2014 Testing, Inspection & Maintenance Plan
Transcript of 2014 Testing, Inspection & Maintenance Plan
2014 Testing, Inspection &
Maintenance Plan Annual Planning Report
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
2
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
3
2014 Testing, Inspection & Maintenance Plan Annual Planning Report
Executive Summary Hydro Ottawa’s testing, inspection and maintenance (TIM) programs are crucial to ensuring a reliable and
sustainable distribution system. Information from the testing, inspection and maintenance programs feed
back into the Asset Management Plan to allow for effective life-cycle planning of assets. Currently, there are
many different types of testing, inspection and maintenance activities that are used to gain asset
information, health information required for the determination of replacement and/or maintenance
prioritization in order to increase asset reliability and longevity.
The TIM Annual Planning Report was developed to serve as a summary and guide of the current activities,
data collection methodologies as well as to identify the gaps in the existing practices.
In 2013, most of Hydro Ottawa Distribution TIM programs met inspection targets within budget. The
programs that did not meet inspection targets include critical switch inspection and pole inspection. These
programs have no outside services budget and rely on availability of Hydro Ottawa resources to complete the
scope of work.
In 2013, most of Hydro Ottawa Station TIM programs did not meet target number of inspections and were
under budget. The Station’s maintenance information is transitioning to new software called PowerDB that
has limited reporting function. Hydro Ottawa is working with the PowerDB software to create effective
inspection reports to summarize Station TIM program performance numbers. This will allow for proper
evaluation of Station TIM program data. Stations TIM programs often do not meet targets as Station
resources are heavily focused on capital projects.
Through the examination of the various maintenance programs, a common theme was seen: a lack of a long
term plan, finances and available resources. This document will outline the current and future requirements
in order to identify the activities that need more or less attention and resources.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
4
Contents Executive Summary .................................................................................................................................. 3
1 Background ...................................................................................................................................... 5
1.1 Purpose of the Testing, Inspection, and Maintenance Plan ................................................................ 5
2 Distribution Testing, Inspection and Maintenance ............................................................................. 6
2.1 Infrared (IR) and Visual Inspection ....................................................................................................... 7
2.2 Padmount Switchgear CO2 Wash ....................................................................................................... 12
2.3 Civil Structure Inspections .................................................................................................................. 14
2.4 Vegetation Management ................................................................................................................... 16
2.5 Insulator Washing .............................................................................................................................. 18
2.6 Cable Inspection ................................................................................................................................. 20
2.7 Critical Switch Inspections.................................................................................................................. 22
2.8 Pole Inspections ................................................................................................................................. 24
2.9 Graffiti Abatement ............................................................................................................................. 26
2.10 Vault Maintenance ............................................................................................................................. 28
3 Station Testing, Inspection, and Maintenance .................................................................................. 30
3.1 Battery Maintenance ......................................................................................................................... 31
3.2 Relay Maintenance ............................................................................................................................. 33
3.3 Transformer Maintenance ................................................................................................................. 34
3.4 Transformer Oil Analysis Testing ........................................................................................................ 36
3.5 Transformer Doble Testing ................................................................................................................ 37
3.6 Station Visual Inspections .................................................................................................................. 38
3.7 Tap Changer Maintenance ................................................................................................................. 40
3.8 Stations Infrared (IR) Inspection ........................................................................................................ 43
3.9 Switchgear Maintenance ................................................................................................................... 44
4 SCADA Maintenance - Stations and Distribution .............................................................................. 51
4.1 Program Details .................................................................................................................................. 51
4.2 Program Schedule .............................................................................................................................. 51
4.3 Program Performance Indicators ....................................................................................................... 51
4.4 Data Governance ................................................................................................................................ 51
4.5 Reactive Maintenance ........................................................................................................................ 51
4.6 Gap Analysis ....................................................................................................................................... 51
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
5
1 Background
1.1 Purpose of the Testing, Inspection, and Maintenance Plan The intention of the Testing, Inspection and Maintenance (TIM) Plan is to document the asset TIM practices
used by Hydro Ottawa Limited (HOL) as part of the optimized lifecycle strategy for distribution and station
assets. The objective of the TIM plan is to outline the current and future requirements in order to identify the
activities that need more or less attention and resources to ensure a sustainable and reliable system.
The TIM Plan is a key component of the maintenance planning process which will identify the HOL
maintenance programs, the type of assets the maintenance is being performed on, the current maintenance
schedule, budgeting information, and identify any gaps in the current programs.
Ongoing TIM programs have been sustained by HOL with limited involvement from the Asset management
group in the past. In the interest of better leveraging the current activities, for the purposes of inclusive asset
management, a review has been undertaken of the current programs and practices. The TIM Plan serves as a
summary and guide of the current activities and data collection methodologies.
The purpose of the Hydro Ottawa TIM programs is to test, inspect and maintain the equipment to gather
equipment information for use in asset lifecycle planning. Testing of equipment involves using test/metering
devices to obtain equipment, material or component condition information either during equipment
operation or shutdown. Inspection of equipment usually refers to visual or infrared inspection through which
equipment nameplate information, physical equipment condition and operating temperature of equipment is
obtained. Maintenance activities refer to the physical work being performed on the equipment and can
include cleaning, torquing, greasing, operating the equipment, or replacing components.
Many of the TIM programs are evolving from utilizing paper forms for data capture, which are extremely
difficult to analyze, to new portable inspection tablets. These tablets allow for the electronic entry of
inspection information creating data sets that are easily queried and analyzed.
Hydro Ottawa’s TIM Plan is divided into three categories: Distribution, Stations, and SCADA. These sections
will define the current TIM programs, including scheduling, data governance, reactive maintenance and gap
analysis.
Further development of the TIM programs will continue to improve scheduling, analyses, and more efficient
use of inspection resources. All of these items will drive the optimization between asset maintenance versus
replacement.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
6
2 Distribution Testing, Inspection and Maintenance
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
7
2.1 Infrared (IR) and Visual Inspection Hydro Ottawa performs infrared (IR) and visual inspection
for many of its assets. The IR inspections allow crews and
contractors to examine equipment operating temperature
to detect defective components, poor connections, or
overloaded equipment which can indicate the potential for
failures. Visual inspections are important to monitor
cleanliness, ease of access, obtain updated nomenclature
and equipment information, and to assess damage and any
potential follow-up activities required.
In order to effectively use the IR scanning information, an
equipment health index was created
and is used for all IR scanned equipment
(see Table 2.1). The condition rating is
based on the temperature difference
between the reference temperature
and the equipment’s actual measured
temperature. Equipment that is within
the critical temperature range has an Outage Management System (OMS) ticket created to schedule
immediate repair. It is the responsibility of the area supervisor to schedule the work and close out the ticket
when the issue is verified to be resolved.
2.1.1 Padmount Switchgear
2.1.1.1 Program Details The padmount switchgear inspection consists of IR
scanning and a visual inspection of air-break
switchgear. The IR scan detects loose connections,
tracking, overloaded equipment, and other heat
related problems. Visual inspection includes recording equipment information as well as checking for
swollen elbows, exposed electrical hazards, operating hazards, rusting and graffiti.
2.1.1.2 Program Schedule Padmount switchgear is inspected on a three year cycle (see Table 2.2). Hydro Ottawa contracts out these
inspections to a qualified third party. The switchgear cycle transpired from historical cleaning records.
The Ontario Energy Board (OEB) minimum inspection for switchgear requires they are patrolled in urban
areas at a maximum interval of 3 years and in rural
areas at a maximum interval of 6 years.
2.1.1.3 Program Performance Indicators In 2013, Hydro Ottawa completed 82 out of 83
switchgear inspections (see Table 2.3).
The number of air brake switchgear and cost of the
program continues to decrease, as they are replaced
with newer SF6 switchgear.
TABLE 2.2 - SWITCHGEAR INSPECTION
Frequency 2013 Budget
Every 3 Years
(90 switchgear / year)
$14,000
TABLE 2.1 - INFRARED CONDITION RATING
Critical - (>75°C), immediate repair
Major Problem - (>36°C-75°C), repair as soon as possible
Intermediate - (>10°C- 36°C)
Minor - 10°C or less
TABLE 2.3 - 2013 INSPECTION ACTUALS
2013
Budget
Actuals
Switchgear
Inspection
Target
Switchgear
Inspection
Actuals
Cost of
Inspection
/ SG
$11,748 83 82 $143
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
8
2.1.1.4 Data Governance Inspection records are currently being stored in an Access database with the information found in Table 2.4.
The inspection records can be viewed in the Hydro Ottawa Portal via GIS asset attribute tab hyperlink.
TABLE 2.4 - SWITCHGEAR INSPECTION STORED INFORMATION
Manufacturer Comments Hinges OK
Model Type Contact Condition Base Pad Condition
Year of Manufacture Fault Indicators Vault Condition
Voltage Class (in kV) Follow Up Action Required Penta Bolt
No SW Fuse Ways Comments Lock
Fuse Sizes Exterior Condition Visible Gap Lid/Door
Insulation Lifting Bolts Removed Operation Type
SCADA Control Safety Labels IR Temp
Contact Condition Unit ID Label Hot Stick Operation
Fault Indicators Exterior SW Oper Label Oil Leak
Follow Up Action Required Access to Location Internal Labeling to Spec
2.1.1.5 Reactive Maintenance Equipment that is considered critical condition will have an OMS ticket created for immediate follow-up
action. It is the responsibility of the area supervisor to schedule the work and close out the ticket when the
issue is resolved.
Most of the switchgear hot spots can be mitigated by cleaning connections, replacing minor components or
tightening connections. If the switchgear is unable to be improved through minor maintenance it will be
prioritized for replacement.
