2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC)...

24
2017 (FY 21,22,23) Ohio CMAQ Project Selection Executive Committee September 14, 2017

Transcript of 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC)...

Page 1: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

2017 (FY 21,22,23) Ohio CMAQ

Project SelectionExecutive Committee

September 14, 2017

Page 2: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Eligible Applicants• Cities

• Counties

• Port Authorities

• Transportation Improvement Districts (TID)

• Transit Authorities

• Other units of government eligible to sign contracts with ODOT

• Public Private Partnerships

Page 3: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Eligible Activities� FHWA capital funding program

� Must be spent on transportation projects in air quality nonattainment or maintenance areas and demonstrate emissions reduction. Air quality area includes Butler, Clermont, Hamilton and Warren

� OKI limits funding to urbanized area only

� 20% local match

� Categories

� Demand Management

� Transportation Control Measures

� Intelligent Transportation Systems

� Pedestrian and Bicycle Programs

� Shared Ride

� Traffic Flow Improvements

� Transit Improvements

� Freight/Intermodal

Page 4: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Ohio Statewide Urban CMAQ Committee (OSUCC)

� Statewide process for 8 largest MPO’s in Ohio

� Developed statewide process and application

� Cost effectiveness in reducing congestion and vehicle emissions is a priority

Page 5: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

� Call for FY 2021-2023

� 14 applications received

� $34 million requested

� $35 M available based OKI annual allocation prior to statewide

program

Funding Available

Page 6: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

OSUCC Scoring (100 points max)Criteria Max Points

Available

1 Project Type 10

2 Cost Effectiveness (per emission reduced) 20

3 Other Benefits (safety, fixed route transit, bike/ped, freight EJ) 10

4 Existing Modal Level-of-Service 15

5 Positive Impact on Level-of-Service 15

6 Status of Project 10

7 Non-Federal Match of Requested CMAQ Funds 10

8 History of Project Delivery (0, -5 or -10 point deduction) 0

9 Regional Priority 10

Page 7: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

ScheduleDate Action

April 2017 Call for Projects

May 9, 2017 CMAQ workshop

June 30, 2017 Applications due

August 8, 2017 Prioritization subcommittee meeting

September 12, 2017 ICC Recommended Approval

September 14, 2017 Executive Committee Approval

September 15, 2017 Projects submitted to OSUCC

By November 30, 2017 OSUCC identifies the recommended program of projects

By December 31, 2017 MPO Executive Directors approve projects for funding

Application OKI Staff Scoring

Prioritization Subcommittee ICC/OKI

Board OSUCCMPO

Executive Directors

Page 8: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Roundabouts at

Eastgate Square

Drive, Glen Este-

Withamsville Rd

(west) and Glen

Este-Withamsville

Rd (east)

• Amount

Requested:

$5,000,000

Clermont Co TID-Aicholtz Rd Roundabouts

Page 9: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Provide new connection between Babson Place

and Hetzel Street

• Amount Requested: $2,860,000

• New capacity is not CMAQ eligible

• Not recommended

Cincinnati-Babson Extension

Page 10: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Multi-modal transportation facility

with Metro fixed route bus hub with

amenities.

• Amount Requested: $6,600,000

Cincinnati-Uptown SMART Center

Page 11: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Dedicated crossing for

pedestrian and bicycle

movement across River

Road and the railroads

where none exists today.

• Amount Requested:

$923,460

Cincinnati-Thornton Av Improvements

Page 12: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Extend existing southbound drop

lane and add additional turn lane

for ramp to WB I-275

• Amount Requested: $784,000

Fairfield-Gilmore/I-275 Ramp

Page 13: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Construct 12’ wide

multi-use trail from

the existing trail

termini north of

Beechmont

Avenue, crossing

Little Miami River

via new bridge

utilizing existing

bridge

foundations.

• Amount

Requested:

$4,320,000

Great Parks-Little Miami Trail Beechmont

Page 14: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Construct a paved multi-use path from the

existing path at the intersection of Deerfield and

East St. to existing trail at the YMCA. Extend

path south to Turtlecreek Union Road and over

Byp 48 to Bike Park.

