2012_UnitCosts

download 2012_UnitCosts

of 6

Transcript of 2012_UnitCosts

  • 7/28/2019 2012_UnitCosts

    1/6

    Project Name:

    Termini:

    Date:

    Summary

    2010 SUMMARY COST ESTIMATES (Current Dollars)

    COST CATEGORIES Factors No Build Alternative 1 Alternative 2

    Construction -$ -$ -$

    Design (10% TO 15%) 12% -$ -$ -$

    Construction Management 15% -$ -$ -$

    Right-of-Way -$ -$ -$

    Structures -$ -$ -$

    Utility Relocation -$ -$ -$

    Administration (8% TO 13%) 10% -$ -$ -$

    Total -$ -$ -$

    PRELIMINARY SUMMARY COST ESTIMATES (Adjusted for Inflation)

    Assumed Annual Inflation Rate = 3.50%Assumed Number of Years = 5

    $ $ $

  • 7/28/2019 2012_UnitCosts

    2/6

    Adj t d C t ti C t $ $ $

    Project Name:Termini:Date:

    Road Construction

    Alternative:

    Item Description Unit Quantity Unit Cost Total

    N.P.D.E.S. Lump Sum 20,972.99$ -$

    Community Relations Allowance 9,190.11$ -$

    Engineer's Field Office Lump Sum 61,730.38$ -$

    Roadway Excavation C YD 4.81$ -$ Gr

    Borrow Excavation (if anticipated) C YD 8.37$ -$ Gr

    Channel & Retention Basin Excavation C YD 11.31$ -$ Inc

    Subgrade Preparation SQ YD 2.02$ -$

    New Asphalt Concrete Pavement (see Pavement sheet) SQ YD 15.00$ -$ Inc

    New Rubberized Asphalt Pavement (see Pavement sheet) SQ YD 23.60$ -$

    Asphalt Rubber Overlay (see Pavement sheet) SQ YD 8.80$ -$ Inc

    Chip Seal on AC Pavement (see Pavement sheet) SQ YD 3.10$ -$ Inc

    Double Chip Seal on Aggregate Base (see Pavement sheet) SQ YD 5.90$ -$ Inc

    Concrete Single Curb LF 8.76$ -$ Inc

    Concrete Curb & Gutter LF 11.16$ -$ Inc

    Concrete Sidewalk Ramp Std Det 231, Type "A" EA 1,387.38$ -$

    Concrete Sidewalk Std Det 230 SQ YD 28.85$ -$ Ty

    Concrete Driveway with 5' Wings, Std Det 250 SQ YD 39.25$ -$

    Traffic Signing & Striping - 2 lanes LF 1.06$ -$

    Traffic Signing & Striping - 5 lanes LF 2.28$ -$

    Traffic Signing & Striping - 7 lanes LF 4.85$ -$

    Traffic Signal, Full Intersection EA 361,788.98$ -$

    Interconnect/Traffic Signals LF 9.47$ -$Traffic Signal, Future "Box-in" EA 6,049.59$ -$

    Catch Basin EA 8,854.81$ -$

    Scupper EA 1,514.51$ -$

  • 7/28/2019 2012_UnitCosts

    3/6

    Pro ject Name:Termini:Date:

    Pavement*Note: Quantities will be automatically calculated when section widths are entered in "Used" column.Unit Cost Derivation for Arterial Section Shown: Actual (mm) Actual (in) Used (in)

    1 Aggregate Base Thickness 250 9.843 6 SeeAsphalt Rubber Concrete Thickness 37 1.457 2 Computations

    Asphalt Concrete Thickness 63 2.480 2 Below

    Item Description Unit Quantity Unit Cost Total

    Aggregate Base* Ton 0.3150 16.30$ 5.14$Bituminous Prime Coat (0.4 gal per SY)* Ton 0.0010 1,329.09$ 1.28$Tack Coat SY 1 0.26$ 0.26$Asphalt Rubber Concrete* Ton 0.1095 77.76$ 8.51$Asphalt Concrete* Ton 0.1095 76.46$ 8.37$Rubberized Pavement cost per SY 23.56$Rubberized Pavement cost per SQ M 28.17$

    Rounded unit cost per SQ YD for Rubberized Asphalt Pavement Total 23.60$

    Unit Cost Derivation for Arterial Section Shown: Actual (mm) Actual (in) Used (in) See2 Aggregate Base Thickness 250 9.843 6 Computations

