2.1 Process Introduction(1)

download 2.1 Process Introduction(1)

of 26

Transcript of 2.1 Process Introduction(1)

  • 8/11/2019 2.1 Process Introduction(1)

    1/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde - Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    1 (26)

    1 2005 - 08 - 30 T. Anttonen

    0 2005 - 02 - 11 T. Anttonen

    Muut.Rev. PvmDate LaatinutPrepared by PvmDate TarkastanutReviewed by PvmDate HyvksynytApproved byKLY-1 1997-05 P:\582-RAPP-PB3\int\Kayttoonotto\koulutus\Training Manuals\Folder 1\2.1Process_introduction(1).doc

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    TABLE OF CONTENTS

    2. PROCESS DESCRIPTION.................................................................................... 2

    2.1

    Introduction............................................................................................................ 2

    2.1.1 General.................................................................................................................. 22.1.2

    Circulating Fluidized Bed Process ......................................................................... 3

    2.1.3

    Condensate and feedwater system ....................................................................... 5

    2.1.4 Boiler water/steam system..................................................................................... 62.1.5

    Vents, Drains and Blowdown............................................................................... 12

    2.1.6 Chemical Dosing and Sampling........................................................................... 132.1.7

    Air System ........................................................................................................... 15

    2.1.8 Flue Gas System ................................................................................................. 182.1.9 Solid fuel handling system ................................................................................... 202.1.10

    Limestone Feeding System.............................................................................. 22

    2.1.11 Sand feeding system........................................................................................ 222.1.12

    Coarse Material Removal System.................................................................... 23

    2.1.13 Fly Ash Handling System ................................................................................. 242.1.14

    Oil System........................................................................................................ 24

    2.1.15

    Sootblowing steam system............................................................................... 25

    2.1.16 Cooling Water System ..................................................................................... 262.1.17

    Medium and Low Pressure Steam System ...................................................... 26

    2.1.18 Compressed Mill Air System ............................................................................ 262.1.19 Compressed Instrument Air System................................................................. 26

  • 8/11/2019 2.1 Process Introduction(1)

    2/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    2 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2. PROCESS DESCRIPTION

    2.1 Introduction

    This section describes general operation principles and technical

    data of a circulating fluid bed boiler with auxiliaries.

    2.1.1 General

    The unit will be designed to generate 650 t/h of high pressure steam,

    at 142 bar(a) and 540C from feedwater at 130 C.

    The main fuel for the boiler is bituminous coal. Also bark and

    woodwaste can be fired. The design allows also use of smalleramount of sludge (reservation made for sludge silo and feeding

    equipment). Boiler start-up burners are designed for heavy fuel oil

    and diesel oil.

    Kvaerner's circulating fluidized bed boiler is a single drum unit which

    consists of a gas-tight, membrane construction furnace, three

    parallel cyclones and a second pass where the primary and tertiary

    superheaters and smooth economizer section are located. In thethird pass are located finned tube economizers and air preheaters.

    Kvaerner Power CFB technology ensures low emission and high

    efficiency combustion process. The boiler is furnished with limestone

    injection to meet sulfur dioxide emission requirements.

  • 8/11/2019 2.1 Process Introduction(1)

    3/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    3 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.2 Circulating Fluidized Bed Process

    A fluid bed contains a mass of particulate solids through which an

    upwardly flowing fluid is passed at a velocity sufficient to cause the

    particles to behave like a liquid. The bed material consists mainly of

    fine sand particles, fuel ash and limestone which can be fed to the

    furnace to reduce SO2emission. The fluidizing medium consists of

    air and flue gas produced by the combustion of the fuel.

    In the circulating fluidized bed (=CFB) boiler the velocity of fluidizing

    medium is so high that part of the particles is carried with the gas.

