2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital...
Transcript of 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital...
![Page 1: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/1.jpg)
AIM: HGM
2018 Annual Results
and Project Update
April 2019
![Page 2: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/2.jpg)
Disclaimer
Certain statements within this presentation constitute forward looking statements. Such forward looking statements involve risks and
other factors which may cause the actual results, achievements or performance of the Group to be materially different from any
future results, achievements or performance expressed or implied by such forward looking statements. Such risks and other factors
include, but are not limited to, general economic and business conditions, changes in government regulations, currency fluctuations
(including the US$/RUR rate), the gold price, the Group’s ability to recover its reserves or develop new reserves, competition,
changes in development plans and other risks.
There can be no assurance that the results and events contemplated by the forward looking statements contained in this
presentation will, in fact, occur. These forward-looking statements are correct or represent honestly held views only as at the date of
delivery of this presentation.
The Company will not undertake any obligation to release publicly any revisions to these forward looking statements to reflect
events, circumstances and unanticipated events occurring after the date of this presentation except as required by law or by
regulatory authority.
***
Total cash costs include mine site operating costs such as mining, processing, administration, royalties and production taxes, but are
exclusive of depreciation, depletion and amortisation, capital and exploration costs. Total cash costs are then divided by ounces sold
to arrive at the total cash costs of sales. This data provides additional information and is a non-GAAP measure.
In line with guidance issued by the World Gold Council, the formula used to define all-in sustaining cash costs measure commences
with total cash costs per ounce sold and then adds sustaining capital expenditures, corporate general and administrative costs, mine
site exploration and evaluation costs and environmental rehabilitation costs. This data seeks to represent the total costs of producing
gold from current operations, and therefore it does not include capital expenditures attributable to projects or mine expansions,
exploration and evaluation costs attributable to growth projects, income tax payments, interest costs or dividend payments.
2
![Page 3: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/3.jpg)
Highland Gold Today
3
Russia
Kazakhstan
Four Operating Mines
with 290-300 koz
Annual Production1
2018: 270 koz
Pipeline of High-Grade
Development
Projects
Low-Cost Producer
with AISC of
US$ 682 per oz2
Strong track record of
paying dividends
1. Guidance for 2019 production of gold and gold equivalent
2. Figures for FY 2018
Chukotka
Cluster
Khabarovsk
Cluster
Baikal
Cluster
Kyrgyzstan
Unkurtash
Mongolia
China
Novo
Baley Hub Taseevskoye, ZIF-1,
Sredny Golgotay
MNV Belaya Gora
Blagodatnoye
Klen
Kekura
Valunisty
Kayen
Operating Mines
Development Projects
![Page 4: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/4.jpg)
2018 Results Highlights
► 2018 production within guidance range of
265-275k oz.
► A strong operational year at MNV plus
completion of a new JORC-compliant
reserve audit that extended the project's
life of mine to 2029
► Belaya Gora output rose driven by better
recoveries, and a pre-feasibility study was
published regarding upgrades to the
processing plant and the processing of ore
from the nearby Blagodatnoye deposit
► Novo 1.3 Mtpa expansion continues in
order to offset expected decrease in
grades
► Costs remained stable despite growth in
expenses for fuel, energy, and labour
► The acquisition of the Valunisty mine and
related properties closed in December
2018
► Construction of the Kekura project
commenced following the completion of a
definitive feasibility study
4
2017 2018
Production (Oz gold and gold eq.)
272,274 269,500
All-in sustaining costs (US$/oz)
664 682
Total cash costs (US$/oz)
507 506
Revenue (US$ k)
316,682 311,153
EBITDA (US$ k)
155,275 153,060
Net profit (US$ k)
65,855 56,084
Net cash flow from
operations (US$ k)
130,990 136,247
Capital expenditure (US$ k)
58,336 62,347
Net debt*
(US$ k) (198,320) (194,286)
* On 01 Jan. 2019, excluding Valunisty debt
![Page 5: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/5.jpg)
Commitment to Dividends
5
2.9%
6.2% 6.3%
7.7%
9.6%
9.8%
6.5%
9.1%
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
US$ M
US$
per oz
* Based on the average share price for the period.
