2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp...

48
2010 West Slope Road/Bridge Capital Improvement Program (CIP) for Cameron Park & Shingle Springs Prepared for the Shingle Springs–Cameron Park Chamber of Commerce May 19, 2010 This presentation can be found at http://www.edcgov.us/DOT/index.html

Transcript of 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp...

Page 1: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

2010 West Slope Road/Bridge Capital Improvement Program

(CIP) for Cameron Park & Shingle Springs

Prepared for the Shingle Springs–Cameron Park Chamber of Commerce

May 19, 2010

This presentation can be found at http://www.edcgov.us/DOT/index.html

Page 2: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 2SS-CP Chamber Presentation

Purpose for this Presentation:

Provide an update on–

DOT projects planned in the Cameron Park and Shingle Springs area

The Cameron Park Drive Interchange Project

Answer questions.

Page 3: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 3SS-CP Chamber Presentation

Background

Projects Planned in Shingle Springs, Cameron Park Area

Overview of the 2010 CIP

Cameron Park Drive Interchange

Agenda

Page 4: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 4SS-CP Chamber Presentation

CIP Purpose and Background•

The Board of Supervisors annually adopts the CIP and provides direction to DOT.

The purpose of the CIP is to provide strategic direction regarding DOT’s capital project priorities over a 10 to 20 year horizon:–

20 year horizon for road improvement projects–

5 to 10 year horizon for all other projects.

DOT updates the CIP annually as new information becomes available regarding priorities, funding sources, design alternatives, project cost estimates and timing.

CIP projects are prioritized based on a number of factors such as safety, capacity, traffic circulation patterns, level of service (LOS) requirements, available funding, and economic development needs.

Page 5: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 5SS-CP Chamber Presentation

Background

Projects Planned in Shingle Springs, Cameron Park Area

Overview of the 2010 CIP

Cameron Park Drive Interchange

Agenda

Page 6: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 6SS-CP Chamber Presentation

DOT plans to make major CIP investments in the Shingle Springs/Cameron Park area over the next 20 years; examples include:

Durock

Rd / Business Dr Signalization

U.S. 50/HOV Lanes (Bass Lake Rd to Ponderosa Rd)

Durock

Rd Widening –

Robin Ln

to S. Shingle Rd

Ponderosa Rd Interchange

Cameron Park Dr Interchange

Cambridge Rd Interchange

Page 7: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 7SS-CP Chamber Presentation

EAST EL DORADO HILLS, WEST CAMERON PARK PROJECTS IN PROCESS OR PROPOSED

US HWY 50/BASS LAKE RD – INTERCHANGE IMPROVEMENTS PH 1 AND 2

(71330, GP148)

─ US HWY 50/HOV LANE BASS LAKE GRADE TO CAMERON PARK DR (53113)

─ BASS LAKE RD – FULL IMPROVEMENTS PHASE 1A (66109)

─ BASS LAKE RD WIDENING – US HWY 50 TO SILVER SPRINGS PKWY PH 1B (GP166)

─ BASS LAKE RD – FRONTAGE IMPROVEMENTS AT SILVER SPRINGS PKWY (66115)

SILVER SPRINGS PKWY TO GREEN VALLEY RD – NORTH SEGMENT AND

SIGNALIZATION (76107)

─ SILVER SPRINGS PKWY TO BASS LAKE RD – SOUTH SEGMENT (76108)

─ GREEN VALLEY RD WIDENING – DEER VALLEY RD EAST TO LOTUS RD (GP179)

GREEN VALLEY RD AT DEER VALLEY RD – WEST INTERSECTION IMPROVEMENTS

(76114)

─ GREEN VALLEY RD WIDENING – SALMON FALLS TO DEER VALLEY RD (GP159)

─ COUNTRY CLUB DR EXTENSION – BASS LAKE RD TO SILVER DOVE RD (GP124)

COUNTRY CLUB DRIVE EXTENSION – SILVER DOVE RD TO WEST BASS LAKE

HILLS SP BOUNDARY (GP125)