Switchgear that pose a safety, environmental or operating concern and are deemed defective are scheduled
for immediate replacement.
2.1.1.6 Gap Analysis The data captured through the infrared inspection needs to be fed back into the maintenance and Physical
Asset Management Plan. Determination of the number of switchgear undergoing maintenance and
replacement due to the influence of IR is required. Maintenance cost versus the replacement needs to be
analyzed to be incorporated in long term planning.
Information collected from the inspections needs to be fed back into GIS to verify base data, equipment
information and nomenclature.
Currently, there is no TIM program for the SF6 switchgear. In accordance with the manufacturers
recommendations no mechanical maintenance is required for the SF6 switchgear. The manufacturer
recommends occasional inspection of the switchgear and exercising the load interrupter switches and fault
interrupters. In addition to the manufacturer’s recommendations an inspection program should verify gas
pressure, record overall equipment condition and complete an infrared inspection of elbow connections.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
9
2.1.2 Padmount and Kiosk Transformers
2.1.2.1 Program Details The padmount and kiosk transformer inspections consist of an infrared scan and a visual inspection. Infrared
scanning detects loose connections, tracking, equipment overload, and other heat related problems. Visual
inspection checks for swollen elbows, exposed electrical hazards, operating hazards and graffiti. Additional
patrol inspection is performed as a result of the Graffiti Abatement and Repainting program.
2.1.2.2 Program Schedule Padmount transformers and kiosk transformers are inspected on
a three year cycle (see Table 2.5).
The OEB minimum inspection requirements dictates that
padmount transformers are to be patrolled in urban areas at a
maximum interval of 3 years and in rural areas at a maximum
interval of 6 years.
2.1.2.3 Program Performance Indicators In 2013, Hydro Ottawa inspected 99.7% of the
targeted padmount or kiosk transformers (see Table
2.6). The target number of transformers for 2013 was
higher as some of the scope from 2012 carried over.
Transformer bulk inspection lowers cost per
inspection with comparison of the air break
switchgear.
2.1.2.4 Data Governance Hydro Ottawa contracts out the padmount transformer inspections to a qualified third party. Currently, the
inspections are being completed using HOL tablets and the records are being stored in an Access database
with the information found in Table 2.7.
TABLE 2.6 - 2013 INSPECTION ACTUALS
XFMR
Inspection
Target
XFMR
Inspection
Actuals
2013
Budget
Actuals
Cost per
XFMR
Inspected
6,156 6,137 $220,086 $36.00
TABLE 2.5 - PADMOUNT INSPECTION
Frequency 2013
Budget
Every 3 Years
(5000 transformers /
year)
$300,000
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
10
TABLE 2.7 - TRANSFORMER INSPECTION STORED INFORMATION
Exterior Condition Spot Primary (degrees C) Elbow Manufacturer
Lifting Bolts Removed Spot Secondary (degrees C) Open Point
Safety Labels Spot Tank (degrees C) Open Point LA
Unit ID Label Spot Ambient (degrees C) Insulators
Access to Location Connected to phase XFRM ID Lbl Inside
Hinges OK Integ Sec Conn Asbestos
Base Pad Condition Elbow Condition Prim Lbl Per Spec
Vault Condition Tap Changer Sec Lbl Per Spec
Penta Bolt Curr Limt Fuse Manufacturer
Lock Fuse Type Year of Manufacture
Visible Gap Lid/Door Fault Ind Serial Number
Operation Type Fault Ind Correctly Installed Condition Rating
Hot Stick Operation Under Oil LBS Follow Up Action Required
Oil Leak Insert Vent Follow Up Action
Internal Labeling to Spec Elbow Posi Break Comments
2.1.2.5 Reactive Maintenance Equipment that is considered critical condition will have an OMS ticket created for immediate follow-up
action. It is the responsibility of the area supervisor to schedule the work and close out the ticket when the
issue is resolved.
Most of the transformer hot spots can be mitigated by cleaning connections, replacing minor components or
tightening connections. If the transformer is unable to be improved through minor maintenance it will be
prioritized for replacement.
Transformers that pose a safety, environmental or operating concern and are deemed defective are
scheduled for immediate replacement.
2.1.2.6 Gap Analysis Confirmation is required that the infrared inspection information is fed back into the maintenance and
replacement plan. The number of transformers undergoing maintenance and replacement due to the
influence of IR scans needs to be determined. The cost of maintenance versus the cost of replacement needs
to be analyzed for incorporation in future planning.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
11
2.1.3 Overhead Equipment
2.1.3.1 Program Details Overhead switches, transformers, lines, and associated
attachments are inspected through the IR Scanning Program.
The IR Scanning Program consists of performing infrared
inspections on overhead equipment from ground level.
Equipment that is over a temperature threshold is flagged as requiring further investigation.
2.1.3.2 Program Schedule All overhead power lines and associated apparatus, including switches and transformers, are scanned on a
three year cycle (see Table 2.8). Hydro Ottawa contracts out these inspections to a qualified third party.
The OEB minimum inspection requirement for overhead conductors and cables is to patrol urban areas at a
maximum interval of 3 years and rural areas at a maximum interval of 6 years.
2.1.3.3 Program Performance Indicators The target area for overhead insulator IR scan was completed and was under budget in 2013.
2.1.3.4 Data Governance Any problematic equipment in the critical equipment temperature range, as per Table 2.1, is included in a
report which is later given to Hydro Ottawa in paper and PDF format.
2.1.3.5 Reactive Maintenance Any equipment that is identified as a priority for maintenance will be further investigated for remediation of
any problems. The hot spots that are found usually indicate that connections need to be torqued and/or
cleaned, equipment needs to be replaced, or the equipment is being overloaded.
2.1.3.6 Gap Analysis The need for ultrasonic surveying should be investigated for the purpose of identifying equipment that is
tracking, but not yet overheating. Confirmation is required to determine if the contractor is trained and has
the proper equipment to conduct ultrasonic inspections while completing the infrared scanning.
The infrared inspection information must be fed back into the maintenance and replacement plan. The
number of overhead assets undergoing maintenance and replacement due to the influence of IR scans needs
to be determined. The cost of maintenance versus the cost of replacement needs to be analyzed for
incorporation into the development of long term plans.
Digital Image Thermal Image
TABLE 2.8 – OVERHEAD IR SCAN
Frequency 2013
Budget
2013
Actuals
1/3rd of the City
Every 3 Years
$15,000 $13,770
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
12
2.2 Padmount Switchgear CO2 Wash
2.2.1 Program Details Currently, all identified air-brake switchgear are being CO2
washed by contractors to remove contamination, such as road
salt or dirt, that contributes to tracking and flashover. To
eliminate the contamination’s impact on the IR results, the
switches are washed prior to performing IR scan. The carbon
dioxide is mixed with clean compressed air at the spraying
nozzle and safely removes surface contamination from both energized and de-energized internal equipment.
CO2 wash allows switchgear to be cleaned while energized, is environmentally friendly, safe, and will increase
system reliability by removing surface contamination that can lead to flashover.
C02 Wash: Before CO2 Wash: After
2.2.2 Program Schedule Currently, air-break switches are being washed on a 3 year cycle. The program schedule was developed based
on the switchgear cleaning prioritization that organized the switches based on their last CO2 wash.
The OEB minimum inspection requirements dictate that switchgear be patrolled in urban areas at a
maximum interval of 3 years, and in rural areas at a maximum interval of 6 years. CO2 wash is a
supplementary maintenance activity from the OEB’s minimum
inspection requirements.
2.2.3 Program Performance Indicators Hydro Ottawa had 79 out of 82 switchgear cleaned (see Table 2.10).
The remaining switchgear were inaccessible with the CO2 wash
equipment. These switchgear will continue to have visual and IR
inspections to ensure acceptable operating conditions. The number
of air brake switchgear and cost of the program continues to decrease, as they are replaced with SF6
switchgear.
TABLE 2.9 – SWITCHGEAR CO2 WASH
Frequency 2013 Budget 2013
Actuals
Every 3 Years
$100,000 $54,510
TABLE 2.10 - 2013 INSPECTION ACTUALS
SG Wash
Target SG Washed
Cost per
Switch
82 79 $690
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
13
2.2.4 Data Governance The CO2 wash information is being stored in a dedicated directory. The information is contained in an
inspection sheet completed by the contractor as well as a photo of the gear taken before and after the
cleaning (see Table 2.11).
2.2.5 Reactive Maintenance Equipment that has noticeable damage or requires further attention is reported to HOL for further
investigation. An OMS ticket is then entered for scheduling of the work. It is the responsibility of the area
supervisor to schedule the work and close out the ticket when the issue is resolved.
2.2.6 Gap Analysis The switchgear CO2 wash period will be reviewed to determine if the switchgear is being over washed and if
the cycle should be adjusted to make the program more cost effective. A method to determine if the wash
cycle is too frequent is to perform an IR scan prior to and after cleaning to prove a temperature change.
Ultrasonic testing is another method that will be investigated for use to determine the intensity of tracking
prior to and after the CO2 wash.
Switchgear failure analysis should trend the time between CO2 washing and the equipment failure to
evaluate the current CO2 wash cycle and the effectiveness of the wash.
The program should integrate the use of the inspection tablets to easily capture the CO2 wash inspection
information.