    There are two distinctive phases of solids in the combustion

    chamber, the dense phase and the dilute phase. The dense phase,

    or bed, consists of fuel ash, sand, a small percentage of unburned

    fuel and possibly of limestone. The fluidization gas elutriates fine

    particles into the dilute phase. The dilute phase density has a direct

    effect on the heat transfer rate in the furnace. Most of the solids

    elutriated from the combustion chamber are separated from the flue

    gas stream in the cyclone separators and cleaned flue gas flows to

    the second pass. The separated solids fall down to the bottom of the

    cyclones where so called loop seals are located. The loop seals are

    small fluid beds, which act as a seal preventing flue gas to flow from

    lower part of the furnace to the cyclones. From the loop seals solidparticles are returned back to the furnace.

    Normally the bed temperature varies between 750 940 C and due

    to large mass of the circulating material the temperature is almost

    constant throughout the furnace. The bed temperature is controlled

    by variating the air distribution, using flue gas recirculation and

    changing excess air level.

  • 8/11/2019 2.1 Process Introduction(1)

    4/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    4 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    The fuel properties can vary within given range without adversely

    effecting the combustion. The rate of combustion is so high that the

    steam output can be increased/decreased rapidly by changing the

    fuel flow according to the load demand. The lower part of furnace

    walls and other areas where risk for erosion exists are covered by

    refractory to minimize wearing in these sections. Fluidizing velocity is

    designed to be a moderate to ensure low erosion impact into

    refractory in dense bed area.

    The welds are grinded in furnace walls and the number of openings

    is minimized to avoid erosion. The boiler is furnished with the

    functionally needed maintenance doors and sight glasses.

    Moderate inlet velocity of flue gas is used in cyclones. The round

    form of cyclone is used, which ensures high separation efficiency.

    The cyclones, located between the furnace and the second pass,

    are totally water cooled operating in the parallel natural circulation

    loops to the furnace. The gas tight walls of the cyclones are of

    membrane construction. From the flue gas side cyclones are

    completely protected against erosions by refractory.

    The thermal expansion of the cyclones and furnace is the same due

    to same cooling media in water circulation. Therefore there is noneed for expansion joints between the cyclones and the furnace.

  • 8/11/2019 2.1 Process Introduction(1)

    5/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    5 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.3 Condensate and feedwater system

    Condensate water from the mill processes and turbine is introduced

    to the condensate collecting tank (not in scope). From the

    condensate tank water is pumped to the deaerator. Make-up water

    from the demineralization plant and the condensated water from the

    primary air steam preheater are also led to the deaerator. In the

    dearator most of oxygen dissolved in condensate and make-up

    water is thermally removed by heating make-up water with the same

    low pressure steam which is used to feedwater tank pressure

    control. Feedwater tank serves as feedwater storage having about

    15 minutes storing capacity when boiler is operated at MCR load.

    The deaerator is integrated to the feed water tank so that the water

    is first sprayed in a part of the steam space (pre-deaeration) and

    then in the second stage the steam is injected to the water (final

    deaeration). During start-up water is heated to the operating

    temperature by leading low pressure steam below the water level of

    the feedwater tank through a perforated pipe and by distributing the

    steam evenly over the whole length of the feedwater tank.

    From the feedwater tank water is pumped by direct drive feedwater

    pumps (not in scope) to the boiler. Normally three parallel feedwaterpumps are in operation while the fourth one is stand-by.

  • 8/11/2019 2.1 Process Introduction(1)

    6/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    6 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.4 Boi ler water/steam system

    Feedwater is introduced to the CFB boiler at the inlet of an

    economizer. After the economizer sections water enters the steam

    drum.

    From the steam drum boiler water is fed to the furnace walls and

    floor and to the cyclone walls via downcomers, supply pipes and

    distribution headers. The furnace and the cyclones have separate

    downcomers and circulation pipes and thus they form separate

    circulation loops.

    In boilers with natural circulation the circulation of water and

    steam/water mixture is based on the change of specific density, i.e.

    the heavier steamless water column in the downcomers presses thelighter steam/water mixture from the steam generating surfaces to

    the drum.

    From the steam drum the saturated steam flows to the superheaters.

    The superheated steam temperature is controlled in two-stage

    steam attemperators by spraying feedwater to steam flow.

    High pressure parts of the boiler are protected by safety valve

    system consisting of two safety valves located in the drum and two

    located in main steam line before the main steam stop valve.

