2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010 · hills sp...
Transcript of 2010 West Slope Road/Bridge Capital Improvement Program (CIP) …€¦ · 19-05-2010 · hills sp...
2010 West Slope Road/Bridge Capital Improvement Program
(CIP) for Cameron Park & Shingle Springs
Prepared for the Shingle Springs–Cameron Park Chamber of Commerce
May 19, 2010
This presentation can be found at http://www.edcgov.us/DOT/index.html
May 19, 2010 2SS-CP Chamber Presentation
Purpose for this Presentation:
•
Provide an update on–
DOT projects planned in the Cameron Park and Shingle Springs area
–
The Cameron Park Drive Interchange Project
•
Answer questions.
May 19, 2010 3SS-CP Chamber Presentation
•
Background
•
Projects Planned in Shingle Springs, Cameron Park Area
•
Overview of the 2010 CIP
•
Cameron Park Drive Interchange
Agenda
May 19, 2010 4SS-CP Chamber Presentation
CIP Purpose and Background•
The Board of Supervisors annually adopts the CIP and provides direction to DOT.
•
The purpose of the CIP is to provide strategic direction regarding DOT’s capital project priorities over a 10 to 20 year horizon:–
20 year horizon for road improvement projects–
5 to 10 year horizon for all other projects.
•
DOT updates the CIP annually as new information becomes available regarding priorities, funding sources, design alternatives, project cost estimates and timing.
•
CIP projects are prioritized based on a number of factors such as safety, capacity, traffic circulation patterns, level of service (LOS) requirements, available funding, and economic development needs.
May 19, 2010 5SS-CP Chamber Presentation
•
Background
•
Projects Planned in Shingle Springs, Cameron Park Area
•
Overview of the 2010 CIP
•
Cameron Park Drive Interchange
Agenda
May 19, 2010 6SS-CP Chamber Presentation
DOT plans to make major CIP investments in the Shingle Springs/Cameron Park area over the next 20 years; examples include:
Durock
Rd / Business Dr Signalization
U.S. 50/HOV Lanes (Bass Lake Rd to Ponderosa Rd)
Durock
Rd Widening –
Robin Ln
to S. Shingle Rd
Ponderosa Rd Interchange
Cameron Park Dr Interchange
Cambridge Rd Interchange
May 19, 2010 7SS-CP Chamber Presentation
EAST EL DORADO HILLS, WEST CAMERON PARK PROJECTS IN PROCESS OR PROPOSED
─
US HWY 50/BASS LAKE RD – INTERCHANGE IMPROVEMENTS PH 1 AND 2
(71330, GP148)
─ US HWY 50/HOV LANE BASS LAKE GRADE TO CAMERON PARK DR (53113)
─ BASS LAKE RD – FULL IMPROVEMENTS PHASE 1A (66109)
─ BASS LAKE RD WIDENING – US HWY 50 TO SILVER SPRINGS PKWY PH 1B (GP166)
─ BASS LAKE RD – FRONTAGE IMPROVEMENTS AT SILVER SPRINGS PKWY (66115)
─
SILVER SPRINGS PKWY TO GREEN VALLEY RD – NORTH SEGMENT AND
SIGNALIZATION (76107)
─ SILVER SPRINGS PKWY TO BASS LAKE RD – SOUTH SEGMENT (76108)
─ GREEN VALLEY RD WIDENING – DEER VALLEY RD EAST TO LOTUS RD (GP179)
─
GREEN VALLEY RD AT DEER VALLEY RD – WEST INTERSECTION IMPROVEMENTS
(76114)
─ GREEN VALLEY RD WIDENING – SALMON FALLS TO DEER VALLEY RD (GP159)
─ COUNTRY CLUB DR EXTENSION – BASS LAKE RD TO SILVER DOVE RD (GP124)
─
COUNTRY CLUB DRIVE EXTENSION – SILVER DOVE RD TO WEST BASS LAKE
HILLS SP BOUNDARY (GP125)
─
COUNTRY CLUB DR EXTENSION – BASS LAKE RD TO EAST BASS LAKE HILLS SP
BOUNDARY (GP126)
─ HOLLOW OAK DRAINAGE (72369)