25.7
40.3
26.7 23.2 21.8
42.5 45.5
58
2011 2012 2013 2014 2015 2016 2017 2018
Highland Gold paid US$ 215
in dividends per oz produced
in 2018 and US$ 134 per oz
produced since 2011
Total dividends of
GBP 0.134 per share declared
for 2018, representing a yield
of 9.1%*
Future dividends secured by
dividend policy, which sets
target minimum payout of
20% of net operating cash
flow before capex.
114 89 83 163 169 215 140 186
Dividends Paid
Dividend Yield*
![Page 6: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/6.jpg)
Our Strategy: Unlocking Value
6
Focus
corporate
development
on regions
of presence
Develop
assets at the
PFS/DFS
stage into
production
De-risk and
convert
additional
resources
into reserves
Focus on
operational
efficiency
and
continuous
improvement
Strengthen
commitment
to workplace
safety and
protecting
the
environment
Maximise
the upside
potential
of operating
assets
Control
Costs Returns to
Shareholders
Deliver
Growth
![Page 7: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/7.jpg)
Valunisty: Value-Accretive Acquisition
7
In December 2018, Highland Gold acquired the Valunisty mine and related assets for US$ 85.9 M* in shares and assumed debt.
Key Advantages:
► Located in an existing operating region, Chukotka
► Increases annual production by 11%
► Acquisition was value-accretive for shareholders
Assets Purchased:
► Valunisty: an established, operating mine
► KAP: 831 km2 licence surrounding Valunisty, with several satellite deposits and exploration targets including the recently-commissioned Gorny mine
► Kayen: 1,214 km2 exploration area located 130 km from Kupol, the second largest gold mine in Russia
Upside Potential:
► Move to underground to reach higher-grade ore
► Processing plant expansion to 350 ktpa
► Substantial opportunities for resource-to-reserve conversion on KAP licence
1. JORC-compliant Resources and Reserves for Valunisty & KAS as of 01 Jan. 2019 incl. silver
2. FY 2018 estimated
Start Date 1999
Life of Mine 2028
Mine Type Open pit (+ underground)
Processing Gravity + cyanide leaching
Processing Capacity 250 ktpa
Au eq Resources (M,I&I)1 1.67 Moz @ 3.0 g/t
Au eq Reserves (P&P)1 503 koz @ 5.2 g/t
Au eq Production (2018) 38 koz
Avg Head Grade/Recovery 4.7 g/t | 96%
Total Cash Costs2 US$ 752/oz
Valunisty
* US$ 68.13 M in shares issued plus US$ 17.7 M in assumed debt as of closing
on December 27, 2018
![Page 8: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/8.jpg)
MNV: Extending Life of Mine
8
Start Date 1991 (HGM 1999)
Life of Mine 2029
Mine Type Open pit & underground
Processing Gravity + cyanide leaching
Processing Capacity 1.4 Mtpa
Au Resources (M,I&I)1 1.48 Moz @ 3.2 g/t
Au Reserves (P&P)1 787 koz @ 2.7 g/t
Au Production (2018) 113 koz
Avg Head Grade/Recovery 2.92 g/t | 92.3%
Total Cash Costs (2018) US$ 600/oz
Key Challenge:
► Finding additional reserves to extend the life of mine
(was 2018), to continue making use of existing
infrastructure and maintain production level
Solutions:
► Ongoing, extensive near-mine exploration
programme on existing MNV licences
► Acquisition of three adjacent greenfield licences
► Re-examining historic rock waste dumps
Capital Commitment:
► US$ 3-5 million per year
Status:
► Life of mine extended to 2029
► Nearly 600k oz Au added to reserves in 2017-2018
► Over 675k tonnes of ore at 1.09 g/t Au taken from
the rock waste dumps to the mill since 2016
► Near-mine exploration programme continues
1. JORC-compliant Resources and Reserves as of 01 Jan. 2019
Mnogovershinnoye (MNV)
![Page 9: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/9.jpg)
Novo: Capacity Expansion
9
Key Challenge:
► Increase throughput to offset an expected decline in
grades
Solution:
► Expand mining and processing capacity from 800k
tonnes/year to 1.3 million tonnes/year
Capital Commitment:
► US$ 10 million to complete Stage 1
Status:
► Stage 1 (mine capacity expansion) – most
infrastructure built or currently under construction
► Stage 2 (processing plant expansion) – in the design
phase, using ore sorting with X-ray transmission
(XRT)
► Commissioning expected in 2020
Start Date 2009
Life of Mine 2032
Mine Type Polymetallic, underground
