SUMMARY REPORT FOR
Godawari Power & Ispat Limited, Raipur
PROJECT UDAAN
By
Renoir Consulting (India) Pvt Ltd
Project Team:
Nilutpol Borah, Operations Manager
Ajay Vaze, Project Manager
Aashish Kr. Singh, Sr. Consultant
Ashish Vashisth, Consultant
Arpit Banga, Consultant
Project Start: August 4, 2014
Project Completion: February 28, 2015
Duration: 30 weeks
GPIL, Raipur, Confdential Page 1
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
2/101
Executive Summary
Background
Godawari Power & Ispat Ltd. (GPIL) a public Ltd. Co., formally Ispat Godawari Ltd
(IGL), a pioneer constituent belonging to HIRA Group of Industries, Raipur, C.G. was
incorporated in 1999 to set up an integrated steel plant with captive power
generation.GPIL is a flagship Company of Raipur-based Hira Group of Industries
having dominant presence in the long product segment of the Steel industry, mainly
into mild steel wire. Today, GPIL is an end-to-end manufacturer of mild steel wires. In
the process, the company manufactures sponge iron, billets, Ferro alloys, captive
power, wires rods (through subsidiary company), steel wires, Oxygen gas, fly ash
bricks.
GPIL has come a long way since it started its operation in Raipur, Chhattisgarh as a
sponge iron manufacturer in the year 2001. Over the last few years, the company
has scaled up its capacity five-fold and has become one of the largest players in the
mild steel wires segment. Consistency has been a hallmark of GPILs product and in
Steel Melting Shop convert the dream into reality by producing one of the finest
quality of BILEETS in the Industry. This ranges from customized size of 110 x 110
which confirms to BIS standards 2830 & 2831 to the extended range of 200 x 250
thereby any size and composition with ease and balance.
Billets are produced out of pellets based sponge Iron resulting significantly positive
impact on re-rolling process due to its surface finish and chemical property which
holds good at testing parameters. It surpasses any criticality and complexity of the
rolling mills with extended competitive edge in such process integration.
Billets meant for re-rolling of strips, wire, bar, hexagons and profiles, available in
variety of sizes.
In Aug 2014, GPILs management engaged Renoir Consulting for an Operational
Excellence Programme christenedUdaanwith a focus to improve the output by
GPIL, Raipur, Confdential Page 2
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
3/101
improving the efficiency and utilisation. The duration of the project was decided as 30
calendar weeks to identify opportunities, design the solutions, implement the same
and ensure sustainability. A taskforce was formed consisting of GPIL employees who
worked with Renoir Consulting to identify the opportunities and implement the
solutions concurrently in the three areas namely Process, Maintenance and Quality.
Department wise MATs were created which were chaired by the MAT chairman. MAT
members having the desired skills, knowledge and experience were chosen to
validate the studies and solutions to ensure not only the quality but also the
acceptability of the solution.
In SMS MAT, below are some of the issues identified and systems implemented to
resolve them, so that the department and the company can achieve the desired
KPIs.
GPIL, Raipur, Confdential Page 3
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
4/101
Management
Action Team
(MAT) Area
Key Issues Systems Implemented
Process
Process
Linkage of Monthly
production plan with
shift wise schedule
Daily Production Planning
Production Deviation report
KPI Dashboard
Lack of structured
review mechanism
KPI Tree
KPI Dashboard
Shift handover
Daily Review Meeting
Weekly Review Meeting Monthly Review Meeting
Comprehensive Production logsheet
This mentions relevant standards
which are to be followed such as Tap
temperature, empty ladle temperature,
pitside temperature, Monitoring of load
ramp up
RACI matrix for all implemented
systems
KWH/MT
Cycle Time
Key Process
Parameter variations
Empty ladle temperature
Tap temperature
Pit side temperature
Purging time
Temperature at CCM
Carbon level in bath sample
Specific solutions themes to control the
variations (short term and long term)
Productivity
Absence of information
for evaluation of
Critical Equipment listing
Bad Actors identification
Maintenance MIS (frequency, MTTR
GPIL, Raipur, Confdential Page 4
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
5/101
Management
Action Team
(MAT) Area
Key Issues Systems Implemented
Maintenance
Maintenance
Maintenance
Performance
etc.)
Reliability Centred Maintenance
Approach
Lack of structured
Maintenance systems
Breakdown Management System
PM Schedule
Equipment History and criticality list
Shift handover system
Line Walk
RCA Policy and RCA (corrective and
preventive actions
FGDs (Purchase)
Lack of Review
Mechanism
Daily Review Meeting
Weekly Review Meetting
Monthly Review meeting
Quality
Non conformance in
the quality standards
Sponge pellet requirement Vs
fulfilment
Quality checklist in production
Ineffective Shift
Handovers
Shift handover system comprising of
all departments such as production,
quality , maintenance, RM, CCM
RCAs and
enhancement of
current systems
RCA for quality issues
Macro test
In order to drive the implementation, weekly MAT meetings and fortnightly Steering
Committee Meetings were conducted. The purpose of these meetings was to
eliminate any impediments that the Project Team may face during implementation.
The actions derived from these meetings were communicated to all concerned and
GPIL, Raipur, Confdential Page 5
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
6/101
they were directed to initiate actions, track the same and review periodically for
achieving the desired benefits.
Major activities carried out by the Project Udaan team were:
1.Value Drivers mapping for key performance improvements for each plant
2.Standard operating procedure prepared and same has been mentioned in the
production logsheet, which is referred by the melter and shift in charge
3.Implementation of Reliability Centred Maintenance Approach across all plants
4.Improved daily review meeting and analysis of issues through root cause
analysis and implementation of CAPA
5.Interface improvements between the Power Plant and consumer departments
for reduction in export of power
6.Optimum utilization of resources to achieve desired level of targets
Some of the areas, where the actions need to be fast-tracked are:
1.Actual weighment of molten metal and charge mix added in each heat
2.Resolution of issues in Furnace no 06
3.Resolution of shortage and fluctuation in power supply to SMS
Having said this, to ensure sustained implementation of above systems, a structured
three-stage audit mechanism was implemented (Compliance, Understanding and
Usage). The results are as of week 26
MAT Compliance (%) Understanding (%) Usage (%)
SMS 93% 96% 84%
The below mentioned table enumerates the results that were achieved by the
Management Action Teams for the period of implementation. The following were the
results achieved as comparison between Baseline and Actuals:
GPIL, Raipur, Confdential Page 6
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
7/101
Target and baseline was revised considering managements decision to run only 3
furnaces 8-10 till week 26. From week 27 onwards target and baseline were further
revised considering operation of furnace 6-10 and 3-5(depending on power
availability)
Considering Revision 2 : Furnace 8-10 Week 16 to week 26
Sr.
No. Description
Dec13 to
May14
(Baseline
period)
Improvement
Target
(Actuals)
Annualized benefit
based on
comparison with
Baseline and
agreed evaluation
methodology
1.
Production -
Average
production
MT / day
252 290 275 8370
2. KWH/MT 925.3 87154,29,176 units
saved
Conclusion
The improvement program needs to be continued with full compliance to ensure that
the benefits are reaped on a sustainable basis. The necessitated major cultural shift
in the way of functioning of the organization should be sustained.
The management should drive the initiatives inspite of challenges of this industry
such as raw material unavailability, consistency of raw material grade, changing
market conditions (prices, demand) etc.
GPIL, Raipur, Confdential Page 7
880
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
8/101
Standard Operating ProceProduction and Specifc Po!er Conu"ption
Project UdaanGodawari Power and Ispat Limited
It is desirable that the management takes decisive actions in a timely manner to
improve the operations in the plant, as this will go a long way in improving the
efficiency and utilization of SMS Plant.
GPIL, Raipur, Confdential Page #
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
9/101
Godawari Power and Ispat Limited
Siltara, Raipur
Project Udaan: Operational Excellence Manual
Title: Standard Operating Procedure Production and Specific
Power consumption
Revision Number: 000
Issue Date:
Effective Date:
This Copy Printed :
Pages: !Document Reference"#i$e: %tandard &perating Procedures ' Production and %pecific Po(erconsumption
)ocation:
Issued by: Contro$$er to be determined by *PI)
+pproved by: +uditor to be determined by *PI)
GPIL, Raipur, Confdential Page $
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
10/101
Master Revision Table
For ISO 9001 purposes records of previous revisions are to be recorded here. The issuer of
this document should be contacted for verification of the latest release version. All earlier
release versions must be destroyed.
