2012_UnitCosts
-
Upload
venkatarathnam-pulipati -
Category
Documents
-
view
214 -
download
0
Transcript of 2012_UnitCosts
-
7/28/2019 2012_UnitCosts
1/6
Project Name:
Termini:
Date:
Summary
2010 SUMMARY COST ESTIMATES (Current Dollars)
COST CATEGORIES Factors No Build Alternative 1 Alternative 2
Construction -$ -$ -$
Design (10% TO 15%) 12% -$ -$ -$
Construction Management 15% -$ -$ -$
Right-of-Way -$ -$ -$
Structures -$ -$ -$
Utility Relocation -$ -$ -$
Administration (8% TO 13%) 10% -$ -$ -$
Total -$ -$ -$
PRELIMINARY SUMMARY COST ESTIMATES (Adjusted for Inflation)
Assumed Annual Inflation Rate = 3.50%Assumed Number of Years = 5
$ $ $
-
7/28/2019 2012_UnitCosts
2/6
Adj t d C t ti C t $ $ $
Project Name:Termini:Date:
Road Construction
Alternative:
Item Description Unit Quantity Unit Cost Total
N.P.D.E.S. Lump Sum 20,972.99$ -$
Community Relations Allowance 9,190.11$ -$
Engineer's Field Office Lump Sum 61,730.38$ -$
Roadway Excavation C YD 4.81$ -$ Gr
Borrow Excavation (if anticipated) C YD 8.37$ -$ Gr
Channel & Retention Basin Excavation C YD 11.31$ -$ Inc
Subgrade Preparation SQ YD 2.02$ -$
New Asphalt Concrete Pavement (see Pavement sheet) SQ YD 15.00$ -$ Inc
New Rubberized Asphalt Pavement (see Pavement sheet) SQ YD 23.60$ -$
Asphalt Rubber Overlay (see Pavement sheet) SQ YD 8.80$ -$ Inc
Chip Seal on AC Pavement (see Pavement sheet) SQ YD 3.10$ -$ Inc
Double Chip Seal on Aggregate Base (see Pavement sheet) SQ YD 5.90$ -$ Inc
Concrete Single Curb LF 8.76$ -$ Inc
Concrete Curb & Gutter LF 11.16$ -$ Inc
Concrete Sidewalk Ramp Std Det 231, Type "A" EA 1,387.38$ -$
Concrete Sidewalk Std Det 230 SQ YD 28.85$ -$ Ty
Concrete Driveway with 5' Wings, Std Det 250 SQ YD 39.25$ -$
Traffic Signing & Striping - 2 lanes LF 1.06$ -$
Traffic Signing & Striping - 5 lanes LF 2.28$ -$
Traffic Signing & Striping - 7 lanes LF 4.85$ -$
Traffic Signal, Full Intersection EA 361,788.98$ -$
Interconnect/Traffic Signals LF 9.47$ -$Traffic Signal, Future "Box-in" EA 6,049.59$ -$
Catch Basin EA 8,854.81$ -$
Scupper EA 1,514.51$ -$
-
7/28/2019 2012_UnitCosts
3/6
Pro ject Name:Termini:Date:
Pavement*Note: Quantities will be automatically calculated when section widths are entered in "Used" column.Unit Cost Derivation for Arterial Section Shown: Actual (mm) Actual (in) Used (in)
1 Aggregate Base Thickness 250 9.843 6 SeeAsphalt Rubber Concrete Thickness 37 1.457 2 Computations
Asphalt Concrete Thickness 63 2.480 2 Below
Item Description Unit Quantity Unit Cost Total
Aggregate Base* Ton 0.3150 16.30$ 5.14$Bituminous Prime Coat (0.4 gal per SY)* Ton 0.0010 1,329.09$ 1.28$Tack Coat SY 1 0.26$ 0.26$Asphalt Rubber Concrete* Ton 0.1095 77.76$ 8.51$Asphalt Concrete* Ton 0.1095 76.46$ 8.37$Rubberized Pavement cost per SY 23.56$Rubberized Pavement cost per SQ M 28.17$
Rounded unit cost per SQ YD for Rubberized Asphalt Pavement Total 23.60$
Unit Cost Derivation for Arterial Section Shown: Actual (mm) Actual (in) Used (in) See2 Aggregate Base Thickness 250 9.843 6 Computations