Processing Gravity-flotation circuit
Processing Capacity 0.8 Mtpa
Au eq Resources (M,I&I) 1 2.72 Moz @ 3.8 g/t
Au eq Reserves (P&P)1 1.57 Moz @ 3.0 g/t
Au eq Production (2018) 113 koz
Avg Head Grade/Recovery 5.26 g/t | 80.1%
Total Cash Costs (2018) US$ 323/oz (US$ 399/oz)2
1. JORC-compliant Resources and Reserves as of 01 Jan. 2019
2. Including processing costs
Novoshirokinskoye (Novo)
![Page 10: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/10.jpg)
Belaya Gora: Mill Upgrade and Blagodatnoye
10
Start Date 2014
Life of Mine1 2032
Mine Type Open pit
Processing Gravity
Processing Capacity 1.6 Mtpa
Au Resources (M,I&I)1 2 1.35 Moz @ 1.4 g/t
Au Reserves (P&P)1 2 906 koz @ 1.4 g/t
Au Production (2018) 44 koz
Avg Head Grade/Recovery 1.13 g/t | 74.8%
Total Cash Costs (2018) US$ 724/oz
1. Including Blagodatnoye
2. JORC-compliant Resources and Reserves as of 01 Jan. 2019
Key Challenges:
► Increase recoveries at the processing plant
► Adding resources to extend life of mine (was 2023)
Solutions:
► Add a carbon-in-pulp (CIP) circuit to the processing plant to improve recoveries from the current 75% to a range of 86-91%
► Plan for processing ore from the nearby Blagodatnoye licence at the Belaya Gora mill
Capital Commitment:
► US$ 15 M estimated for the plant upgrade (2019-2020)
► US$ 21 M estimated to move mining activity to Blagodatnoye after 2023
Status:
► A PFS for the plant upgrade and mining of Blagodatnoye was completed in 2018
► The plant upgrade is in the design phase
► Exploration is also underway on the Belaya Gora flanks licence
Belaya Gora
![Page 11: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/11.jpg)
Kekura: Premier Development Project
Project Status
► Definitive Feasibility Study (DFS) published in 2018
► Several key infrastructure facilities (power substation, assay lab, fuel storage, shovel assembly, communications tower, roads) completed or under construction
► Camp and pilot processing plant already on site
Capital Commitment:
► US$ 229 M (pre-commissioning as per DFS)
Next Steps
► Stripping and preliminary ore mining in Q4 2019
► Full processing plant scheduled for completion by 2023
Upside Potential
► Included in the list of projects eligible for the government’s new Chukotka Advanced Special Economic Zone (ASEZ), which offers tax incentives that add more than US$ 100 million to NPV
► Exploration drilling commenced on several of 12 additional targets in the broader Kekura licence area to identify additional open pit reserves
11
Kekura
Est. Start Date 2023
Life of Mine 16 years
Mine Type Open pit & underground
Processing Gravity + cyanide leaching
Processing Capacity 0.8 Mtpa
Au Resources (M,I&I) 2.46 Moz @ 8.1 g/t
Au Reserves (P&P) 2.00 Moz @ 7.0 g/t
Au Production
(est. annual)
172k oz (years 1-8)
46k oz (years 9-16)
Total Cash Costs (est.) US$ 511/oz
![Page 12: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/12.jpg)
2018 Financial Review
12
![Page 13: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/13.jpg)
2018 Financial Highlights
13
2016 2017 2018
Gold and GE Production, koz 261 272 270
Revenue, USD m 306 317 311
Operating Profit (w/o impairment), USD m 92 102 109
Impairment Losses, USD m -23 0 0
EBITDA, USD m 162 155 153
STRONG BALANCE SHEET
Total Assets, USD m 1121 1142 1183
Total Equity, USD m 756 778 769
Net Debt, USD m 205 198 194
KEY RATIOS
TCC, USD / oz 454 507 506
AISC, USD / oz 652 664 682
Net Debt / EBITDA 1.3 1.3 1.3
EBITDA margin 53% 49% 49%
DIVIDENDS
Dividends paid during the year, USD m 31.7 43.9 49.6
Dividends declared during the year
Interim, GBP per share 0.050 0.050 0.060
2nd interim, GBP per share 0.054 0.050
3rd interim, GBP per share 0.024
Final, GBP per share 0.054
Total, GBP per share 0.104 0.104 0.134
Total Dividends declared for the year, USD m 41.8 45.5 57.8
All figures exclude the Valunisty acquisition
![Page 14: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/14.jpg)
Metals Prices and Exchange Rates
14
2016 2017 2018
Gold Price 1,247 USD/oz 1,259 USD/oz 1,258 USD/oz
▼-0%
Silver Price 17 USD/oz 17 USD/oz 15 USD/oz
▼-9%
Lead Price 1,815 USD/t 2,293 USD/t 2,299 USD/t
▲ 0%
Zinc Price 1,967 USD/t 2,809 USD/t 2,858 USD/t
▲ 2%
Copper Price 6,546 USD/t
n.a.
