2016 Performance Review Report - · PDF fileContents i SSDP 2016 Performance Review Report...
Transcript of 2016 Performance Review Report - · PDF fileContents i SSDP 2016 Performance Review Report...
Contents
i SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
Glossary and Definition of Terms _________________________________________ 1
1. Introduction ____________________________________________________ 3
1.1 Environmental Approval _________________________________________________ 3
1.2 Report Objective _______________________________________________________ 3
2. Environmental Factors, Risks and Impacts _____________________________ 4
2.1 Key Environmental Factors _______________________________________________ 4
2.2 Key Risks and Impacts __________________________________________________ 4
3. Environmental Monitoring Framework ________________________________ 6
3.1 Environmental Quality Objectives __________________________________________ 6
3.2 Marine Environment Monitoring Programs ___________________________________ 6
3.2.1 Marine Environment Monitoring Program _________________________________ 6
3.2.2 Dissolved Oxygen Monitoring Program __________________________________ 6
3.2.3 Diffuser Performance Monitoring Program ________________________________ 7
3.2.4 Whole Effluent Toxicity Monitoring Program ______________________________ 7
3.3 Revegetation Management Plan ___________________________________________ 7
4. Environmental Performance ________________________________________ 9
4.1 Benthic Health Monitoring _______________________________________________ 13
4.2 Greenhouse Gas Emissions ______________________________________________ 13
5. Benchmarking, Best Available Technology and Improvements in Environmental Management ________________________________________________________ 14
5.1 Diffuser Re-orientation _________________________________________________ 14
5.2 Backfilling ___________________________________________________________ 14
5.3 Seawater Recirculation _________________________________________________ 14
5.4 Diffuser Capping ______________________________________________________ 14
6. Conclusion _____________________________________________________ 16
Appendix 1 – Ministerial Statement 792 __________________________________ 17
Appendix 2 – Report and recommendations of the EPA Report 1302 ____________ 17
Appendix 3 – Marine Environment Monitoring Program _______________________ 17
Appendix 4 – Dissolved Oxygen Monitoring Program_________________________ 17
Appendix 5 – Diffuser Performance Monitoring Program ______________________ 17
Appendix 6 – Whole Effluent Toxicity Monitoring Program ____________________ 17
Appendix 7 – Revegetation Management Plan ______________________________ 17
Appendix 8 – 2015 Marine Environment Monitoring Annual Report ______________ 17
Appendix 9 – 2016 Marine Environment Monitoring Annual Report ______________ 17
Appendix 10 – Letter from OEPA acknowledging completion of dissolved oxygen monitoring _________________________________________________________ 17
SSDP 2016 Performance Review Report
1 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
Glossary and Definition of Terms Actual Dilution The Actual Dilution achieved at the SSDP LEPA boundary is calculated from the results of the Diffuser
Performance Monitoring Program. The method to calculate the Actual Dilution is provided in Section
3.3.3 of the DPMP.
Bottom Saline Layer The bottom saline layer is the whole bottom saline layer, a layer of higher salinity to that of the
background salinity. The layer commences at the first salinity reading above the background salinity.
DER Department of Environment Regulation (previously Department of Environment and Conservation)
Desalination Effluent Desalination effluent consists of the brine stream from the RO system, neutralised clean-in-place (CIP)
streams and wastewater originated from the backwash of the membrane filters and seawater strainers.
The desalination effluent is discharged to the marine environment via a 320m diffuser array.
DPMP Diffuser Performance Monitoring Program (Revision D, 2015)
DO Dissolved Oxygen
DOMP Dissolved Oxygen Monitoring Program
Environmental
Quality Objectives
The Environmental Quality Objectives identified by the OEPA and specified in MS792 Schedule 1 for the
marine environment surrounding the SSDP ocean diffuser.
EPA Environmental Protection Authority
Full Production Full Production of the SSDP is the combined Stage 1 and Stage 2 operations, which produces 100GL of
drinking water per year.
GL Gigalitres
IWSS Integrated Water Supply Scheme
Key Environmental
Factors
The Key Environmental Factors identified as relevant to the construction and operation of the SSDP in
the Report and recommendations of the Environmental Protection Authority (EPA) (Appendix 2 – Report
and recommendations of the EPA Report 1302).