Revision Number: Issue Date: Effective Date: Issued by: +pproved by:
%ummary of Changes:
Revision Number: Issue Date: Effective Date: Issued by: +pproved by:
%ummary of Changes:
Revision Number: Issue Date: Effective Date: Issued by: +pproved by:
%ummary of Changes:
Revision Number: Issue Date: Effective Date: Issued by: +pproved by:
%ummary of Changes:
Disclaimer
This is a reference manual for Production and Management control systems and processes
designed and installed in Godawari Power and Ispat Limited, Siltara, Raipur.
These systems have been implemented after discussion and approval from the Steel Melting
Shop Management Action Team (MAT).
This document is a ready reckoner for all existing employees and new joinees to get a good
view of the systems and processes used by Production team.
GPIL, Raipur, Confdential Page 1%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
11/101
Table of Contents
E,ecutive summary-------------------------------../
ac1ground---------------------------------./
Conc$usion................................................................................................................ ...
2aster Revision Tab$e................................................................................................................
ac1ground...............................................................................................................................
Pro3ect &b3ectives......................................................................................................................Pro3ect +pproach.......................................................................................................................
Pro3ect %tructure........................................................................................................................
#ocus Process...........................................................................................................................
Design and Deve$opment...........................................................................................................
%o$ution Deve$opment +pproach............................................................................................
Imp$ementation and %ustainabi$ity.............................................................................................
Imp$ementation ' Production and P$anning %ystems.................................................................
%hift 4andover--------------------------------.5!Dai$y Revie( 2eeting.............................................................................................................
6ee1$y Revie( 2eeting.........................................................................................................
Purchase #ocus *roup Discussion........................................................................................
+nnua$ Preventive 2aintenance Program..............................................................................
rea1do(n %$ip......................................................................................................................
rea1do(n 2anagement %ystem...........................................................................................
)ine 6a$1...............................................................................................................................
Root Cause +na$ysis..............................................................................................................
Production Deviation sheet....................................................................................................
efore casting chec1$ist..........................................................................................................
Comprehensive Production )ogsheet....................................................................................
E7uipment Critica$ity Ran1ing................................................................................................
ua$ity Chec1$ist9ua$ity gate...............................................................................................
C chec1$ist in production......................................................................................................
%e7uencing bet(een CC2 and furnace.................................................................................
%ponge pe$$et and ore re7uirement ;s #u$fi$ment...................................................................
&perationa$ enefit Trac1er and
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
12/101
Dai$y caster 2aintenance Chec1$ist----------------------....==
Process 7ua$ity chec1s----------------------------..=
Inventory Trac1ing------------------------------..85
Too$ o, standardi>ation and +udit-----------------------.85
ad +ctor )ist---------------------------------..8?
%ustainabi$ity phase...................................................................................................................
%tep by %tep Instruction-----------------------------.88
+ppropriate 2anagement sty$e--------------------------.0
Responsibi$ity and #re7uency--------------------------..0
GPIL, Raipur, Confdential Page 12
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
13/101
Background
In /0!5@ *PI) p$anned to ta1e the ne,t $eap in throughput improvement by imp$ementingrobust systems (ith the he$p of Renoir Consu$ting. Renoir undertoo1 a dip stic1 study toidentify areas of potentia$ improvement. The ma3or areas of opportunity (ere improvement inp$ant uti$i>ation@ efficiency@ and systems for production and p$anning@ maintenance@communication and training.
Project Objectives
The main ob3ective (as to faci$itate an increase in production by dep$oyment of 2anagementContro$ %ystems.
To achieve this@ a pro3ect team (as set up (hich consisted of a Pro3ect 2anager and t(oconsu$tants under the guidance of an &perations 2anager. + separate 2anagement +ctionTeam 92+T for Production and P$anning (as insta$$ed to identify gaps in the Production andP$anning areas and drive systemic changes in this function to improve the Production. The 52+T teams (ere (e$$ supported by A tas1force members (ho (ere pic1ed from therespective sections of *PI). The Pro3ect structure comprised of one 2+T at each forProduction and P$anning@ 2aintenance and Communication and Training. The 2+T (or1(as revie(ed by company $eve$ %teering Committees headed by the 2anaging Director.
6ithin %2% 2+T the primary ob3ective (as to: Improve Production through Bti$i>ation and Efficiency
Reduction in the %pecific Po(er consumption
GPIL, Raipur, Confdential Page 13
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
14/101
Project Approac
Carry out series of studies
Identify the gaps in performance
uantify main areas of opportunities
Deve$op detai$ed approach on de$ivering the resu$ts
Identify resources@ time and cost of moving to pro3ect phase
%et up 2anagement +ction Team for each function. %e$ect $eader for each function.
Define ob3ective for each Team.
Empo(er each 2+T member to $ead an ob3ective
Define "acceptance of ro$es and responsibi$ities of each member.
Carry out detai$ed study together (ith company staff members to ensure
understanding on issues and opportunities of improvements
Deve$op %o$utions to areas identified during focus process
Prioriti>e the imp$ementation and ma1e imp$ementation p$an.
Dry run and (et run of so$utions to be carried out
Insta$$ so$utions in a$$ the areas
Provide training to a$$ the emp$oyees (ith regards to the approach of so$utions
To sustain resu$t@ conduct audit to monitor the comp$iance of ne( system 2onitor the resu$ts to see the benefits accrued
GPIL, Raipur, Confdential Page 14
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
15/101
Project Structure
GPIL, Raipur, Confdential Page 15
Consu$tant
+rpit anga
Pro3ect 2anager: +3ay ;a>e@ &peration 2anager: Ni$utpo$ orah
2+T Chairman:
2r. Raveendra
2+T Chairman:
2r. .
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
16/101
Steering !ommittee
The steering committee comprised of ED 2r. +bhishe1 +gra(a$@ and a$$ 2+Ts Chairman.During the %C2 meeting@ 2+Ts chairman updated the %C2 about the progress of their2+Ts as against the 2anagement +ction P$ans 9as fina$i>ed after the #ocus ProcessT2 .
Management Action Teams
The management action teams 92+Ts comprised of a 2+T Chairman 2r. * % ansa$@ ;iceChairman 2r. %an3ay 2undada and ? other team members. The primary ob3ective of the2+T (as to identify the opportunities for improvement@ design so$utions to fi$$ those gaps andimp$ement the same. The ro$e of 2+Ts a$so inc$udes coaching and mentoring the otherconcerned peop$e in the p$ant about ne( insta$$ed systems " processes.
GPIL, Raipur, Confdential Page 16
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
17/101
"ocus Process
During the initia$ phase studies (ere conducted by the pro3ect team and the 2anagement+ction team to identify@ areas for improvement@ ne( systems " processes. 6e first $oo1edinto the capacity uti$i>ation. 6e ca$cu$ated the capacity of the p$ant based on the 7uarti$e ' 5
methodo$ogy and mapped the production (hich (as achieved by the p$ant. *aps (erecategori>ed under fo$$o(ing categories :
!. rea1do(n )osses/. %hutdo(n $osses5. Performance $osses
;a$ue driver tree (as envisaged to map the 3ourney to financia$ benefit. The root of the treegerminated from profitabi$ity. Three area (ere contemp$ated through (hich (e can attainbenefit as sho(n in the chart be$o( :
In order to va$idate the gaps or opportunities (e focused on fo$$o(ing parameters:
GPIL, Raipur, Confdential Page 17
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
18/101
! Data analysis (plants capacity utilization, breakup of % downtime loss, %
performance loss, key process parameters variation analysis)
2)Observational Studies to map the effectiveness of practices followed in the
plant3)MCS (Management Control System) to map the effectiveness of managing the
business by managing the activities, information and people
4)Issue tree and probable cause analysis
Breakdo#n $osses
2aintenance %ystem '
rea1do(n and shutdo(n $osses (as ana$ysed for the base$ine period and it (as found thatsame constituted to of the idea$ capacity 9ca$cu$ated on the basis of 7uarti$e F5 of theactua$ production
GPIL, Raipur, Confdential Page 1#
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
19/101
&
5%,%%%
1%%,%%%
15%,%%%
2%%,%%%
25%,%%%
121,212
4,386 1,058
12,$64
102,805
SMS Plant - Capacity Utilization - Dec' 13 - May'14
To find the gap (e mapped the +s Is system of maintenance management as sho(n in thechart given be$o(:
It can be seen that maintenance system (as very (ea1 and fo$$o(ing opportunities (ereevident:
!. )ac1 of Preventive maintenancea )ac1 of effective P2 P$anb )ac1 of system for handing over of e7uipment during P2c )ac1 of standard chec1$ist
GPIL, Raipur, Confdential Page 1$
Illustrative
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
20/101
%ame (as va$idated through data ana$ysis and issue tree.
