20111125 Th Site Visit Report 9

download 20111125 Th Site Visit Report 9

of 9

Transcript of 20111125 Th Site Visit Report 9

  • 7/29/2019 20111125 Th Site Visit Report 9

    1/9

    Site visit report

    MMF038 May 2003 - PM/10/12 & PM/14/12 Page 1 of 9 Mott MacDonald 2003

    Project Title Killamarsh Cycleway (TPBN559SUSTRANS Connect2 - Halfway toKillamarsh (Phase 1))

    Purpose of Visit 9th

    Site Inspection

    Project No. 290390 Contact Names Craig Hardy (JCE)

    Site Visited Killamarsh Station Road Contractor Jackson Civil Engineering Ltd

    Date of Visit 25th

    November 2011 Sub-Contractor

    Report

    prepared by

    F Hussain

    Distribution: Architect/Contractor/QS/Sub-Contractor/C of W/RE/File ref PiMS Documents Site Visit

    Report

    Item Text Action on

    1. JCE have been advised of the need to avoid damaging the settlement measuringapparatus during the laying and compaction of material to construct theembankments. JCE need to keep monitoring the settlement measuring apparatus andmake available the recorded data in the required format to Mott MacDonald.

    JCE

    2. Pulverised Fuel Ash (PFA) material continues to be laid on the new embankmentbeing constructed to the west of the field access track. A bulldozer and vibrating rollerare being used to place and compact the PFA material. Refer to photographs 1, 2, 3 &4.

    Information Only

    3. A material testing contractor was present on-site and it is understood that in additionto other testing, 2No. Nuclear density tests per 250mm (max) layer of PFA materialbeing laid on site will be conducted.

    Information Only

    4. Further materials testing results are awaited for samples taken from the PFA materialthat has been placed in the site areas where the new embankments are beingconstructed (i.e. to the east and west of River Rother). These results should beobtained and made available as soon as possible to allow assessment of thedensities being achieved.

    Information Only

    5. The existing field access track embankments (near the gate leading to Station Road)are being cleared as JCE progress with construction of the new embankment andbridge abutment works.

    JCE

    6. Bridge abutment construction works are underway to the west of River Rother. Thereinforcement cage and formwork for the abutment wall are being fixed in to placeready for the concrete pour which is due to take place on Saturday 26

    thNovember

    2011. Refer to photographs 5, 6 & 7. The wing walls for this abutment are due to becast in week commencing 28

    thNovember 2011.

    Information Only

    7. Reinforcement cages for the eastern bridge abutment continue to be fabricated on-site. Refer to photograph 8.

    Information Only

    8. At the east of River Rother, pile (bored) construction works have been completedsubsequent to some corrective action required of Van Elle. The piles are now beingtrimmed down (exposing the re-bars) to the required levels in preparation for receivingthe abutment construction above. Refer to photographs 9 & 10.

    Information Only

    9. The concrete bagwork outfall for the carrier drain installed between manhole S8a andthe existing ditch remains to be constructed.

    JCE

    10. The levels of the Type 1 material placed on the new PFA material embankment in thesite area between Forge Lane and the existing flood embankment to the east of RiverRother need to be reduced to the desired levels before laying the upper materials of

    Information Only

  • 7/29/2019 20111125 Th Site Visit Report 9

    2/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 2 of 9 Mott MacDonald 2003

    Item Text Action onthe proposed footpath/equestrian way construction. The overfilled material is currentlybeing used as an access route for construction plant. Refer to photographs 11 & 12.

    11. At the proposed tie-in to the western side of the railway line, construction of the WestBankseat is being completed. The concrete that was poured on the 25

    thNovember

    2011 was being tidied up in preparation for further works to the bankseat. Refer tophotographs 13 & 14.

    JCE

    12. JCE have commenced preparation of a set of drawings annotated with red line as-built alterations in order to record the few design/construction changes that havetaken place. JCE to mark up the set of red line as-built drawings with the recentchanges to the piling design and construction works to the east of River Rother.

    JCE

  • 7/29/2019 20111125 Th Site Visit Report 9

    3/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 3 of 9 Mott MacDonald 2003

    Photograph 1 PFA embankment in construction to the west of the existing field access track

    Photograph 2 PFA embankment in construction to the west of the existing field access track

  • 7/29/2019 20111125 Th Site Visit Report 9

    4/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 4 of 9 Mott MacDonald 2003

    Photograph 3 PFA embankment in construction to the west of the existing field access track

    Photograph 4 PFA embankment in construction to the west of the existing field access track

  • 7/29/2019 20111125 Th Site Visit Report 9

    5/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 5 of 9 Mott MacDonald 2003

    Photograph 5 Abutment construction works being carried out to the west of River Rother

    Photograph 6 Abutment construction works being carried out to the west of River Rother

  • 7/29/2019 20111125 Th Site Visit Report 9

    6/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 6 of 9 Mott MacDonald 2003

    Photograph 7 Abutment construction works being carried out to the west of River Rother

    Photograph 8 Fabrication of reinforcement cages on-site

  • 7/29/2019 20111125 Th Site Visit Report 9

    7/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 7 of 9 Mott MacDonald 2003

    Photograph 9 Pile trimming works being carried out to the east of River Rother

    Photograph 10 Pile trimming works being carried out to the east of River Rother

  • 7/29/2019 20111125 Th Site Visit Report 9

    8/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 8 of 9 Mott MacDonald 2003

    Photograph 11 Embankment construction to the east of River Rother

    Photograph 12 Embankment construction to the east of River Rother

  • 7/29/2019 20111125 Th Site Visit Report 9

    9/9

    SiteSiteSiteSite Visit ReportReportReportReport

    Continuation SheetContinuation SheetContinuation SheetContinuation SheetProject No. 290390 Date of Visit 25

    thNovember 2011

    MMF038 Jun 2003 - PM/10/12 & PM/14/12 Page 9 of 9 Mott MacDonald 2003

    Photograph 13 West bankseat construction works in the tie-in area at the west of the proposed railway bridge

    Photograph 14 West bankseat construction works in the tie-in area at the west of the proposed railway bridge