LEPA Low Ecological Protection Area
Marine Environment
Monitoring
Environmental monitoring undertaken in the marine environment as per the MEMP, DOMP, DPMP and
WETMP.
MEMP Marine Environmental Monitoring Program, including Discharge Water Quality Monitoring and Benthic
Health Monitoring.
MF Membrane Filtration
MS792 Ministerial Statement 792
NOEC No Observed Effect Concentration
OEPA Office of the Environmental Protection Authority
OEMF SSDP Operation Environmental Management Framework developed to address MS792 requirements.
ppt Parts per thousand
Recirculation Seawater entering through the seawater intake pipelines is recirculated directly back into the
desalination effluent diffuser pipeline to increase on-shore dilution prior to diffusing into the marine
environment.
RMP Revegetation Management Plan
RO Reverse Osmosis
SSDP Southern Seawater Desalination Plant
SSWA Southern Seawater Alliance
Target Dilution The minimum number of dilutions required to meet the ANZECC (2000) 99% species protection trigger
at the boundary of the LEPA as per the latest valid WET testing results provided by the WET testing
consultant. The 99% species protection trigger is theoretical or statistically inferred based on the results
of sub-lethal toxicity testing and species sensitivity distributions.
WET Whole Effluent Toxicity
SSDP 2016 Performance Review Report
2 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
WETMP Whole Effluent Toxicity Monitoring Program
Worst Case Dilution The Worst Case Dilution achieved at the SSDP LEPA boundary can be calculated from the Actual Dilution
results of the Diffuser Performance Monitoring Program (salinity monitoring). If the number of marine
salinity monitoring events (n) is less than 20, then the worst dilution result calculated for all of the
salinity monitoring events in the reporting period will be used to represent the Worst Case Dilution. If
the number of marine salinity monitoring events (n) is greater than 20 then the lower 5th percentile of
the dilution results calculated for all of the salinity monitoring events in the reporting period will be used
to represent the Worst Case Dilution.
SSDP 2016 Performance Review Report
3 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
1. Introduction
The Southern Seawater Desalination Plant (SSDP) consists of offshore marine infrastructure
(intake and diffuser systems) and onshore infrastructure (treatment and storage infrastructure)
on Taranto Road, Binningup, WA. Drinking water is supplied to Water Corporation’s Integrated
Water Supply Scheme (IWSS) via a storage tank facility near Harvey.
The SSDP was designed and constructed in two stages, each capable of producing 50 GL of
water annually. Stage 1 of the plant began commercial operations on the 12 March 2012. Stage
2 was commissioned on 17 January 2014. The combined plant is capable of producing 100GL of
drinking water annually.
1.1 Environmental Approval
In July 2007 Water Corporation referred the proposal to construct and operate the SSDP to the
Minister for Environment for assessment under Section 38 of the Environmental Protection Act
1986. It was formally assessed at the level of Public Environmental Review under the State
process. The Proposal was approved by the Minister for Environment, with Ministerial Statement
792 (MS792) published on the 14 April 2009 (provided in Appendix 1 – Ministerial Statement
792). The approval acknowledged that construction and operation of the desalination plant will
have an impact on the marine environment.
The project was referred to the Commonwealth Department of Environment, Water, Heritage
and the Arts (now Department of the Environment) for assessment under the Environment
Protection and Biodiversity Conservation Act 1999. The project was approved under conditions
published in approval EPBC2008/4173 on 24 June 2009.
1.2 Report Objective
Water Corporation is required to submit a Performance Review Report (PRR) at the conclusion
of the second, forth, and sixth year after commencement of operation in accordance with
MS792 condition 5-1.
Condition 5-1 specifies that the PRR is required to address the following items:
1. The major environmental risks and impacts; the performance objectives, standards and
criteria related to these; the success of risk reduction/impact mitigation measures and
results of monitoring related to the management of the major risks and impacts;
2. The level of progress in the achievement of best practice environmental performance,
including industry benchmarking, and the use of best available technology where
practicable; and
3. Improvements gained in environmental management which could be applied to this and
other similar projects.
