ 5 39/39.4 01/06/14
11-26041_ SD 8 R037.8/000 03/05/14
11-41540_ SD 816.0/R
030.501/29/14
11-41710_ IMP 86 27.571 02/05/14
11-41720_ IMP 86 25.571 02/05/14
12-0H890_ ORA 55 9.6/12 01/23/14
12-0N000_ ORA 405 15.4 01/23/14
12-0N140_ ORA 57 20.73/20.7 01/21/14
12-0N330_ ORA 5 12.8-21.3 03/19/14
12-0N420_ ORA 55 11.7 03/06/14
12-0N540_ ORA 405 8.44/ 02/20/14
12-0N600_ ORA 142 0.8/2.6 03/06/14
12-0N690_ ORA 22 4.6/7.36 03/13/14
District-EA County Route Post Mile Project Description TypeDate
Signed
NONE
District-EA County Route Post MileDate
Signed
05-0Q590_ SCR 9 1.7/23.9 12/04/13
05-1A640_ SB, SB 101, 135 82.1 / 90.9, 10/31/13
Enhance Striping and Upgrade Bridge End
Treatments
Hwy 9 Source Control
Approvals from Quarters 23 - 26 State Highway System Projects1
Santa Maria planting and rehab
Project Description
Drainage Improvements
Landscape Rehabilitation
I-5, Native Planting and Corridor Enhancements
Repair and Line Culverts
Pavement Rehabilitation
LA-60 Storm Water Source Control
Pavement Rehabilitation
Repair drainage benches on hillside
At Westmont/Delasonde Dr, redo signals & striping
Upgrade Irrigation & Hwy Planting
Replace diseased and dying shrubs
Highway Planting Restoration
Realign & Upgrade Ramps @ Paramont Blvd
Repair wire-mesh covered hillside & install anchored
cable net
SBd 38 Hathaway Bridge Deck Replacement
Overlay and shoulder backing
Vista del Lago Drive signalization
Stanislaus County CAPM
Bridgeport culverts
Mission Ave Left Turn Lane
SR4 - I5 Connector
Tri-Cities Flashing Beacons Safety Project
SR 57 On/Off Ramps at Lambert
Capital Preventive Maintenance
Overlay and restriping
Intersection Signalization
Upgrade curb ramps to ADA
Repair Existing Rock Blanket Upgrade Existing
Irrigation
Minor B project
San Joaquin HFST
Remove & repair damaged rdwy, slope embankment
Rte 142 CAPM PR
Install Irrigation Controllers
State Highway System Projects - Section 4(f)
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
2
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
05-1C800_ SLO 101 37.7 10/14/13
05-1F480_ SB 101 47.38/47.8 10/17/13
05-1F610_ SB 101 14.19 12/20/13
11-28230_ SD 5 31.5/32.0 10/16/13
District-EA County Route Post Mile Project Description TypeDate
Signed
NONE
Federal Aid Project
NumberDistrict
Date
Signed
RPSTPLE-5021(019) 01 HUM 03/18/14
BRLO-5914(072) 01 LAK 03/05/14
BHLO-5914(069) 01 LAK 03/06/14
BRLO-5904(113) 01 HUM 03/07/14
ER-20A0(021) 01 HUM 01/15/14
ER-20A0(001) 01 HUM 01/16/14
ER-20A0(005) 01 HUM 01/16/14
ER-20A0(002) 01 HUM 01/16/14
RPSTPLE-5161(013) 02 TEH 03/25/14
BRLS-5908(070) 02 TEH 03/12/14
RSTPL-5902(073) 02 SIS 01/21/14
BRLS-5020(016) 02 SIS 02/11/14
HSIPL-5919(110) 03 PLA 02/21/14
HSIPL-5924(196) 03 SAC 02/27/14
Approvals from Quarters 23 - 26 State Highway System Projects - Section 4(f)
County
Bridge Replacement-Mathews Road Bridge over
Manning Creek (Br. No. 14C-0082)
Pedestrian and Bike Path-Rails with Trails from
Samoa Blvd to Foster Ave
Project Description
Reconfigure Route 101 Southbound Off-Ramp to
Route 58
Gaviota HFST
Castillo Street Pavers
Bridge Rehabilitation-Mockingbird Lane Bridge over
Robinson Creek (Br. No. 14C-0086)
Bridge Replacement-Big Rock Gulch Bridge on Red
Cap Road 04C0117
Restoration-Bell Springs Rd PM 4.85, in Humboldt
County. DAF # JLB-HUM-019-0
Restoration-Alderpoint Rd PM 4.9, in Humboldt
County. DAF# JLB-HUM-001-0
Restoration-Alderpoint Rd PM 6.6-6.7, in Humboldt
County. DAF # JLB-HUM-005-0
Restoration-Alderpoint Rd PM 5.5, in Humboldt
County. DAF # JLB-HUM-002-0
TEA - Other-In the City of Corning in the downtown
area. Downtown area preservation and
enhancements.