  • 8/11/2019 2.1 Process Introduction(1)

    7/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    7 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.4.1 Economizers

    The feedwater is introduced at the both ends of the distribution

    header of the first economizer section.

    In the three stage economizer sections feedwater temperature is

    raised by flue gas before entering the steam drum.

    The flue gas flows downwards, across horizontally arranged

    economizer sections. The feedwater rises counter/cross flow to the

    flue gas. Two first two economizer packages are of finned tube

    construction and the last, the third one is constructed of smooth

    tubes. The advantage of the finned tube construction is the effective

    heat transfer ability and space utilization.

    2.1.4.2 Steam Drum

    The purpose of the drum is to operate as a separator in the water-

    steam circulation between the steam generator and the superheater

    as well as boiler short-term water storage.

    The feedwater coming from economizer enters the drum at the both

    ends through a perforated distribution pipe. From the drum, water is

    supplied to the steam generating surfaces, furnace and cyclones viadowncomers. From the steam generating surfaces the steam/water

    mixture is returned back to the drum through cyclone type steam

    separators. After cyclone separators steam is furthermore dried in

    chevron type secondary scrubbers before leaving steam drum.

  • 8/11/2019 2.1 Process Introduction(1)

    8/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    8 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.4.3 Furnace

    The size of the furnace is determined by the design fuels and the

    required evaporation capability. The heat released in the furnace is

    transferred effectively by the means of radiation heat transfer and

    particle convection to the furnace wall tubes.

    Proper water circulation in the furnace walls is ensured by using a

    sufficient amount of downcomers, circulating pipes and supply and

    collection headers. The water circulation in the furnace walls is

    carried out by natural circulation.

    By downcomers (5 pcs) originating from the drum, the water is

    introduced to the level of the lower section of the furnace.

    Distribution headers of the furnace are fed through supply pipesoriginating from lower part of the downcomers. The furnace bottom

    forms a fluidized combustion grate which is also fully water cooled

    since it is used to provide water to the rear wall distribution header.

    In the furnace wall tubes part of the boiler water is evaporated.

    Furnace walls are made of gas tight membrane construction.

    From the collection headers of each wall section the water/steam

    mixture is introduced by the upper circulation pipes (raiser pipes)

    back to the drum.

    The furnace is equipped with tight inspection openings (sight

    glasses) in order to monitor the burners, grate and furnace. For the

    maintenance and repair of the furnace and heat transfer surfaces the

    boiler is equipped with tightly closed access doors.

  • 8/11/2019 2.1 Process Introduction(1)

    9/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    9 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.4.4 Cyclone separators and loop seals

    The size of the cyclones is determined by produced flue gas amount

    and the required dust separation efficiency. The heat released in the

    cyclones and loop seals is transferred by particle convection to the

    refractory layer protecting wall tubes. Gas tight cyclone and loop

    seal walls are same type of membrane construction as furnace

    walls.

    By downcomers (2 pcs) originating from the drum, the water is

    introduced through supply pipes to distribution headers of the loop

    seals. After flowing through loop seal tubes water/steam mixture

    enters to wall tubes of the cyclones. In upper parts of the cyclones

    water/steam mixture is collected to round shaped collection headers

    and then led through upper circulating pipes (raisers) back to the

    steam drum.

    Since cyclones and loop seals are totally refractory covered only

    little heat is transferred to those evaporation surfaces. Most of

    evaporation takes place in the furnace wall tubes.

    2.1.4.5 Superheaters

    The purpose of the superheater section is to achieve a steam

    temperature of 540 C after the superheaters.

  • 8/11/2019 2.1 Process Introduction(1)

    10/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    10 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    The superheater has been divided into three stages. The first stage

    (primary superheater) is a convective type superheater (located in

    the 2nd pass), the second stage (secondary superheater) is a

    radiant type superheater (located inside the furnace) and the third

    stage (tertiary superheater) again a convective type superheater

    (located in upper part of the 2nd pass).