68% 32% 1%%'
Baseline - Electrical and Mechanical Breakdown
Mechanical Electrical
ISSUE TREE - Electrical Breakdown - Furnaces
Level 1 Level 2 Level 3 Level 4 Level 5 Level 6
Electrical
Breakdown
in furnaces
Bus Bar
cooling
tube
leakage
Sparkin
g in
Busbar
Due to dust
accumulation on busbar
Panel is not dust
proof
Due to rupture of
cooling pipe which
results in leakage of
water
Loosing of clamp Poor maintenance
Wear and tear in
pipe
Lack of periodic
checks
Loosening of busbar
bolts
Due to frequent
cooling heating of
busbars
Lack of periodic
checks for tightening
Temperature of busbar
should be below 65
degree C.
DM water inlet
temperature should
be less than 32degree
Cooling tower is not
efficient, which
resulted in poor heatexchange and
higher DM water
temperature
Brazing
opens
Sparking in busbar Due to dust
accumulation on
busbar
Panel is not dust
proof
Due to rupture of
cooling pipe which
results in leakage of
water
Loosing of clamp Poor
maintenance
Wear and tear in
pipe
Lack of periodic
checks
Increase in busbar
GPIL, Raipur, Confdential Page 2%
IllustrativeIllustrative
E$ectrica$ brea1do(ns constituted A8 (hich is 7uite high. &ver a$$ uptime of furnace(as = .
Illustrative
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
21/101
temp. Temperature of
busbar should be
below 65 degree C.
DM water temp inc.
beyond 38 degree,
which should be
below 32 degree.
Cooling tower is
not efficient,
which resulted in
poor heat
exchange and
higher DM water
temperatureDue to loose nut
bolts
Due to frequent
cooling heating of
busbars
Lack of periodic
checks
2ain issues (hich resu$ted in e$ectrica$ brea1do(n (ere as fo$$o(ing:
!. )ac1 of preventive maintenance/. )ac1 of standard chec1$ist5. In effective coo$ing due to inefficient coo$ing to(er
Per%ormance $oss& Productivity $oss 'Performance $oss (as ana$ysed for the base$ine period and it (as found that sameconstituted to of the idea$ capacity 9ca$cu$ated on the basis of 7uarti$e F5 of the actua$production
&
5%,%%%
1%%,%%%
15%,%%%
2%%,%%%
25%,%%%
121,212
4,386 1,058
12,$64
102,805
SMS Plant - Capacity Utilization - Dec' 13 - May'14
To find out the reason for the gap bet(een capacity and actua$ production (e mappedproduction management system 2C% on a bro(n paper. The 2anagement Contro$ %ystem92C% is a uni7ue 1ind of business management too$. 6hereas a norma$ process mapcata$ogues events in a chrono$ogica$ order and uncovers operationa$ inefficiency@ a 2C%cata$ogues the data f$o( of a$$ the concurrent events and identifies if the appropriateinformation is avai$ab$e to ma1e appropriate and correct business decisions.
GPIL, Raipur, Confdential Page 21
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
22/101
It is a t(o a,is diagram@ one a,is being a chrono$ogica$ sca$e of systems e$ements under theco$umn headings of:
#orecast
This is forecasting e,penses re$ated to production 9production budget
P$an
This invo$ves defining month$y " 7uarter$y e,penses p$an re$ated to production
Contro$
Coordination bet(een p$ant head@ shift managers@ production heads and operators
Report
o Providing numerous va$uab$e point of information in a structured manner
o Ro$$ up operationa$ activities through (ee1$y operationa$ and month$y ba$anced
scorecards
The other a,is is a fre7uency sca$e of e$ements at (hich the above activities of #orecast@P$an@ Contro$ and Report shou$d be performed. The +s ' Is 2C% for Production andP$anning is depicted be$o(:
+s ' Is 2anagement Contro$ %ystem
GPIL, Raipur, Confdential Page 22
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
23/101
+s Is process (as mapped and criti7uing (as done to find gaps in the present productionsystem.
#o$$o(ing (ere critica$ points
!. )ac1 of effective production p$an/. )ac1 of standard parameters5. )ac1 of understanding among (or1men about %&P
As()s Management !ontrol System !riti*ues !lassi%ication( Steel Melting Sop
Sr Critique Related to which
MCS Element?
Leads to
(Impact)
Category Priority for
Implementat
Approach
Just
Do
Rea
Stat
Sys
1 Maintenance of caster
is to be done on daily
basis and hence
schedule is needed
Control Loss in
productivity
System High 1
2 Caster PM checklist to
be revisited.
Control Production
loss due to
equipment
unavailability
System High 1 1
3 Role of Quality
department to freeze
standards and ensure
compliance.
Control Rejection,
increase cycle
time
System High 1
4 There is no system of
generating Bad Actor
list
Report Less
opportunity to
review
breakdown
reasons
System Medium 1
5 Interface with Power
department for
availability of power
Control Production
loss due to
unavailability
of required
power
Medium 1
6 Critical equipment list
needs be refined
(basis history of
breakdowns, MTTR,
MTBF, PM non
compliance etc.)
Plan Ineffective PM,
repeated
failures
System High 1
7 Yearly shutdown plan
for caster to be made
Plan Ineffective PM,
repeated
failures
High 1
GPIL, Raipur, Confdential Page 23
Criti7ues c$assification '
!. %ystem G ?A/. Process G ??5. ehaviour G 8
Criti7ues formed the base$ine for theformu$ation of the so$utions and fi$$the gap of +s Is 2C%
Illustrative
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
24/101
8 Strict supervision
required at caster and
furnace to ensure
adherence to SOPs.
Control Production
loss due to
non
compliance of
SOP
High 1
9 SOPs to be refined Control Impact on
effectivenessof jobs
performed
Process Medium 1
ott$enec1 ana$ysis (as done to estimate the capacity of the process
Through capacity estimation it (as found that furnaces are the bott$enec1 and caster need to
subordinate furnace.
GPIL, Raipur, Confdential Page 24
Illustrative
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
25/101
#urther to this@ issues pertaining to caster@ (hich resu$ted in tonnage $oss@ (ere ana$ysed.2ain reason for the same (ere as fo$$o(ing:
!. )oss due to chemistry issue/. )oss due to non F adherence to the standard parameters5. %e7uencing issues
. )ac1 of short interva$ contro$?. )ac1 of 7ua$ity gate
Po#er Saving ' +,-&MT
%pecific po(er consumption (as ana$ysed in the base$ine period and regression ana$ysis(as done to predict the specific po(er consumption at target production. *aps (ereana$ysed (hich cou$d resu$t in reduction in po(er consumption.
!. Improvement in the productivity of furnace/. &peration of furnace at fu$$ capacity5. +dherence to standard parameters such as Tap temperature@ $ad$e preheat@ $oad
rampup@
. &ptimi>ed charge mi,?. %hort Interva$ Contro$A. Effective p$anning=. Revie( mechanism8. Effective se7uencing bet(een furnace and CC2
Data ana$ysis (as done to va$idate the hypothesis. In data ana$ysis productivity of furnaces(as mapped.
9 HH ase$ine ' Dec!5 ' 2ay!
GPIL, Raipur, Confdential Page 25
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
26/101
Furnace 08 Furnace 09 Furnace100
2
4
6
8
10
12
14
16
11
12.4 12.512
15 15
Productivity - MT/Heat
Baseline Standard
MT/heat
There (as shortage of != in furnace and !0 and 8 in furnace 08. %imi$ar e,ercise (asdone for a$$ furnaces to estimate the potentia$ improvement in the po(er consumption.
Regression ana$ysis (as done on e,isting
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
27/101
%o$ution (as designed to strengthen the preventive maintenance system. #o$$o(ing systems(ere insta$$ed :
!. Preventive maintenance system/. rea1do(n management system5. Root cause ana$ysis and C+P+. E7uipment critica$ity ran1ing?. 2onth$y bad actor $istA. )ine 6a$1
GPIL, Raipur, Confdential Page 27
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
28/101
GPIL, Raipur, Confdential Page 2#
Re$iabi$ity Centred 2aintenance Phi$osophy
Illustrative
O/T!OME O/T!OME
IllustrativeIllustrative
ase$ine ' Dec!5 ' 2ay!