USD/RUB 66.8 58.3 62.9
▲ 8%
EUR/USD 1.1 1.1 1.2
▲ 4%
GBP/USD 1.4 1.3 1.3
▲ 3%
HGML Revenue Breakdown
6 8 15
10 14 13 12 18 14 12
16 16
1 333 1 334 1 326 1 334 1 304 1 282
1 238 1 202 1 199 1 215 1 221
1 250
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2018 Gold Price Dynamics Compared To The Volume Of Sales
Au sold by MNV and BG, koz LMBA average price, USD/oz
Novo 23%
Belaya Gora 18%
MNV 45%
14%
2018
Au
86%
Cu 1%
Zn 2%
Pb 5%
Ag 6%
Novo 27%
Belaya Gora 17%
MNV 41%
15%
2017
Au
85%
Zn 2%
Pb 6%
Ag 8%
2018 Gold Price vs Volume of Sales
Other
Metals
Other
Metals
![Page 15: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/15.jpg)
Low Cost, High Margin Producer
All-In Sustaining Costs
US$/oz (2018)
Source: Company data
Highland Gold’s EBITDA Margin: 49%
15
International Majors
Russian Companies
1309 1231
1057 1057 1051 1051 994 981 965 945
909 889 884 877 866 861 851 843 835 806
682 679 605
0
200
400
600
800
1000
1200
1400
![Page 16: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/16.jpg)
TCC & AISC
16
HGML TCC was flat at USD 506/oz. The positive effect of the weaker rouble
(-8%) was offset by a 5% increase in MNV’s share of the volume of sales,
replacing less costly Novo ounces
MNV TCC decreased by 3% as the share of processed low-grade ore from waste
dumps fell from 24% to 1%, thus increasing head grade at the mill by 15%
Belaya Gora TCC decreased by 16%, mainly due to the lower share of ore from
stockpiles used in processing (23% in 2018 compared to 78% in 2017)
Novo TCC decreased by 8% due to a change in contract terms and conditions
(-USD 66 per oz in processing costs)
HGML AISC increased slightly to USD 682/oz due to increases in G&A (+9%)
and supporting CAPEX (+25%)
617 600
2017 2018
861
724
2017 2018
291 323
141 75
2017 2018
432
507 506
2017 2018
Total Cash Costs
664 682
H1 2017 H1 2018
399
-0%
-16%
-8%
+3%
TCC by Operating Asset Total Cash Costs
All-In Sustaining Costs
-3%
HGML, US$/oz MNV, US$/oz Belaya Gora, US$/oz Novo, US$/oz
HGML, US$/oz
Processing costs (US$/oz)
![Page 17: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/17.jpg)
EBITDA
17
G&A -15
G&A -16
G&A -18
Novo 96
Novo 92 Novo
77
BG 26 BG
17 BG 23
MNV 55 MNV
62 MNV 69
Other 2
162 155 153 11.7
2.2
0.5 5.7 6.8
2.6
2016 2017 ExchangeRate
MetalPrices
Volume ofSales
Costs G&A Other 2018
G&A Costs Volume
of Sales
Metal
Prices
Exchange
Rate
+ US$ 4.9 m - exchange rate effect
- US$ 0.2 m - lower Au prices
+ US$ 6.0 m - increase in volume of sales (+10%)
- US$ 3.1 m - increase in cost of sales
+ US$ 3.2 m - exchange rate effect
- US$ 0.1 m - lower metal prices
- US$ 11.6 m - decrease in the volume of sales (-13%)
- US$ 7.3 m - increase in cost of sales
+ US$ 2.5 m - exchange rate effect
- US$ 0.1 m - lower Au prices
- US$ 0.3 m - decrease in the volume of sales (-2%)
+ US$ 3.5 m - decrease in cost of sales
+ US$ 1.1 m - exchange rate effect
- US$ 2.6 m - increase in G&A costs
Other
Income
![Page 18: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/18.jpg)
Capital Expenditure
MNV
► USD 8.5 m – supporting investments: replacing worn-out equipment and
capital construction
► USD 2.8 m – exploration work and reserves estimations
► USD 1.6 m – regulatory filings and design work for a new tailings dam
