2017 FEDERAL RESEARCH CENTER MASTERPLAN PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT SEPTEMBER 12, 2017

Transcript of 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL...

Page 1: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

2017 FEDERAL RESEARCH CENTER MASTERPLANPRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORTSEPTEMBER 12, 2017

Page 2: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.122

1. PROGRAM ASPIRATIONS

• Create a collegial environment to foster scientific interaction

• Create opportunities for constant, creative interchange and collaboration

• Create an image of scientific excellence, vigor and dignity.

• Create an image of the FDA as a leading scientific institution for attraction and retention

• Create state-of-the-art work spaces

• Create efficiencies through shared use

• Reduce Travel times for meetings and conferences

• Reduce dependence on leased facilities

Page 3: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

32017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

Sustainability goals and objectives:

• Executive Order 13693 – Planning for Federal Sustainability in the Next Decade - “reduce agency direct greenhouse gas emissions by at 40% over the next decade”

• Executive Order 13653 - Climate Change Risk Mitigation and Resiliency

• Executive Order 13693 - Stormwater Management

• Executive Order 13508 - Federal Leadership in Chesapeake Bay Protection and Restoration

• FDA’s Agency Sustainability Plan

• EISA 438 - Storm water runoff requirements for federal development projects

• MD MDE MS4 Permit - General Permit for Discharges from State and Federal Small Municipal Separate Storm Sewer Systems

STRATEGIES – assuming major implementation is 10 years out of the Master Plan:

• LEED Gold

• Energy Net Zero Buildings

• Water Net Zero

• SITES Silver

SUSTAINABILITY

Page 4: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

42017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

2. SPACE / POPULATION

EXISTING LABORATORY AND OFFICE GROSS SQUARE FOOTAGE (GSF)• 3.8 million GSF

PROPOSED ADDITIONAL OFFICE GROSS SQUARE FOOTAGE (GSF)• 1.6 million GSF (approx.)

EXISTING CAMPUS POPULATION• 12,855 people

PROJECTED CAMPUS POPULATION• up to approximately 18,000 people

CURRENT PEAK DAILY CAMPUS POPULATION• 7,793 people

Page 5: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

52017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

3. PROJECT SCHEDULE

NHPA• NHPA Initiation : • Consulting Party Meetings :• Programmatic Agreement:

NEPA• Notice Of Intent:• Scoping Public Meeting : • End of Public Scoping Period: • Draft EIS : • Final EIS :• Record of Decision :

Master Plan• Draft MP Submission/Hearing: • Final MP Submission/Hearing:

TMP• Draft TMP Complete:• Final TMP Complete:*TMP Submitted with Master Plan and EIS to NCPC

August 2017 Fall 2017 – Spring 2018Summer 2018

August 18, 2017September 12, 2017September 25, 2017Spring 2018Summer 2018Fall 2018

Spring 2018 / June 2018Fall 2018 / December 2018

January 2018June 2018

Page 6: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

62017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

The Enclave Apartments19 Floors R-H ZONING

White Oak Shopping Center CR ZONING 200’ Height

Viva White Oak CR ZONING 220’ Height

White Oak Tower23 Floors

4. EXISTING CONDITIONS

Page 7: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

72017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

MASTERPLANDEVELOPMENT

1997 Master Plan 2002 Master Plan

2006 Master Plan 2009 Master Plan

Naval Ordnance Laboratory

Naval Ordnance Laboratory

SECTION 3. EXISTING CONDITIONS

Page 8: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

82017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

AREA OF POTENTIAL EFFECT MAP

2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER AREA OF POTENTIAL EFFECT MAP

LEGEND

AreaofPotentialEffect

Building One

Flagpole Environmental Setting

FDA Campus Boundary

NavalOrdnanceLaboratoryNationalRegisterDistrictBoundary

Page 9: 2017 FEDERAL RESEARCH CENTER MASTERPLAN€¦ · 12/9/2017  · 2017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER 3 PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12 Sustainability

92017 MASTERPLAN | FDA FEDERAL RESEARCH CENTER PRELIMINARY DRAFT DEVELOPMENT ALTERNATIVES REPORT 2017.09.12

5. DEVELOPMENT AREAS AND CONSTRAINTS

Existing Campus, Stream Valleys, and Land Bays.

100 Area

200 Area

400 Area 300

Area600 Area

500 Area

700 Area