2015 Snake River Salmon Recovery Board Project Application...Pre-Application Due Date: April 2, 2015...

39
Pre-Application Due Date: April 2, 2015 Draft Application Due Date: April 29, 2015 Final Application Due Date: July 17, 2015 1 2015 Snake River Salmon Recovery Board Project Application Complete Application Checklist Summary: Through the application process each of the following elements, depending on the project type, will need to be created and submitted at some point before the final application due date. Local Snake River Salmon Recovery Board Application this does not need to be submitted in PRISM, but is required and will assist in finalizing a complete application may elements including the project title, description, property details, etc., can be copied and pasted throughout. The SRSRB Application includes this entire form, the pre-application, draft application, and final application sections. The relevant Salmon Project Proposal (Appendix C, found in RCO Manual 18), which includes the response to the SRFB Review Panel comments if required. Three maps: 1. a general vicinity map, 2. a detailed worksite map for planning and restoration projects or a parcel map for acquisitions, and 3. a map showing the project’s Area of Potential Effect with the section, township, and range identified. A minimum of two site photographs in JPEG file format. The proposed project design including plans, specifications, and a design report if available (for restoration projects only). Detailed Cost Estimate. Landowner Acknowledgement Form (Appendix F, found in RCO Manual 18). Barrier Evaluation Form (fish passage construction and design projects only). Correction Analysis Form (fish passage construction projects only). Intensively Monitored Watershed Certification (when relevant). Waiver of Retroactivity (for acquisition projects only). Deliverables from prior phases of the project (when relevant). Project partnership contribution form (when relevant, Appendix G, found in RCO Manual 18). Complete required elements of PRISM Online Application: (https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn). Please contact the Snake River Salmon Recovery Board Lead Entity office for questions or assistance with the application and application process at 509-382-4115 or [email protected].

Transcript of 2015 Snake River Salmon Recovery Board Project Application...Pre-Application Due Date: April 2, 2015...

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    1

    2015 Snake River Salmon Recovery Board Project Application

    Complete Application Checklist Summary:

    Through the application process each of the following elements, depending on the project type, will need to be created and submitted at some point before the final application due date.

    Local Snake River Salmon Recovery Board Application – this does not need to be submitted in PRISM, but is required and will assist in finalizing a complete application – may elements including the project title, description, property details, etc., can be copied and pasted throughout. The SRSRB Application includes this entire form, the pre-application, draft application, and final application sections.

    The relevant Salmon Project Proposal (Appendix C, found in RCO Manual 18), which includes the response to the SRFB Review Panel comments if required.

    Three maps: 1. a general vicinity map, 2. a detailed worksite map for planning and restoration projects or a parcel map for acquisitions, and 3. a map showing the project’s Area of Potential Effect with the section, township, and range identified.

    A minimum of two site photographs in JPEG file format.

    The proposed project design including plans, specifications, and a design report if available (for restoration projects only).

    Detailed Cost Estimate.

    Landowner Acknowledgement Form (Appendix F, found in RCO Manual 18).

    Barrier Evaluation Form (fish passage construction and design projects only).

    Correction Analysis Form (fish passage construction projects only).

    Intensively Monitored Watershed Certification (when relevant).

    Waiver of Retroactivity (for acquisition projects only).

    Deliverables from prior phases of the project (when relevant).

    Project partnership contribution form (when relevant, Appendix G, found in RCO Manual 18).

    Complete required elements of PRISM Online Application: (https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn).

    Please contact the Snake River Salmon Recovery Board Lead Entity office for questions or assistance with the application and application process at 509-382-4115 or [email protected].

    https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    2

    Pre-Application Section (This section must also must be included as part of the Draft and Final Applications if you don’t submit a pre-application).

    Project Title (less than 50 characters including spaces, please create a title that accurately reflects the project): Penawawa Creek: Instream Habitat Rehabilitation

    Submitting Organization: Whitman Conservation District in partnership with Eco Logical Research, Inc.

    Project Contact Information (Complete for each project contact)

    Mr. Ms. First Name: Nancy Last Name: Hoobler

    Address: 601 N. Main, Suite A City/Town: Colfax State: WA Zip: 99111

    Telephone # (509) 288-4644 Cell # ( ) -

    E-mail address: [email protected]

    Project Location: Provide a brief description of the project location including watershed, stream

    reach, position in watershed and if the project is within an major or minor spawning area (MSA or mSA)

    and within a designated restoration or protection reach (according to the Funding Habitat Restoration

    Projects for Salmon Recovery in the Snake River Region Booklet and Snake River Salmon Recovery

    Plan (2011)).

    Penawawa Creek is a mainstem tributary to the Snake River in southeast Washington and drains 122

    km2 (47 mi2) of the Palouse Hills level 4 ecoregion (Omernik and Griffith, 2014). The project will be

    located within the lower 1.5 km (1 mi) of the mainstem of Penawawa Creek. The lower 1.5 km (1 mi) is

    within United States Army Corps of Engineers (USACE) land. All of the land upstream from the

    confluence with the Snake River is privately owned, and will not be addressed in this proposal.

    Maps: Provide both a map illustrating project vicinity and a site map. Map descriptions can be placed

    in this section but maps should be attached as a separate page. (Contact SRSRB staff for assistance

    if needed). Figures are located at the end of this document.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    3

    Figure 1. Proposed location of stream channel rehabilitation on the lower 1.5 km of Penawawa Creek

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    4

    (green line). Post assisted log structures (PALS) will be implemented in the channel on United States

    Army Corps of Engineer property.

    Figure 2. Area of Potential Effect for the proposed stream rehabilitation on Penawawa Creek

    represented by the green outline surrounding the channel. The influence of the proposed structures is

    not expected to go beyond 20 meters on either side of the stream channel.

    Figure 3. Overhead view of the proposed project area on Penawawa Creek within United States Army

    Corps of Engineers property. The riparian zone in this section is in recovery, but instream habitat

    complexity is low. Post Assisted Log Structures in this section will promote geomorphic and hydraulic

    change to the channel that is beneficial to juvenile and adult steelhead.

    Figure 4. A beaver dam upstream of the proposed project area on Penawawa Creek. At the time this

    photo was taken, steelhead were witnessed spawning downstream of this beaver dam. Beaver Dam

    Analogues mimic natural beaver dams to produce the same ecologic benefits as real ones.

    Figure 5. The conceptual design and hypothesized effects of a bank attached Post Assisted Log

    Structure. The structure increases hydraulic roughness and complexity which leads to predictable

    geomorphic change in the channel during high flows.

    Project Description

    Must be less than 1,500 characters including spaces.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    5

    Important Note:

    Many audiences, including the Salmon Recovery Funding Board (SRFB), SRFB’s Technical Review

    Panel, media, legislators, and the public who may inquire about your project, use this description.

    Provide as clear, succinct, and descriptive an overview of your project as possible – many will read

    these 1-2 paragraphs! This project description will be used in your online PRISM application and

    can be used in the Salmon Project Proposal, please take your time to craft a well written project

    description.

