Cell Tower Process - New Cell Tower
TELCO CompanyIndicates interest ininstalling monopole
Determine fromSchool Principal ifthere is interest in
monopoleinstallation
Arrange meeting Yeswith cell tower reps
and principal(principal's
discretion whetherto invite PTArepresentative)
If principal is stillinterested, directTELCO reps to
prepareschematicdrawings
If Right of Entry isrequired for testing,prepare ROE (usingROE template) forexecution by DFMdirector. RequireTELCO to prepare
exhibit
REM reviewsschematic
drawings withDOC.
Do future plans/site constraintsprohibit tower
Principalschedules anii:lforrnationalmeetinglat aregular PTAmeeting andinvites thecommunity
Will the processrequire a Special
Exception?>----------No [proceed t
Yes
TELCO cowill make TELCO Co must thenapplication to the prepare information for
Tower Committee. If Special Exceptionproject is approved, it process.will be conditioned on MCPSwill have to be aSpecial Exception co-applicant on the SE
approval. application.
Cities of Rockville and Gaithersburg have their own review process
NoNotify TELCO
Company that thereis no interest
I' 'Final signature is by theSuperintendent, once
everything is acceptable.Usually we get five originaldocuments, two for MCPS,three for TELCO provider.-,
TELCO must provide Leaseexhibits, acceptable suretybond or security deposit,
acceptable radio frequency(RF) and structural reports.
.
Prepare Lease Agreement,using most recent Leasetemplate. Make sureagreement includes
language that should therebe taxes assessed byState, responsibility forpayment is Lessee's.
Once the hearing
o Mandatory ReferralExaminer has prepared arecommendation, TELCOreps then have to prepareinformation for MandatoryReferral before the M-
NCPPC.
Require that when.•..
notifying adjacent andconfronting property
owners, notices must besent registered mail.Check their lists andmake sure they arenotifying appropriateCitizens/Homeowner
Associations
Cell Tower Leasing Process - Steps
Step Description1 The Real Estate Management Team is contacted by a Cellular Service provider to
locate a tower at an MCPSsite. The real estate management team will receive basicinformation from the provider concerning proposed size, location, and specialrequirements. REM staff will direct the provider to the MCPS Policy ECNand explainthe process.
2 REM staff will contact the school principal and present the request. The schoolprincipal will make the decision whether they will permit a tower on the property ornot. If the request is denied, REM staff will contact the provider and inform themthe request is denied. If the principal is interested, REM will contact the provider toobegin the approval process.
3 REM will request the provider provide schematic drawings showing the proposedtower location and associated equipment. REM will review the plan with DOCstaffto determine if there are any conflicts with future expansion plans or current siteissues. If there are conflicts that cannot be resolved, REM staff will notify theprovider and principal the tower is not compatible for the site. If issues can beresolved, the provider will move to the next step.
4 The principal will schedule an informational meeting with the PTA.The principal willensure members of the surrounding community, HOAs, and civic associations areinvited. Should there be substantial opposition; the principal may decline therequest. Should the community be supportive, the provider will begin the formalapproval process with local and County government agencies.
5 The provider will manage the public approval process and notify REM uponcompletion and verify all approvals were received.
6 REM staff will prepare the lease for review by the provider. Following successfullease negotiations, the lease may be forwarded to the MCPS attorney for review.
7 Once lease is finalized and signed by the provider, it will be forwarded to theSuperindent for execution.