This PRR is the second PRR for the SSDP. The first PRR was submitted in 2014.
SSDP 2016 Performance Review Report
4 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
2. Environmental Factors, Risks and Impacts
2.1 Key Environmental Factors
The following Key Environmental Factors were identified as relevant to the construction and
operation of the SSDP in the Report and recommendations of the Environmental Protection
Authority (EPA) (Appendix 2 – Report and recommendations of the EPA Report 1302):
Water quality and Marine Biota – impacts from construction and operation of the desalination
plant;
Terrestrial Fauna – impacts from clearing of habitat;
Terrestrial Vegetation and Wetlands – impacts from clearing during infrastructure
construction; and
Greenhouse Gas Emissions – proposed no net greenhouse gas emissions.
2.2 Key Risks and Impacts
MS792 acknowledges that the discharge of desalination effluent will have an impact in the
immediate vicinity of the discharge to the marine environment. A Low Ecological Protection Area
(LEPA) has been established to limit the extent which the local marine ecosystem will be
impacted. The LEPA is 100 metres by 600 metres (50 metres either side of the diffuser array),
as required by MS792 Condition 6-1. A High Ecological Protection Area exists beyond the LEPA
boundary, at which 99% protection of species must be met.
The environmental risks and impacts for the construction and operation of the SSDP according
to each key environmental factor are shown in Table 1.
Table 1: SSDP Environmental Risks and Impacts
EPA Key Environmental
Factor
Environmental risk Potential environmental impact
Water Quality and Marine Biota - impacts from construction and operation of the desalination plant
Discharge water quality
Desalination effluent discharge quality exceeds trigger values (combination of 80th percentile of baseline results and ANZECC 2000 triggers) at the LEPA boundary, causing a risk of adverse biological impacts.
Dissolved Oxygen (DO)
Desalination effluent discharge results in a DO concentration at the LEPA boundary below MS792 condition 6-7 criteria of 60% saturation. DO is a key environmental quality indicator which may impact marine ecosystem integrity (structure biomass and
biota abundance) if the concentration is below 60%
saturation.
Salinity Desalination effluent discharge results in salinity levels at the LEPA boundary of 1 ppt above background more
than 5% of the time and/or salinity levels above 1.3 ppt above background on any occasion resulting in non-compliance with MS792 conditions. Note – a salinity level of 1 ppt above background at the LEPA boundary equates to a dilution factor of 24.6. The 2015 WET testing determined that the Target Dilution (the dilution required to meet 99% species protection at
the LEPA boundary) for Full Production operations is 9.6. Therefore a salinity level of 1 ppt above
SSDP 2016 Performance Review Report
5 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
background is protective of more than 99% species. The salinity of the bottom saline layer would need to be above 2.68 ppt above background to not meet 99% species protection at the LEPA boundary.
Whole Effluent Toxicity (WET)
N/A no risk of adverse impacts from WET testing – WET Testing is required to establish the Target Dilution (the dilution required to protect 99% species at the LEPA boundary). The 2015 WET Testing results,
representative of Full Production operations, determined that a dilution of 9.6 is required to meet 99% species protection.
Dilution The Worst Case Dilution does not achieve the Target Dilution (dilution required to achieve 99% species protection at the LEPA boundary) resulting in a risk of adverse impact to marine species.
Benthic Health (construction and operation)
Construction of SSDP infrastructure has a long-term adverse impact on benthic seagrass health. Discharge of desalination effluent during SSDP operation has an adverse impact on benthic seagrass health.
Marine fauna & flora (construction phase)
Applicable for stage one construction only (i.e. dredging, blasting, construction) during the completion of all marine infrastructure works.
Terrestrial Fauna - impacts from clearing of habitat
Terrestrial fauna Applicable for construction only. The revegetation of areas not required for above-ground infrastructure according to MS792 and EPBC2008/4173 requirements
will minimise the impact from clearing on terrestrial fauna.