TABLE 2.11 – CO2 WASH STORED INFORMATION
Support Insulators Connection Pad Foundation
Switch Insulators Fault Indicators Latch/Mech Bolt
Arc Supressors Excess Moisture Door Hinges
Cable Terminations Evidence of Overheating Paint Condition
Barrier Boards Evidence of Arcing Nomenclature
Grounding Infrared Inspection Pad Grade/Level
Fuse holder Metal Enclosure Graffiti
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
14
2.3 Civil Structure Inspections
2.3.1 Program Details The manhole inspection program targets 300
manholes annually as part of a 10 year inspection
cycle. Underground chambers are also inspected
through regular work activities when crews perform
scheduled work in manholes and handholes.
2.3.2 Program Schedule All of the manholes will have undergone inspection
by 2017. Once all manholes are completed,
inspection or new build information will be
available for every HOL manhole. This will allow for
accurate prioritization of refurbishment and/or
replacement.
The OEB minimum inspection requirement for civil
infrastructure dictates that all structures be inspected
as part of patrol or in the course of doing routine work,
for urban civil structures at a maximum interval of 3
years and for rural structures at a maximum interval of
6 years.
The inspection will continue to meet 300 manholes per year to ensure a 10 year inspection cycle is
maintained. The civil structures are being inspected to
meet the OEB requirements through routine utility work.
2.3.3 Program Performance Indicators In 2013, Hydro Ottawa surpassed its target and had 589
manholes inspections logged (see Table 2.13). This large
inspection surplus was due to Hydro Ottawa resources
completing inspection during routine work along with two
contracted inspectors.
2.3.4 Data Governance Planned inspection of manholes is completed by a third
party contractor using HOL tablets. Hydro Ottawa crews also complete inspections when the civil structure is
entered as part of regular work activities. Inspection records are currently being stored in an Access
database containing the information found in the Table 2.14.
TABLE 2.12 – REMAINING INSPECTION FOR BASELINE
Manholes Inspected or
installed since 1999
Remaining Manholes to
be Inspected for Baseline
1716 1437
TABLE 2.13 – MANHOLES INSPECTED IN 2013
Inspector Manholes
Inspected
Cost per
Manhole
Greely 312 $300
Pipetek 31 $100
HOL 277 $100
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
15
TABLE 2.14 – MANHOLE INSPECTION STORED INFORMATION
Cover Location Sewer Connections
Okay
Sensors Okay Flat Sleeve Floor Rating
Cover Size Pump Required Asbestos Present Leaking Cables Racks Rating
Cover Condition Cleaning Required Asbestos Damaged Collar Rating Inspector Name
Cover Requires
Maintenance
Water Glass
Required
Swollen Sleeve Roof Rating Follow up Action
Sewer Connection Sump Pump Okay Split Sleeve Wall Rating Remarks
2.3.5 Reactive Maintenance The manholes that are considered to have critically poor components are reported to Hydro Ottawa for
immediate attention. These manholes will be investigated by Hydro Ottawa and will have work prioritized for
refurbishment or replacement.
2.3.6 Gap Analysis A review must be conducted to determine if inspection of handholes, equipment pads and other civil
structures requires a formal inspection program. Risk of possible civil structure failure will be compared to
the cost and benefit of the inspections to determine the extent of the program.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
16
2.4 Vegetation Management
2.4.1 Program Details Vegetation that encroaches on the distribution lines on
any right-of-way is managed to ensure system reliability
and public safety. The Hydro Ottawa service territory is
currently divided into regions for vegetation
management: 12 suburb and 16 core areas (Figure 2.1)
Third party arborist contactors are hired to maintain
certain vegetation areas annually.
2.4.2 Program Schedule Hydro Ottawa has a vegetation management
program that removes vegetation on either a
two-year or three-year cycle, depending on
whether an area is considered core or suburbs.
Hydro Ottawa also completes off cycle work for
removals, quick tree growth, customer
requests, or storm work.
The OEB minimum inspection for vegetation requires
patrol in urban areas at a maximum interval of 3 years
and rural areas at a maximum interval of 6 years.
2.4.3 Program Performance Indicators The vegetation management program completed the
planned scope of work and was slightly over budget due
to increased planned tree trimming (see Table 2.15).
FIGURE 2.1 - VEGETATION MANAGEMENT AREAS
TABLE 2.15 – VEGETATION MANAGEMENT
Frequency 2013 Budget 2013 Actuals
Core: Every 2 Years
Suburb: Every 3 Years
$2,842,939 $3,074,426
TABLE 2.16 –BUDGET ACTUALS BY TRIM TYPE
Planned Tree
Trimming
Emergency
Trimming
Emerald Ash
Borer
$2,768,987 $101,100 $204,338
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
17
2.4.4 Data Governance A vegetation inspection program was started in 2012 to collect tree information for each HOL pole span. The
inspection program is used to track primary tree species, line overhang risk, vegetation growth, the
vegetation access type, clearance distance from the primary conductor and overall condition of vegetation
growth. The inspection records are stored in an Access database with the information found in Table 2.17
and can be analyzed using Intergraph GeoMedia software or Microsoft Excel. Customer calls are tracked in
OMS and can be used to provide insight into problem areas.
2.4.5 Reactive Maintenance In addition to a cyclical vegetation management program, overhead conductor is subject to regular patrol
inspection by crews through everyday work. Off cycle trimming is performed when vegetation is identified
by Hydro Ottawa staff, a customer, or a third party.
2.4.6 Gap Analysis The inspection information will be used to reevaluate the tree trimming program to make the program more
effective by creating new trim cycle areas and well defined standards. This reevaluation will be complete by
the end of May 2014 for input into the next tree trimming cycle.
TABLE 2.17 – VEGETATION INSPECTION STORED INFORMATION
Is the span clear? Ash Trees outside of 10', Hazard
Access Primary Species
Clearance from Primary (in feet) Species 2
Main Bole less than 10' from line Species 3
Trim Class Smart Removal
Overhang Class Smart Removal Comments
Ash Trees within 10', Hazard Minimum Trim Cycle Required
Ash Trees within 10', No Hazard Additional Remarks
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
18
2.5 Insulator Washing
2.5.1 Program Details Hydro Ottawa has adopted an extensive insulator washing program
with full washing of critical 44 kV, 27.6 kV and 13.2 kV circuits.
Washing is used to clean insulators with contamination build-up.
Contamination decreases the insulation strength and causes tracking
and flashover. This arcing causes electrical losses but can also lead to
pole fires, further equipment damage, and outages to the system.
Currently, only porcelain insulators are being washed as part of the
program.
The program was revisited in 2013 and the insulator routes were modified based on several criteria. The
main selection criteria were system voltage, type of traffic or
nearby industry, numbers of recorded pole fires and percentage of
porcelain insulators.
The insulator wash is a supplementary activity from those stated in
the OEB’s Minimum Inspection Requirement document.
2.5.2 Program Schedule Insulators are washed in early spring (around mid-February) and selectively washed in fall (around mid-
October) each year. The spring wash is more crucial to cover all areas due to the large amounts of
contamination caused by the winter roadway snow clearance and salt spray.
2.5.3 Program Performance Indicators The 2013 insulator wash scope of work was completed and was under budget. As part of the new insulator
wash program the new contractor must report the number of poles visited and the quantity of porcelain
insulators present (see Table 2.19). HOL will use the feedback to update and track washing routes and to
better monitor program costs. The scope of work and
budget for this program will decrease as porcelain
insulators are replaced with polymer as part of the ongoing
Insulator Replacement Program.
2.5.4 Data Governance The contractor provides records of the poles being washed
and the number of insulators present on the poles to allow
Hydro Ottawa to track the washing routes.
2.5.5 Reactive Maintenance The contractor reports any equipment that appears visually problematic for further assessment. An OMS
ticket is then entered for scheduling of the work. It is the responsibility of the area supervisor to schedule
work and close out the ticket when the issue is resolved.
TABLE 2.18 – INSULATOR WASHING
Frequency 2013
Budget
2013
Actuals
Spring & Fall
Annually
$130,000 $117,097
TABLE 2.19 – 2013 FALL POLE WASH
Poles Visited
Insulators Washed
Wash Cost Per Insulator
Average Replacement
Cost
1032 5682 $9.67 $1000
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
19
2.5.6 Gap Analysis The root cause of pole fires needs to be recorded so the information can be used to support the insulator
washing program. The information can be used to compare the proportion of pole fires where the insulators
have been washed to those that have not.
The 2013 changes to the program will need to be reviewed and analyzed to determine if they have
contributed positively to the reduction of pole fires. The program evaluation will be based on the number of
pole fires and insulator failures, compared with historical record.
FIGURE 2.2 - INSULATOR WASHING MAP
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
20
2.6 Cable Inspection
2.6.1 Program Details Underground cables are patrol inspected during
manhole inspections. Select condition testing of XLPE
cable is done annually in the winter through a cable
testing program with National Research Council of
Canada (NRC). Specific cable segments are tested using
a polarization / depolarization technique and the results
are compared to reference cables. Test locations are
determined based on fault history, age and future
planned replacement projects. Test results provide
input to Hydro Ottawa’s cable
replacement and cable injection
strategy.
2.6.2 Program Schedule The OEB minimum inspection for cable
requires patrol at a maximum interval of
3 years in urban areas and at a maximum
interval of 6 years in rural areas. The
number of cable segments inspected
annually is currently limited by the
NRC and Hydro Ottawa resources.
2.6.3 Program Performance Indicators
In 2013, HOL completed 119 out of
the 120 inspection sites. The program
exceeded budget due to the increase
in contractual costs (see Table 2.20).
The total cost of cable testing is a fraction of the cost of cable
replacement (see Table 2.21). Cable testing allows for major cost
savings through focused cable replacement and cable injection
projects. Although cable age is a main factor in cable condition,
there are many other variables that affect the cable condition
and cable testing is a necessary maintenance activity which
allows for appropriate prioritization of replacement or injection
projects (see Table 2.22).