COUNTRY CLUB DR EXTENSION – BASS LAKE RD TO EAST BASS LAKE HILLS SP

BOUNDARY (GP126)

─ HOLLOW OAK DRAINAGE (72369)

F1

F3

F4

F5

F6

Last updated 05/17/2010

SILVA VALLEY PKWY

SERRANO PKWY

US HWY 50

BASS LAK

E RO

AD

F7

F8

F9

F10

F12

F13

F14

GREEN VALLEY RD

HOLLOW OAK D

R

COUNTRY CLUB DR

F1

F2

F3

F4

F5

F6

F7

F14

F8

F9

F10

F13F12

BASS LAKE AREAEDC C.I.P. PROJECTS

F2

Legend: In Process, Active Proposed xx

F11

F11

CAMBRIDGE RD

Page 8: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 8SS-CP Chamber Presentation

CAMERON PARK / SHINGLE SPRINGS PROJECTS IN PROCESS OR PROPOSED

SERRANO PKW

Y

─ US HWY 50 / CAMBRIDGE RD INTERCHANGE IMPROVEMENTS PHASE 1 (71332)

─ US HWY 50 / CAMBRIDGE RD INTERCHANGE IMPROVEMENTS PHASE 2 (GP149)

─ CAMERON PARK DR WIDENING – DUROCK RD TO COACH LN (72367)

─ DUROCK RD WIDENING – ROBIN LN TO SOUTH SHINGLE RD (GP171)

─ DUROCK RD / BUSINESS DR SIGNALIZATION (73354)

─ US HWY 50 / PONDEROSA RD INTERCHANGE – N. SHINGLE RD REALIGNMENT (71339)

US HWY 50 / PONDEROSA RD / S. SHINGLE RD – INTERCHANGE IMPROVEMENTS

(71333)

─ US HWY 50 / PONDEROSA RD INTERCHANGE – DUROCK RD REALIGNMENT (71338)

─ PONDERSOSA RD WIDENING – N. SHINGLE RD TO MEDER RD (GP175)

─ US WHY 50 HOV LANES PHASE 2B – CAMERON PARK DR TO PONDEROSA RD (53122)

─ US HWY 50 HOV LANES PHASE 3 – PONDEROSA RD TO GREENSTONE RD (53116)

─ US HWY 50 / CAMERON PARK DR INTERCHANGE IMPROVEMENTS PHASE 1 (72361)

─ US HWY 50 AUXILARY LANES EB – CAMBRIDGE RD TO PONDEROSA RD (GP150)

─ GREEN VALLEY RD – TENNESSEE CREEK BRIDGE REPLACEMENT (77109)

─ GREEN VALLEY RD – CAMERON PARK DR INTERSECTION IMPROVEMENTS (73150)

─ US HWY 50 HOV LANES PHASE 2A – BASS LAKE RD TO CAMERON PARK DR (53113)

─ CAMERON PARK DR WIDENING – PALMER DR TO MEDER RD (GP144)

─ PALMER DR TO WILD CHAPARRAL DRIVE CONNECTION (71365)

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

F11

F12

F13

F14

F15

F16

F1F2

F6

F7F8

F9

F10

F11

F12F13

F14

F15

F16

F17

CAMERON PARK DRIVE

CAMBRIDGE ROAD

GREEN VALLEY RD

NO

. SHIN

GLE R

OA

D

DUROCK ROAD

PONDEROSA

ROAD

MEDER ROAD

SO. S

HING

LE R

OAD

CAMBRIDGE RD TO PONDEROSA RDEDC C.I.P. PROJECTS

F3

F4 F5U.S. HWY 50

CAMERON PARK

F17

Legend: In Process, Active Proposed xx

Last updated 05/17/2010

F18

F18

Page 9: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 9SS-CP Chamber Presentation

Background

Projects Planned in Shingle Springs, Cameron Park Area

Overview of the 2010 CIP

Cameron Park Drive Interchange

Agenda

Page 10: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 10SS-CP Chamber Presentation

