20120726 Briefing on BAKUN HEP (Technical)

76
Project Background Progress of Works Reservoir Impoundment Power Generation Other Benefits IET MALAYSIA IET MALAYSIA IET MALAYSIA IET MALAYSIA – PRESENTATION ON BAKUN HEP PRESENTATION ON BAKUN HEP PRESENTATION ON BAKUN HEP PRESENTATION ON BAKUN HEP 13 April 2013 13 April 2013 13 April 2013 13 April 2013 Nanthagopi Velaairam

description

hydro

Transcript of 20120726 Briefing on BAKUN HEP (Technical)

Page 1: 20120726 Briefing on BAKUN HEP (Technical)

� Project Background

� Progress of Works

� Reservoir Impoundment

� Power Generation

� Other Benefits

IET MALAYSIA IET MALAYSIA IET MALAYSIA IET MALAYSIA ––––PRESENTATION ON BAKUN HEPPRESENTATION ON BAKUN HEPPRESENTATION ON BAKUN HEPPRESENTATION ON BAKUN HEP

13 April 2013 13 April 2013 13 April 2013 13 April 2013 Nanthagopi Velaairam

Page 2: 20120726 Briefing on BAKUN HEP (Technical)

Distance : Bakun to Bintulu ~ 180 km Bakun to Miri ~ 3Distance : Bakun to Bintulu ~ 180 km Bakun to Miri ~ 3Distance : Bakun to Bintulu ~ 180 km Bakun to Miri ~ 3Distance : Bakun to Bintulu ~ 180 km Bakun to Miri ~ 300 km 00 km 00 km 00 km Bakun to Sibu ~ 390 km Bakun to Kuching ~ Bakun to Sibu ~ 390 km Bakun to Kuching ~ Bakun to Sibu ~ 390 km Bakun to Kuching ~ Bakun to Sibu ~ 390 km Bakun to Kuching ~ 900 km900 km900 km900 km

Bakun HEPBakun HEPBakun HEPBakun HEPLocated on the Btg. Balui Located on the Btg. Balui Located on the Btg. Balui Located on the Btg. Balui in the upper Rajang Basinin the upper Rajang Basinin the upper Rajang Basinin the upper Rajang Basin

PROJECT LOCATION

Bakun CatchmentBakun CatchmentBakun CatchmentBakun Catchment

Page 3: 20120726 Briefing on BAKUN HEP (Technical)

PROJECT LAYOUT

Spillway

Power IntakeMain Dam

Powerhouse

Switchyard

Plunge Pool

Sg Murum Btg Balui

Page 4: 20120726 Briefing on BAKUN HEP (Technical)

Dam type Concrete Faced Rockfill Dam

Max. Height above Foundation 205 m

Base Length (U/S to D/S) 580m

Crest Length 750 m

Crest Elevation EL 236.5 m

Max. Flood Level EL 234 m

Max. Operating Level EL 228.0 m(Reached on 9 March 2012)

Min. Operating Level EL195.0 m (Reached in April 2011)

Catchment Area 14,750 km2

Reservoir Area at EL 228 asl 695 km2

PROJECT MAIN FEATURES

Page 5: 20120726 Briefing on BAKUN HEP (Technical)

233 mm

205 mmShuibuya

China

Bakun Malaysia

202 mm

196 m196 m

Karahjukar

Iceland

187m187m

Aquamilpa Mexico

Campos

Novos Brazil

CFRD DAMS IN THE WORLD

Page 6: 20120726 Briefing on BAKUN HEP (Technical)

BATANG AIR (9,000 ha)

�BAKUN (69,500 ha)BAKUN (69,500 ha)BAKUN (69,500 ha)BAKUN (69,500 ha)

�KENYIR (39,600 ha)KENYIR (39,600 ha)KENYIR (39,600 ha)KENYIR (39,600 ha)

�MURUMMURUMMURUMMURUM (24,500 ha)

TEMENGGORTEMENGGORTEMENGGORTEMENGGOR (15,200 ha)

RESERVOIRS IN MALAYSIA

PERGAU

Page 7: 20120726 Briefing on BAKUN HEP (Technical)

� The Project

� Progress of Works

� Reservoir Impoundment & Release

� Power Generation

� Other Benefits

THE PRESENTATION

Page 8: 20120726 Briefing on BAKUN HEP (Technical)