F1
F3
F4
F5
F6
Last updated 05/17/2010
SILVA VALLEY PKWY
SERRANO PKWY
US HWY 50
BASS LAK
E RO
AD
F7
F8
F9
F10
F12
F13
F14
GREEN VALLEY RD
HOLLOW OAK D
R
COUNTRY CLUB DR
F1
F2
F3
F4
F5
F6
F7
F14
F8
F9
F10
F13F12
BASS LAKE AREAEDC C.I.P. PROJECTS
F2
Legend: In Process, Active Proposed xx
F11
F11
CAMBRIDGE RD
May 19, 2010 8SS-CP Chamber Presentation
CAMERON PARK / SHINGLE SPRINGS PROJECTS IN PROCESS OR PROPOSED
SERRANO PKW
Y
─ US HWY 50 / CAMBRIDGE RD INTERCHANGE IMPROVEMENTS PHASE 1 (71332)
─ US HWY 50 / CAMBRIDGE RD INTERCHANGE IMPROVEMENTS PHASE 2 (GP149)
─ CAMERON PARK DR WIDENING – DUROCK RD TO COACH LN (72367)
─ DUROCK RD WIDENING – ROBIN LN TO SOUTH SHINGLE RD (GP171)
─ DUROCK RD / BUSINESS DR SIGNALIZATION (73354)
─ US HWY 50 / PONDEROSA RD INTERCHANGE – N. SHINGLE RD REALIGNMENT (71339)
─
US HWY 50 / PONDEROSA RD / S. SHINGLE RD – INTERCHANGE IMPROVEMENTS
(71333)
─ US HWY 50 / PONDEROSA RD INTERCHANGE – DUROCK RD REALIGNMENT (71338)
─ PONDERSOSA RD WIDENING – N. SHINGLE RD TO MEDER RD (GP175)
─ US WHY 50 HOV LANES PHASE 2B – CAMERON PARK DR TO PONDEROSA RD (53122)
─ US HWY 50 HOV LANES PHASE 3 – PONDEROSA RD TO GREENSTONE RD (53116)
─ US HWY 50 / CAMERON PARK DR INTERCHANGE IMPROVEMENTS PHASE 1 (72361)
─ US HWY 50 AUXILARY LANES EB – CAMBRIDGE RD TO PONDEROSA RD (GP150)
─ GREEN VALLEY RD – TENNESSEE CREEK BRIDGE REPLACEMENT (77109)
─ GREEN VALLEY RD – CAMERON PARK DR INTERSECTION IMPROVEMENTS (73150)
─ US HWY 50 HOV LANES PHASE 2A – BASS LAKE RD TO CAMERON PARK DR (53113)
─ CAMERON PARK DR WIDENING – PALMER DR TO MEDER RD (GP144)
─ PALMER DR TO WILD CHAPARRAL DRIVE CONNECTION (71365)
F1
F2
F3
F4
F5
F6
F7
F8
F9
F10
F11
F12
F13
F14
F15
F16
F1F2
F6
F7F8
F9
F10
F11
F12F13
F14
F15
F16
F17
CAMERON PARK DRIVE
CAMBRIDGE ROAD
GREEN VALLEY RD
NO
. SHIN
GLE R
OA
D
DUROCK ROAD
PONDEROSA
ROAD
MEDER ROAD
SO. S
HING
LE R
OAD
CAMBRIDGE RD TO PONDEROSA RDEDC C.I.P. PROJECTS
F3
F4 F5U.S. HWY 50
CAMERON PARK
F17
Legend: In Process, Active Proposed xx
Last updated 05/17/2010
F18
F18
May 19, 2010 9SS-CP Chamber Presentation
•
Background
•
Projects Planned in Shingle Springs, Cameron Park Area
•
Overview of the 2010 CIP
•
Cameron Park Drive Interchange
Agenda
May 19, 2010 10SS-CP Chamber Presentation
53110
53113*2019
US 50 HOV Lane Phase 2A
Bass Lake Grade to Cameron Park Dr
*2011
US 50 HOV Lanes Phase 1
El Dorado Hills Blvd to Bass Lake Grade
53116*Beyond 2019
US 50 HOV Lane Phase 3
Ponderosa Rd to Greenstone Rd
*PROPOSED COMPLETION YEAR from 2010 CIP
*Beyond 2019
US 50 HOV Lane Phase 2B
Cameron Park Dr to Ponderosa Rd
53122
There are 4 HOV Lane Projects:
May 19, 2010 11SS-CP Chamber Presentation
Current Status on HOV Lane Projects:•
Phase 1 (EDH
Blvd. to Bass Lake Grade) may be extended* due to savings, and is still planned for completion in 2011;
•
Fast-track timing for Phases 2A and 2B was dependent on being awarded a Federal TIGER grant–
DOT made the short list for the TIGER grant (~$20M)–
However, DOT learned in Feb: not selected this round–
Therefore, Phase 2A (Bass Lake Grade to Cameron Park Dr.) is currently planned for completion in 2019, and
–
Phase 2B (Cameron Park Dr. to Ponderosa Rd.) is planned for completion beyond 2019;
•