Bridge Replacement-Near Corning, HWY 99W @
Thomes Creek Br. No. (#8C-0110).
Road Rehabilitation-In Siskiyou County on Gazelle
Callahan Road from MP 16.7 to MP 25.0.
Bridge resurfacing-Fairlane Road Bridge #02C0149
0.3 miles south of Sharps Road
Pavement Markings-Various locations throughout the
county
Install sidewalks, curb ramps, curb and gutter-Fair
Oaks Blvd. between Day Dr. and Arden Way
Los Penasquitos Slope Stabilization Project
Local Assistance Projects
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
3
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
CML-6236(012) 03 SAC 01/06/14
STPL-6085(055) 03 SAC 02/21/14
HSIP-5924(198) 03 SAC 02/21/14
CML-6085(056) 03 SAC 03/21/14
CML-5916(091) 03 YUB 03/17/14
RSTP-5919(120) 03 PLA 02/16/14
HSIPL-5002(165) 03 SAC 02/12/14
BPMP-5925(105) 03 ED 01/14/14
BRLO-5925(093) 03 ED 02/19/14
STPL-5042(056) 04 NAP 02/07/14
CML-5019(033) 04 SCL 02/07/14
CML-5005(125) 04 SCL 03/07/14
CML-6429(013) 04 NAP 01/10/14
STPL-6160(025) 04 MULT 01/14/14
SRTS-5038(024) 04 CC 01/02/14
CML-5124(030) 04 SCL 02/04/14
STP-6249(034) 04 SOL 02/24/14
Spare the Air Program/Phase II-Sacramento Federal
non-attainment area that includes all of Sacto and
Yolo Counties
Planning,Programming and Monitoring-Programming
and Monitoring (RSTP) Phase 2, 13/14 fy
Upgrade Signals-Ten (10) signalized intersections
throughout the city
Planning,Programming and Monitoring-Transportation
Demand Management (TDM) Phase 2 (13/14 fy)
Pedestrian and Bike Path-Olivehurst, on Powerline
Rd, from 15th Ave to 9th Ave
Asphalt Concrete Overlay-Placer County HMA
Overlay 2014
Upgrade Signals & Right turn lane-Mack Rd./Valley Hi
Dr. (La Mancha Way)
Replace elastomeric bearing pads; remove and
replace abutment backfill-Ice House Rd @ Jones Fork
Silver Creek 12.8 miles north of US-50
Replace existing functionally obsolete 2-lane bridge
with a new 2-lane bridge-Alder Dr over EID Canal at
Pony Express Trail
Priority Development Area (PDA) Infrastructure
Financing Strategy including Bike/Ped Facilities-City of
Napa
Pedestrian Walkway-Hughes Elementary, Don
Callejon School, Montaque Elementary, Bracher
Elementary, Bowers Elementary, Briarwood
Elementary, Cabrillo Middle, Scott Lane Elementary,
Sutter Elementary
Construct Pedestrian Safety and Transit Access
Including Installing 3 New Signalized Crosswalks-On
Jackson Ave between McKee Rd and Alum Rock Ave
Non-infrastructure project to continue the service
provided by SRTS project 6446(001)-Napa County
Freeway Service Patrol, Call Box and Safe Capital
Projects-Bay Area Freeways, Bridges
Bike Path-various location Cavallo Garrow road from
Wilbur Ave to Davidson Dr.