► USD 2.6 m – capital development
► USD 5.2 m – capitalized ore bodies
Novo
► USD 2.8 m – supporting investments (replacement of worn-out equipment) and
design work for a new tailings dam
► USD 3.6 m – capital development
► USD 7.2 m – 1.3 Mtpa Expansion Project
Belaya Gora
► USD 1.0 m – supporting investments
► USD 2.1 m – exploration work
► USD 1.8 m – design work for new tailings dam and PFS for Blagodatnoye
Kekura
► USD 8.2 m – field camp and road maintenance , G&A
► USD 2.9 m – exploration work
► USD 2.9 m – purchases of fuel and equipment for plant-120
► USD 1.9 m – DFS and other research work
► USD 1.6 m – capital construction of the power substation
Baley Hub
► USD 0.6 m – exploration and research work
► USD 1.9 m – site maintenance
Development Projects - Highland Exploration (Unkurtash), Klen, Lyubov
► Minimal investments only to meet license commitments
18
US$ k, excl. VAT 2017 2018
KHABAROVSK CLUSTER 17,690 25,434
Mnogovershinnoye 13,872 20,659
Belaya Gora 3,818 4,775
BAIKAL CLUSTER 16,462 16,332
Novo 13,518 13,697
Taseevskoye 2,782 2,527
Lyubov 162 108
CHUKOTKA CLUSTER 22,532 18,749
Kekura 22,368 17,665
Klen + VK area 163 1,084
OTHER 1,652 1,834
Highland Exploration 1,456 1,088
Other 195 744
Total 58,336 62,347
![Page 19: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/19.jpg)
Debt Portfolio
Debt Status as at 31.03.2019
► Gross debt: $222 m
► Net debt: US$ 201
► Effective interest rate: 4.19%
► Average tenor: 21 months
► US$ 490 m of undrawn
revolving credit facilities
► Net Debt/EBITDA ratio: 1.3
19
By Lender By Interest Rate By Term
60% Short-Term
40% Long-Term
77% Fixed
23% Floating
15% Rosba
nk
48% Unicre
dit
27% Raiffei
sen
10% Sberba
nk
212 208 232 222 206 199 194 201
4.54%
3.44%
4.20% 4.19%
0.77%
1.56%
2.50% 2.49%
31.12.2016 31.12.2017 31.12.2018* 31.03.2019
Gross Debt (US$ M)
Net Debt (US$ M)
Interest Rate
Libor 1M US$
Debt Breakdown
* Excluding US$ 17.7 m of Valunisty
debt @ 5.12% assumed on
27.12.2018 and repaid in Q1 2019
![Page 20: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/20.jpg)
2019 Outlook
20
![Page 21: 2018 Annual Results and Project Update · Re-examining historic rock waste dumps Capital Commitment: US$ 3-5 million per year Status: Life of mine extended to 2029 Nearly 600k oz](https://reader033.fdocuments.us/reader033/viewer/2022051815/603d47657d3ce438d4043e05/html5/thumbnails/21.jpg)
Key Targets for 2019
►2019 production forecast: 290,000-300,000 oz gold & gold equivalent
►Continue to advance projects designed to improve operations at existing mines:
– Near-mine exploration at MNV and adjacent licences
– Construction on Stage 1 (mine) and design work for Stage 2 (mill) of Novo expansion
– Design work for processing plant upgrades at Belaya Gora
►Ramp-up construction at Kekura
– Begin initial stripping and mining in Q4 2019
► Integrate the recently-acquired Valunisty mine and related operations and begin studies
on potential upgrades to its operations
►Capital Expenditure Budget: US$ 116 million
– About 50% of capex for Kekura
►Roll-out new programmes for health & safety, operational efficiency and continuous
improvement across each of the Company's operating units 21