Phase 3 (Ponderosa Rd. to Greenstone Rd.): No change from 2009 CIP; planned for completion beyond 2019.
* Contingent upon CTC approval
May 19, 2010 12SS-CP Chamber Presentation
Timing of construction of Cameron Park Dr. and Ponderosa Rd. Interchanges:•
Cameron Park Dr. Interchange is included in the CIP at the current estimate of $58.7M.–
Due to the expanded set of alternatives that DOT will analyze over the next several months, it is uncertain if the estimate will remain that high.
•
Both the Ponderosa Rd. and Cameron Park Dr. Interchanges are not expected to be constructed for several years.–
Both rely on a dramatic increase in residential permit activity before then.
•
DOT expects that between now and next year’s CIP, there will be updates to the timing and cost estimates for both interchanges, as more information becomes available.
May 19, 2010 13SS-CP Chamber Presentation
72361**
72367**
*2014/2019
US 50/Cameron Park Dr
Interchange Improvements
*2014/2019
Cameron Park Dr Widening
Durock Rd to Coach Ln
GP144
*Beyond 2019
Cameron Park Widening
Palmer Dr to Meder Rd
*2014/2019
Durock Rd Widening
Robin Ln to S. Shingle Rd
GP171 73354
*2010/2011
Durock Rd at Business Dr
Intersection Signalization
*PROPOSED COMPLETION YEAR GP150
*Beyond 2019
US 50 Auxiliary Lane
Eastbound from Cambridge Rd to Ponderosa Rd
Cameron Park Dr Interchange Projects:
** CURRENTLY UNDER REVIEW
71365
*Beyond 2019
Palmer Dr to Wild Chaparral Dr Connection
May 19, 2010 14SS-CP Chamber Presentation
GP175
GP171
73354
71338
Beyond 2019
Ponderosa Rd Widening
N. Shingle Rd to Meder Rd
2012/2013
US 50/Ponderosa Rd Interchange
Durock
Rd Realignment
2014/2019
Durock Rd Widening
Robin Ln to So. Shingle Rd2010/2011
Durock Rd/Business Dr
Intersection Signalization
71339
2012/2013
US 50/Ponderosa Rd Interchange
No. Shingle Rd Realignment
71333
2014/2019
US 50/Ponderosa Rd/So. Shingle Rd Interchange Improvements
*PROPOSED COMPLETION YEARProposed Ponderosa Interchange Projects:
GP150
Beyond 2019
US 50 Eastbound Auxiliary Lanes
Cambridge Rd to Ponderosa Rd
May 19, 2010 15SS-CP Chamber Presentation
Timing of Ponderosa Rd Interchange projects are all dependent on available funding:
•
Planning for 71333, including 71338 and 71339, is underway now and the environmental document is targeted for certification
by the end of this year
•
71339: N. Shingle Rd Realignment–
Includes realignment of approx. ¼
mile of N. Shingle Rd about 600 ft. north of Ponderosa Rd, realignment of the WB off-ramp with Wild Chaparral Dr, and signalization
•
71338: Durock
Rd Realignment–
Includes realignment of approx. ¼
mile of Durock
Rd and signalization of the new intersection
•
GP171: Durock
Rd Widening–
Includes widening of Durock
Rd from Robin Ln
to S. Shingle Rd including a 2-way left turn lane
•
71333: the Ponderosa Rd overcrossing
is planned to be widened to 5 lanes and includes ramp widenings
May 19, 2010 16SS-CP Chamber Presentation
•
Background
•
Projects Planned in Shingle Springs, Cameron Park Area
•
Overview of the 2010 CIP
•
Cameron Park Drive Interchange
Agenda
May 19, 2010 17SS-CP Chamber Presentation
Current Situation:•
On January 25, 2010, DOT provided the Board of Supervisors with an update on the U.S. 50/Cameron Park Dr Interchange projects.