Terrestrial Vegetation and Wetlands- impacts from clearing
during infrastructure construction
Terrestrial flora & vegetation
Applicable mainly to construction phase, with the exception of ongoing revegetation as part of the Revegetation Management Plan. Risk of revegetation
not meeting regulatory requirements (MS792 and EBPC2008/4173 conditions) due to internal or external factors.
Greenhouse Gas Emissions – proposed no net greenhouse gas emissions
Greenhouse gas emissions
It is intended to purchase renewable energy or carbon offset credits to offset SSDP’s electricity usage. Therefore there is no risk from greenhouse gas emissions.
SSDP 2016 Performance Review Report
6 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
3. Environmental Monitoring Framework
3.1 Environmental Quality Objectives
The following Environmental Quality Objectives were identified by the OEPA and specified in
MS792 Schedule 1 for the surrounding marine environment:
Maintenance of ecosystem integrity at a low level of ecological protection within the Low
Ecological Protection Area (LEPA) and at a high level of ecological protection at the
designated LEPA boundary;
Maintenance of aquatic life for human consumption assigned to all parts of the marine
environment surrounding the ocean outlet;
Maintenance of primary contact recreation values assigned to all parts of the marine
environment surrounding the ocean outlet;
Maintenance of secondary contact recreation values assigned to all parts of the marine
environment surrounding the ocean outlet;
Maintenance of aesthetic values assigned to all parts of the marine environment surrounding
the ocean outlet;
Maintenance of cultural and spiritual values assigned to all parts of the marine environment
surrounding the ocean outlet; and
Maintenance of Industrial Water Supply.
3.2 Marine Environment Monitoring Programs
The following programs were designed to meet the Environmental Quality Objectives for the
marine environment specified in MS792 Schedule 1:
Marine Environment Monitoring Program (MEMP), including discharge water quality
monitoring and benthic habitat monitoring;
Diffuser Performance Monitoring Program (DPMP);
Dissolved Oxygen Monitoring Program (DOMP); and
Whole Effluent Toxicity Monitoring Program (WETMP)
3.2.1 Marine Environment Monitoring Program
The MEMP was developed by Water Corporation and endorsed by the former Department of
Environment and Conservation (now Department of Environment Regulation (DER)). The MEMP
outlines the monitoring commitments for the discharge of desalination effluent to the Indian
Ocean via the marine outfall diffuser as per the requirements of MS792 condition 6-2.
Specifically the MEMP includes commitments for desalination effluent discharge quality
monitoring and benthic habitat health monitoring.
The Southern Seawater Alliance (SSWA) engaged an external contractor to undertake a review
of the Marine Monitoring Programs (MEMP, DPMP, DOMP and WETMP) to assess the current
requirements and determine which requirements have been met, which requirements are still to
be completed and the anticipated completion dates. Water Corporation submitted the findings,
including a new version of the MEMP to the OEPA on 7 October 2015. The MEMP is provided in
Appendix 3 – Marine Environment Monitoring Program.
3.2.2 Dissolved Oxygen Monitoring Program
The Dissolved Oxygen Monitoring Program (DOMP) was developed:
SSDP 2016 Performance Review Report
7 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
To address MS792 condition 6-5 which requires Water corporation to monitor dissolved
oxygen levels at least weekly, either by deploying data loggers or by hand, at sites agreed by
the CEO of the Department of Environment and Conservation to determine whether the
“trigger” values are being achieved, for a period of 12 months immediately following:
o Completion of commissioning phase or six months from commencement of the
commissioning phase, whichever is sooner; and
o The initiation of full production (according to design specifications).
To address MS792 condition 6-7 which specifies a trigger of 60% DO saturation at the
boundary of the LEPA.
The DOMP is provided in Appendix 4 – Dissolved Oxygen Monitoring Program.
3.2.3 Diffuser Performance Monitoring Program
The Diffuser Performance Monitoring Program (DPMP) was developed:
To determine compliance against the salinity trigger levels defined in MS792 condition 6-2-4
of 1 parts per thousand (ppt) salinity increase above background 95% of the time and not
exceeding an increase of 1.3 ppt above background at the boundary of the Low Ecological
Protection Area; and
To assess the diffuser performance in terms of number of dilutions achieved at the LEPA
boundary required by MS792 condition 6-8.
