2009 08 05 BC Hydro 2009 Mica Gas Insulated Switchgear ... Hydr… · Mica Gas Insulated Switchgear...
Transcript of 2009 08 05 BC Hydro 2009 Mica Gas Insulated Switchgear ... Hydr… · Mica Gas Insulated Switchgear...
BChydro mFOR GENE 100\JS
Joanna SofieldChief Regulatory OfficerPhone: (604) 623-4046Fax: (604) 623-4407bchyd [email protected]
August5,2009
Ms. Erica M. HamiltonCommission SecretaryBritish Columbia Utilities CommissionSixth Floor - 900 Howe StreetVancouver, BC V6Z 2N3
Dear Ms. Hamilton:
RE: British Columbia Utilities Commission (BCUC)British Columbia Hydro and Power Authority (BC Hydro)Mica Gas Insulated Switchgear Project
BC Hydro encloses its application filed pursuant to section 44.2(1 )(b) of the UtilitiesCommission Act, seeking a BCUC Order accepting that the expenditures associated with theMica Gas Insulated Switchgear Project are in the public interest.
BC Hydro proposes to hold a workshop on August 20, 2009 as the first step of the regulatoryreview process.
All communications with respect to the application should be directed to:
Ms. Joanna SofieldChief Regulatory OfficerBC Hydro333 Dunsmuir Street, 17th FloorVancouver, BC V6B 5R3Telephone No. (604) 623-4046Fax No. (604) 623-4407
E-Mail: [email protected]
and to:
Ms. Nicole PriorLegal CounselBC Hydro333 Dunsmuir Street, 17th FloorVancouver, BC V6B 5R3Telephone No. (604) 623-3692Fax No. (604) 623-3606
British Coiumbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3www.bchydro.com
B-1
August5,2009Ms. Erica M. HamiltonCommission SecretaryBritish Columbia Utilities CommissionMica Gas Insulated Switchgear Project
For further information, please contact Lyle McClelland at 604-623-4306.
Yours sincerely,
~£///Joanna SofieldChief Regulatory Officer
Enclosure (1)
BChydro
Page2 of2
c. BCUC Project No. 3698500 (BCHydro F2009/F2010 Revenue Requirements Application)Registered Intervenor Distribution List.
First Nations and Tribal Councils identified for consultation (per Table 5-1 of the application)
Mica Gas Insulated Switchgear Project
i
Table of Contents
Chapter 1. INTRODUCTION 1.1 Introduction .......................................................................................................................1-1 1.2 B.C. Government Energy Policy........................................................................................1-1 1.3 Revenue Requirement and Service Plan Cost Estimates .................................................1-1 1.4 Project Highlights ..............................................................................................................1-2
1.4.1 Mica Generating Station Description.......................................................................1-2 1.4.2 Project Description ..................................................................................................1-2 1.4.3 Project Schedule .....................................................................................................1-3
1.5 Project Justification ...........................................................................................................1-3 1.5.1 Need........................................................................................................................1-4 1.5.2 Project Benefits .......................................................................................................1-4 1.5.3 Cost-Effectiveness ..................................................................................................1-4
1.6 Public and First Nations Consultation ...............................................................................1-5 1.7 Order Sought.....................................................................................................................1-5 1.8 Proposed Review and Application Process.......................................................................1-6 1.9 Structure of the Application ...............................................................................................1-6
Chapter 2. APPLICANT 2.1 Name, Address and Nature of Business ...........................................................................2-1
2.2 Financial and Technical Capacity of the Applicant..................................................2-1 2.2.1 Financial Capacity ...................................................................................................2-1 2.2.2 Technical Capacity ..................................................................................................2-1
2.3 Project Delivery Governance.............................................................................................2-2
Chapter 3. PROJECT DESCRIPTION AND IMPACTS 3.1 Project Description ............................................................................................................3-1
3.1.1 Description of Mica..................................................................................................3-1 3.1.2 Project Description ..................................................................................................3-4 3.1.3 Project Components................................................................................................3-9
3.2 Project Schedule .............................................................................................................3-10 3.3 Project Costs ...................................................................................................................3-13
3.3.1 Construction Costs ................................................................................................3-13 3.3.1.1 Contingency/Risk Allowance: ........................................................................3-14 3.3.1.2 Mica Units 5 and 6 Equipment.......................................................................3-16
3.3.2 Operating, Maintenance and Outage Costs ..........................................................3-16 3.3.3 Planned Outage Costs and Risks .........................................................................3-16 3.3.4 Non-BC Hydro Project Related Capital Costs .......................................................3-17
3.4 Project Life Cycle ............................................................................................................3-17 3.5 Construction Market Impacts...........................................................................................3-18
Mica Gas Insulated Switchgear Project
ii
3.6 Social and Environmental Impacts ..................................................................................3-18 3.6.1 Environmental Assessment Approvals..................................................................3-18 3.6.2 Federal Permits, Approvals and Authorizations ....................................................3-19 3.6.3 Provincial Permits, Approvals and Authorizations.................................................3-19 3.6.4 Municipal Bylaws...................................................................................................3-19 3.6.5 SF6 Management ..................................................................................................3-20 3.6.6 Columbia River Water Use Plan............................................................................3-20
3.7 Analysis of Estimated Rate Impact..................................................................................3-21
Chapter 4. PROJECT JUSTIFICATION 4.1 Introduction .......................................................................................................................4-1 4.2 Need for the Project ..........................................................................................................4-1
4.2.1 Reliability and Outage Risk .....................................................................................4-2 4.2.2 Life Cycle Asset Management.................................................................................4-3 4.2.3 GIS Condition Assessment .....................................................................................4-5
4.2.3.1 Independent Condition Assessment Reports ..................................................4-5 4.2.3.2 BC Hydro Condition Assessment Conclusions................................................4-7 4.2.3.3 Condition Assessment Summary ..................................................................4-13
4.3 Identification of Project Benefits ......................................................................................4-13 4.3.1.1 Disconnect Switches .....................................................................................4-14 4.3.1.2 Maintenance Access .....................................................................................4-14
4.3.2 Environmental Benefits .........................................................................................4-17 4.3.3 Benefit to Mica Units 5 and 6 ................................................................................4-18
4.4 Architecture Evaluation and Selection.............................................................................4-18 4.4.1 Problem Scope and Architecture Options .............................................................4-19 4.4.2 Architecture Conclusions.......................................................................................4-21 4.4.3 Holm, Hampton and Heil Recommended Architectures........................................4-22
4.5 Timing and Sequencing of GIS Replacement .................................................................4-23 4.5.1 Timing of GIS Replacement ..................................................................................4-23 4.5.2 Planned Outage Requirements for Alternatives ....................................................4-25 4.5.3 Sensitivity Analysis for Mica Units 5 and 6 ISDs ...................................................4-29 4.5.4 Recommended Project Scope...............................................................................4-33
Chapter 5. PUBLIC AND FIRST NATIONS CONSULTATION 5.1 Introduction .......................................................................................................................5-2 5.2 General Consultation.........................................................................................................5-2
5.2.1 Environmental Assessment.....................................................................................5-2 5.2.2 Core Committee ......................................................................................................5-3 5.2.3 Future Public Consultation ......................................................................................5-4
5.3 First Nations Consultation .................................................................................................5-4 5.3.1 Identification of Interested First Nations ..................................................................5-5 5.3.2 Expected First Nation Impacts ................................................................................5-6
Mica Gas Insulated Switchgear Project
iii
5.3.3 First Nation Consultation Activities..........................................................................5-7 5.3.4 Presentation of Project at Core Committee Meeting ...............................................5-8 5.3.5 Project Notification Letter from BC Hydro ...............................................................5-8 5.3.6 Project BCEAO Amendment ...................................................................................5-9 5.3.7 Future First Nation Consultation Plan ...................................................................5-10 5.3.8 Adequacy of First Nations Consultation ................................................................5-10
Chapter 6. PROJECT RISKS AND RISK MANAGEMENT 6.1 Introduction .......................................................................................................................6-1 6.2 Definition Phase Risks ......................................................................................................6-1
6.2.1 Investment at Risk...................................................................................................6-1 6.2.2 Environmental Regulatory .......................................................................................6-2 6.2.3 First Nations ............................................................................................................6-2
6.3 Implementation Phase Risks.............................................................................................6-3 6.3.1 Safety Risks ............................................................................................................6-3 6.3.2 Security Risk ...........................................................................................................6-5 6.3.3 Capital Cost Risk.....................................................................................................6-5 6.3.4 Schedule Risk During Construction.........................................................................6-6 6.3.5 Risk of Labour Unrest during Construction .............................................................6-7 6.3.6 Congestion in the Mica Powerhouse during Construction.......................................6-8 6.3.7 Environmental Risk during Construction .................................................................6-8 6.3.8 SF6 Risk During Construction..................................................................................6-9 6.3.9 Contractor Credit/Counterparty Default...................................................................6-9 6.3.10 Commissioning Risk..............................................................................................6-10
6.4 Operations Risks.............................................................................................................6-10 6.4.1 Failure and Outage Risk........................................................................................6-10 6.4.2 Environmental Risk ...............................................................................................6-10 6.4.3 Operating and Maintenance Costs........................................................................6-11
6.5 Risk Summary.................................................................................................................6-11
Mica Gas Insulated Switchgear Project
iv
List of Figures
Chapter 1. INTRODUCTION Figure 1-1 Project Schematic...............................................................................................1-3
Chapter 2. APPLICANT Figure 2-1 EARG Functional Organization Chart.................................................................2-3 Figure 2-2 Project Organization Structure ...........................................................................2-4
Chapter 3. PROJECT DESCRIPTION AND IMPACTS Figure 3-1 Columbia/Kootenay Area Generation.................................................................3-2 Figure 3-2 Mica Underground Powerhouse .........................................................................3-3 Figure 3-3 Mica Dam Showing Planned Switchgear Building Extension .............................3-3 Figure 3-4 GIS in Transformer Gallery for Single Generating Unit ......................................3-5 Figure 3-5 GIS Bus in Lead Shaft ........................................................................................3-6 Figure 3-6 Cut-away of GIS Bus ..........................................................................................3-6 Figure 3-7 GIS Conducts High Voltages in the Powerhouse ...............................................3-7 Figure 3-8 Original Design of Mica GS included Three Lead Shafts Running to
Switchgear Building ............................................................................................3-8 Figure 3-9 Project Schedule ..............................................................................................3-11 Figure 3-10 Annual Rate Impact ..........................................................................................3-22
Chapter 4. PROJECT JUSTIFICATION
Figure 4-1 Bus Cone Insulator ...........................................................................................4-10 Figure 4-2 Condition Assessment Summary .....................................................................4-13 Figure 4-3 Repair of Surge Arrestor under Existing GIS Layout........................................4-15 Figure 4-4 Height of Existing GIS ......................................................................................4-16 Figure 4-5 Improved GIS Layout........................................................................................4-17 Figure 4-6 Mica GIS Ultimate Layout.................................................................................4-22 Figure 4-7 Reliability Realization from Staging Lead Shaft 3 First.....................................4-27
Mica Gas Insulated Switchgear Project
v
List of Tables
Chapter 3. PROJECT DESCRIPTION AND IMPACTS Table 3-1 Project Stages ..................................................................................................3-12 Table 3-2 Project Cost ......................................................................................................3-14 Table 3-3 Total Contingencies and Reserves...................................................................3-15
Chapter 4. PROJECT JUSTIFICATION Table 4-1 Analysis of GIS by Component.........................................................................4-11 Table 4-2 PV of Replacement Alternatives.......................................................................4-24 Table 4-3 Replacement of Lead Shaft 1 and 2 with or without Lead Shaft 3 in Place......4-28 Table 4-4 Sensitivity Analysis for Meeting Alternative Mica Units 5 and 6 ISD ................4-32
Chapter 5. PUBLIC AND FIRST NATION CONSULTATION Table 5-1 First Nations and Tribal Councils Identified for Consultation..............................5-6
Chapter 6. PROJECT RISKS AND RISK MANAGEMENT
Table 6-1 Mica Project Risks Summary............................................................................6-11
Mica Gas Insulated Switchgear Project
vi
List of Appendices
Appendix A Glossary and Key Assumptions
Appendix B Draft Order
Appendix C Project Schedule
Appendix D Project Lifecycle and Project Cost Estimating
Appendix E Condition Assessment Reports
Appendix F Mica Gas Insulated Switchgear Capital Expenditures
Appendix G Most Severe Single Contingency
Appendix H Lead Shaft Requirements for Mica with Four to Six Units
Appendix I GIS Replacement Alternative Assumptions
Appendix J First Nations Consultation Record
Appendix K B.C. Environmental Assessment Act Order
Mica Gas Insulated Switchgear Project
Chapter
1
Introduction
Mica Gas Insulated Switchgear Project
1-i
Table of Contents
1.1 Introduction.................................................................................................................1-1
1.2 B.C. Government Energy Policy .................................................................................1-1
1.3 Revenue Requirement and Service Plan Cost Estimates ..........................................1-1
1.4 Project Highlights........................................................................................................1-2
1.4.1 Mica Generating Station Description ..............................................................1-2
1.4.2 Project Description..........................................................................................1-2
1.4.3 Project Schedule.............................................................................................1-3
1.5 Project Justification.....................................................................................................1-3
1.5.1 Need ...............................................................................................................1-4
1.5.2 Project Benefits...............................................................................................1-4
1.5.3 Cost-Effectiveness ..........................................................................................1-4
1.6 Public and First Nations Consultation.........................................................................1-5
1.7 Order Sought ..............................................................................................................1-5
1.8 Proposed Review and Application Process................................................................1-6
1.9 Structure of the Application.........................................................................................1-6 List of Figures
Figure 1-1 Project Schematic ........................................................................................1-3
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-1
1.1 Introduction 1
This application (the Application), filed pursuant to section 44.2(1)(b) of the Utilities 2
Commission Act (UCA), contains a schedule of capital expenditures that British Columbia 3
Hydro and Power Authority (BC Hydro) anticipates making for the Mica Dam and 4
Generating Station (Mica) 500 kilovolt (kV) Gas Insulated Switchgear (GIS) Project (the 5
Project). BC Hydro seeks, per section 44.2(3)(a) of the UCA, that the British Columbia 6
Utilities Commission (BCUC) accepts that the expenditures referred to in the schedule of 7
capital expenditures are in the public interest. 8
In considering whether the expenditures are in the public interest, according to 9
section 44.2(5) of the UCA the BCUC must consider: the Government’s energy objectives; 10
BC Hydro’s most recent long term resource plan; whether the expenditure schedule is 11
consistent with section 64.01 and 64.02 of the UCA in respect of electricity self-sufficiency 12
and clean and renewable resources; and the interests of present and future ratepayers. 13
1.2 B.C. Government Energy Policy 14
The Project is consistent with Policy Action Item #17 of the British Columbia (B.C.) 15
Government’s updated energy policy, “The BC Energy Plan: A Vision for Clean Energy 16
Leadership”, (2007 Energy Plan) regarding investment in upgrading and maintaining the 17
heritage facilities and transmission lines to retain the ongoing competitive advantage these 18
assets provide to the Province. 19
1.3 Revenue Requirement and Service Plan Cost Estimates 20
BC Hydro’s F2009 and F2010 Revenue Requirements Application (F09/F10 RRA) Capital 21
Plan (Exhibit B-1) and the 2009/2010 to 2011/2012 Service Plan estimated that the cost for 22
the replacement of the Mica 500 kV GIS would fall within a range of cost of 23
$120 million - $300 million (Exhibit B-1, Appendix J page 36 of 120). Since the time of these 24
previous estimates, the scope of the Project has been finalized. The F09/F10 RRA stated 25
“we are also considering replacing the transformers at the same time.” Further investigation 26
showed that the unit transformers are in fair condition and they were, therefore, removed 27
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-2
from the Project’s scope of work. The Project Expected Cost1 of $180.6 million and 1
Authorized Cost of $200.2 million are in the project cost estimate range provided in 2
BC Hydro’s F09/F10 RRA and the 2009/2010 to 2011/2012 Service Plan. 3
1.4 Project Highlights 4
1.4.1 Mica Generating Station Description 5
Mica is located on the Columbia River approximately 130 kilometres (km) upstream from the 6
Revelstoke Dam and Generating Station (Revelstoke), and 135 km upstream of the City of 7
Revelstoke. Mica accounts for roughly 17 per cent of BC Hydro's current installed capacity. 8
The large storage capacity at Mica Dam, the Kinbasket reservoir, enables BC Hydro to 9
serve domestic load during high demand periods and store water in light load periods or to 10
maximize export earnings for ratepayers by generating at peak value periods and storing 11
water at low value periods. 12
The Mica powerhouse contains the four generating units, Mica Units 1 through 4 and is 13
located underground, 200 meters (m) below the dam crest. Electricity is generated by 14
Mica Units 1 through 4 at 16 kV and transformed to 500 kV in single-phase transformers 15
located in the transformer chamber at Mica. The 500 kV electricity then flows through the 16
GIS which runs through lead shafts2 to the switchgear building located at the dam crest 17
200 m above. From the switchgear building, the 500 kV electricity flows into the transmission 18
system operated by British Columbia Transmission Corporation (BCTC). 19
Refer to Chapter 3 for further details on Mica and GIS. 20
1.4.2 Project Description 21
With the exception of the recently replaced circuit breakers in the switchgear building, the 22
Project will replace, with modern GIS technology, all the existing GIS at Mica. In addition, 23
the Project includes the installation of GIS to lead shaft 3. To accommodate the GIS in lead 24
shaft 3, the switchgear building will be extended as part of the Project because lead shaft 3 25
1 Refer to Appendix D-2 for an explanation of Expected and Authorized Costs. 2 At Mica the three lead shafts are tunnels of approximately 3 m in diameter that lead from the transformer
chamber through bedrock to the switch gear building.
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-3
currently terminates outside of the switchgear building. Figure 1-1 is a schematic showing 1
the Mica GIS equipment before and after the Project. 2
Figure 1-1 Project Schematic 3
Not in the scope of this project
Style Legend
Not In Scope
Replace
Remain
Lead
Sha
ft
Lead
Sha
ft
G1
T1
500 kV16 kV
Pow
erho
use
Sw
itchg
ear B
uild
ing
Circuit Breaker
Disconnect Switch
Transformer
Generator
Surge Arrester
Transmission Line
Reactor
5L71 5L72
G2
T2
G3
T3
G4
T4
G5
T5
G6
T6Le
ad S
haft
New
1.4.3 Project Schedule 4
BC Hydro is of the view that it is in the interest of ratepayers to proceed with the Project as 5
soon as possible, and has framed the Application around a June 2013 Project completion 6
date. Refer to Chapter 3 and Appendix C for more details on the Project schedule. 7
1.5 Project Justification 8
The existing GIS is more than 30 years old and poses the risk of forced outages to 9
BC Hydro. The purpose of the Project is to mitigate the risk of forced outages. 10
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-4
1.5.1 Need 1
The GIS at Mica was the first 500 kV GIS installed in North America. BC Hydro understands 2
that Mica may have the last GIS equipment of this vintage in North America. As a result, 3
there are no spare parts for surge arrestors, spare parts for disconnect switches have limited 4
availability and BC Hydro has only about 30 m of spare bus. 5
Three independent condition assessments were carried out on the GIS (attached in 6
Appendix E). The condition assessments were consistent in that they recommended that 7
BC Hydro address the reliability issues of the GIS. One of the risk assessments concluded 8
that the risk of simultaneous multiple outages of Mica Units 1 through 4 as a result of GIS 9
failure could be as high as one in ten years. 10
1.5.2 Project Benefits 11
The purpose of the Project is to maintain the reliability of Mica; however, the Project 12
provides additional safety and environmental benefits. Refer to Chapter 4 for more details 13
on the Project benefits. 14
1.5.3 Cost-Effectiveness 15
The replacement of the GIS at Mica is cost-effective when compared to deferring 16
replacement or replacing using different configurations. The Project is attractive because it: 17
maintains the reliability of the Mica; 18
reduces sulphur hexafluoride3 (SF6) leakage; 19
reduces safety risks to workers; and 20
allows BC Hydro to achieve the earliest in-service date (ISD) for Mica Units 5 and 6 of 21
F2014 and F2016 as per BC Hydro’s 2008 Long-Term Acquisition Plan Application 22
(2008 LTAP) contingency resource plans (CRPs). 23
3 GIS contains SF6, an extremely good electrical insulator; however SF6 is also a potent greenhouse gas
(GHG).
