2011 Dan Gibbon Enerphit Retrofit Talk
-
Upload
jean-charles-vaillant -
Category
Documents
-
view
220 -
download
0
Transcript of 2011 Dan Gibbon Enerphit Retrofit Talk
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
1/45
bere:architects
UK Passivhaus Conerence
October 2011
Aiming or the Passivhaus/EnerPHit standard inoccupied buildings
Dan Gibbons, bere:architects
www.bere.co.uk
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
2/45
bere:architects
Retrot or the Future
The RF programme was split into two phases, Phase 1 saw 194 design and easibility studies
developed, while Phase 2 took 86 o these studies and unded the implementation o the retroftproposals
Each o the projects will see innovative plans put in place or low carbon refts o existing low-risesocial housing that will meet the UK governments target or reducing greenhouse gas emissionso 80% by 2050, while also cutting energy use dramatically.
Programme applicants were asked to develop whole house retroft solutions that would result indeep cuts to CO
2emissions whilst also signifcantly improving energy perormance. Applicants
were required to take a whole house approach, i.e. to consider a households energy needsand carbon dioxide impacts as a whole, and establish a comprehensive package o measures toreduce them.
(http://www.retroftortheuture.org)
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
3/45
bere:architects
Existing Buildings
3 Passeld Drive 78 Grove Road
Terraced house
No lot insulation
Solid wall construction
Single-glazed metal-ramed
windows
Lean-to extension
Concrete ground slab
(Semi) detached house
No lot insulation
Solid wall construction
Poorly tted double-glazedwindows
Suspended timber ground
foor
Bay window in poor repair
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
4/45
bere:architects
3 Passeld Drive beore the Retrot works (rear extension)
Passeld Drive
3 Passeld Drive beore the Retrot works
Existing Buildings
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
5/45
bere:architects Passeld Drive
The proposed Retrot works as shown on the original competition entry
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
6/45
bere:architects
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
7/45
bere:architects Grove Road
The proposed Retrot works as shown on theoriginal competition entry
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
8/45
bere:architects Grove Road
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
9/45
bere:architects
A Passivhaus Planning Package (PHPP) assessment o the energy
requirements o the existing house
A PHPP assessment o the proposed Retrot works as shown on the
original competition entry
3 Passfield drive3 Passfield drive
Passeld Drive
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
10/45
bere:architects
Passive House Verification
Photo or Drawing
Building: TSB retrofit for the future property proposed work
Location and Climate: Hounslow, London GB-London
Street: 78 Grove Road
Postcode/City: TW3 3PT London
Country: United Kingdom
Building Type: Detached house
Home Owner(s) / Client(s): Hounslow Council
Street: Lampton Road
Postcode/City: TW3 4DN Hounslow
Architect: bere:architects
Street: 73 Poets Road
Postcode/City: N5 2SH
Mechanical System: Alan Clarke T
Street: The Woodlands, Woodland Close, Whitecroft
Postcode/City: GL15 4PL Lydney
Year of Construction: 1950's
Number of Dwelling Units: 1 Interior T emperature: 21.0 C T
Enclosed Volume Ve: 353.1 m3 Internal Heat Gains: 2.1 W/m2
Number of Occupants: 2.7
Specific Demands with Reference to the Treated Floor Area
Treated Floor Area: 84.2 m2
Applied: Monthly Method PH C ertificate: Fulfilled? Verification:
Specific Space Heat Demand: 26 kWh/(m2a) 15 kWh/(m2a) No
Pressurization Test Result: 0.6 h-1 0.6 h-1 Yes
Specific Primary Energy Demand
(DHW, Heating, Cooling, Auxiliary and Household Electricity):94 kWh/(m2a) 120 kWh/(m2a) Yes
Specific PrimaryEnergyDemand
(DHW, Heating and AuxiliaryElectricity):53 kWh/(m2a)