The DPMP was revised in 2015 as recommended by a third party. The DPMP is provided in
Appendix 5 – Diffuser Performance Monitoring Program.
3.2.4 Whole Effluent Toxicity Monitoring Program
The Whole Effluent Toxicity Monitoring Program (WETMP) was developed to meet MS792
condition 6-9 which requires Water Corporation to conduct Whole Effluent Toxicity testing of
wastewater consistent with the toxicity and testing protocol at the following intervals:
One month following the initiation of the commissioning phase;
12 months following the completion of commissioning or 18 months following the initiation of
commissioning (whichever occurs first);
12 months following the commencement of full production.
The WETMP was revised in 2015 as recommended by a third party. The WETMP is provided in
Appendix 6 – Whole Effluent Toxicity Monitoring Program.
3.3 Revegetation Management Plan
The SSDP Revegetation Management Plan (RMP) (Appendix 7 – Revegetation Management
Plan) was developed to guide revegetation on the SSDP site to meet MS792 condition 9 and
EPBC2008/4173 condition 7 requirements. The plan was based on a flora and fauna survey
conducted in 2008 (360 Environmental), the Public Environmental Review (Water Corporation
2008) and the Construction Environmental Management Framework (Water Corporation 2009).
The RMP outlines the revegetation schedule and number of species that will be revegetated.
Revegetation of the SSDP commenced in July 2009 with stockpiling of topsoil, mulch and
branches and pre-planting weed spraying. Direct seeding and planting commenced in mid-2010
SSDP 2016 Performance Review Report
8 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
and the second seeding/planting campaign commenced in mid- 2011. Planting of tubestocks
and seedlings for 1.3ha cleared at the northern area of the site was completed in 2014.
The DoE requested an amendment to the RMP to remove all references to the Harvey water
tank site based on an audit conducted in February 2015. Water Corporation provided a revised
plan to the DoE on 24 June 2015, which was subsequently approved on 4 January 2016.
SSDP 2016 Performance Review Report
9 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
4. Environmental Performance
Table 2 provides the status of each of the monitoring programs designed to meet the Key
Environmental Factors and Environmental Quality Objectives during SSDP operations. In
general the monitoring results indicate that the SSDP is operating effectively and that the
Environmental Quality Objectives for the marine environment are being maintained.
Monitoring has demonstrated that MS792 conditions for salinity and dissolved oxygen in the
marine environment have been met. In addition the SSDP is meeting the required diffuser
performance to achieve 99% species protection at the LEPA boundary.
One of the two triggers for seagrass shoot density was not met in the 2015 benthic health
monitoring survey. Water Corporation is currently undertaking an investigation into the
reported seagrass shoot density decline. Further detail is provided in Section 4.1.
SSDP 2016 Performance Review Report
10 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
Table 2: Status of SSDP Environmental Monitoring Programs
EPA Key Environmental
Factor
Project risk (MS792)
MS792 Criteria
Status Description
Water Quality and Marine Biota - impacts from construction and
operation of the
desalination plant
Discharge water quality
6-2-4 Compliant Discharge water quality monitoring conducted between 2014 and 2016 demonstrates that
the desalination effluent quality is within the anticipated range. There were four occasions
where the calculated contaminant concentrations at the LEPA boundary were above trigger
levels. However, the results were only very slightly above trigger levels and were not
considered to present a risk to the marine environment. In addition, the trigger levels are
the 80th percentile of the baseline measurements and as a result it is anticipated that
exceedances of the trigger levels will occur 20% of the time under normal ocean
conditions. There were no other occasions where the calculated contaminant concentration
at the LEPA boundary was above trigger levels, except on occasions where the background
seawater concentration was already above trigger levels. Details are provided in the 2015
and 2016 Marine Environment Monitoring Annual Reports (see Appendix 8 – 2015 Marine
Environment Monitoring Annual Report and Appendix 9 – 2016 Marine Environment
Monitoring Annual Report).
The final 6-monthly discharge quality monitoring event will be conducted in September
2016.