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
29/101
.esign and .evelopment
Project team started to thrash out issues identified during focus process and
channelize substantial improvement. Steering committee was formed to guide the
overall implementation plan. A dedicated team, comprising the task force and crossfunctional Management Action Teams', was appointed for the design and
implementation of systems.
The MATs started working on design and implementation as per the Management
Action Plan. Gaps in the MCS were plugged in and new systems mapped to increase
the effectiveness. Their progress was monitored in the Steering Committee Meeting
every alternative week. Various systems and process changes were implemented.
The new systems implemented have been added here as a procedure manual to
help as future reference or training guide for new employees.
To be MCS
Performance )oss '
%o$ution tree (as envisaged for reduction in the performance and boost productivity of thep$ant. This so$ution tree (as originated from the va$ue drivers
GPIL, Raipur, Confdential Page 2$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
30/101
GPIL, Raipur, Confdential Page 3%
Solution Tree ' Productivity 1 Per%ormance $oss
Illustrative
Approac %or )mprovement
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
31/101
As - I sM a p p i n g
( Pro duct io n
) C S * + r o ! np a p e r ( P ro c e
) a p p i n g*- ig- l e. e l /u+ le. e l
Oppo r t un i ty
I d en t i f ca t io n
( 0 r e a , 0 c t i. i t1a n a l 1 i ,C r i t 2 u eo n + r o ! n p a p e r) C S
( I d e n t i f c a t io n o 34 e 1 c o n t r i + u t o r i n . a r i a n c e 5
( ) e a u r i n g 4 e 1p r o c e i n d i c a t o r *S P C
( I n t e r . i e ! in g ,+ r a in t o r " in g ,RC 0
( P ro c e ) a t u r it 1/ S 1 t e "6 7 e c t i . e n e t u d ie
To -e!"o l u t i o n# e s i g n i n g
$( R e f n e 8 9 e . e l
o p S t a n d a r d / :P I ;
( < - i t e Pa p e rP ro duct io n) C S
( 9 r1 ru n( 9 e . e l o p
=er" o 3Re 3e rence ,a g e n d a e t c 5
3 o r re. ie!" e e t i n g
I m p l em e nta t i on
( R u n t ra i ni n g
! o r 4 - o p ( In ta l l a t i o no 3 ) C S a n dre. i edp r o c e e
( I" p le " e n ta n d c a c a d ein i t ia t i.e
( P r o d u c t i o nr e . i e !" e e t i n g
( Re. i eS O P ; , S = S
" y s t emAud i t
( S 1 te " a n de 7 e c t i . e" e e t i n ga ud i t
inc lud ingn o n &c o " p l i a n c erepo r t ing
( 0na l1 i o 3a ud i t co re
)mplementation Pase
KPI based operational scorecard for each MAT will ensure continuous improvement
in operational Performance for the entire business.
Standard Operating Procedures (SOPs) detailing new systems and streamlined
processes are handed over to respective process owners to ensure sustainability.
The audit system procedure has been developed to ensure the system elements.
GPIL, Raipur, Confdential Page 31
Illustrative
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
32/101
GPIL, Raipur, Confdential Page 32
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
33/101
Standard Operating Procedures Process, Maintenance and Quality
Shift Handover Report
Objective
Ste"atic -ando.er o !or reponi+ilit +et!een t!o -it in c-argeto enure proper coordination +et!een inco"ing and outgoing -it inc-arge
Responsibility
Annotated "ormat RA!) ' Si%t -andover
Frequency
Every Shift changeover
Procedure
Below is the diagrammatic representation of shift handover process
GPIL, Raipur, Confdential Page 33
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
34/101
Annotated Process "lo# ' Si%t -andover Report
Shift Handover Report (Format)
Common Shift Handover has been implemented in SMS, wherein shift in charge ofproduction, maintenance, CCM, quality and RM will meet and carry out handover take over
process
Shift Handover Report
GPIL, Raipur, Confdential Page 34
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
35/101
Shift Details:
A. Mention Plan vs Actual Production and actual KWH/MT
B. Mention % scrap added
C. Mention % PI added
D. Any deviation in carbon bath sample and corrective action taken
E. Any major issues in the shift pertaining to furnace, CCM or safety
F. PM done or to be done in next shift
G. Signature of incoming Shift in charge
H. Any critical observation related to quality, Raw material or communication to incoming
shift in charge
I. Any breakdown or breakout issues in CCM and corrective action taken
J. Status of daily PM of CCM
K. Signature of Out going Shift in charge
GPIL, Raipur, Confdential Page 35
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
36/101
Implementation Production and Planning Systems
Daily Review Meeting
Objective
Proper co-ordination between individual department (Mechanical, Electrical, Process, &
Quality), Improve Productivity, Establish Standards, Reducing Shutdown and breakdown, &
Improving Yield
Responsibility
RACI
Annotated Format RACI Review Meeting
Frequency
Every Day
Procedure
Explanation and Information flow. Kind of a process flow diagram.
GPIL, Raipur, Confdential Page 36
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
37/101
HOD Operation
GPIL, Raipur, Confdential Page 37
4&D F %2%
ua$ity2aintenanceE$ectrica$&peration4ead
Corrective+ction+ction )ogPreparation of+ction )og
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
38/101
Annotated Process Flow Daily Review Meeting
Annotated Terms of Reference Daily Review Meeting
Terms of Reference
Daily Production and Maintenance Review Meeting SMS
Time: 11:00 AM to 11:30 AM
Duration: 30 minutes
Location: Office of Sr. Vice President
Frequency: Daily
Objective:
Improve Productivity
Reduce Shutdown and breakdown
Reduce Power consumption per Metric Ton
Improve Quality
Attendees:
Operations Head Furnace
GPIL, Raipur, Confdential Page 3#
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
39/101
Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head
Agenda:
Review of previous action logs and taking corrective action for deviations
Plan Vs actual Production and Productivity
Raw material consumption for charge Mix
Power consumption per Ton
Daily production and plan
Allotment of RCA for major loss, breakdown and quality deviation
PM plan Vs Actual
Availability of raw material
Releasing equipments for PM
Specific consumption
Inputs:
Production Plan Compliance
Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report
Breakdown management system
RCA Policy
PM Plan
Outputs:
Action Log
GPIL, Raipur, Confdential Page 3$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
40/101
Terms of Reference
Weekly Production and Maintenance Review Meeting SMS
Time: 3:00 PM to 4:00 PM
Duration: 1 Hour
Location: Office of Sr. Vice President
Frequency: Weekly
Objective:
Improve Productivity
Reduce Shutdown and breakdown
Reduce Power consumption per Metric Ton
Improve Quality
Attendees:
Operations Head Furnace
Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head
Agenda:
Review of previous action logs
Plan Vs actual Production and Productivity. Corrective action for any deviation
Raw material consumption for charge Mix
Power consumption per Ton
Daily production and plan
Allotment of RCA for major loss, breakdown and quality deviation
PM plan Vs Actual
Availability of raw material
GPIL, Raipur, Confdential Page 4%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
41/101
Breakdown and uptime of equipments
Conversion cost, Actual Vs Plan
Inputs:
Production Plan Compliance
Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report
Breakdown management system
RCA Policy
PM Plan
Outputs:
Action Log
Terms of Reference
Monthly Production and Maintenance Review Meeting SMS
Time: 3:00 PM to 4:00 PM
Duration: 1 hour
Location: Office of Sr. Vice President
Frequency: Monthly
Objective:
Improve Productivity
Reduce Shutdown and breakdown
Improve Power consumption per Metric Ton
GPIL, Raipur, Confdential Page 41
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
42/101
Improve Quality
Attendees:
Operations Head Furnace
Operations Head - Caster
Electrical Maintenance Head
Mechanical Maintenance Head
Manager and Deputy Manager - Production
Quality Head
Agenda:
Review of previous action logs
Plan Vs actual Production and Productivity Raw material consumption for charge Mix
Power consumption per Ton
Monthly PM compliance and plan for next month
Breakdown review, RCA and CAPA status
Monthly breakdown management system and Bad actor list
Availability of raw material
Safety Review - CAPA on near miss and incident
Quality deviations
Udaan system compliance
Conversion cost
Inputs:
Production Plan Compliance
Production Deviation Report
Charge Mix Report
Quality Checklist Report
Down Time Reports
Daily Raw Material Report Breakdown management system
RCA Policy
PM Plan
Outputs:
Action Log
Annotated Process Flow Daily Review Meeting
GPIL, Raipur, Confdential Page 42
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
43/101
Purchase Focus Group Discussion
Objective:
Proper co-ordination of Purchase Department & SMS Department to ensure that the critical
spares and production consumables are available in time. Discussions between Purchase
and SMS Department also ensures that the other issues are surfaced and thereby resolved.