Specific PrimaryEnergyDemand
EnergyConservation bySolar Electricity: kWh/(m2a)
Heating Load: W/m2
Frequencyof Overheating: 8 % over 25 C
Specific Useful Cooling EnergyDemand: kWh/(m2a) 15 kWh/(m
2a)
Cooling Load: W/m2
A Passivhaus Planning Package (PHPP) assessment o the energy
requirements o the existing house
A PHPP assessment o the proposed Retrot works as shown on the
original competition entry
78 Grove road 78 Grove road
Grove Road
Initial Proposals
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
11/45
bere:architects Grove Road
78 Grove Road beore the Retrot works
78 Grove Road beore the Retrot works
Existing Buildings
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
12/45
bere:architects
Architect: Schulze Darup & Partner
Location: Bernadottestrae, Nrnberg
Year o rst construction: 1964
Year o retrot: 2006
Heated foor area: 918m2
Number o residences: 24 > 31
images: Dr. Burkhard Schulze Darup schulze darup & partner architekten nrnberg
Precedent Study
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
13/45
bere:architects
Retrot:
Walls: 200-240mm external insulation = 0.16-0.14 W/(mK)
Roo Terrace: 200mm external insulation = 0.18 W/(mK)
Ceilings: 120-240mm = 0.16-0.22 0.18 W/(mK)
Windows: triple glazing = 0.92 W/(mK)
Heat Recovery Ventilation = 85% Eciency
District heating system
Precedent Study
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
14/45
bere:architects
Retrot:
Walls: 200-240mm external insulation = 0.16-0.14 W/(mK)
Roo Terrace: 200mm external insulation = 0.18 W/(mK)
Ceilings: 120-240mm = 0.16-0.22 0.18 W/(mK)
Windows: triple glazing = 0.92 W/(mK)
Heat Recovery Ventilation = 85% Eciency
District heating system
New Build Lot Apartments:
6 new Passivhaus certied apartments 70-110m
Precedent Study
204 26 15
heating demand
kWh/(my)
Beore Ater Lots
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
15/45
bere:architects
Retrot Works
3 Passeld Drive 78 Grove Road
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
16/45
bere:architects
Passivhaus Windows and Doors
3 Passeld Drive 78 Grove Road
Windows and doors achieve
0.8 W/(m2K)
Timber rames position
windows and doors within
line o insulation
Frames provide tolerance
to allow early ordering o
windows
Existing windows remain in
place longer
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
17/45
bere:architects
Airtight membranes provide continuity
between the window sealing tapes and
the parge coat o the external walls
The window sealing tapes are continuous
with rabbit ears at the corners to
acilitate sealing and allow or dierential
movement
The rabbit ears are olded back so that
they can be sealed to the membranes
Passivhaus Windows and Doors
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
18/45
bere:architects
Passivhaus Windows and Doors
3 Passeld Drive 78 Grove Road
membranes and tapes
provide continuous seal to
parge coat
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
19/45
bere:architects
External Insulation
3 Passeld Drive 78 Grove Road
240mm EPS insulation to
ront and rear walls. (180mm
extended one meter below
ground creating thermal
bubble beneath building)
Average U-values:
pre-retrot = 1.76 W/(m2K)
post retrot = 0.117W/(m2K)
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
20/45
bere:architects
External Insulation
3 Passeld Drive 78 Grove Road
200mm and 250mmm EPS
insulation to ront and
rear walls. (180mm extended
one meter belowground creating thermal
bubble beneath house)
Average U-values:
pre-retrot = 1.76 W/(m2K)
post retrot = 0.13 W/(m2K)
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
21/45
bere:architects
New Construction
3 Passeld Drive 78 Grove Road
New extension insulated
with 375mm wood bre
insulation to walls and
225mm mineral wool and
150mm wood bre
insulation to roo.
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
22/45
bere:architects
New Construction
3 Passeld Drive 78 Grove Road
New bay window
construction insulated
with 375mm wood bre
insulation to walls and
225mm mineral wool.
