ISO Public ISO Public 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13, 2020

Transcript of 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton...

Page 1: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO PublicISO Public

2021 & 2025 Final LCR Study Results

Stockton Area

Ebrahim Rahimi

Lead Regional Transmission Engineer

Stakeholder Call

April 13, 2020

Page 2: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Stockton Area Transmission System & LCR Sub-areas

Slide 2

Legend: Rio Oso230 kV

Lockeford 60 kV

LockefordLCR Sub-Area

Lodi60 kV

Industrial60 kV

60 kV

Colony60 kV

Victor60 kV

Lockeford 230 kV

Bellota230 kV

230 kV

Wodberg60 kV

Manteca 115 kV

Legend: 115 kV

Kasson 115 kV

Vierra 115 kV

Schulte

Tesla 115 kV

Tracy

Salado 115 kV

Ingram Creek 115 kV

G

GWF Tracy Units

Lammers

Melones 115 kV

Bellota 115 kV

Riverbank115 kV

Tulloch115 kV

Stanislaus115 kV

Ripon 115 kV

Riverbank JCT

115 kV

Bellota 230 kV

Stanislaus

Tesla - Bellota

Lockeford

Weber was a sub-area within the

Stockton area in the past, requiring

generation to address P6

contingencies on 60 kV non-bulk

system. However due to change in

LCR criteria, Weber doesn’t have

any LCR requirement.

Page 3: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

New major transmission projects

Slide 3

Project Name Expected ISD

Year 2021

Ripon 115 kV LineOperational

since May 2019

Stockton A – Weber #1 & #2 60 kV lines ReconductorOperational

since Aug. 2019

Year 2025

Vierra 115 kV Looping Project Jan-23

Tesla 230 kV Bus Series reactor Dec-23

Lockeford-Lodi Area 230 kV Development Jun-25

Page 4: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Power plant changes

Additions:

• No new resource addition

Retirements:

• No new retirements

Slide 4

Page 5: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Stockton Area Overall: Load and Resources

Slide 5

Load (MW) 2021 2025 Generation (MW) 2021 2025

Gross Load 1,095 938 Market/ Net Seller/ Battery 445 491

AAEE -4 -7 Solar 12 12

Behind the meter DG 0 0 Wind 0 0

Net Load 1,091 931 Muni 139 116

Transmission Losses 22 19 QF 0 0

Pumps 0 0Future preferred resource

and energy storage0 0

Load + Losses +

Pumps1,113 950 Total Qualifying Capacity 596 619

Page 6: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Lockeford Sub-Area : Requirements

Slide 6

Year Category Limiting Facility ContingencyLCR (MW)

(Deficiency)

2021 P3Lockeford – Lodi #2 60

kV

Lockeford-Industrial 60 kV

line and Lodi CT36 (12)

2025 All No requirements due to Lockeford-Lodi Area 230 kV Development project

Lockeford

Lodi

Industrial

New HopeColony

Victor

Lodi Jct

Lockeford-Lodi #1

Lockeford-Industrial

Lockeford-Lodi #2

Lockeford-Lodi #3

Legend: 60 kV

X

XContingency

Overload

Page 7: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Lockeford Sub-area: Load Profiles

Slide 7

Lockeford Sub-area LCR requirement will be eliminated due to the Lockeford--Lodi Area 230 kV

development transmission project expected to be in service in 2025

Page 8: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Stanislaus Sub-Area : Requirements

Slide 8

Year Category Limiting Facility ContingencyLCR (MW)

(Deficiency)

2021 P3Manteca - Ripon 115 kV

Line

Bellota-Riverbank-Melones 115

kV line and Stanislaus PH unit205

2025 P3Manteca - Ripon 115 kV

Line

Bellota-Riverbank-Melones 115

kV line and Stanislaus PH unit213 (1)

