Utility scale solar PV projects Explore our Precedent Project ...
2016 Utility Service Board Projects
-
Upload
city-of-portage -
Category
Documents
-
view
216 -
download
2
description
Transcript of 2016 Utility Service Board Projects
West Side Interceptor Rehab/Redundancy • Interceptors receive accumulated sewage from sewer branches
• This project will repair the existing 45-year old interceptor
• Implementation of 2010 report from StructurePoint
• A parallel interceptor will be constructed under the CSX RR and Hwy 20
• This interceptor collects wastewater for nearly the entire sewer service area, which includes Portage and several other contributors
Wastewater Treatment Plant
Treatment Plant Bio-solids • Bio-solids are the organic materials resulting from treated sewage
• This project will expand and improve our bio-solids system
• Implementation of 2010 report from StructurePoint
• 13% increase in capacity- Essential for continued growth within City
• Preparation for additional development
WWTP Field Crew Facility • This project will relocate the sanitary field crew from a facility at the Street Department to
the wastewater treatment plant • Additional storage for new equipment • Allows Street Department to utilize the existing facility
Cost: $3,750,000
2
• Based on 2007/2012 DLZ Building Assessment
• New Utility Service Board and City Council Chambers
• Utility Department office space
City Hall/USB Office Improvements
• Additional parking
• Elevator
• ADA Accessibility
Cost: $2,000,000
3
• Project is local match for widening/modernizing Central Avenue
• Hamstrom Road to Scott Street
• Since 2007 the City has invested approximately $750k for design and right-of-way purchases in preparation for construction
Central Avenue East
Cost: $1,300,000
4
• Project will eliminate flooding on Willowcreek Road south of U.S. Hwy 6
• Create development opportunities along Willowcreek Road
• Combined DLZ & SEH study with ongoing design work
Willow Creek Headwaters Regional Detention System
Cost: $1,250,000 plus land acquisition
5
Expansion
Existing Location
To Lakefront Park
SR 249
• Expand and improve existing North Side compost facility
• Current site with poor drainage and infrastructure affecting composting operations
• County is now paying for limb mulching with an understanding that the site will be upgraded and open to public
Compost Site Expansion
Cost: $250,000
6
PHS
• Relocate ditch along east side of Airport Road between Lute Road and Sandalwood Subdivision
• Improve east side of Airport Road for safety and stormwater management
Airport Road Ditch Relocation
Cost: $500,000
7
Project Type
• Drainage rehabilitation
• Pavement rehabilitation
• Slip lining
Neighborhood Locations
• Poplar, Plaza, Lancer Street
• Parker, Danube, Bryant Reconstruction
Neighborhood Projects
Cost: $1,500,000
8
• The projects total $10.5M
• The Utility Service Board has a bonding capacity of $18M with the rate increase
• The intent is to keep the bond below $10M
• Some projects or project components can be removed from the bond and “cashed” without affecting bonding rates or capacity to keep bond at $9.5 to 9.95M
Proposed Bond
9