•
The current CIP projects for the Cameron Park Drive Interchange and associated projects, may impact many existing residences and businesses and total $68M.
•
Other alternatives have been analyzed but have similar impacts and costs.
•
Additional alternatives have not been fully analyzed, but they may not meet Level of Service (LOS) requirements or receive Caltrans’
approval, but they could impact
fewer businesses/residences and cost less.
May 19, 2010 18SS-CP Chamber Presentation
ALT. 0. $0M DO NOTHING
•
PROS:–
No out of pocket cost –
No right of way impacts–
General Plan allows portion to operate at LOS F*
–
Supervisors could vote (4/5th) to allow LOS F
•
CONS:–
Existing LOS issues at EB off–
Doesn’t meet LOS requirements based on 2025 or 2035 forecasts
–
Unknown implications of allowing LOS F*
*
*Maximum Volume to Capacity = 1.1
May 19, 2010 19SS-CP Chamber Presentation
Alt 1. $68M Current Plan: 8 Lane Cameron Park Dr (PSR Alt #1)
•
PROS:–
Maintains LOS through General Plan’s buildout forecast (2035)
–
Improves overall circulation
•
CONS:–
Expensive–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term–
Median installed at Coach Lane
For Illustrative Purposes
May 19, 2010 20SS-CP Chamber Presentation
Alt 2a. $51.4M: 7 Lane Cameron Park Dr (PSR Alt #2)
•
PROS:–
Less expensive initially–
Upgrade when needed
•
CONS:–
Approx. 10 year LOS Life–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term–
Median installed at Coach Lane
For Illustrative Purposes
PROPOSED REALIGNMENT/CONNECTION
May 19, 2010 21SS-CP Chamber Presentation
•
CONS:–
Cost undetermined–
May require other local road improvements–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term
•
PROS:–
May not require median at Coach–
Upgrade when needed–
Likely to have 20 yr LOS life
Alt 2b. $??M: 7 Lane Cameron Park Dr + other local road improvements (PSR Alt #2 + )
For Illustrative Purposes
PROPOSED REALIGNMENT/CONNECTION
May 19, 2010 22SS-CP Chamber Presentation
•
CONS:–
Unknown cost–
May not deliver enough LOS benefit–
Unknown environmental mitigation
•
PROS:–
Could be less expensive–
Provides some relief to Cam Park Dr–
Provides Parallel capacity
Alt 2c. $??M: Other local road improvements onlyFor Illustrative Purposes
May 19, 2010 23SS-CP Chamber Presentation
Alt 3. $96M: Single Point Diamond (PSR #3)
•
CONS:–
Alt 1 achieves same result with lower cost
–
More impacts to local businesses/ residences than Alt 1
–
Lowers Cam Park Dr by 7 ft -- requires pumping station (maintenance)
•
PROS:–
Eliminates left turns improving traffic flow & LOS
–
Maintains LOS through General Plan’s buildout forecast (2035)
For Illustrative Purposes
May 19, 2010 24SS-CP Chamber Presentation
•
CONS:–
Unknown LOS benefit–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term–
Median installed at Coach Lane
Alt 4a. $9.1M: Build 72367 Only – widen Cameron Park Dr from Durock to Coach
•
PROS:–
Improved capacity on this section
For Illustrative Purposes
May 19, 2010 25SS-CP Chamber Presentation
•
CONS:–
Unknown LOS benefit–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term–
Median installed at Coach Lane
Alt 4b. $??M: Build 72367 (widen Cameron Park Dr from Durock to Coach) and connect Rodeo to Robin
