2016 FRA Capital Cost Estimation Guidance

27
FRA Capital Cost Estimation Guidance Seema Javeri U.S. Department of Transportation Federal Railroad Administration

Transcript of 2016 FRA Capital Cost Estimation Guidance

Page 1: 2016 FRA Capital Cost Estimation Guidance

FRA Capital Cost Estimation GuidanceSeema Javeri

U.S. Department of TransportationFederal Railroad Administration

Page 2: 2016 FRA Capital Cost Estimation Guidance

2

ObjectivesNew FRA Cost Estimating Guidance

Estimate Checks/Risks

Characteristics of a Good Estimate

Questions

Estimate Development Resources

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 3: 2016 FRA Capital Cost Estimation Guidance

3

New FRA Cost Estimating Guidance

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 4: 2016 FRA Capital Cost Estimation Guidance

4Why did FRA create the cost estimation guidance?

US Government of Accountability Office prompted FRA to develop a guidance

To help Grantees compensate for uncertainties, unforeseen conditions, and unknowns in capital cost estimates

Responses to NOFO/NOFA must include cost estimates, Estimator’s Methodology Memo, and estimate checks

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 5: 2016 FRA Capital Cost Estimation Guidance

5FRA EstimatesProject Cost Estimates

• Utilize appropriate level detail

• Consider risks & contingency

Basis of Estimate

• Identify estimating methods

• Document methods

Estimate checks

• Verify project quantities

• Submit revised and original estimates

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 6: 2016 FRA Capital Cost Estimation Guidance

6Estimating Considerations

Costs outside of design

• Host railroad conditions• Delivery methods and market conditions

Cost Impacts of Time

• Project schedule & inflation• Financing costs & funding release

Extrapolate

• Look at total picture including risks• Before design and management decisions

completed

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 7: 2016 FRA Capital Cost Estimation Guidance

7Preparing Basis of Estimate Memo1. Introduction And Project

Description 2. Project Technical Baseline 3. Estimating Methodologies And

Standard Cost Categories 4. Supporting Assumptions/Ground

Rules 5. Estimate Limitations/Risks 6. Estimate Checks

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 8: 2016 FRA Capital Cost Estimation Guidance

8

Estimate Checks/ Risks

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 9: 2016 FRA Capital Cost Estimation Guidance

9Types of RisksRequirements Risk• Variability of fundamental

goals and conditions of a project

Design Risk• Performance and variability of design-

related activities occurring after Alternatives Analysis

Market Risk• Procurement of project

management, right-of-way, design & construction services

Construction Risk• Variability in the project’s

environment and in performance of contractors

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 10: 2016 FRA Capital Cost Estimation Guidance

10

Railroad Specific IssuesUnderstanding scope and responsibilities

Vehicle procurements - requirements coordination, schedule

Davis Bacon/ prevailing wage

Utility changes

Station ADA requirements

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 11: 2016 FRA Capital Cost Estimation Guidance

11

Railroad Specific Issues cont’d

Closure Windows

Construction staging under operating railroad conditions

Work site access agreed early in the design process

Grade crossings

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 12: 2016 FRA Capital Cost Estimation Guidance

12

Host Railroad CostsCosts of stopping, diverting, or slowing

existing trainsCosts and risks associated with line closure

windowsCosts to the host railroad for personnel for

construction, flagging, roadway worker protection

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 13: 2016 FRA Capital Cost Estimation Guidance

13

Host Railroad Costs cont’d

Flaggers and signals crews availabilityLabor rates, per diem/travel time

guaranteesTime and labor to inspect, commission,

and accept the work

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 14: 2016 FRA Capital Cost Estimation Guidance

14Signals And Special Track Lead times for special track work

items (double slip switches, crossing diamonds, and size of turnouts)

Signal lead time and ripple effect to the existing system

Spare parts availability if materials are lost or stolen at the job site

Buy America requirements

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 15: 2016 FRA Capital Cost Estimation Guidance

15

Characteristics of a Good Estimate

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 16: 2016 FRA Capital Cost Estimation Guidance

16Characteristics of a Well-Developed Cost Estimate 1. Consistent estimating approach

2. Based on a schedule with all phases

3. Well documented and traceable - include assumptions and ground rules

4. Includes contingencies and risk review

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 17: 2016 FRA Capital Cost Estimation Guidance

17Characteristics of a Well-Developed Cost Estimate cont’d

Justifiable inflation ratesSums to a Total Project Cost in YOE

dollarsIncludes management reserve, if

necessaryFormally approved by the project

sponsor

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 18: 2016 FRA Capital Cost Estimation Guidance

18Good PracticesTrack and document bid estimates

Update the estimate to reflect current market conditions

Use a risk based approach to evaluate future market conditions

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration

Page 19: 2016 FRA Capital Cost Estimation Guidance

19

Common OmissionsFlagging – costs can quickly grow if not

estimated correctly.

Archeological or environmental issues

Wider footprints have more room for errors

Buy America

Grade crossings

Utility relocations

Right of WayU.S. Department of Transportation

Federal Railroad AdministrationU.S. Department of Transportation

Federal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 20: 2016 FRA Capital Cost Estimation Guidance

20

Estimate Development Resources

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 21: 2016 FRA Capital Cost Estimation Guidance

21

Estimating Resources

FRA Capital Cost Estimating Guidance FRA Capital Cost Estimating Guidance https://www.fra.dot.gov/Page/P0926FRA Standard Cost Category spreadsheet FRA Standard Cost Category spreadsheet https://www.fra.dot.gov/eLib/details/L16055

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration2016 FRA Rail Program Delivery Meeting

Page 22: 2016 FRA Capital Cost Estimation Guidance

22

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration

FRA 10 Standard Cost Categories

Guideway & Track Elements

Stations, Stops, Terminals, Intermodels

Support Facilities: Yards, Shops, Admin. Bldgs

Sitework & Special Conditions

Systems

2016 FRA Rail Program Delivery Meeting

Page 23: 2016 FRA Capital Cost Estimation Guidance

23

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration

FRA 10 Standard Cost Categories (cont’d)

Row, Land, Existing Improvements

Vehicles

Professional Services

Unallocated Contingency

Finance Charges

2016 FRA Rail Program Delivery Meeting

Page 24: 2016 FRA Capital Cost Estimation Guidance

24

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration

Estimating Resources Risk and Contingency Review and Other FRA Monitoring ProceduresRisk and Contingency Review and Other FRA Monitoring ProceduresFTA Capital Cost DatabaseFTA Capital Cost Database

2016 FRA Rail Program Delivery Meeting

Page 25: 2016 FRA Capital Cost Estimation Guidance

25

U.S. Department of TransportationFederal Railroad Administration

U.S. Department of TransportationFederal Railroad Administration

Cost Estimating Session Takeaways1. New FRA Cost estimating guidance

2. New requirements: basis of estimate & estimate checks

3. Online estimating resources

2016 FRA Rail Program Delivery Meeting

Page 26: 2016 FRA Capital Cost Estimation Guidance

26

Questions

U.S. Department of TransportationFederal Railroad Administration

Page 27: 2016 FRA Capital Cost Estimation Guidance

Thank you!Seema JaveriGeneral [email protected]://www.fra.dot.gov/Page/P0926

U.S. Department of TransportationFederal Railroad Administration