53110

53113*2019

US 50 HOV Lane Phase 2A

Bass Lake Grade to Cameron Park Dr

*2011

US 50 HOV Lanes Phase 1

El Dorado Hills Blvd to Bass Lake Grade

53116*Beyond 2019

US 50 HOV Lane Phase 3

Ponderosa Rd to Greenstone Rd

*PROPOSED COMPLETION YEAR from 2010 CIP

*Beyond 2019

US 50 HOV Lane Phase 2B

Cameron Park Dr to Ponderosa Rd

53122

There are 4 HOV Lane Projects:

Page 11: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 11SS-CP Chamber Presentation

Current Status on HOV Lane Projects:•

Phase 1 (EDH

Blvd. to Bass Lake Grade) may be extended* due to savings, and is still planned for completion in 2011;

Fast-track timing for Phases 2A and 2B was dependent on being awarded a Federal TIGER grant–

DOT made the short list for the TIGER grant (~$20M)–

However, DOT learned in Feb: not selected this round–

Therefore, Phase 2A (Bass Lake Grade to Cameron Park Dr.) is currently planned for completion in 2019, and

Phase 2B (Cameron Park Dr. to Ponderosa Rd.) is planned for completion beyond 2019;

Phase 3 (Ponderosa Rd. to Greenstone Rd.): No change from 2009 CIP; planned for completion beyond 2019.

* Contingent upon CTC approval

Page 12: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 12SS-CP Chamber Presentation

Timing of construction of Cameron Park Dr. and Ponderosa Rd. Interchanges:•

Cameron Park Dr. Interchange is included in the CIP at the current estimate of $58.7M.–

Due to the expanded set of alternatives that DOT will analyze over the next several months, it is uncertain if the estimate will remain that high.

Both the Ponderosa Rd. and Cameron Park Dr. Interchanges are not expected to be constructed for several years.–

Both rely on a dramatic increase in residential permit activity before then.

DOT expects that between now and next year’s CIP, there will be updates to the timing and cost estimates for both interchanges, as more information becomes available.

Page 13: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 13SS-CP Chamber Presentation

72361**

72367**

*2014/2019

US 50/Cameron Park Dr

Interchange Improvements

*2014/2019

Cameron Park Dr Widening

Durock Rd to Coach Ln

GP144

*Beyond 2019

Cameron Park Widening

Palmer Dr to Meder Rd

*2014/2019

Durock Rd Widening

Robin Ln to S. Shingle Rd

GP171 73354

*2010/2011

Durock Rd at Business Dr

Intersection Signalization

*PROPOSED COMPLETION YEAR GP150

*Beyond 2019

US 50 Auxiliary Lane

Eastbound from Cambridge Rd to Ponderosa Rd

Cameron Park Dr Interchange Projects:

** CURRENTLY UNDER REVIEW

71365

*Beyond 2019

Palmer Dr to Wild Chaparral Dr Connection

Page 14: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 14SS-CP Chamber Presentation

GP175

GP171

73354

71338

Beyond 2019

Ponderosa Rd Widening

N. Shingle Rd to Meder Rd

2012/2013

US 50/Ponderosa Rd Interchange

Durock

Rd Realignment

2014/2019

Durock Rd Widening

Robin Ln to So. Shingle Rd2010/2011

Durock Rd/Business Dr

Intersection Signalization

71339

2012/2013

US 50/Ponderosa Rd Interchange

No. Shingle Rd Realignment

71333

2014/2019

US 50/Ponderosa Rd/So. Shingle Rd Interchange Improvements

*PROPOSED COMPLETION YEARProposed Ponderosa Interchange Projects:

GP150

Beyond 2019

US 50 Eastbound Auxiliary Lanes

Cambridge Rd to Ponderosa Rd

Page 15: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 15SS-CP Chamber Presentation

Timing of Ponderosa Rd Interchange projects are all dependent on available funding:

Planning for 71333, including 71338 and 71339, is underway now and the environmental document is targeted for certification

by the end of this year

71339: N. Shingle Rd Realignment–

Includes realignment of approx. ¼

mile of N. Shingle Rd about 600 ft. north of Ponderosa Rd, realignment of the WB off-ramp with Wild Chaparral Dr, and signalization

71338: Durock

Rd Realignment–

Includes realignment of approx. ¼

mile of Durock

Rd and signalization of the new intersection

GP171: Durock

Rd Widening–

Includes widening of Durock

Rd from Robin Ln

to S. Shingle Rd including a 2-way left turn lane

71333: the Ponderosa Rd overcrossing

is planned to be widened to 5 lanes and includes ramp widenings

Page 16: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 16SS-CP Chamber Presentation

Background

Projects Planned in Shingle Springs, Cameron Park Area

Overview of the 2010 CIP

Cameron Park Drive Interchange

Agenda

Page 17: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 17SS-CP Chamber Presentation

Current Situation:•

On January 25, 2010, DOT provided the Board of Supervisors with an update on the U.S. 50/Cameron Park Dr Interchange projects.

The current CIP projects for the Cameron Park Drive Interchange and associated projects, may impact many existing residences and businesses and total $68M.

Other alternatives have been analyzed but have similar impacts and costs.

Additional alternatives have not been fully analyzed, but they may not meet Level of Service (LOS) requirements or receive Caltrans’

approval, but they could impact

fewer businesses/residences and cost less.

Page 18: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 18SS-CP Chamber Presentation

ALT. 0. $0M DO NOTHING

PROS:–

No out of pocket cost –

No right of way impacts–

General Plan allows portion to operate at LOS F*

Supervisors could vote (4/5th) to allow LOS F

CONS:–

Existing LOS issues at EB off–

Doesn’t meet LOS requirements based on 2025 or 2035 forecasts

Unknown implications of allowing LOS F*

*

*Maximum Volume to Capacity = 1.1

Page 19: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 19SS-CP Chamber Presentation

Alt 1. $68M Current Plan: 8 Lane Cameron Park Dr (PSR Alt #1)

PROS:–

Maintains LOS through General Plan’s buildout forecast (2035)

Improves overall circulation

CONS:–

Expensive–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term–

Median installed at Coach Lane

For Illustrative Purposes

Page 20: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 20SS-CP Chamber Presentation

Alt 2a. $51.4M: 7 Lane Cameron Park Dr (PSR Alt #2)

PROS:–

Less expensive initially–

Upgrade when needed

CONS:–

Approx. 10 year LOS Life–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term–

Median installed at Coach Lane

For Illustrative Purposes

PROPOSED REALIGNMENT/CONNECTION

Page 21: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 21SS-CP Chamber Presentation

CONS:–

Cost undetermined–

May require other local road improvements–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term

PROS:–

May not require median at Coach–

Upgrade when needed–

Likely to have 20 yr LOS life

Alt 2b. $??M: 7 Lane Cameron Park Dr + other local road improvements (PSR Alt #2 + )

For Illustrative Purposes

PROPOSED REALIGNMENT/CONNECTION

Page 22: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 22SS-CP Chamber Presentation

CONS:–

Unknown cost–

May not deliver enough LOS benefit–

Unknown environmental mitigation

PROS:–

Could be less expensive–

Provides some relief to Cam Park Dr–

Provides Parallel capacity

Alt 2c. $??M: Other local road improvements onlyFor Illustrative Purposes

Page 23: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 23SS-CP Chamber Presentation

Alt 3. $96M: Single Point Diamond (PSR #3)

CONS:–

Alt 1 achieves same result with lower cost

More impacts to local businesses/ residences than Alt 1

Lowers Cam Park Dr by 7 ft -- requires pumping station (maintenance)

PROS:–

Eliminates left turns improving traffic flow & LOS

Maintains LOS through General Plan’s buildout forecast (2035)