    From the drum the saturated steam is introduced by connection

    pipes (saturated steam pipes) to the 2nd pass front wall distribution

    header. Second pass walls, roof and load carrying tubes (supporting

    tubes for heat transfer bundles in the 2nd pass) are the first part of

    the primary superheater. Steam flows first downwards in front wall

    tubes and is then divided to side wall tubes and to first row of load

    carrying tubes. Steam which has flown upwards through side walls is

    collected to upper headers of the side walls and then led through

    connection pipes to 2nd pass roof distribution header. Steam then

    flows downwards through second pass roof and rear wall tubes to

    rear wall collection header. To this same header is collected steam

    from load carrying tubes after it has flown the second row of carrying

    tubes. From the second pass rear wall collection header steam flows

    through connection pipes to the actual primary superheater sections.

    The actual primary superheater sections (2 pcs) are located in themiddle part of the 2nd pass. In the superheater tubes the steam

    flows counterflow to the flue gas. The primary superheater sections

    are supported from the above mentioned load carrying tubes.

  • 8/11/2019 2.1 Process Introduction(1)

    11/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    11 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    From the collection header of the primary superheater the steam is

    introduced to two parallel steam attemperators. Attemperator is

    divided to parallel units because then it is easier to control

    temperature across the wide superheater. The purpose of the first

    stage steam attemperators is to keep steam temperature after the

    secondary superheater on the required level.

    The steam attemperators are so-called spraying attemperator where

    the feedwater is injected into the steam. While being vaporized and

    superheated it binds the heat whereupon the temperature of the

    steam leaving the attemperators falls. The spraying attemperator

    consists of a spraying chamber, a spraying nozzle and an internal

    venturi tube.

    The vertical secondary superheater is located in the upper part of

    the furnace, near the furnace front wall. It is a radiant type

    superheater that operates on a so called parallel-flow principle,

    where steam is led to superheater lower part header and steam then

    flows upwards to collection headers of the superheater elements

    located above the furnace roof.

    From the collection header of the secondary superheater the steam

    is introduced to the second attemperator stage. Also thisattemperator is divided into two parallel spray chambers located on

    both sides of the boiler and in these units steam temperature is

    controlled to correspond required temperature after the tertiary

    superheater section.

  • 8/11/2019 2.1 Process Introduction(1)

    12/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    12 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    From the second stage attemperators steam flows to the tertiary

    superheater sections located in the upper part of the second pass.

    Tertiary superheater consists of two sections and is convective type

    superheater where steam flows counterflow to flue gas flow. From

    the final superheater collection header steam is lead to the steam

    turbine.

    2.1.5 Vents, Drains and Blowdown

    Vents are supplied for the purpose of venting the boiler during start-

    up and shutdown. High pressure part vents are piped to the common

    collection funnel to where vent valves are also gathered.

    Air and vent steam are then led to the blowdown tank vent pipe. Also

    water coming to funnel with vents is drained to that same vent pipe.

    Drains are used for the drainage of the boiler during start-up and

    shutdown. The drains from the economizer, furnace, cyclones,

    superheaters and sootblowing system are piped to a common

    drainage header and further to the blowdown tank. Drains from low

    pressure parts are introduced to the blowdown tank through own

    drainage header.

    One furnace drain, which can be used for limiting drum high water

    level, and feedwater tank overflow pipe are connected directly to

    blowdown tank.

    In the blowdown tank hot drains are cooled down and then led to the

    sewer.

  • 8/11/2019 2.1 Process Introduction(1)

    13/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    13 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    All high pressure part vent and drain lines are equipped with two

    sequential shut off valves.

    Since small amounts of unvolatile matters (salts) enter the boiler

    continuously with feedwater, these are enriched in water and the

    quality of boiler water and steam becomes poor. To eliminate this

    problem, continuous blowdown from the drum is taken out all the

    time. The blowdown water is introduced to the continuous blowdown

    tank where part of water evaporates due to lower pressure. Flash

    steam (expansion steam) generated in continuous blowdown tank is

    led to feedwater tank and condensate flows to blowdown tank where

    it is cooled and finally led to sewer.

    The flashed water vapor from the blowout tank is vented to

    atmosphere via vent steam pipe to roof and water is lead to sewer.