•
PROS:–
Improved capacity on this section
For Illustrative Purposes
May 19, 2010 26SS-CP Chamber Presentation
•
CONS:–
May not deliver enough LOS benefit–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term
Alt 4c. $??M: Make Coach one-way, widen Cameron Park Dr to 6 lanes and connect Rodeo to Robin
•
PROS:–
Improved capacity on this section
For Illustrative Purposes
May 19, 2010 27SS-CP Chamber Presentation
•
CONS:–
Unknown LOS benefit–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term
Alt 4d. $??M: Remove signal at Coach; disallow all lefts at Cam Park Dr & Coach; connect Rodeo & Robin
•
PROS:–
Improved capacity on this section–
Eliminates signal at Coach
For Illustrative Purposes
May 19, 2010 28SS-CP Chamber Presentation
Alt 5. $??M: Build 72367 and expand ramps
•
CONS:–
Unknown LOS benefit–
Likely to impact some existing properties –
Could impact property/sales tax revenues in near-term–
Median installed at Coach Lane
•
PROS:–
Improved ramp operations–
Improved capacity on this section
For Illustrative Purposes
May 19, 2010 29SS-CP Chamber Presentation
Alt 6. $9.6M+R/W+ mitigation cost: Connect Palmer to Wild Chaparral
•
PROS:–
Provides additional circulation alternative–
Parallel Highway 50 capacity–
Minimal impact to existing businesses & residences
•
CONS:–
Didn’t show much LOS benefit at the Interchange in Traffic Study
–
Unknown environmental mitigation
For Illustrative Purposes
May 19, 2010 30SS-CP Chamber Presentation
Alt 7. $??M: 7 Lanes on Cameron Park Dr now expanding to 8 lanes when needed (Starts out as PSR Alt. 2)
•
PROS:–
Less expensive to start ($51.4M)–
Upgrade when needed–
Would address LOS needs for 2025 and 2035 with expansion
•
CONS:–
Throw-away costs (retaining walls, staging costs, moving signals, intersections)
–
Median installed at Coach Lane
For Illustrative Purposes
May 19, 2010 31SS-CP Chamber Presentation
Alt 8. $??M: Diverging Diamond
•
CONS:–
Eliminated by Caltrans 8/07 for being non- standard
–
May require a larger footprint than Alt 1. and therefore more right of way
–
Unknown LOS benefit–
Not enough analysis has been done to identify all the potential impacts
•
PROS:–
Improves operations because no conflicting left turns
–
May be relatively inexpensive
–
Proven in Missouri–
May be eligible for Federal demonstration grant
–
May allow left turns from Coach
For Illustrative Purposes
May 19, 2010 32SS-CP Chamber Presentation
Alt 9. $??M: Roundabout
•
CONS:–
Will require a significantly larger footprint and therefore more right of way
–
Unknown LOS benefit–
Unknown impacts to existing businesses
–
Non-standard for Caltrans
•
PROS:–
Improves operations because no need for left turns
–
May be eligible for Federal demonstration grant
For Illustrative Purposes
May 19, 2010 33SS-CP Chamber Presentation
Alt 10. $??M: Widen Cameron Park Dr to 7 lanes
•
CONS:–
Unknown LOS benefit–
Not costed as stand-alone–
Eliminated by DOT 5/06 as incomplete solution
•
PROS:–
Improves capacity on this section
For Illustrative Purposes
May 19, 2010 34SS-CP Chamber Presentation
Alt 11. $??M: Expand ramps; move retaining walls back under Hwy 50 to allow free right from EB off-ramp.