• Amount Requested: $927,755

Lebanon-Countryside YMCA Trail

Page 15: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Convert two existing stop-controlled “T” intersections (US42 @ Bethany and US42 @

Mason-Morrow-Millgrove Rd) to roundabouts. Construct a multi-use path.

• Amount Requested: $2,751,535

Mason-US42 Roundabouts

Page 16: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Replace the existing 4-way stop at Pfeiffer and Deerfield with a roundabout

• Amount Requested: $893,575

Montgomery-Pfeiffer Rd @Deerfield Rd Roundabout

Page 17: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Upgrade traffic

signal system with

new equipment and

software.

• Amount Requested:

$923,287

Mt.Healthy-Upgrade Signals

Page 18: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Add turn lanes and

upgrade signals with

interconnection at

the two

intersections of

US50 and SR132.

• Amount Requested:

$1,572,123

Owensville-SR 132 and US 50 intersections

Page 19: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Segment D, Chestnut

Connector, Segment B

east and High School

Connector.

• Amount Requested:

$1,500,000

Oxford-Oxford Area Trail Phase 3

Page 20: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Upgrade signals at

Highland Avenue,

Sampson Lane and

Elwynne Drive.

Retrofit signal at

Plainfield. Access

Management

improvements.

• Amount Requested:

$2,374,845

Silverton-Montgomery Road Signals

Page 21: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

• Replacement of ten 40’

diesel buses.

• Amount Requested:

$3,103,400

SORTA-Bus Replacements

Page 22: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Scoring ResultsProject Name Total Points

Owensville-SR 132 and US 50 Intersection Improvements 80

SORTA-Transit Rolling Stock Replacement 77

Mt. Healthy-Signal System 66

Mason-US 42 Roundabouts 59

Fairfield-South Gilmore/I-275 Ramp "Y" Improvements 56

Montgomery-Pfeiffer Road and Deerfield Road Roundabout 56

Cincinnati-Uptown SMART Center 54

Hamilton County-Great Parks Little Miami Scenic Trail-Beechmont Connector 54

Silverton-Montgomery Road Corridor Improvements 40

Clermont County TID-Aicholtz Rd Roundabouts 37

Cincinnati-Thorton Avenue Improvements 35

Lebanon-Countryside YMCA Trail Extension and Realignment 35

Oxford-Area Trail Phase 3 31

Page 23: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Regional Priority (10 pts)Measure Points

First Priority Project 10

Second Priority Project 7

Third Priority Project 4

Fourth Priority Project 2

All Other 0

Page 24: 2017 (FY 21,22,23) Ohio CMAQ Project Selection...Ohio Statewide Urban CMAQ Committee (OSUCC) Statewide process for 8 largest MPO’s in Ohio Developed statewide process and application

Draft Funding PlanProject Name Phase CMAQ $ Requested

Clermont County TID-Aicholtz Rd Roundabouts CO $5,000,000

Cincinnati-Uptown SMART Center CO $6,600,000

Cincinnati-Thornton Avenue Improvements CO $923,460

Fairfield-South Gilmore/I-275 Ramp "Y" Improvements CO$784,000

Hamilton County-Great Parks Little Miami Scenic Trail-Beechmont Connector CO$4,320,000

Lebanon-Countryside YMCA Trail Extension and Realignment CO$927,755

Mason-US 42 Roundabouts RW & CO 2,771,535

Montgomery-Pfeiffer Road and Deerfield Road Roundabout CO$893,575

Mt. Healthy-Signal System CO $923,287

Owensville-SR 132 and US 50 Intersection ImrpovementsPE, DD, RW

& CO $1,572,123

Oxford-Phase 3 Chestnut Fields Connector CO $1,500,000

Silverton-Montgomery Road Corridor Improvements RW & CO$2,374,845

SORTA-Transit Rolling Stock Replacement CO $3,103,400

TOTAL REQUEST $31,673,980