For Illustrative Purposes

Page 24: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 24SS-CP Chamber Presentation

CONS:–

Unknown LOS benefit–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term–

Median installed at Coach Lane

Alt 4a. $9.1M: Build 72367 Only – widen Cameron Park Dr from Durock to Coach

PROS:–

Improved capacity on this section

For Illustrative Purposes

Page 25: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 25SS-CP Chamber Presentation

CONS:–

Unknown LOS benefit–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term–

Median installed at Coach Lane

Alt 4b. $??M: Build 72367 (widen Cameron Park Dr from Durock to Coach) and connect Rodeo to Robin

PROS:–

Improved capacity on this section

For Illustrative Purposes

Page 26: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 26SS-CP Chamber Presentation

CONS:–

May not deliver enough LOS benefit–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term

Alt 4c. $??M: Make Coach one-way, widen Cameron Park Dr to 6 lanes and connect Rodeo to Robin

PROS:–

Improved capacity on this section

For Illustrative Purposes

Page 27: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 27SS-CP Chamber Presentation

CONS:–

Unknown LOS benefit–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term

Alt 4d. $??M: Remove signal at Coach; disallow all lefts at Cam Park Dr & Coach; connect Rodeo & Robin

PROS:–

Improved capacity on this section–

Eliminates signal at Coach

For Illustrative Purposes

Page 28: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 28SS-CP Chamber Presentation

Alt 5. $??M: Build 72367 and expand ramps

CONS:–

Unknown LOS benefit–

Likely to impact some existing properties –

Could impact property/sales tax revenues in near-term–

Median installed at Coach Lane

PROS:–

Improved ramp operations–

Improved capacity on this section

For Illustrative Purposes

Page 29: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 29SS-CP Chamber Presentation

Alt 6. $9.6M+R/W+ mitigation cost: Connect Palmer to Wild Chaparral

PROS:–

Provides additional circulation alternative–

Parallel Highway 50 capacity–

Minimal impact to existing businesses & residences

CONS:–

Didn’t show much LOS benefit at the Interchange in Traffic Study

Unknown environmental mitigation

For Illustrative Purposes

Page 30: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 30SS-CP Chamber Presentation

Alt 7. $??M: 7 Lanes on Cameron Park Dr now expanding to 8 lanes when needed (Starts out as PSR Alt. 2)

PROS:–

Less expensive to start ($51.4M)–

Upgrade when needed–

Would address LOS needs for 2025 and 2035 with expansion

CONS:–

Throw-away costs (retaining walls, staging costs, moving signals, intersections)

Median installed at Coach Lane

For Illustrative Purposes

Page 31: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 31SS-CP Chamber Presentation

Alt 8. $??M: Diverging Diamond

CONS:–

Eliminated by Caltrans 8/07 for being non- standard

May require a larger footprint than Alt 1. and therefore more right of way

Unknown LOS benefit–

Not enough analysis has been done to identify all the potential impacts

PROS:–

Improves operations because no conflicting left turns

May be relatively inexpensive

Proven in Missouri–

May be eligible for Federal demonstration grant

May allow left turns from Coach

For Illustrative Purposes

Page 32: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 32SS-CP Chamber Presentation

Alt 9. $??M: Roundabout

CONS:–

Will require a significantly larger footprint and therefore more right of way

Unknown LOS benefit–

Unknown impacts to existing businesses

Non-standard for Caltrans

PROS:–

Improves operations because no need for left turns

May be eligible for Federal demonstration grant

For Illustrative Purposes

Page 33: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 33SS-CP Chamber Presentation

Alt 10. $??M: Widen Cameron Park Dr to 7 lanes

CONS:–

Unknown LOS benefit–

Not costed as stand-alone–

Eliminated by DOT 5/06 as incomplete solution

PROS:–

Improves capacity on this section

For Illustrative Purposes

Page 34: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 34SS-CP Chamber Presentation

Alt 11. $??M: Expand ramps; move retaining walls back under Hwy 50 to allow free right from EB off-ramp.