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
23/45
bere:architects
Floor Insulation
3 Passeld Drive 78 Grove Road
150mm Mineral wool
suspended between
timber joists on geo-textile
membrane
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
24/45
bere:architects Grove Road
Geo-textile membranes were laid across the foor joists to
support mineral wool insulation. OSB boards are laid over
the foor and taped to the walls to provide an airtightness
barrier. This work was also carried out on a room by room
basis
Original proposals assumed that the suspended timber foor could be
replaced with a similar insulated slab requiring a decant o the tenants
Floor Insulation
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
25/45
bere:architects
Floor Insulation
3 Passeld Drive 78 Grove Road
10mm thick Vacuum
Insulation panels protected
by 4mm sheets o EPS
sheets
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
26/45
bere:architects Passeld Drive
Original proposals assumed that the ground foor slab could be replaced
with a new insulated slab requiring a decant o the tenants
Preabricated vacuum insulation panels were tted above
the existing concrete ground foor slab; protected with oam
sheets. The insulation could be installed one room at a time
Floor Insulation
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
27/45
bere:architects
Roo Insulation
3 Passeld Drive 78 Grove Road
490mm mineral wool
insulation to attic space
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
28/45
bere:architects
Roo Insulation
3 Passeld Drive 78 Grove Road
100mm mineral wool and
300mm cellulose insulation
to attic space
U value = 0.10 W/(m2K)
PUR insulation at eaves
provides continuity oinsulation rom attic space
to walls
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
29/45
bere:architects Grove Road
Eaves were extended to allow continuity o insulation rom
the lot to the walls without removing the entire roo
Original proposals assumed that the existing roo tiles could be replaced
allowing insulation to be installed between and above the raters.
Hounslow Homes wanted to avoid the requirement or a temporary roo
and requested an alternative solution.
Roo Insulation
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
30/45
bere:architects
Heat Recovery Ventilation
3 Passeld Drive 78 Grove Road
Paul Novus 300 Heat
Recovery Ventilation units
located in lot spaces
provide continuous hygienic
ventilation
Tilt and turn windowsprovide secure natural
ventilation in summer
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
31/45
bere:architects
Heat Recovery Ventilation
3 Passeld Drive 78 Grove Road
Duct routes ollow chimney
breasts and existing storage
spaces to minimise intrusion
into living spaces
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
32/45
bere:architects
Solar Thermal
3 Passeld Drive 78 Grove Road
Grove Road:
3 no. AuroTHERM exclusive
VTK570/2 tube collectors
with new Vaillant solar
cylinder and boiler.
Passeld Drive:
2 no. AuroTHERM plus VFK150V collectors with Vaillant
cylinder and reconditioned
Vaillant boiler.
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
33/45
bere:architects
Other Measures
3 Passeld Drive 78 Grove Road
Breathable internalinsulation on party walls
Low fow taps and dual fush
WC throughout
High perormance insulation
(0.038 W/m2K at 40C)
to hot water pipes.
All timber products were
either FSC or PEFC.
Water butt and outside tap
provided to assist residents
commitment to their garden
Additional kitchen and
bathroom upgrades carried
out by RSLs during retrotworks to minimise later
disruptions
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
34/45
bere:architects
Air Tightness
3 Passeld Drive 78 Grove Road
Continuous membraneinstalled in attic sealed to
parge coat on walls.
Continuous seal rom parge
coat to airtightness
membranes in extension.
Windows sealed to parge
coat with continuous
tapes.
Airtightness grommets tted
to all service
penetrations.
Passeld Drive:
Improved airtightness rom
5.6 ach - 1.9 ach at 50Pa
Grove Road:
Improved airtightness rom
6.3 ach - 1.7 ach at 50Pa
(as veried by ALDAS and BSRIA)
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
35/45
bere:architects Passeld Drive
A continuous membrane installed in the lot at Passeld Drive to create the
airtightness barrier, sealed to the external walls.
The membrane proved dicult to install; requiring many taped joints and
dicult sealing details around service penetrations
Air Tightness
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
36/45
bere:architects
The boards allowed access to be maintained in the roo space and simple
seals to be used around services
18mm OSB provides the airtight barrier. Membranes are used to seal
around roo timbers and connect to the external walls
Grove Road
Air Tightness
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
37/45
bere:architects
Air Tightness: potential losses
3 Passeld Drive 78 Grove Road
air inltration through
interstitial foors suggested
party walls may be source
o some air losses
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
38/45
bere:architects
Air Tightness: potential losses
3 Passeld Drive 78 Grove Road
additional losses through
discontinuity o air tightness
layer at oundation level
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
39/45
bere:architects Handover
These vents remove possiblestale and damp air rom thekitchen, bathroom and WC.The heat recovery unit savesheat, which saves money. Theventilation runs continuously all
year round but specialmotors have tinyenergy consumption.The extract air ventlter in the kitchenneeds to be cleanedabout every 3 monthsdepending on use.
Passeld DriveUser Guide
bere:architects
This unit saves heatrom the internal airproduced by solargains, people andelectric items to pre-heat a supply o reshair. I air heating is notrequired only reshltered air is supplied.These lters need to bereplaced every 6months
in London. The system saves about 10 times moreenergy than it uses! It is located in the store in aninsulated cupboard.
