Cell Tower Process - New Cell Tower TELCO Company Indicates interest in installing monopole Determine from School Principal if there is interest in monopole installation Arrange meeting Yes with cell tower reps and principal (principal's discretion whether to invite PTA representative) If principal is still interested, direct TELCO reps to prepare schematic drawings If Right of Entry is required for testing, prepare ROE (using ROE template) for execution by DFM director. Require TELCO to prepare exhibit REM reviews schematic drawings with DOC. Do future plans/ site constraints prohibit tower Principal schedules an ii:lforrnational meetinglat a regular PTA meeting and invites the community Will the process require a Special Exception? >----------No [proceedt Yes TELCO co will make TELCO Co must then application to the prepare information for Tower Committee. If Special Exception project is approved, it process. will be conditioned on MCPS will have to be a Special Exception co-applicant on the SE approval. application. Cities of Rockville and Gaithersburg have their own review process No Notify TELCO Company that there is no interest I' ' Final signature is by the Superintendent, once everything is acceptable. Usually we get five original documents, two for MCPS, three for TELCO provider. -, TELCO must provide Lease exhibits, acceptable surety bond or security deposit, acceptable radio frequency (RF) and structural reports. . Prepare Lease Agreement, using most recent Lease template. Make sure agreement includes language that should there be taxes assessed by State, responsibility for payment is Lessee's. Once the hearing o Mandatory Referral Examiner has prepared a recommendation, TELCO reps then have to prepare information for Mandatory Referral before the M- NCPPC. Require that when .•.. notifying adjacent and confronting property owners, notices must be sent registered mail. Check their lists and make sure they are notifying appropriate Citizens/Homeowner Associations

Transcript of 2014 MCPS Cell Tower Process

Page 1: 2014 MCPS Cell Tower Process

Cell Tower Process - New Cell Tower

TELCO CompanyIndicates interest ininstalling monopole

Determine fromSchool Principal ifthere is interest in

monopoleinstallation

Arrange meeting Yeswith cell tower reps

and principal(principal's

discretion whetherto invite PTArepresentative)

If principal is stillinterested, directTELCO reps to

prepareschematicdrawings

If Right of Entry isrequired for testing,prepare ROE (usingROE template) forexecution by DFMdirector. RequireTELCO to prepare

exhibit

REM reviewsschematic

drawings withDOC.

Do future plans/site constraintsprohibit tower

Principalschedules anii:lforrnationalmeetinglat aregular PTAmeeting andinvites thecommunity

Will the processrequire a Special

Exception?>----------No [proceed t

Yes

TELCO cowill make TELCO Co must thenapplication to the prepare information for

Tower Committee. If Special Exceptionproject is approved, it process.will be conditioned on MCPSwill have to be aSpecial Exception co-applicant on the SE

approval. application.

Cities of Rockville and Gaithersburg have their own review process

NoNotify TELCO

Company that thereis no interest

I' 'Final signature is by theSuperintendent, once

everything is acceptable.Usually we get five originaldocuments, two for MCPS,three for TELCO provider.-,

TELCO must provide Leaseexhibits, acceptable suretybond or security deposit,

acceptable radio frequency(RF) and structural reports.

.

Prepare Lease Agreement,using most recent Leasetemplate. Make sureagreement includes

language that should therebe taxes assessed byState, responsibility forpayment is Lessee's.

Once the hearing

o Mandatory ReferralExaminer has prepared arecommendation, TELCOreps then have to prepareinformation for MandatoryReferral before the M-

NCPPC.

Require that when.•..

notifying adjacent andconfronting property

owners, notices must besent registered mail.Check their lists andmake sure they arenotifying appropriateCitizens/Homeowner

Associations

Page 2: 2014 MCPS Cell Tower Process

Cell Tower Leasing Process - Steps

Step Description1 The Real Estate Management Team is contacted by a Cellular Service provider to

locate a tower at an MCPSsite. The real estate management team will receive basicinformation from the provider concerning proposed size, location, and specialrequirements. REM staff will direct the provider to the MCPS Policy ECNand explainthe process.

2 REM staff will contact the school principal and present the request. The schoolprincipal will make the decision whether they will permit a tower on the property ornot. If the request is denied, REM staff will contact the provider and inform themthe request is denied. If the principal is interested, REM will contact the provider toobegin the approval process.

3 REM will request the provider provide schematic drawings showing the proposedtower location and associated equipment. REM will review the plan with DOCstaffto determine if there are any conflicts with future expansion plans or current siteissues. If there are conflicts that cannot be resolved, REM staff will notify theprovider and principal the tower is not compatible for the site. If issues can beresolved, the provider will move to the next step.

4 The principal will schedule an informational meeting with the PTA.The principal willensure members of the surrounding community, HOAs, and civic associations areinvited. Should there be substantial opposition; the principal may decline therequest. Should the community be supportive, the provider will begin the formalapproval process with local and County government agencies.

5 The provider will manage the public approval process and notify REM uponcompletion and verify all approvals were received.

6 REM staff will prepare the lease for review by the provider. Following successfullease negotiations, the lease may be forwarded to the MCPS attorney for review.

7 Once lease is finalized and signed by the provider, it will be forwarded to theSuperindent for execution.