CONS:–

Unknown LOS benefit•

PROS:–

Improves ramp operations

For Illustrative Purposes

Free Right

Page 35: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 35SS-CP Chamber Presentation

Alt 12. $??M – Realign Country Club Dr.

CONS:–

Unknown LOS benefit–

Eliminated by DOT 5/06 due to large R/W impacts

PROS:–

Relieves some congestion at westbound ramps and new Country Club

For Illustrative PurposesTO BE ABANDONED

Page 36: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 36SS-CP Chamber Presentation

Alt 13. $??M: Move the Interchange East

Close existing ramps

Build new ramps & overcrossing;

connect to Coach

CONS:–

Unknown LOS benefit–

Uses up developable land–

Impacts freeway access of existing businesses–

May require additional road connections–

Will require widening/realigning of Palmer–

Unknown environmental mitigation

PROS:–

Relieves Cameron Park Dr–

Avoids physical impacts to existing businesses

No need to lengthen existing bridges–

Improves access to currently undeveloped non residential land

For Illustrative Purposes

Page 37: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 37SS-CP Chamber Presentation

Alt. 14: $??M:“Hook” eastbound offramp to Coach/Robin:

PROS:–

Simple–

Would reduce congestion at the interchange & Coach

CONS:–

Caltrans already rejected this alternative–

May require widening of Coach leading to R/W impacts

R/W impacts near Robin Ln–

Unknown LOS benefit

For Illustrative Purposes

Page 38: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 38SS-CP Chamber Presentation

Alt. 14: Site of “Hook” eastbound offramp from Hwy 50:

Page 39: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 39SS-CP Chamber Presentation

ALTER-

NATIVE #

NAME COSTCameron Park Dr and Coach Ln POTENTIAL

RIGHT OF WAY COSTS/

IMPACTS

OTHER

IMPACTSLOS PM Peak Hour

in 2015

LOS PM Peak Hour

in 2025

LOS PM Peak Hour

in 2035

0 DO NOTHING $0 F F F NO

1 CURRENT PLAN -

8 LANE CAMERON PARK DR UNDER HWY 50 (PSR #1)

$68M D N/A E $12M

2a 7 LANE CAMERON PARK DR (PSR #2) UNDER HWY 50

$51.4M E E F $12M

2b 7 LANE CAMERON PARK DR w/Other Local Road Improvements (PSR #2 +)

> $61M E E E $12M+

2c OTHER LOCAL ROAD IMPROVEMENTS ONLY

Not Costed Preliminary study shows benefits but unknown to what level

LIKELY + PLANT PRESERVE

3 SINGLE POINT DIAMOND (PSR #3) $96.3M C N/A E $20M Lower Cam Park Dr 7 ft; add Pump Stn.

4a, b, c, d WIDEN CAMERON PARK DR FROM DUROCK TO COACH +

$9.1M and up

Not Studied $6.2M

5 4a PLUS EXPAND HWY 50 RAMPS Not Costed Not Studied AT LEAST $6.2M

6 CONNECT PALMER TO W. CHAPPARAL

$9.6M + R/W cost

Preliminary study showed little benefit to making this connection alone

PLANT PRESERVE

7 7 Lanes on Cam Park Dr now expanding to 8 lanes when needed

> $51.4M D N/A E $12M Throw-away costs (e.g., retain. walls)

8 DIVERGING DIAMOND Not Costed Not Studied UNKNOWN Non Std. for Caltrans

9 ROUNDABOUT Not Costed Not Studied YES Non Std. for Caltrans

10 WIDEN CAMERON PARK DR. to 7 Lns. Not Costed Not Studied YES

11 EXPAND HWY 50 RAMPS; ALLOW FREE RIGHT FROM EB OFF-RAMP

Not Costed Not Studied YES

12 REALIGN COUNTRY CLUB Not Costed Not Studied YES

13 MOVE THE INTERCHANGE EAST Not Costed Not Studied ?, PLANT PRESERVE

14 “HOOK”

