20150903 THSRC Case Study

6
Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston Max word limit: 1300 / 325 max per question; 250 ideally 1) Explain the precise nature of this public-private partnership ie: what are the obligations of the private consortium and what are the obligations of government. In February 2000 the Taiwan government and the Taiwan High Speed Rail Corporation (THSRC) finalized a contract that codified their respective obligations under the BOT public- private partnership model. The governments primary obligation under the RFP was the acquisition and payment of the land for the railway track, eight stations, maintenance depots, and station development districts at a total cost of $1.7 billion. The government also granted THSRC the right to real estate development revenues for 50 years in the areas immediately adjacent to the station called special zones.1 It also granted THSRC the exclusive use of the land over the 35-year concession period. The original RFP committed the government to acquiring and paying for the land for the railway track, station, and maintenance depots, and granted THSRC the right to use the land over the 35-year concession period. The government obligations: o Station development districts (this was the large tracts of land the government had purchased the “surrounded” the real estate THSRC controlled) Made no promise on how quickly it would develop THSRC is not entitled to participate in the planning or development process of these areas Provided the land for a 50 year concession period Concession for real estate development revenues for 50 years in the areas around the station (special zones) Build roads into and out of the stations Promised to buy the system if the winner went bankrupt at a price to be determined by an independent 3 rd party to help repay winner’s bank loans 1 The government envisioned strong economic developed in the areas surrounding the greenfield” stations and subsequently purchased large tracts of land, which the contract termed station districts.The government, however, did not make commitments on how quickly it would develop these areas, which had a direct impact on the real estate revenues THSRC could capture.

description

Case study analysis on the Taiwan High Speed Rail

Transcript of 20150903 THSRC Case Study

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston Max word limit: 1300 / 325 max per question; 250 ideally

    1) Explain the precise nature of this public-private partnership ie: what are the

    obligations of the private consortium and what are the obligations of government.

    In February 2000 the Taiwan government and the Taiwan High Speed Rail Corporation

    (THSRC) finalized a contract that codified their respective obligations under the BOT public-

    private partnership model.

    The governments primary obligation under the RFP was the acquisition and payment of the

    land for the railway track, eight stations, maintenance depots, and station development districts

    at a total cost of $1.7 billion. The government also granted THSRC the right to real estate

    development revenues for 50 years in the areas immediately adjacent to the station called

    special zones.1

    It also granted THSRC the exclusive use of the land over the 35-year concession period.

    The original RFP committed the government to acquiring and paying for the land for the railway

    track, station, and maintenance depots, and granted THSRC the right to use the land over the

    35-year concession period.

    The government obligations:

    o Station development districts (this was the large tracts of land the government had

    purchased the surrounded the real estate THSRC controlled)

    Made no promise on how quickly it would develop

    THSRC is not entitled to participate in the planning or development process

    of these areas

    Provided the land for a 50 year concession period

    Concession for real estate development revenues for 50 years in the areas around the

    station (special zones)

    Build roads into and out of the stations

    Promised to buy the system if the winner went bankrupt at a price to be determined by an

    independent 3rd party to help repay winners bank loans

    1 The government envisioned strong economic developed in the areas surrounding the greenfield stations and

    subsequently purchased large tracts of land, which the contract termed station districts. The government, however, did not make commitments on how quickly it would develop these areas, which had a direct impact on the real estate revenues THSRC could capture.

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston

    Provided a loan guarantee to the bank consortium

    Supervision of construction

    From the negotiations:

    o Permitting issues, commit to deadlines and provide support

    o Diversion of utility lines

    o Loan guarantee

    Dates

    RFP released in 1996

    Guarantee signed in February 2000

    Negotiations ended in ??

    Construction began in March 2000

    Transition to new government in March 2000

    Equity stake increased over 2003-05 by state-owned companies (doesnt really solve the

    issue)

    Service began in March 2007 (12 month time slippage)

    The PPP structure, high-level:

    BOT model

    Concession of 35 years (not 5 to build and 30 to operate incentive to complete on time)

    The THSRC obligations:

    Operational performance requirements

    o P. 7

    Financial obligations

    o Pay for the capital expense of:

    Stations

    Trains Japanese company

    Build the track

    o Operating costs of the railroad

    o Design

    Stations with themes and identities

    o Equity requirement 25 percent of the companys total assets (against the loan?)

    Was eventually in the actual contract?

    Unique to their bid what helped them win

    o Pay for all the civil works (estimated 45 percent of capital expense)

    o Complete construction by 2003 (not 2005)

    35 year total concession period

    o Provide 10 percent of its profits each year with a minimum payment over the life of

    the concession period equal to governments contribution to the project

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston

    What this means government investment would be zero over the life of the

    project completely privately owned

    Independent verification THSRC pays; government has veto power. This type of thing was

    a first for Taiwan

    2) Did the government consider all of the significant costs and benefits in its cost-

    benefit analysis? If not, what else might it have considered?