2.6.4 Data Governance Following testing, Hydro Ottawa receives a report from the NRC
including: cable segment overall condition, length, age and
conductor type and size of the segments tested. The information
is then stored in Excel where it can be analyzed using Intergraph
GeoMedia software or Microsoft Excel (see Figure 2.3)
TABLE 2.20 – 2013 CABLE INSPECTION BUDGET
2013 Budget
for Outside
Services
Actual Costs
Outside
Services
Inside
Services
Total
$110,000 $120,500 $119,074 $239,574
TABLE 2.21 – 2013 CABLE INSPECTION ACTUALS
Cables
Inspected
Length of
Cable
tested
(m)
Total Cost per Meter
Testing Replacement
w/o duct
Replacement
with duct
Injection
119 22,141 $11 $300 $600 $60
TABLE 2.22 – 2013 CABLE INSPECTION RESULTS
Cable Condition
(ave. cable age
1982)
Percentage of
Cable Tested
Like New 6.7%
Good 52.1%
Fair 32.8%
Bad 5.0%
Critical 3.4%
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
21
2.6.5 Reactive Maintenance The cable inspection program will be used in 2014 to test cables that were injected during 2013. The results
from the cable inspection program will be used for comparison to determine the overall effectiveness of the
cable injection technique.
2.6.6 Gap Analysis The cable testing program budget should increase to reflect the increase in contract costs. The program relies
heavily on internal resources and this cost should also be considered for budgeting.
Future development of the cable inspection program to increase the scope of work to inspect more cable on
an annual basis should be evaluated.
Other cable testing methods should be investigated to establish if there is more information that can be
obtained about cable and associated attachments that could aid in improving system reliability.
FIGURE 2.3 – SAMPLE OF CABLE INSPECTION RESULTS
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
22
2.7 Critical Switch Inspections
2.7.1 Program Details Hydro Ottawa currently has a critical switch program with the purpose of maintaining and inspecting
switches that are deemed a higher priority. These switches are selected based on the requirements to
interrupt higher loads, supply many customers, or critical customers such as hospitals. The cyclic inspection
program will ensure all areas (urban, rural and difficult access), will be visited, and problems detected before
they lead to system failures that may:
Impair the safety of Hydro Ottawa employees or the public at large;
Impair system reliability and reduce the quality of service to our customer;
Seriously reduce the life expectancy of the equipment and increase costs; and/or
Adversely affect the environment.
Currently, the critical switch maintenance includes a visual and mechanical inspection, electrical tests, and
comparison of resistance tests with similar connections. The mechanical and visual inspection includes a
visual check of the physical appearance of the mechanical and electrical connections, cleaning of the switch,
and mechanical operator test. The electrical test includes connection resistance checks, equipment torquing,
and Megger checks on each pole and/or control
wiring.
2.7.2 Program Schedule Currently, the program inspects switches on a 3
year cycle, with the intention of identifying system
problems such as deterioration or defective
equipment, abnormal condition, safety hazards,
etc.
The OEB minimum inspection requirements for switches dictates that they be patrolled in urban areas at a
maximum interval of 3 years and in rural areas at a
maximum interval of 6 years.
2.7.3 Program Performance Indicators In 2013, HOL inspected 13 out of 30 switches (see Table
2.24). The switches that were not inspected in 2013 will
be carried over to the 2014 scope of work. No outside
service budget was spent as internal resources were used
for TIM activities.
2.7.4 Data Governance Currently, the inspections are being completed using HOL tablets and the records are being stored in an
Access database with the information found in Table 2.25. The records can be viewed using Intergraph
GeoMedia software or Microsoft Excel.
TABLE 2.23 – CRITICAL SWITCH INSPECTION
Frequency 2013 Budget Outside Service
Budgeted Actuals
Every 3 years
$15,000 0
TABLE 2.24 – CRITICAL SWITCH INSPECTION
ACTUALS
Target number of
Switch Inspections
Switches Inspected
30 13
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
23
2.7.5 Reactive Maintenance The inspection program will report any major issues with the switches and will feed into capital replacement
projects. If any problems are located that can be immediately resolved, HOL will be notified for further
follow-up. An OMS ticket is then entered for scheduling of the work. It is the responsibility of the area
supervisor to schedule the work and close out the ticket when the issue is resolved.
2.7.6 Gap Analysis The critical switch list should be re-evaluated periodically to include any new switches that are deemed as
critical as the distribution system expands and evolves. Other possible switch maintenance activities should
be investigated that could increase the inspection effectiveness and switch reliability.
TABLE 2.25 – CRITICAL SWITCH INSPECTION STORED INFORMATION
Access to Location Hazards Mechanical Operation
Air Break Insulation Cleanliness Motorized SCADA
Blade Movements and Contact Insulation Condition Mounting
Condition Rating Insulation Type Nomenclature
Current Rating (Amps) Insulators Normally Open Point
Electrical Connections kV Rating Remarks (Explain Deficiencies Here)
Follow Up Action Needed Lead Connections Security
Gang Operated "Live" Component Condition Serial Number
Ground Operated Load Break Switch and Component Anchorage
Grounding intact Manufacturer Year of Manufacture
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
24
TABLE 2.26 – POLE INSPECTION
Frequency 2013 Budget
4500 per year
(Every 10 years)
$0
TABLE 2.27 – POLE INSPECTION ACTUALS
Poles
Inspected in
2013
2013
Actuals
2013 Cost
per pole
Historical
Cost
(Contractor)
Historical
Cost
(HOL)
360 (8% of
Target) $18,890 $58 $22 $33
2.8 Pole Inspections
2.8.1 Program Details One of Hydro Ottawa’s largest asset classes is distribution poles and attached hardware. These assets are
used to support overhead to support distribution and sub-transmission conductors throughout the city.
Maintaining these assets is essential for a reliable and safe system.
Hydro Ottawa currently performs visual inspection and drill testing on poles. Visual inspections record
detailed information about the pole, the attached hardware and any other relevant information. This
information is used in conjunction with the drill test to prioritize pole replacement, hardware replacement or
to create new designs that will integrate with the present configuration. Drill assessment is a nondestructive
testing method using an International Distribution Network (IML) Resistograph drill which measures the
density or resistivity of the wood against the drill bit. The drill test provides an overall indication of rot, void,
and solid wood thickness that can be used to calculate the
remaining strength of the pole.
2.8.2 Program Schedule The planned inspection schedule calls for the inspection of 4,500
poles annually, creating a 10 year inspection cycle (see Table 2.26).
The OEB minimum inspection for poles requires that they be
inspected in urban areas at a maximum interval of 3 years and in rural areas at a maximum interval of 6
years. In addition to the pole inspection program HOL poles are being inspected during IR scans, insulator
washing, and normal patrol to meet the OEB requirements.
2.8.3 Program Performance Indicators In 2013, HOL only reached 8% of its target amount (see Table 2.27) and the cost per pole was almost double
historical costs due to the lack of dedicated pole inspectors.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
25
2.8.4 Data Governance Currently, the inspections are being completed using HOL tablets and the records are being stored in an
Access database with the information found in the Table 2.28. The records can be viewed using Intergraph
GeoMedia software or Microsoft Excel.
TABLE 2.28 – POLE INSPECTION STORED INFORMATION
Pole Material Broken or Loose Guying Max Pole Circumference
Pole Age Ground Wire Missing or not Intact Min Pole Circumference
Preservative Pole Leaning or Twisting External Damage Hole Width
Crossarm Condition Signs of Fire/Lighting/Arcing External Damage Hole Depth
Transformer Standard Comments Insect Infestation Drill Orientation
Porcelain Insulator Vegetation Growth Max External Decay Width
Pole Top Condition Debris or Bird's Nesting Max Internal Decay Width
Shell Condition Cut-out Switch Minimum Remaining Shell Width
Wood Pecker Damage Sound Test Interpretation of Test Result
Inline Switch Overall Visual and Sound Remarks
2.8.5 Reactive Maintenance If an emergent issue is identified, System Office will be notified to submit a work request for crews. The
regional crews will prioritize the work to be completed in an acceptable period. The non-emergent issues and
inspection information is reviewed by Assets for future work planning.
2.8.6 Gap Analysis The program fails to meet the target goal of 4,500 poles annually since it mainly relies on light duty resources
and is approached as a low priority task, often being scheduled in the slow season of winter. Since the
program was developed in 2009, the number of poles inspected per year has been inconstant and below
targets.
The pole inspection program needs a budget to ensure dedicated resources can return target inspection
numbers. Currently, HOL does not have the internal resources to complete inspections without affecting
focus on capital projects.
Using non-dedicated resources affects the quality of the inspection returned. The information is inconsistent
and does not return reliable pole quality calculations. It is recommended that HOL hire a qualified third party
to perform the annual inspection as it will ensure scheduled completion and has historically proven to be the
most cost effective method.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
26
2.9 Graffiti Abatement
2.9.1 Program Details The objective of the Graffiti Abatement program is for painting rusted equipment, graffiti removal,
refurbishment and removal of eyesores and extending equipment life when necessary. Currently, equipment
requiring attention is identified through regular patrol by a contractor. The Graffiti Abatement program was
developed in response to the City of Ottawa Graffiti By-Law to ensure HOL keeps its property free of graffiti.
It also allows HOL to work cooperatively with the City of Ottawa By-Law department to address criminal acts
of graffiti to deter future acts of vandalism.
Before After
2.9.2 Program Schedule The graffiti abatement program does not have a
periodic inspection cycle. The contractor performs
regular inspections of the HOL region to identify
equipment requiring attention. The frequency of
inspections is based on the area’s historical
requirement for follow-up action.