    Your description needs to include the following:

    Who is sponsoring the project

    Type of project (acquisition, restoration, development, design)

    Location information

    Overall specific goal to be achieved and why it is important to do at this time

    Primary type of habitat to be protected or restored and to what extent the project will protect,

    restore, and/or address salmon habitat

    Priority species supported

    Primary outdoor recreation opportunity to be provided if relevant

    What will be acquired, restored, developed, and/or designed with grant funds

    Example of a Project Description:

    The Jones Nonprofit will use this grant to acquire approximately 20 acres to protect salmonid habitat. Five of

    these acres will be restored. The property is located in B County, adjacent to Liquid Creek, east of Highway

    1101. The acquisition will help conserve the ecological integrity and biological diversity of the Liquid Creek

    watershed by protecting parcels containing critical riparian habitats and linking these parcels to existing public

    lands. The primary habitat that will be protected is riparian and in‐stream habitat. Approximately 20 acres will

    be acquired, 10 acres of riparian and wetland habitat and 10 acres of adjacent upland. Five of the riparian

    acres will be restored by planting native vegetation. The primary species supported by these habitats are

    Endangered Species Act listed anadromous fish including coho, summer and fall Chinook, chum, and

    steelhead.

    This acquisition has been identified as a high priority for B County, and the protection of functioning habitat is

    the highest priority in the Northwestern chapter of the Salmon Recovery Plan. The Jones Non‐ Profit group has

    worked closely with B County, the local school district and the Friends of Liquid Creek to secure funding and

    other support for this project. The University of Fun Education has agreed to conduct the baseline study and

    develop a restoration plan. This project builds upon the Land Trust’s adjacent land holdings and the Liquid

    Creek Preserve which has already conserved 45 acres and 3,700 feet of Liquid Creek

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    6

    The PRISM database limits project descriptions to 1500 characters (including spaces); any

    excess text will be deleted. Additional detail should be provided in the project proposal!

    Your Project Description: The Whitman County Conservation District (WCD) in cooperation with Eco Logical Research, Inc. (ELR) will use this grant to install up to 50 Post Assisted Log Structures (PALS; e.g. Wheaton et al., 2012) on Penawawa Creek from the mouth to approximately 1.5 km (1 mi) upstream on USACE property. The limiting factors on Penawawa Creek were identified as excessive fine sediment, low stream flow, and poor habitat complexity related to a lack of large woody debris and poor riparian function (SRSB, 2013). The primary benefits to adding high densities of large woody debris using PALS are to (1) increase instream habitat complexity through the development of pools, bars, and structural refugia for juvenile salmonids, (2) temporarily store fine sediment around the installed structures, and (3) and back up water behind structures to encourage hyporheic exchange and provide localized floodplain access. Therefore, this project addresses the goals of SRSB Priority Protection reaches by addressing factors related to riparian function, instream flow, and water quality parameters. The project will primarily benefit ESA listed Snake River steelhead and is located in a designated priority protection reach in a minor spawning area as identified in the Salmon Recovery Plan for SE Washington and regional the three year work plan.

    Pre-Application Cost Estimate: Note: Please only use this section for the Pre-Application – the Cost Estimate for the Draft and Final Applications must be more detailed and in a separate document or spreadsheet – please contact LE Staff for examples. List SRFB request, match, and total project costs.

    Budget Items Cost/Unit Unit Matching

    Funds SRFB

    Request Total Project

    Cost

    Whitman Conservation District Admin 5,000 1 - 5,000 5,000

    Watershed Assessment 2,000 1 - 2,000 2,000

    Develop Restoration Plan 1,000 1 - 1,000 1,000

    Project Management and Site Visits 3,000 1 1,000 2,000 3,000

    Posts for construction of 60 structures 6,000 1 - 6,000 6,000

    Large Woody Debris 7,000 1 7,000 - 7,000

    Post Driver Rental 2,500 1 2,500 - 2,500

    Construction labor 8,000 1 - 8,000 8,000

    Implementation Monitoring 1,000 1 - 1,000 1,000

    Acquisition of Permits 3,000 1 - 3,000 3,000

    Cultural Resource Survey 3,000 1 - 3,000 3,000

    Final Report 2,000 1 - 2,000 2,000

    Total Matching $10,500

    Total SRFB Request $33,000

    Total Project Cost $43,500

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    7

    Restoration Project Preliminary Design Requirements Starting in 2013, the SRFB changed the requirement for design review of restoration projects which exceed $250,000 in SRFB requested funds. If your grant request from the SRFB will exceed $250,000 you will be required to submit a preliminary design or equivalent with the final application. Check the SRFB Manual18 (Appendix D) for information of the Design Requirements or contact LE Staff. Please check the appropriate box below as to whether the design requirement can be met.

    I have preliminary designs completed and have cross walked them w/ SRFB requirements

    I am currently working on preliminary design and may be able to complete by final application deadline

    I do not have preliminary designs and will not have them by the final application

    Evidence that this project is part of the Snake River Salmon Recovery Plan: List the HWS project number and the title of the project as stated in the Snake river Salmon Recovery Region Provisional Work Plan 2013-2018. If project is not directly stated in the Work Plan, list the general project category your project pertains to and describe the correlation.

    Work Plan Number(s): 35-00406 – Increase Habitat Complexity: Installation of high densities of large woody debris mimic natural processes that lead to the development of pools, structural refuge for juvenile salmonids, and sorted gravel bars for adult salmonid spawning areas. 35-00407 – Restore Floodplain Connectivity and Function: PALS and BDAs create constriction points in the channel that force water onto the floodplain during high flows.

    35-00408 – Channel Length and Sinuosity: PALS increase thalweg sinuosity by disrupting uniform flow regimes in homogenous channels. Following high flow events, PALS also promote lateral stream movement and the development of bars which increase sinuosity of the channel at the reach level.

    This is the end of the PRE-APPLICATION

    When submitting your draft application, make sure to update the pre-application information where required as well as completing the following draft application. The pre-application will become part of the draft application to reduce redundant forms.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    8

    Draft Application Section (This section is in addition to the pre-application, please update sections above in the Pre-Application section where necessary).

    Salmon Recovery Funding Board

    Draft Application Information

    Draft Date Submitted to SRSRB 4/29/2015

    Vicinity / Site Maps & Photos Please submit photos as JPEG or other non PDF picture format. Maps and designs maybe submitted in photo or PDF format. If maps and photos were submitted with the pre-application, re-submit only if they have been updated.

    Attached Vicinity Map

    Detailed Worksite Map (planning and restoration projects) or parcel map (acquisition projects)

    Map showing the project’s Area of Potential Effect (APE) with Section/Township/Range A minimum of two (2) Aerial or Site Specific Photos Attached Designs (conceptual, preliminary, or final) or Field Sketches

    Salmon Project Proposal To complete this section download the Salmon Project Proposal template that fits your proposed project and attach as a separate document. Check appropriate box below. NOTE: This project proposal will be used primarily to evaluate your project and is the meat of the application. Please include appropriate metrics within the body of the text. The Salmon Project Proposal template documents listed below can be found at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in Appendix C of SRFB Manual 18.