It also ensures that the SMS team plans for the spares in a proper timely and a phased
manner.
Responsibility:
Representatives from SMS Team and Purchase Team
Terms of Reference
Purchase Focus Group Discussion SMS
Terms of Reference
Time: 03:00 PM to 03:30 PM
Day: Saturday
Duration: 30 minutes
Location: Office of Sr. Vice President
Frequency: Weekly
Objective:
Streamline Purchase activities
Reduce instances of material stock out situation
Reduce slow moving inventory
Improve Quality of material purchased
Attendees:
Operations Head Furnace
Operations Head - Caster
Electrical Maintenance Head Mechanical Maintenance Head
GPIL, Raipur, Confdential Page 43
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
44/101
Manager and Deputy Manager - Production
Quality Head
Purchase Manager
Purchase - HOD
Agenda:
Review of previous action logs
Review status of open POs and PRs
Review vendor performance
Concern pertaining to quality of material
Inputs:
Details of POs and PRs
Material quality report
Vendor list
Outputs:
Action Log
Annotated Terms of Reference Weekly Purchase meeting
Frequency:
Weekly once
Procedure:
GPIL, Raipur, Confdential Page 44
%2%Chairman
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
45/101
Annotated Process Flow Production Loss Book
Annual Preventive Maintenance Program Review
It is a tool to assess the adequacy of existing maintenance program, incorporate new
machines and lesson learnt,
Objective:
To optimize the maintenance program with available resource and downtime target.
Responsibility:
GPIL, Raipur, Confdential Page 45
#o$$o( up ofcritica$ items
+ction )ogPreparation of+ction )og
"pares
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
46/101
Annotated Format RACI - Preventive Maintenance Program Review
Frequency:
Preventive maintenance program is reviewed every year in the month of March
Procedure:
Annotated process flow: Procedure for Preventive Maintenance Program Review
GPIL, Raipur, Confdential Page 46
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
47/101
An annotated format for equipment criticality ranking is outlined below
A.Enter the serial number
B.Enter the name of the equipment e. g. Furnace 15 T, 5.5 MW
GPIL, Raipur, Confdential Page 47
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
48/101
C.Enter the weighted average score from the equipment criticality ranking review
D.Write whether PM exists, Yes/No
E.Write PM frequency in months
F.State whether we have checklist for PM, Yes/No
G.State whether we are doing maintenance as per checklist, Yes/No
H.State whether we are doing maintenance as per checklist, Yes/No
I. Remarks, if any
J.List down the actions identified to close the gaps
K.Name of the person who is responsible to close the actions
L.Date by which actions should be completed. This date must be agreed with the person
responsible
Annual Preventive Maintenance Schedule
A structured approach to prepare and track the preventive maintenance of each equipment.Objective:
To ensure timely completion of planned maintenance
This also serves as master list of equipment under maintenance
This also gives the visibility of maintenance due in future so that advance planning and
preparation can be done to execute the due maintenance jobs on time
Responsibility:
Annotated Format RACI - Preventive Maintenance Schedule
Frequency:
Daily, Weekly, Monthly, Quarterly and yearly
GPIL, Raipur, Confdential Page 4#
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
49/101
Procedure:
Annotated process flow : Procedure for Preventive Maintenance Schedule
GPIL, Raipur, Confdential Page 4$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
50/101
Standard Checklists
GPIL, Raipur, Confdential Page 5%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
51/101
GPIL, Raipur, Confdential Page 51
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
52/101
Breakdown Slip
Objective:
1.This is the first document generated for any breakdown observed in operation. It will
initiate the corrective action from maintenance/operation department to rectify the
problem at the earliest.
2.The work against breakdown slip will be carried out by technician or can be outsourced
to the contractor. The data in the breakdown slip will form the primary information for
breakdown management system. This document registers and communicates
breakdowns occurring in machines.
Frequency: Annotated Format RACI Breakdown slip
As and when the breakdown happens
Procedure:
1.Breakdown of the equipment occurs on site
2.Once the breakdown occurs, shift engineer (operations) informs the shift engineer
(mechanical and electrical maintenance)
3.He fills the relevant entries in the breakdown slip (before attending the breakdown)
such as breakdown start time, machine on which the breakdown has occurred and
problem description, section, date, shift etc.
4.The maintenance team arrives at the site and discuss regarding the issue
5.Details during the breakdown are written in the slip by the maintenance team (job
start time, response time, root cause for breakdown etc.)
GPIL, Raipur, Confdential Page 52
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
53/101
6.Repair or replacement job is complete and plant starts
7.Operation & responsible department having breakdown meets and fills the remaining
details of the breakdown slip (after attending the breakdown) such as job end time,
equipment handover condition etc.
8.Respective section heads (operations and maintenance) review and sign thebreakdown slip
9.Breakdown slip is sent to the IT person and details are entered in Breakdown register
GPIL, Raipur, Confdential Page 53
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
54/101
Annotated Process Flow Breakdown Slip
Breakdown Slip (Format)
GPIL, Raipur, Confdential Page 54
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
55/101
0
>
C
9
?
Annotated Format Breakdown
Slip
A.Basic Details: Mention the basic details such as section, date, shift
B.Before attending the breakdown: Mention the details such as breakdown start time,machine on which breakdown has occurred, problem description
C.During Breakdown: Mention the activities done during the process of resolving the
breakdown (job start time, response time, reason for delays, team attending the
breakdown, root cause of the breakdown)
D.After attending the breakdown: Mention the details of activities post repair or replacement
by the maintenance team (job end time, equipment handover condition, details of the job
done on the equipment, spares used.
E.Remarks: Enter remarks, if any
F.Signoff: Sign-off by the staff and section heads (maintenance and operations team)
Breakdown Management System
Objective:
1.Enter the details of the breakdown slip in soft form. Conduct analysis of the data
weekly and monthly and send across to the concerned stakeholders for review and
action
2.Review frequency of equipments, mean time taken to repair, cases of feed loss
3.To provide relevant information related to bad actors so that the list can be looked into
and revised, if needed
GPIL, Raipur, Confdential Page 55
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
56/101
0 > C 9
Responsibility:
Procedure
Breakdown Management System (Format):
Annotated Format Breakdown Management System
A.Basic Details: Mention the basic details such as section, date, shift, slip no
GPIL, Raipur, Confdential Page 56
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
57/101
B.Before attending the breakdown: Mention the details such as breakdown start time,
machine on which breakdown has occurred, problem description, breakdown category
C.During Breakdown: Mention the activities done during the process of resolving the
breakdown (job start time, response time, reason for delays, team attending the
breakdown, root cause of the breakdown)D.After attending the breakdown: Mention the details of activities post repair or replacement
by the maintenance team (job end time, equipment handover condition, details of the job
done on the equipment, spares used.
E.Remarks: Enter remarks, if any
1.Production shift in charge will call maintenance staff to attend the breakdown
2.Maintenance staff will assess the situation and inform the production shift in charge
about the expected time to repair the machinery
3.In case repair time is more than 15 minutes, production personnel will raisebreakdown slip
4.On repair maintenance staff will fill the necessary details on the breakdown slip
5.Production personnel verify the repair work and acknowledge same by counter
signing on the slip
6.Manager Maintenance will review the slip on the next day
7.Manager Maintenance captures the details from slip to excel sheet.
8.Manager maintenance to carry out analysis of MTTR, % uptime from the excel sheet
9.In case breakdown does not lead to production loss or equipment belongs to utility,
maintenance personnel will raise and close the breakdown ensuring all details are
captured in the slip.
Explanation and Information flow. Kind of a process flow diagram.