Manteca 115 kV

Melones 115 kV

Bellota 115 kV

Riverbank115 kV

Tulloch115 kV

Stanislaus115 kV

Ripon 115 kV

Bellota – Riverbank – Melones SW STABellota – Riverbank

Riverbank JCT SW STA - Menteca

Stanislaus – Melones SW STA - Manteca

Stanislaus – Melones SW STA – Riverbank JCT SW STA

Stanislaus – Manteca #2

Riverbank JCT

115 kVX

Legend: 115 kV

XContingency

Overload

Page 9: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO PublicSlide 9

Year Category Limiting Facility ContingencyLCR (MW)

(Deficiency)

2021 P2-4

Stanislaus –

Melones –

Riverbank Jct line

Tesla 115 kV bus690

(117 NQC/129 Peak)

2021 P6

Schulte-Kasson-

Manteca 115 kV

line

Schulte – Lammers and

Tesla – Tracy 115 kV

lines

909

(646 NQC/658 Peak)

Total LCR Need in 20211,219

(646 NQC/658 Peak)

Tesla - Bellota Sub-Area : Requirements (2021)

Manteca 115 kV

Legend: 115 kV

Kasson 115 kV

Vierra 115 kV

Schulte

Tesla 115 kV

Tracy

Salado 115 kV

Ingram Creek 115 kV

G

GWF Tracy Units

LammersX

X

Melones 115 kV

Bellota 115 kV

Riverbank115 kV

Tulloch115 kV

Stanislaus115 kV

Ripon 115 kV

Riverbank JCT

115 kV

Bellota 230 kV

Page 10: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO PublicSlide 10

Year Category Limiting Facility ContingencyLCR (MW)

(Deficiency)

2025 P2-4

Stanislaus –

Melones –

Riverbank Jct line

Tesla 115 kV bus674

(55 NQC/67 Peak)

2025 P6Tesla – Vierra 115

kV line

Schulte – Lammers and

Schulte-Kasson-

Manteca 115 kV lines

431

(122 NQC/134 Peak)

Total LCR Need in 2025741

(122 NQC/134 Peak)

Tesla - Bellota Sub-Area : Requirements (2025)

Manteca 115 kV

Legend: 115 kV

Kasson 115 kV

Vierra 115 kV

Schulte

Tesla 115 kV

Tracy

Salado 115 kV

Ingram Creek 115 kV

G

GWF Tracy Units

LammersX

X

Melones 115 kV

Bellota 115 kV

Riverbank115 kV

Tulloch115 kV

Stanislaus115 kV

Ripon 115 kV

Riverbank JCT

115 kV

Bellota 230 kV

Page 11: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Tesla - Bellota Sub-area: Load Profiles

Slide 11

Page 12: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public Slide 12

Sub-area2020 2021

Load LCR Load LCR

Lockeford 190 97 (73) 194 36 (12)

Weber 238 26 243 N/A

Stanislaus N/A 179 N/A 205

Tesla - Bellota 848 1,117 (543) 898 1,219 (658)

Total 1,275 1,241 (616) 1,349 1,255 (670)

LCR increases in sub-areas are mostly due to load increase. The LCR decreases

in sub-areas are due to the change in criteria.

N/A=Flow-through area. No defined load pocket or not an LCR sub-area anymore

Changes from 2020 to 2021

Page 13: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Changes from 2024 to 2025

Slide 13

Reduction in total LCR is due to transmission development or some sub-areas not

being an LCR sub-area anymore due to change in LCR criteria.

N/A=Flow-through area. No defined load pocket.

Sub-area2024 2025

Load LCR Load LCR

Lockeford 193 102 (78) 198 N/A

Weber 238 26 247 N/A

Stanislaus N/A 185 N/A 213 (1)

Tesla - Bellota 899 881 (260) 950 741 (134)

Total 1,330 1,009 (338) 1,395 741 (134)

Page 14: 2021 & 2025 Final LCR Study Results Stockton Area · 2021 & 2025 Final LCR Study Results Stockton Area Ebrahim Rahimi Lead Regional Transmission Engineer Stakeholder Call April 13,

ISO Public

Stockton Area Total LCR Need

Slide 14

Study YearExisting Generation

Capacity Needed (MW)Deficiency (MW) Total MW Need

2021 585 670 1,255

2025 607 134 741