2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15

Transcript of 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan...

Page 1: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

2015 APAM Conference Hot Mix Asphalt (HMA) Update

Kevin Kennedy HMA Operations Engineer

Michigan Department of Transportation 4-22-15

Page 2: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Hot Mix Asphalt (HMA) Update• Acceptance of HMA on Local Agency Projects

• HMA Quality Improvements

• Portable Plants and Utilizing Recycled Asphalt Pavement (RAP) from the same project

• Recycled Tire Rubber Permissive Specification

• Miscellaneous Specification Changes

• HMA Production Manual

• National Peer Review

Page 3: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects

• New Specification Approved• Immediate Use- NHS Routes and Routes Chosen by Local Agency• Full Implementation October 2015• Interim- Old Specification With Minor Revisions or New Specification

• Covers Roller Method and Density Testing with Nuclear Gauge

• Revises Tolerance Limits and Penalty Structure for HMA Mixtures

• Strengthens Sampling and Testing Requirements

• Adds Time Frame for Reporting Quality Assurance Test Results

Page 4: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Local Agency- Tolerance Limits

Table 1 – Uniformity Tolerance Limits for HMA

Page 5: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects Sampling and Testing

Requirements• All persons performing testing must be Bituminous (Bit) Level One certified or

Bit Quality Assurance/Quality Control (QA/QC) Technician certified.

• All laboratories performing local acceptance testing must be qualified laboratories.o Qualified per the HMA Production Manual and participate in the MDOT

Round Robin processo or Laboratory must be AASHTO Materials Reference Laboratory (AMRL)

accredited for AASHTO T 30 or T 27, and AASHTO T 164 or T 308.

• Contractor Laboratories:o Non-NHS: Allowedo NHS: Not Allowed

Page 6: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects Sampling and Testing

Requirements• Qualified Samplers Required o Qualifying of Samplers to be handled by Ferris State Universityo MTM 313 (Sampling HMA Paving Mixtures) o MTM 324 (Sampling HMA Paving Mixtures Behind the Paver)

• Minimum – Obtain and test two samples per day o No longer testing at frequency determined by engineer

• Quality Assurance Test Results – Time Requiremento 7 days – projects more than 5000 tonso 14 days – projects less than 5000 tons

Page 7: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects

Penalty StructureTable 3: Penalty Per Parameter

Out of specification- 2 consecutive tests outside of range 1 or range 2

Mixture Parameter out-of-specification

per Acceptance Tests

Mixture Parameter out-of-specification per Dispute

Resolution Test Lab Price Adjustment per Parameter

NO N/A None

YES

NO None

YES

Outside Range 1 but not Range 2: decrease by 10%

Outside Range 2: decrease by 25%

Page 8: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects

Density Testing• Two Optionso Direct Density Method

• Nuclear density gauge• 92-98 percent of density control target (Gmm from JMF)

o Roller Method• Added table for Minimum Number of Rollers Recommended Based on

Placement Rate• Added table for Density Frequency Curve Development.

• Timingo During paving operationso Prior to traffic staging changeso Prior to subsequent lifts and opening to traffic

Page 9: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects

Additional Significant Changes

• Regress air voids in production to 3.5%

• Dispute Processo Range 1- Independent Laboratoryo Range 2- Construction Field Services HMA laboratory (MDOT Central

Laboratory)

Page 10: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Acceptance of HMA on Local Agency Projects

Future Changes

•Move towards volumetric testing

•Air Voids, VMA, ??

•Doesn’t Necessarily Mean SuperPave

•Sampling Behind the Paver/Mini-Stockpile

Page 11: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

HMA Quality Improvements

• Regress Mixes to 3% Air Voids

• Requiring Fine-Graded or Gap-Graded for Top Courses

• Ride Quality Incentive

Page 12: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality –Regress High Volume Mixes

• Regress Mixes to 3% Air Voids in Production for E10, E30 and E50 Mixes

• Effective October Letting

Table 3- For mixtures meeting the definition for top and leveling courses: Mixtures must be designed to 96.0% of Maximum Specific Gravity (%Gmm) at the design number of gyrations, (Nd). During field production Percent of Maximum Specific Gravity (%Gmm) at the design number of gyrations, (Nd) will be increased to 97.0% for E10, E30, & E50 mixes. For all other mixes, Percent of Maximum Specific Gravity (%Gmm) at the design number of gyrations, (Nd) will be increased to 96.5% during field production.