GPIL, Raipur, Confdential Page 57
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
58/101
GPIL, Raipur, Confdential Page 5#%eport analysed
& correctiveaction to 'e
Analysis o) MTT% &MT*+ , Uptime
done 'y -ngineer
.O# %eview & doanalysis
rea(down slipentered in P/
/losing'rea(down sli
Jes
No
%aise t0e'rea(down in
t0e slip
%esolving
rea(down
Production shiftin charge
%aise t0e'rea(down in t0e
sli
Is brea1do(n resu$ted inproduction $oss
2aintenanceshift in charge
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
59/101
GPIL, Raipur, Confdential Page 5$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
60/101
Below is sample analysis
1$5
12%
7%
6%
Breakdown(Min.) - Crane 06
CT Motor Fault CT Power contactor issue Magnet cable cut
LT Wheel problem
%1%%2%%3%%4%%5%%6%%7%%#%%$%%
%'
2%'
4%'
6%'
#%'
1%%'
12%'#5% #35
47536%
22% 2%5 17%7%27'
53'6#'
7$'
Breakdown Analysis - Dec'14
> rea do! n t i" e* )in, '
)in
675
1154%2%
Breakdown (Min.) - Furnace 10
>u +ar pared SCR ?ault
Po!er ca+le leaage Sparing
7%5
5545 3%
Breakdown(Min.) - Crane 05
Load gear shaft damaged Contactor broken Magnet cable cut Master controler lock broken
GPIL, Raipur, Confdential Page 6%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
61/101
Line Walk
Objective:
1.Line walk is a systematic way to identify abnormalities through observations (LLF: Look,
Listen, Feel) through a daily walk in the plant area. First-hand information/observation
provides great insights into the current state of various equipment and the plant
environment.
2.This system can potentially improve the plant reliability as it reduces the forced
deterioration of the equipments which are major causes of failures. The abnormalities
found can be rectified immediately by the observer or can be forwarded to maintenance
planner for further planning.
3.Line walk summary sheet is used to register observations during a line walk on the shop
floor. Line walk sheet is divided into CBM (Condition based maintenance), 5S and Safety
NMS.
Responsibility:
Frequency:
As per the line walk schedule
Procedure:
Below is the diagrammatic representation of Line Walk system and how it is followed:
GPIL, Raipur, Confdential Page 61
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
62/101
Annotated Process Flow Line Walk
Line Walk: Format
Below is the line walk format and its description
GPIL, Raipur, Confdential Page 62
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
63/101
A.Basic Details: Mention the basic details such as line walker name, date and designation
B.Department and Section: Mention the department name and section
C.Equipment Name: Please mention the equipment name on which line walk was doneD.Code: It is essentially the category code (under which category it lies) such as 5S, safety,
condition based monitoring, spillages/leakages etc.
E.Observations: Mention the observation of the line walker
F.Priority Level: Please mention the priority level (low/medium/high)
G.Actions Required: Mention the desired actions that need to be taken
H.Responsibility: Person responsible for taking the action
I. Target Date: Target date by when the action needs to be completed
J.Status: Updated status of the activity (delayed, in progress, completed, to be taken in
shutdown)
Root Cause Analysis
Objective:
1.The purpose of Why Why Analysis/ (Root Cause Analysis) (RCA) is to identify reasons
why reactive maintenance is occurring and to instigate appropriate steps to eliminate the
root causes. The fundamental message is that: If a business does not have a Root
GPIL, Raipur, Confdential Page 63
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
64/101
Cause Analysis (RCA) methodology, the business will remain in a fire fighting (reactive)
mode.
2.This will be conducted as a tool to arrive at a root cause in a cross functional
(Maintenance and Production) manner as and when a breakdown occurs. The action
plan will be made for correcting the problem identified which will have both a short term
and a long term plan. The action plan will be reviewed in the weekly meeting for
correctness and horizontal deployment.
Responsibility:
Below is the snapshot of RCA policy which should be followed for conducting a RCA. It gives
the information on the team representation for RCA, criteria for conducting the RCA, owner
of the RCA, lead time in hrs for first draft of RCA preparation
Frequency:
As per the RCA policy
Procedure:
Below is the diagrammatic representation of the process flow for carrying out a RCA.
GPIL, Raipur, Confdential Page 64
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
65/101
RCA Template (Format):
Below is the format for the RCA (root cause analysis)
GPIL, Raipur, Confdential Page 65
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
66/101
A.Problem Statement: Mention the problem statement on which RCA needs to be done.
B.1stWhy: Mention the first element of the root cause which could have led to the problem.
C.2ndWhy: Mention the second element (2
ndwhy) that led to occurrence of 1
stWhy.
D.3rdWhy: Mention the third element (3
rdwhy) that led to the occurrence of 2
ndWhy. Follow
the steps along with findings/data to eliminate the probable causes and arrive at a rootcause
GPIL, Raipur, Confdential Page 66
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
67/101
E.Actions taken / identified: Actions taken in the form of corrective and preventive actions.
While mentioning the CAPA, please make sure that the expected date of completion for
corrective and preventive action is mentioned
F.Members name: Mention the name of the members doing the RCA and sign off
Production Deviation sheet
It is a tool to capture actual production and highlight deviation against the target. Further to
this, losses are categorized under various heads such as production loss, loss due to power
shortage, loss due to breakdown loss.
Objective:
Tool to provide details of deviation against target production and category of losses
Responsibility:
Annotated Format RACI Production Deviation sheet
Frequency:
Daily
Procedure:
GPIL, Raipur, Confdential Page 67
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
68/101
Format 1: Procedure for completing the document
An annotated format for Production deviation sheet is outlined below
GPIL, Raipur, Confdential Page 6#
MIS Manager will
collect documents
such as production
logsheet,
MIS Manager
enters the
details in the
HODs
review for
corrective
PRODUCTION DEVIATION SHEET
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
69/101
A : Mention plan for power availability
B: Mention actual Heat achieved, total production of furnace 1-10, total power consumption
by furnace only and specific power consumption without auxiliary
C: Mention actual power consumed, Power export and specific power consumption with
auxiliary. Particular cell will be highlighted red if SPC is greater than target value and green if
SPC is lesser than target value
D: Mention following details for furnace 6 -10
i) Target productionii) Target KWH/MT
iii) Target heat
iv) Actual heat achieved
v) Actual production
vi) Actual Power consumed
vii) Actual KWH/MT
E: Mention Losses such as loss due to furnace /crane breakdown, loss due to CCM. Loss
due to shortage of power and hidden loss will be calculated on its own
F: Mention charge mix i.e. Scrap and PI
GPIL, Raipur, Confdential Page 6$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
70/101
G: Mention chemistry of ore, pellet and Mix
H: Mention monthly PM of furnace and cranes
Before casting checklist
Objective
To standardi>e the chec1s done before carrying out casting on CC2. +$so this (ou$d ensurethat a$$ CC2 is in desired condition to carry out casting of one campaign (ithout any issue
Responsibility
As per RACI
Frequency
Before casting
Checklist
GPIL, Raipur, Confdential Page 7%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
71/101
Implementation Production and Planning Systems
Comprehensive Production Log sheet
Objective
To provide standard values of parameters required to be followed in a recipe for producing
molten metal
To capture actual parameters and charge mix added in the recipe
Responsibility
GPIL, Raipur, Confdential Page 71
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
72/101
RACI
Annotated Format RACI Production log sheet
Frequency
Every Day
Procedure
Production log sheet has standard values of the parameters, which are must to be followed
during melting process.
GPIL, Raipur, Confdential Page 72
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
73/101
** Post installation of liquid metal weight measurement system, actual figure of
production per heat to be noted in the log sheet.
Melter will refer to these values while preparing recipe in a furnace.
A: Mention the plan for number of heat, production, PI and scrap
B: Mention pan for Simn, KWH/MT, coke and ladle preheat temperature
C: Mention standard value of furnace temperature, Pit side temperature of transfer ladle
and slide gate ladle, CCM temperature
D: Mention furnace life and its condition
E: Mention start and end time of heat
F: Mention actual consumption of scrap and PI
G: Mention actual temperature of empty ladle, furnace temperature and filled ladle
temperature
H: Mention actual value of frequency and voltage
I: Mention load ramp up values at 30 minutes, 1.5 hours and 2.5 hours
J: Mention production data. After installation of molten metal weighing system actualvalue of production to be mentioned
K: Mention actual KWH and KWH/MT
L: Name and signature of shift manager
M: Signature of melter and in remark column any special communication which led to
deviation from standard values
Steps to be followed:
GPIL, Raipur, Confdential Page 73
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
74/101
1.Melter will charge scrap into furnace as per the plan mentioned in the log sheet.
Melter will also mention whether he has used charge basket for charging. Melter will
also mention the start time of the furnace
2.Melter then add PI and DRI as per the plan given by the production planner
3.Melter then follow the process of adding DRI and remove slag subsequently.4.Melter will write power ramp up value of furnace at 30 minutes and he will repeat
same exercise after 1.5 hour and 2.5 hour.
5.Melter will provide details of furnace frequency, voltage in the log sheet
6.Melter will also mention amount of SiMn added in the recipe. For this he will refer to
the standard value given at the top of the log sheet. For any deviation he will consult
shift in charge and mention in remark column
7.Melter then mention empty ladle temperature taken through temperature gun and
ensure same is as per the standard value mentioned in the log sheet.