    2.1.6 Chemical Dosing and Sampling

    Chemical dosing stations includes own tanks for:

    oxygen scavenger

    pH control chemical (amine) phosphate

    The dosing tanks are used for preparation of chemical solutions. In

    preparation of dosing solutions make-up water is used. System is

    equipped with necessary ejectors for solution preparation and

    venting fan, which removes harmful vent gases to safe location.

  • 8/11/2019 2.1 Process Introduction(1)

    14/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    14 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Each tank is furnished with two parallel dosing pumps of which one

    is in operation and the other ones are stand-by. Pumps used for

    oxygen scavenger and pH control chemical dosing are diaphragm

    type pumps and pumps for phosphate dosing piston type pumps.

    The sampling system consists of:

    sample probes

    sample piping with valves

    sample coolers

    Sample tapping probes are installed in the condensate pipe before

    deaerator, feedwater tank, feedwater pipe, continuous blow-down

    pipe, downcomer, saturated and superheated steam pipes. The

    water or steam is led into the sample cooler, where it is condensed

    and cooled. Condensated and cooled sample is then analyzed in

    laboratory or in on-line analyzers.

    With continuous pH-monitoring are equipped the following samples:

    condensate water

    feedwater

    boiler water

  • 8/11/2019 2.1 Process Introduction(1)

    15/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    15 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    With continuous conductivity monitoring are equipped the following

    samples:

    condensate water

    feedwater from the feedwater tank and from feedwater line

    boiler water saturated steam

    superheated steam

    In addition to those continuous O2-monitoring is provided for

    feedwater line sample and continuous silica monitoring for boiler

    water sample.

    The adjustments to the continuous blow-down flow and to dosing

    chemical feeding will be done based on the indications from the

    samples. There are no actual control loops and the adjustments will

    be done by the operator.

    2.1.7 Air System

    The combustion air is divided into primary (fluidizing) air, secondary

    air and loop seal air. The combustion air for the start-up burners is

    supplied from the secondary air system.

    Combustion air distribution to different locations depends mainly on

    fuel (coal / woodwaste) and boiler load. Boiler control system takes

    care of air distribution according to preset values but in some

    operation situations fine tuning may be required by the operators.

  • 8/11/2019 2.1 Process Introduction(1)

    16/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    16 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Along with the low combustion temperatures, the combustion air is

    staged to obtain low NOx -emission levels by utilizing fluidizing air

    and secondary air. The fluidizing air is introduced into the furnace

    through air nozzles penetrating the furnace floor. The secondary air,

    which completes the combustion, is introduced through air ports

    located on the furnace walls at two separate levels. The fluidization

    results in an expanded combustion zone with high turbulence,

    intimate solids to-gas contact that results in a high heat transfer rate

    within the bed.

    The bed temperature depends on the quality and amount of the fuel

    in the bed and bed material circulation rate (fluidizing velocity).

    2.1.7.1 Primary Air System

    The primary air (fluidizing air) is introduced into the furnace by two

    parallel high pressure primary air fans (2 x 60 %), located at ground

    floor. The primary air pressure is controlled by inlet vanes and air

    flows to two separately controlled windbox sections are controlled by

    dampers.

    Primary air is preheated by low pressure steam in steam coil

    preheater, when needed, before entering tubular flue gas air

    preheater.

    Flue gas air heater bundles are made of vertically arranged plain

    tubes where air flows inside the tubes and flue gas outside them.

    The flue gas air heater sections are located in the lower part of the

    third pass and they are the last heat transfer surfaces of the boiler.

  • 8/11/2019 2.1 Process Introduction(1)

    17/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    17 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    The purpose of flue gas air preheater is to increase combustion air

    temperature, which helps the combustion of wet fuels. At the same

    time it decreases flue gas outlet temperature and thus increases

    boiler thermal efficiency.

    The fluidizing air is introduced into the furnace from the windbox,

    located underneath the furnace, through evenly spaced fluidizing air

    nozzles penetrating the furnace floor.