Water Corporation and the SSJV will continue to monitor in-pipe discharge effluent quality
including conductivity (and calculated salinity), dissolved oxygen, pH, turbidity and
Oxidation Reduction potential on a continuous basis for the duration of SSDP operations.
Dissolved Oxygen (DO)
6-5, 6-6, 6-7
Completed OEPA acknowledged that Water Corporation met the requirements of MS792 condition 6-5
and 6-6 in a letter dated 21 October 2015 (Appendix 10 – Letter from OEPA acknowledging
completion of dissolved oxygen monitorin). The OEPA also noted that oxygen saturation
never fell below 60% at the LEPA boundary and therefore condition 6-7 was never
triggered. Water Corporation ceased weekly DO monitoring on 21 October 2015 in
response to OEPA’s acknowledgement of the completion of MS792 conditions 6-5 and 6-6.
Salinity 6-2-4 Compliant The SSDP has implemented strategies to ensure that the salinity trigger levels specified in
MS792 condition 6-2-4 are met. This includes the optimisation of the seawater
recirculation system to turn the recirculation pumps on and off depending on the volume
of RO brine produced. This system has been shown to ensure that MS792 condition 6-2-4
salinity triggers are, and will continue to be met for future SSDP operations.
SSDP 2016 Performance Review Report
11 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
The monthly salinity monitoring required for 12 months following the completion of Full
Production on 17 January 2014 has been completed. Condition 6-2-4 triggers for salinity
were met during the monitoring period.
Water Corporation provided the DPMP and WETMP Completion Report to the OEPA on 18
December 2015. The report advised that the salinity triggers specified in condition 6-2-4
have been met and that Water Corporation will be ceasing monthly salinity monitoring at
the SSDP LEPA boundary based on compliance with condition 6-2-4.
Water Corporation will commence annual salinity monitoring in 2016 as per DPMP
commitments. The five year monitoring period will run from 2016 until 2020.
Whole Effluent Toxicity
6-9, 6-11 Completed WET testing has been undertaken at the following intervals to meet the requirements of
MS792 condition 6-9:
One month following the initiation of the commissioning phase, on 14 December 2011;
12 months following the completion of commissioning, on 11 February 2013;
An additional sample representative of commissioning of Full Production (100GL per
year), on 14 January 2014; and
A sample on 19 March 2015, 12 months following the commencement of Full
Production.
The 2015 WET Testing results, representative of Full Production operations, determined
that a dilution of 9.6 is required to meet 99% species protection.
Water Corporation provided the DPMP and WETMP Completion Report to the OEPA on 18
December 2015. The report advised that MS792 conditions 6-9 and 6-11 have been
adequately addressed and that no further WET testing will be undertaken unless there is a
change to operations which alters the components of the desalination effluent discharge.
Dilution 6-8 Compliant Monthly diffuser assessment required for 12 months following the completion of Full
Production on 17 January 2014 as per MS792 condition 6-8 has been completed.
Water Corporation provided the DPMP and WETMP Completion Report to the OEPA on 18
December 2015. The report advised that MS792 condition 6-8 has been adequately
addressed and that Water Corporation will be ceasing monthly dilution assessment at the
SSDP LEPA boundary based on compliance with condition 6-8.
Water Corporation will commence annual diffuser assessment in 2016 as per DPMP
commitments. The five year monitoring period will run from 2016 until 2020.
SSDP 2016 Performance Review Report
12 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
Benthic
Health
6-2-3 Investigation
underway
In 2015 the median shoot density measured at the impact sites was 168 shoots per m2.
This result is above the one year trigger of the 5th percentile of the reference sites of 96
shoots per m2. The median shoot density at the impact sites over two consecutive years
(2014 and 2015) was 232 shoots per m2. This result is less than the trigger value of the
20th percentile of 288 shoots per m2 measured at the reference sites over the same two
years.
There has been a year on year decrease in seagrass shoot density at both the southern
reference sites and the impact sites since 2012. The reason for the decline in seagrass
shoot density is unknown.
Water Corporation is currently undertaking an investigation into the cause of the reported
seagrass shoot density decline as advised in the letter to the OEPA dated 17 September
2015.