PROJECT PROGRESS

PackagePackagePackagePackage ProgressProgressProgressProgress

MAIN CIVIL WORKS (MCHJV) Completed

ELECTRO - MECHANICAL I (ALSTOM) Completed

ELECTRO - MECHANICAL II (IMPSA) 95.0%

SWITCHYARD (MRCB) Completed

Page 9: 20120726 Briefing on BAKUN HEP (Technical)

ELECTRO-

MECHANICAL

BEM1-C (IMPSA)

95%

ELECTRO-

MECHANICAL

ALSTOM

COMPLETED

BAKUN

HYDROELECTRIC

PROJECT

MAIN CIVIL WORKS

MCHJV

COMPLETED

RIVER DIVERSION

DONG AH (KOREA)

COMPLETED

PROJECT WORK PACKAGES

COFFERDAM

GUSB (MALAYSIA)

COMPLETED

SWITCHYARD

MRCB

COMPLETED

BIOMASS REMOVAL

WARGANA CONSORTIUM

COMPLETED

Page 10: 20120726 Briefing on BAKUN HEP (Technical)

� Constructed by Dong Ah, Korea from 1996 – 2001.

DIVERSION INLET

Page 11: 20120726 Briefing on BAKUN HEP (Technical)

� 3 tunnels of 12 m diameter with average length of 1.5 km.

� Currently all 3 tunnels are plugged.

DIVERSION TUNNELS

Page 12: 20120726 Briefing on BAKUN HEP (Technical)

� Total discharge capacity = 7,260 m3/s.

DIVERSION OUTLET

Page 13: 20120726 Briefing on BAKUN HEP (Technical)

DAM SITE CLEARING (2003)� Commencement in April 2003 under Malaysia – China Hydro JV.

Page 14: 20120726 Briefing on BAKUN HEP (Technical)

Feb 2006Nov 2005

Page 15: 20120726 Briefing on BAKUN HEP (Technical)

Aug 2007March 2006

Page 16: 20120726 Briefing on BAKUN HEP (Technical)

July 2008 Aug 2009

Page 17: 20120726 Briefing on BAKUN HEP (Technical)

17Aug’07

Jan’05 Feb’06

Oct’09

Page 18: 20120726 Briefing on BAKUN HEP (Technical)

July 2008 Aug 2009

Page 19: 20120726 Briefing on BAKUN HEP (Technical)

MAIN DAM

� Completed in 2009.

Upstream View Downstream View

Page 20: 20120726 Briefing on BAKUN HEP (Technical)

MAIN DAM - SIDE VIEW (8 June 2009)

Page 21: 20120726 Briefing on BAKUN HEP (Technical)

Intake

Powerhouse

Concrete Lined

Steel Lined

INTAKE, POWER TUNNEL & POWERHOUSE

Page 22: 20120726 Briefing on BAKUN HEP (Technical)

Oct 2005 May 2006

July 2008

Feb 2009

Building Height = 65m,

Width = 58m, Length = 171m.

POWER INTAKE STRUCTURE

Page 23: 20120726 Briefing on BAKUN HEP (Technical)

POWER INTAKE STRUCTURE

02 Feb 2012

Page 24: 20120726 Briefing on BAKUN HEP (Technical)

POWER INTAKE – LOG BOOM�Blocking floating logs and debris.

Page 25: 20120726 Briefing on BAKUN HEP (Technical)

POWER INTAKE – FLOW TRAINING LOG

� Allow withdrawal of top 10 to 15m good quality surface water.

Page 26: 20120726 Briefing on BAKUN HEP (Technical)

� Blocking finer floating debris.

POWER INTAKE - TRASHRACK

Page 27: 20120726 Briefing on BAKUN HEP (Technical)

Aug 2007Oct 2006

8.5m

� Concrete lined section.� Discharge capacity = 208m3/s.

POWER TUNNEL – LOW PRESSURE SECTION

Page 28: 20120726 Briefing on BAKUN HEP (Technical)

Dec 2006Oct 2006

� Concrete lined section.� Vertical drop from upper elbow to lower elbow = 90m.

POWER TUNNEL - VERTICAL SHAFT

Page 29: 20120726 Briefing on BAKUN HEP (Technical)

� Diameter of Tunnel = 7.0 m.