    Attached 1) Restoration, Acquisition, and Combination (Restoration & Acquisition) Project

    2) Planning Projects (Assessment, Design, and Study) and Combination (Planning & Acquisition) Projects

    3) Barrier Inventory Projects

    Projects that address Imminent Threats – Population Effect Determination When the Lead Entity Committee reviews and evaluates project proposals, addressing an Imminent Threat to salmon and/or steelhead is taken into consideration Following the submission of the draft application, if your project addresses an Imminent Threat as identified in the Funding Habitat Restoration Projects for Salmon Recovery in the Snake River Region Application Booklet, the Snake River Salmon Recovery Board Regional Technical Team (RTT) will be consulted on the severity of Imminent Threats being proposed for restoration funding. The RTT will consider population level effects the project may have if the project is implement and provide a technical recommendation to the LE Committee either (I) large improvement on a population scale or (i) minimum impact on a population scale for project scoring and evaluation.

    RTT Technical Opinion (Filled in by LE Staff)

    Population Scale (I) OR Local Scale (i)

    http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    9

    Landowner Acknowledgment Forms To complete this section, download the landowner acknowledgment form (different from the landowner agreement form), have the landowner complete and sign the form, and submit a copy with the draft application. Draft applications without signed agreement forms may not be considered by the SRSRB for final scoring and ranking. Remember to complete a Landowner Acknowledgement form for each separate Landowner.

    These forms can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.

    Number of Landowners and Attached Landowner Forms Number: 1

    Project Proposal Cost Estimate Please provide a detailed cost estimate to supplement the general cost information required by PRISM (it is easiest to align the cost estimate you create with the cost fields from PRISM). Applicants may use their own formats, but, in general, restoration and design project cost estimates should separate costs for individual construction, design, and project administration elements and tasks (e.g., survey, design, permits, cultural resources, materials, labor, and equipment). Acquisition projects should include costs for land, incidentals (including, as appropriate, appraisals, review appraisals, hazardous substance assessment, title reports and insurance, baseline documentation for conservation easements, closing, recording fees, wetland delineation, fencing, signing, taxes), boundary survey, cultural resources review, demolition, noxious weed control, relocation, stewardship plan, and project administration. Contingency costs should NOT be included as a separate line item in the attached cost estimate. For more information and eligible costs, see RCO Manual 18. For this section, you may use an existing example cost estimate which can be found on the SRSRB website at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ OR you may submit a detailed budget in your own format. Please check the appropriate project budget type below that you have completed.

    Attached

    Detailed Cost Estimate

    Barrier Evaluation Form (Fish Passage construction and design projects only) This form is used to document fish passage barrier conditions. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.

    Attached

    Barrier Evaluation From

    http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    10

    This is the END of the DRAFT APPLICATION.

    Don’t forget to update the pre-project information to reflect

    changes, if didn’t submit in the pre-application round fill out the pre-application information on your draft submittal.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    11

    Final Application Section (This section is in addition to the pre-application and draft application sections, please update sections above where necessary).

    SRFB Final Application

    In completing your final application make sure to update changes in your project on the sections listed under Pre-Application and Draft Application in track changes to aid in final review and comment of your project. It is also important to update previous sections to reduce replication in the final application.

    Final Date Submitted to SRSRB

    Non-profit Organizations must answer the following questions

    Is your organization registered as a non-profit with the Washington Secretary of State? If so, what is your Unified Business Identifier (UBI) number?

    No Yes, UBI #:

    What date was your organization created?

    How long has your organization been involved in salmon and habitat conservation?

    Application Questionnaire All applicants must answer the following questions.

    Property Details Enter a brief description (250 characters or less) of the Property and the work that you will complete there.

    For acquisition projects please provide some basic information about the Property (acreage, acquisition type, site characteristics, etc…).

    Driving Directions (provide directions that will enable staff to locate the project):

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    12

    For any grants listed in the Summary of Funding Request and Match Contribution Section, are there any restrictions on the use of these grant funds (double click on box to select it)? No Yes

    When and how long will the grant funds be available to this project?

    Describe the type of donated labor (skilled and unskilled), donated equipment, and donated materials that will be used for this project, identified in the Summary of Funding Request and Match Contribution Section.

    What is the current land use of the site, and its history? Describe past human uses and salmon habitat functions. Are there any structures on site?

    Planning Questions These questions are specifically related to Cultural Resources. These questions must be answered, even if they are redundant or repetitive – i.e., please do not reference other sections of your application or state that they have previously been addressed. The response to these questions will be reviewed independently of the rest of your application.

    Has the worksite been investigated for historical, archeological, or cultural resources? If yes, when did this occur and what agencies and tribes were consulted? Make sure to attach related documents (letters, surveys, agreements, etc.) to your project in PRISM.

    What is the current land use of the site? Has there been ground disturbances historically, if so, what are/were those disturbances? Is there any fill where ground disturbance is proposed? If known, how deep is the fill?

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    13

    Is the worksite(s) located within an existing park, wildlife refuge, natural area preserve, or other recreation or habitat site? If yes, name the area and specify if the land is owned by local, state or federal government.

    Correction Analysis Form (Fish Passage construction projects only) This form is used to document how a fish passage barrier will be corrected. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.

    Attached

    Correction Analysis From

    Intensively Monitored Watershed Certification (when relevant) If the proposed project is in or near an intensively monitored watershed, attach a letter from the regional organization (Snake River Salmon Recovery Board) certifying that the proposed project contributes to and will not negatively affect ongoing data collection and salmon restoration efforts.

    Attached

    Intensively Monitored Watershed Certification

    Waiver of Retroactivity (for acquisition projects) Required if a land acquisition will occur before project agreement. Waivers of Retroactivity are discussed in detail in SRFB Manual 18. Note that they must be secured before closing on the property

    Attached

    Waiver of Retroactivity

    Deliverables from Prior Phases of the Project If you have received a planning or design grant from SRFB for your proposed restoration project, then you must submit completed design deliverables, at a minimum preliminary designs, from that grant as part of your final application.

    Attached

    Deliverables from Prior Phases

    http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    14

    Project Partnership Contribution Form State agencies are required to have a local partner and must attach a signed Partner Contribution Form. A Partner Contribution Form also is recommended, but not required, for other eligible applicants where a third party is providing a funding match. This form can be found on the SRSRB web site at: http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.

    Attached

    Project Partnership Contribution Form

    Complete required elements of PRISM Online Application

    Many of the questions and information that needs to be completed for the PRISM Online Application can be taken directly from this SRSRB application (and is designed to do so). Work with SRSRB Staff to complete. PRISM Online can be accessed here: https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn

    Work with SRSRB Staff to complete the PRISM Online Application

    http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/https://secure.rco.wa.gov/Prism/Sponsor/Account/LogOn

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    15

    Permits

    Please check the appropriate boxes to indicate required and/or anticipated permits. General permit information can be obtained at the Governor’s Office for Regulatory Innovation and Assistance by calling 1-800-917-0043 or on the web at: http://www.oria.wa.gov/site/alias__oria/347/default.aspx.