Non-infrastructure educational program-Education
Program in Mountain View public schools
NON-INFRASTRUCTURE: Priority Development
Areas (PDAs) and Priority Conservation Areas (PCAs)-
Various local agencies in Solano County
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
4
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
CML-6249(035) 04 SOL 02/24/14
CML-6447(006) 04 SF 02/21/14
CML-5005(128) 04 SCL 01/10/14
CMLNI-5928(121) 04 CC 03/13/14
RSTPLNI-6072(017) 04 CC 02/10/14
HSIPL-5239(023) 04 CC 01/21/14
SRTSL-5043(034) 04 MRN 01/31/14
HSIPL-5005(121) 04 SCL 03/06/14
HSIPL-5005(123) 04 SCL 03/07/14
HSIP5-5213(048) 04 SCL 03/26/14
ER-22X0(001) 04 SM 02/19/14
CML-5350(019) 04 SM 03/13/14
STPL-5339(003) 04 SCL 02/06/14
RSTP-5239(024) 04 CC 01/21/14
STPL-5404(025) 04 CC 01/02/14
STPL-5050(041) 04 ALA 03/03/14
STPL-5032(028) 04 SOL 02/24/14
CML-5437(028) 04 CC 03/03/14
Solano Transit Ambassador Program - NON-
INFRASTRUCTURE-various locations throughout
Solano County
In City and County of San Francisco
SRTS, Encourage and promote mode shift to walking
and Biking.-San Jose Schools
Safe Route to Schools Non-Infrastructure-Conduct
Educational and outreach programs for 17 elementary
and middle schools in West CCCo
Planning,Programming and Monitoring-Contra Costa
County
AC overlay, ADA ramp replacement to complie with
FHWA-Arlington blvd and Brewster Dr. in city of El
Cerrito
Road Reconstruction-on Lindardo Street in San
Rafael
Install tubular markets, pavement treatment, and
payment markings for bicycle lanes-Park Ave between
Hedding St and South Market St, San Jose
Install tubular marker, Pavement treatment, and
pavement markings for bicycle lances-North First
Street between SR 237 and Brokaw Rd
Upgrade Traffic Signals-Saratoga Road/Fremont Ave
Restoration : Stich Pier/ lag retaining wall, rip rap
stabalize bank-Alpine Rd. 5500 Block to 3940' S. from
Willowbrook Dr. DAF#MEM-PTLV-001-0
Pavement Rehab and pedestrian sidewalk
improvements-Palmetto Ave fr. Bella Vista Ave to
Clarendon Rd.
Road Rehabilitation-Andrews St (Rose Ave to city
limit), Rose St (SR9 to Andrews St) and Daves Ave
(Poppy Ln to Carril Ct)
AC Overlay, striping, loop detectors, curb ramps, tree
planting - Arlington, Central, Colusa, Fairmont and
Manila
Road Rehabilitation-Mt. Diablo Blvd from Mtn View Dr.
to El Nido Ranch Rd.
Pavement Rehabilitation-Industrial Blvd. from Clawiter
Road to South of Depot Road
Road Rehabilitation-Walters Rd. between Petersen
Rd. and Bella Vista, Pintail Dr. between Walters Rd.
and Blackspur Dr.
Pedestrian and Bike Path-Windemere Parkway at
Holborn Way and Kearny Way; Harcourt Way at
Craiglee Dr; Talavera Dr at Cardona Circle; Alcosta
Blvd at Firestation #34 south driveway
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
5
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
STPL-5019(032) 04 SCL 02/10/14
STPL-5318(028) 04 SCL 02/04/14
STPL-5437(027) 04 CC 01/21/14
STPL-5014(041) 04 ALA 01/21/14
STPL-5034(025) 04 SCL 03/10/14
HSIPL-5928(110) 04 CC 01/31/14
CML-5003(028) 04 SOL 03/10/14
STPL-5390(005) 04 SM 02/19/14
STPL-5029(033) 04 SM 02/19/14
STPL-5273(023) 04 SM 02/19/14
STPL-5003(027) 04 SOL 03/10/14
STPL-5303(015) 04 CC 02/26/14
HRRRL-5944(113) 05 MON 01/15/14
HRRRL-5944(114) 05 MON 01/15/14
HSIPL-5936(098) 05 SCR 03/24/14
BRLO-5936(089) 05 SCR 03/25/14
ER-20E0(012) 05 SCR 03/21/14
CML-5208(127) 06 FRE 02/12/14
Rehabilitate Roadways-Benton St (Kiely Blvd to
Blackfield Dr), Los Padres Blvd (El Camino Real to
Benton St), Lincoln St (El Camino Real to Homestead
Rd)
Rubberized Asphalt Overlay-Stevens Creek Blvd
(SR85 to De Anza Blvd)
Rehabilitate Roadway-San Ramon Valley Blvd.
between Bollinger Canyon Rd and Montevideo Dr
Rehab pavement and make minor imprvmnts to
strmwtr, bike/ped, and transit facilities-Pacific Avenue
from Main Street to Fourth Street and Otis Drive for
Park St to BroadwayStreet Resurfacing-Eigleberry st. between 1st to 10th
st.
