![Page 1: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/1.jpg)
Date: O3lttl?OtsWR-EA- 6\22lr5-t6
subject : Providing assistangg for carrying out Energy Audit of 2x25O MW
---'unit" at MSPGCL, Paras Akola
Dear Sir,
we are sending you one set of tender documents for the above subject work and
request you for submitting your most competitive quotation'
The schedule of rate, Scope of work, Terms & conditions and plant load details are
attached as annexure -A'
The offer should reach our office on or before the due date and time of submission
givenbelow'PCRAwi||notberesponsib|eforanyposta|delay'
Providing assilstance for carrying outEnergy nlait of 2x25o MW units atMSPGCL, Paras Akola
Name of Work
WR-EA-60 2Zl L5-t6 dated 03/ Lt I 20L5Tender no. & Date
Eatimated cGt for energy Audit is Rs'
7,7O,OOO /- Plus t+oZo servicTotal Estimated value of the work
03.11. 2015 at 15:OO HrsPuebate A-ime for submission ofTender
19.11. 2O15 at 15:3O hrsDate & Tlme of oPening of Tender
Director,PCRA _WR
C - 5, Keshava Bldg., Ground Floor,
Bandra - Kurla ComPlex,Bandra (E) - Mumbai - 400 051
Sealed Tender Should be droPPed /sent at tender box kePt in theoffice of :
Page L of 1.1
![Page 2: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/2.jpg)
The Bidder should sign on each page of tender document along with company sealas a token of acceptance to our terms and conditions of tender, Deviations to ourterms and conditions are not acceptable.
Incomplete tender of any nature, or not accompanied with the required documents,or conditional tender is liable for rejection without assigning any reason thereof.Each Annexure / Documents attached with the tender notice will form the part ofthe tender.
The Tender document should be submitted only in the prescribed tender scheduleform / envelope supplied by the PCRA, boldly superscribed on the outer cover theTender Number, Closing date and time and sealed and sent by post so as to reachthe concerned authority as laid down in the tender document,
Tender No, & Date WR- EA-6022/ I5-L6 dated 03/ LL / 2OL5
Due Date & Time for Submissionof sealed Tender 19.11.2015 at 15:OO Hrs
Date & Time of opening ofTender 19.11.2015 at 15:3O hrs
All the work will be allotted to one party. Work will not be split in case more thanone vendor are L1 jointly. In such cases discount in sealed cover will be taken fromall the L1 vendors to decide the final lowest vendor.
Yours Faithfully,
For Petroleum Conservation Research Association
ADDL DIRECTOR & CRC, WR
Encl:
i)
ii)
Price bid :
Terms & Conditions :
Scope of Work :
Load / Equip details :
Annexure A-I
Annexure A-II
Annexure A-III
Annexure A-IV
i ii)
iv)
Pase 2 of 11
![Page 3: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/3.jpg)
Annexure A-I
PETROLEUM CONSERVATION RESEARCH ASSOCIATION, WESTERNREGION, MUMBAI
SUBJECT- Providing assistance for Carrying out Energy Audit of Unit 1 and2 (2x25O MW) Paras Thermal Power Plant Akola.
Tender No. & Date : WR-EA-6022/L5 dated 03/II/20L5DUE DATE &TIME: L9/LL/20L5 at 15:00 Hrs
TENDER OPENING DATE & TIME : I9/1L/20L5 at 15:30 Hrs
PRICE BID
sl.No
ITEMDESCRIPTION
QTY
UNIT RATE(Rs)
AMOUNT (Rs)
(a) Assistance forcarrying outEnergy
Audit unitl &2
1 LumpSum
77 OOOO / 77OOOO /-
(b)Sub Total 77OOOO /-
(c)Service Tax @ 7,4o/o LOTAOOI -
(d)TOTAL ESTIMATED PRICE (in
Fiqures)a77AOO/ -
The percentage (%) rate either (+) above or (-) below quoted by contractor will beapplicable equally to all items of schedule of rates - basic price, service tax andTotal Amount, The rate quoted by tenderer should be inclusive of all other taxes,levies and duties, travel, etc.