The resh airsystem can belet on autobut the anspeed can also
be manuallychangedusing thispanel duringcooking or i thebathrooms are
steamy. I you go away or a period o time dont turnit o but leave it on the lowest speed.
This unit stores hot water produced bythe panel (8) on your roo and or theheating and added water heated by thegas boiler (7). The tank is well insulatedmeaning there is hot water day and
night. The temperate o the tank isset with the control panel below. Thespace heating is controlled with the
Thermostat inthe entranceway (5) andnot via thispanel.
In summeralmost all thewater in thesolar tank isheated by the
sun shiningon the solarpanel on theroo. In winter
the panel can heat the bottom hal o the tank andthe boiler is used to top up the temperature. Thismeans there is always hot water available in the tankeven on a cloudy day.
To keep the internaltemperature cool in thesummer utilise the coolernight temperatures byleaving the windows
open in the secure tiltposition overnight. Iits hotter outside inthe day you can shut
the windows then turn the heat recovery ventilationto summer by pass using the user settings on thecontrol panel (4) to keep cool inside. Please reer tothe heat recovery ventilation unit manual surplied byAD enviro.
This house has beenwrapped in insulation, foorwalls and roo. The ront wallhas 200mm, rear 250mm,the roo 490mm andvacuum insulation on thefoors. Every penetrationso this insulation has beensealed to produce a dratree building suitable orusing a heat recovery unit.These improvement willmake your energy cost muchlower.
Alan Clarke (Building Services Engineer)Tel: 01594 563356E-mail: [email protected]
bere:architects (passivhaus specialists)Tel: 020 7359 4503E-mail: [email protected]
The thermostatin the entranceway sets thetemperatureor your house.20-21C isthe normaltemperature,but you couldturn it down i
you are away or a ew days or just or a ew hours tosave energy. To adjust the room temperature, locatethe room temperature display and simple rotate theright knob up or down.
This boiler serves asback up or the solartank (6). I there has notbeen enough sun thewater in the solar tankmay not be hot enoughor heating or showering.In this instance the gasboiler will top up the solartank. There is no needto amended the settingon the boiler. To turnthe heating up use thethermostat (5).
The resh air (pre-warmedin winter) is supplied bythe heat recovery unitand delivered to thebedrooms and living
room using these resh airvents. The heating system(6,7) is automatic but youcan adjust the an speed(4) manually with the wall
mounted panel in the kitchen. This will keep the airresh during a amily gathering or intensive cooking(in addition to the extractor an.
1 Heat recovery ventilation unit
4 Heat recovery ventilation control panel 6 Solar tank and control panel
7 Bo iler and cont rol pane l 9 Insulation and dra t ree cons truc tion
8 Hot water rom the sun 10 Windows (or summer cooling)
5 Thermostat
Passeld drive north elevation
2 Fresh air vents
3 Extract air vents
The term passivhaus reers to an advanced lowenergy construction standard or buildings, whichhave excellent comort conditions in both winter andsummer. They typically achieve a heating saving o 90%compared to existing housing. Passivhaus buildings areeasy to live in and require little maintenance, but theydo have some important eatures, which are explainedin this guide. The eatures are simple to operate, but aull understanding will help you get the lowest energy
consumption and best comort. This guide has beendesign by Alan Clarke and bere:architects or you (theuser) to understand how a passivhaus works and how tooperate the controls in this house.Each eature is labelled on the drawings below,highlighting their locations and briefy explaining how tooperate them in the corresponding text. Please take thetime to read this guide and amiliarise yoursel with thecontrols.
This house is built towards a buildingstandard called Passivhaus.