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-5
For further details on the Project justification refer to Chapter 4. 1
1.6 Public and First Nations Consultation 2
BC Hydro has undertaken consultation with First Nations and public stakeholders to identify 3
issues specific to the Project. BC Hydro expects the Project will have minimal, if any adverse 4
impacts since it is within the Mica generating station or on previously disturbed ground and 5
has no impact on the Kinbasket or Revelstoke reservoirs. Taking into consideration the 6
factors listed in section 5.3.8, BC Hydro is of the view that the consultation conducted for the 7
Project is adequate. BC Hydro will continue to update First Nations and public stakeholders 8
during the implementation phase of the Project. 9
Details of the consultation that has taken place are in Chapter 5 while a full consultation 10
record with First Nations is provided in Appendix J. 11
1.7 Order Sought 12
BC Hydro is applying for a BCUC order that accepts that this expenditure schedule to 13
complete the Project is in the public interest according to subsection 44.2(3)(a) of the UCA. 14
BC Hydro is targeting a completion date of June 2013 with a Project Expected Cost of 15
$180.6 million and a Project Authorized Cost of $200.2 million. 16
BC Hydro intends to file with the BCUC quarterly progress reports on the Project schedule, 17
costs and any variances or difficulties that the Project may be encountering. The form and 18
content of the quarterly progress reports will be consistent with other BC Hydro capital 19
project quarterly reports filed with the BCUC. Within six months of the end or substantial 20
completion of the Project BC Hydro will file a final report. The final report will include a 21
complete breakdown of the final costs of the Project, a comparison of these costs to the 22
Project Expected Cost estimate and provide an explanation of all material cost variances. 23
As directed per BCUC Letter No. L-78-06, BC Hydro has included in Appendix B of the 24
Application a draft final order. 25
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-6
1.8 Proposed Review and Application Process 1
BC Hydro proposes a written hearing process consisting of: 2
Application Filed 3
Application filed on Wednesday, August 5, 2009. 4
Workshop 5
A BC Hydro workshop on the Application on Thursday, August 20, 2009. 6
Information Request (IRs) 7
BCUC IRs issued by Tuesday, August 25, 2009; 8
BC Hydro responds to BCUC IRs on Tuesday, September 15, 2009. 9
BCUC Round 2 and Intervenors IRs issued by Tuesday, September 22, 2009; 10
BC Hydro responds to BCUC and Intervenor IRs on Tuesday, October 13, 2009. 11
Written Submissions/Reply 12
BC Hydro final written submission by Tuesday, October 20, 2009; 13
Intervenors final written submissions by Tuesday, October 27, 2009; and 14
BC Hydro written reply by Tuesday, November 3, 2009. 15
To meet the June 2013 ISD, BC Hydro is filing the Application with the expectation that the 16
proposed process will support a BCUC order being granted by no later than the end of 17
December 2009. 18
1.9 Structure of the Application 19
The Application consists of six chapters. It has been structured to comply with the BCUC’s 20
March 2004 CPCN Application Guidelines (Letter No. L-18-04). 21
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-7
Chapter 2 contains information on BC Hydro including the Project team. 1
Chapter 3 contains a detailed description of the Project, including costs and schedule and 2
rate impact. 3
Chapter 4 details the justification, including the need for the Project, the benefits, and 4
alternatives. 5
Chapter 5 details the First Nations, public and government agency consultations conducted 6
by BC Hydro. 7
Chapter 6 identifies the various risks to the Project. 8
Appendix A-1 is a glossary of terms and acronyms and Appendix A-2 provides key financial 9
assumptions used in this Application. 10
Appendix B contains a draft of the requested final order for the Project. 11
Appendix C sets out the schedule for the completion of the Project. 12
Appendix D-1 sets out BC Hydro’s standard project life cycle for large generation projects 13
and Appendix D-2 provides a summary of BC Hydro’s project cost estimating practices for 14
large generation projects. 15
Appendix E contains the three condition assessment reports of the Mica GIS. 16
Appendix F provides the Project capital expenditures. 17
Appendix G is a letter from BCTC related to its most severe single contingency (MSSC) 18
limits. 19
Appendix H is an explanation of the lead shaft requirements for Mica. 20
Appendix I is a summary of the assumptions for GIS replacement alternatives and options. 21
Chapter 1 - Introduction
Mica Gas Insulated Switchgear Project
1-8
Appendix J-1 is BC Hydro’s First Nations consultation log for the Project, Appendix J-2 1
contains the notification letter. Appendix J-3 contains BC Hydro’s core committee 2
presentation material for the project. 3
Appendix K-1 contains a letter to the British Columbia Environmental Assessment Office 4
(BCEAO) requesting the removal of the switchgear building extension from the British 5
Columbia Environmental Assessment Certificate (BCEAC) review. Appendix K-2 is a copy 6
of the notice from the BCEAO seeking First Nations comments regarding BC Hydro’s 7
request and Appendix K-3 is the BCEAO Order removing the Switchgear Building extension 8
from the BCEAC Review. 9
Mica Gas Insulated Switchgear Project
Chapter
2
Applicant
Mica Gas Insulated Switchgear Project
2-i
Table of Contents
2.1 Name, Address and Nature of Business.....................................................................2-1
2.2 Financial and Technical Capacity of the Applicant .....................................................2-1
2.2.1 Financial Capacity...........................................................................................2-1
2.2.2 Technical Capacity..........................................................................................2-1
2.3 Project Delivery Governance......................................................................................2-2 List of Figures
Figure 2-1 EARG Functional Organization Chart ..........................................................2-3
Figure 2-2 Project Organization Structure.....................................................................2-4
Chapter 2 Applicant
Mica Gas Insulated Switchgear Project
2-1
2.1 Name, Address and Nature of Business 1
BC Hydro is a Crown Corporation established in 1962 under the Hydro and Power Authority 2
Act. BC Hydro is mandated to generate, distribute and sell electricity; upgrade its power 3
sites; and purchase power from, or sell power to, a firm or person. BC Hydro is the largest 4
electric utility in B.C., serving over 94 per cent of the provincial population. 5
BC Hydro’s head office is located at 333 Dunsmuir Street, Vancouver, B.C. 6
2.2 Financial and Technical Capacity of the Applicant 7
2.2.1 Financial Capacity 8
BC Hydro is an agent of Her Majesty the Queen in right of the Province of B.C. The 9
B.C. Minister of Finance is the fiscal agent of BC Hydro. BC Hydro has constructed some of 10
the largest projects in the Province undertaken by a single corporation and has the financial 11
capacity to undertake the Project and other large projects by means of: borrowing 12
guaranteed by the Province, borrowing directly from the Province, and by funds generated 13
internally from the operation of its business. 14
Moody’s Investors Service and Standard & Poor’s Corporation, two major financial rating 15
agencies in the United States of America (U.S.), have rated BC Hydro bonds as Aaa and 16
AAA respectively. The rating from the Dominion Bond Rating Service in Canada is at 17
AA High. 18
2.2.2 Technical Capacity 19
BC Hydro has been responsible for the planning, design and construction of generation and 20
distribution facilities since 1962. BC Hydro was also responsible for these functions with 21
respect to the transmission system until 2003. In 2003, BCTC was formed. Under the 22
Transmission Corporation Act and a number of designated agreements between BC Hydro 23
and BCTC, BCTC currently has the responsibility to operate, plan and manage the 24
BC Hydro-owned transmission system. BC Hydro currently owns and operates 25
30 grid-connected hydroelectric generating stations within the Province. The existing GIS at 26
Chapter 2 Applicant
Mica Gas Insulated Switchgear Project
2-2
Mica was put into service in 1976. The GIS in the switchgear building is under BCTC 1
management but is in the process of being transferred back to BC Hydro. 2
BC Hydro has a proven track record in implementing capital projects at BC Hydro’s 3
generation facilities. In recent years BC Hydro designed, constructed and commissioned 4
into service the Seven Mile Generating Station (Seven Mile GS) gas insulated switchgear 5
replacement project and is in the process of adding gas insulated switchgear to support the 6
addition of the fifth unit at Revelstoke. The contractor, Mitsubishi Electric Power Products 7
Inc. (MEPPI), which supplied and installed the gas insulated switchgear for both the 8
Revelstoke and Seven Mile GS gas insulated switchgear projects, was also awarded the 9
design, supply and install contract for the Project. These projects have provided BC Hydro 10
and MEPPI with experience and technical knowledge that will benefit the Project. 11
The Seven Mile GS gas insulated switchgear replacement project was completed on time 12
and on budget. The addition of gas insulated switchgear to support Revelstoke Unit 5 is 13
currently projected to be completed on time and on budget. 14
Along with MEPPI and BC Hydro staff working on the Project, BC Hydro has retained the 15
services of specialized consultants to advise on various aspects of the Project. For example, 16
BC Hydro has retained SNC-Lavalin Group Inc. to design the switchgear building extension 17
and MWH Canada Inc for project management advice. BC Hydro commissioned 18
independent condition assessment reports of the GIS (refer to Appendix E) by Mr. Bjorn 19
Holm, Dr. Brian Hampton, and Rohe International Inc. 20
2.3 Project Delivery Governance 21
Figure 2-1 is a functional organization chart of the Engineering, Aboriginal Relations and 22
Generation (EARG) business group that is accountable for the delivery of the Project. 23
Chapter 2 Applicant
Mica Gas Insulated Switchgear Project
2-3
Figure 2-1 EARG Functional Organization Chart 1
Chris O’Riley, a senior vice-president, leads the EARG line of business. David Lebeter, who 2
reports directly to Chris O’Riley, leads the EARG generation operations group. This group is 3
responsible for operating and maintaining the plants in the fleet, as well as asset and capital 4
planning and for initiating EARG projects. The generation operations group also directly 5
delivers some of the smaller projects in BC Hydro’s capital plan. Diane McSherry, another 6
direct report to Chris O’Riley, leads EARG generation project delivery group. This group is 7
accountable for delivery of the majority of the EARG projects in BC Hydro’s capital plan. 8
Other functional groups in EARG such as Engineering, Aboriginal Relations and 9
Negotiations (ARN), and Safety and Technical Training provide personnel to staff projects; 10
those individuals are accountable to the project manager for the purposes of the project. 11
The Project organization chart is provided as Figure 2-1. 12
Safety & TechnicalTraining
Diana Cochran
Finance
Gurj Parmar
Senior Vice-President- Chris O’Riley
Generations Operations
David Lebeter
Generation ProjectDelivery
Diane McSherry
Aboriginal Relations & Negotiations
Lyle Viereck
Human Resources
Terry Schumaker
Engineering
Roy Grout
Chapter 2 Applicant
Mica Gas Insulated Switchgear Project
2-4
Figure 2-2 Project Organization Structure 1
Project InitiatorDavid Lebeter
Project ManagerOwen Williams
Construction Mgr.Bill Hanson
Aboriginal RelationsRyan McFadden
EnvironmentalDavid Wilson
Project Sponsor Chris O’Riley
Communications Jeanette Hoft
Estimating & SchedulingKelman Ng
Reg. Env. Stakeholder
CommunicationsDeb Bisson
Contract Mgr.Clement Terragni
Project Engineer/Design Lead
Damien Clapa
Commercial Mgr.Alan Tan
Director, Generation Project DeliveryDiane McSherry
Project DirectorKen McKenzie
BC Hydro EARG projects are led by a project manager who is accountable to a project 2
initiator and to a portfolio project director. The project manager leads the project team to 3
complete the objectives of the project and is accountable to the project initiator for the 4
definition (statement of objectives, original and revisions) and justification (original and 5
revised business case) of the project. The project initiator defines the problem or opportunity 6
that requires a project to be initiated. The project manager, representing the project team, 7
proposes a set of objectives (statement of objectives) to address the problem or opportunity 8
and a plan to achieve those objectives. Approval of the proposed objectives by the project 9
initiator defines the project to be delivered. The same concept applies to the business case. 10
The project manager is accountable to the portfolio project director for delivery of the project 11
in accordance with the approved definition of the project. In other words, the project 12
manager is accountable for determining how the project will be delivered, including delivery 13
models, procurement strategies, obtaining resources, obtaining all permits and regulatory 14
approvals, putting contracts in place, and managing to the plan to achieve the agreed 15
objectives. 16
Chapter 2 Applicant
Mica Gas Insulated Switchgear Project
2-5
Chris O’Riley, senior vice-president of EARG is the project sponsor (Project Sponsor) of 1
this Project and is responsible for supporting the success of the Project by acting as liaison 2
with BC Hydro’s executive team and approving key decisions. David Lebeter, the Director of 3
Generation Operations, is project initiator (Project Initiator) and is accountable to the 4
Project Sponsor for the definition and the justification of the Project, while Diane McSherry, 5
the Director of Generation Project Delivery, is accountable to the Project Sponsor for 6
delivery of the Project. The Director of Finance, Gurj Parmar, is accountable to the Project 7
Sponsor and BC Hydro’s Executive Vice President and Chief Financial Officer for financial 8
due diligence for the Project. 9
Additional information on BC Hydro’s project lifecycle and project cost estimating practices is 10
contained in Appendix D. 11
Mica Gas Insulated Switchgear Project
Chapter
3
Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-i
Table of Contents
3.1 Project Description......................................................................................................3-1
3.1.1 Description of Mica .........................................................................................3-1
3.1.2 Project Description..........................................................................................3-4
3.1.3 Project Components .......................................................................................3-9
3.2 Project Schedule.......................................................................................................3-10
3.3 Project Costs ............................................................................................................3-13
3.3.1 Construction Costs........................................................................................3-13
3.3.1.1 Contingency/Risk Allowance:................................................................3-14
3.3.1.2 Mica Units 5 and 6 Equipment ..............................................................3-16
3.3.2 Operating, Maintenance and Outage Costs..................................................3-16
3.3.3 Planned Outage Costs and Risks .................................................................3-16
3.3.4 Non-BC Hydro Project Related Capital Costs...............................................3-17
3.4 Project Life Cycle......................................................................................................3-17
3.5 Construction Market Impacts ....................................................................................3-18
3.6 Social and Environmental Impacts ...........................................................................3-18
3.6.1 Environmental Assessment Approvals .........................................................3-18
3.6.2 Federal Permits, Approvals and Authorizations............................................3-19
3.6.3 Provincial Permits, Approvals and Authorizations ........................................3-19
3.6.4 Municipal Bylaws ..........................................................................................3-19
3.6.5 SF6 Management ..........................................................................................3-20
3.6.6 Columbia River Water Use Plan ...................................................................3-20
3.7 Analysis of Estimated Rate Impact ...........................................................................3-21 List of Figures
Figure 3-1 Columbia/Kootenay Area Generation ..........................................................3-2
Figure 3-2 Mica Underground Powerhouse ..................................................................3-3
Figure 3-3 Mica Dam Showing Planned Switchgear Building Extension.......................3-3
Figure 3-4 GIS in Transformer Gallery for Single Generating Unit................................3-5
Figure 3-5 GIS Bus in Lead Shaft .................................................................................3-6
Figure 3-6 Cut-away of GIS Bus ...................................................................................3-6
Figure 3-7 GIS Conducts High Voltages in the Powerhouse ........................................3-7
Figure 3-8 Original Design of Mica GS included Three Lead Shafts Running to Switchgear Building .....................................................................................3-8
Figure 3-9 Project Schedule........................................................................................3-11
Figure 3-10 Annual Rate Impact ...................................................................................3-22
Mica Gas Insulated Switchgear Project
3-ii
List of Tables
Table 3-1 Project Stages............................................................................................3-12
Table 3-2 Project Cost ...............................................................................................3-14
Table 3-3 Total Contingencies and Reserves ............................................................3-15
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-1
3.1 Project Description 1
3.1.1 Description of Mica 2
Mica is located on the Columbia River about 130 km upstream from Revelstoke, and 135 km 3
upstream of the City of Revelstoke (refer to Figure 3-1). Mica consists of an earth-filled dam, 4
an underground powerhouse, which contains generating units 1 through 4 and a switchgear 5
building (refer to Figure 3-2 and Figure 3-3). When constructed, the Mica powerhouse was 6
built to accommodate two additional generating units, Mica Units 5 and 6. Mica Dam forms 7
the Kinbasket reservoir, which extends 10 km to the confluence of the Columbia Reach, the 8
Wood Arm, and the Canoe Reach. From this confluence Kinbasket reservoir extends 9
120 km along the Columbia Reach to Donald and 95 km along the Canoe Reach to 10
Valemount. 11
Mica Dam was built under the terms of the Columbia River Treaty ratified by Canada and 12
the U.S. in 1964. Kinbasket and Arrow reservoirs are principal components of the Columbia 13
River Treaty and are governed by operating plans between B.C. and U.S. entities. Within 14
the constraints of these operating plans Mica and Revelstoke are key generating resources 15
that are operated with flexibility to follow BC Hydro system load and support trade 16
opportunities. Because of its size (1,805 megawatts (MW)), Mica is valued for the operating 17
flexibility it provides to the BC Hydro system as a whole. 18
Mica and Revelstoke together comprise 37 per cent of BC Hydro’s capacity. BC Hydro is 19
generally able to operate Kinbasket reservoir and Revelstoke reservoir to generate more 20
electricity at the times of the day when the load is greatest. The large storage capacity in the 21
Kinbasket reservoir and the synchronous condense ability at Mica and Revelstoke, allow 22
BC Hydro to take advantage of fluctuations in market prices. BC Hydro can import electricity 23
at times when it is cheaper than the value placed on the stored water and meanwhile store 24
that water for use and sale when demand and market prices are high. 25
Kinbasket and Revelstoke reservoirs are key swing reservoirs that allow BC Hydro to 26
effectively manage instantaneous demand for electricity as well as providing ancillary 27
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-2
services4 to the electric grid. Mica and Revelstoke are operated in balance with operations 1
on the Peace River system at GM Shrum Generating Station (at the Bennett dam) and 2
Peace Canyon Generating Station. For instance, Mica and Revelstoke are critical in 3
balancing generation when GM Shrum Generating Station is required to reduce its 4
generation to lower the risk of flooding in the town of Peace River, located in Alberta on the 5
Peace River, during ice freeze-up in the fall and ice break-up in the spring. 6
Figure 3-1 Columbia/Kootenay Area Generation 7
Definitions DDM – Duncan Dam HLK – Hugh Keenleyside KCL – Kootenay Canal MCA – Mica REV – Revelstoke SEV – Seven Mile Small Generation ABF – Aberfeldie ELK – Elko SHU – Shuswap SPN – Spillimacheen WGS – Whatshan WHN – Walter Hardman
4 These services include operating and spinning reserve, voltage support, black start, Voltage amps reactive
(VAR) compensation and rotating energy.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-3
Figure 3-2 Mica Underground Powerhouse 1
Figure 3-3 Mica Dam Showing Planned Switchgear 2 Building Extension 3
Existing Switchgear & Office Building
Switchgear Building extension
Dam face
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-4
3.1.2 Project Description 1
The Mica powerhouse is underground, approximately 200 m below the dam crest. The 2
technology used to conduct the electricity out of the underground powerhouse to the 3
transmission network is 500 kV GIS. The GIS runs from the 500 kV (high-voltage) side of the 4
single-phase transformers through the lead shafts to the switchgear building. Figure 3-4 5
shows the GIS configuration in the transformer chamber from the three single-phase 6
transformers of one generating unit to the GIS entering a lead shaft. The glossary, found in 7
Appendix A explains the function of the bus, disconnect switches, circuit breakers and surge 8
arrestors identified in Figure 3-4. 9
GIS is used at three BC Hydro generating stations and a number of BCTC managed 10
substations because of its unique electrical insulating properties. SF6, the insulating gas 11
used in GIS, provides extremely good electrical insulation and effectively quenches electric 12
arcs. These properties of SF6 make it possible to build electrical equipment that is very 13
compact and safe. Figure 3-5 shows the close proximity of three phases of 500 kV GIS bus 14
in a lead shaft. Figure 3-6 shows a cut-away of GIS bus which includes an inside conductor 15
supported by an epoxy bus cone insulator within an outer SF6 enclosure. Workers are able 16
to safely stand beside GIS without risk of electrical contact (refer to Figure 3-7). SF6 is the 17
only feasible technology for 500 kV disconnect switches, surge arrestors and circuit 18
breakers. 19
As Mica was originally designed to accommodate six units, three lead shafts were 20
constructed (refer to Figure 3-8). However, only four generating units and the GIS bus 21
associated with these generating units, including GIS in two of the three lead shafts, was 22
installed. As a result, Mica currently does not have GIS in lead shaft 3. 23
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-5
Figure 3-4 GIS in Transformer Gallery for Single 1 Generating Unit 2
500 kV GISDisconnect Switches
3 -500kV Single Phase TransformersPer Generator
16kV Circuit Breakers
500kV GIS Surge
Arrestors
500kV Gas Insulated Bus
16kV Iso-Phase bus
Bus up lead shaft 200 meters to surface and to switchgear building
From Turbines and Generators
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-6
Figure 3-5 GIS Bus in Lead Shaft 1
Figure 3-6 Cut-away of GIS Bus 2
Conductor Bus Cone Insulator
Outer Enclosure
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-7
Figure 3-7 GIS Conducts High Voltages in the Powerhouse 1
The scope of the Project is to replace, with modern GIS technology, the existing 500 kV GIS 2
at Mica and install GIS in lead shaft 3. 3
The switchgear building houses the interface between the GIS and the transmission system. 4
This includes the termination of lead shafts 1 and 2, disconnect switches, circuit breakers 5
and bus. The switchgear building will be extended to house the termination of the lead 6
shaft 3 and the associated disconnect switches, circuit breakers and bus. The switchgear 7
building extension will also provide a clean, protected working area necessary during the 8
installation of GIS.5 9
A partial mezzanine6 and overhead crane will be added to the transformer chamber to 10
improve the operability and maintainability of the new GIS. Additionally, the mezzanine and 11
5 It is critical that no particles or impurities enter the GIS bus on installation. This is to prevent flash over failure
when energized or gradual degradation and eventual failure due to partial discharge. 6 The partial mezzanine are the platforms which support access to the disconnect switches and some of the
main bus in the transformer chamber.