Page 13: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality - Regress All Mixes

• Regress Mixes to 3% Air Voids in Production For All Mixes

• Effective March Letting

Unless noted otherwise on the plans, all mixtures must be designed to 96.0% of Maximum Specific Gravity (%Gmm) at the design number of gyrations, (Nd). During field production Percent of Maximum Specific Gravity (%Gmm) at the design number of gyrations, (Nd) will be increased to 97.0%.

Page 14: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality - Regress All Mixes

• Additional Changes

• Changing the upper air voids limit on single test acceptance (changed to 2.0 from 2.5)

• Changing suspension limits in Table 4 for binder content (changed from 1.00 to 0.75)

• Changing the sublot Rejectable Quality Limits (RQL) for air voids (changed to +2, -1.5 from +2,-2)

• Adding removal limits for lots on one course overlays (501V)

Page 15: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality - Regress All Mixes Table 4

Col. I - Quality Characteristic

Col. II - QC Action Limits (a)

Col. III - QC Suspension Limits (b)

Col. IV - QA Suspension Limits

Form 1165 (a)Col. V - Sublot RQL

Form 1165 (c) Col. VI - Lot AQL (d)Col. VII - Lot RQL

(d)

Aggregate Gradation (optional)

Aggregate Moisture

Binder Content ± 0.50 JMF ± 0.75 JMF PWLBINDER ≥ 90 For

any lotPWLBINDER < 50 For

any lot

Combined Mixture Gradation

Defined in the HMA-QC Plan Refer to Table 2

Maximum Theoretical Specific Gravity ± 0.013 JMF ± 0.020 JMF

Bulk Specific Gravity

Volumetrics: Air VoidsDefined In the HMA-

QC Plan ± 1.00 of Target Air Voids + 2.00, -1.50 of Target

Air voidsPWLAV ≥ 90 For any

lotPWLAV < 50 For any

lot

Volumetrics: VMADefined In the HMA-

QC Plan± 1.00 of VMA Targets in

Table 3

± 2.00 of VMA Targets in

Table 3PWLVMA ≥ 90 For

any lotPWLVMA < 50 For

any lot

Fines to Effective Binder

Defined In the HMA-QC Plan 0.60 – 1.40 (a) 0.60 – 1.40

In-Place DensityDefined in the HMA-

QC PlanDefined in the HMA-QC

Plan Average Sublot Value

< 90.00%PWLD ≥ 90 For any

lotPWLD < 50 For any

lot

a. Limits apply to two consecutive QC or QA tests.b. Limits apply to single QC tests.c. Specified. Limits apply to a single QA sublot Air Void or VMA test or on the sublot average In-Place Density.d. Specified. Limits apply on a lot-by-lot basis. Based on QA results for the lot.

Page 16: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality –Fine Graded/Gap Graded on Top Course

• Changed Gradation to Eliminate Coarse Graded Mixes

• Eliminated Restricted Zone

• FUSP 902E

• Effective January Letting

• Revises Table 902-5 and 902-6

Page 17: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality – Fine Graded/Gap Graded on Top Course

Revised Table 902-5

Superpave Final Aggregate Blend Gradation Requirements

Standard Sieve

Percent Passing Criteria (control points) Mixture Number

5 4 3 Leveling Course3 Base Course

2 LVSP (a)

1½ in — — — — 100 —

1 in — — 100 100 90–100 —

¾ in — 100 90–100 90–100 ≤90 100

½ in 100 90–100 ≤90 ≤90 — 75–95

⅜ in 90–100 ≤90 — — — 60–90

No. 4 ≤90 — — — — 45–80

No. 8 47-67 39-58 35–49 23–49 19–45 30–65

No. 16 — — — — — 20–50

No. 30 — — — — — 15–40

No. 50 — — — — — 10–25

No. 100 — — — — — 5–15

No. 200 2.0–10.0 2.0–10.0 2.0–8.0 2.0–8.0 1.0–7.0 3–6 a. For LVSP, less than 50 percent of the material passing the No. 4 sieve may pass the No. 30 sieve.