Quote Plus (+) / o/o Abovethe estimate
Minus (-) / o/o Belowthe estimate
In Figures
In Words
We accept all the terms and conditions of PCRA mentioned in this tender documentand Scope of work,
SIGNATURE & SEAL OF TENDERER
Page 3 of11
![Page 4: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/4.jpg)
Annexure A-IITERMS & CONDITIONS:
SCHEDULE OF ENERGY AUDITIt may be noted that field study shall start immediately within 7 days from the dateof issue of work order. The successful bidder to whom the job is awarded, has tocommence the activities as per the schedule as under. If the customer factory isnot in readiness due to any reason, PCRA will inform the vendor the altered date ofcommencement of work.
Sl No Activitv Time in weeks1 Mobilization Within 7 days from issue of work
order2 Field study completion Within 30 davs3 Submission of Draft Report Within 40 days after completion of
field studv4 Review bv Tata Power / PCRA
5Preparation of Final report andPresentation (color print) &Submission (6 sets of hard spiralbound copy & soft copies in CD inMS word/XL & PDF format).
Within a week after review &concurrence from MSPGCL/ PCRA
1. The energy audit shall be carried out in line with the guidelines of Bureau ofEnergy Efficiency (BEE) and Energy Conservation Act -2001 as amended ofGovernment of India.Tender will deploy BEE certified Energy Auditor at the site location during entireField study period along with Technician /Electrician and also for observation /Analysis for all site work related to Complete Energy audit study,
2. The tenderer shall arrange the required portable and monitoring instrumentsalong with calibration certificates for undertaking the energy audit.
3. Travel & transport will be arranged by contractor / tenderer.
4. The Energy Auditor should follow the state / central government rules andregulations in respect of PF, insurance, labor laws, electricity act and otherstatutory regulations in force.
5, The Energy Auditor has to fulfill/comply with safety rules of MPPGCL, securityclearances of personal, PF rules, labour laws, insurance formalities etc
7. The Energy Auditor is required to maintain following minimum equipment's withcalibration certificates while carrying out the Energy Audit.
s.No.
Equipment Details Quantity
1 Diqital power Recorder 2 Nos.2 Portable Power Analyser 2 Nos.3 Ultrasonic Flow meter 2 No,
4 Diqital Tachometer 2 No,
Page 4 of 11
![Page 5: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/5.jpg)
5 Non Contact / Infrared type temperature sensor 2 No.6 Lux Meter 2 No.7 Anemometer 2 No.B Dry - wet Bulb psychomotor 2 No.9 Ultrasonic air / qas / steam leak detector 2 No.10 Flue Gas Analvser 1 No.11 Thermoqraphy Scanner 1 No.
The Equipments listed above are minimum indicative only. However, additionalquantity / new equipment if required depending on the nature of work, shall haveto be deployed by Auditor.
S..Auditor will have to deploy two teams concurrently at the site
9.The Auditor has to provide manpower & equipment deployment plan along withvalid calibration certificates for the equipments,
1O. The field measurement taken during the Field study shall be recorded in fielddata sheets / handy record book & shall be maintained, so that back up data forfinal report are available with the Auditor. The same shall be produced to PCRA forverification / authenticity if it is asked by PCRA .
11. Tenderer should quote in o/o rate either (+) above or (-) below in the givenschedule both in figure and words, and where there is a difference between two,the rate given in words will be taken as authentic,
12.EMD of Un successful bidders will be without any interest. EMD of successfulbidder will be converted in to security deposit and will be released with final bill ieafter 2nd followup.
Completion Period:
1. Completion period for entire work will be B0 days for entire work reckonedfrom the date of issue of work order by PCRA or date of commencement asmentioned in commencement letter issued by PCRA whichever is later.
2. Date receipt of draft report by PCRA from the Energy Auditor will be the dateof completion of work.
3. The recovery of liquidated damages for delay in completion of job beyondscheduled date will be @ L.Oo/o per week subject to maximum of 10olo of WorkOrder Value.
Reoort Submission:
1. Hard & Soft copy of draft report made as per BEE-GTZ format for thermalpower plant Energy Audit shall be submitted to PCRA.
2. Draft reports should be discussed and presented as per time schedule toMSPGCL /PCRA before finalization of the repofts.
Page 5 of 1L
![Page 6: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/6.jpg)
3. 3 sets of spiral bound hard copies of final report along with soft copy in CD (inMS Word/ Exel & PDF format) should be submitted to PCRA.