GIS Bus
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-8
overhead crane will reduce the cost to remove the existing equipment and install the new 1
GIS7. The new GIS in the switchgear building will be more accessible than the current 2
design. 3
Figure 3-8 Original Design of Mica GS included Three Lead 4 Shafts Running to Switchgear Building 5
7 Based on the 1984 repair at Mica, a faulted bus section in a lead shaft can be expected to take between
one and three months to repair depending on the location of the fault, the phase of bus affected and the availability of skilled workers and supervisors.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-9
3.1.3 Project Components 1
The Project will result in a complete upgrade of all original GIS at Mica. In addition, the 2
Project includes the installation of GIS required to put lead shaft 3 into service. Specifically, 3
the Project includes the design, supply and installation of: 4
3,500 m of single phase gas insulated bus; 5
66 (22 sets of 3) disconnect switches; 6
three (one set of three) circuit breakers; 7
18 (six sets of three) surge arrestors; 8
an overhead crane in the transformer chamber; 9
a partial mezzanine in the transformer chamber; 10
a new lift8 for lead shaft 3 and upgrades to the lifts in lead shafts 1 and 2; 11
upgrades to fire protection, auxiliary mechanical systems, electrical infrastructure and 12
miscellaneous civil improvements to support the new equipment; 13
an extension of approximately 560 square metres to the switchgear building and related 14
heating, ventilation and air conditioning (HVAC), electrical and fire protection systems; 15
and 16
protection and control (P&C) for GIS. 17
The circuit breakers in the switchgear building which were replaced by BCTC9 in 2008 due 18
to reliability problems are not required to be replaced. 19
8 The lift is a small inclined geared elevator, also referred to as a funicular. 9 Equipment in the switchgear building, under BCTC management, is being transferred to BC Hydro’s control.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-10
3.2 Project Schedule 1
The Project will be implemented in stages over four years. The first step is the construction 2
of an extension to the switchgear building. The switchgear building extension will house an 3
extended bus, circuit breakers and disconnect switches that connect lead shaft 3 bus to the 4
existing switchgear equipment. The Switchgear building extension work is expected to be 5
complete by March 2010. 6
The GIS equipment required to put lead shaft 3 into service will be installed next. This will 7
reduce the risk of a forced outage as lead shaft 3 will be available prior to and during the 8
replacement of bus in lead shafts 1 and 2. 9
The existing GIS will be replaced over two years, two units at a time. In 2011 the GIS 10
serving Mica Units 3 and 4 will be replaced. A four month outage of Mica Units 3 and 4 is 11
required from March to July in 2011. In 2012, the GIS serving Mica Units 1 and 2 will be 12
replaced. A four-month outage of Mica Units 1 and 2 is required from March to July in 2012. 13
The Project includes civil work, lead shaft lift installation and upgrades, and nine stages of 14
major activities as shown in Figure 3-9 and Table 3-1. A detailed Project schedule is 15
provided in Appendix C. 16
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-11
Figure 3-9 Project Schedule 1
Mica Switchgear Project 1
Mica Switchgear Project Schedule July 09 –Dec 09
Lead Shaft 3
Jan 10 –Jun 10
Jun 10 –Dec 10
Jan 11 –Jun 11
Jan 12 –Jun 12
Jun 12 –Dec 12
Jan 13 –Jun 13
Stage 1
Stage 2
Stage 3
Jun 11 –Dec 11
Design & Manufacture
Stage 4
Stage 5
Stage 6
Stage 7
Stage 8
Stage 9
RingSwitchgear Building Ring Extension
Lead Shaft 3
InterfaceInterface existingGIS to Lead Shaft 3
Unit 3 & 4Mica Units 3 & 4
RingSwitchgear BuildingRing Bus
Units 1 & 2Mica Units 1 & 2
RingSwitchgear BuildingRing Bus
Lead Shaft 2 LS 2
Lead Shaft 1 LS 1
Completion Completion
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-12
Table 3-1 Project Stages 1
Stage Location Description Start of Work End of Work
Non-GIS Work
Switchgear building Addition of 560 square meters to Switchgear building to house termination of lead shaft 3.
September 2009 March 2010
Lead Shaft Lifts
Lead Shafts 1 - 3 Upgrade lifts in lead shafts 1 and 2. Add lift to lead shaft 3.
May 2010 August 2010
GIS Work
1 Install GIS support structures in Lead Shaft 3
Install bus, GIS support structures, and gas monitoring systems for lead shaft 3 GIS
October 2010 December 2010
2 Switchgear Building Ring Extension
Install disconnects, ground switches, gas monitoring, GIS support systems required to operate and connect lead shaft 3 to existing GIS in switchgear building
October 2010 January 2011
3 Install GIS equipment in Lead Shaft 3
Install disconnects, surge arrestors, gas monitoring and interface between existing equipment and lead shaft 3 in transformer chamber. Includes crane and mezzanine over this section of the chamber.
October 2010 January 2011
4 Mica Units 3 and 4 GIS Replacement
Replace disconnects, surge arrestors and connecting bus on Mica Units 3 and 4 in transformer chamber. Extend crane and mezzanine and all GIS support structures for this section of transformer chamber.
March 2011 May 2011
5 Switchgear Building - Transmission Line to Reactor
Replace all existing original disconnects, air bushing and bus between Transmission Line Air Bushing 5L71 to Reactor 5RX4 in switchgear building including Return bus.
(Excludes circuit breakers replaced by BCTC in 2008.)
April 2011 June 2011
6 Mica Units 1 and 2 GIS Replacement
Replace disconnects, surge arrestors and connecting bus on Mica Units 1 and 2 in transformer chamber. Extend crane and mezzanine and all GIS support structures for this section of transformer chamber.
March 2012 July 2012
7 Switchgear Building to Lead Shaft 2
Replace all existing original GIS between Air Bushing 5L72 and Reactor 5RX3.
March 2012 July 2012
8 Lead Shaft 2 Replace with new GIS equipment in lead shaft 2. Upgrade skip and gas monitoring systems.
August 2011 January 2012
9 Lead Shaft 1 Replace with new GIS equipment in lead shaft 1. Upgrade skip and gas monitoring systems.
August 2012 December 2012
Project Close Complete documentation, manuals and maintenance instructions.
June 2013
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-13
3.3 Project Costs 1
3.3.1 Construction Costs 2
The Expected Cost for the Project is $180.6 million -10 per cent/+15 per cent (range from 3
$163 million to $208 million) and the Authorized Cost for the Project is $200.2 10million (refer 4
to Table 3-2). This estimate includes the Project costs to date, all management, engineering 5
and design costs, the cost to supply and install all equipment, the cost of the switchgear 6
building extension, an allowance for overhead, interest during construction (IDC), costs for 7
regulatory and permitting approvals, inflation adjustments and a contingency. 8
Cost certainty has been increased by tendering the Project early. On March 26, 2009, 9
BC Hydro received three competitive bids in response to an open tender for the design, 10
supply and installation of the GIS. A fixed price contract was awarded to MEPPI for a base 11
value of $42 million. The contract represents about 60 per cent of the total amounts to be 12
contracted for this Project or 43 per cent of the direct construction costs. As a result, a 13
significant portion of the direct construction costs are defined, limiting the potential for future 14
cost increases.15
10 Appendix F contains the capital expenditure schedule for the Project.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-14
Table 3-2 Project Cost 1
PROJECT COMPONENT AMOUNT ($ million)
Direct Construction Cost $ 94.6 Project Management and Engineering 18.8
Sub-total: Construction Cost before Contingency (Note 1) $113.4 Contingency on Expected Cost 11.3 Dismantling and Removal 1.0 Inflation and Escalation (Note 2 ) 8.4
Sub-total: Implementation Phase Cost (Direct) $134.1 Capital Overhead (Note 3) 17.7 Interest During Construction (Note 4) 21.3
Sub-total: Implementation Phase Cost (Loaded) $173.1
Identification and Definition Phase (loaded) 7.5 Total Expected Cost $180.6
Project Reserve (Note 5) 19.6 Total Authorized Cost (note 6) $200.2
Notes: 2 1. The construction cost before contingency includes allowances for other supporting items such as P&C, 3
HVAC, and Fire Protection equipment. 4 2. Inflation and escalation rates used are five per cent and four per cent in F2010 and F2011 respectively, and 5
three per cent in F2012 and beyond. 6 3. Capital overhead is 13.3 per cent of the direct Implementation phase cost excluding dismantling and 7
removal. 8 4. An IDC rate of 6.52 per cent is applied to the sum of the direct Implementation phase cost and corporate 9
overhead accumulated in each year. 10 5. The Project reserve is the sum of the management reserve and the additional contingency in the Authorized 11
Cost above the contingency in the Expected Cost (refer to section 3.3.1.1 for further details on 12 contingencies). 13
6. On May 22, 2009, BC Hydro’s Board of Directors approved the project with an authorized cost of 14 $238 million for implementation. Subsequently, with the award of the MEPPI contract, the authorized cost 15 has been reduced to $200.2 million. 16
3.3.1.1 Contingency/Risk Allowance: 17
Contingencies have been assigned to take into account the uncertainties and risks identified 18
during the Project Identification and Definition phases. Contingencies are estimated based 19
on the total construction costs. 20
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-15
The Expected Cost includes a contingency of $11.3 million (unloaded) while the Authorized 1
Cost includes additional contingencies of $11.3 million. Inflation, capital overhead and IDC 2
are applied to contingencies such that there is a total contingency of $32.2 million (loaded) 3
included in the Authorized Cost. The contingency for the Expected Cost and Authorized 4
Cost are based on range estimating methods in developing a Monte Carlo risk analysis. 5
Refer to Appendix D-2 for a description of BC Hydro’s cost estimating practices. 6
Table 3-3 provides a more detailed breakdown of the Project contingency and reserves. 7
Table 3-3 Total Contingencies and Reserves 8
$ millions
Description Total Contingency on
Expected and Authorized Costs
Project Reserve Project Cost
Project Expected Cost A $180.6 Contingency included in Expected Cost B $11.3
Inflation, escalation and loadings on Contingency included in Expected Cost (Note 1)
C $4.8
Incremental Contingency on Authorized Cost D $11.3
Inflation, escalation and loadings on Incremental Contingency included in Authorized Cost (Note 1)
E $4.8
Total Contingency included in Project Authorized Cost B+C+D+E $32.2
Total Incremental Contingency included in Authorized Cost F=D+E $16.1
Management Reserve (Note 2) G $3.5 Authorized Project Reserve H=F+G $19.6 $19.6 Project Authorized Cost A+H $200.2
Notes: 9 1. Loadings on contingency include capital overhead and interest during construction. 10 2. Management reserve is requested to allow for additional snow removal costs, accommodation allowances 11
and contract claims. 12
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-16
3.3.1.2 Mica Units 5 and 6 Equipment 1
The supply and installation of six of 18 (two out of the six sets) surge arrestors and related 2
bus11 is for the yet to be installed Mica Units 5 and 6. It is estimated that the loaded cost of 3
these six surge arresters and related bus is approximately $2 million. These six surge 4
arrestors are being installed as part of the Project to ensure operating instructions and spare 5
parts will be the same throughout Mica. In the event Mica Units 5 and 6 do not proceed, the 6
cost would be stranded. However, BC Hydro is of the view that the operational benefit 7
makes it worthwhile to commit to this relatively small expenditure at this time. 8
3.3.2 Operating, Maintenance and Outage Costs 9
There is no material change in maintenance costs expected as a result of the Project. 10
Ongoing maintenance requires two to three person days per month for inspection and 11
monitoring of the GIS and an annual inspection of each lead shaft lift. The addition of GIS 12
equipment to lead shaft 3 will increase the amount of equipment that will need monitoring 13
and inspection. However, efficiencies introduced as a result of modern monitoring, P&C 14
equipment and the easier access for inspection are expected to offset any additional costs 15
associated with the inspection and maintenance of the added equipment. 16
3.3.3 Planned Outage Costs and Risks 17
A four month outage for Mica Units 3 and 4 and a separate four month outage for 18
Mica Units 1 and 2 are scheduled in 2011 and 2012 respectively to connect the new GIS to 19
the single-phase transformers of Mica Units 1 to 4. The two outages are planned from 20
March to July of each year as this period represents the lowest average cost to BC Hydro. 21
The actual cost of the outage and the cost of possible extensions of the outage are highly 22
dependant on a number of variables including: 23
systems reservoir conditions particularly the relative storage of Kinbasket and Williston 24
reservoirs; 25
stream flow conditions; 26
11 Related bus refers to the bus extension beyond lead shaft 3 to connect Mica Unit 6 transformers and the
branches from the main bus to the Mica Units 5 and 6 transformers.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-17
market conditions; and 1
electricity demand. 2
All of these variables are highly uncertain. Heavy winter loads or high demand is less likely 3
after mid-March so outages in this time frame are preferred. One of the best indicators for 4
predicting system reservoir conditions and stream flows is the snow pack condition that 5
exists around the beginning of March. This information is evaluated to ensure that BC Hydro 6
can meet firm load and flow obligations under the Columbia River Treaty during the outage 7
period. 8
There is a risk that the Project could extend beyond the planned four month period of each 9
year. The cost of extending the planned four month outage by one month in August can vary 10
significantly from as low as $3 million to as high as $20 million. The range is based on the 11
lost export opportunity cost, Mica stream flows, Columbia Treaty obligations and Pacific 12
Northwest flow conditions. Columbia River Treaty storage is usually full in the Arrow and 13
Kinbasket reservoirs by August. Extending the planned outage because of schedule delays 14
in the Project could lead to spills at Mica. 15
3.3.4 Non-BC Hydro Project Related Capital Costs 16
There are no non-BC Hydro related capital costs. BCTC has confirmed that the Project does 17
not require any changes to the transmission system. 18
3.4 Project Life Cycle 19
The Project began in the Initiation phase with three condition assessment reports. These 20
indicated the unsatisfactory condition of a number of components of the GIS requiring 21
immediate replacement, and the eventual replacement of all GIS equipment. 22
The Identification phase began in November 2007. During the Identification phase BC Hydro 23
developed and analyzed numerous potential replacement architectures and configurations. 24
BC Hydro then recommended a specific architecture. A business case and Project plan was 25
prepared for the Definition phase. At the end of the Identification phase the Project Sponsor 26
made the decision in July 2008 to continue the Project through to the Definition phase. 27
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-18
The next phase of the Project was the Definition phase in parallel with early Implementation 1
phase work. This phase included the development of the preliminary design. It also included 2
the tendering of the GIS design, supply and install contract. 3
BC Hydro’s Board of Directors approved the Project to advance to Implementation phase on 4
May 22, 2009. The Implementation phase includes detailed design, material and equipment 5
procurement, construction, testing, and commissioning into service. The fixed price contract 6
for the GIS was awarded to MEPPI on June 15, 2009 for a base value of $42 million. The 7
Implementation phase will end with the Project Initiator acknowledging acceptance of the 8
Project results by signing the Project completion report. 9
Appendix D1 describes BC Hydro’s project life cycle. 10
3.5 Construction Market Impacts 11
The ongoing global financial crisis and current economic conditions have significantly 12
impacted the landscape in many industries. In general, circumstances are such that 13
BC Hydro is in a favourable position to proceed at this time, and in the near future, with 14
capital projects. BC Hydro does not expect material challenges to the Project related to the 15
general construction market conditions. Additionally BC Hydro now has a contract with 16
MEPPI for the design, supply and installation of the GIS. As a result MEPPI now assumes, 17
for a significant portion of the Project, any risks related of the construction market. 18
3.6 Social and Environmental Impacts 19
3.6.1 Environmental Assessment Approvals 20
The Project does not require any regulatory approval pursuant to either the B.C. 21
Environmental Assessment Act (BCEAA) or the Canadian Environmental Assessment Act 22
(CEAA). 23
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-19
Under the BCEAA, approval is not required because the Project is not a “modification” to 1
increase capacity.12 2
Under the CEAA there are no federal permits or approvals required for the Project, therefore 3
there is no requirement for a CEAA review. 4
Most of the Project work will be performed indoors, and there will be no releases or activities 5
that could affect fish bearing waters. As a result, there is no requirement for approval (or 6
authorization) for the Project under the federal Fisheries Act. 7
3.6.2 Federal Permits, Approvals and Authorizations 8
There are no federal permits, approvals or authorizations required for construction or 9
operation of the Project. 10
3.6.3 Provincial Permits, Approvals and Authorizations 11
Depending on construction methodologies there may be provincial permits or approvals 12
required for culverts to redirect natural surface drainage on the cliff above where the 13
switchgear building will be extended. 14
In accordance with the contract BC Hydro entered into with MEPPI for the supply and 15
installation of the GIS equipment and BC Hydro’s Environmental Management Plan for the 16
Project, any contractors will be required to obtain any environmental permits, licences, or 17
approvals applicable for their work. 18
3.6.4 Municipal Bylaws 19
There are no applicable municipal bylaws. 20
12 Appendix K contains the BCEAO order removing the switchgear building from the BCEAC review of
Mica Unit 5.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-20
3.6.5 SF6 Management 1
SF6 is used in three BC Hydro generating stations and at various BCTC operated 2
substations because of its electrical insulating properties. SF6 is a potent GHG: 3
1 kilogram (kg) of SF6 is equal to 23,900 kg of carbon dioxide (CO2) equivalents. The 4
current GIS at Mica leaks an excessive amount of SF6 and more significant leaks are 5
expected to develop over time as the equipment ages. In 2008, a total of 565 kg of SF6, 6
representing a leakage rate of 3.8 per cent per year, leaked at Mica. Due to the GHG 7
intensity of SF6, this amount is equivalent to 13,503 tonnes of CO2, and accounts for about 8
20 per cent of total BCTC and BC Hydro SF6 leakage. Based on the U.S. Environmental 9
Protection Agency estimates, the average passenger vehicle produces 5.2 tonnes of CO2 10
equivalents a year. Based on this, the SF6 leakage at Mica is comparable to 2,600 average 11
passenger vehicles. 12
For new GIS, the current industry standard leakage rate is 0.5 per cent per year. New GIS 13
equipment being installed in Japan and Europe is achieving leakage rates of 0.1 per cent 14
per year or less. GIS installations at Revelstoke generating station and Seven Mile GS are 15
currently achieving nearly zero losses. 16
As part of its GHG management program, BC Hydro has implemented procedures to 17
minimize SF6 releases during maintenance and operation of SF6 equipment, and to monitor 18
any releases. The contract for the design, supply and installation of the GIS equipment 19
specifies a maximum SF6 leakage rate at the industry standard level of 0.5 per cent. During 20
construction, MEPPI is required to implement SF6 tracking and management procedures 21
and standards equivalent to BC Hydro’s. MEPPI will also be required to comply with all 22
applicable federal and provincial legislation with respect to the management, storage, and 23
transportation of new and used SF6, including the monitoring of releases. Used SF6 will be 24
recycled by MEPPI. 25
3.6.6 Columbia River Water Use Plan 26
Because this Project has no effect on water flows or water levels upstream or downstream 27
of Mica, there is no impact on the Columbia Water Use Plan and no need for a 28
Project-related Addendum. 29
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-21
3.7 Analysis of Estimated Rate Impact 1
The impact that the Project would have on BC Hydro’s revenue requirements is discussed in 2
this section and the resulting estimated annual incremental rate impacts from the Project 3
with a final ISD of June 2013 at an Expected Cost of $180.6 million and an Authorized Cost 4
of $200.2 million are shown in Figure 3-10. 5
The Long Term Rate Increase Forecast (LTRIF) as filed in the 2008 LTAP13 is the starting 6
point for the analysis of the incremental revenue requirements and rate increase/decrease 7
impacts of the Project14. 8
The Project would affect the following elements of BC Hydro’s revenue requirements: 9
amortization; finance charges; and return on equity. 10
There is an initial increase to BC Hydro’s revenue requirements in the early years the 11
Project is placed into service. This annual increase, based on the Project Expected Cost, 12
would be highest in F2014 at around $19 million the first year the entire project is in-service. 13
By F2033 the annual revenue requirement would be at around $11 million based on the 14
Project Expected Cost. 15
Figure 4-8 shows the resulting estimated incremental annual rate impact of the Project, 16
relative to the overall projected annual BC Hydro rate increase forecast for a particular year 17
as estimated in the LTRIF. 18
As shown in Figure 4-8, the Project would give rise to incremental annual rate increases in 19
the beginning in F2010 as components of the Project are placed in-service. This results from 20
the initial effect of the amortization and financing costs of the Project. From F2014, there 21
would be small, but declining incremental rate increase impacts arising from the Project. 22
13 Exhibit B-3, BC Hydro response to BCUC IR 1.7.1. 14 BC Hydro reiterates that this forecast is highly uncertain and subject to significant variability depending on
the assumptions used. The forecast does not represent BC Hydro’s view as to its future revenue requirements applications, and any rate increases requested in those applications will be based on BC Hydro’s detailed assessment of its expected revenues and costs at the time of filing.