Page 18: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality –Fine Graded/Gap Graded on Top Course

Revised Table 902-6Superpave Final Aggregate Blend Physical Requirements

Est. Traffic(million ESAL)

MixType

Percent Crushed Minimum Criteria

Fine Aggregate Angularity Minimum

Criteria% Sand EquivalentMinimum Criteria

Los Angeles Abrasion

% Loss Minimum Criteria

% Soft ParticlesMaximum Criteria

(a)

% Flat and Elongated Particles

Maximum Criteria (b)

Top & Leveling Courses

BaseCourse

Top & Leveling Courses

BaseCourse

Top & LevelingCourses

BaseCourse

Top & LevelingCourses

BaseCourse

Top & LevelingCourses

Base Course

Top & LevelingCourses

BaseCourse

< 0.3 LVSP 55/— — — — 40 40 45 45 10 10 — —

< 0.3 E03 55/— — — — 40 40 45 45 10 10 — —

>0.3 -<1.0 E1 65/— — 40 — 40 40 40 45 10 10 — —

>1.0 - < 3 E3 75/— 50/— 43 40 40 40 35 40 5 5 10 10

>3 - <10 E10 85/80 60/— 45 40 45 45 35 40 5 5 10 10

>10 - <30 E30 95/90 80/75 45 40 45 45 35 35 3 4.5 10 10

>30 - <100

E50 100/100 95/90 45 45 50 50 35 35 3 4.5 10 10

(a) Soft particles maximum is the sum of the shale, siltstone, ochre, coal, clay-ironstone and particles that are structurally weak or are non-durable in service.(b) Maximum by weight with a 1 to 5 aspect ratio. Note: “85/80” denotes that 85 percent of the coarse aggregate has one fractured face and 80 percent has at least two fractured faces. 

Page 19: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Quality – Ride Quality Incentive

• Specification Approved (12RC501-A435)

• Incentive Starts at IRI of 45

• Increases to $.50 per square yard at IRI of 25

• Applies to High Speed Roads (50 MPH)

• Class I and Class II Roads per Ride Quality Specification

Page 20: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Portable Plants- RAP

Stockpile Requirements. Process RAP to the size required forthe specified HMA mix. Ensure the stockpile contains enoughmaterial to produce the recycled mixtures the Engineer

approves for the project. If the RAP stockpile is not sufficient to produce recycled mix quantities required for the project, provide an Engineer-approved mix design without RAP at the same unit price.

Page 21: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Requirements for Utilizing RAP Millings from the Same Project When Using a Portable Plant

Sampling

• Samples to be taken a minimum of every mile in each lane by milling or coring.

• Sample areas to be repaired.• Shoulder samples should also be taken if RAP from shoulder is to

be used.• Samples should also be taken if visual observations show

significant variations in existing mat.• Sampling required for the percentage/tonnage of RAP that will be

utilized on the project.

Page 22: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Requirements for Utilizing RAP Millings from the Same Project When Using a Portable Plant

Mix Design

• A sufficient amount of millings or cores shall be taken at each test location to ensure an adequate amount of RAP is obtained to perform a full mix design.

• No paving shall occur using RAP from the project until a mix design is approved.