8.Melter will then take the furnace temperature and if same is in the standard range, he
will tap it into the ladle
9.Melter will then monitor fill ladle temperature (pit side) and same must adhere to the
standard. In case of any issue with the temperature he will consult shift supervisor
and CCM in charge and take necessary action and mention same in the remark
column.
10.At the end he will mention end time of the process and production as per reading
shown by load cell in the crane and mention unit of power consumed.
11.Melter then signs against his column.
Later in a shift, shift supervisor and manager will check the log sheet for any deviation.
Necessary action to correct issues like high KWH/MT, cycle time, Si-Mn, load ramp up will betaken and they signed against their name.
Same process to be followed in the next shift.
Next day Production AGM and GM production will analyse the sheet for any deviation
against the target and initiate corrective and preventive action.
Equipment Criticality Ranking
Objective:
1.To rank the equipments in order of the criticality.
2.Based on the criticality of the equipments, maintenance planning (PM, line walk) can be
modified to suit the equipments (highly critical to be given more importance and
attention)
3.Also, based on the criticality, critical spares can be identified and min-max levels along
with consumption planning can be done accordingly.
Responsibility:
GPIL, Raipur, Confdential Page 74
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
75/101
Below is the RACI for preparation and review of Equipment Criticality Ranking
Annotated Format RACI Equipment Criticality List
Frequency:
Prepared once and reviewed yearly or in case of installation of new equipment
Procedure:
GPIL, Raipur, Confdential Page 75
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
76/101
Equipment Criticality Ranking (Template):
Below is the sample snapshot for equipment criticality ranking sheet
GPIL, Raipur, Confdential Page 76
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
77/101
** All pressure and temperature gauges to be calibrated once in a year or on need basis.
However critical gauges to be calibrated once in six month
A.Plant: Plant in which these equipments and sub-equipment are installed
B.Equipment Tag No. : Equipment tag number to be mentioned
C.Description: Equipment description such as name, make and rating to be mentioned
D.Maintenance interval to be maintenance such as yearly, monthly
E.Criticality Criteria: Rankings has to be done from (0-5, 5 being the highest and 0 being
the lowest). Rankings have to be given by operations, maintenance, quality and spares
availability)
F.Overall Weightage: 25% weightage is given to all the four departments rankings
(operations, maintenance, quality, safety). Based on the weighted average, one score is
calculated
G.Sections ranking: Based on the overall weightage, section ranking is calculated
Quality Checklist - Quality Gate
Objective
Quality gate is a system which is aimed at identifying problem and stopping at that at the
stage of identification so that it does not lead to bigger problem at later stage of a process.
Based on this philosophy we designed quality gate templet for the molten metal by checking
quality parameters of batch sample of a heat.
Responsibility
GPIL, Raipur, Confdential Page 77
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
78/101
Format :
Procedure:
1.Once first batch pool is ready, melter will send the sample to quality lab. Quality lab
person then checks the sample for carbon value and mention same on the sheet
along with the standard range.
2.Helper carries this sheet back to melter, who will check the sheet for carbon value. In
case carbon value is not in the standard value, he will consult shift supervisor to
lower the carbon and keep it within range
3.Melter will again send second bath sample to quality along with the quality checklist.
GPIL, Raipur, Confdential Page 7#
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
79/101
4.Melter will refer to the standard values against each bath sample and correct the
value before sending the molten metal to CCM
QC Checklist in Production
Objective:
1.To capture the actual heat parameters
2.To review these parameters against the standard and take necessary corrective action
Responsibility:
Below is the RACI for the same
Frequency: Daily
Format:
Sequencing between furnace and caster
Objective:
1.To have effective sequencing plan, which would result in subordination of CCM to
furnace
2.To have sufficient time between campaign for daily caster maintenance
3.Utilization of CCM and associated consumables at fullest to ensure reduction in cost
GPIL, Raipur, Confdential Page 7$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
80/101
Responsibility:
Below is the RACI for the same
Sequencing Plan:
Sponge Pellet and ore Re*uirement 2s "ul%ilment
Objective3!. To stream$ine p$anning of pe$$et and ore re7uirement
GPIL, Raipur, Confdential Page #%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
81/101
/. To estab$ish service $eve$ agreement bet(een %ID and %2% departments
Responsibility3
R+CI for the same is as be$o( :
Format
A: Date to be mentioned
: Pe$$et chemistry and 7uantity to be mentioned
C: #ines chemistry and 7uantity to be mentioned
D: Iron ore chemistry and 7uantity to be mentioned
E: Remar1 for any deviation
#: This to be fi$$ed by %ID
Operational Benefit Tracker and KPI Dashboard
Objective:
GPIL, Raipur, Confdential Page #1
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
82/101
3.To review plan vs actual KPI achievement daily and week on week basis
4.To ensure that the gaps in achieving the target production are reviewed stringently and
action are taken to resolve the issues preventing the plant to achieve the desired KPI
Responsibility:
Below is the RACI for operational benefit tracker and KPI Dashboard
RACI-Operational Benefit tracker and KPI Dashboard
Frequency:
Data Updation: Daily
KPI dashboard generation and performance review: Weekly
Procedure:
Below is the process flow for Operational Benefit tracker and KPI dashboard
GPIL, Raipur, Confdential Page #2
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
83/101
O p era t o ns t e a m t opro v ide
dai lypro duct io
na c 0 i e v e d
a n dr e a s o n s)o r ) eedloss + i )
a n y
M a i n t e n a nc e t e a m t o
pro v idein )o o n
)eed lo ssd u e t o
' r e a ( d o wns + ac t io n
ta(en +% / A e t c 1
2ua l i tyt e a m t opro v ided a t a w r t3ua l i ty
p a r a m e t e rs s u c 0 a s*e!t $ + LOI
!,$ +' la ine e tc 1
% e c o r dt 0 e d a t a
in t0etem pla te +p o p u l a t et 0 e 4 P I
d a s 0 ' o a r d
% ev ewt 0 e 4 P I
d a s 0 ' o a r dwee(ly +
ta(eac t io ns
a n ds i g n o 5
t 0 eo pera t io na l ' e n e f t
t rac(er
Operational Benefit tracker and KPI Dashboard (Template):
First Sheet:Below is the snapshot of the first sheet of the template. Same template is
followed for both the Pellet Plants (0.6 MTPA and 1.5 MTPA)
A.Project Week: Mention the project week
B.Date: Mention the date for which production is being tracked
C.Baseline and target production: The cells refer to the baseline production, avg. ball mill
feed % Fe(t) during the baseline period and target production
D.Actual production details: Mention the actual ball mill feed Fe(t) %, baseline LOI %,actual LOI % and reported production
E.Production improvement: Tracks the target incremental daily tonnage against the actual
achieved incremental daily tonnage
Second Sheet:Below is the snapshot of the second sheet of the template (weekly tracker)
GPIL, Raipur, Confdential Page #3
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
84/101
A.KPI: Mention the KPI being tracked
B.KPI details: For each day, baseline production, target production, actual production,
operational benefit, remarks for exclusion if any are being tracker
C.Week no and its details: Mention the week no and the dates in the particular week
D.Cumulative data for the week: Mention the cumulative production for the week afterexclusions
E.Remarks: Mention the details of the exclusion because of which the day is not taken in
the operational tracker
F.Exclusion: Mention the exclusion code because of which the day is not taken in the
operational tracker such as Planned shutdown, forced shutdown, issues faced in other
departments hampering SMS Plants production, power supply failure etc.