Marine fauna & flora (construction phase)
7-1, 7-2, 7-3, 7-4, 7-5, 7-6
Completed Applicable for stage one construction phase only (i.e. dredging, blasting, construction)
which saw completion of all marine infrastructure works.
Terrestrial Fauna - impacts from clearing of habitat
Terrestrial fauna
8-1, 8-2 Completed Applicable for construction only.
Terrestrial Vegetation and Wetlands- impacts from clearing during
infrastructure construction
Terrestrial flora & vegetation
9-7, 9-8, 9-9
Compliant The results of the 2015 Revegetation survey, the final survey required under the
Revegetation Management Plan, will be provided to the OEPA in 2016. Water Corporation
is currently finalising the results for the 2015 revegetation survey. The 2014 survey
results demonstrated that the revegetation is on track to meet MS792 and
EPBC2008/4173 requirements. The revegetation program will be considered complete
provided the criteria in MS792 condition 9-7 and EPBC 2008/4173 condition 7 are met in
the 2015 survey.
Greenhouse Gas Emissions – proposed no net greenhouse gas
emissions
Greenhouse gas emissions
11-1, 11-2
Non-compliant Water Corporation was non-compliant with Conditions 11-1 and 11-2 during the reporting
period. Water Corporation is in the process of developing a strategy for the purchase of
renewable energy and/or carbon offsets for the SSDP.
SSDP 2016 Performance Review Report
13 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
4.1 Benthic Health Monitoring
The 2015 annual benthic health monitoring of seagrass Posidonia angustifolia was conducted by
Murdoch University Marine and Freshwater Research Laboratory between 12 and 13 May 2015.
In 2015 the median shoot density measured at the impact sites was 168 shoots per m2. This
result is above the one year trigger of the 5th percentile of the reference sites of 96 shoots per
m2. The median shoot density at the impact sites over two consecutive years (2014 and 2015)
was 232 shoots per m2. This result is less than the trigger value of the 20th percentile of 288
shoots per m2 measured at the reference sites over the same two years.
There has been a year on year decrease in seagrass shoot density at both the southern
reference sites and the impact sites since 2012. The northern reference site seagrass density
has also decreased since 2012, however not to the same extent as the impact sites and
southern reference sites. The two year trigger has been met in previous years due to the
decrease in seagrass density observed at both impact and reference sites. The reason for the
decline in seagrass shoot density is unknown.
Water Corporation is currently undertaking an investigation into the cause of the reported
seagrass shoot density decline as advised in the letter to the OEPA dated 17 September 2015.
Murdoch University Marine and Freshwater Research Laboratory and BMT Oceanica were
engaged in late 2015 to conduct the investigation into the seagrass shoot density decline. OEPA
was provided with details of the scope of the investigation in the letter dated 12 February 2016.
4.2 Greenhouse Gas Emissions
Water Corporation was non-compliant with MS792 conditions 11-1 and 11-2 during the
reporting period. Water Corporation is in the process of developing a strategy for the purchase
of renewable energy and/or carbon offsets for the SSDP.
SSDP 2016 Performance Review Report
14 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
5. Benchmarking, Best Available Technology and Improvements in
Environmental Management
Water Corporation and the SSJV have implemented several initiatives at the SSDP based on
industry benchmarking, best available technology and improving environmental management.
These initiatives have improved the environmental performance of the SSDP. The initiatives
include:
Diffuser re-orientation;
Diffuser backfilling;
Optimisation of seawater recirculation; and
An investigation into diffuser capping.
5.1 Diffuser Re-orientation
The diffuser was re-orientated on 13 January 2014 as recommended by an independent study
on diffuser performance (Hatch 2013). Prior to the diffuser re-orientation all of the 80 diffuser
ports pointed north. This orientation exposed site 50S (50m south of the diffuser) to reduced
mixing and hence lower dilutions compared to 50N (50m north of the diffuser). Results show
that re-orientation did not have a dramatic immediately visible result on improving dilutions.