•
CONS:–
Unknown LOS benefit•
PROS:–
Improves ramp operations
For Illustrative Purposes
Free Right
May 19, 2010 35SS-CP Chamber Presentation
Alt 12. $??M – Realign Country Club Dr.
•
CONS:–
Unknown LOS benefit–
Eliminated by DOT 5/06 due to large R/W impacts
•
PROS:–
Relieves some congestion at westbound ramps and new Country Club
For Illustrative PurposesTO BE ABANDONED
May 19, 2010 36SS-CP Chamber Presentation
Alt 13. $??M: Move the Interchange East
Close existing ramps
Build new ramps & overcrossing;
connect to Coach
•
CONS:–
Unknown LOS benefit–
Uses up developable land–
Impacts freeway access of existing businesses–
May require additional road connections–
Will require widening/realigning of Palmer–
Unknown environmental mitigation
•
PROS:–
Relieves Cameron Park Dr–
Avoids physical impacts to existing businesses
–
No need to lengthen existing bridges–
Improves access to currently undeveloped non residential land
For Illustrative Purposes
May 19, 2010 37SS-CP Chamber Presentation
Alt. 14: $??M:“Hook” eastbound offramp to Coach/Robin:
•
PROS:–
Simple–
Would reduce congestion at the interchange & Coach
•
CONS:–
Caltrans already rejected this alternative–
May require widening of Coach leading to R/W impacts
–
R/W impacts near Robin Ln–
Unknown LOS benefit
For Illustrative Purposes
May 19, 2010 38SS-CP Chamber Presentation
Alt. 14: Site of “Hook” eastbound offramp from Hwy 50:
May 19, 2010 39SS-CP Chamber Presentation
ALTER-
NATIVE #
NAME COSTCameron Park Dr and Coach Ln POTENTIAL
RIGHT OF WAY COSTS/
IMPACTS
OTHER
IMPACTSLOS PM Peak Hour
in 2015
LOS PM Peak Hour
in 2025
LOS PM Peak Hour
in 2035
0 DO NOTHING $0 F F F NO
1 CURRENT PLAN -
8 LANE CAMERON PARK DR UNDER HWY 50 (PSR #1)
$68M D N/A E $12M
2a 7 LANE CAMERON PARK DR (PSR #2) UNDER HWY 50
$51.4M E E F $12M
2b 7 LANE CAMERON PARK DR w/Other Local Road Improvements (PSR #2 +)