POWER TUNNEL – STEEL LINED HIGH PRESSURESECTION

Page 30: 20120726 Briefing on BAKUN HEP (Technical)

� Diameter of Penstock = 4.85m.

POWER TUNNEL – PENSTOCK TO P/HOUSE

Page 31: 20120726 Briefing on BAKUN HEP (Technical)

SPIRAL CASE

Page 32: 20120726 Briefing on BAKUN HEP (Technical)

POWERHOUSE – SIDE VIEW

Page 33: 20120726 Briefing on BAKUN HEP (Technical)

Draft Tube Gate

Tailrace Channel

POWERHOUSE – D/S VIEW� Building Height = 71m, Width = 48m, Length = 250m.

Page 34: 20120726 Briefing on BAKUN HEP (Technical)

Unit 8

Unit 1

Last 2 Rotors

Unit 8

Unit 7

CURRENT POWERHOUSE INTERNAL VIEW

Page 35: 20120726 Briefing on BAKUN HEP (Technical)

Draft Tube

Concreting

Stay Ring

Spiral Case

Concreting

Bottom Ring

Vanes

Runner

Distributor

Shaft

Stator + Winding

Rotor

Bus Duct

Cooling Water Floor

Turbine Floor

Control Room Floor

VAC Floor

Transformer

Generator Floor

TURBINE ERECTION SEQUENCE

Page 36: 20120726 Briefing on BAKUN HEP (Technical)

Stay Ring Spiral Case (Dilatation piece diameter = 4.85m)

TURBINE & GENERATOR INSTALLATION

Pit Liner Enclosure Concreting

Page 37: 20120726 Briefing on BAKUN HEP (Technical)

Turbine Runner (5.125m diameter;Francis – no inlet valve)

Guide Vanes (24 x 1.108m H)

TURBINE & GENERATOR INSTALLATION

Distributor Head Lower Shaft

Page 38: 20120726 Briefing on BAKUN HEP (Technical)

Rotor (Nominal power=306MW, Nominal speed = 166.7 rpm)

Stator

TURBINE & GENERATOR INSTALLATION

Upper BracketGenerator Cover

Page 39: 20120726 Briefing on BAKUN HEP (Technical)

EM1 (ALSTOM) STATUS

� All 4 turbine units completed and in commercial operation.

Unit 5

Unit 8

Page 40: 20120726 Briefing on BAKUN HEP (Technical)

EM2 (IMPSA) STATUS

� Unit 4Unit generally complete

� Unit 3Stator/rotor completeTurbine generally complete

� Unit 2Stator completeRotor in progress

� Unit 1Stator / Rotor in progress

� Common ServicesElectrical services subcontract awarded

� Tentative COD Unit 4 Aug 2013Unit 3 Oct 2013Unit 2 Dec 2013Unit 1 Jan 2014

Unit 4

Unit 1

Page 41: 20120726 Briefing on BAKUN HEP (Technical)

41

SPILLWAY – KEY DATA

Design DischargesDesign Flood 15,000 m3/s

1 in 10,000 year flood 13, 303 m3/s

Weir

Spillway weir crest elevation EL 209 m

Number of radial gates 4

Width of gates 15 m

Height of gates 21 m

Chutes

Width of chutes 2 x 25 m

Maximum water velocity 44 m/s

Number of aerators 4

Flip Buckets

Flip bucket radius 40 m

Estimated sweepout discharge 640 m3/s

Maximum jet throw 245 m

Plunge PoolExcavated plunge pool floor elevation EL 50 m

Estimated maximum scour depth 30m

Page 42: 20120726 Briefing on BAKUN HEP (Technical)

SPILLWAY - RADIAL GATE

Page 43: 20120726 Briefing on BAKUN HEP (Technical)

SPILLWAY – U/S VIEW

� Spillway Crest Level is EL 209m, current water level at EL 225.8m.

EL 209m

Page 44: 20120726 Briefing on BAKUN HEP (Technical)

� Chute Length = 660m; Chute Width = 2 x 25m� Designed Flood Discharge = 15.000 m3/s� First spillway testing conducted on 4 Oct 2011.