Chapter 3 - Project Description and Impacts
Mica Gas Insulated Switchgear Project
3-22
Figure 3-10 Annual Rate Impact 1
0.00%
0.10%
0.20%
0.30%
0.40%
0.50%
0.60%
2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032
Fiscal Year
Per C
ent
Expected
Approved
Mica Gas Insulated Switchgear Project
Chapter
4
Project Justification
Mica Gas Insulated Switchgear Project
4-i
Table of Contents
4.1 Introduction.................................................................................................................4-1
4.2 Need for the Project....................................................................................................4-1
4.2.1 Reliability and Outage Risk.............................................................................4-2
4.2.2 Life Cycle Asset Management ........................................................................4-3
4.2.3 GIS Condition Assessment .............................................................................4-5
4.2.3.1 Independent Condition Assessment Reports..........................................4-5
4.2.3.2 BC Hydro Condition Assessment Conclusions .......................................4-7
4.2.3.3 Condition Assessment Summary..........................................................4-13
4.3 Identification of Project Benefits ...............................................................................4-13
4.3.1.1 Disconnect Switches.............................................................................4-14
4.3.1.2 Maintenance Access.............................................................................4-14
4.3.2 Environmental Benefits .................................................................................4-17
4.3.3 Benefit to Mica Units 5 and 6 ........................................................................4-18
4.4 Architecture Evaluation and Selection ......................................................................4-18
4.4.1 Problem Scope and Architecture Options.....................................................4-19
4.4.2 Architecture Conclusions ..............................................................................4-21
4.4.3 Holm, Hampton and Heil Recommended Architectures ...............................4-22
4.5 Timing and Sequencing of GIS Replacement...........................................................4-23
4.5.1 Timing of GIS Replacement..........................................................................4-23
4.5.2 Planned Outage Requirements for Alternatives............................................4-25
4.5.3 Sensitivity Analysis for Mica Units 5 and 6 ISDs...........................................4-29
4.5.4 Recommended Project Scope ......................................................................4-33 List of Figures
Figure 4-1 Bus Cone Insulator ....................................................................................4-10
Figure 4-2 Condition Assessment Summary...............................................................4-13
Figure 4-3 Repair of Surge Arrestor under Existing GIS Layout .................................4-15
Figure 4-4 Height of Existing GIS................................................................................4-16
Figure 4-5 Improved GIS Layout .................................................................................4-17
Figure 4-6 Mica GIS Ultimate Layout ..........................................................................4-22
Figure 4-7 Reliability Realization from Staging Lead Shaft 3 First ..............................4-27
Mica Gas Insulated Switchgear Project
4-ii
List of Tables
Table 4-1 Analysis of GIS by Component ..................................................................4-11
Table 4-2 PV of Replacement Alternatives ................................................................4-24
Table 4-3 Replacement of Lead Shaft 1 and 2 with or without Lead Shaft 3 in Place.................................................................................4-28
Table 4-4 Sensitivity Analysis for Meeting Alternative Mica Units 5 and 6 ISD..........4-32
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-1
4.1 Introduction 1
Section 4.2 of this chapter explains BC Hydro’s need to replace the GIS. Section 4.3 2
describes the additional benefits that BC Hydro will realize as a result of implementing the 3
Project. Section 4.4 explains the process BC Hydro has undertaken to identify GIS as the 4
proposed architecture for the Project taking into consideration the recommendations by 5
external experts, BC Hydro’s own analysis and considering the longer term requirements of 6
a six unit Mica which requires GIS in all three lead shafts in order to transmit the full output 7
of six units. 8
In section 4.5.1, alternative GIS implementation timing and sequences for the proposed GIS 9
architecture for the Project are compared. These alternatives result in the replacement GIS 10
being fully installed at later dates than the Project schedule provided in Table 3-1, and have 11
different present values (PV) than the Project as proposed. The timing of the installation of 12
lead shaft 3 and the switchgear building is considered in the implementation timing of 13
alternatives since without the GIS in lead shaft 3, additional planned outages are required 14
leading to a later ISD for the Project. The reason for the additional planned outages is 15
discussed in section 4.5.2. Given the uncertainty of the ISDs for Mica Units 5 and 6, 16
section 4.5.3 compares the PV of the Project to other options that may be feasible if the ISD 17
for Mica Unit 5 was alternatively 2018 or 2025. These other options are sequenced 18
differently than as proposed in Chapter 3, but result in the proposed GIS architecture being 19
implemented prior to an ISD for Mica Unit 5 of 2018 or 2025. Section 4.5.4 summarizes the 20
justification for BC Hydro’s recommended Project scope. 21
4.2 Need for the Project 22
The existing GIS at Mica presents a substantial risk of forced outages to BC Hydro. The 23
GIS, which is over 30 years old, may be the last 500 kV GIS equipment of this vintage and 24
manufacturer still in operation in North America. The purpose of the Project is to mitigate this 25
risk of forced outages. 26
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-2
4.2.1 Reliability and Outage Risk 1
Mica is designated as a key facility in BC Hydro’s generation strategic asset management 2
system. Key generation facilities provide approximately 90 per cent of BC Hydro’s average 3
annual energy. BC Hydro’s F2007 Generation Strategic Asset Plan (filed as Attachment 1 to 4
the response to BCUC IR 1.5.1 (Exhibit B-11) during BC Hydro’s F07/F08 RRA), includes 5
the following objective: 6
Over the next 5 years, cost effective plans will be implemented (and completed) 7
at all large (key) facilities to refurbish or replace all equipment assessed by EHR 8
to be in “poor” or “unsatisfactory” condition or, alternatively, a strategy 9
implemented to mitigate the risk of failure of such equipment. 10
Replacement of the GIS, as described in this application, is one of the actions required to 11
meet this objective. 12
Mica supplies approximately 16 per cent of the energy and 17 per cent of the capacity for 13
BC Hydro. At Mica, the expected cost of a forced or unplanned outage in any month varies, 14
ranging from zero to over $20 million per month depending on time of year. In the event of 15
an outage, replacement energy and capacity may need to be purchased on the market at a 16
higher cost than the cost of self-generation. The costs of outages at Mica are mitigated as 17
BC Hydro can store water in the Kinbasket reservoir for future generation and income 18
earning opportunities. However, BC Hydro would incur a permanent loss of generation due 19
to an outage at Mica if BC Hydro needs to spill water at Mica to manage Kinbasket reservoir 20
levels or downstream flow requirements. 21
Currently, if all other Mica equipment is in operation, failure of the GIS in one lead shaft 22
restricts the output of Mica to 1,500 MW15 (single contingency outage). During the repair 23
period for such a failure, Mica is vulnerable to a full plant outage if a second GIS failure 24
occurs (BC Hydro does not typically design equipment to mitigate second contingency 25
failures). 26
15 The BCTC Most Severe Single Contingency (MSSC) requirement restricts the plant output which can be
connected to the transmission system through one lead shaft bus (refer to Appendix G).
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-3
Many GIS failures may result in either one or two units being out of service for an extended 1
period. In particular, the disconnect switches and the majority of bus in the transformer 2
chamber all require two unit outages for repair work to proceed. 3
One of the independent GIS experts who assessed the Mica GIS (as discussed in 4
section 4.2.3.1 below) concluded that there was a 99 per cent chance of a GIS failure within 5
ten years or, in other words, there is a 33 per cent chance of failure in each of the next ten 6
years. The risk of a GIS failure is expected to increase over time as the GIS ages. 7
4.2.2 Life Cycle Asset Management 8
BC Hydro has applied its Life Cycle Asset Management (LCAM) principles and practices in 9
its assessment of the need to replace the Mica GIS. LCAM is described further below. 10
BC Hydro is committed to managing its generation assets through the effective and efficient 11
application of the LCAM principles and practices. LCAM is used to maximize economic 12
return on physical assets over their life by achieving desired performance outcomes, while 13
effectively managing the risks inherent in owning, managing and operating a large asset 14
base. 15
LCAM considers several dimensions of business value including: safety; availability and 16
reliability; commercial performance; contribution to revenue; total unit cost of production; 17
and environmental and social performance. 18
The asset management framework enables making trade-offs amongst these value 19
dimensions, leading to optimization of business value. 20
The LCAM is used for BC Hydro’s generation assets to ensure consistency in decision-21
making processes and to provide transparency to external stakeholders and regulatory 22
agencies16. 23
16 BC Hydro’s LCAM system for generation assets is consistent with the British Standard Institution (BSI)
PAS 55 Asset Management Specifications.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-4
One of the key decisions in asset management is when to overhaul or replace equipment. 1
There are three specific factors that trigger replacement: 2
1. Below target reliability or availability or declining reliability or availability trend combined 3
with: 4
maintenance costs that are increasing or can be economically reduced by equipment 5
replacement; or 6
equipment is obsolete (e.g., spare parts are no longer economically available or 7
technical experience is limited or difficult to obtain). 8
2. Estimated business risk to BC Hydro is too high; or 9
3. Additional energy or capacity can be produced economically (e.g., Resource Smart 10
opportunity). 11
Under the LCAM model, BC Hydro uses, for most major assets, a standardized condition 12
assessment methodology known as Equipment Health Rating (EHR), to assist in identifying 13
when capital investment in major equipment is required. 14
In assessing the health of specific equipment, the EHR methodology considers: 15
the design and original quality of the asset; 16
the current condition of the asset; 17
the maintainability of the asset, including the availability of spare parts and technical 18
experience; 19
how the asset has been and will be operating; 20
how the asset has been and will be maintained; and 21
opportunities for investment to improve the asset. 22
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-5
BC Hydro also uses a risk assessment methodology to assist in making investments in 1
generation assets. Risks are assessed in terms of their frequency or probability of 2
occurrence and in terms of their consequences or severity and are evaluated in four 3
categories: safety, financial, environmental, and damage to reputation. 4
Because of the limited use of GIS at its facilities, BC Hydro has not developed an EHR 5
methodology for assessing the condition of GIS equipment. Instead, BC Hydro retained 6
three consultants to assess the condition of the Mica GIS, using the same factors 7
considered in BC Hydro’s EHR and risk methodologies. 8
Finally, BC Hydro’s LCAM requires that alternative solutions be evaluated. This involves, for 9
each of the alternative solutions considered, balancing the tradeoffs between the risk and 10
performance dimensions and the total lifecycle cost. BC Hydro’s objective is to maximize the 11
lifecycle value of its generation assets while being mindful of the impact on customer rates. 12
Alternative solutions with respect to the Project are addressed in section 4.4 13
4.2.3 GIS Condition Assessment 14
This section outlines the conclusions and recommendation from condition assessments 15
performed by both external GIS experts and by BC Hydro. 16
4.2.3.1 Independent Condition Assessment Reports 17
Three independent condition assessments were performed17 by three external GIS experts. 18
The relevant recommendations from these reports are presented in this section. The reports 19
are provided in Appendix E. 20
17 The independent experts did not assess the condition of the GIS in the switchgear building as this equipment
was managed by BCTC (the management of the switchgear building is being transferred to BC Hydro). BC Hydro considers the condition assessments applicable to the equipment in the switchgear building because the switchgear building contains GIS of the same vintage and manufacturer as that in the transformer chamber.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-6
Bjorn Holm Condition Assessment Recommendations 1
Mr. Bjorn Holm of International Switchgear Consulting prepared a report titled “Condition 2
Assessment of 550 KV ITE SF6 Gas Insulated Switchgear Equipment in the Transformer 3
Gallery and Lead Shafts” dated October 2005. 4
His recommendations include: 5
Install spare phase of bus in the transformer chamber in the short term; 6
Install GIS in lead shaft 3; and 7
Replace the GIS in stages starting within about eight years (or by 2013). 8
Edgar Heil Condition Assessment Recommendations 9
Mr. Edgar Heil (of RoHe International) prepared a report titled ”BC Hydro Mica Generating 10
Station - ITE GIS Condition Risk Assessment” dated, June 30, 2007. 11
His recommendations include: 12
Immediately - Replace all disconnect switch operating rods; 13
Medium Term (within five years) - Replace all “O-rings” in bolted flanges to stop SF6 14
leaks; and 15
Long Term (five - 30 years): 16
install bus in lead shaft 3; and 17
replace all GIS components in the transformer chamber. 18
Mr. Heil provided the following note to the recommendations: 19
“If a replacement GIS is considered, then the recommended “Medium Term Solution” 20
may be delayed. However, some unscheduled outages, repairs maintenance will 21
most likely be the result of this delay.” 22
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-7
Dr. Brian Hampton Condition Assessment Recommendations 1
Dr. Brian Hampton, formerly of the Central Electricity Generating Board London, prepared 2
the condition assessment report titled “The Present Condition and Future Reliability of the 3
Transformer Gallery GIS at Mica Unit 500 kV Substation” dated June 25, 2007. 4
His recommendations include: 5
Phase 1 - Replace all disconnects and surge arrestors in the transformer chamber in the 6
short term; 7
Phase 2 - Install a second (or redundant) bus in the transformer chamber in the medium 8
term; and 9
Phase 3 - Replace lead shaft 1 and 2 in 2014. 10
4.2.3.2 BC Hydro Condition Assessment Conclusions 11
The condition assessments consistently recommend that BC Hydro address the reliability 12
issues of the GIS. The details of the recommendations may vary – but the general 13
recommendations are consistent. Dr. Hampton concluded that there was a 99 per cent 14
chance of GIS failure within ten years. Nine months after this prediction, a surge arrestor 15
failed on Unit 3, which resulted in it being out of service for ten weeks. 16
Since the condition assessments, BC Hydro identified additional GIS issues for the following 17
key GIS components: 18
Surge Arrestors – Surge arrestors protect electrical equipment, particularly transformers, 19
from damage that could result from voltage spikes. A transformer is capable of absorbing 20
a narrower range of voltage variation and without a surge arrestor in place could be 21
damaged if exposed to voltage variation outside of this range. 22
Mica Unit 3 has been in operation without surge arrestors on A and C phases since 23
spring 2008. The A-phase surge arrestor on Mica Unit 3 was removed immediately after it 24
failed in March 2008 and the C-phase surge arrestor was removed shortly after. 25
Mica Unit 3 has only one remaining surge arrestor on B-phase. This results in Mica Unit 4 26
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-8
surge arrestors protecting both Mica Units 3 and 4 transformers from fast front surges, 1
typically caused by lightning. This means the transformers on Mica Unit 3 and Mica Unit 4 2
have a lower level of protection than designed. This designed redundancy in surge 3
arrestors might otherwise act to prevent damage in the event of a voltage surge. 4
Following the March 2008 surge arrestor failure, the damaged surge arrestor was 5
inspected to investigate the cause of failure. The grading capacitor of the surge arrestor 6
had damage that clearly preceded the surge arrestor flashover that caused the 7
March 2008 outage. It is likely that the surge arrestor was providing little or no protection 8
before it failed, and in fact was the cause of the forced outage. BC Hydro also concluded 9
that the surge arrestor could not be refurbished. An operating restriction has been 10
established at Mica to prevent manual operation of the disconnect switches while the bus 11
is energized to reduce the occurrence of voltage surges. Based on the root cause 12
analysis performed on the failed surge arrestor, a hypothesis for the failure mechanism 13
was developed. As part of the ongoing regular monitoring of the surge arrestors, the 14
remaining surge arrestors are now monitored for indications of this failure mode 15
occurring. 16
As a result of this ongoing monitoring, a surge arrestor on Mica Unit 2 showed indications 17
of this failure mode and as a result was removed from service. 18
The remaining nine surge arrestors on Mica Units 1 through 4: 19
have reached the end of life; 20
have a high likelihood of failure; 21
may no longer be protecting the transformers; and 22
are likely increasing the risk of failure and subsequent damage to surrounding 23
equipment. 24
Disconnect Switches – There has been a history of disconnect switch failures over the life 25
of Mica. Many have been due to disconnect rod failures. Disconnect rods are insulated 26
rods connected to the mechanism used to open and close disconnect switches. To date, 27
BC Hydro has successfully repaired all of the disconnect switch failures. However, with 28
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-9
the surge arresters out of service, failure of a disconnect switch may result in damage to 1
other equipment such as the 500 kV transformers, as the surge arrestors offer protection 2
to the transformers for this sort of fault. In 2000 Powertech Labs Inc. examined a number 3
of Mica disconnect rods and found a breakdown of the insulating properties of the rods. 4
This will eventually lead to flash-over failures of the disconnect switches, which in most 5
cases will result in a forced outage of at least one generating unit. 6
Bus Cone Insulators – BC Hydro performed in situ ultra high frequency testing in 2005 7
and again in 2008 on the bus cone insulators during normal operation. The bus cone 8
insulators are distributed throughout the bus to support the conductor (refer to Figure 9
4-1). The testing detected extensive partial discharge which is an indicator of poor 10
equipment health, and will eventually result in flash-over failure leading to forced outages. 11
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-10
Figure 4-1 Bus Cone Insulator 1
Spare Parts - There are no spare parts for surge arrestors, and spare parts for disconnect 2
switches have limited availability. There is 30 m of spare bus available. 3
Table 4-1 provides additional details on the current state of the GIS components along with 4
additional details on outage requirements to replace GIS and the consequences of forced 5
outages.6
Conductor Bus Cone Insulator
Outer Enclosure
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-11
Table 4-1 Analysis of GIS by Component
Component Current State Planned Outage Required for Replacement or Installation
Forced Outage Consequence
Benefits of New Equipment
Surge Arrestors
The probability of failure is very high: – one has already failed – another has been removed – a third is suspect
Existing surge arrestors may not be protecting transformers.
No spare parts
Mica staff monitoring electrical behaviour for signs of imminent failure with every switching event.
5 – 7 days per Surge Arrestor or one month per unit (3 surge arrestors per unit).
One generator out of service.
No spare parts.
Surge arrester must be removed or substituted.
6 weeks outage to remove and repair associated damage.
6 months to obtain new technology replacement.
Risk of catastrophic transformer failure increased.
Existing surge arresters are an obsolete technology.
Modern metal oxide surge arrestors are demonstrably better at protecting transformers than the existing gap type surge arresters.
Disconnect switches and bus in Transformer Chamber
The probability of failure is very high.
Motor operating mechanisms on disconnects do not function properly and are not repairable.
Existing disconnects are first generation of GIS equipment and there have been several past failures. To reduce risk of failures, operating restrictions are imposed on how disconnect switches are operated. Need to de-energize units on either side to operate – consequently operation results in short outage in all cases.
Extensive partial discharge has been found in most disconnect operating rods indicating electrical breakdown activity. Operating rods with the highest risk have been replaced.
Partial discharge has also been detected in several other locations. Repairs at other partial discharge locations would require extensive dismantling and refurbishing.
3 – 4 months to replace the GIS for one or two units.
Replacing two units at a time would minimize outage times and costs.
Long lead times and customized design work required.
Two coincident failures could result in full Mica outage depending on location.
Any repair requires extensive scaffolding, rigging and dismantling.
Enables remote operation, alleviating staff resources and improve operating efficiency.
Newer technology disconnects will not impose any operating restrictions.
Reduced risk of fault and resulting forced outage.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-12
Component Current State Planned Outage Required for Replacement or Installation
Forced Outage Consequence
Benefits of New Equipment
Disconnect switches and bus in switchgear building
Same as above. Same as above but can transfer power from 3½ units up alternate lead shaft during replacement. Limit dictated by transmission restrictions.
Failure of one disconnect switch could result in extended ½ unit outage.
Enables remote operation.
Reduced risk of fault and resulting forced outage.