    Permits Comments Regarding Permit Status

    Aquatic Lands Use Authorization (Dept of Natural Resources)

    Building Permit (City/County)

    Clear & Grade Permit (City/County)

    Cultural Assessment [Section 106] (CTED-OAHP)

    Dredge/Fill Permit [Section 10/404 or 404] (US Army Corps of Engineers)

    Endangered Species Act Compliance [ESA] (US Fish & Wildlife/NMFS*)

    *(The SRFB has a permit programmatic with NMFS such that for a SRFB Funded project you just need a Self-Certification 4(d) Rule, Limit 8 Form signed and attached. Find the form at http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/ or in SRFB Manual 18.

    Forest Practices Application [Forest & Fish] (Dept of Natural Resources)

    Health Permit (Dept of Health/County)

    Hydraulics Project Approval [HPA] (Dept of Fish & Wildlife)

    NEPA (Federal Agencies)

    SEPA (Local or State Agencies)

    Shoreline Permit (City/County)

    Water Quality Certification [Section 401] (County/Dept of Ecology)

    Water Rights/Well Drilling Permit (Dept of Ecology)

    Other Required Permits (identify)

    None – No permits Required

    http://www.oria.wa.gov/site/alias__oria/347/default.aspxhttp://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/http://snakeriverboard.org/wpi/salmon-recovery/lead-entity-committee/grant-applications/

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    16

    This is the END of the FINAL APPLICATION.

    Don’t forget to update the pre-project information to reflect changes, if didn’t submit in the pre-application round fill out the

    pre-application information on your draft submittal. Please contact the Snake River Salmon Recovery Board Lead Entity office for questions or assistance with the application and application process at

    509-382-4115 or [email protected].

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    17

    Figure 1. Proposed location of stream channel rehabilitation on the lower 1.5 km of Penawawa Creek (green line). Post assisted log structures (PALS) will be implemented in the channel on United States Army Corps of Engineer property.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    18

    Figure 2. Area of Potential Effect for the proposed stream rehabilitation on Penawawa Creek

    represented by the green outline surrounding the channel. The influence of the proposed structures is

    not expected to go beyond 20 meters on either side of the stream channel.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    19

    Figure 3. Overhead view of the proposed project area on Penawawa Creek within United States

    Army Corps of Engineers property. The riparian zone in this section is in recovery, but instream

    habitat complexity is low. Post Assisted Log Structures in this section will promote geomorphic and

    hydraulic change to the channel that is beneficial to juvenile and adult steelhead.

    Figure 4. A beaver dam upstream of the proposed project area on Penawawa Creek. At the time this

    photo was taken, steelhead were witnessed spawning downstream of this beaver dam. Beaver Dam

    Analogues mimic natural beaver dams to produce the same ecologic benefits as real ones.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    20

    Figure 5. The conceptual design and hypothesized effects of a bank attached Post Assisted Log

    Structure. The structure increases hydraulic roughness and complexity which leads to predictable

    geomorphic change in the channel during high flows.

  • Pre-Application Due Date: April 2, 2015

    Draft Application Due Date: April 29, 2015

    Final Application Due Date: July 17, 2015

    21

    Literature Cited Omernik, J.M., Griffith, G.E., 2014. Ecoregions of the Conterminous United States: Evolution of a

    Hierarchical Spatial Framework. Environ. Manage. 54, 1249–1266. doi:10.1007/s00267-014-

    0364-1

    SRSB, 2013. Snake River Salmon Recovery Region Provisional Work Plan 2013-2018. Snake River

    Salmon Recovery Board, Dayton, WA.

    Wheaton, J., Bennett, S., Bouwes, N., Camp, R., 2012. Asotin Creek Intensively Monitored Watershed:

    Restoration Plan for Charley Creek, North Fork Asotin, & South Fork Asotin Creeks. (Restoration

    Design). Snake River Salmon Recovery Board, Dayton, WA.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 1

    Restoration, Acquisition, and Combination Project Proposal

    List all related projects previously funded or reviewed by RCO:

    Project # or Name Status

    Status of Prior Phase Deliverables and Relationship

    to Current Proposal?

    Asotin Creek IMW In progress Restoration phases are complete – effectiveness

    monitoring will continue until 2019.

    Pataha Creek:

    Working with

    Beaver to Restore

    Salmon and

    Steelhead Habitat

    In progress Trial restoration to be completed in the summer of

    2015.

    If previous project was not funded, describe how the current proposal differs from the original.

    1. Project Location.

    Penawawa Creek is a mainstem tributary to the Snake River in southeast Washington and drains

    122 km2 (47 mi2)of the Palouse Hills level 4 ecoregion (Omernik and Griffith, 2014). The project

    will be located within the lower 1.5 km (1 mi) of the mainstem of Penawawa Creek. The lower 1.5

    km (1 mi) is within United States Army Corps of Engineers (USACE) land. All of the land upstream

    from the confluence with the Snake River is privately owned, and will not be addressed in this

    proposal.

    2. Brief Project Summary.

    The Whitman County Conservation District (WCD) in cooperation with Eco Logical Research, Inc.

    (ELR) will use this grant to install up to 50 Post Assisted Log Structures (PALS; e.g. Wheaton et

    al., 2012) on Penawawa Creek from the mouth to approximately 1.5 km (1 mi) upstream on

    USACE property. The limiting factors on Penawawa Creek were identified as excessive fine

    sediment, low stream flow, and poor habitat complexity related to a lack of large woody debris

    and poor riparian function (SRSB, 2013). The primary benefits to adding high densities of large

    woody debris using PALS are to (1) increase instream habitat complexity through the

    development of pools, bars, and structural refugia for juvenile salmonids, (2) temporarily store

    fine sediment around the installed structures, and (3) and back up water behind structures to

    encourage hyporheic exchange and provide localized floodplain access.

    3. Problems Statement.

    Project Number

    Project Name Penawawa Creek: Instream Habitat Rehabilitation

    Sponsor Whitman Conservation District

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 2

    A. Describe the problem including the source and scale.

    Penawawa Creek is listed on the Washington State Department of Ecology’s 303(d) list for

    excessive water temperatures (WADOE, 2013). There is little available information for other

    habitat parameters on Penawawa Creek, however, brief reports conducted by the Washington

    Department of Fish and Wildlife (WDFW), indicate other potential problems in the watershed.

    There may be excessive fine sediment in the channel from adjacent hillslopes, vegetation in the

    riparian zone is sporadic, and there is an overall lack of shade in the channel from riparian

    vegetation (Mendel et al., 2004). However, portions of the riparian appear to be in recovery, and

    the riparian buffer generally widens moving downstream. Excessive fine sediment clogs

    interstitial spaces between spawning gravels, reducing the number of suitable spawning

    locations for adults salmonids. Additionally, the lack of shade on Penawawa Creek, likely

    contributes to high water temperatures which have exceeded the lethal limit for salmonids.

    Likewise, summer discharges on Penawawa Creek were very low (

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 3

    Excessive fine sediment (egg life stage): fine sediments clog the interstitial spaces between the

    gravels that adult salmonids target for spawning. Sufficient water flow through redds is required

    to deliver oxygen to developing salmonid eggs and alevin.