SPILLWAY – D/S VIEW

Page 45: 20120726 Briefing on BAKUN HEP (Technical)

HYDROLOGICAL & SEISMIC STATIONS

Page 46: 20120726 Briefing on BAKUN HEP (Technical)

HYDROLOGICAL & SEISMIC STATIONS

Page 47: 20120726 Briefing on BAKUN HEP (Technical)

SHORELINE BIOMASS REMOVAL

EL228m

EL180m

Page 48: 20120726 Briefing on BAKUN HEP (Technical)

� Animal Rescue Team of Sarawak Forestry Corporation commenced rescue operation on 21st Oct 2010.

WILDLIFE MONITORING & RESCUE

Page 49: 20120726 Briefing on BAKUN HEP (Technical)

� A total of 1,552 animals (48 mammal spp., 22 reptile spp. and 15 bird spp) were rescued and released at mainland (outside flooded zone).

Western Tarsier

Crested Fireback

Banded Palm Civet

Slow Loris

Porcupine

Langur

WILDLIFE RESCUE

Page 50: 20120726 Briefing on BAKUN HEP (Technical)

Class Total

number of

individuals

rescued

Total

number

of

species

Number of species classified

according to WPO 1998

TOTALLY

PROTECTED

PROTECTED TRADE

BAN

NON

PROTECTED

Mammals 1419 48 6 24 6 12

Birds 47 15 2 4 9

Reptiles 86 22 7 15

TOTAL 1552 85 8 35 6 36

DETAILS OF WILDLIFE RESCUED

Page 51: 20120726 Briefing on BAKUN HEP (Technical)

PLANT RESCUE – NURSERY

� More than 34,900 seedlings of tree species & 1,221 non-trees (orchids, gingers, aroids) raised in nursery.

Page 52: 20120726 Briefing on BAKUN HEP (Technical)

REPLANTING� A total of 33,715 seedlings were replanted along the reservoir shoreline of permanent islands and mainland.

Page 53: 20120726 Briefing on BAKUN HEP (Technical)

Num Species (Scientific name) Total number of seedlings

1 Ensurai (Dipterocarpus oblongifolius) 12,467

2 Tegelam/Engkabang terendak (Shorea

seminis) 3,154

3 Meranti putih (Shorea sp.) 1,104

4 Rengas pitoh (Swintonia sp.) 1,993

5 Meranti merah kesumba (Shorea rubra) 5,554

6 Resak (Vatica sp.) 207

7 Meranti sarang punai (Shorea parvifolia) 60

8 Engkabang jantong (Shorea macrophylla) 68

9 Binatoh (Shorea argentifolia) 5,679

10 urat mata (Parashorea sp.) 878

11 Luis (Hopea sp.) 2,551

12 Engkabang pinang licin (Shorea amplexicaulis) Dead (20)

13 Ubah (Syzygium sp.) Dead (16)

Grand TotalGrand TotalGrand TotalGrand Total 33,71533,71533,71533,715

DETAILS OF PLANT SPECIES REPLANTED

Page 54: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR CLEANING: REMOVAL OF FLOATING LOGS & DEBRIS

� Contract awarded to a local consortium on 28 Dec 2010 (2+1 yrs contract).� Reservoir cleaning commenced on 28 April 2011.

Page 55: 20120726 Briefing on BAKUN HEP (Technical)

� The Project & Company

� Progress of Works

� Reservoir Impoundment & Release

� Power Generation

� Other Benefits

THE PRESENTATION

Page 56: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR IMPOUNDMENT

13th Mar2012 – EL 228.7m13th October 2010 – EL 56m(Day of Impoundment)

� Reservoir area = 695km2 (largest lake in M’sia)� Reservoir reached full supply level of EL 228m on 9 March 2012.

� Impoundment commenced on 13th Oct 2010.

Page 57: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR IMPOUNDMENT (Cont…)� Reservoir @ EL 201.7m as of 25th May 2011

Page 58: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR IMPOUNDMENT (Cont…)

� Reservoir level reached EL 208.6m on 5 August 2011.

Page 59: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR IMPOUNDMENT - THEN & NOW

�Reservoir level reached EL 228m on 9 March 2012.

Page 60: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR RELEASE� Continuous release of around 550 cumecs to enable passenger boatnavigation in between Kapit-Belaga-Bakun commenced on 11Nov2011.

Page 61: 20120726 Briefing on BAKUN HEP (Technical)

RESERVOIR LOWERING

� Lowering of reservoir level started on 12.03.2012.� Maximum release of 2,800 m3/s.� Currently reservoir level at EL 225.8m.