The OEB Minimum Inspection Requirement states that transformer and switching kiosks are patrolled to
locate degraded paint and enclosure corrosion or damage. The graffiti abatement program supports Hydro
Ottawa in meeting these requirements.
2.9.3 Program Performance Indicators The graffiti abatement program has no predetermined
target. Equipment is routinely inspected and attended to
by a 3rd party. There were 1169 sites needing graffiti
removal or restoration (see Table 2.30) in 2013.
2.9.4 Data Governance The contractor provides Hydro Ottawa with paper records and before and after photos of the work that is
completed.
TABLE 2.29 – GRAFFITI ABATEMENT
Frequency 2013
Budget
2013
Actuals
Variable $102,000 $100,931
TABLE 2.30 –NUMBERS BY VISIT TYPE
Rust
Restoration
Tag
Removal
Total
Visits
Average
Cost
205 964 1169 $86
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
27
2.9.5 Reactive Maintenance If attention is required beyond the scope of the contractor, HOL will be contacted to further assess the
equipment condition. An OMS ticket is then entered for scheduling of the work. It is the responsibility of the
area supervisor to schedule the work and close out the ticket when the issue is resolved.
2.9.6 Gap Analysis Public awareness of the maintenance costs for this program could deter vandalism and deliberate damage to
HOL equipment. The program should integrate the use of the inspection tablets to easily capture the Graffiti
Abatement inspection information and potentially capture other equipment information.
Before After
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
28
2.10 Vault Maintenance
2.10.1 Program Details Hydro Ottawa has approximately 1500 vaults in its system, most of which are customer owned. Hydro
Ottawa is in the process of creating a vault maintenance program. Customer owned vaults are the customers’
responsibility to maintain along with the containing equipment. If no current maintenance is being
performed on customer owned vaults, Hydro Ottawa will recommend that maintenance is performed by the
customer. In the rare case that a customer does not complete maintenance on their vaults and there are
obvious issues, the vault could be reported to the Electrical Safety Authority (ESA) for follow-up.
Vault maintenance being performed is at the discretion of the customer or the contractor completing the
work. Most often vault maintenance includes visual inspection of the civil structure, ventilation fans, and all
electrical equipment, cleaning of the switchgear, transformer(s), breakers, the vault floors and any other
required equipment, IR scanning of the electrical equipment, torquing connections, inspecting grounding and
lighting and any other supplementary maintenance.
2.10.2 Program Schedule Currently, Hydro Ottawa is recommending 3 year inspection periods for vaults containing air break switches
and 6 years for vacuum, SF6 filled and oil filled switchgear. It is the customer’s responsibility to maintain their
vault.
Most often, inspection by Hydro Ottawa crews happens indirectly with the act of entering the vault to
perform field switching. This allows HOL crews to observe the equipment and the vault condition to ensure
that it is acceptable. HOL also performs inspections for smoke and heat detectors on a regular basis allowing
for spot checks of the vault condition.
2.10.3 Program Performance Indicators Currently, there are no performance indicators for this program. Performance indicators will be created once
inspections are completed using the tablets.
2.10.4 Data Governance Customer owned vaults that have contractors’ perform maintenance work often use paper forms for
maintenance records. It is at the discretion of the customer if they want to send a copy of the report to HOL
for its records. HOL indirectly keeps records of the vault maintenance in the System logs. When a customer is
performing vault maintenance HOL is required to isolate the vault. A request is submitted to HOL for the
switching isolations and a system log is created that can be used as a record of maintenance.
In past HOL inspection programs, such as PCB inspections, HOL has used paper format to record information
in the vault. The inspection fields that are completed by inspectors can be found in Table 2.31.
Currently, HOL keeps an Access database of the most current vault information including equipment details
and TIM records.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
29
TABLE 2.31 – VAULT INSPECTION STORED INFORMATION
Primary Voltage Floors Manager Company
Nomenclatures Sills Circuits1
Feed Type Grounding Signs
Asbestos (Y/N) Switchgear Type Prim. Cable Size
Heat Detectors(s) Incomers Fencing
Transformer Size Fourth Cable Hinges/Locks
Transformer Leaks/Noise Vault Pictures Ceiling
Ventilation Bucket Access Water Signs
Louvers 65F/16C Address Drains
Lighting Company Public Safety Concern
Door Condition Also Feeds Fuse Disconnects
Walls Sub Vaults Pole Pictures
2.10.5 Reactive Maintenance If problems are detected by HOL, the customer will be contacted to initiate maintenance activities for their
vault. If a customer does not initiate maintenance to rectify a problem that can impact HOL equipment and
reliability or affect public safety, the ESA can be contacted to initiate an inspection. If a problem is detected in
an HOL owned vault, underground crews are contacted immediately to attend to the equipment.
2.10.6 Gap Analysis Currently, there is no formal process of tracking customer vault maintenance. A periodic inspection program
of vaults containing HOL equipment needs to be implemented. HOL is in the process of incorporating the
tablets with the inspection program to improve data analysis and inspection tracking.
Communication to customers owning vaults needs to occur to properly educate customers on the
requirement for maintenance and ensuring it is clear the equipment for which they are responsible for
maintaining.
Through the amalgamation of the local distribution companies into HOL, some vault ownership and
demarcation points have become undecided by both parties. Vault ownership and demarcation points must
be determined in order to be able to consistently develop a path forward for maintenance activities.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
30
3 Station Testing, Inspection, and Maintenance
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
31
TABLE 3.1 – BATTERY MAINTENANCE
2013
Budget
2013
Actuals
$65,430 $42,930
TABLE 3.2 –BATTERY INSPECTION SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Electrical Test Yearly
TABLE 3.3 – BATTERY MAINTENANCE
Battery Visual
Inspection Target
Battery
Inspection
Actuals
1,008 443
TABLE 3.4 – BATTERY INSPECTION STORED
INFORMATION
General Appearance Access to Location
Battery Voltage Equalize Cycle
Battery Equalize Remarks
Battery Rack Bonding Follow-up Action
3.1 Battery Maintenance
3.1.1 Program Details Currently, the station battery and battery charger are inspected by completing voltage measurements and
visual inspection of the DC supply components. Included in the voltage measurements are recording
individual cell voltages, the battery charger normal charging voltage and the battery charger equalization
voltage. The voltage of the individual cells will ensure that they are holding their nominal level and will
confirm the cell is in good condition. The charging voltages are taken to ensure the battery charger is set up
to charge the battery at the manufacturer’s recommendations. Visual inspections are completed for the
bonding connections, the battery and battery charger as
well as all connecting equipment. The visual inspection
determines if there are low electrolyte levels and if
corrosion exists at the battery terminals.
3.1.2 Program Schedule Currently, the cells and DC supplies are visually inspected
as part of the monthly station visual inspections. The goal
for the battery maintenance schedule is to meet the
requirements set out in Table 3.2.
3.1.3 Program Performance Indicators In 2013, HOL performed 443 battery monthly visual
inspections and maintenance actuals were under budget
(see Table 3.1 and Table 3.3). The inspection performance
numbers do not include inspections completed using
PowerDB software. Hydro Ottawa is working with the
PowerDB software to create effective inspection reports
to summarize Station TIM program performance
numbers.
3.1.4 Data Governance Electrical testing is completed using Alber’s testing
equipment and results are uploaded to an HOL database.
The Alber’s test equipment measures individual cell
voltage, resistance, specific gravity, temperature and
provides an overall cell health rating. Other records are
completed in paper form and are stored in the stations
directory (see Table 3.4). As well as yearly inspection, the SCADA system continuously monitors the stations
battery voltage levels and in turn is monitored by system office.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
32
3.1.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations required maintenance activities. The
work is then scheduled to be performed by the
crews after any necessary planning and
procurement has been completed.
Common failure modes of cells in a battery are:
under voltage due to improper equalization charge,
low electrolyte levels, and loose strap connections
connecting the cells together. Cells with low voltage
should be replaced to ensure thermal runaway does
not happen and the battery’s integrity is
maintained. A thermal runaway can occur when
cells in a battery bank vary in voltage. The difference
in cell voltages cause internal currents to circulate in
the battery bank and can cause more heat to be
generated in a cell than can be dissipated on the
case. The heat then causes catastrophic damage to
the cell casing and can lead to thermal runaways in other cells.
If terminal connections are found to be corroded and or loose, the connections should be cleaned, an oxide
exhibitor should be used and the connections should be torqued to specifications.
3.1.6 Gap Analysis PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
33
3.2 Relay Maintenance
3.2.1 Program Details Relays are currently undergoing complete inspections every 4 to
6 years. Visual inspections are part of the monthly stations
inspection and check for obvious equipment deficiencies.
Electrical, mechanical and operational inspections identify loose
connections, broken studs, burned insulation, dirty contacts,
setting configuration and proper operation. IR scans are
completed as part of the station annual IR scan and detects
equipment operating over the manufacturers temperature
specifications.
3.2.2 Program Schedule Visual inspections are part of the monthly stations inspection (see Table 3.6). IR scans are completed as part
of the station annual IR scan. Electrical, mechanical and operational test are completed every 4 to 6 years.
3.2.3 Program Performance Indicators In 2103, HOL did not meet monthly relay inspection targets (see
Table 3.7) and was under budget (see Table 3.5) due to lack of
available resources and capital projects taking precedence. Also,
the inspection performance numbers do not include inspections
completed using PowerDB software. Hydro Ottawa is working with
the PowerDB software to create effective inspection reports to
summarize Station TIM program performance numbers.
3.2.4 Data Governance Relay inspections have transitioned over to PowerDB software.
The inspection information is centralized in an Access database
and can be viewed using PowerDB (see Table 3.8).