5.2 Backfilling
Backfilling of the diffuser pipeline was completed on 1 May 2015. This work has ensured that
the diffuser pipeline is covered with sand to prevent erosion of the partially exposed pipe and
hence prevent movement and potential for damage to the pipeline itself.
5.3 Seawater Recirculation
An investigation carried out with assistance from external parties in 2015 determined that
seawater recirculation is required to ensure the salinity at the LEPA boundary is less than 1 ppt
above background salinity for Reverse Osmosis (RO) brine flows of up to 300ML/day. For RO
brine flows above 300 ML/day no seawater recirculation is required to ensure the salinity at the
LEPA boundary is less than 1 ppt above background. An equation was implemented in the
continuous control system in October 2015 which turns the recirculation pumps on and off
depending on the volume of RO brine produced. This system has been shown to ensure that
MS792 condition 6-2-4 salinity triggers are, and will continue to be met for future SSDP
operations.
5.4 Diffuser Capping
An investigation conducted in July 2015 recommended capping ten of the 80 ocean outfall
diffuser ports. The analysis indicated that port capping would reduce the recirculation volume
required to meet MS792 salinity criteria through increasing discharge velocities and mixing.
OEPA were advised of the intention to cap diffuser ports in the DPMP and WETMP completion
report, submitted to the OEPA on 18 December 2015. The driver at the time was a forecast
annual drinking water production volume of approximately 63 GL. The drinking water production
profile for 2015-16 was revised in December 2016 to 92 GL, resulting in drinking water
production of approximately 285-295 ML per day for the remainder of 2016 (January to June
2016). Drinking water production of 295 ML per day results in RO brine flows of 392 ML per
day, which is above the volume at which seawater recirculation is required (300 ML per day). As
SSDP 2016 Performance Review Report
15 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
a result diffuser capping is no longer required to reduce the recirculation volume. Diffuser
capping may be reinvestigated in the event that drinking water production volumes return to
below 226ML per day (or RO brine flows above 300ML per day).
SSDP 2016 Performance Review Report
16 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
6. Conclusion
In general monitoring results indicate that the SSDP is operating effectively and that the
Environmental Quality Objectives for the marine environment are being maintained. Water
Corporation has demonstrated that the SSDP has met MS792 criteria for salinity and dissolved
oxygen and is achieving the required diffuser performance to meet 99% species protection at
the LEPA boundary.
One of the two triggers for seagrass shoot density was not met in the 2015 benthic health
monitoring survey. Water Corporation is currently undertaking an investigation into the
seagrass shoot density decline.
Water Corporation and the SSJV plan to undertake the following over the next two years (2016
to 2018):
Cease monthly salinity monitoring and diffuser assessment in the marine environment based
on the DPMP and WETMP Completion Report submitted to the OEPA on 18 December 2015;
Commence annual salinity monitoring and dilution assessment in the marine environment as
per DPMP commitments. Annual salinity monitoring and dilution assessment is required for a
period of five years (from 2016 to 2020);
Undertake an investigation into the benthic seagrass shoot density decline at both the
potential impact sites and the reference sites as per the letter to OEPA dated 17 September
2015;
Undertake a benthic health monitoring survey in autumn 2016 as per MEMP commitments;
Provide evidence to the OEPA to cease 6-monthly discharge water quality monitoring once
the final sampling event in September 2016 is completed provided triggers are met;
Provide evidence to the OEPA to close-out the revegetation requirements provided MS792
conditions are met.
Appendices
17 SSDP 2016 Performance Review Report
aquaDOC 14646239
watercorporation.com.au
Appendix 1 – Ministerial Statement 792
Appendix 2 – Report and recommendations of the EPA Report 1302
Appendix 3 – Marine Environment Monitoring Program
Appendix 4 – Dissolved Oxygen Monitoring Program
Appendix 5 – Diffuser Performance Monitoring Program
Appendix 6 – Whole Effluent Toxicity Monitoring Program
Appendix 7 – Revegetation Management Plan
Appendix 8 – 2015 Marine Environment Monitoring Annual Report
Appendix 9 – 2016 Marine Environment Monitoring Annual Report
Appendix 10 – Letter from OEPA acknowledging completion of
dissolved oxygen monitoring