Page 62: 20120726 Briefing on BAKUN HEP (Technical)

� The Project

� Progress of Works

� Reservoir Impoundment & Release

� Power Generation

� Other Benefits

THE PRESENTATION

Page 63: 20120726 Briefing on BAKUN HEP (Technical)

63

BAKUN SWITCHYARD (275KV)

� First Commissioning of Line Similajau 1 & Switchyard Diameter 5 on 13th April 2011.

Page 64: 20120726 Briefing on BAKUN HEP (Technical)

COMMERCIAL GENERATION

UNIT NO COD DATE

Unit 8 6 August 2011

Unit 7 2 October 2011

Unit 5 18 December 2011

Unit 6 23 March 2012

Page 65: 20120726 Briefing on BAKUN HEP (Technical)

TRANSMISSION ROUTE

Bintulu

Miri

Mambong

Matang

EngkililiBatang Ai

Kemantan

Kanowit

Mulu NP

EXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRID

275kV Tee275kV Tee275kV Tee275kV Tee----off Bintuluoff Bintuluoff Bintuluoff Bintulu----Miri to Similajau Miri to Similajau Miri to Similajau Miri to Similajau SubstationSubstationSubstationSubstation

TWO 275kV Double Circuit TWO 275kV Double Circuit TWO 275kV Double Circuit TWO 275kV Double Circuit Transmission Lines Transmission Lines Transmission Lines Transmission Lines

to Similajau Substationto Similajau Substationto Similajau Substationto Similajau Substation

BAKUN HEPBAKUN HEPBAKUN HEPBAKUN HEP

SIMILAJAU SIMILAJAU SIMILAJAU SIMILAJAU SUBSTATIONSUBSTATIONSUBSTATIONSUBSTATION

EXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRIDEXISTING 275kV SESCO GRID

Page 66: 20120726 Briefing on BAKUN HEP (Technical)

Maximum Installed Capacity 2,400 MW

Firm Generating Capacity 1,773* MW

Firm Annual Energy Generation 15,514 GWh

Current SEB’s Demand 550 - 700 MW

* Based on SAMA Report – Our preliminary assessment (2002 to 2010 flow data) shows

higher firm energy @ 1,872 MW.

BAKUN CAPACITY AND ENERGY GENERATION

Page 67: 20120726 Briefing on BAKUN HEP (Technical)

� The Project & Company

� Progress of Works

� Reservoir Impoundment & Release

� Power Generation

� Other Benefits

THE PRESENTATION

Page 68: 20120726 Briefing on BAKUN HEP (Technical)

POSITIVE IMPACT ON BAKUN

Power Generation 1. Spill way Operationa.Flood mitigation - Belaga and Sibu saved

from flooding in March & April 2012 (5 times the average flow of 1,500 cumec)

b. Regulated flow - allowing uninterrupted boat traffic - plentiful water supply

2. Dam a. Reduce hazard to downstream (block

floating logs, debris and silt - 80, 000 tonnes of logs collected)

b. Better quality water release from dam.

3. Contributing to Grid System Performance

Unit 4

Page 69: 20120726 Briefing on BAKUN HEP (Technical)

HUGE RESERVOIR FOR ECO-TOURISM

Bakun Dam

� Length = 140km, Widest Zone = 6kmLength = 140km, Widest Zone = 6kmLength = 140km, Widest Zone = 6kmLength = 140km, Widest Zone = 6km

Batang Balui

Sungai Murum

Sungai LinauBatang Rajang

Page 70: 20120726 Briefing on BAKUN HEP (Technical)

ISLANDS WITH POTENTIAL FOR DEVELOPMENT� 20+ big islands of total size 6,000 ha.

Page 71: 20120726 Briefing on BAKUN HEP (Technical)

SCENIC SITES WITH GREAT TOURISM POTENTIAL

Page 72: 20120726 Briefing on BAKUN HEP (Technical)

GOOD SPOT FOR BIRD WATCHING & FISHING

Page 73: 20120726 Briefing on BAKUN HEP (Technical)

HEAVEN FOR PHOTOGRAPHER

Page 74: 20120726 Briefing on BAKUN HEP (Technical)

74

21 kg Empurau caught at Bakun DT’s outlet costing > RM9,000 – Jun 2003

POTENTIAL FOR CAGE CULTURE &AGR0-TOURISM