AD enviro (passeld drive building contractor)Consult the specic manuactures guides supplied
For urther inormation regarding these eatures:
Ground foor plan First foor plan Second foor plan Section AA
Supply ducts
Extract ducts
Insulation
Wall construction
Outside air intake
KitchenEntrance
Dining area
Sitting area
Sitting area
Bedroom
Radiator
Bedroom
Bathroom
Bedroom
Roo space
BedroomLiving room
Living room
Garden
WC
WC
18
9
9
9
37
10
10
10
10
3
4
5
63
3
2
2
2 2
2
2
2
2
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
40/45
bere:architects
Passive House Verification
Photo or Drawing
Building: TSB retrofit for the future property proposed work
Location and Climate: Hounslow, London GB-London
Street: 78 Grove Road
Postcode/City: TW3 3PT London
Country: United Kingdom
Building Type: Detached house
Home Owner(s) / Client(s): Hounslow Council
Street: Lampton Road
Postcode/City: TW3 4DN Hounslow
Architect: bere:architects
Street: 73 Poets Road
Postcode/City: N5 2SH
Mechanical System: Alan Clarke
Street: The Woodlands, Woodland Close, Whitecroft
Postcode/City: GL15 4PL Lydney
Year of Construction: 1950's
Number of Dwelling Units: 1 Interior Temperature: 20.0 C
Enclosed Volume Ve: 353.1 m3 Internal Heat Gains: 2.1 W/m2
Number of Occupants: 2.4
Specific Demands with Reference to the Treated Floor Area
Treated Floor Area: 76.0 m2
Applied: Monthly Method PH Certificate: Fulfilled?
Specific Space Heat Demand: 28 kWh/(m2a) 15 kWh/(m2a) No
Pressurization Test Result: 1.7 h-1 0.6 h-1 No
Specific Primary Energy Demand
(DHW,Heating, Cooling,Auxiliary and Household Electricity):97 kWh/(m2a) 120 kWh/(m2a) Yes
Specific Primary Energy Demand
(DHW,Heating and Auxiliary Electricity):56 kWh/(m
2a)
Specific Primary Energy Demand
Energy Conservation by Solar Electricity:kWh/(m
2a)
Heating Load: W/m2
Frequency of Overheating: 15 % over 25 C
Specific Useful Cooling Energy Demand: kWh/(m2a) 15 kWh/(m
2a)
Cooling Load: W/m2
We confirm that the values given herein have been Issued on:
determined following the PHPP methodology and based
on the characteristic values of the building. The calculations signed:
with PHPP are attached to this application.
Passive House Verification
Photo or Drawing
Building: TSB retrofit for the future property proposed work
Location and Climate: London GB-London
Street: 3 Passfield Drive
Postcode/City: E14 6QJ London
Country: United Kingdom
Building Type: Terraced house
Home Owner(s) / Client(s): Southern Housing
Street: P0 Box 643
Postcode/City: West Sussex RH12 1XJ
Architect: bere:architects
Street: 73 Poets Road
Postcode/City: N5 2SH London
Mechanical System:
Street:
Postcode/City:
Year of Construction: 1960's
Number of Dwelling Units: 1 Interior Temperature: 20.0 C
Enclosed Volume Ve: 352.9 m3 Internal Heat Gains: 2.1 W/m2
Number of Occupants: 4.0
Specific Demands with Reference to the Treated Floor Area
Treated Floor Area: 82.2 m2
Applied: Annual Method PH Certificate: Fulfilled?
Specific Space Heat Demand: 25 kWh/(m2a) 15 kWh/(m2a) No
Pressurization Test Result: 1.9 h-1 0.6 h-1 No
Specific Primary Energy Demand
(DHW, Heating, Cooling, Auxiliary and Household Electricity): 119 kWh/(m2a) 120 kWh/(m
2a) Yes
Specific Primary Energy Demand
(DHW, Heating and Auxiliary Electricity):58 kWh/(m
2a)
Specific Primary Energy Demand
Energy Conservation by Solar Electricity: kWh/(m2a)
Heating Load: W/m2
Frequency of Overheating: 0 % over 25 C
Specific Useful Cooling Energy Demand: kWh/(m2a) 15 kWh/(m
2a)
Cooling Load: W/m2
We confirm that the values given herein have been Issued on:determined following the PHPP methodology and based
on the characteristic values of the building. The calculations signed:
with PHPP are attached to this application.
Predicted specic heat demand reduction o 91%
78 Grove road3 Passfield drive
Predicted specic heat demand reduction o 94%
Results
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
41/45
bere:architects
Results
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
42/45
bere:architects
Results
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
43/45
bere:architects
Results
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
44/45
bere:architects
Results
-
7/27/2019 2011 Dan Gibbon Enerphit Retrofit Talk
45/45
bere:architects
thank you
Dan Gibbons, bere:architects
www.bere.co.uk