Roadway Widening-Camino Tassajara Road- approx
1 mile S of Highland Rd. to .2 miles N of Windemere
Pkwy.
Pedestrian Walkway, Signal Modifications and Striping-
Robert Semple and Matthew Turner Elementary and
Benicia Middle School
Asphalt Concrete Overlay-Alpine Rd . , Corte Madera
Rd., Portola Rd., Westridge Dr.
Road Rehabilitation-Whipple Ave:E. Bayshore to
Veterans, El Camino Real to Upland, Veterans: 101
Off Ramp to Whipple
Road Rehabilitation-Hamilton, Olive, Woodland,
University Dr
Asphalt Concrete Overlay-East Second Street from
Military Rd to Old Lake Herman Rd
Road Rehabilitation-Emeric, San Pablo, & Market
Avenues
Road Related - Other-River Road Pavement
Delineation
Road Related - Other-Castroville Boulevard Pavement
Delineation
Guardrail & slope stabilization
-In the Co of SCR on Felton Empire Rd 0.8 mi E of
Empire Grade
Bridge Replacement 36C-0095-Old Country Rd Br at
Earl Crk-0.25 mile NW of SR9
Emergency Opening & Restoration- On Glenwood Dr
(PM 0.21), in the Co of Santa Cruz. DAF# DDM-
SCRCO-006-0
Upgrade Signals-Clovis Ave and Gettysburg Ave, City
of Clovis
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
6
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
CML-5157(093) 06 MAD 02/19/14
CML-5258(031) 06 MAD 01/24/14
CML-5157(097) 06 MAD 03/14/14
STPLNI-6087(044) 06 KER 01/08/14
RPSTPLE-5109(205) 06 KER 02/03/14
RPSTPLE-5950(377) 06 KER 01/13/14
CML-5950(381) 06 KER 02/07/14
CMLNI-6087(045) 06 KER 02/13/14
CML-5109(206) 06 KER 03/26/14
CML-5170(052) 06 FRE 01/15/14
CML-5245(015) 06 FRE 03/14/14
CML-5109(208) 06 KER 02/11/14
CML-5060(223) 06 FRE 03/27/14
CML-5208(126) 06 FRE 02/20/14
CML-5950(380) 06 KER 01/08/14
STPL-5060(259) 06 FRE 03/05/14
CML-5950(371) 06 KER 01/23/14
CML-5060(239) 06 FRE 01/24/14
CML-5109(207) 06 KER 03/06/14
CML-5060(200) 06 FRE 02/07/14
CML-5060(201) 06 FRE 01/24/14
ER-18D2(007) 07 LA 03/05/14
Purchase of a PM-10 Certified Streetsweeper
Pedestrian Facilities-Sidewalks, Curb Ramps, Etc.-
Monterey Ave - 3rd to 13th Street
10 foot wide AC Bike Path-Laurel Street from Sunset
Avenue to Fresno River Trail
13/14 Regional Traffic Count Program-Kern County
Landscape-Mount Vernon Median Improvements from
Columbus Street to University Avenue
Pedestrian and Bike Path-Bernard street from Mt.
Vernon to Haley
New Signals-Merle Haggard Dr. and Airport Drive
13/14 Rideshare Program-Various locations
throughout Kern County
Interconnect Signals-Calloway from Olive to Norris,
and Jewetta from Hageman to Olive
Pedestrian Walkway(Construct sidewalk)-West Side
of 18th Ave from Lewis Street to Washingtion Street
and East Side of 18th Ave from Mariposa Street to
Kern Street
Pedestrian and Bike Path-Sports Park and 8th Street
New Signals-Jewetta Avenue at Reina Road
Install New Traffic Signals-Shields and Sunnyside
Avenues Intersection
New Signals-Ashlan Ave and Armstrong Ave, City of
CLovis
Road Rehabilitation-in Tehachapi: Roost Ave from
Bear Valley Rd to End limit
Pedestrian Trail resurfacing & Bicycle Bridge repairs-
Eaton Trail from 1/4 mile north of Audubon Drive to
Copper Avenue
Surfacing Unpaved Shoulders-Redrock-Randsburg
Road for SR 14 to Garlock Road
Install ITS Electronic Communications-Tulare St.
btwn. 'C' Street and Clovis Avenue
Signal Synchronization-H from California to White,
White from H to Monitor, White from H to Stine, and
Stine from White to Ming
Install fiber in existing conduit, cameras, upgrade
signal controllers, and impacted ramps-Friant Rd.
from Fresno St. to Nees Ave., along Nees Ave. to
Palm Ave., along Palm Ave. to Palmdon Ave.