    Excessive water temperatures (all life stages): Steelhead are a cold water species, and require low

    water temperatures to reach a metabolic optimum. The upper thermal limit (>25° C; Myrick and

    Jr, 2005) is surpassed during the summer months on Penawawa Creek.

    4. Project Goals and Objectives.

    A. What are your project’s goals?

    The goal of this project is to increase habitat diversity, reduce uniform fine sediment deposition,

    improve riparian function, reconnect floodplain processes, and improve accessible habitat for

    steelhead on Penawawa Creek. This project will focus primarily on the natural mitigation effects

    of LWD to riparian and fluvial processes.

    B. What are your project’s objectives?

    The specific objectives of this project are to:

    1. Assess the current habitat conditions in the treatment area by estimating the density of

    pools, bars, and LWD, and mean embeddedness.

    2. Add up to 50 Post Assisted Log Structures (PALS) comprised of 200 qualifying LWD

    pieces (>10 cm diameter, >1 m long) to the active channel by 2017.

    3. Increase pool density to 5 pools/100 m within 5 years of funding.

    4. Decrease mean embeddedness in the active channel by 1 ranking on the Platts et al.

    (1983) method within 5 years of funding.

    5. Test viable methods for removing water hemlock within a small portion of the project

    area.

    C. What are the assumptions and constraints that could impact whether you

    achieve your objectives?

    The geomorphic effectiveness of PALS are dependent on peak discharge. However, the

    immediate hydraulic effects of PALS are still beneficial for steelhead in all life stages. We have

    received support from the USACE for this project on the lower 1.5 km (1 mi) of Penawawa Creek.

    We would like this project to act as a demonstration site for potential future projects in the

    Whitman Conservation District.

    5. Project Details.

    A. Provide a narrative description of your proposed project.

    Prior to performing restoration, we will perform a habitat assessment survey of the project area

    to calculate pool, bar, and LWD density. In addition, we will quantify mean embeddedness by

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 4

    geomorphic unit, using the Platts et al. (1983) ranking method. We will also perform of a

    desktop assessment of watershed controls including climate, geology, and hydrology that might

    affect the project design. We will use this data to identify priority locations for individual PALS

    when developing the restoration design. In addition, this data will act as a baseline for assessing

    our success at reaching the project objectives. In the year following implementation, we will

    repeat the survey to monitor changes to those habitat attributes.

    We propose to use a method of restoration extensively tested on the Asotin Creek Intensively

    Monitored Watershed project (IMW; Wheaton et al., 2012), using Post Assisted Log Structures

    (PALS) to increase habitat diversity and reconnect floodplain processes. Penawawa Creek is

    similar in many was to the study streams with the IMW, as have wild steelhead populations and

    both are affected by poor riparian function. Our approach will be to drive wooden fence posts

    into the stream bed spanning 80-90% of the active channel. The posts will support 3-5 pieces of

    LWD, keeping the LWD in place for 5-10 years while the riparian zone continues to recover. Each

    post is installed 40-70 cm (1-3 feet) into the channel bed, and extend slightly above the active

    flood height. Because the structures are not fully channel spanning, steelhead migration will not

    be impeded. The initial effects of altering the uniform flow regime in Penawawa Creek will

    provide more suitable habitat for steelhead by creating multiple feeding lanes and slow-water

    resting areas. Additionally, the specific design of each PALS will lead to predictable geomorphic

    effects following high flows. These geomorphic effects include the development of pools and

    bars, increased floodplain sediment deposits, and better sediment sorting. The influence of PALS

    on sediment sorting leads to distinct, similarly sized grain patches within the channel; therefore

    fine sediment is collected within eddys, rather than uniformly distributed throughout the active

    channel.

    Water hemlock is an invasive plant that is poisonous when ingested by humans and livestock

    and is currently found within the proposed project area. Although difficult to control, water

    hemlock is easiest to remove in early spring when the soil in which it grows is soft, allowing the

    full removal of the plant’s roots. We propose to explore methods for reducing the threat of

    water hemlock through manual removal. Prior to structure implementation in 2016, we will

    remove water hemlock plants and roots within the top 100 m (~325 feet) of the project area to

    determine the feasibility of this method.

    B. Provide a scope of work.

    Deliverable Description Completion Date Completed by

    Project management Project area

    assessment,

    restoration planning,

    construction,

    implementation,

    project reporting

    December 31, 2017 ELR

    Permitting Complete and apply July 15, 2016 ELR

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 5

    for all necessary

    permits

    Develop restoration

    plan

    Based on the project

    area assessment,

    develop a plan for

    constructing PALS

    July 15, 2016 ELR

    Install up to 50 PALS PALS will be

    constructed using

    wooden fence posts

    and LWD, based on

    the restoration plan

    August 30, 2016 ELR

    Implementation

    monitoring

    Describe each as-

    built structure using

    the HDLWD

    Effectiveness App

    September 30, 2016 ELR

    Water hemlock

    removal trial

    Manually remove

    water hemlock within

    the top 100 m of the

    project area

    June 1st, 2016 ELR

    C. Explain how you determined your cost estimates.

    Detailed budget is attached.

    The proposed costs are largely based off of ELR’s previous projects that are similar in size and

    scope. Labor costs are based on competitive prevailing wage rates. Materials costs are based on

    estimate matches from participating agencies, and quotes from the material providers.

    D. Describe the design or acquisition alternatives that you considered to

    achieve your project’s objectives.

    We considered two other alternatives. 1) Do nothing. This option assumes that the current

    condition of the project area is not degraded, or is exhibiting a rate of recovery that could not

    be enhanced through intervention. Based on the history of the Palouse Hills ecoregion, land use

    practices, and the best available data, we believe that Penawawa Creek is degraded compared to

    its historic condition. 2) Riparian planting. This option would address one of our project

    objectives (improve riparian function) over the long term; however, it does not provide short

    term improvement to instream habitat that would be beneficial for steelhead. Therefore, we

    settled on our preferred option, to implement PALS, because their hydraulic and geomorphic

    benefits have been well documented within the Asotin IMW project (Camp, 2015), as well as

    others in southeast Washington. Likewise, the long term benefits of reconnecting floodplain

    processes through the use of PALS will likely improve riparian function.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 6

    E. How have lessons learned from completed projects or monitoring studies

    informed your project?

    ELR has been developing many low-cost restoration alternatives throughout the Northwest

    United States. In particular, they have completed three years of PALS implementation on three

    different streams in the Asotin Creek watershed. Within an adaptive management framework,

    ELR improved structure designs and placement with each subsequent year. The effects and

    potential uses for PALS are well documented in Camp (2015). This project with benefit further

    from monitoring the effects of PALS on Penawawa Creek, including changes to instream habitat,

    riparian structure, temperature, and discharge.

    F. Describe the long-term stewardship and maintenance obligations for the

    project or acquired land.

    There are no expected maintenance responsibilities for any landowners involved in the project.

    The grantee will maintain or repair the PALS, when necessary, throughout the life of the project.

    However, PALS are designed to be dynamic and work in concert with each other and, therefore,

    no maintenance is required. All of the materials used are biodegradable.

