2012-04-05_171442_riggs
description
Transcript of 2012-04-05_171442_riggs
Riggs Manufacturing Company completed Job #221 on February 28 and there were no jobs in process in the plant. Prior to February, the pre-determined overhead application rate for March was computed from the following dataTotal budgeted overheadsTotal estimated direct labour hours$40,0005,000The factory has one production department and applies factory overheads on the basis of direct labour hours.Three jobs were started during the month and postings were made daily to the job cost sheets from the materials requisition and time cards. The following schedule shows the jobs and amounts posted to the job sheets.During the month of August, the cost record for Job #400 shows the following:
Job # Date Started Direct Material Direct Labour Direct Labour Hrs$ $ $222 March 1 7,500 15,000 2,400223 March 15 15,000 22,500 2,850224 March 25 4,000 10,500 1,950
The Manufacturing overhead control account was debited during the month for actual overhead expenses of $65,000.
On March 11, Job # 222 was completed and delivered to the customer at a mark-up of 40% on manufacturing cost.
On March 24th, Job # 223 was completed and transferred to finished goods.
On March 31st, Job #224 was still in process.
Any overhead variance is closed out to Cost of Sales,Required:a) Calculate Riggs overhead application rate. (2 marks)
40000/5000= $8 per direct labor hour
b) Calculate the production cost for each job, clearly showing the
manufacturing overhead allocated to each of the three (3) units. (6marks)Job Direct MaterialDirect laborOverhead
Total
222 7,500
15,000 2,400x8=1920041700223 15,000
22,500 2,850x8=2280060300224 4,000
10,500
1,950x8=1560030100
c) Using total figures, state the journal entries necessary to record the above transactions in the General Journal. (10 marks)WIP Job #222
Dr41700
Material
Cr7500
Payroll
Cr15000
FOH control
Cr19200
WIP Job #223
Dr60300
Material
Cr15000
Payroll
Cr22500
FOH control
Cr22800
WIP Job #224
Dr30100
Material
Cr4000
Payroll
Cr10500
FOH control
Cr15600
Finished Goods
Dr102000
WIP Job 222
Cr41700
WIP Job 223
Cr60300
Account Receivable
Dr58380Sales
Cr58380
41700x1.4
Cost of goods sold
Dr41700
Finished Goods
Cr41700
d) Show the journal entry necessary to dispose of this variance. Does your entry increase or decrease Cost of Goods Sold? (2 marks)Cost of goods sold
Dr7400
FOH control
Cr7400
65000-57600
It will increase cost of goods sold by $7400.PART (ii) (30 marks)Hewitt Electronics makes CD players by way of three consecutive processes: Assembly, Programming & Packing. Inspection takes place during the processing operation, at which point bad CD players are separated from good CD players and sold as scrap at $40 each.The following data relates to the Programming Department for the month of June. During June, 20,000 units valued at $515,000 were transferred from the Assembly Department to the Programming Department.Other costs incurred during the month were:
Direct Materials Added $323,000Direct Labour $258,000Manufacturing Overhead $241,200
Normal losses are estimated to be 5% of the units transferred in from Assembly.At inspection, 3,000 CD players were rejected as scrap. These units had reached the following degree of completion:
Transfer from Assembly 100%Direct material added 80%Conversion costs 50%
Work-in-progress at the end of June was 4,000 CD players and had reached the following degree of completion:
Transfer from Assembly 100%Materials added 60%Conversion costs 40%
There were no incomplete units in the Programming Department at the beginning of the period.
Materials added and conversion costs are incurred evenly throughout the process.
Required:a) Complete the template given to determine the equivalent units for direct materials (From AAssemblyMaterialConversion
Completed130001300013000
Closing WIP400024001600
Abnormal loss200016001000
190001700015600
ssembly & Materials added) and conversion costs. (8 marks)
b) Compute the cost per univalent unit for direct materials and conversion costs.(3 marks)
Direct Materials
= $323,000/17000 = $19 per unitConversion cost 258000+241200/15600
=499200/15600 = $32 per unitIt is assumed that cost of scrap of normal loss has already been deducted from manufacturing overhead of $241200.
c) Compute:a. The total cost of the CD players completed and transferred out to the Packing Department.51 x 13000 +515000/19000x13000 = $1015368
b. Cost of the unexpected lossesAssembly54211
D.M30400
CC32000
Total116611
c. Cost of ending work in process inventory in the Programming Department.(4 marks)Assembly108421
D.M45600
CC51200
Total205221
d) Prepare the Work in Process Inventory Programming Department T-account, clearly showing the ending balance. (4 marks)WIP Programming
Assembly515000Packing 1015368
Material 323000Abnormal los116611
Labor 258000Closing WIP 205221
FOH 241200
13372001337200
e) State the journal entries to record the assignment of direct materials and direct labour and the allocation of manufacturing overhead to the process during June. Also give the journal entry to record the cost of the units completed and transferred out to the Packing Department. (6 marks)DebitCredit
WIP Programming822200
Material323000
Payroll258000
FOH control 241200
WIP Packing1015368
WIP Programming1015368
f) What is the manufacturers true loss? (2 marks)
116611 2000x40 = 36611
g) Chico Angel is the owner of a small furniture manufacturing company that makes furniture based of customers orders. After consulting with his friend Joe, who is an accounting student, he decided to prepare quotes for customers using process costing; his friend Joe disagrees with his choice and recommended that he uses job costing. With whose choice do you agree? Explain.(3marks) When goods are made according to customer specification, the job order costing should be used; the process costing is used where the homogenous nature products are produced in bulk quantity. When the goods are made for different customers and they are different in nature, the material, labor and overheads used are different from each other therefore it is not possible to use process costing.