Reoorts on implementation Follow-up:
1. First implementation follow-up and results achieved survey will be done byFafty, six month after submission of final report.
2. Second implementation follow-up and results achieved will be done byparty six month after first follow up.
3. Both follow up reports in PCRA format signed by MSPGCL will besubmitted by pafty to PCRA,
PAYMENT TERMS:
L. 90o/o payment will be released after acceptance of final energy audit reportby customer ie MSPGCL and on receipt of 100% payment by PCRA fromcustomer MSPGCL
2, 5o/o of work order value will be released after completion of l't follow-up,which shall be done six months after the date of submission of final report.
3. 5 o/o of work order will be released after completion of 2no follow-up, whichshall be done six month after the date of 1't follow up.
Pase 6 of 1L
![Page 7: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/7.jpg)
Annexure A-III
Scope of Work
scoPE oF woRK / TECHNTCAL SPECTFTCATTONS / SPECTAL CONDTTTONSOFCONTRACT
1. Scope Of Work
As a designated consumer, Tata Power Co. would like to carryout Energy Audit of
Paras Thermal Power plant Akola under the notification received by BEE dated 27th
May2014. Paras Thermal Power Plant has installed capacity of 500 MW and
comprises of two units having 250 MW (each) coal based fuel power plant
The audit of each unit will be carried out separately but under the same defined
scope. Heat Rate and Unit auxiliary consumption are the two main parameters of
the power plant which represent the health of that plant. Hence Auditing agency
shall *
1, Assess thorough tests, the potential available to improve Thermal and electrical
energy consumption
2. Suggest specific measures to reduce Thermal and electrical energy consumption
over a period of time with techno commercial viability.
3. Audit the major equipments, auxiliaries and include fact findings, assessment of
equipment and loss levels, performance measurement and analysis, suggestions
for improvement of performance parameters over a period of time, maintenance
improvements, operational performance, raw material improvements and strategic
planning.
4, Preparation and submission of report within 20 days after collection of data in
the format specified in the BEE notification.
5. Use the Calibrated instruments with the valid certificates for analysis and to
eliminate any doubt on the measurement
Detailed Scope of work1. Steam generator:
1,1 Boiler efficiency evaluation,
1.2 Effectiveness of air pre heaters
1.3 Air Heater leakages
Page 7 of 11
![Page 8: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/8.jpg)
1.4 Mill performance
1.5 Air ingress through furnace at different levels
1.6 Furnace radiation loss
1.7 Dry stack & wet stack loss
1.8 Moisture in combustion air loss
1.9 Blow down loss
1,10 Loss due to combustion in slag & bottom ash
1,11 Loss due to leakages steam & water
1.12 Sensible heat loss of fly ash & bottom ash
1,13 Boiler auxiliary equipment performance & energy consumption
1.14 Performance deviation with change in design fuel quality
1,15 Pedormance of water wall, super haters etc with respect to heat transfer
2. Turbine cycle
2.1 Turbine cycle, heat rate & efficiency
2.2 Turbine cylinder efficiency
2.3 Pressure survey
2.4 Performance of turbine gland sealing system
2.5 Condenser pedormance
2.6 Peformance of HP heaters, LP heaters, de-aerator, drain coolers
2.7 Performance study of Vacuum Pumps (For all units)
3. Electrical System (For all units)
3.1 Peformance study of generators & associated system
3.2 Study of transformer losses & power factor management
3,3 Energy consumption and audit of HT & LT motor in above area ( Boiler, turbine
&Balance Of Plant)
3.4 Peformance study of all other electrical system
4. Coal handling plant
Coal handling plant (Screw un-loader, pipe conveyer & other auxiliaries), long
distance pipe conveyor system associated with breakers, magnetic separators,
dewatering pumps etc. The system is spread from screw un-loader to the coal
yard, Then coal is fed to bunkers of respective units via pipe conveyers. The
system structure includes stacker re-claimer Tipplers, Crushers, Feeders,
Page 8 of 11
![Page 9: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/9.jpg)
Conveyors, Dust suppression/extraction systems. The above complete system is
to be energy audited for peformance study & energy conservation
5, Thermal Insulation:
The scope of insulation study includes carrying out temperature profile survey of
insulated sudace in areas of boiler, steam pipes, ducts & turbine etc, thorough
thermal scanning of all related surfaces for identifying hot spot with poor insulation,
identification of areas of poor / damaged insulation, contributing to excess heat
losses, estimation of extra heat loss / revenue loss due to the hot spots because of
damaged or poor insulation.