    What analysis is this all based on?

    1990 study

    Formal cost-benefit in 1992 to obtain final approval for the project

    Ridership studies

    1991 study distorted #s to favor high-speed rail

    1997 estimate RFP released

    o

    Benefits

    Ridership

    Economic activity right not to include this

    Environmental impact (reduced pollution)

    Lower accident rates

    Energy savings

    Costs

    Cost overruns

    Time slippage

    Actual capital expense #s (different technologies and approaches); media sources

    reported various ranges from $12.5 to $18 BN (government)

    Land OK

    Project costs a hell of a lot less clear

    Operating costs a hell of a lot less clear for the same reason

    Financing costs for long-term borrowing

    Impact on reduction in competing industries

    Impact on time savings of shifting the railway to the East harder to get to and impact on

    ridership

    The greater the # of stations the greater the cost

    Environmental

    Worst case scenario expense?

    Capital expense

    Civil works expense

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston

    Operating expense

    Maintenance expense

    Ridership predictions (main driver)

    How many stations was the 1992 and 1997 estimates based on?

    The main issue was with the approach:

    Verifying assumptions

    More conservative assumptions

    Inclusion of terminal value?

    Looking at global examples none of these other trains are economically viable!

    3) In its procurement process (bidding) and negotiations with the winning consortium,

    what might the government have done better to minimize the risk of a failed project?

    General issues (move to other sections potentially)

    Recognize their lack of experience, the size of the project, and the amount of money

    involved (all significant risks) reach out to US, Japan, France governments for guidance

    and advice

    Ensure a balance between engineering teams (dominant) and financial folks (ignored)

    Create systems for independent assessment and judgment (get politics out) maybe not

    that feasible

    Procurement issues:

    Track record can you execute?

    Selection committee was this the right group?

    Financial letter of intent who? How serious?

    Vetting of assumptions

    o Ridership

    Requirement of contingency plans

    Validity of no need for a government subsidy on civil works

    Opportunity to reach out to more established Western firms? Why didnt they end up bidding

    on the project?

    Transparency

    Negotiation issues:

    Better resources and provide more support (reduce time, damage to relationship)

    Been more aggressive on the equity issue required that no state funds (outside the major

    banks) could count toward the contribution (aligning incentives and distributing risk)

    o So much government support what types of incentives does this create?

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston

    o They obviously wanted to exit ASAP as soon as things looked bad

    The requirement of the government guarantee should have been a serious red flag

    Should have listened to the banks concerns

    Being less stringent on international financing options diversify risk outside the state-

    owned banks

    4) What options does Chi-kuo Mao (Taiwans Minister of Transportation and

    Communications) have in dealing with this problematic PPP? Which of those options

    is the one that you would take if you were him?

    What are Maos goals?

    Avoid a $13 billion outlay (25 percent of budget)

    Not lose face internationally embarrassing first PPP, tied to Taiwans growth and identity

    Avoid political backlash from citizens

    Find a way to make this work

    Not adding to the existing financial constraints

    Inability to operate (to avoid large gaps in service)

    What are the key issues and constraints?

    Bankruptcy or buying out are basically the same thing and leads to a worst case scenario

    within the next 12 months; no secondary market value left with useless infrastructure

    o Equity stakeholders were also state-owned companies (i.e., government had a lot at

    stake indirectly)

    Still on the hook due to the government guarantees

    The key constraint is the interest and principal debt servicing government is in a good

    position to help them restructure

    THSRC is good at operations and construction

    Mao has several options:

    Allow THSRC to go into bankruptcy

    Follow the original terms of the contract government buys the system

    Provide technical assistance to

    o Increase revenues

    Integrate with broader transportation system

    Identify most profitable customer segments and service them

    o Decrease costs

    Reduce frequency

    Lay off staff or reduce hours

    Prioritize most profitable lines, cut or reduce service to others

    Allow a third party consortium to buy the system

    o Political risk

    o Public perception issue

    o May not solve the actual issue

  • Jason McCoy Developing Infrastructure through PPPs March 10, 2015 Professor Featherston

    o May not receive the full amount still stuck with debt

    o Would this be attractive to anyone given the uncertainty of future long-term

    revenues?

    Gain control of the company (ensure immediate payments are satisfied) and leverage the

    power of the government to renegotiate interest rates and tenor; revise depreciation rules

    o Upside

    More control and oversight; government owns the system (or at least a

    majority stake)

    THSRC has strong performance as an operator the real issue is their

    massive debt

    Restructure loan to pay off old loan at a lower interest rate