Third Sheet:Below is the snapshot of the third sheet of the template (overall weekly tracker)
Fourth Sheet:Below is the snapshot of the KPI dashboard
GPIL, Raipur, Confdential Page #4
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
85/101
KPI dashboard contains:
1)Production Furnace 6-10 and furnace 1-5. Red bar shows that production is below
target and green shows production above the target value
2)KWH/MT Furnace 6-10 and furnace 1-5. Red bar shows that KWH/MT is above
target and green shows below the target
3)Loss due to power, breakdown and production inefficiency
4)Productivity MT/Heat
5)Percentage heat achieved
Process Standard operating procedure (SOP)
Objective:
GPIL, Raipur, Confdential Page #5
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
86/101
To standardize the process i.e melting process, casting process, ladle preparation
Responsibility:
RACI has been defined in the SOP and same to be followed
SOPs :
1.SOP for Ladle
2.SOP for melting process
3.SOP for quality
4.SOP for tundish
5.SOP for CCM6.SOP for coil insulation
7.SOP for attaining higher life of Ladle
Daily Caster Maintenance Checklist
Objective
1.To standardize the checks on Caster
2.To avoid breakdown in caster
Responsibility:
Below is the RACI for daily caster maintenance checklist
GPIL, Raipur, Confdential Page #6
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
87/101
Format :
GPIL, Raipur, Confdential Page #7
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
88/101
A : Mention date and shift in which checks were carried out
: Chec1s@ (hich are to be referred
C: %tandard parameters against (hich chec1s to be mapped
D: %tatus of the e7uipment to be mentioned
E: Remar1 to be mentione din case of any deviation
#: Concerned person needs to sign on the sheet
Process *uality cecks
Objective3
!. To meet 7ua$ity parameters as per I%
Responsibility3
R+CI for the same is as be$o(:
GPIL, Raipur, Confdential Page ##
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
89/101
Format :
GPIL, Raipur, Confdential Page #$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
90/101
Procedure3
+: 2ention heat number
: 2ention campaign number
C: 2ention furnace number
D: 2ention tapping time
E: CC2 on (hich casting done
#: 2ention chemistry in terms of Carbon@ 2n@ %i@ %u$phur and Phosphorous
GPIL, Raipur, Confdential Page $%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
91/101
Inventory Tracking
Objective3
!. To ensure smooth supp$y of ra( materia$ and avoid stoc1 out situation
Responsibility3
e$o( is the R+CI for the inventory trac1ing
GPIL, Raipur, Confdential Page $1
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
92/101
Format
Tool Box standardization and Audit
Objective3
!. To ensure right too$s are avai$ab$e and to avoid time (astage in searching too$s
Responsibility3
GPIL, Raipur, Confdential Page $2
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
93/101
R+CI for the Too$ o, standardi>ation and audit
GPIL, Raipur, Confdential Page $3
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
94/101
Format
Bad Actor list
Objective:
1.To identify the bad actors affecting production (feed loss or plant hold) with frequent
breakdowns/failures
2.To take actions on the bad actors and do probable cause analysis to resolve the issues3.Reduction in failures of major equipments would reduce spares consumption/MT
GPIL, Raipur, Confdential Page $4
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
95/101
Responsibility:
Below is the RACI for Bad Actor list preparation and probable cause analysis
Frequency:
Breakdown management system analysis: weekly and monthly
Bad actor list review: Monthly
Bad Actor List (Snapshots):
Procedure:
GPIL, Raipur, Confdential Page $5
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
96/101
P e r ) o r m r e a ( d o w
nM a n a g e m
e n ts y s t e m
a n a l y s i s
P r e p a r a t i on o ) a da c to r l is t' a s e d o n
t 0 e r e a ( d o w
nm a n a g e m
e n ts y s t e m
a n a l y s i s
% e v i e wa n d
a p p r o v et 0 e ' a d
a c to r l is t
Ta (ea c t io n s o n
t 0 e ' a da c t o r s o rc o n d u c t% / A o r
p r o ' a ' l ec a u s e
a n a l y s i s
% e v i e wa n d
u p d a t et 0 e ' a da c t o r s
m o n t 0 onm o n t 0
Below is the procedure for Bad Actor list preparation
Sustainability Pase
The System Audit is a tool to verify that all the appropriate system elements are
being installed and to check that they continue to be pursued.
For the purpose of the audit, every single component of a system is listed three times
and is interrogated in different ways to assess the overall status of implementation.
The four states that are taken into account are:
S1 Compliance
S2 Understanding
S3 Usage
S4 Culture
Only the first three states of this model are measured since the Culture state
already represents full ownership of the system.
S1: Compliance. The system element has been introduced and it is being used by
ensuring compliance. Direct supervision is required. After a few weeks no element
should have a pending S1 status unless a very good reason is available.
GPIL, Raipur, Confdential Page $6
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
97/101
S2: Understanding. The system element is being used, but people in question do
not see yet the whole benefit of using the element. If the review process was taken
away system elements usage would probably stop. Short interval controls and
review process are vital to ensure continuous compliance through proactive
coaching.
S3: Usage. People now realize the whole benefits of the system and how to use it to
improve their performances. But they still see it as a new system and need support.
S4: Culture. Having complied with and understood the purpose of the systems,
people now own it. The full benefits are derived and modifications / improvements
may also be volunteered. It can be assumed that the system element will continue tobe used. At this stage the management can begin to rely on delegation of system
elements rather than any direct review or supervision. In this manner the risk of
having elements dropped out is minimized as the ownership will not be lost or would
be tackled at an inappropriate management level.
Step by Step Instructions
Please find below following key guidelines:
Audited by the name of the manager who conducted the latest audit.
A position that is being audited should be captured as appropriate.
Status and Score the sheet is divided into 3 status sections. The scoring method is
also indicated here.
Audit Level Number S1, S2, S3
System Element each system element is listed out under each section.
Target the person/position to which the auditor should focus their investigation
Engineer, Sr. Engineer, Manager, Sr. Manager, AGM, DGM
Section In charge
Shift In charge
Supervisor
Questions Questions that need to be asked to audit the behavioural changes.
Score under each status the score, 0, 1 or 3 is indicated:
GPIL, Raipur, Confdential Page $7
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
98/101
S1: Use score 0 for not installed, not correct. Use score 1 for installed and partially
correct. Use score 3 for installed or completely correct.
S2 and S3: Use score 0 for not correct. Use score 1 for partially correct. Use score 3
for completely correct.
These cells auto-format red for score 0, yellow for score 1, green for score 3.
P.S: If a category is not applicable then leave the cell blank so it will not be counted
as 0.
Weekly scores would be measured. For the system elements the audit is conducted
on Daily basis, the Weekly Score will be the arithmetic average of Daily Scores
Total Score the total score divided by the maximum possible score expressed as a
percentage.
Question for S2 and S3 in place of actions the audit questions should be closed
ended questions.
These questions should be updated on Quarterly basis in order to ensure overall
system adoption.
Annotated "ormat3 Audit Template
Annotated "ormat3 Audit Result
The audit scores must be reviewed on a weekly basis until a performance of S1
ninety percent (90%) S2 eighty percent (80%) and S3 seventy percent (70%) are
achieved. Until these performance levels are attained, the system is not fully installed
and or in use. It is the responsibility of the associated Management Action Team
GPIL, Raipur, Confdential Page $#
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
99/101
(MAT) to identify any relevant problems/issues and initiate actions to resolve this as
quickly as possible.
GPIL, Raipur, Confdential Page $$
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
100/101
Appropriate Management Styles
In line with the Leader Behaviour Analysis Model, the outcome of the audit helps
dictate the kind of actions that are required see table 1 for details.
Table 1: Appropriate Management Styles
%tate
%ystem+doption
%tate of 2ind+ppropriate2anagement%ty$e
Re7uired Contact Time
%! Comp$ianceBna(are andunab$e
Direct#u$$ time or very high ' increaseattention if score is $o( or fa$$sbac1.
%/Bnderstanding
+(are and unab$e Coach%ignificant time ' focus onassurance and positive feedbac1.
%5 Bsage +(are and ab$e %upport2oderate ' as %! and %/ scoresstabi$i>e step bac1 from directinvo$vement as much as possib$e.
% Cu$tureBna(are and ab$e9ta1en forgranted
De$egate 2inima$
All action logs should contain the appropriate type of activities to ensure that the
issues faced with any one particular element are addressed. Examples:
If a previously installed element has completed dropped from usage, people need to
be told exactly why this is wrong and what they must do (directive).
If an installed element is not being filled out correctly, you should get the appropriate
owner to go and invest significant time and detail in understanding why it was not
filled out and making sure that the user understands how to use it correctly (coach).
If the actions coming out of a meeting are not as good as they should be then the
appropriate area owners need encouragement and support to build on the current
status.If the system is not throwing out any concerns under S1, S2 and S3 then the results
should be coming through. In this case the amount of time invested in the review
process can be lessened.
Responsibility and Frequency
The Audit must be conducted on all MCS elements at least once a week. In the initial
stages of roll-out audits will be conducted once per week by the consultants as wellas the taskforce members assigned and results will be forwarded to the MAT for
GPIL, Raipur, Confdential Page 1%%
-
7/25/2019 20150212-GPIL-SMS- SOP - Final (2)
101/101
review. In later stages the Team Leaders will be responsible for conducting the audit
for their Team on all the MCS elements and forward it to their Department Head as
well as to an auditor outside the concerned Department. Results will be reviewed
both at the MAT meeting and Steering Committee.