Asphalt Concrete Thickness 100 3.937 2 Below
Item Description Unit Quantity Unit Cost Total
Aggregate Base Ton 0.3150 16.30$ 5.14$Bituminous Prime Coat (0.4 gal per SY) Ton 0.0010 1,329.09$ 1.28$Tack Coat SY 1 0.26$ 0.26$Asphalt Concrete Ton 0.10935 76.46$ 8.36$Pavement cost per SY 15.04$Pavement cost per SQ M 17.98$
Rounded unit cost per SQ YD for Asphalt Concrete Pavement Total 15.00$
Unit Cost Derivation for Asphalt Rubber Overlay: Actual (mm) Actual (in) Used (in) See3 Asphalt Rubber Concrete Thickness 50 1.969 2 Computations
Below
Item Description Unit Quantity Unit Cost Total
Tack Coat SY 1 0.26$ 0.26$Asphalt Rubber Concrete Ton 0.1095 77.76$ 8.51$
50 mm Asphalt Rubber Overlay per SY 8.78$50 mm Asphalt Rubber Overlay per SQ M 10.50$
Rounded unit cost per SQ YD for 50 mm Asphalt Rubber Overlay Total 8.80$
-
7/28/2019 2012_UnitCosts
4/6
Project Name:
Termini:
Date:
Structures
BOX CULVERT COST CALCULATIONS
TYPE OF ROAD BOX LENGTH (ft) BOX DESCRIPTION BOX WIDTH (ft) TOP SFC AREA* UNIT
URBAN MINOR ARTERIAL OR LESS 0 0 0 SQ FT $
(27 m or 88.58' for 5 lanes & 2 sidewalks)
URBAN MINOR ARTERIAL W/ BIKE LANES 0 0 0 SQ FT $
(28.8 m or 94.49' for 5 lanes, 2 B/L's & 2 S/W's)
URBAN MAJOR ARTERIAL 0 0 0 SQ FT $ (31.8 m or 104.33' for 7 lanes & 2 S/W's)
SPECIAL LOW VOLUME ROAD CONDITION*** 0 0 0 SQ FT(16 m or 52.49' for 2 lanes with shoulders)
* Top surface area of box.
** Includes cost of standard wing walls and bridge barrier. For special construction review unit cost with MCDOT bridge section.*** 16 m box with approval only. Generally a non-section line, low volume location.
Cost in Red is based on bridges constructed from 2005-2008 as there was not any new data available for FY 2010
BRIDGE COST CALCULATIONS
TYPE OF ROAD BRIDGE LENGTH (ft) DESCRIPTION BRIDGE WIDTH (ft) TOP SFC AREA* UNIT
URBAN MINOR ARTERIAL OR LESS 0 0 0 SQ FT $
(27 m or 88.58' for 5 lanes & 2 sidewalks )
URBAN MINOR ARTERIAL W/ BIKE LANES 0 0 0 SQ FT $(28.8 m or 94.49' for 5 lanes, 2 B/L's & 2 S/W's)
URBAN MAJOR ARTERIAL 0 0 0 SQ FT $(31.8 m or 104.33' for 7 lanes & 2 S/W's)
SPECIAL LOW VOLUME ROAD CONDITION*** 0 0 0 SQ FT $(16 m or 52 49' for 2 lanes with shoulders)
-
7/28/2019 2012_UnitCosts
5/6
-
7/28/2019 2012_UnitCosts
6/6
Project Name:
Termini:
Date:
SRP Irrigation
Alternat ive:
Item Descrip t ion Unit Quanti ty Un it Cost Total
Mobilization LS 10,455.62$
Clearing, Grubbing and Site Clean Up EA 10,455.62$
Irrigation Structure w/ Gates, Medium EA 61,804.80$
Irrigation Structure w/ Gates, Large EA 112,953.60$
24" RGRCP LF 58.55$
30" & 36" RGRCP LF 88.84$
42" & 48" RGRCP LF 183.28$
54" & 60" RGRCP LF 231.08$
Headwall w/ Trash Rack EA 12,574.08$
Headwall EA 8,737.92$
Manhole EA 6,180.48$
Remove Existing Structures LS 26,853.12$
Concrete Lined Ditch LF 92.71$
Subtotal Construction
Irrigation System Design 10%
Total SRP Relocation Estimate
*Note: Engl ish uni ts used per SRP standards
6/29/2013