    2.1.7.2 Secondary Air System

    The secondary air is fed into the furnace by two parallel high

    pressure secondary air fans (2 x 60 %), located at ground floor. The

    secondary air pressure is controlled by variable frequency drive of

    the fan and air flows to separate sections are controlled by dampers.

    Secondary air is not preheated.

    The secondary air is introduced into the furnace through secondary

    air ports on the furnace walls. The secondary air ports are located at

    two elevations. The first level is located directly above the bed and

    the second is above the fuel feeding openings few meters above the

    bottom.

    2.1.7.3 Loop seal air system

    Fluidizing air for loop seals is produced by two parallel roots type

    high pressure blowers. During the cold start-up both blowers are

    running parallel but when normal operation temperature is reached

    only one blower is needed and the other is stand-by.

  • 8/11/2019 2.1 Process Introduction(1)

    18/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    18 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Air pressure is adjusted by rotation speed of the blowers and air flow

    for each loop seal section is controlled by dampers.

    2.1.8 Flue Gas System

    2.1.8.1 Furnace and Cyclones

    The boiler furnace is a combustion chamber where the thermal

    energy bound in the fuel is released. The flue gas amount and

    properties generated in the combustion process depend on the fuels

    used.

    In three parallel cyclones most of particles conveyed with flue gas

    from the combustion chamber are separated and returned back tothe furnace.

    2.1.8.2 Second and third pass

    The walls in the 2nd pass are cooled by superheated steam flowing

    in the wall tubes. After plain tube economizer flue gas is led to third

    pass where walls are constructed with a plate casing.

    In the second and third pass flue gas cools down when it flows

    across superheater, economizer and air preheater sections.

  • 8/11/2019 2.1 Process Introduction(1)

    19/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    19 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.8.3 Electrostatic precipitator (not in scope)

    Fly ash is removed from the flue gas in electrostatic precipitator (not

    in scope), which comprises two parallel chambers and three fields.

    Both ESP chambers are designed for 60% boiler capacity. Flue gas

    ducts before the ESP chambers are equipped with guillotine

    dampers.

    Dust-laden flue gas from the boiler is sucked by means of a flue gas

    fan into the inlet funnel of the electrostatic precipitator and further to

    the precipitator casing where dust collection takes place. The

    cleaned gas is led from the precipitator casing through the outlet

    funnel via the flue gas fan and the flue gas ducts to the stack.

    The collected dust falls down to the precipitator bottom cones and isled via ash conveyors to the ash silo.

    2.1.8.4 Flue gas fans

    The two (2 x 60 %) parallel operated radial-type induced draft (ID)

    fans, located after the electrostatic precipitator, provide the draft

    required to keep flue gas pressure in upper part of the furnace at

    about -0,1 ... -0,2 kPa. The draft is controlled by the variable

    frequency drives of the fans. The ID fans also discharge flue gas into

    the stack.

  • 8/11/2019 2.1 Process Introduction(1)

    20/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    20 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    2.1.8.5 Recirculating gas system

    When needed, part of the flue gas can be recirculated after the ID

    fans through recirculation flue gas fan to the lower part of the

    furnace. Flue gas recirculation system is used to lower combustion

    temperature in the furnace and it can also be used to increase full

    superheating range. Recirculating flue gas pressure in controlled by

    inlet vanes of the fan and flow to separate sections is adjusted by

    dampers. Recirculating flue gas duct before the fan is equipped with

    guillotine damper.

    2.1.9 Solid fuel handling system

    2.1.9.1 Coal feeding system

    From the coal storage (not in scope) crushed coal is fed by belt

    conveyor (not in scope) to dividing drag conveyor (not in scope)

    which transfer fuel to two coal silos located by the furnace left side

    wall.

    The coal is conveyed from the silos to the furnace with three

    independent feeding lines.

    Coal is discharged from the feeding silos by variable frequency

    controlled chain dischargers, two pieces on each silo. Dischargers

    carry coal to the mixing screws where it is mixed to the fuel coming

    from biofuel silos. After mixing screws fuel (or fuel mixture) goes to

    drag chain type feeding conveyors.