> $61M E E E $12M+
2c OTHER LOCAL ROAD IMPROVEMENTS ONLY
Not Costed Preliminary study shows benefits but unknown to what level
LIKELY + PLANT PRESERVE
3 SINGLE POINT DIAMOND (PSR #3) $96.3M C N/A E $20M Lower Cam Park Dr 7 ft; add Pump Stn.
4a, b, c, d WIDEN CAMERON PARK DR FROM DUROCK TO COACH +
$9.1M and up
Not Studied $6.2M
5 4a PLUS EXPAND HWY 50 RAMPS Not Costed Not Studied AT LEAST $6.2M
6 CONNECT PALMER TO W. CHAPPARAL
$9.6M + R/W cost
Preliminary study showed little benefit to making this connection alone
PLANT PRESERVE
7 7 Lanes on Cam Park Dr now expanding to 8 lanes when needed
> $51.4M D N/A E $12M Throw-away costs (e.g., retain. walls)
8 DIVERGING DIAMOND Not Costed Not Studied UNKNOWN Non Std. for Caltrans
9 ROUNDABOUT Not Costed Not Studied YES Non Std. for Caltrans
10 WIDEN CAMERON PARK DR. to 7 Lns. Not Costed Not Studied YES
11 EXPAND HWY 50 RAMPS; ALLOW FREE RIGHT FROM EB OFF-RAMP
Not Costed Not Studied YES
12 REALIGN COUNTRY CLUB Not Costed Not Studied YES
13 MOVE THE INTERCHANGE EAST Not Costed Not Studied ?, PLANT PRESERVE
14 “HOOK”
EASTBOUND OFFRAMP TO COACH, ROBIN
Not Costed Not Studied UNKNOWN Non Std. for Caltrans
DOT reviewed 14 possible alternatives with the Board:
May 19, 2010 40SS-CP Chamber Presentation
The Board directed DOT to expand its preliminary matrix by adding other important evaluation measures:
•
Impacts on economic development–
Property tax and sales tax impacts
–
Public benefits e.g.,:•
Lost time and fuel caused by delays
•
Impacts on Air Quality•
Ease of finding way back to Hwy 50;
•
Effects of Recent State Legislation i.e., SB375;
•
Define and differentiate Regional vs. Local benefits;
May 19, 2010 41SS-CP Chamber Presentation
The Board directed DOT to expand its preliminary matrix by adding other important measures for evaluation (cont.):•
Benefits of adding parallel capacity:
–
Expand area of analysis to include the Cambridge Rd. Interchange to the Ponderosa Rd. Interchange –
look
at the area as a system to include:
•
Rodeo Rd. connection from Cameron Park Dr. to the Cambridge Rd. Interchange,
•
Country Club Dr. connection from the Cambridge Rd. Interchange to the Cameron Park Dr. Interchange,
•
Wild Chaparral Dr. and Palmer Dr. connection (Ponderosa Rd. Interchange to Cameron Park Dr. Interchange).
May 19, 2010 42SS-CP Chamber Presentation
The Board directed DOT to expand the area of interest and to look at traffic circulation as a system.
Country Club Dr
Cambridge Rd.
Alignments for illustrative purposes only
May 19, 2010 43SS-CP Chamber Presentation
The Board also directed DOT to add the Wild Chaparral Dr. to Palmer Dr. connection.•
Included in the approved 2010 CIP;
•
This connection will require an environmental analysis in the future;
•
There is no other source of revenues to pay for it so DOT is exploring having the cost added to the TIM Fee Program–
Current estimate is about $9.1M (does not include R/W);
•
DOT will include this in the evaluation as a stand-alone alternative, as well as in combination with other components where it makes sense.
May 19, 2010 44SS-CP Chamber Presentation
The Board was clear that they did not want DOT to undertake a large,
expensive evaluation at this time, nor did they want DOT to whittle down
the alternatives without the Board’s participation.
May 19, 2010 45SS-CP Chamber Presentation
Proposed Evaluation Timeline and Process:•
May –
July: Working with subject matter experts (e.g.,
Economic Development Coordinator, Caltrans) define/refine Evaluation Measures and refine definitions of alternatives; add new alternatives if appropriate–
Review with the Public (e.g., members from this group)
–
Review with the Board•
July –
Sept: Evaluate Alternatives (Matrix –
level evaluation)
and recommend subset for further evaluation–
Review with the Public (e.g., members from this group)
–
Review with the Board•
Oct –
Jan: Do Detailed Evaluation on a viable subset of
alternatives (i.e., 3 –
5) and make recommendation–
Review with the Public (e.g., members from this group)
–
Review with the Board
May 19, 2010 46SS-CP Chamber Presentation
DOT’s Project Team:•
Darryl Brown, Senior Civil Engineer and Project Manager–
Phone: (530) 621 –
5920
–
Email: [email protected]•
Rupa Somavarapu, Supervising Civil Engineer–
Phone: (916) 358 –
3639
–
Email: [email protected]•
Craig McKibbin, Deputy Director of Transportation Planning and Land Development–
Phone: (530) 621 –
5914
–
Email: [email protected]•
Jim Ware, Director of Transportation–
Phone: (530) 621-7533
–
Email: [email protected]
May 19, 2010 47SS-CP Chamber Presentation
DOT wants lots of public feedback on this project:
•
Who?–
This group
–
Board of Realtors–
Cameron Park CSD
–
Cameron Park Visioning Committee–
Public Workshop
–
????
May 19, 2010 48SS-CP Chamber Presentation
QUESTIONS???