GIS in Lead Shaft 1 & 2
Deteriorated condition of solid insulators is associated with increased risk of failure.
Equipment is at steep inclines in confined space so any failure is difficult to repair.
Condition of solid insulators and SF6 seal systems have deteriorated and require replacement.
Some spare bus parts.
Mica limited to transferring only 3½ units of power up single lead shaft because of MSSC limitations.
See alternatives in Table 4-3.
Based on the 1984 lead shaft repair at Mica and similar repairs carried out at Revelstoke, a faulted bus section in a lead shaft in Mica can be expected to take between one to three months to repair depending on the location of the fault, the phase of bus affected and the availability of skilled workers and supervisors. The work would not extend the useful life of equipment.
Mica output is reduced by 300 MW if one lead shaft is out of service.
Mica would be out of service for extended period of time if the second lead shaft fails.
Reduced risk of failure
New equipment would provide an estimated life of 50 years
New equipment would be more cost effective than refurbishing
Better monitoring of SF6 pressure. Partial discharge activity will be monitored to better provide warning of impending failure.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-13
4.2.3.3 Condition Assessment Summary 1
Based upon the condition assessment work performed by external GIS experts and 2
BC Hydro, the condition assessment of the GIS is summarized in Figure 4-2. 3
Figure 4-2 Condition Assessment Summary 4
Lead
Sha
ft
Lead
Sha
ft
500 kV16 kVP
ower
hous
eS
witc
hgea
r Bui
ldin
g
4.3 Identification of Project Benefits 5
In addition to the purpose of the Project, namely to maintain the reliability of Mica, there are 6
benefits that will be realized with the implementation of the Project. 7
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-14
4.3.1.1 Disconnect Switches 1
One of the benefits from the Project will be to improve worker safety at Mica. Currently, the 2
existing disconnect switches have disconnect motors that do not operate as intended and as 3
a result, manual operation of the disconnect switches is required. Such operations introduce 4
the risk of operator error and pose potential electrical contact risk to workers. This risk is 5
currently being managed through BC Hydro safe work practices and site-specific operating 6
instructions. The disconnect switches can also only be operated when the bus is 7
de-energized. In some cases, this requires a two unit outage and impacts the operating 8
flexibility of Mica. 9
Replacing the GIS provides an opportunity to address this issue while also improving the 10
layout or architecture of the GIS. This latter benefit, also results in safety benefits as 11
equipment is made more accessible for maintenance and repair, as described further below. 12
4.3.1.2 Maintenance Access 13
Currently access for repair of the GIS requires the construction of temporary structures as 14
shown in Figure 4-3. For example, in 2008, scaffolding was erected to remove the failed 15
surge arrestor. Lifting equipment had to be rigged from the roof. Temporary rigging is 16
required to lift many types of heavy equipment currently. This temporary rigging often does 17
not provide an optimum configuration and as a result, workers are required to perform 18
considerable manual lifting which puts them at risk of strains and sprains. Figure 4-4 is 19
another view showing the height at which the GIS is currently located. 20
Worker safety and access to the equipment can be improved through the addition of cranes 21
and partial mezzanines. 22
The Project is designed to include structural safety improvements including an overhead 23
crane and a mezzanine. These additions reduce risks to workers by improving access, and 24
reduce repair time by providing a crane which can safely remove and install equipment, 25
eliminating the need for workers to lift heavy equipment or work from scaffolding. Figure 4-5 26
is a computer generated three dimensional image showing the improved GIS layout on the 27
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-15
mezzanine along with the new crane which will allow for easy installation and removal of 1
GIS components. 2
Figure 4-3 Repair of Surge Arrestor under Existing GIS Layout 3
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-16
Figure 4-4 Height of Existing GIS 1
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-17
Figure 4-5 Improved GIS Layout 1
4.3.2 Environmental Benefits 2
SF6 is used in three BC Hydro generating stations and at various BCTC operated 3
substations because of its electrical insulating properties. SF6 is a potent GHG: 1 kg of SF6 4
is equal to 23,900 kg of CO2 equivalent. The GIS leaks an excessive amount of SF6 and 5
more significant leaks are expected to develop over time as the equipment ages. In 2008, a 6
total of 565 kg of SF6, representing a leakage rate of 3.8 per cent per year, leaked at Mica. 7
Due to the GHG intensity of SF6, this amount is equivalent to 13,503 tonnes of CO2. 8
The “O” rings, which provide a seal between the bus flanges, have a finite life. BC Hydro 9
has taken measures to reduce SF6 leakage by in part replacing “O” rings where practicable. 10
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-18
However, the “O” rings in the bus in the lead shafts are difficult and costly to replace due to 1
the design of the equipment. As identified in the Edgar Heil condition assessment, these 2
remaining “O” rings are likely to begin to fail soon as a result of their age, resulting in more 3
significant SF6 gas leaks. In addition, the replacement of “O” rings does not improve the 4
reliability of the vast majority of bus cone insulators in the lead shafts, which are a more 5
critical reliability concern. 6
For new GIS, the current industry standard leakage rate is 0.5 per cent per year. New GIS 7
equipment being installed in Japan and Europe is achieving leakage rates of 0.1 per cent 8
per year or less. GIS installations at Revelstoke and Seven Mile GS are currently achieving 9
nearly zero losses. 10
BC Hydro has specified that MEPPI must meet standards of 0.5 per cent leakage or less 11
per year. However, based on typical performance of modern equipment it is reasonable to 12
expect near zero leakage. 13
4.3.3 Benefit to Mica Units 5 and 6 14
In order to operate Mica with six units, GIS is required in all three lead shafts. The Project 15
reduces the scope of a future Mica Units 5 and 6 project by eliminating the need to include 16
installation of GIS in lead shaft 3 and extension of the switchgear building in that project. As 17
a result, the Project will benefit these units by enabling them to achieve an earlier ISD. 18
In the 2008 LTAP, Mica Units 5 and 6 are identified capacity resources required in 19
2013 (F2014) and 2015 (F2016) respectively in the CRP, while in the 2008 LTAP Base 20
Resource Plan (BRP) Mica Unit 5 is a required capacity resource in 2024 (F2025). The 21
Project allows for Mica Units 5 and 6 to achieve the ISDs required in the CRP. 22
4.4 Architecture Evaluation and Selection 23
This section discusses the process BC Hydro undertook to analyze and evaluate various 24
architecture alternatives to replace the GIS. This process led to BC Hydro’s 25
recommendation of new GIS architecture to replace the existing GIS. Also, this section 26
discusses BC Hydro’s consideration of the external GIS experts’ recommendations in the 27
selection of architecture for the Project. 28
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-19
4.4.1 Problem Scope and Architecture Options 1
Section 4.2.3 presented the conclusions and recommendations made by three external GIS 2
experts. The focus of each expert was how to reduce the risk of forced outages posed by 3
the GIS. Once it became clear to BC Hydro that a significant investment would be required, 4
BC Hydro broadened the scope of the investigation. The broader investigation scope 5
included the consideration of delivering additional benefits such as improved safety for 6
workers, improved maintenance access for workers, and reduced leakage of SF6. 7
BC Hydro considered a number of options for GIS replacement architectures. Alternatives 8
and evaluation criteria were based on BC Hydro’s user requirements developed through 9
consultation with the Project Initiator and other BC Hydro stakeholders. Initially, high level 10
options were considered including some with architecture that would, if practical, 11
significantly alter the configuration of Mica. Also, while BC Hydro initiated the Project to 12
address the reliability risks posed by the aging GIS, consideration was also given to the 13
longer term requirements of a six unit Mica18 which requires GIS in all three lead shafts in 14
order to transmit the full output of six units. 15
Two of the architectures BC Hydro considered that did not include GIS were: 16
moving the 500 kV transformers out of the Mica powerhouse to the surface; and 17
using an insulating gas other than SF6. 18
However, BC Hydro concluded early in the process that the constraints of the underground 19
Mica powerhouse and technology did not permit the development of these architectures. 20
Also, SF6 gas is the only technology available for disconnect switches, circuit breakers and 21
surge arrestors for indoor 500 kV applications such as at Mica. 22
A structured decision making process was used to select the architecture that best 23
addressed BC Hydro’s requirements. As part of this process detailed engineering studies 24
18 Appendix H contains analysis of the number of lead shafts required for Mica GIS with four, five and
six generating units.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-20
were conducted to help make architecture recommendations. Following this, the options 1
were analyzed to determine the best timing for replacement. 2
BC Hydro identified eight of the more practical architecture alternatives. The options 3
included architectures with either high or low side circuit breakers, different bus 4
arrangements in the transformer chamber and options using cross-linked polyethylene 5
(XLPE) cable in the lead shafts. These eight alternatives were further narrowed to four after 6
further evaluation. Of the four architectures that were studied, two (XLPE cable and 7
replacement GIS) were clearly superior and warranted further optimization and subsequent 8
restudy. Subject matter experts and quantitative data were used to score the final two 9
alternatives and select the best architecture for Mica. 10
As a result of the structured decision making analysis, BC Hydro concluded that: 11
Application of 500 kV XLPE cables in the lead shafts is not recommended for Mica based 12
on the maturity of the technology, repair complexity, installation duration and the 13
configuration and technical requirements of Mica. Specifically: 14
knowledgeable personnel are available locally for GIS, but not 500 kV XLPE cable; 15
the cable alternative is not available with the same transfer capacity as GIS; 16
the initial cost of the cable alternative is estimated to be lower but had higher risks 17
because the technology had never been implemented in North America; 18
the cable has insufficient operational history, for its long-term performance to be 19
adequately assessed, particularly for 500 kV applications; 20
the cost over the life of the cable alternative was estimated to be higher than GIS due 21
to the cost of planned outages required for installation; and 22
the safety and environmental risks for both alternatives are estimated to be similar; 23
GIS is the only feasible technology for replacement of active components (circuit 24
breakers, disconnect switches, and surge arrestors) due to the space constraints of 25
locating equipment in indoor and underground locations; 26
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-21
The current architecture with circuit breakers on the low voltage side of the transformers 1
should remain; 2
Obsolete gap type surge arrestors should be replaced with modern metal oxide surge 3
arrestors; 4
Disconnect switches should be replaced with ones that are more reliable and can be 5
operated remotely; 6
Worker safety and access to equipment in the transformer chamber can be improved by 7
installation of partial mezzanine and overhead crane; 8
A single bus architecture is preferable to a ring or double bus architecture in the 9
transformer chamber; and 10
An architecture can be developed that is more tolerant of equipment failure than the 11
current architecture. 12
4.4.2 Architecture Conclusions 13
A one line diagram of the ultimate layout for Mica was completed with a proposal that Mica 14
should be operated with GIS installed in all three lead shafts (refer to Figure 4-6). A 15
conceptual general arrangement was completed using three dimensional modelling to 16
confirm space requirements for new equipment in the Mica transformer chamber. 17
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-22
Figure 4-6 Mica GIS Ultimate Layout 1
Not in the scope of this project
Style Legend
Not In Scope
Replace
Remain
G1
T1
Circuit Breaker
Disconnect Switch
Transformer
Generator
Surge Arrester
Transmission Line
Reactor
5L71 5L72
G2
T2
G3
T3
G4
T4
G5
T5
G6
T6
New
4.4.3 Holm, Hampton and Heil Recommended Architectures 2
In this section, the GIS architectures recommended by the external GIS experts are 3
compared with the proposed Project. 4
Dr. Hampton’s recommended GIS architecture formed the basis of one of the architectures 5
considered. The basis for this architecture was the addition of a second bus in the 6
transformer chamber. Upon detailed analysis, it was concluded that: 7
1. the second bus provides limited reliability improvements once the primary bus is 8
replaced; and 9
2. the physical constraints of the transformer chamber makes it impractical to install the 10
second bus. 11
Mr. Holm’s recommendation is incorporated into the BC Hydro proposed architecture with 12
the exception of the spare phase of GIS. It would be difficult to add this spare phase due to 13
the space constraints in the transformer chamber. 14
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-23
Mr. Heil’s recommended architecture is similar to the architecture proposed by BC Hydro. 1
However, while Mr. Heil recommended that all “O” ring seals be replaced by the year 2012, 2
BC Hydro views this as being risky, expensive, and disruptive to Mica. BC Hydro is of the 3
view that replacing the GIS with architecture similar to that recommended by Mr Heil, and in 4
the timeframe recommended by Mr Heil is more appropriate. 5
4.5 Timing and Sequencing of GIS Replacement 6
4.5.1 Timing of GIS Replacement 7
Given the significant reliability risks posed by the existing GIS, the option to “do nothing” 8
was not considered viable. The existing GIS must be replaced and as a result of the process 9
described in section 4.4, BC Hydro proposes replacing the existing GIS with new GIS and 10
adding GIS to lead shaft 3. 11
BC Hydro’s analysis of the alternatives for the timing and sequencing of the GIS 12
implementation assumes in all cases that the GIS in lead shaft 3 would be completed first to 13
meet a Mica Unit 5 ISD of 2013 (F2014) and varies the timing for replacing the existing GIS 14
in lead shaft 1 and 2. Four primary alternatives for the timing and sequence of the BC Hydro 15
proposed architecture were considered for replacement: 16
1. Replacement of the aging GIS with new GIS equipment by 2013 (Alternative 1); 17
2. Alternative 1 but defer the replacement by five years (Alternative 2a) or ten years 18
(Alternative 2b); 19
3. Replacement of the existing GIS as a series of smaller projects between 2010 and 20
2017, rather than a single project (Alternative 3); and 21
4. Alternative 1 with the exception of deferring the replacement of the GIS in lead shafts 1 22
and 2 (Alternative 4). 23
The analysis in section 4.5.3 considers variation of the ISD of Mica Units 5 and 6. 24
The cost of each of the four alternatives is evaluated taking into account a range of probable 25
outage costs, the capital investment required, and the cost of GHG emissions. 26
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-24
The actual cost of an outage at Mica can vary significantly depending on the time of year, 1
the market price of capacity and energy, and demand. Table 4-2 shows the life cycle 2
PV cost of each alternative under three scenarios of low, moderate and high outage costs 3
ranging from $6 million to $19 million19. An inverse relationship is applied such that there is a 4
higher probability of a low cost outage compared to a high cost outage. As the existing 5
equipment is aging, the probability of failure is increased by one per cent per annum. 6
Table 4-2 PV of Replacement Alternatives 7
Schedule for GIS component Installation/Replacement
1 2 3 4 5 6 7 8 9 10 11 12 13Low Cost
($6 M)Moderate
Cost ($12 M) High Cost
($19 M)
Activity 2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
Probability(33%)
Moderate Probability
(25%)
Low Probability
(15%)Alternative 1
Replace Existing GIS $61Lead shaft 3 and interface $56
PV of project costs $117 $117 $117 $117Range of Outage costs $5 $8 $8GHG Credit Cost $1 $1 $1Range of Adjusted PV of Project $123 $126 $126
Alternative 2 a
Replace Existing $54Lead shaft 3 and interface $53
PV of project costs $107 $107 $107 $107Range of Outage costs $13 $19 $18GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $122 $129 $128
Alternative 2 bReplace Existing $46Lead shaft 3 and interface $53
PV of project costs $99 $99 $99 $99Range of Outage costs $18 $28 $27GHG Credit Cost $3 $3 $3Range of Adjusted PV of Project $121 $130 $129
Alternative 3Replace Existing $65Lead shaft 3 and interface $53
PV of project costs $119 $119 $119 $119Range of Outage costs $11 $17 $19GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $132 $138 $140
Do Nothing - Defer implementaion of Project by 5 years
PV Project and Outage Costs(in $millions)
Outage probability increasing by 1% per year
Implement project piecemeal over time
Do Nothing - Defer implementaion of Project by 10 years
PV Project
Cost
Full implementation of Project by 2013
Alternative 4Replace existing GIS in tranformer chamber and switchgear building
$42
Lead shaft 3 and interface $56Lead shafts 1 and 2 $20
PV of project costs $118 $118 $118 $118Range of Outage costs $7 $10 $9GHG Credit Cost $2 $2 $2Range of Adjusted PV of Project $127 $130 $130
Same as Alternative 1 but defer replacement of lead shafts 1 and 2
Note: For Alternatives 2a, 2b and 3, the activity “lead shaft 3 and interface” PV of $53 million is calculated 8 based on an in-service date in 2012 whereas for Alternative 1 and Alternative 4 the PV is $56 million for 9 an in-service date of 2011. 10
19 For details on the range of outage costs refer to section 3 and section 4 of Appendix I.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-25
As shown in Table 4-2, the life cycle PV cost20 of Alternative 1 is not significantly different 1
than the PV of Alternatives 2(a) and 2(b) (deferring the Project by five or ten years), when 2
the potential cost of outages is included. For moderate and high outage consequences, 3
replacing the GIS now is the least cost alternative. 4
Alternative 3, “a series of smaller projects”, is an estimate of the increase in cost if the GIS 5
were run to failure. Replacing the existing GIS in a series of small projects is the most 6
expensive option as the cost to design, engineer, supply and install increase significantly if 7
portions of the Project are deferred. The design and engineering of bus and interfaces is 8
customized or unique to each location. Deferring any portion of the Project would require the 9
duplication of design and engineering work by both the supplier and BC Hydro. The unit cost 10
of manufacturing is also expected to increase as the size of the order decreases. Additional 11
mobilizing and training costs are also expected to be incurred if the Project is segmented. 12
The replacement cash flows were escalated by 15 per cent to reflect the incremental 13
procurement and mobilization costs, and $3 million is included for additional engineering 14
and planning costs. BC Hydro is of the view that the actual planned and forced outage costs 15
for this alternative are likely to be much higher than indicated in Table 4-2. 16
Alternative 4 (deferring replacement of GIS in lead shafts 1 and 2) is more expensive than 17
Alternative 1 since, like Alternative 3, there will be additional costs as a result of the work 18
being broken into separate projects. 19
Given that the existing Mica 500 kV GIS poses substantial reliability risks to BC Hydro, it 20
was concluded that deferral was not an option. Alternative 1 has the lowest life cycle PV 21
cost under moderate and high outage scenarios. Additionally, Alternative 1 realizes the 22
safety and environmental benefits at the earliest date, allows the development of an 23
improved GIS design and architecture, and allows replacement of the aging GIS with new 24
GIS equipment by 2013. As a result, Alternative 1 is the proposed alternative. 25
4.5.2 Planned Outage Requirements for Alternatives 26
Different implementation or staging strategies for the GIS replacement have a significant 27
impact on the planned outage required and the Project risks. The proposed Project 28
20 For the basis of the PV project costs shown in Table 4-2, refer to section 5 of Appendix I.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-26
recommends building the switchgear building extension and installing GIS in lead shaft 3 1
first. The switchgear building extension will also serve as a clean storage and working area 2
while replacing the existing GIS. 3
If lead shaft 3 and the switchgear building extension are in place, it is possible to implement 4
the full Project scope over four years with planned spring outages in two of the years. 5
Staging analysis for the proposed Project scope indicates that it would be possible to 6
construct the GIS in lead shaft 3 as non-outage work prior to the first spring outage in 2011. 7
All remaining work would then occur in a four month spring outage in 2011 and a 8
subsequent four month outage in spring of 2012, during periods when the cost of the 9
outages are significantly lower. 10
If the scope of the Project were to only include the replacement of the existing GIS, it would 11
result in longer planned outages and increase the Project schedule and reliability risk. 12
Replacement of the existing GIS would require four consecutive years of four month 13
outages. The critical work in the transformer chamber and switchgear building would occur 14
in the first two outages and each lead shaft would be replaced in each of the following two 15
years during similar spring outages. The requirement for four separate outages is driven by: 16
space constraints for staging work (since the switchgear building would not have been 17
extended) and schedule and outage risks associated with undertaking the lead shaft 18
replacement and the transformer chamber replacement concurrently. Figure 4-7 below 19
illustrates the approximate reliability realization in time with the two options (GIS in lead 20
shaft 3 first versus replacing existing GIS only). The area between the curves is the net 21
resulting reduction in exposure to outages based on the two options. Building lead shaft 3 22
and extending the switchgear building first provides early improvements and significantly 23
reduces exposure to forced outages. Table 4-3 provides additional details on the outage 24
requirements for the replacement of the GIS in lead shafts 1 and 2 with and without GIS in 25
lead shaft 3. 26
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-27
Figure 4-7 Reliability Realization from Staging Lead Shaft 3 First 1
0%
20%
40%
60%
80%
100%
2010 2011 2012 2013 2014Year
Rel
iabi
lity
Rea
lizat
ion
Lead Shaft 3 FirstOnly Replace Existing
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-28
Table 4-3 Replacement of Lead Shaft 1 and 2 with or without Lead Shaft 3 in Place 1
Component Current State Planned Outage Required for Replacement or Installation
Forced Outage Consequence Benefits of New Equipment
Replace GIS in lead shafts 1 or 2 without lead shaft 3 in place
Curtail transfer of power to 3½ units for alternate lead shaft.