Install wireless ITS, Cameras, cabinets, vaults, &
upgrade signal controllers-Shields Ave. from West
Ave. to Chestnut Ave.
Emergency Opening-East Fork Rd @ MM 0.29
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
7
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
HSIPL-5378(037) 07 LA 03/20/14
STPL-5348(028) 07 LA 02/13/14
RPSTPLE-5006(762) 07 LA 03/07/14
ER-20W0(009) 07 LA 01/16/14
HSIPL-5413(015) 07 LA 01/14/14
CML-5006(608) 07 LA 02/04/14
CML-5006(609) 07 LA 03/17/14
HPLU-5064(058) 07 LA 01/10/14
CML-5953(622) 07 LA 02/14/14
STPL-5118(018) 07 LA 01/23/14
SRTSL-5131(019) 07 LA 03/03/14
STPL-5070(031) 07 LA 03/13/14
STPL-5108(163) 07 LA 01/23/14
HSIPL-5212(010) 07 LA 01/22/14
HSIPL-5392(052) 07 VEN 02/06/14
Install Protected left-turn phasing and non-motorized
detection-Ave S / 30th St. East
Pavement rehabilitation of segment of Flower Street
from East City Limit to Woodruff Avenue.
Watts streescape enhancements-Along 103rd St
corridor from Central Avenue to Grape St
Tree and debris removal by agency forces and
contractor to make the road accessible to the public-
Streets throughout San Marino, DAF # MKN-SMRO-
001-0
Install Median Barriers, Delineators, Replace Signs-
Palos Verdes Dr. East from Bronco Drive to Headland
Drive
Pedestrian Walkway-North Broadway between
Bernard Street and Solano Ave
Pedestrian Walkway-Exposition Blvd between
Crenshaw Blvd to Jefferson Blvd
Sound Wall-07/LA/210/22.5 - 24.6/Pasadena
Route 210 Fwy Between Arroyo Bl & Orange Groove
Bl.
Bike Trail-Emerald Lake bicycle trail from Duarte
Road to the San Gabriel River bicycle trail
Resurfacing of Streets: Hollenbeck, Cypress, et. al.-
Hollenbeck Avenue- Arrow Highway to San Dimas
Wash and Cypress - San Bernardino Rd to Northerly
Construct sidewalks, bulb-outs, curb ramps;install
crosswalks, ped countdown heads &signs-Various
locations throughout the city
Street Rehabilitation - Slurry Seal and Overlay Various
Locations Citywide-Street Rehabilitation - Slurry Seal
and Overlay Various Locations Citywide
Foothill Blvd.
Road Rehabilitation-Bixby Rd: Atlantic Ave / Orange
Ave
Install: Cross-walks, Ped. Count-down Heads,
Flashing Beacons and Signs; Construct Bulb-Outs-22
intersections
Modify median to extend northbound left turn pocket,
modify signage & pavement markings.-Westlake Blvd.
between Avenida de los Arboles and Lang Ranch
parkway.