    Asphalt Concrete Thickness 100 3.937 2 Below

    Item Description Unit Quantity Unit Cost Total

    Aggregate Base Ton 0.3150 16.30$ 5.14$Bituminous Prime Coat (0.4 gal per SY) Ton 0.0010 1,329.09$ 1.28$Tack Coat SY 1 0.26$ 0.26$Asphalt Concrete Ton 0.10935 76.46$ 8.36$Pavement cost per SY 15.04$Pavement cost per SQ M 17.98$

    Rounded unit cost per SQ YD for Asphalt Concrete Pavement Total 15.00$

    Unit Cost Derivation for Asphalt Rubber Overlay: Actual (mm) Actual (in) Used (in) See3 Asphalt Rubber Concrete Thickness 50 1.969 2 Computations

    Below

    Item Description Unit Quantity Unit Cost Total

    Tack Coat SY 1 0.26$ 0.26$Asphalt Rubber Concrete Ton 0.1095 77.76$ 8.51$

    50 mm Asphalt Rubber Overlay per SY 8.78$50 mm Asphalt Rubber Overlay per SQ M 10.50$

    Rounded unit cost per SQ YD for 50 mm Asphalt Rubber Overlay Total 8.80$

  • 7/28/2019 2012_UnitCosts

    4/6

    Project Name:

    Termini:

    Date:

    Structures

    BOX CULVERT COST CALCULATIONS

    TYPE OF ROAD BOX LENGTH (ft) BOX DESCRIPTION BOX WIDTH (ft) TOP SFC AREA* UNIT

    URBAN MINOR ARTERIAL OR LESS 0 0 0 SQ FT $

    (27 m or 88.58' for 5 lanes & 2 sidewalks)

    URBAN MINOR ARTERIAL W/ BIKE LANES 0 0 0 SQ FT $

    (28.8 m or 94.49' for 5 lanes, 2 B/L's & 2 S/W's)

    URBAN MAJOR ARTERIAL 0 0 0 SQ FT $ (31.8 m or 104.33' for 7 lanes & 2 S/W's)

    SPECIAL LOW VOLUME ROAD CONDITION*** 0 0 0 SQ FT(16 m or 52.49' for 2 lanes with shoulders)

    * Top surface area of box.

    ** Includes cost of standard wing walls and bridge barrier. For special construction review unit cost with MCDOT bridge section.*** 16 m box with approval only. Generally a non-section line, low volume location.

    Cost in Red is based on bridges constructed from 2005-2008 as there was not any new data available for FY 2010

    BRIDGE COST CALCULATIONS

    TYPE OF ROAD BRIDGE LENGTH (ft) DESCRIPTION BRIDGE WIDTH (ft) TOP SFC AREA* UNIT

    URBAN MINOR ARTERIAL OR LESS 0 0 0 SQ FT $

    (27 m or 88.58' for 5 lanes & 2 sidewalks )

    URBAN MINOR ARTERIAL W/ BIKE LANES 0 0 0 SQ FT $(28.8 m or 94.49' for 5 lanes, 2 B/L's & 2 S/W's)

    URBAN MAJOR ARTERIAL 0 0 0 SQ FT $(31.8 m or 104.33' for 7 lanes & 2 S/W's)

    SPECIAL LOW VOLUME ROAD CONDITION*** 0 0 0 SQ FT $(16 m or 52 49' for 2 lanes with shoulders)

  • 7/28/2019 2012_UnitCosts

    5/6

  • 7/28/2019 2012_UnitCosts

    6/6

    Project Name:

    Termini:

    Date:

    SRP Irrigation

    Alternat ive:

    Item Descrip t ion Unit Quanti ty Un it Cost Total

    Mobilization LS 10,455.62$

    Clearing, Grubbing and Site Clean Up EA 10,455.62$

    Irrigation Structure w/ Gates, Medium EA 61,804.80$

    Irrigation Structure w/ Gates, Large EA 112,953.60$

    24" RGRCP LF 58.55$

    30" & 36" RGRCP LF 88.84$

    42" & 48" RGRCP LF 183.28$

    54" & 60" RGRCP LF 231.08$

    Headwall w/ Trash Rack EA 12,574.08$

    Headwall EA 8,737.92$

    Manhole EA 6,180.48$

    Remove Existing Structures LS 26,853.12$

    Concrete Lined Ditch LF 92.71$

    Subtotal Construction

    Irrigation System Design 10%

    Total SRP Relocation Estimate

    *Note: Engl ish uni ts used per SRP standards

    6/29/2013