  • 8/11/2019 2.1 Process Introduction(1)

    21/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    21 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    On the furnace front wall fuel is divided to two parallel drag

    conveyors from which the fuel is divided to the six feeding points, so

    that each drag conveyor is feeding three separate feeding points. On

    the rear wall side there is only one drag conveyor. Each of the three

    conveyors are equipped with variable frequency drives.

    The even distribution of fuel to all feeding points is controlled by

    metering screws on each feeding points. Also these screws are

    variable frequency controlled.

    Each fuel feeding chute is equipped with rotary lock feeders in order

    to prevent any backflows from the furnace. The lower part of each

    fuel feed chutes on the front wall is equipped with constant speed

    feeding screw. These screws are equipped with a feed/purge air

    system that improves the fuel injection and distribution while also

    cooling the feeding system. On the rear wall fuel is fed from the

    rotary feeders directly to loop seals.

    2.1.9.2 Bark feeding system

    Biofuel is fed from the bark yard (not in scope) by a belt conveyor

    (not in scope) to dividing drag conveyor (not in scope) located above

    the biofuel feeding silos.

    Round shaped bark silos are equipped with slewing screw

    dischagers. Dischargers drop biofuel to drag conveyors, which

    furthermore take biofuel to mixing screws, where biofuel and coal

    are mixed. After that biofuel is fed to the combustion chamber

    through same conveyor system and feeding points as coal.

  • 8/11/2019 2.1 Process Introduction(1)

    22/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    22 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Bark flow is controlled by variable frequency controlled electric motor

    drives of the silo discharger, drag conveyor and metering screw.

    2.1.10 Limestone Feeding System

    Limestone system is used to reduce flue gas SO2emission.

    Big and moist limestone particles are first crushed and dryed in a

    separate limestone prehandling factory consisting of limestone

    receiving hopper, intake belt with magnet, mill feeding hopper with

    feeder, integrated mill and separator, cyclone, baghouse filter, diesel

    oil fired burner, fans and all necessary connections in the drying and

    crushing loop. Dried limestone is then conveyed to limestone

    storage (or feeding) silo by bucket conveyor.

    From the storage silo limestone is discharged by variable frequency

    controlled dosing screws. After screws there is a rotary lock feeder,

    which drops the limestone to the pneumatic feeding lines. Pneumatic

    feeding is divided in six feeding points at furnace front wall. Feeding

    openings are located close to the fuel feeding points. The pneumatic

    conveying air comes from separate high pressure blower.

    2.1.11 Sand feeding system

    Sand handling system is used to produce suitable bed material for

    fluid bed combustion.

  • 8/11/2019 2.1 Process Introduction(1)

    23/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    23 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Sand handling system includes sand receiving hopper with

    discharger screw, elevator type of conveyor, rotary feeder and

    piping.

    Sand is received to the hopper (volume 20 m3), which also serves

    as a small storage. To this hopper comes also sieved ash from the

    bottom ash screening. Sand is discharged from the hopper via screw

    into the elevator which lifts sand up enough to be able to gravitation

    fed it via rotary feeder and piping to fuel feeding screw located on

    the front wall of the furnace.

    2.1.12 Coarse Material Removal System

    The bottom ash, including coarse particles, is removed from the

    furnace through twelve chutes, which penetrate the furnace floor and

    the primary air windbox. The coarse material chutes are equipped

    with pneumatic valves, which are opened only when bottom ash is

    discharged. The bottom ash from the chutes falls into the water

    cooled bottom ash screws (3 pcs).

    The cooling of these bottom ash screws is done with closed cooling

    water system, which includes unpressurized cooling water tank, twocirculating pumps (with the other pump as a reserve), heat

    exchanger and all the necessary piping needed. The circulating

    water is cooled via heat exchanger, which is using cooling water of

    temperature 32 C.

  • 8/11/2019 2.1 Process Introduction(1)

    24/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    24 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    Bottom ash is transferred from the screws by bottom ash conveyor

    to bottom ash screening. From the screen coarse material is led via

    drag conveyor and bucket elevator to ash silo and fine particles are

    returned to sand hopper. When it is not necessary to return fine

    material to the process, screening system can be bypassed, and all

    bottom ash material is conveyed to ash silo.