    6. Context within the Local Recovery Plan.

    A. Discuss how this project fits within your regional recovery plan and/or local

    lead entity’s strategy to restore or protect salmonid habitat

    This project addresses ESA listed steelhead habitat in a priority protection reach. The general

    project categories for a priority protection reach in the 2013-2018 Snake River Salmon Recovery

    Region Provisional Work Plan include: protecting floodplain and riparian function, reducing fine

    sediments, and maintaining instream flow. PALS reconnect instream process with riparian and

    floodplain processes by mimicking trees that have fallen into the channel. The riparian zone in

    the project area appears to be in recovery, but because of the homogenous age structure of the

    trees, there is little to no LWD recruitment to the channel. Structural elements in streams, such

    as LWD, increase hydraulic roughness which leads to sorted patches of sediment grains.

    Similarly, fine sediment is stored upstream of PALS, and within the eddys they create; therefore,

    concentrating the amount of fines deposited to predictable locations, rather than uniformly

    throughout the channel. Some PALS significantly backup water upstream, thereby increasing

    water depth and helping to maintain instream flow. Additionally, the hydraulic and geomorphic

    effects of PALS increase habitat complexity, presumably creating more suitable habitat for ESA

    listed steelhead.

    B. Explain why it is important to do this project now instead of later.

    Penawawa Creek was not immune to the last 100+ years of land use practices in the Palouse

    Hills ecoregion. While some of the upland management practices have improved, the stream is

    still degraded and may not recover by itself, or may take many decades to do so without

    assistance. There do not appear to be any imminent threats on Penawawa Creek. Instream

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 7

    actions appear to be the next necessary step to rehabilitate Penawawa Creek by promoting the

    natural processes that lead to improved fish habitat. At the time this proposal was written, a

    total of 236 steelhead (188 wild, 55 hatchery) were collected at an adult weir near the mouth of

    Penawawa Creek (J. Trump, WDFW, personal communication, April 24, 2015). In contrast, 33

    steelhead (27 wild, 6 hatchery) were captured in 2014 (Trump and Gembala, 2015), and 71

    steelhead (24 wild, 47 hatchery) were captured in 2013 (Trump et al., 2014). This current year

    may be anomaly; however, considering the limited years of data, there is still much more to be

    learned about steelhead use in Penawawa Creek. Additionally, the current numbers suggest that

    Penawawa Creek may be an important component of the Middle and Lower Snake River

    steelhead metapopulation.

    C. If your project is a part of a larger overall project or strategy, describe the

    goal of the overall strategy, explain individual sequencing steps, and which

    of these steps is included in this application for funding.

    NA

    7. Project Proponents and Partners.

    A. Describe your experience managing this type of project.

    The Whitman Conservation District has effectively coordinated landowner operations to

    establish best management practices to their region. Additionally, landowners within the district

    develop, test, and implement their own strategies for improving land management practices.

    The district also holds regular meetings to discuss projects and management goals with

    stakeholders and producers in the region. A team of board members for the WCD coordinate

    with other agencies to address resource problems and prioritize solutions for addressing local

    land use issues.

    Eco Logical Research Inc. with assistance from Utah State University will be providing technical

    support and some project management and implementation duties as required. The primary

    people involved are Dr. Nick Bouwes, Dr. Joe Wheaton, and Dr. Stephen Bennett. The project

    team has managed dozens of restoration and monitoring projects related to stream habitat

    restoration and fisheries research. Dr. Bouwes and Dr. Bennett are currently managing two IMWs

    where restoration activities have already been implemented that are similar to those proposed

    in this application. Specifically, in Bridge Creek, a tributary to the John Day River, Dr. Bouwes was

    part of a team that developed a method to drive posts into the stream bottom to create starter

    dams for beaver as part of the Bridge Creek IMW. Additionally, Dr. Bennett is currently

    managing the Asotin Creek IMW, which used PALS as the primary restoration method. As

    manager and president of Eco Logical Research Inc. Dr. Bouwes has managed numerous projects

    for Bonneville Power Administration and National Oceanic and Atmospheric Administration

    including the development and implementation of the Columbia Basin Habitat Monitoring

    Protocol and the John Day portion of ISEMP. Dr. Bennett has been an environmental consultant

    since 1990 and has managed several large restoration and habitat assessment projects for

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 8

    salmon and inland trout. Dr. Wheaton is the Director of Ecogeomorphology & Topographic

    Analysis Lab at Utah State and the Co‐Director of Intermountain Center for River Rehabilitation

    & Restoration and as such manages numerous large scale river restoration, assessment, and

    monitoring projects.

    B. List all landowner names.

    United States Army Corps of Engineers

    C. List project partners and their role and contribution to the project.

    Whitman Conservation District will cover project administration tasks.

    Eco Logical Research, Inc. will implement, manage, and report on the restoration actions.

    D. Stakeholder Outreach.

    We are currently contacting local landowners for project support and outreach; however, the

    proposed actions would not occur on private land. Within the WCD, there are many citizen

    stakeholders that are supportive of best management practices. We will meet with landowners

    and the WCD board to discuss the project in detail. We will implement this project in a manner

    that is satisfactory to all of the involved stakeholders. Ideally, this project would serve as a

    demonstration to encourage landowner participation in future projects.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 9

    Supplemental Questions

    Restoration Project Supplemental Questions

    Answer the following supplemental questions:

    A. Will you complete, or have you already completed, a preliminary design, final

    design, and design report (per Appendix D) before construction?

    Yes

    1. If no, please describe your design process and list all pre-construction

    deliverables you will submit to RCO for review.

    B. Will your project be designed by a licensed professional engineer?

    No

    1. If not, please describe the qualifications of your design team.

    The Whitman Conservation District will team up with Eco Logical Research Inc., (ELR), to

    complete the implementation portion of this project. ELR focuses on process-based restoration

    approaches. Many of our projects are related to using low cost, minimal disturbance approaches

    to adding large woody debris to streams. We also believe in understanding the processes in a

    watershed before conducting any restoration. As such, we promote watershed assessments and

    developing a clear understanding of the ecological concerns and disrupted processes within a

    watershed. An example of the kind of watershed assessment we promote can be seen in (Pollock

    et al. 2012, Wheaton 2012, Portugal et al. 2015). We have over a decade of experience managing

    restoration projects. The ELR staff that will be working on this project and their qualifications are

    listed below.

    Dr. Nicolaas Bouwes

    Dr. Bouwes has a strong foundation in biometric and data analyses, modeling, experimental and

    monitoring design, fisheries research and aquatic ecology and has detailed knowledge of the

    salmon, steelhead, and bulltrout issues in the Columbia River Basin. Nick is the owner of Eco

    Logical Research, Inc. Nick is also an adjunct professor at the Watershed Sciences Department,

    Utah State University, Logan UT. Projects he is currently working on include: Asotin Creek

    Intensively Monitored Watershed (IMW) Project in southeast Washington and the Integrated

    Status and Effectiveness Monitoring Program to developed standardized status, trend, and

    effectiveness monitoring programs for salmon and steelhead in the Columbia River Basin. Nick

    has been the lead manager of the Bridge Creek IMW that focuses on using beaver dam analogs

    to restore steelhead habitat and also been a lead in developing restoration plans for the Asotin

    Creek IMW as well as numerous smaller beaver restoration projects in Oregon and Utah. Nick

    was the co-developer of the Columbia Habitat Monitoring Protocol (CHaMP) for the Bonneville

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 10

    Power Administration. Nick received a BS in zoology from the University of WI, Madison, and a

    MS and PhD in aquatic ecology from Utah State University, Logan UT.