3 – 4 months outage to replace. (Cannot replace transformer chamber equipment and switchgear building equipment and lead shaft bus in the same calendar year without lead shaft 3).
Curtails power transfer on alternate lead shaft to 3½ units.
During single lead shaft outage the plant is exposed to risk of complete outage for many second contingency failure events in the GIS.
Same consequence of failure in future as existing plant.
Replace GIS in lead shafts 1 or 2 with lead shaft 3 in place
Addition of third lead shaft recommended by external consultants as this significantly improves reliability of entire Mica.
5 – 8 day outage to disconnect and reconnect. 3 – 5 months to replace but can be done without outage. Replacement can be at same time as outage for disconnects
Provides contingency in event of failure in either lead shaft 1 or lead shaft 2.
Loss of one lead shaft out of three should not impact plant generation output.
Very robust architecture that allows minimal disruption in the case of one lead shaft bus outage and most possible second contingency GIS failure events.
Significantly reduces consequence of failure in future.
Lead shaft 3 is required, in any event, for the proposed Mica Units 5 and 6 capacity addition.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-29
4.5.3 Sensitivity Analysis for Mica Units 5 and 6 ISDs 1
Given the uncertainty as to the ultimate ISD for Mica Units 5 and 6, this section compares 2
the Project PV based on the schedule in Table 3-1 with the PV of options which result in 3
implementing the proposed architecture but which have different ISDs based on later ISDs 4
for Mica Unit 5 of 2018 or 2025. These options could be undertaken if the actual ISD for 5
Mica Unit 5 was known for certain. All options compared have GIS being put into service in 6
the three lead shafts before Mica Unit 5 is put into service. Completing the GIS installation 7
for the proposed architecture assumes that at least a five unit Mica will be in place by at 8
least 2025. 9
In the analysis it is estimated that deferring portions of the Project may incur additional 10
procurement costs as BC Hydro would be ordering less GIS bus with each individual project, 11
and there would also be a duplication of engineering costs and mobilization costs. Savings 12
from use of tools, training, skill development and fixed costs of work plans, high-angle 13
rescue plans and in-place project/construction management structure make the incremental 14
cost of doing the full replacement now low compared to tendering the work separately. In 15
addition, changes in Project scope do not reduce certain fixed Project costs (refer to 16
Appendix I for details of the financial analysis). This analysis only considers the time value 17
of the investment required and does not include a value for reduced planned outage time or 18
the possible forced outage consequences caused by failures in the lead shafts. 19
The analysis compares the PV of the Project cost for seven scheduling alternatives: 20
1. Base Case - Replace all existing GIS, install lead shaft 3 and extend the switchgear 21
building now. This assumes that Mica Unit 5 will have an ISD in 2013; 22
2. Defer lead shaft 1 and lead shaft 2 for Mica Unit 5 ISD of 2018 – Install lead shaft 3, 23
extend the switchgear building and replace the GIS in the transformer chamber and 24
switchgear building now. Defer lead shaft 1 and lead shaft 2 installation until just in 25
advance of the Mica Unit 5 ISD in 2018; 26
3. Defer lead shaft 3 and the switchgear building extension to the Mica Unit 5 ISD 27
of 2018 – Replace all existing GIS now. Lead shaft 3 and the switchgear building 28
extension is deferred and installed just in advance of the Mica Unit 5 ISD in 2018; 29
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-30
4. Defer lead shaft 1 for Mica Unit 5 ISD of 2018 – Replace lead shaft 2, install lead shaft 3 1
and replace GIS in transformer chamber and switchgear building now. Lead shaft 1 is 2
deferred and installed just in advance of the Mica Unit 5 ISD in 2018; 3
5. Defer lead shaft 1 and lead shaft 2 for Mica Unit 5 ISD of 2025 - Install lead shaft 3, 4
extend the switchgear building and replace the GIS in the transformer chamber and 5
switchgear building now. Lead shaft 1 and lead shaft 2 are deferred and installed just in 6
advance of the Mica Unit 5 ISD in 2025; 7
6. Defer lead shaft 3 and the switchgear building extension to the Mica Unit 5 ISD of 2025 - 8
Replace all existing GIS now. Lead shaft 3 and the switchgear build extension is 9
deferred and installed just in advance of the Mica Unit 5 ISD in 2025; and 10
7. Defer lead shaft 1 for Mica Unit 5 ISD of 2025 - Replace lead shaft 2, install lead shaft 3 11
and replace GIS in transformer chamber and switchgear building now. Lead shaft 1 is 12
deferred and installed just in advance of the Mica Unit 5 ISD in 2025. 13
Options 2, 3 and 4 assume a Mica Unit 5 ISD of 2018 while options 5, 6 and 7 assume a 14
Mica Unit 5 ISD of 2025. 15
In all of the options, there is a risk that the Project schedule cannot be met and the planned 16
outage extended. However, in options 3 and 6 the Project risks are greater because: 17
a. These options require planned outages spanning four years compared to two years. An 18
extension of the planned outage by one month, to include the month of August, is 19
estimated to have an opportunity cost in the range of $3 - $20 million. The variance is 20
largely due to varying trade benefits; 21
b. Generation must be curtailed by a minimum of 300 MW for four months in each of 22
four years; and 23
c. There is a risk that the GIS in the alternate lead shaft will fail during construction 24
compromising 1,500 MW of generation at Mica for an extended period. 25
The sensitivity analysis shows that if Mica Unit 5 is constructed at anytime before 2018 the 26
proposed option (base case) with a PV of $117 million is the least cost. If the Mica Unit 5 27
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-31
project is deferred to 2025, the PV of deferring portions of the project (as shown in 1
Options 5, 6 and 7) range from $114 million to $118 million21. Of these, option 6 with a PV of 2
$114 million is the least cost alternative. This is before considering the exposure of a 3
$3 to $20 million outage cost due to an extension in the Project schedule by one month in 4
both of the years that existing GIS in lead shafts 1 and 2 are replaced. There is the 5
additional risk of an entire plant outage should a failure occur in the alternate lead shaft. 6
Since the base case option meets the CRP for Mica Units 5 and 6, the risks associated with 7
option 6 do not justify deferring the installation of GIS in the third lead shaft by 12 years. It is 8
recommended that the full Project scope be implemented with an ISD of 2013 because the 9
risks and cost variances do not justify deferral. Table 4-4 compares the seven options. 10
21 For details on the costs for the seven options refer to section 7 of Appendix I.
Chapter 4 - Project Justification
Mica Gas Insulated Switchgear Project
4-32
Table 4-4 Sensitivity Analysis for Meeting Alternative Mica Units 5 and 6 ISD 1
Option/ Year
Present Value Cost ($millions) 20
10
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
$117 x x
$124 x x
$127 x x x x
$119 x x
$118 x x
$114 x x x x
$116 x x
LEGENDLead Shaft 3 and switchgear buildingLead Shaft 1Lead Shaft 2Base ComponentsPlanned Outage - 4 months xMica Unit 5 In-service date
MIC
A 5 IS
D
MIC
A 5 IS
D
5) Defer Lead Shaft 1&2 ten years
6) Defer Lead Shaft 3 ten years
7) Defer Lead Shaft 1 ten years
MIC
A 5 IS
D
1) Base Case - Do All Now
2) Defer Lead Shaft 1&2
3) Defer Lead Shaft 3
4) Defer Lead Shaft 1
Chapter 4 - Project Justification Project Justification
Mica Gas Insulated Switchgear Project
4-33
4.5.4 Recommended Project Scope 1
The scope of work for the Project has been developed. All original GIS in the transformer 2
chamber and switchgear building are to be replaced to maintain Mica reliability. The 3
disconnect switches and surge arrestors are at end of life, and the condition of the original 4
bus justifies replacement of all original GIS equipment. The addition of GIS equipment to 5
lead shaft 3 is identified as being key to the success of the Project, independent of the 6
proposed Mica Units 5 and 6 projects. Replacement of GIS in lead shafts 1 and 2 is flagged 7
as a high risk to the project schedule if done before GIS is installed in lead shaft 3. 8
Installation of GIS to lead shaft 3 and the related work to integrate lead shaft 3 results in 9
significant reliability improvement and can be done with relatively short and inexpensive 10
outages. 11
The key points for defining the scope of work for the Project are: 12
For the existing four-unit Mica, GIS in lead shaft 3 provides redundancy during 13
construction and ongoing operations; 14
GIS in lead shaft 3 reduces the planned outage required for replacement of the existing 15
lead shafts from months to days; 16
GIS in lead shaft 3 is required for any future installation of Mica Units 5 and 6; 17
Including GIS in lead shaft 3 significantly reduces planned outages once put into service; 18
and 19
Replacement of the GIS associated with Mica Units 1 to 4 and the remaining original 20
equipment in the switchgear building can be completed during spring outages in 2011 21
and 2012 when the costs of the outages are minimized. 22
Mica Gas Insulated Switchgear Project
Chapter
5
Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-i
Table of Contents
5.1 Introduction.................................................................................................................5-2
5.2 General Consultation..................................................................................................5-2
5.2.1 Environmental Assessment ............................................................................5-2
5.2.2 Core Committee..............................................................................................5-3
5.2.3 Future Public Consultation..............................................................................5-4
5.3 First Nations Consultation...........................................................................................5-4
5.3.1 Identification of Interested First Nations..........................................................5-5
5.3.2 Expected First Nation Impacts ........................................................................5-6
5.3.3 First Nation Consultation Activities .................................................................5-7
5.3.4 Presentation of Project at Core Committee Meeting.......................................5-8
5.3.5 Project Notification Letter from BC Hydro .......................................................5-8
5.3.6 Project BCEAO Amendment...........................................................................5-9
5.3.7 Future First Nation Consultation Plan ...........................................................5-10
5.3.8 Adequacy of First Nations Consultation........................................................5-10 List of Tables
Table 5-1 First Nations and Tribal Councils Identified for Consultation .......................5-6
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-2
5.1 Introduction 1
This chapter discusses the consultation processes BC Hydro has undertaken with First 2
Nations and public stakeholders to identify issues specific to the Project. 3
5.2 General Consultation 4
As described in previous chapters, the addition of GIS to lead shaft 3 will reduce the 5
likelihood of outages caused by equipment failures. Three lead shafts will also be required if 6
BC Hydro installs an additional generating unit at Mica. As lead shaft 3 may be used for 7
future interface and operations of Mica Units 5 and 6, the Project was included as a 8
component of the Mica Units 5 and 6 project description to be considered for review under 9
the BCEAA process. Pursuant to the BCEAA process, BC Hydro offered and conducted a 10
range of consultation activities to provide information sharing opportunities for interested 11
stakeholders and First Nations to understand and comment on the Project. This section 12
describes consultation activities associated with the BCEAA process, and those that were 13
components of BC Hydro’s consultative committee process. 14
5.2.1 Environmental Assessment 15
In March 2008, BC Hydro submitted project descriptions to the BCEAO to seek an BCEAC 16
for the Mica Units 5 and 6 projects. The project descriptions included an overview of the 17
Project and described the main components. A number of procedural documents were 18
issued by the BCEAO which made reference to the Project. 19
In July 2008, the BCEAO convened a project working group meeting to discuss the 20
proposed project (including Mica Units 5 and 6) and draft procedural documents. 21
Government agencies, stakeholders, First Nations and Tribal Councils were invited to attend 22
and provide comments. No issues or comments were raised in regards to the Project. 23
On September 17, 2008, BC Hydro and the BCEAO conducted a site visit to Mica. All 24
members of the project working group, which included the 25 First Nation and Tribal 25
Councils identified in the BCEAA section 11 and 13 Procedural Orders were invited to 26
attend. Representatives of the BCEAO, the BC Ministry of Environment, the Columbia 27
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-3
Shuswap Regional District, Okanagan Nation Alliance, Ktunaxa Nation Council, Little 1
Shuswap, Splatsin, as well as some BC Hydro staff at Mica participated. The location of the 2
current building and proposed extension of the switchgear building were pointed out. No 3
concerns were raised by any of the attendees. 4
Since the Project was included in the Mica Units 5 and 6 BCEAA process, replacement of 5
the GIS equipment could not start prior to the issuance of the Environmental Assessment 6
Certificate. However, due to a significant extension of the Mica Units 5 and 6 First Nation 7
consultation timeline, BC Hydro requested the BCEAO approve an amendment to remove 8
the Project from the BCEAA process to preserve the Project schedule (Appendix K-1). 9
It should be noted that BC Hydro made the request for the amendment after most of the pre-10
application consultation had occurred for the Mica Units 5 and 6 projects, during which no 11
concerns had been raised by First Nations. On April 17, 2009, the BCEAO approved the 12
request and granted BC Hydro an amending order, which removed the Project from the 13
Mica Units 5 and 6 BCEAA process (Appendix K-3). The steps taken by the BCEAO to 14
consult with First Nations prior to issuing the amendment are outlined in section 5.3.4. 15
5.2.2 Core Committee 16
A key consultative tool for the Mica Units 5 and 6 project, was the core committee process 17
which began in January 2008 and completed in May 2009. This process was developed by 18
BC Hydro to provide a facilitated and structured process of committees and meetings to 19
integrate First Nation and stakeholder values into environmental assessment and water use 20
planning decisions related to the potential incremental impacts of the Mica Units 5 and 6 21
project. Participants included: 22
federal and provincial agencies; 23
local government representatives; 24
First Nations; 25
former Columbia Water Use Plan and Revelstoke Unit 5 Core Committee members; 26
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-4
not-for-profit organizations; and 1
interested community individuals. 2
On January 29, 2009, during a core committee meeting at the City of Revelstoke, BC Hydro 3
made a presentation on the Project. BC Hydro’s presentation materials for this meeting are 4
contained in Appendix J-3. In the presentation BC Hydro explained: 5
the purpose of the Project and the switchgear building extension; 6
the need for the switchgear maintenance and refurbishment work; 7
the connection to the Mica Units 5 and 6 project; 8
the expectation that there would be no environmental or heritage impacts; 9
the contract and procurement timelines; and 10
the possibility of employment opportunities. 11
Participants in the meeting, including First Nations representatives, did not raise any 12
concerns related to the Project. 13
5.2.3 Future Public Consultation 14
In support of the Mica Units 5 and 6 projects, BC Hydro created a webpage for the public to 15
view project information. On May 29, 2009, BC Hydro posted Project content on its website 16
and sent local stakeholders a newsletter about current and planned upgrades at Mica. 17
Further newsletters and website updates will be provided throughout the Project as 18
appropriate. 19
5.3 First Nations Consultation 20
This section identifies the First Nations that may be impacted by the Project, describes the 21
First Nation consultation activities in support of the Project, including the consultation that 22
has taken place and proposed activities as the Project proceeds. 23
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-5
The objectives of this consultation in respect of those First Nations, whose rights or interests 1
are potentially impacted by the Project, are to: 2
ensure that the First Nations are provided with all appropriate and relevant information 3
associated with the Project so that the First Nations understand the nature and potential 4
impacts of the Project; 5
receive any input from the First Nations on the Project; 6
ensure that any potential adverse and beneficial impacts on the First Nations’ 7
rights or interests are clearly understood by BC Hydro and the First Nations; and 8
where First Nations are potentially adversely impacted by the Project, work with the First 9
Nations to identify possible strategies for avoiding or mitigating such impacts and, to the 10
extent avoidance or mitigation of impacts is not possible, discuss and develop with the 11
affected First Nation, other potential accommodation options. 12
5.3.1 Identification of Interested First Nations 13
Mica is located on the Columbia River about 130 km upstream from Revelstoke, and 135 km 14
upstream of the City of Revelstoke (refer to Figure 3-1). Based on a review of consultative 15
boundary maps provided by the Province, and maps of Statement of Intent (SOI) areas 16
submitted by First Nations in the British Columbia Treaty Commission process, BC Hydro 17
determined that the Project lies within the collective traditional territory of the Ktunaxa, 18
Okanagan, and Shuswap Nations which are comprised of 29 First Nations and four Tribal 19
Councils. Additionally, Lheidli T’enneh First Nation’s consultative boundary is situated just 20
north of Mica. 21
Through information sharing and discussions with First Nations, Tribal Councils, and the 22
BCEAO, 22 First Nations and three Tribal Councils were identified as having a potential 23
interest in the Mica Projects (Mica Units 5 and 6, and GIS). Table 5-1 lists the First Nations 24
and Tribal Councils that were identified and subsequently contacted. 25
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-6
Table 5-1 First Nations and Tribal Councils Identified for Consultation 1
First Nation/Tribal Council/Association Shuswap Nation Tribal Council
(SNTC) Ktunaxa Nation Council (KNC) Okanagan Nation Alliance (ONA) Other
Adams Lake Columbia Lake Okanagan Lheidli T’enneh
Bonaparte Lower Kootenay Osoyoos Kamloops St. Mary’s Lower Similkameen
Little Shuswap Tobacco Plains Penticton Neskonlith Upper Nicola Shuswap Upper Similkameen Simpcw Westbank
Skeetchestn Splatsin
Whispering Pines
5.3.2 Expected First Nation Impacts 2
BC Hydro anticipates that the Project will have minimal, if any, adverse impacts on First 3
Nations or Tribal Councils for the following reasons: 4
Most of the work on the Project will occur underground within the existing powerhouse 5
and three lead shafts; 6
The Project will have no impact on the Kinbasket or Revelstoke reservoirs; 7
Although the Project will have an incremental footprint impact due to an extension of the 8
existing switchgear building: 9
the works will occur on previously disturbed lands owned by BC Hydro; and 10
the extension area was assessed under the Mica Units 5 and 6 BCEAA process and 11
no potential heritage or environmental impacts or other concerns were identified. 12
Environmental and social impacts are addressed in section 3.6. 13
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-7
5.3.3 First Nation Consultation Activities 1
The First Nations and Tribal Councils were contacted to determine their interest and 2
requirements for consultation and communications. Consultation activities included the 3
following: 4
Consultative Processes: All 25 First Nations and Tribal Councils were invited to 5
participate as members of the BCEAA, core committee or sub-committee process, and/or 6
engage in consultation directly with BC Hydro. 7
Capacity Funding: To facilitate participation of First Nation and Tribal Council 8
representatives in meaningful consultation and BCEAA activities, BC Hydro offered initial 9
capacity funding to ensure participants were provided with opportunities to review project 10
materials, determine level of interest, and identify potential project-related impacts. 11
BC Hydro advised First Nations and Tribal Councils that should they require more 12
extensive resources, further capacity funding would be provided though Comprehensive 13
Capacity Funding Agreements (CCFAs). Opportunities to receive capacity funding were 14
outlined in project letters, discussed during follow-up phone calls and further explained 15
throughout all of the project meetings. BC Hydro has an ongoing commitment that should 16
any First Nation or Tribal Council require capacity funding, BC Hydro is prepared to work 17
with them to ensure they have sufficient resources to facilitate their participation in 18
consultation activities. 19
Participation in Environmental Studies: BC Hydro invited interested First Nations or 20
Tribal Councils by letter and through follow-up phone calls to participate on field teams to 21
conduct wildlife and vegetation, fisheries, and archaeology studies. Ktunaxa Nation 22
Council, Okanagan Nation Alliance, Splatsin, Little Shuswap, and Adams Lake were 23
active participants as determined by their interest. Field studies included an assessment 24
of the proposed area for the switchgear building extension. All 25 First Nations and Tribal 25
Councils were provided with copies of the completed project studies for review and 26
comments. BC Hydro offered to engage in direct consultation to review and address any 27
issues that were identified. Upon review of the completed project studies, no First Nations 28
or Tribal Councils raised any issues specific to the Project. 29
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-8
Traditional Use Studies: BC Hydro offered capacity funding for First Nations and Tribal 1
Councils to gather and submit traditional use information to inform BC Hydro’s 2
understanding of potential impacts. BC Hydro provided terms of reference which outlined 3
the study area which should include the proposed area for the switchgear building 4
extension. Six First Nations and two Tribal Councils representing ten additional First 5
Nations are currently involved in gathering traditional use information. The deadline for 6
Final Reports is October 2009. Any issues identified in these reports that relate to the 7
Project will be addressed accordingly. 8
Site Visits: As outlined in section 5.2.1, on September 17, 2008, the BCEAO hosted a 9
tour of Mica. Members of the Okanagan Nation Alliance, Ktunaxa Nation Council, Little 10
Shuswap, and Splatsin attended. During the site visit the location of the switchgear 11
building extension was pointed out. No concerns were raised by any of the attendees. 12
A separate site visit was requested by the Ktunaxa Lands and Resources Committee and 13
was held on May 26, 2009. As part of a comprehensive tour to view the major 14
components of the Mica Units 5 and 6 projects, participants viewed the three lead shafts 15
from the powerhouse to the interconnection point at the existing switchgear building, the 16
flange sections where much of the leakage of SF6 gas seems to occurs were pointed out, 17
and the site for the proposed switchgear building extension was inspected for potential 18
environmental impacts. No issues were raised by any of the participants. 19
5.3.4 Presentation of Project at Core Committee Meeting 20
As outlined in section 5.2.2, a presentation on the Project was given at the January 29, 2009 21
Core Committee meeting at the City of Revelstoke. This meeting was attended by 22
environmental technical representatives for the Ktunaxa Nation Council and the Okanagan 23
Nation Alliance. None of the core committee participants raised any concerns related to the 24
Project. 25
5.3.5 Project Notification Letter from BC Hydro 26
On February 19, 2009, BC Hydro sent a “Switchgear Replacement Project” Notification 27
Letter (Notification Letter) to all 25 First Nations and Tribal Councils indicating BC Hydro 28
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-9
would be performing work to extend the switchgear building to accommodate the installation 1
of new and replacement switchgear (Appendix J-2). The Notification Letter included: 2
a Google Earth Photo of Mica GS Showing switchgear building; 3
a photo of the existing switchgear building; 4
a rendering showing what the switchgear building will look like with the extension; and 5
a diagram showing an architectural view of how the lead shafts connecting the 6
switchgear building to the underground powerhouse. 7
In the Notification Letter, BC Hydro provided an overview of the environmental assessment 8
findings, offered capacity funding, and invited First Nations and Tribal Councils to contact 9
BC Hydro if they are concerned that the Project may affect Aboriginal rights or interests. 10
On March 31 and April 1, 2009, follow-up phone calls were made to all 25 First Nations and 11
Tribal Councils identified in Table 5-1 to confirm their receipt of the Notification Letter and to 12
determine if they had any questions or concerns. 13
A complete list of the record of contact is included in Appendix J-1. 14
No issues were raised by any of the First Nations or Tribal Councils and no requests were 15
made to receive any capacity funding. As of the June 25, 2009, no further comments or 16
issues have been raised by First Nations or Tribal Councils either directly to BC Hydro or 17
through ongoing consultation meetings in support of Mica Units 5 and 6. 18
5.3.6 Project BCEAO Amendment 19
As described in section 5.2.1, on April 17, 2009, the BCEAO issued an amendment order 20
(Appendix K-3) removing the switchgear building extension from the Mica Units 5 and 6 21
BCEAA process. 22