3.2.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is
created in either Track-It or PowerDB depending on the work
complexity. This enables tracking of stations requiring maintenance
activities. The work is then scheduled to be performed by the crews
after any necessary planning and procurement has been
completed.
3.2.6 Gap Analysis The maintenance schedule needs to be developed to meet the
minimum periodic inspections listed in Table 3.6. Information
on failure modes should then be evaluated as part of the
Physical Asset Management Plan.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
TABLE 3.5 –RELAY/BREAKER MAINTENANCE
Frequency 2013
Budget
2013
Budget
Actuals
4 - 6 Years
$573,333 $315,700
TABLE 3.6 –RELAY MAINTENANCE SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Operational Test 4 - 6 Years
Mechanical Test 4 - 6 Years
Electrical Test 4 - 6 Years
TABLE 3.8 –RELAY INSPECTION STORED
INFORMATION
As Found Settings Visual Condition
As Left Settings Electrical Test
Results
TABLE 3.7 –RELAY INSPECTIONS
Relay Visual
Inspections
Target
Inspections
300
1,008
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
34
3.3 Transformer Maintenance
3.3.1 Program Details Transformer maintenance currently includes: visual inspection,
electrical tests, mechanical tests and oil sampling. The visual
inspection involves current and voltage readings, temperature
readings, liquid level check, physical condition assessment and
pressure/vacuum gauge readings.
The visual inspections of current, voltage and temperature
readings ensure that the transformers are operating within the
acceptable limits. If the levels are measured outside of the
specifications, investigation will be required to determine the root cause
and remediation plans.
Liquid, pressure and vacuum level readings are checked to ensure that
the transformer is not leaking in any way. If the readings are out of the
acceptable range, the stations office is contacted to provide immediate
support or to create a Track-It entry to schedule follow-up action.
3.3.2 Program Schedule The power transformer maintenance uses Table 3.10 as a guide for scheduling.
3.3.3 Program Performance Indicators In 2013, Hydro Ottawa did not meet target inspection numbers
(see Table 3.11). The inspection report is created from inspections
completed on the tablet. TIM activities apart from the visual
inspection are not recorded by tablet and may account for the
program being over budget. Also, the inspection performance
numbers do not include inspections completed using PowerDB
software. Hydro Ottawa is working with the PowerDB software to
create effective inspection reports to summarize Station TIM
program performance numbers.
TABLE 3.9 –POWER TRANSFORMER
MAINTENANCE
2013
Budget
2013
Actuals
$18,000 $62,860
TABLE 3.10 - POWER TRANSFORMER
SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Mechanical Test 3 - 5 Years
Electrical Test 3 - 5 Years
Operational Test 3 – 5 Yearly
Oil Samples Yearly
TABLE 3.11 –POWER TRANSFORMER VISUAL
INSPECTION
2013 Visual
Inspections
2013 Target
Inspections
1,011 4,008
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
35
3.3.4 Data Governance Transformer inspections have transitioned over to PowerDB software. The inspection information is
centralized in an Access database and can be viewed using PowerDB (see Table 3.12).
TABLE 3.12 – TRANSFORMER INSPECTION STORED INFORMATION
General Appearance Explosion Vent Condition Recorded Tank Pressure
Oil Leaks Silica Gel Breather Condition Recorded Oil Temp Present
Bushings Condition Grounding Intact Recorded Oil Temp Maximum
Cooling Pump Condition Recorded Oil Level Bushings Gauge Recorded Wind Temp Present
Fans Condition Recorded Oil Level Bushings Sight
glass
Recorded Wind Temp
Maximum
Control Cabinet/Heaters
Condition
Recorded Oil Level Transformer
Gauge
Remarks
Gas Relay Condition Recorded Gas Pressure FollowUp Action Required
3.3.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.3.6 Gap Analysis A well-defined periodic inspection schedule must be created for station transformers to allow for more
efficient future maintenance activities.
Transformer inspections need to be tracked more accurately to ensure the different maintenance, inspection
and testing activities are being completed.
The current TIM should be compared with industry best practice to ensure HOL is creating an effective TIM
Plan.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
36
3.4 Transformer Oil Analysis Testing
3.4.1 Program Details Currently, transformers undergo dissolved gas analysis (DGA) and oil quality analysis annually. The DGA and
oil quality analyses are an important diagnostic tool used to monitor the condition of the unit. Emphasis is
placed on these tests for detecting insulation breakdown, water in the oil, stressing of the coils, localized
overheating and arcing that can lead to failure of the transformer. Currently, HOL sends oil samples to an oil
testing laboratory, uses DGA portable equipment and uses DGA online monitoring equipment. The oil testing
laboratory uses sophisticated lab equipment that creates a full analysis of the oil sample, compares the
results to any previous transformer oil samples, and specifies detailed recommendations for the transformer.
If the laboratory processing lead time is too lengthy, HOL will use portable DGA equipment for immediate
results. The online DGA equipment is used for continuous monitoring of transformer gas concentrations and
can be used to set alarms at specific gas concentration thresholds. DGA online monitoring systems are being
installed as part of HOL standards and are capable of sending DGA
data to the PI server data historian.
DGA and oil quality tests identify abnormalities within the transformer
and provide detailed information to allow for sound decision making
for future operation and maintenance of the transformer.
3.4.2 Program Schedule The target inspection schedule is to annually complete DGA testing
and oil quality analyses on all transformers, with
more frequent testing on units showing
abnormalities.
3.4.3 Program Performance Indicators In 2013, HOL met the testing targets (see Table
3.14). Transformers or tap changers showing
abnormal results may be tested more frequently as recommended by the consultant. The budget for outside
services needs to be reevaluated to be more consistent with actual spending.
3.4.4 Data Governance Currently, the DGA and oil quality analysis are performed by a qualified oil testing laboratory and provides
HOL with DGA summary reports that are stored in the HOL stations network directory. The portable oil
analyzer prints a paper copy of the DGA results that are analyzed immediately. The DGA online monitoring
results are fed back into the PI data server and can be accessed via PI software.
3.4.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations required maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.4.6 Gap Analysis HOL should investigate performing its own oil analysis and implementing a central repository for all of the
historical data.
The budget for this program should be re-evaluated to better reflect the program’s actual budget.
TABLE 3.13 –TRANSFORMER OIL
SAMPLING
Frequency 2013
Budget
2013
Actuals
Annually
$198,000 $64,340
TABLE 3.14 –TRANSFORMER OIL TESTING RESULTS
XFMR
Target
Tap Changers
Target
XFMR Tests
Completed
Tap Changer
Tests Completed
151 41 163 45
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
37
3.5 Transformer Doble Testing
3.5.1 Program Details Doble testing equipment is being used to assess the overall power factor, turns ratio testing, leakage
reactance and exciting current of the transformer. These tests are used to detect moisture in the oil or
insulation, detect contamination in the transformer bushing, determine the electrical insulation quality, and
locate bad connections and winding movement. The Doble equipment provides test results and expected
values and thresholds to effectively translate the results. Doble testing, DGA testing and oil quality analysis
complement each other to provide clear
indication of the overall health of the
transformer.
3.5.2 Program Schedule Doble testing follows transformer maintenance
and is targeted every 3 to 5 years (see Table
3.15).
3.5.3 Program Performance Indicators In 2013, HOL did not meet inspection targets (see Table 3.15) due to lack of available resources and capital
projects taking precedence.
3.5.4 Data Governance The Doble testing results are stored in the stations network directory and can be viewed in Microsoft Internet
Explorer or using the Doble Software.
3.5.5 Reactive Maintenance The test results are used to plan future operation, maintenance, and replacement of the transformer.
3.5.6 Gap Analysis A periodic inspection cycle needs to be created for all station transformers. The Doble testing results need to
be analyzed closely to be able to better determine equipment health indexing and prioritization. Testing
results should be located in a central repository with all other transformer testing results.
TABLE 3.15 –TRANSFORMER DOBLE TESTING
Frequency 2013 Target
Testing
2013 Testing
Actuals
Every 3 to 5 years 33-55/year 24
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
38
3.6 Station Visual Inspections
3.6.1 Program Details The Station Visual Inspection program is used
to assess the condition of the station yard, the
station building exterior and interior, the
station security, and general equipment
condition.
3.6.2 Program Schedule The current inspection program visits stations
on a monthly basis. The stations are
categorized by voltage and location type (see
Table 3.17).
3.6.3 Program Performance Indicator In 2013, HOL did not meet its targets for station inspections due
to lack of available resources and capital projects taking
precedence. Station inspection targets are once a month for every
station (see Table 3.18). The inspection performance numbers do
not include inspections completed using PowerDB software.
Hydro Ottawa is working with the PowerDB software
to create effective inspection reports to summarize
Station TIM program performance numbers.
3.6.4 Data Governance Stations visual inspections have transitioned over to
PowerDB software. The inspection information is
centralized in an Access database and can be viewed
using PowerDB. Station visual inspection is completed
for all main components:
Yard
Building Exterior
Building Interior
Basement
DC System
Station RTU
Protection Relay Panels
Outdoor Structures
Station Service Transformers
Power Transformers
Circuit Breakers / Reclosers
Voltage Regulators
Switchgear Assemblies
Circuit Switches
Ground Grid
TABLE 3.16 –STATION INSPECTIONS
Frequency 2013
Budget
2013
Actuals
Monthly $295,616 $100,670
TABLE 3.18 –STATION INSPECTIONS
Inspection Type Quantity
(Target
1,008)
Building Exterior 380
Building Interior 380
Basement 287
Station Structure 161
Stations Yard 443
TABLE 3.17 –STATIONS BY TYPE
Station Type Quantity
Urban Outdoor Open TS 9
Urban Outdoor Open DS 13
Urban Outdoor Enclosed DS 13
Urban Indoor Enclosed DS 47
Rural Outdoor Open DS 2
Urban Outdoor Open TS 9
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
39
3.6.5 Reactive Maintenance If a deficiency is identified by the inspections, a
maintenance activity is created in either Track-It or
PowerDB depending on the work complexity. This
enables tracking of stations requiring maintenance
activities. The work is then scheduled to be
performed by the crews after any necessary
planning and procurement has been completed.