    2.1.13 Fly Ash Handl ing System

    Fly ash consists of the ash in the fuel, unburned carbon, fine sand

    fractions and limestone. The fly ash is mainly collected from the flue

    gas in the electrostatic precipitator. The fly ash is collected from the

    electrostatic precipitator hoppers to the drag conveyors and

    transferred mechanically to ash silo.

    Fly ash retained in the 2nd and 3rd pass hoppers is collected and

    mechanically transferred to the ash silo. Fly ash silo is equipped with

    moisturizing screw discharger.

    2.1.14 Oil System

    Heavy fuel oil and diesel oil are used as a boiler start-up fuels in six

    start-up burners. Diesel oil is used also for limestone drying. Both

    oils are delivered from pumping units, designed for 2 x 100 % burner

    capacity of power boiler including all necessary equipment.

  • 8/11/2019 2.1 Process Introduction(1)

    25/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    25 (26)

    This document is the exclusive intellectual property of Kvaerner Power Oy and is furnished for the sole purpose of operating and maintaining of the specific project, and re-use of the document for any other project orpurpose is prohibited. The document or the information shall not be reproduced or copied, or disclosed to a third party without prior written consent of Kvaerner Power Oy.

    Kvaerner Power Oy, Tampere, Finland 2005

    The start-up burners are located on furnace walls, two on each side

    wall and two on rear wall. The combustion air is supplied from the

    secondary air ducting. The start-up burners are utilized to heat the

    bed (sand or ash) to the temperature required to begin the firing of

    solid fuel.

    The combustion air to the burners is measured with aerofoil type

    flow measuring devices and controlled with a control damper.

    Burners utilize a gas electric igniter system. The propane gas

    igniters offer maintenance free igniters, which allow in a very smooth

    burner start-up operation.

    2.1.15 Sootblowing steam system

    The boiler is furnished with sootblowers for the removal of ash

    deposits from the heat transfer surfaces.

    Due to wide second and third pass width sootblowers are located on

    the both sides of the boiler. The tertiary superheater packages are

    equipped with totally retractable sootblowers. The multi-nozzle type

    sootblowers with motion (partial stroke) are utilized to clean the

    primary superheaters, plain tube economizer and air preheaters.Finned tube economizers are equipped with rake type sootblowers.

    Sootblowing steam is taken after the primary superheater. The

    sootblowing steam pressure is reduced by pressure reduction valve

    prior to the sootblowers and system is protected against

    overpressure by safety valve.

  • 8/11/2019 2.1 Process Introduction(1)

    26/26

    Asiakirjan nimi - Name of Document Tunniste - Identification Rev.

    PROCESS DESCRIPTIONS2.1 INTRODUCTION

    CFBT-582-1 1

    Osasto - Department Kohde Subject Sivu - Page

    Power GenerationSystems

    RAPP PB3 PROJECTCFB MULTIFUEL BOILER

    26 (26)

    2.1.16 Cooling Water System

    Closed circuit cooling water is furnished to the heat exchanger of the

    closed circulation of the water-cooled bottom ash screws, feedwater

    pumps, sample coolers and to five lubrication oil units of the fans.

    2.1.17 Medium and Low Pressure Steam System

    Medium pressure steam is used for heavy fuel oil preheating and oil

    atomizing in the burners.

    Low pressure steam is used for feedwater tank pressure control and

    combustion air preheating (primary air) and as extinction steam for

    fuel feeding equipment.

    2.1.18 Compressed Mill Air System

    Compressed mill air is taken from the existing compress air system.

    The biggest mill air consumers are the start-up burners, fuel feeding

    rotary feeders cleaning and limestone storage silo fluidizing. Some

    mill air is also used in ash, coal and limestone silo filter cleaning and

    for bag filter cleaning in the limestone prehandling.

    2.1.19 Compressed Instrument Air System

    Instrument air is primarily used for burner flame detector cooling and

    for pneumatic actuators of control valves and dampers.