Prior to this, on March 23, 2009, the BCEAO sent an email with a copy of the draft 23
amending order to First Nations and Tribal Councils listed in Table 5-1 to provide an 24
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-10
opportunity for representatives to raise any questions or concerns (included in 1
Appendix K-2). The email outlined the background and scope of the Project and the 2
switchgear building extension, reviewed completed activities to assess the potential for 3
environmental impacts, and highlighted no issues were raised during the site visit or through 4
the core committee process. 5
First Nations and Tribal Councils were asked to contact the BCEAO prior to April 3, 2009 6
with any comments or specific concerns about the removal of the switchgear building 7
extension work from the Mica Units 5 and 6 BCEAA approved Terms of Reference and the 8
draft amending order. No First Nations responded with any comments or concerns. 9
5.3.7 Future First Nation Consultation Plan 10
BC Hydro will continue consultation with First Nations and Tribal Councils as the Project is 11
implemented. BC Hydro will provide additional information updates when applicable and will 12
respond to any questions of information requests that may be received regarding the 13
Project. BC Hydro will work to understand and address any concerns or issues that are 14
raised by First Nations and Tribal Councils and where appropriate, BC Hydro will engage in 15
discussions with First Nations and Tribal Councils to further identify means to mitigate, 16
minimize and otherwise accommodate any concerns or issues relating to the Project. 17
5.3.8 Adequacy of First Nations Consultation 18
Taking into consideration the following factors, BC Hydro is of the view that the consultation 19
conducted for the Project is adequate: 20
Information shared through the BCEAA, consultative committee processes, Notification 21
Letters, field work, and site visits provided adequate opportunities for First Nations and 22
Tribal Councils to understand the scope of the Project and to raise comments or 23
concerns; 24
No First Nations or Tribal Councils expressed any concerns or interest in engaging in 25
consultation or discussions following a Project Notification Letter that was sent by 26
Chapter 5 - Public and First Nations Consultation
Mica Gas Insulated Switchgear Project
5-11
BC Hydro to all 25 First Nations and Tribal Councils, and subsequently followed-up by 1
phone; 2
First Nations and Tribal Councils were offered capacity funding to review Project 3
materials, participate in the BCEAA and consultative committee processes, attend site 4
visits, and engage in community and Chief and Council discussions to identify issues 5
relating to the Project; 6
No First Nations or Tribal Councils expressed any concerns or interest in engaging in 7
consultation or discussions with the BCEAO following a Project amendment letter that 8
was sent by BCEAO to all 25 First Nations and Tribal Councils; 9
It is anticipated that the Project will have minimal, if any, adverse impacts in First Nations 10
or Tribal Councils for the reasons described in section 5.3.2; 11
BC Hydro has been consulting with the identified First Nations since March 2008 and will 12
continue to inform First Nations about the Project through the implementation phase as 13
required and will address any issues as they arise; and 14
BC Hydro will address any issues connected to Project that arise from the Traditional Use 15
Studies (TUS) and/or Aboriginal Interest and Use Studies (AIUS). 16
Mica Gas Insulated Switchgear Project
Chapter
6
Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-i
Table of Contents
6.1 Introduction.................................................................................................................6-1
6.2 Definition Phase Risks................................................................................................6-1
6.2.1 Investment at Risk ..........................................................................................6-1
6.2.2 Environmental Regulatory...............................................................................6-2
6.2.3 First Nations....................................................................................................6-2
6.3 Implementation Phase Risks ......................................................................................6-3
6.3.1 Safety Risks ....................................................................................................6-3
6.3.2 Security Risk ...................................................................................................6-5
6.3.3 Capital Cost Risk ............................................................................................6-5
6.3.4 Schedule Risk During Construction ................................................................6-6
6.3.5 Risk of Labour Unrest during Construction .....................................................6-7
6.3.6 Congestion in the Mica Powerhouse during Construction ..............................6-8
6.3.7 Environmental Risk during Construction.........................................................6-8
6.3.8 SF6 Risk During Construction .........................................................................6-9
6.3.9 Contractor Credit/Counterparty Default ..........................................................6-9
6.3.10 Commissioning Risk .....................................................................................6-10
6.4 Operations Risks ......................................................................................................6-10
6.4.1 Failure and Outage Risk ...............................................................................6-10
6.4.2 Environmental Risk .......................................................................................6-10
6.4.3 Operating and Maintenance Costs ...............................................................6-11
6.5 Risk Summary ..........................................................................................................6-11 List of Tables
Table 6-1 Mica Project Risks Summary .....................................................................6-11
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-1
6.1 Introduction 1
This chapter describes the Project Definition and Implementation phase risks as well as 2
operational risks once the Project is complete. It does not address the risk to BC Hydro and 3
its customers of any shortfall in capacity that might occur as a result of a failure of the 4
Mica GIS. 5
Over the life of the Project, and consistent with BC Hydro’s standard project management 6
practices and procedures, risk screenings have been conducted to identify the major Project 7
risks and their associated mitigation strategies. This chapter provides a summary of the 8
material risks, plans to manage these risks, and any residual risks. 9
The risks associated with the Project are considered within the phases of the project life 10
cycle. In the Definition phase, the major risks are associated with the design, estimating, 11
and tendering processes. The main risks for the Implementation phase are construction 12
related. Equipment risks once in service are primarily those associated with performance 13
and maintenance of the GIS. 14
6.2 Definition Phase Risks 15
Although normally an Implementation phase activity, the Project design, supply and install 16
contract was tendered in December 2008 during the Definition phase of the Project to 17
provide for greater cost certainty before deciding to proceed to Implementation phase. 18
Accordingly this reduced the cost risk. Further development risks arise as a result of the 19
regulatory approval process and related First Nations consultation. These risks are 20
addressed in the subsections below. 21
6.2.1 Investment at Risk 22
BC Hydro seeks per section 44.2(3)(a) of the UCA that the BCUC accepts that the capital 23
expenditures for the Project are in the public interest. If approval for Implementation phase 24
is not granted, the remaining Project investment is at risk. Rather than proceed, BC Hydro 25
may defer the Project. If the Project is deferred there will be investment at risk. If the Project 26
is deferred in January 2010 then the investment at risk is estimated to be $43 million. If the 27
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-2
Project is deferred in April or December 2010 then the investments at risk would be 1
$58 million or $91 million respectively. 2
Although, BC Hydro awarded the contract for the GIS design, supply and install to MEPPI, it 3
retains the right to terminate the contract in the event BCUC or any other approval is not 4
granted. 5
6.2.2 Environmental Regulatory 6
There are no major environmental regulatory approvals required for the Project. However, 7
parts of the Project were included in the Mica Unit 5 project under the Mica Units 5 and 6 8
BCEAA review process – namely the addition of GIS to lead shaft 3, and the extension of 9
the switchgear building for GIS addition to lead shaft 3. These parts of the Project are 10
included in the Mica Unit 5 project under BCEAA because they are required for the 11
operation of Mica Units 5 and 6. Under BCEAA, the scope of a project must include all parts 12
of the project, and no part of the project can be constructed without the BCEAA approval 13
(certificate). So, if the Mica Unit 5 BCEAA process or certificate is delayed, it could delay the 14
addition of GIS to lead shaft 3, which is the necessary first stage of the Project. 15
This risk was partially mitigated by an April 17, 2009 Order under BCEAA (provided in 16
Appendix K-3), removing the switchgear building extension from the scope of the 17
Mica Unit 5 project. BC Hydro applied for this order because a delay in the BCEAA schedule 18
for the Mica Unit 5 project to accommodate further First Nations consultation put the 19
switchgear building construction schedule at risk. 20
6.2.3 First Nations 21
Inadequate First Nations consultation is a risk to regulatory approvals and the Project 22
schedule. BC Hydro consulted First Nations, as described in Chapter 5. BC Hydro submits 23
that the consultation conducted is adequate and meets the current standard for a 24
refurbishment project that is not adding capacity. No First Nations have indicated any 25
concerns with the Project, or any desire for further consultation or accommodation. 26
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-3
However, there is a risk that a First Nation could challenge the adequacy of consultation. 1
This may impact the BCUC approval process and consequently BC Hydro’s decision to 2
proceed with the proposed Project schedule. This risk is mitigated in part by the ongoing 3
consultation and updates that BC Hydro will be conducting on all the projects planned for 4
Mica over the coming years. This consultation is expected to include funding and 5
employment opportunities for those First Nations that are interested. 6
6.3 Implementation Phase Risks 7
The following are the risks that may occur during Implementation phase. The key risks at 8
this stage of the Project relate to safety, environment, cost escalation, schedule delays and 9
labour unrest. 10
6.3.1 Safety Risks 11
Safety risks are those with the potential to result in harm to workers or members of the 12
public. During construction, safety risks are being managed through the following 13
preventative measures: 14
During the Definition phase of the Project BC Hydro conducted a safety risk analysis 15
(safety hazard assessment), the results of this analysis will be communicated to 16
contractors so that BC Hydro’s recommendations may be incorporated into work plans; 17
BC Hydro conducted further safety reviews that incorporated both construction and 18
on-going maintenance safety considerations into the design of the new equipment, 19
facilities, and work plans, for inclusion in the tender specifications; 20
Tender documents include a copy of BC Hydro’s site specific Safety Management Plan, 21
and contractors are required to submit their own safety management plan in conformance 22
that: 23
indicates how the contractors would comply with BC Hydro’s “Site Specific Safe Work 24
Procedures”, as well as safety standards issued by WorkSafe BC and BC Hydro; 25
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-4
indicates how the contractors would comply with the BC Hydro Safety Management 1
Plan; and 2
provides for worker safety training. 3
During construction there will be dedicated construction and safety officers on site who 4
are further supported by BC Hydro’s Coordinator of Occupational Safety and Health 5
assigned to site operations. These representatives will monitor work to ensure that the 6
contractors are following safety plans and will intervene if unsafe conditions are identified. 7
During construction, work will be undertaken near live transformers and within the confines 8
of the underground transformer chamber. There is a low risk that a transformer may fail 9
catastrophically resulting in fire or explosion that causes harm to workers. A risk analysis 10
was undertaken to identify potential causes of failure and define preventative and mitigating 11
measures. Such measures include: 12
development of procedures for running the transformers under low load during periods of 13
construction; 14
monitoring the health of the transformers continually during the Project; 15
protecting the transformers from accidental contact from equipment, including the 16
installation of physical barriers; 17
providing enough air to ensure maximum venting of smoke from the transformer chamber 18
in the event of a fire; 19
making mandatory personal protective equipment for working in the transformer 20
chamber; and 21
development of an emergency evacuation plan for the people who will be working in the 22
transformer chamber during construction. 23
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-5
6.3.2 Security Risk 1
During construction there is an increased security risk. BC Hydro will assess the risk and 2
develop a security plan that will include measures such as: 3
training of on-site operations staff and contractors on site-security; 4
providing extra security guards where appropriate; 5
providing visible identification for staff and construction workers; and 6
installing new access locks on gates and doors. 7
6.3.3 Capital Cost Risk 8
As identified in Chapter 3, BC Hydro has completed an Implementation phase cost estimate 9
with a range of -10 per cent/+15 per cent. Cost risks are being managed by: 10
tendering the majority of work prior to the Implementation phase. BC Hydro now has a 11
fixed price contract with MEPPI for the supply and install of the 500 kV GIS; 12
obtaining fixed price bids for the switchgear building extension; 13
clearly defining the scope of the Project; 14
preparing unambiguous specifications; 15
basing the cost estimate upon costs from previous comparable projects. For instance the 16
Revelstoke Unit 5 project and Seven Mile GS Unit 4 project both installed 500 kV GIS 17
similar to the equipment to be installed at Mica; 18
using appropriate contingencies and reserves based on detailed cost analysis using a 19
Monte Carlo simulation that takes into consideration uncertainty in the estimates. Costs 20
are estimated over a possible range with the most likely cost being the Project Expected 21
Cost; and 22
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-6
planning implementation work early and thoroughly so as to reduce the number of 1
equitable adjustments. 2
6.3.4 Schedule Risk During Construction 3
There is a risk that the implementation of all or portions of the Project are delayed. An 4
outage of four months for two units is planned in each of spring 2011 and 2012. If work does 5
not proceed as planned, there is a risk that the outage will be extended beyond the 6
four-month period. The outages are planned during the spring months when BC Hydro’s 7
domestic demand is typically low, and can be serviced by two units. However, if the outage 8
extends beyond this period the opportunity cost to BC Hydro and ratepayers could be high. 9
These costs could be as low as $3 million or as high as $20 million for the month of August, 10
depending on the market. 11
The following are measures taken to mitigate the risk of schedule delays causing extended 12
outages: 13
bonus payments and liquidated damages were included in the GIS design, supply and 14
install contract to better ensure equipment is delivered on a timely basis and to reflect the 15
importance of meeting the schedule; 16
Implementation phase work was planned well in advance and in detail; 17
BC Hydro plans to prepare the site prior to the start of GIS installation; 18
the schedule was planned to ensure significant contingency to avoid the need to spill 19
water in the event of a delay; and 20
a detailed schedule analysis was conducted using Monte Carlo simulation to represent 21
the potential best, worst and most likely scenarios for work completion. 22
BC Hydro reserves the right to decide whether or not it deems the vendor to be adequately 23
prepared to start work at milestone dates, particularly prior to decommissioning and removal 24
of existing equipment. 25
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-7
Delays may also be initiated by BC Hydro due to water conditions. Should water conditions 1
throughout the Province be such that Mica will be required to meet domestic demand, 2
BC Hydro reserved the right to defer the construction. 3
There is also risk of schedule delay from a Mica failure. With two units out of service during 4
construction, there is a risk that failure in the other two units may impact BC Hydro’s ability 5
to generate electricity from Mica. Also, a failure in the GIS in lead shaft 1 or 2 could require 6
up to 12 weeks for repair. 7
The risk of failure of an operating unit has been mitigated with the following measures: 8
maintenance on equipment in the transformer chamber prior to the start of construction; 9
procedures developed for the continuance of Project work in the event of a failure of one 10
of the generating units; 11
the Project will have limited dependence on Mica equipment and tools that may be 12
required in the event of a unit outage. MEPPI are required to supply the tools and 13
equipment required to complete their work; and 14
there is a communications plan between the Mica operations personnel and the Project 15
personnel that includes a plan to escalate unresolved issues to senior management for 16
resolution. 17
The consequence of failure of GIS in lead shafts 1 or 2 during construction will be reduced 18
by installing GIS in lead shaft 3 at the beginning of the Project. 19
6.3.5 Risk of Labour Unrest during Construction 20
Labour unrest can lead to construction delays. BC Hydro has agreed to apply the Columbia 21
Hydro Constructors22 agreement (CHC) to the Project because the Project and the 22
Mica Units 5 and 6 project may occur on site simultaneously and some GIS work supports 23
the Mica Units 5 and 6 projects. The Mica Units 5 and 6 projects are named projects under 24
22 Columbia Hydro Constructors is a subsidiary of BC Hydro.
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-8
the Collective Agreement between the Allied Hydro Council (AHC) and the CHC. The site 1
trade labour required for work in connection with a named project must be supplied by the 2
unions in compliance with the Collective Agreement. The Collective Agreement contains a 3
no-strike clause and provisions to address working conditions. Therefore by applying the 4
CHC agreement to the Project, the risk of labour unrest is mitigated. 5
6.3.6 Congestion in the Mica Powerhouse during Construction 6
Mica has an underground powerhouse with limited space and limited access. Construction 7
for the Project may occur at the same time as some of the Mica Units 5 and 6 project 8
construction. Between the two projects and the day-to-day operation of Mica, there is the 9
potential for congestion in the powerhouse and routes to the powerhouse. This risk is being 10
mitigated by: 11
the Implementation phase work has been thoroughly planned to ensure there are 12
appropriate allocated work areas for all activities occurring at Mica; 13
large components will be preassembled outside the powerhouse; 14
a traffic control plan has been developed for workers and material; 15
work areas and access routes have been clearly delineated; and 16
there will be coordinated bus transportation between Mica Village and Mica. 17
6.3.7 Environmental Risk during Construction 18
Environmental incidents on site during construction could cause costly delays and have 19
further cost implications. The agreements that the major Project contractors enter into with 20
BC Hydro include an Environmental Management Plan that establishes requirements and 21
prohibitions necessary to ensure environmental protection during construction. As well, for 22
activities posing particularly significant environmental risk, contractors are required to submit 23
to BC Hydro an Environmental Protection Plan that provides how those activities will be 24
conducted so as to meet the requirements of the BC Hydro Environmental Management 25
Plan. During construction BC Hydro will have an on-site Environmental Monitor to ensure 26
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-9
appropriate environmental management. These measures mitigate the risk of an 1
environmental incident. 2
6.3.8 SF6 Risk During Construction 3
Two risks related to SF6 are present for this Project. The first, which can impact the 4
schedule, is related to removing the used SF6 from the equipment to be decommissioned. 5
To do this, good quality and adequate capacity gas carts are required. Inadequate gas carts 6
triple the time it will take to remove the used SF6 from the GIS as it is being 7
decommissioned. MEPPI is required to supply its own gas carts of adequate capacity and 8
quality. These gas carts will be delivered to Mica in advance of the work so BC Hydro has 9
the opportunity to determine that they are adequate. If the gas carts are found to be 10
inadequate, there will be sufficient time for alternative gas carts to be delivered to Mica. The 11
SF6 removed from the equipment to be decommissioned will be recycled by MEPPI. 12
The second risk related to SF6 is related to it being a GHG. Releases of SF6 impact the 13
environment and affect BC Hydro’s ability to meet its GHG inventory targets. SF6 releases 14
are tracked by BC Hydro as part of its GHG inventory. They are not currently regulated other 15
than for reporting purposes, but may be regulated in the future. BC Hydro has addressed 16
this risk with contractual terms, including the requirement for a specific SF6 management 17
plan, in the contract with MEPPI. These terms require the contractor to take responsibility for 18
the cost of penalties or GHG offsets in the event of a negligent or uncontrolled release of 19
SF6 arising from the contractor’s work. 20
6.3.9 Contractor Credit/Counterparty Default 21
There is the potential for a contractor to experience credit failures that affect its ability to 22
deliver on its obligations to BC Hydro. BC Hydro’s normal tender procedures address this 23
risk as follows: 24
the tender documents require all bidders to submit bid security with their tenders in the 25
form of a bid bond, letter of credit, or certified cheque in the amount equivalent to 26
10 per cent of the total tendered amount; 27
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-10
BC Hydro reviews the preferred contractor’s capacity to perform the scope of work 1
detailed in the contract including its financial capacity and credit rating. BC Hydro’s 2
Treasury group performs a background check on all bidders, including a review of each 3
company’s financial structure; and 4
the award of contracts are subject to the contractor submitting performance security in 5
the form of performance and labour and materials bonds or letter of credit in the amount 6
of 17.5 per cent of the total contract price supported by a third party guarantee. 7
6.3.10 Commissioning Risk 8
There is a risk that the new GIS will not perform to specifications. This risk is mitigated 9
through the procurement process in which BC Hydro specifies the standards required and 10
evaluates the vender’s qualifications bids, including its experience with past similar projects. 11
At the commissioning stage the new GIS will be subject to high voltage testing on 12
installation to ensure its suitability for service. Once commissioned, the GIS will be subject to 13
guarantees and manufacturer warranties. 14
6.4 Operations Risks 15
6.4.1 Failure and Outage Risk 16
The risk of an outage on the new GIS will be less than the risk of an outage on the current 17
aged GIS. The new equipment will have a manufacturer’s estimated life of 50 years and is 18
expected to be reliable. 19
There will also be significant improvement in monitoring and detection devices that will 20
reduce the potential impacts of failure. Plus, the addition of GIS to lead shaft 3 provides an 21
additional conductor to transfer energy from the Mica powerhouse. If a failure occurs in one 22
lead shaft or if maintenance is being performed, there is more redundancy. 23
6.4.2 Environmental Risk 24
As described in Chapter 4, because of its age and deterioration, the current GIS leaks SF6 25
which impacts BC Hydro’s GHG inventory and targets. These emissions will be reduced with 26
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-11
the installation of new GIS with a much improved leakage rate. BC Hydro has specified that 1
MEPPI must meet standards of 0.5 per cent or less per year. But, based on typical 2
performance of modern equipment it is reasonable to expect a leakage rate of near zero. 3
6.4.3 Operating and Maintenance Costs 4
Design improvements have reduced the risk of an increase in operating and maintenance 5
costs. BC Hydro expects no material change in planned maintenance costs. The 6
maintenance on existing GIS requires two to three person days per month for inspection and 7
an annual inspection of lead shaft lifts. With this Project, while there will be more equipment 8
length to inspect and maintain as well as an additional lift, it is expected that the cost of this 9
work will be offset by improvements to monitoring systems as well as equipment that is 10
designed for easier access. Training for plant personnel on new equipment has been 11
included in the contract with MEPPI. 12
6.5 Risk Summary 13
Table 6-1 is a summary of the material risks for the Project. 14
Table 6-1 Mica Project Risks Summary 15
Risk Mitigation strategy Frequency and Consequence
Definition Phase First Nations consultation on switchgear building extension not considered adequate, resulting in a schedule risk.