3.6.6 Gap Analysis Monthly station inspections need to be consistently
completed to meet the target schedule. If capital
work continues to dominate HOL resources, a
dedicated maintenance crew or a 3rd party may be required to complete the inspections.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
40
3.7 Tap Changer Maintenance
3.7.1 Oil Filled (Filtered) Tap Changers
3.7.1.1 Program Details Oil filled tap changer TIM activities include
recording position of the tap changer, inspecting
the physical and mechanical condition, verifying
correct auxiliary device operation, verifying
correct liquid level in all tanks, performing tests
as recommended by the manufacturer, verifying
operation of heaters and verifying grounding.
An internal inspection is also conducted and
includes removing of the oil and cleaning carbon
residue and debris from compartment, inspecting the contacts
for wear and alignment, tightening all electrical and mechanical
connections to calibrated specifications, inspecting the tap
changer components for signs of moisture, cracks, electrical
tracking or excessive wear and then refilling the tank with
filtered oil.
3.7.1.2 Program Schedule The oil filled (filtered) tap changer inspections are completed
monthly and maintenance is performed every 3 to 5 years.
HOL completes oil analyses on select tap changers during
transformer oil analysis.
3.7.1.3 Program Performance Indicator In 2013, Hydro Ottawa did not meet the monthly inspection
targets (see Table 3.21) and budget actuals were greatly
exceeded (see Table 3.19). The increase in maintenance costs
were associated to exceeded labor and material costs. The
inspection report is created from inspections completed on
the tablet. TIM activities apart from the visual inspection are
not recorded by tablet and may account for the program being
over budget. Also, the inspection performance numbers do
not include inspections completed using PowerDB software. Hydro Ottawa is working with the PowerDB
software to create effective inspection reports to summarize Station TIM program performance numbers.
3.7.1.4 Data Governance Tap changer inspections have transitioned over to PowerDB software. The inspection information is
centralized in an Access database and can be viewed using PowerDB.
3.7.1.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
TABLE 3.19 –TAP CHANGER BUDGET
2013
Budget
2013 Actuals
$36,324 $229,569
TABLE 3.20 –TAP CHANGER SCHEDULE
Visual
Inspection
Maintenance
Monthly Every 3-5 years
TABLE 3.21 –TAP CHANGER INSPECTIONS
Visual Inspection
Target
Inspection
Actuals
3406 305
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
41
3.7.1.6 Gap Analysis Tap changer inspections need to be consistently completed to meet the target schedule. If capital work
continues to dominate HOL resources, a dedicated maintenance crew or a 3rd party may be required to
complete the inspections.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
42
3.7.2 Oil/Vacuum Filled Tap Changers
3.7.2.1 Program Details Oil/vacuum tap changer inspection includes: recording position of the tap changer, inspecting the physical
and mechanical condition, verifying correct auxiliary device operation, verifying vacuum level, performing
tests as recommended by the manufacturer, verifying operation of heaters, verifying grounding, and
inspecting the vacuum bottles for wear or erosion.
3.7.2.2 Program Schedule The oil filled/vacuum tap changer inspections are completed monthly and maintenance is performed every 3
to 5 years. HOL completes oil analyses on select tap changers during transformer oil analysis.
3.7.2.3 Program Performance Indicator In 2013, Hydro Ottawa did not meet the monthly inspection targets (see Table 3.21) and budget actuals were
exceeded (see Table 3.19). The increase in maintenance costs were associated to exceeded labor and
material costs. The inspection report is created from inspections completed on the tablet. TIM activities apart
from the visual inspection are not recorded by tablet and may account for the program being over budget.
Also, the inspection performance numbers do not include inspections completed using PowerDB software.
Hydro Ottawa is working with the PowerDB software to create effective inspection reports to summarize
Station TIM program performance numbers.
3.7.2.4 Data Governance Tap changer inspections have transitioned over to PowerDB software. The inspection information is
centralized in an Access database and can be viewed using PowerDB.
3.7.2.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.7.2.6 Gap Analysis Tap changer inspections need to be consistently completed to meet the target schedule. If capital work
continues to dominate HOL resources, a dedicated maintenance crew or a 3rd party may be required to
complete the inspections.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
43
3.8 Stations Infrared (IR) Inspection
3.8.1 Program Details Infrared (IR) inspection on station equipment is
completed in conjunction with more specific equipment
inspection. The IR inspection checks equipment for hot
spots to indicated loose connections, defective
equipment, overloading, contamination, short circuits
and ground faults. HOL performs IR scanning, internally,
on station equipment.
3.8.2 Program Schedule The IR inspection is conducted in conjunction with other
station equipment inspections.
3.8.3 Program Performance Indicators In 2013, there were no charges to the stations IR scanning program
(see Table 3.22). The IR scanning was completed during station
inspection but was not formally documented.
3.8.4 Data Governance Currently, IR photos are stored in the stations network directory
with a record of IR scans kept in an Excel spreadsheet.
3.8.5 Reactive Maintenance Any hot spots identified by the inspection are monitored closely by station electricians. If the temperature
trends past a threshold, further maintenance is planned by creating an entry in Track-It or PowerDB. The
Station Office then schedules the work after any necessary planning and procurement has been completed.
3.8.6 Gap Analysis IR scans need to be documented using PowerDB. If a deficiency is found the IR image(s) should be attached
with the PowerDB work form for follow-up action.
TABLE 3.22 –STATION IR
INSPECTIONS
Frequency 2013
Budget
Actuals
Yearly $38,000 0
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
44
3.9 Switchgear Maintenance
3.9.1 Switchgear General Maintenance
3.9.1.1 Program Details Currently, switchgear undergoes inspections that check the switches,
over current relays, position indicator, heaters, breaker tools, and
breaker and racking mechanism operation (see Table 3.24).
3.9.2 Program Schedule Visual inspection follows the monthly station inspection. Thorough
switchgear maintenance and testing is completed every 4 – 6 years cycle.
3.9.3 Program Performance Indicators In 2013, HOL did not meet target inspection numbers (see Table 3.23). HOL
did not meet its targets for switchgear inspections due to lack of available
resources and capital projects taking precedence. Also,
the inspection performance numbers do not include
inspections completed using PowerDB software. Hydro
Ottawa is working with the PowerDB software to
create effective inspection reports to summarize
Station TIM program performance numbers.
3.9.3.1 Data Governance Switchgear inspections have transitioned over to PowerDB software. The inspection information is
centralized in an Access database and can be viewed using PowerDB.
3.9.3.2 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.9.3.3 Gap Analysis Switchgear testing, inspection, and maintenance needs to be consistently completed to meet the target
schedule. If capital work continues to dominate HOL resources, a dedicated maintenance crew or a 3rd party
may be required to complete the inspections.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
TABLE 3.24 –SWITCHGEAR INSPECTION
General Appearance Breaker Tools Condition
Heaters Condition Breakers Condition
Position Indicator
Position
Remarks
TABLE 3.23 –STATION
SWITCHGEAR INSPECTIONS
Target
Inspections
Actual
Inspections
1,008 288
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
45
3.9.4 Breaker Maintenance
3.9.4.1 Program Details The current TIM activities for circuit breakers
include: visual inspection and electrical,
mechanical, and operational tests (see Table 3.26).
Visual inspection ensures that the breakers are
clean, there are no signs of arcing or leaking oil,
and there is no damage to the breaker or arc
chute. Electrical testing includes performing insulation resistance and contact resistance testing. Mechanical
tests include: cleaning the bushing, checking for any leaks around the gaskets, cleaning, lubricating and
testing the operating mechanism, checking the contacts, and tightening all bolts, pins, and connections.
Operational testing of the breaker checks the operating mechanisms, and ensures the proper operation of
the breaker and the charging motor.
TABLE 3.26 –BREAKER MAINTENANCE
Equipment TIM Activity
Visual Electrical Mechanical Operational
Contacts
Arc Interrupters
Insulation
Trip Device Circuit
Operating Mechanism
3.9.4.2 Program Schedule The schedule for the different types of breakers varies depending on the recommended maintenance
requirements of the manufacturer. The tables below list the ideal maintenance schedule for the various
breaker types.
TABLE 3.27 –MINIMUM OIL CIRCUIT BREAKER SCHEDULE
Maintenance
Activity
Frequency
Visual Inspection Monthly
IR Inspection Yearly
Mechanical Test 4 – 6 years
Electrical Test 4 – 6 years
Operational Test 4 – 6 years
TABLE 3.28 – HIGH VOLTAGE CIRCUIT BREAKER
SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Mechanical Test 4 – 6 years
Electrical Test 4 – 6 years
Operational Test 4 – 6 years
TABLE 3.25 –RELAY/BREAKER MAINTENANCE
Frequency 2013
Budget
2013
Budget
Number
of
Breakers
4 - 6 Years
$573,333 $315,700 929
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
46
3.9.4.3 Program Performance Indicators In 2013, HOL did not meet its targets (see Table 3.31) and
was under budget (see Table 3.25). Recloser and breaker
inspections are completed using the same inspection class,
impeding recloser and breaker inspections numbers from
being evaluated independently. HOL did not meet its targets for breaker and recloser maintenance due to
lack of available resources and capital projects taking precedence. Also, the inspection performance numbers
do not include inspections completed using PowerDB software. Hydro Ottawa is working with the PowerDB
software to create effective inspection reports to summarize Station TIM program performance numbers.