    Dr. Stephen N. Bennett

    Dr. Bennett has been working for Eco Logical Research, Inc. since 2007 as the project

    coordinator of the Asotin Creek Intensively Monitored Watershed Project in southeast

    Washington. Stephen’s focus in the last eight years has been on developing and implementing

    restoration and monitoring programs in southeast Washington with a focus on building

    structures similar to BDAs (called post-assisted log structures). Stephen is familiar with the

    permitting and regulatory requirements of working with the Salmon Recovery Funding Board

    and works closely with the Snake River Salmon Recovery Board on several projects including

    monitoring restoration effectiveness in the Tucannon River. Stephen has also worked to aid in

    the development and assessment of regional salmonid monitoring programs. Stephen

    completed a PhD in Fisheries Biology in 2007 at the Watershed Sciences Department at Utah

    State University, Logan, Utah. Prior to starting his PhD Stephen was a biological consultant for

    12 years working on a variety of fisheries issues including fish inventory, fish passage

    assessment, watershed analysis, habitat monitoring, impact assessments, and salmonid

    enhancement projects. Stephen also has a Masters in Resource and Environmental Management

    (M.R.M.) from Simon Fraser University, Canada, and a Wildlife Biology (B.Sc. Honors), University

    of Montana.

    Dr. Joseph Wheaton

    Dr. Wheaton is an Assistant Professor at Utah State University and a fluvial geomorphologist

    with over a decade of experience in river restoration, including working with beaver in

    restoration. Joe runs the Ecogeomorphology & Topographic Analysis Lab at Utah State

    University and is a leader in the monitoring and modeling of riverine habitats and watersheds.

    He has worked to develop monitoring protocols for the USFS, NOAA, USGS and National Park

    Service and he and his lab have produced software for monitoring applications and simulation

    modeling. He is the co-director of the Intermountain Center for River Rehabilitation &

    Restoration. He worked four years in consulting engineering before completing his B.S. in

    Hydrology (2003, UC Davis), M.S. and Ph.D. in Hydrologic Sciences (2003, UC Davis; 2008, U. of

    Southampton, UK). He has worked as a lecturer (U. of Wales 2006-08), Research Assistant

    Professor (Idaho State U. 2008-09) and is an Assistant Professor at Utah State U. (2009-present)

    where he teaches courses on GIS, Fluvial Hydraulics and Ecohydraulics as well as workshops on

    'Restoration Monitoring: Geomorphic Change Detection', 'Partnering with Beaver in Restoration

    Design', and 'Geomorphology and Sediment Transport in Channel Design'. Joe works regularly

    with Eco Logical Research on projects including: Asotin Creek Intensively Monitored Watershed

    Project in southeast Washington, Intercomparing Monitoring Methods in the Lemhi Watershed

    of Idaho for the Integrated Status and Effectiveness Monitoring Program, Bridge Creek

    Intensively Monitored Watershed restoration project in Central Oregon, developing a Big River

    Monitoring Protocol for the National Park Service, working on sediment budgeting in the Grand

    Canyon with the USGS Grand Canyon Monitoring & Research Center.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 11

    Reid Camp

    Reid has eight years of experience monitoring wild salmonid populations, and conducting

    stream restoration effectiveness monitoring in southeast Washington and throughout Idaho. He

    began working for ELR in 2009 on the Asotin Creek Intensively Monitored Watershed where he

    is currently coordinating field operations on Asotin Creek and other ELR projects in southeast

    Washington. Reid has substantial technical experience collecting, organizing, and analyzing

    fisheries and stream data, is proficient in many software packages including Access, FileMaker,

    ArcGIS, R, and is a certified Microsoft Office User Specialist. He has helped to develop multiple

    protocols and mobile device applications for facilitating rapid, low-cost monitoring methods

    that are currently being used by public and private entities in WA, ID, UT, and MT. Reid received

    a B.S. in Fishery Resources from the University of Idaho in Moscow, ID and a M.S. in Watershed

    Science from Utah State University in Logan, UT. Pertinent to this project, Reid’s M.S. thesis

    primarily assessed the geomorphic effectiveness of low-cost stream restoration structures (PALS

    on the Asotin IMW, specifically), at increasing habitat diversity that is beneficial for steelhead.

    C. If this project includes measures to stabilize an eroding streambank, explain why

    bank stabilization there is necessary to accomplish habitat recovery.

    NA

    D. Describe the steps you will take to minimize the introduction and spread of

    invasive species during construction and restoration.

    We will use locally sourced wood and non-treated fence posts for the construction of each

    restoration structure to reduce the potential of introducing new invasive species to the project

    area. Our methods are very low impact to the surrounding riparian vegetation, and cause little

    disturbance to the stream bed and floodplain. We do not anticipate that our actions will

    contribute to the spread of invasive species currently found within the Penawawa watershed.

    Although water hemlock is present within the project area, we will test viable options for its

    removal.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 12

    Comments

    Use this section to respond to the comments you will receive after your initial site visits, and

    then again after you submit your final application.

    Response to Site Visit Comments

    Please describe how you’ve responded to the review panel’s initial site visit comments. We

    recommend that you list each of the review panel’s comments and questions and identify how you

    have responded. You alsomay use this space to respond directly to their comments.

    Response to Post-Application Comments

    Please describe how you’ve responded to the review panel’s post-application comments. We

    recommend that you list each of the review panel’s comments and questions and identify how you

    have responded. You alsomay use this space to respond directly to their comments.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 13

    Literature Cited

    Camp, R., 2015. Short Term Effectiveness of High Density Large Woody Debris, a Cheap and

    Cheerful Restoration Action, in Asotin Creek (Thesis). Utah State University, Logan, UT.

    Fausch, K.D., 1993. Experimental Analysis of Microhabitat Selection by Juvenile Steelhead

    (Oncorhynchus mykiss) and Coho Salmon (O. kisutch) in a British Columbia Stream. Can.

    J. Fish. Aquat. Sci. 50, 1198–1207. doi:10.1139/f93-136

    Mendel, G., Trump, J., Fulton, C., Gembala, M., 2004. Brief Assessment of Salmonids and Stream

    Habitat Conditions in Snake River Tributaries of Asotin, Whitman and Garfield Counties

    in Washington: March 2001-June 2003. Washington Department of Fish and Wildlife,

    Olympia, WA.

    Myrick, C.A., Jr, J.J.C., 2005. Effects of Temperature on the Growth, Food Consumption, and

    Thermal Tolerance of Age-0 Nimbus-Strain Steelhead. North Am. J. Aquac. 67, 324–330.

    doi:10.1577/A04-050.1

    Omernik, J.M., Griffith, G.E., 2014. Ecoregions of the Conterminous United States: Evolution of a

    Hierarchical Spatial Framework. Environ. Manage. 54, 1249–1266. doi:10.1007/s00267-

    014-0364-1

    Platts, W.S., Megahan, W.F., Minshall, G.W., 1983. Methods for evaluating stream, riparian, and

    biotic conditions.