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
8
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
BHLO-5450(066) 07 LA 01/08/14
BHLS-5405(064) 07 VEN 01/15/14
BPMPL-5953(674) 07 LA 01/22/14
BPMPL-5953(673) 07 LA 01/21/14
SRTS-5449(027) 08 SBD 01/15/14
SRTS-5449(026) 08 SBD 01/15/14
STPL-5956(232) 08 RIV 02/05/14
STPL-5384(018) 08 RIV 02/10/14
SRTSL-5439(028) 09 MNO 03/28/14
HSIPL-5385(051) 09 KER 02/04/14
HSIPL-5385(049) 09 KER 02/07/14
HSIPL-5385(052) 09 KER 02/04/14
CML-5385(046) 09 KER 01/22/14
CML-5184(021) 09 KER 02/18/14
STPL-5385(047) 09 KER 02/07/14
CML-5938(217) 10 STA 03/17/14
CML-6308(014) 10 MER 02/11/14
CML-6089(062) 10 STA 03/25/14
STPL-6089(063) 10 STA 03/25/14
CML-5279(006) 10 MER 03/17/14
Bridge Rehabilitation- On Lost Canyon Rd from 130 Ft
to 240 Ft west of the Intersection of Lost Canyon Rd
and Sand Canyon Dr. State Bridge No. 53c1024
Bridge Widening-Cochran Street over Las Llajas
Creek, .4 Mile E/O Tapo Street. Brd #52c-0115
NULL-Various Locations within Los Angeles County -
Group 3
Bridge Related - Other-Various Locations within Los
Angeles County- Group 2
Construct sidewalk,curb,gutter, ramps, in pavement
crosswalk lights, flashing beacons-9th St. between
Cunningham St. and Palm Ave.; Church
Ave./Norwood St.
Construct sidewalk,curb,gutter, ramps, in pavement
crosswalk lights, flashing beacons-McKinley St.
between 9th St. and Base Line; Base Line/Valaria Dr.
Regional Rideshare Program-StanCOG area
Road Rehabilitation-62nd Street Pavement Rehab
from Jackson Street to Harrison Street
NULL
Pedestrian and bike path-Along the north side of
Meridian Boulevard from the end of the multi-use path
near Joaquin Road to Sierra Park Road
Upgrade signals-Seven intersections throughout the
City of Ridgecrest
New signals and signal interconnect, ADA-compliant
ramps, curb, and gutter-Intersection of China Lake
Boulevard and Bowman Road
Upgrade traffic signs and pavement markings-Twelve
intersections throughout the City of Ridgecrest
Pave dirt road-South Sunland Drive from East
Bowman Road to East Upjohn Avenue
Cross gutter removal and subsurface drainage
improvements-Intersection of Curry Street and Valley
Boulevard
Road rehabilitation-South China Lake Boulevard from
Bowman Road to Upjohn Avenue
Equipment Purchase-Stanislaus County
Public Outreach and Marketing
Planning,Programming and Monitoring-StanCOG area
Purchase One Tier 4 loader-City of Dos Palos
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
9
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
CASB12-6190(026) 10 STA 02/19/14
CML-5165(073) 10 STA 02/24/14
HSIPL-5008(128) 10 SJ 02/10/14
CML-5059(190) 10 STA 03/17/14
CML-5059(185) 10 STA 02/11/14
CML-5254(017) 10 MER 01/23/14
HSIPL-5938(197) 10 STA 01/23/14
STPL-5255(049) 10 STA 03/12/14
STPL-5192(038) 10 SJ 02/07/14
STPL-5165(076) 10 STA 02/05/14
STPL-5255(050) 10 STA 03/18/14
STPL-5165(074) 10 STA 01/23/14
CML-5059(197) 10 STA 03/26/14
BRLOZ-5938(156) 10 STA 01/23/14
FSP14-6066(118) 11 SD 02/18/14
Road Rehabilitation-Geer Rd. - Monte Vista Ave. to
Taylor Rd.
Road Rehabilitation ( Widening existing pavement and
overlay )-Morrill Rd. (Jackson to Roselle Avenue)
Freeway Service Patrol-San Diego Association of
Governments
Install New Traffic Signals-At the intersections of: 1)
Prescott Rd & Mt. Vernon Dr, 2) Floyd Ave & Milbrook
Ave, 3)Roselle Ave & Belharbour
Construct/ Install pedestrian Improvements around
Elem. School in City of Atwater-1. "Olive Ave" east of
city limit to Herman St 2. "Marguerite St" From South
of Olive Ave to North of Mitchell Ave.3 "Willow St"
North of Olive Ave to north of Mitchell Ave
Realign roadway, widen shoulders, re-surface and re-
stripe area to conform to new pavement.-About 1250
feet north and south of the northern intersection of
Central Ave. & E. Taylor Rd.
Asphalt Concrete Overlay-Central Ave ( California to
Kentucky Ave)
Rubberized Asphalt Concrete overlay. Pavement
repair, signing & striping, traffic signal loop rep-Tracy
Blvd. from Clove Road to Larch Road and
MacArthur Drive from Grant Line Road to North of I-
205.