3.9.4.4 Data Governance Breaker TIM activities have transitioned over to PowerDB software. PowerDB enables form customization to
have breaker specific TIM activities per the manufacturers’ recommendations. The inspection information
can be viewed using the PowerDB software.
TABLE 3.32 – BREAKER INSPECTION
Overall Cleanliness Structural Members Main Contacts
Insulating Members Cubicle Arcing Contacts
Mechanical Connections Auxiliary Devices Arcing Chutes
Contact Sequence Ground Connection Insulation Testing
Contact Resistance Temperature Puffer Operation
Racking Device Shutter Contact Fingers
3.9.4.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
TABLE 3.29 –SF6 CIRCUIT BREAKER SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Mechanical Test 4 – 6 years
Electrical Test 4 – 6 years
Operational Test 4 – 6 years
TABLE 3.30 – AIR MAGNETIC CIRCUIT BREAKER SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Inspection Yearly
Mechanical Test 4 – 6 years
Electrical Test 4 – 6 years
Operational Test 4 – 6 years
TABLE 3.31 – BREAKER & RECLOSER INSPECTIONS
Target Actuals
11,844 1,295
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
47
3.9.4.6 Gap Analysis A well-defined breaker inspection schedule needs to be created to ensure that the recommended
maintenance is being performed in an acceptable time period. Analysis of test results needs to be done by
Assets following setting clear direction on expected test results and thresholds.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
48
3.9.5 Stations Recloser Maintenance
3.9.5.1 Program Details Recloser maintenance includes: visual inspection, electrical testing, mechanical testing and dielectric
sampling. The visual inspection checks the bushings, contacts and liquid level and includes an IR scan of the
recloser and its components. The electrical, mechanical, and operational inspection includes checking
mechanical connections, testing insulation resistance and recloser function test to ensure proper operation.
3.9.5.2 Program Schedule The schedule for recloser maintenance is every 4-6 years (see Table
3.33).
3.9.5.3 Program Performance Indicators In 2013, HOL did not meet its targets for breaker and recloser
inspections (see Table 3.31). Recloser and breaker inspections are
completed using the same inspection class, impeding recloser and breaker inspections numbers from being
evaluated independently. HOL did not meet its targets for breaker and recloser maintenance due to lack of
available resources and capital projects taking precedence. Also, the inspection performance numbers do not
include inspections completed using PowerDB software. Hydro Ottawa is working with the PowerDB software
to create effective inspection reports to summarize Station TIM program performance numbers.
3.9.5.4 Data Governance Recloser TIM activities have transitioned over to PowerDB software. PowerDB enables form customization to
have recloser specific TIM activities per the manufacturers’ recommendations. The inspection information
can be viewed using the PowerDB software.
3.9.5.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.9.5.6 Gap Analysis Recloser operating and electrical test should include time-travel analysis to ensure the recloser is operating
within the manufactures specification.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
TABLE 3.33 –RECLOSER MAINTENANCE
Frequency Number of
Reclosers
4 - 6 Years 58
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
49
3.9.6 Station Switch Maintenance
3.9.6.1 Program Details Switches are currently undergoing visual inspection on a
monthly basis. Visual inspection checks for issues with the arc
shoots, arc tips, broken insulators, burned insulators, and dirty
components. The visual inspection is completed to ensure that
the switch has no issues that could indicate a problem with day
to day operation.
3.9.6.2 Program Schedule Electrical and operational tests that verify the overall switch
integrity are completed every 4 to 6 years.
3.9.6.3 Program Performance Indicators In 2013, switch inspections did not meet target due to lack of
available resources and capital projects taking precedence (see
Table 3.36). The inspection performance numbers do not
include inspections completed using PowerDB software. Hydro
Ottawa is working with the PowerDB software to create
effective inspection reports to summarize Station TIM program
performance numbers.
3.9.6.4 Data Governance Switch inspections have transitioned over to PowerDB
software. The inspection information is centralized in an
Access database and can be viewed using PowerDB (see Table
3.37).
3.9.6.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance
activity is created in either Track-It or PowerDB depending on
the work complexity. This enables tracking of stations requiring
maintenance activities. The work is then scheduled to be
performed by the crews after any necessary planning and
procurement has been completed.
3.9.6.6 Gap Analysis A well-defined switch maintenance schedule and budget needs to be created to ensure the recommended
maintenance is being performed in an acceptable time period.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
TABLE 3.34 – STATION SWITCH MAINTENANCE
BUDGET
Switch Budget Actuals
0 $3,722
TABLE 3.35 – STATION SWITCH MAINTENANCE
SCHEDULE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Scan Yearly
Mechanical Test 4 – 6 years
Electrical Test 4 – 6 years
Operational Test 4 – 6 years
TABLE 3.36 – STATION SWITCH INSPECTION
Approximate
Switch Inspection
Target
Switches Inspected
2000 109
TABLE 3.37 – STATION SWITCH INSPECTION
STORED INFORMATION
General
Appearance
Components
Condition
Switches/Fuses
Condition
Remarks
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
50
3.9.7 High Voltage Fuse Maintenance
3.9.7.1 Program Details High voltage fuse inspection involves: IR scans, visual
inspection and cleaning and clip pressure inspection.
The visual inspection includes: inspecting the fuse
holders, insulators and fuse for breaks, cracks, burns,
pitting, and indication of flashover and sign s of
deterioration. The IR inspection checks the fuse
holder to ensure the components are under the
threshold temperature.
3.9.7.2 Program Schedule Fuse inspections and maintenance follows
switch inspections (see Table 3.38).
3.9.7.3 Program Performance Indicators In 2013, fuse inspections did not meet target
due to lack of available resources and capital
projects taking precedence (see Table 3.36). The
inspection performance numbers do not include
inspections completed using PowerDB software.
Hydro Ottawa is working with the PowerDB
software to create effective inspection reports
to summarize Station TIM program performance
numbers.
3.9.7.4 Data Governance Fuse inspections have transitioned over to PowerDB software. The inspection information is centralized in an
Access database and can be viewed using PowerDB.
3.9.7.5 Reactive Maintenance If a deficiency is identified by the inspections, a maintenance activity is created in either Track-It or PowerDB
depending on the work complexity. This enables tracking of stations requiring maintenance activities. The
work is then scheduled to be performed by the crews after any necessary planning and procurement has
been completed.
3.9.7.6 Gap Analysis A well-defined high voltage fuse schedule needs to be created to ensure the recommended maintenance is
being performed in an acceptable time period. A more centralized database of fuse inspection and
maintenance needs to be created. PowerDB software should be used to store high voltage fuse inspection
information.
PowerDB must be developed to have the ability to show effective inspection reports. Hydro Ottawa is
currently working with the PowerDB software to create effective inspection reports to summarize Station
TIM programs.
TABLE 3.38 – STATION HIGH VOLTAGE FUSE
MAINTENANCE
Maintenance Activity Frequency
Visual Inspection Monthly
IR Scan Yearly
Other – Check clip contact
pressure & clean
4-6 year
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
51
4 SCADA Maintenance - Stations and Distribution
4.1 Program Details Supervisory Control and Data Acquisition (SCADA) is a control system that allows for the monitoring and
control of compatible electrical equipment in the Hydro Ottawa electrical system. The maintenance
performed on SCADA controlled equipment includes visual inspection, checking communication, cleaning,
torquing, function testing and ground inspection.
4.2 Program Schedule Currently, SCADA devices are being inspected on an annual basis and
the SCADA controlled equipment has an operational test every 3 years.
The program does not have a predetermined budget (see Table 4.1).
4.3 Program Performance Indicators In 2013, HOL did not meet the target numbers due to lack of
available resources (see Table 4.2).
4.4 Data Governance The inspection records are currently being stored in an Access
database containing the information found in Table 4.3 and can be viewed using Intergraph GeoMedia
software or Microsoft Excel.
TABLE 4.3 – SCADA INSPECTION STORED INFORMATION
Device Type Pole Resistance Drawings "As Built"
Cabinet Nomenclature Verified Radio / RTU Lights Cabinet Condition
Pole Nomenclature Verified Antenna Appearance Cabinet Comment
By-Pass Switch Nomenclature Lightning Arrestors Additional Cabinet Comment
Nomenclature Remarks RSSI Signal (in dB) Check SF6 Gas Alarm Indicator
RTU Type All Locks in Place Check Air Break Position Sensor
Firmware Versions Heater and Fan Verified Fault Indicators
Config Saved Thermostat set at 5°C Date of Inspection
Cabinets Properly Grounded Infrared on All Electronics Battery Voltage (V)
Pole Properly Grounded Drawings in Cabinet Battery Date Installed
4.5 Reactive Maintenance If during the inspection the equipment cannot be repaired immediately an OMS ticket is created for HOL
crews to perform follow-up action.
4.6 Gap Analysis A defined budget and inspection cycle should be created. The inspection data needs to be analyzed in greater
depth. IR inspections could be completed on the switches at the time of SCADA maintenance to check for
overheating.
TABLE 4.2 –SCADA INSPECTIONS
Inspection
Target
Inspections
Actuals
135 40
TABLE 4.1 –SCADA BUDGET
2013 Budget 2013 Budget
Actuals
0 $68,422
201
4 T
esti
ng,
Insp
ecti
on
& M
ain
ten
ance
Pla
n
52