EASTBOUND OFFRAMP TO COACH, ROBIN

Not Costed Not Studied UNKNOWN Non Std. for Caltrans

DOT reviewed 14 possible alternatives with the Board:

Page 40: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 40SS-CP Chamber Presentation

The Board directed DOT to expand its preliminary matrix by adding other important evaluation measures:

Impacts on economic development–

Property tax and sales tax impacts

Public benefits e.g.,:•

Lost time and fuel caused by delays

Impacts on Air Quality•

Ease of finding way back to Hwy 50;

Effects of Recent State Legislation i.e., SB375;

Define and differentiate Regional vs. Local benefits;

Page 41: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 41SS-CP Chamber Presentation

The Board directed DOT to expand its preliminary matrix by adding other important measures for evaluation (cont.):•

Benefits of adding parallel capacity:

Expand area of analysis to include the Cambridge Rd. Interchange to the Ponderosa Rd. Interchange –

look

at the area as a system to include:

Rodeo Rd. connection from Cameron Park Dr. to the Cambridge Rd. Interchange,

Country Club Dr. connection from the Cambridge Rd. Interchange to the Cameron Park Dr. Interchange,

Wild Chaparral Dr. and Palmer Dr. connection (Ponderosa Rd. Interchange to Cameron Park Dr. Interchange).

Page 42: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 42SS-CP Chamber Presentation

The Board directed DOT to expand the area of interest and to look at traffic circulation as a system.

Country Club Dr

Cambridge Rd.

Alignments for illustrative purposes only

Page 43: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 43SS-CP Chamber Presentation

The Board also directed DOT to add the Wild Chaparral Dr. to Palmer Dr. connection.•

Included in the approved 2010 CIP;

This connection will require an environmental analysis in the future;

There is no other source of revenues to pay for it so DOT is exploring having the cost added to the TIM Fee Program–

Current estimate is about $9.1M (does not include R/W);

DOT will include this in the evaluation as a stand-alone alternative, as well as in combination with other components where it makes sense.

Page 44: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 44SS-CP Chamber Presentation

The Board was clear that they did not want DOT to undertake a large,

expensive evaluation at this time, nor did they want DOT to whittle down

the alternatives without the Board’s participation.

Page 45: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 45SS-CP Chamber Presentation

Proposed Evaluation Timeline and Process:•

May –

July: Working with subject matter experts (e.g.,

Economic Development Coordinator, Caltrans) define/refine Evaluation Measures and refine definitions of alternatives; add new alternatives if appropriate–

Review with the Public (e.g., members from this group)

Review with the Board•

July –

Sept: Evaluate Alternatives (Matrix –

level evaluation)

and recommend subset for further evaluation–

Review with the Public (e.g., members from this group)

Review with the Board•

Oct –

Jan: Do Detailed Evaluation on a viable subset of

alternatives (i.e., 3 –

5) and make recommendation–

Review with the Public (e.g., members from this group)

Review with the Board

Page 46: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 46SS-CP Chamber Presentation

DOT’s Project Team:•

Darryl Brown, Senior Civil Engineer and Project Manager–

Phone: (530) 621 –

5920

Email: [email protected]

Rupa Somavarapu, Supervising Civil Engineer–

Phone: (916) 358 –

3639

Email: [email protected]

Craig McKibbin, Deputy Director of Transportation Planning and Land Development–

Phone: (530) 621 –

5914

Email: [email protected]

Jim Ware, Director of Transportation–

Phone: (530) 621-7533

Email: [email protected]

Page 47: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 47SS-CP Chamber Presentation

DOT wants lots of public feedback on this project:

Who?–

This group

Board of Realtors–

Cameron Park CSD

Cameron Park Visioning Committee–

Public Workshop

????

Page 48: 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010  · hills sp boundary (gp125) ... hollow oak drainage (72369) f1. f3. f4. f5. f6. last updated

May 19, 2010 48SS-CP Chamber Presentation

QUESTIONS???