    Roni, P., Quinn, T.P., 2001. Density and size of juvenile salmonids in response to placement of

    large woody debris in western Oregon and Washington streams. Can. J. Fish. Aquat. Sci.

    58, 282–292. doi:10.1139/f00-246

    SRSB, 2013. Snake River Salmon Recovery Region Provisional Work Plan 2013-2018. Snake River

    Salmon Recovery Board, Dayton, WA.

    Trump, J., Gembala, M., 2015. Estimate Adult Steelhead Abundance in Small Streams Associated

    with the Tucannon and Asotin Populations. Washington Department of Fish and Wildlife,

    Dayton, WA.

    Trump, J., Mendel, G., Gembala, M., 2014. Estimate Adult Steelhead Abundance in Small Streams

    Associated with the Tucannon and Asotin Populations. Washington Department of Fish

    and Wildlife, Dayton, WA.

    WADOE, 2013. 2012 Water Quality Assessment - 305(b) Report. Washington State Department

    of Ecology, Olympia, WA.

    Wheaton, J., Bennett, S., Bouwes, N., Camp, R., 2012. Asotin Creek Intensively Monitored

    Watershed: Restoration Plan for Charley Creek, North Fork Asotin, & South Fork Asotin

    Creeks. (Restoration Design). Snake River Salmon Recovery Board, Dayton, WA.

  • Restoration, Acquisition, or Combination Project Proposal May 1, 2015

    Page 14

    Zalewski, M., Lapinska, M., Bayley, P., 2003. Fish relationships with wood in large rivers, in: The

    Ecology and Management of Wood in World Rivers. American Fisheries Society,

    Bethesda, pp. 195–211.

  • RESTORATION

    OVERALL

    PROJECT GRANT REQUEST MATCH

    Budget must

    account for all

    costs to

    complete the

    project

    Enter only the

    amount of the

    grant request

    Qty Rate Amount Amount Match in PRISM

    Funding not reported

    in PRISM

    Source (Grant,

    Cash, Materials,

    Labor, Volunteers,

    etc)

    Match Type

    (federal, state,

    local)

    Construction

    Category (choose one) Task Description

    Construction supervision Implementation monitoring 30.00 40.56$ 1,217$ 1,217$ -$ -$

    Construction supervision Project management and

    site visits

    70.00 40.56$ 2,839$ 2,000$ 839$ -$ Labor Local

    Materials Non-treated wood posts 400.00 10.00$ 4,000$ 4,000$ -$ -$

    Equipment and equipment use Post driver rental 1.00 2,500.00$ 2,500$ -$ 2,500$ -$ Equipment Local

    Construction labor Crew of 4 biologists for 7

    days to implement

    structures

    200.00 40.56$ 8,112$ 8,112$ -$ -$

    Permits Shoreline, HPA, JARPA 70.00 40.56$ 2,839$ 2,839$ -$ -$

    Permits Army Corps of Engineers 1.00 5,000.00$ 5,000$ 5,000$ -$ -$

    Cultural resources Cultural resources

    consultation

    1.00 4,000.00$ 4,000$ 4,000$ -$ -$

    Materials Large woody debris pieces 220.00 30.00$ 6,600$ -$ 6,600$ -$ Materials Federal

    Materials Large wood debris felling

    and delivery

    1.00 2,000.00$ 2,000$ 2,000$ -$ -$

    Construction labor 1 biologist for 2 days to test

    viable options for water

    hemlock removal

    20.00 40.56$ 811$ 811$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    STotal 39,918$ 29,979$ 9,939$ -$

    Administrative, Architechtural &

    Engineering

    Category Task Description

    Final design Develop restoration plan 30.00 40.56$ 1,216.80$ 1,217$ -$ -$

    Assessments (geologic, hydraulic, etc.) Watershed assessment 65.00 40.56$ 2,636.40$ 2,636$ -$ -$

    Administrative Whitman Conservation

    District administration

    1.00 5,000.00$ 5,000.00$ 5,000$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    -$ -$ -$ -$ -$

    Stotal $ 8,853.20 $ 8,853.20 $ - -$

    GTOTAL 48,772$ 38,832$ 9,939$ -$

    A&EPRISM Project

    Total

    $ 48,771

    A&E maximum allowed in PRISM $ 11,975.40 RCO Percentage Match Percentage

    A&E validation 3,122 0.796211699 0.203788301

    The Grant Request and Match should equal the total project cost and Budget

    Check cell should be 0. Sponsors must account for all sources and types of match

    need to complete the project.

    See SRFB Manual 5 for additional information regarding allowable costs.

    Lower Columbia Habitat Project Application Detailed Cost Estimate 2/1/2013

  • Appendix F: Landowner Acknowledgement Form

    Manual 18, Salmon Recovery Grants January 2015

    Appendix F:

    Landowner

    Acknowledgement Form

    Landowner Information

    Name of Landowner: United States of America, U.S. Army Corps of Engineers

    Landowner Contact Information:

    Mr. Ms. Title: Chief of Real Estate

    First Name:Rodney Last Name: Huffman

    Contact Mailing Address: 201 North Third Avenue, Walla Walla, WA 99362

    Contact E-Mail Address:[email protected]

    Property Address or Location: Penawawa Creek, Little Goose Lock and Dam Project

    1. The United States of America (Landowner or Organization) is the legal owner of property

    described in this grant application.

    2. I am aware that the project is being proposed on my property.

    3. If the grant is successfully awarded, I will be contacted and asked to engage in negotiations.

    4. My signature does not represent authorization of project implementation.

    April 24, 2015

    Landowner Signature Date

    Project Sponsor Information

    Project Name:

    Project Applicant Contact Information:

    Mr. Ms. Title

    First Name: Last Name:

    Mailing Address:

    E-Mail Address:

  • Appendix G: Project Partner Contribution Form

    Manual 18, Salmon Recovery Grants January 2015

    Appendix G: Project Partner Contribution Form

    Project Partner: Eco Logical Research, Inc.

    Partner Address: 456 S 100 W, Logan, UT 84321

    Contact Person:

    Mr. Ms. Title:

    First Name: Reid Last Name: Camp

    Mailing Address: 1493 Northwood Dr. #104, Moscow, ID 83843

    E-Mail Address: [email protected]

    Description of contribution to project:

    Eco Logical Research, Inc. will assist with restoraiton implementation, management,

    and reporting.

    Estimated value to be contributed: $30,000

    4/27/2015

    X Reid CampReid Camp

    Research Biologist, ELR

    Signed by: Reid Camp 04/27/2015_

    Partner’s signature Date

  • 1 DraftApplication_PenawawaCreek_1504292 Appendix_C_PenawawaProposal_ELR_1504294 SRFB_Cost_Estimate_PenawawaCreek_1504275 Appendix_F_Landowner_Ack_Form_USACE6 Appendix_G_Proj_Partner_Contribution_Form_ELR7 Penawawa_USACE_letter of support