Page 23: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Requirements for Utilizing RAP Millings from the Same Project When Using a Portable Plant

Processing RAP• It is not required to have a stockpile with enough material to

produce the recycled mixtures approved for the project.• RAP should be stockpiled* and tested according to existing

requirements (one test per 1000 tons, minimum of 3 tests).• If the millings have aggregates larger than what it is required for

the mix design, it should be processed (crushed and/or screened) prior to stockpiling*. If aggregates larger than what is required for mix design still exist after processing, the contractor must demonstrate that additional screens are installed on the RAP feed system to ensure that the RAP being introduced into the HMA Mixture contains no aggregate larger than the top size aggregate allowed in the mix design.

Page 24: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Requirements for Utilizing RAP Millings from the Same Project When Using a Portable Plant

Processing RAP• In addition, a RAP scalper screen is required**. The top size of

the top scalping screen shall be 1.5” for top and leveling courses and 2” for base courses.

*If approved by the engineer, in-line crushing and/or screening will be allowed in lieu of processing RAP into a stockpile. The contractor must demonstrate that additional screens are installed on the RAP feed system to ensure that the RAP being introduced into the HMA Mixture contains no aggregate larger than the top size aggregate allowed in the mix design.

**If in line crushing and/or screening is being used a RAP scalper screen may not be required.

Page 25: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Recycled Tire Rubber

• Grand Region Pilot Project – 2013• M-57 from East of Northland Drive to West of Morgan Mills

Avenue • Crumb rubber portion approximately 3.2 miles on M-57

between Wabasis Road and Morgan Mills• Allowed Wet Process or Terminal Blend (contractor’s option)• Three binders (64-22, 70-22P, 70-22 crumb rubber modified)• 6,007 tons HMA 5E3 Crumb Rubber Modified• Bids

• Low Bidder- $79.45 vs $85.83• 2nd Bidder- $71.15 vs $102.97

Page 26: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

MDOT Pilot Project

Page 27: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Recycled Tire Rubber

• HMA Tech Committee Directed to Develop Permissive Specification

o Originally- specification to mirror pilot projecto Concern over reports of poor performance (Waverly Road,

Haslett Road, various Saginaw County projects)

o PG Binder performance tests have been modified or waived o HMA Technical Committee believes revised tests do not

accurately predict performanceo No deviations to acceptance test methods/procedures

allowed.

Page 28: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Waverly Road

2011 Construction County Road

(Photo taken in 2013)

Page 29: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Miscellaneous Specification Changes

• FUSP 501G (RAP/RAS)- Added language referring to production manual for blending charts:• When incorporating RAS the asphalt binder grade will be selected using

a blending chart for high and low temperatures.• The Contractor must supply the blending chart used in determining the

binder selection according to AASHTO M 323 and the HMA Production Manual.

• FUSP 501L (Temp Pavement) - Added language clarifying removal of temporary pavement is not part of temporary pavement pay item

Page 30: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Miscellaneous Specification Changes

• Gap-Graded SuperPave- New specification for ½” nominal mix and 3/8” nominal mix

• FUSP 504C (HMA ultra-thin overlay)- New specification , no longer Marshall mix. Includes mix design submittal requirements

• HMA Binders- Changes coming to Price Adjustment and Certification procedures

• Non-Tracking Bond Coat (Trackless Tack)

Page 31: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

HMA Production Manual• Bureau of Highway Instructional Memorandum 14-12

o Includes blending chart instructions for RAP/RAS.

o RAP now part of mix design submittal.

o Section 4 was removed from the MDOT HMA Production Manual and added to Section 5.03.01 of the MDOT Materials Quality Assurance Procedures Manual (MDOT MQAPM).

Page 32: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

National Peer Review• NCAT/NAPA/FHWA

• Construction Best Practices• Bond Coat• Minimizing segregation• Longitudinal Joint Construction

• RAP/RAS – Are we doing it right?• Local Agency Acceptance (present and future)• Mix Design

• Aggregate/RAP specific gravity• Fine graded mixes

Page 33: 2015 APAM Conference Hot Mix Asphalt (HMA) Update Kevin Kennedy HMA Operations Engineer Michigan Department of Transportation 4-22-15.

Questions?

Kevin Kennedy HMA Operations Engineer

[email protected] 517-322-6043