Miscellaneous - Other-Silvertip Campground,
Adjacent Highway 4 in Bear Valley, Stanislaus
National Forest
Install Traffic signal, striping, accessibility ramps-
Intersection of Christoffersen Pkwy and Fosberg Rd.
Miscellaneous - Other (Modify Traffic Signal).-On
Harding Way at El Dorado and Center Street Dorado
St
Upgrade Signals - install detector loops, pedestrian
push buttons, and indications for ADA stndards.-
Intersection of: 9th & B St., 7th & G St., 7th & H St.
and 7th & I St.
Road Rehabilitation-Hawkeye Ave. from Del's Lane to
Olive Ave.
Install Bus Turnout-Dale Road (south of Veneman
Ave. and North of Standiford Ave.)
Deck restrainers; Enlarge/modify footings; Retrofit
columns.-Pete Miller Road over Delta-Mendota Canal,
Bridge 38C0202
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
10
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
CML-5243(013) 11 IMP 03/04/14
HSIPL-5381(035) 11 SD 02/13/14
HSIPL-5957(116) 11 SD 02/24/14
CML-5181(179) 12 ORA 03/12/14
HSIPL-5955(086) 12 ORA 03/04/14
CML-5229(015) 12 ORA 02/27/14
Federa Aid
Project NumberDistrict Project Description Type
Date
Signed
RPSTPLE-5021(019) 01 HUM Pedestrian and Bike Path De minimis 03/18/14
ER-22X0(001) 04 SM
Restoration : Stich Pier/ lag
retaining wall, rip rap
stabalize bank
De minimis 02/19/14
BRLOZ-5938(156) 10 STA
Deck restrainers;
Enlarge/modify footings;
Retrofit columns.
De minimis 01/23/14
Federal Aid Project
NumberDistrict County Project Description
Date
Signed
BRLO-5922(074) 03 YOL 09/26/13
VPPLNI-6072(016) 04 CC 12/10/13
BPMPL-5080(027) 05 SB 11/15/13
BPMP-5942(219) 06 FRE 10/14/13
BRLO-5946(110) 06 TUL 11/13/13
CML-5109(187) 06 KER 01/30/13
RSTPL-5950(372) 06 KER 12/23/13
STPCML-5227(045) 06 KER 05/07/13
STPCML-5227(046) 06 KER 05/22/13
STPL-5146(012) 06 FRE 05/16/13
CML-5160(024) 10 MER 01/25/13
STPL-6089(060) 10 STA 04/11/13
Federal Aid Project
NumberDistrict County Project Description Type
Date
Signed
Traffic signal & lighting system
Road Reconstruction
purchase 2- new tier 4-powered title 23 Backhoes to
replace older -Diesel Backhoes
Planning and Monitoring Activities
Roadway resurfacing and shoulder paving
Shoulder paving, road rehabilitation
Approvals Quarters 23 - 26 Local Assistance Projects - Section 4(f)1
Approvals from Quarters 23 - 26 Local Assistance Projects1
County
Westminster Ave. Bicycle Lane from Seal Beach Blvd.
to Bolsa Chica Rd.
Replace existing functionally obsolete 2 lane bridge
with a new 2 lane bridge
I-80 Real Time Rideshare
Bridge Related - Other
Local Assistance Projects - Section 4(f)
Road Rehabilitation & Reconstruction with pedestrian
improvements.-North International Avenue from Delta
St. to Main St.
Signs-Various locations in the City of San Marcos
Install center-line rumble strips-Mission Rd, Olive Hill
Rd, El Nopal, Reche Rd, and Old Hwy 395
2 - bicycle signs, 4 - sharrows, & 28 - bike racks-Lake
St. from Pecan Ave. to Orange Ave. & Downtown
Main St. Area
Gilbert St. from Katella Ave. to Ball Rd.
Bridge Preventative Maintenance for various locations
Replace Bridge
Asphalt Concrete Overlay
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
11
23 USC 326 Categorical Exclusions
Quarterly Report #27
January 1, 2014 - March 31, 2014Report date: April 21, 2014
RPSTPLE-5924(191) 03 SAC
New signal, signal
modifications, CGSW,
drainage, bike lanes
De minimis 04/24/2013
1Erroneously omitted from previous reporting periods (January 1 - June 30, 2013 and July 1, 2013 - December 31, 2013)
23 USC 326 Quarterly Report #27: January 1, 2014 - March 31, 2014
4/21/2014
12