6. Ash Handling:
Ash handling plant at Trombay consists of Filtration plant, sea water system,
Bottom ash system, Fly ash system, Ash disposal system, ESP. The above
complete system is to be energy audited for performance study & energy
conservation
7, Water Pumping:
Condensate Extraction Pumps, Boiler feed water Pumps (Turbine driven & Motor
driven), Circulating Water Pumps, Heater drain pumps/ HP water Pump, Ash
Slurry pumps, Air conditioning plant pumps/ Steam Generator water circulating
pumps/ FO pumps, Control fluid pumps, Sea water booster pumps, Auxiliary
cooling water pumps.
B, FANS:
8.1 Induced Draft, Forced Draft Fans
8.2 Primary Air , seal air fans
9. AIR COMPRESSOR
Free air delivery test (compressor output assessment test), Estimation of specific
power consumption # Compressor wise, Estimation of actual compressed air
consumption, Pefformance of intercoolers and after coolers, Pressure drop survey,
Energy consumption pattern motor loading survey.
Page 9 of 11
![Page 10: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/10.jpg)
10. D M plant
DM water plant is common for all units. DM plant auxiliary consumption audit.
11, Flue Gas Desulphurisation Plant (FGD)
Scrubber pumps, Aeration fans, Booster fans & GGH,
12. AIR CONDITIONING:
Evaluation of net refrigeration capacity and specific energy consumption,
Operating efficiency and pedormance evaluation of the pumps, Pefformance of
cooling towers, power consumption of CT Fans, Performance evaluation of air
handling units, Pressure drop and insulation survey of chilled water lines,
Performance of condensers and evaporators,
13, LIGHTING:
Exploration of energy conservation possibilities, measurement of power
consumption of lighting loads, study of lux level at various area and the
recommendation of optimum lux levels, study of recommendation of suitable
energy efficient lighting system, Study and recommendation for maximum possible
use of natural light,
14, SPECIFIC ENERGY CONSUMPTION AUDIT:
After taking the data from all the above systems audit of overall the auxiliary power
consumption & fuel (coal/oil/gas) consumption to be carried out.
15, ACCURACY OF INSTRUMENTS:
Calibrated instruments with the valid certificates are to be used for analysis and to
eliminate any doubt on the measurement
16. ENERGY AUDIT REPORT AND RECOMMENDATION:
The recommendation shall include simply payback calculation for those
suggestions which require investment for implementation and all the proposal shall
be grouped into the following categories:
-Shon term: without or with minimum investments
-Medium term: simply payback within 1-3 years
Pase 10 of11
![Page 11: 22lr5-t6 - PCRA...WR-EA- 6\22lr5-t6 subject : Providing assistangg for carrying out Energy Audit of 2x25O MW---'unit" at MSPGCL, Paras Akola Dear Sir, we are sending you one set of](https://reader035.fdocuments.us/reader035/viewer/2022070705/5e97fd0c3d738e7d65472364/html5/thumbnails/11.jpg)
-Long term payback period more than 3 Years.
17. Other than final energy audit report if any data /information pertain to
efficiency of
the plant deemed necessary, three years after completion of Audit the firm has to
submit the same without any cost.
18. Whole work is to be carried out in three parts -18.1 Preliminary checking and data collection
LB.2 Analysis for efficiency and submission of provisional draft report after
discussions
on provisional draft report with the Performance department,
18.3 After discussion on provisional draft report with the Pedormance depaftment,
Auditing agency may submit final energy audit report.
19. Preliminary data /actual measurement of data at site - All possible preliminary
information / historical data will be furnished by Performance department however
19.1 In case of unavailability of any information/data firm has to collect the same
by own resource / staff from desired locations, Pedormance department will
coordinate with the concerning head of the circle.
19.2 In case of unavailability of any information/data at Auditing agency may
collect then same with their own resource from other identical units after obtaining
consent from Performance depaftment.
19.3 In case of unavailability of any information/data in respect of characteristics of
anyauxiliaries Auditing agency may use current data for analysis.
Energy Audit repoft shall be made as per BEE-GTZ guidelines/Formats for thermal
power plant