All local First Nations notified, and no First Nations have indicated any concerns with the Project, or any desire to consult further.
Moderate probability Moderate Impact to schedule
Implementation Phase Fire and smoke in transformer chamber during construction due to catastrophic failure of transformers resulting in a safety risk.
Real-time monitoring of transformer health.
Perform transformer maintenance prior to the start of construction.
Lower transformer load during construction.
Emergency egress plans.
Procedures for plant and construction personnel working in the area.
Low probability High impact
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-12
Risk Mitigation strategy Frequency and Consequence
During construction, there is an increased security risk
The Project will as a minimum:
provide extra security guards,
provide for identifying signage on hard hats, and
install new access locks on gates and doors.
Medium probability Low impact
Risk that contractors will not be able to meet scheduled milestones and work will extend beyond scheduled outage windows.
Write liquidated damages and bonuses into the GIS contract.
Do not allow work to start if all required equipment and tools are not onsite prior to an outage.
Moderate probability Moderate impact
Risks that implementation costs will exceed estimates.
Obtaining firm pricing on major contracts.
Prepare detailed cost estimates based upon tendered prices, and costs incurred on previous, comparable projects.
Detailed cost analysis using a Monte Carlo simulation that takes into consideration uncertainty in the estimates. Costs are calculated over a possible range with a most likely at Expected Cost.
Medium probability Moderate impact
Labour relations problems due to differences in agreements between those working on GIS and those working on Mica Units 5 and 6 could cause delays.
Inclusion of Project under CHC agreement.
Low probability Low impact
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-13
Risk Mitigation strategy Frequency and Consequence
Congestion in powerhouse due to two large projects (Mica GIS and Mica Units 5 and 6) occurring at the same time leading to safety concerns and/or delays.
Thoroughly plan the implementation work.
Preassemble large components outside the powerhouse.
Develop a traffic control plan.
Delineate work areas and access routes have been clearly delineated.
Low probability Low impact
Risk of damage to environment or non-compliance with environmental regulatory requirements resulting in delays and/or increased costs.
BC Hydro has prepared an Environmental Management Plan (EMP) that must be complied with throughout the project.
The contractors must submit Environmental Protection Plans conforming to the BC Hydro EMP.
BC Hydro will engage an Environmental Monitor during construction to oversee implementation and conformance with the plans and general ensure environmental protection.
Low probability Low impact
Risk of a significant uncontrolled release of SF6 that impact the environment.
MEPPI is required to provide equipment before the start of work for BC Hydro inspection.
MEPPI is required to submit a SF6 management plan for BC Hydro’s approval prior to the commencement of construction.
Under the contract MEPPI assumes the risk of any releases of SF6.
Low probability Low impact
Contractors experience credit and cash flow issues that could affect their ability to perform.
Tender documents require all bidders to submit bid security.
A background financial check is preformed on all bidders and the preferred bidder’s financial capacity is reviewed by BC Hydro prior to award.
BC Hydro obtains performance security in the form of labour and materials bonds or a letter of credit in the amount of 17.5 per cent of the total contract price supported by a third party guarantee.
Low probability Low impact
Equipment fails during commissioning, thus affecting operation schedule
Warranty clauses in contract.
Commissioning tests have been defined.
Moderate probability Low impact
Chapter 6 - Project Risks and Risk Management
Mica Gas Insulated Switchgear Project
6-14
Risk Mitigation strategy Frequency and Consequence
Operations Phase The equipment does not perform as expected and the number of unplanned outages increases
Warranty provisions in the contracts. Low probability High impact
Risk of SF6 releases during operation that impact the environment.
Train staff on the operation and maintenance of the new equipment.
The new equipment is subject to SF6 standards specified in the tender.
Warranties against SF6 leakage in any amounts exceeding industry standards.
Low probability Low impact
The cost of operation and maintenance of the equipment increases
Use of modern equipment and design reduces the time required for maintenance.
Include training for plant personnel in the operation and maintenance of the new equipment.
Low probability Low impact
Mica Gas Insulated Switchgear Project
Appendix
A
Glossary and Key Financial Assumptions
Glossary
This Appendix lists defined terms, acronyms and metric units used in the Application.
Authorized Cost Estimate
Authorized Cost is comprised of the Expected Cost and a Project Reserve amount.
AHC Allied Hydro Council of British Columbia, an affiliation of international building and construction trades unions.
ARN Aboriginal Relations and Negotiations, a department of BC Hydro’s EARG group.
BCEAA British Columbia Environmental Assessment Act
BCEAO British Columbia Environmental Assessment Office
BC Hydro BC Hydro is a crown corporation established in 1962 under the Hydro and Power Authority Act.
BCTC British Columbia Transmission Corporation
BCUC British Columbia Utilities Commission
BRP Base Resource Plan as defined in BC Hydro’s 2008 Long-Term Acquisition Plan filed with the BCUC.
Bulk Transmission System
This is the “backbone” or major high voltage transmission system that carries the majority of the power from the generators to the lower voltage regional systems and carries the interchanges with the U.S. and Alberta.
Bus and Buswork An electrical conductor that provides shared connection to equipment.
Bus Cone Insulators Bus cone insulators are installed throughout the bus enclosure at specified length to support the conductor and also to provide enough clearance insulation between the conductor and enclosure.
Mica Gas Insulated Switchgear Project Appendix A-1
Page 1 of 7
Capacity 1. The instantaneous power output of a generator at any given time, normally measured in kilowatts (kW) or megawatts (MW), of a power plant.
2. The instantaneous electricity demand at any given time, normally measured in kilowatts (kW) or megawatts (MW).
3. A transmission facility’s ability to transmit electricity, at any instant.
Several related terms are commonly used:
Maximum Capacity: The highest generating plant output or transmission loading that can actually be achieved in situ.
Installed Capacity: (Also referred to as Nameplate Rating). The maximum rating of a generator or transmission station equipment identified by the manufacturer under specified conditions.
Dependable Capacity: The amount of megawatts a plant can reliably produce when required, assuming all units are in service. Factors external to the plant affect its dependable capacity. For example, streamflow conditions can restrict the dependable capacity of hydro plants and fuel supply constraints can impact thermal plant dependable capacity. Planned and forced outage rates are not included.
CEAA Canadian Environmental Assessment Act
CHC Columbia Hydro Constructors Ltd., the employer of all employees working under the scope of the collective agreement applicable to the construction of the Mica dam and powerhouse.
Circuit Breakers A device used for switching-in and switching-out a piece of equipment or part of the system or for tripping when there is a fault.
CCFA Comprehensive Capacity Funding Agreement. A BC Hydro agreement to provide funding for First Nation participation in decision-making processes.
CFO Chief Financial Officer
CO2 Carbon dioxide
CRP Contingency Resource Plan as defined in BC Hydro’s 2008 Long-Term Acquisition Plan filed with the BCUC.
Mica Gas Insulated Switchgear Project Appendix A-1
Page 2 of 7
Demand The rate at which electric energy is delivered to or by a system, generally expressed in kilowatts (kW) or megawatts (MW), at a given instant or averaged over any designated time interval. Several related terms are commonly used:
Instantaneous Demand: Rate of energy delivered at a given instant.
Average Demand: The electric energy delivered over any interval as determined by dividing the total energy by the units of time in the interval.
Peak Demand: The highest electric requirement occurring in a given period (e.g. an hour, a day, month, season or year). For an electric system, it is the sum of the metered net outputs of all generators within a system and the metered line flows into the system, less the metered line flows out of the system.
Disconnect Rods Disconnect rods are insulated rods connected to the mechanism used to open and close disconnect switches.
Disconnect Switches A device used for isolating a piece of equipment or section of bus.
EAC Environmental Assessment Certificate, issued pursuant to the BC Environmental Assessment Act.
EARG BC Hydro’s Engineering, Aboriginal Relations and Generation Business Unit
Efficiency The effective rate of conversion of a natural resource (e.g. natural gas) to useable energy and capacity or the effective rate of conversion of electricity to an end use (e.g. heating).
Equipment Health Ratings (EHR)
An objective, repeatable equipment health evaluation system. EHR enables comparison of the health of BC Hydro generation assets. The EHR system uses test and inspection data and other information to determine the condition or health of assets. The result is a technical evaluation of the asset resulting in a letter grade; Good, Fair, Poor, Unsatisfactory (G,F,P,U), as follows:
• Good - no noticeable deterioration/defects;
• Fair - some deterioration/defects exist (function not affected);
• Poor - serious deterioration/defects exist in at least some portions of the asset (function affected); and
• Unsatisfactory - extensive deterioration/defects (no longer functions as required).
Mica Gas Insulated Switchgear Project Appendix A-1
Page 3 of 7
Expected Cost Estimate
Expected Cost is comprised of the Cost Estimate, Contingencies, Escalation, Overhead and Interest During Construction (IDC).
Flash-over Failure A short circuit failure caused by electrical discharge between phase to phase or phase to ground.
Forced Outage An outage caused by a permanent fault or equipment failure.
Gas Cart A portable device used for adding or removing SF6 to or from GIS.
Generator A machine that converts mechanical energy into electric energy.
GHG Greenhouse Gas
Gigawatt-Hour (GWh) One million kilowatt-hours – an amount of electric energy that will serve about 100 residential customers for one year.
GIS Gas Insulated Switchgear
GMS Gordon M. Shrum, the Generating Station at the Bennett Dam
GS Generating Station
HVAC Heating, Ventilation, and Air Conditioning
Headcover Non-rotating structural component that: 1) supports the wicket gate upper stems and the operating mechanism, 2) acts as a seal between the water passages and turbine pit, 3) is an important part of the system for managing the thrust load created by water passing through the turbine.
IDC Interest During Construction
Kilovolt (kV) A volt as a unit of electromotive force. Kilovolt is equal to 1,000 volts.
Interconnection Study A British Columbia Transmission Corporation (BCTC) study determines the technical feasibility of a customer’s facilities connecting to the BC transmission system.
IR Information Request
ISD In-Service Date
LCAM Life-Cycle Asset Management
Lead Shafts The vertical tunnels at Mica containing the gas insulated switchgear that runs from the underground transformer chamber to the above-ground switchgear building.
Mica Gas Insulated Switchgear Project Appendix A-1
Page 4 of 7
Long-Term Acquisition Plan (LTAP)
BC Hydro’s action plan to cost effectively meet growing customer electricity requirements. The LTAP sets the course for the first 10 years of a 20-year planning horizon.
Megawatt (MW) One million watts. This term is commonly used to measure both the capacity of generating stations and the rate at which energy can be delivered.
MEPPI Mitsubishi Electric Power Products, Inc.
Mica Mica Dam and Generating Station.
MSSC Most severe single contingency
NPV Net Present Value
Refurbishment Inspection and replacement of worn components.
P & C Protection and Control
Control equipment enables remote operation of the circuit breakers and disconnect switches and monitors the SF6 gas pressure. Protection equipment includes relays that detect equipment faults and automatically isolate faulted equipment from the electrical system.
Penstock Enclosed intake / pipe system that delivers water to a hydroelectric turbine.
Project The BC Hydro Mica Gas Insulated Switchgear Project
Project Initiator David Lebeter, BC Hydro’s Director of Generation Operations in the EARG line of business. Is accountable to the Project Sponsor for the definition and the justification of the Project.
Project Sponsor Chris O’Riley, BC Hydro’s Senior Vice President of EARG. Is responsible for supporting the success of the Project by acting as liaison with BC Hydro’s executive team and approving key decisions.
Reliability A measure of the continuity and quality of electric service. Reliability of service to an individual customer depends on the reliability of generation, high-voltage transmission and low-voltage distribution.
Revelstoke Revelstoke Dam and Generating Station
Revenue Requirements Application (RRA)
BC Hydro filing to the British Columbia Utilities Commission (BCUC) to seek approval for rate levels to support forecast revenue requirements.
Mica Gas Insulated Switchgear Project Appendix A-1
Page 5 of 7
Runner Device for transforming potential energy (water stored in reservoir) into kinetic energy. It is constructed of multiple hydrofoil blades fixed to a supporting structure (crown and band).
Seven Mile GS Seven Mile Generating Station
SF6 Sulphur Hexafluoride. Used as the insulating gas in GIS.
Statement of Intent (SOI)
Under the Six-Stage treaty process coordinated by the BC Treaty Commission, A First Nation files with the Treaty Commission a SOI to negotiate a treaty with Canada and BC. The SOI must identify the First Nation's governing body for treaty purposes and the people that body represents and show that the governing body has a mandate from those people to enter the process. The SOI must also describe the geographic area of the First Nation's distinct traditional territory and identify any overlaps with other First Nations.
Surge Arrestor Surge arrestors are mechanisms to protect transformers from lightening and switching power surges.
Switchgear A combination of circuit breakers, disconnect switches, and ground switches used for switching and isolating part of the electrical system.
Transient Surges A transient surge is an over-voltage (higher than normal voltage) that can occur during the closing or opening of a switch or when a fault (e.g. short circuit) occurs on a system.
Transformer A device that transfers energy from one circuit to another with different voltages.
Transformer Chamber The location of the transformers in the generating station.
Turbine A rotary device caused to turn by the movement of gases, steam or water.
UCA Utilities Commission Act
Unit A single power generation system within a multi-unit power generation facility. For example, the BC Hydro GMS Generating Facility contains 10 Units. Each Unit is comprised of several components, including the turbine, generator, transformers, conductors, circuit breakers, and ancillary equipment, all of which are required to create electrical energy and deliver it to the Bulk Transmission System.
Upgrade Replacement of components
Water License The authority granted under the Water Act to BC Hydro by the Comptroller of Water Rights of the Province of British Columbia to store and divert water for generating electricity and other purposes.
Mica Gas Insulated Switchgear Project Appendix A-1
Page 6 of 7
Water Use Plan A Water Use Plan is a technical document that defines the detailed operating parameters to be used by hydroelectric facility managers in their day-to-day decisions. WUPs are intended to clarify how rights to Provincial water resources should be exercised, and to take account of the multiple uses for those resources. WUPs are reviewed by the Comptroller of Water Rights pursuant to the Water Act.
Wicket Gates A series of hydrofoil-shaped gates that regulate the flow of water from the penstocks to the runners. The wicket gates for GMS Units 1 to 5 are being proposed for replacement as part of the upgrade project.
XLPE cable Cross-linked polyethylene cable
Mica Gas Insulated Switchgear Project Appendix A-1
Page 7 of 7
Key Financial Assumptions
Factor Assumption
Nominal Discount Rate 8 per cent
General Inflation F2009: 0.5 per cent
F2010: 2.0 per cent
F2011 through F2013: 2.1 per cent
F2013+: 2 per cent
Construction Escalation Rates Ranges from 0.9 per cent to 3.0 per cent with cumulative escalation of 25.5 per cent over 15 years or 1.7 per cent average per year
Reference Value of Energy (to Lower Mainland)
$93/MWh. Figure calculated using the cost of marginal energy delivered to the Lower Mainland, identified in the 2006 Call for Tenders at $88/MWh (F2006 Dollars)
Dependable Capacity Reservation cost $17/MW winter
Mica Gas Insulated Switchgear Project Appendix A-2
Page 1 of 1
Mica Gas Insulated Switchgear Project
Appendix
B
Draft Order
SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA
web site: http://www.bcuc.com
TELEPHONE: (604) 660-4700 BC TOLL FREE: 1-800-663-1385
FACSIMILE: (604) 660-1102
BRITISH COLUMBIA
UTILITIES COMMISSION ORDER NUMBER G-
IN THE MATTER OF the Utilities Commission Act, R.S.B.C. 1996, Chapter 473
and
An Application by British Columbia Hydro and Power Authority
Mica Gas Insulated Switchgear Project
BEFORE: ________, Commissioner XX, 2009
O R D E R WHEREAS:
A. On August 5, 2009, British Columbia Hydro and Power Authority (“BC Hydro”) filed an application for
acceptance, pursuant to Section 44.2(1)(b) of the Utilities Commission Act (the “Act”), that capital
expenditures BC Hydro anticipates making in respect of the Mica Gas Insulated Switchgear Project (“Mica
GIS Project”) are in the public interest; and
B. The Commission has considered the application, evidence, and submissions of intervenors and BC Hydro.
. . ./2
Mica Gas Insulated Switchgear Project Appendix B
Page 1 of 2
2
Order/
BRITISH COLUMBIA
UTILITIES COMMISSION ORDER NUMBER G-
NOW THEREFORE the Commission determines for the Reasons stated in the Decision, that: 1. The expenditures required to complete the Mica GIS Project, as described in the application, are in the public
interest in accordance with Section 44.2(3)(a) of the Act.
2. BC Hydro is directed to file with the Commission quarterly progress reports on the Mica GIS Project
schedule, costs and any variances or difficulties that the Mica GIS Project may be encountering. The form and
content of the quarterly progress reports will be consistent with other BC Hydro capital project quarterly
reports filed with the Commission. The quarterly progress reports will be filed within 30 days of the end of
each reporting period.
3. BC Hydro is directed to file a final report within six months of the end or substantial completion of the Mica
GIS Project. The final report is to include a complete breakdown of the final costs of the Mica GIS Project, a
comparison of these costs to the Project Expected Cost estimate and provide an explanation of all material
cost variances.
DATED at the City of Vancouver, in the Province of British Columbia, this day of ________ 2009.
BY ORDER
Mica Gas Insulated Switchgear Project Appendix B
Page 2 of 2
Mica Gas Insulated Switchgear Project
Appendix
C
Project Schedule
Act
ivity
Nam
eO
rigin
alD
urat
ion
Sta
rtFi
nish
Def
initi
on P
hase
293
17-D
ec-0
8 A
24-F
eb-1
0
File
BC
UC
App
licat
ion
175
17-D
ec-0
...18
-Aug
-09
Rem
oval
of S
GB
from
Mic
a 5/
6 E
AO
(Dra
ft)20
02-A
pr-0
9 A
30-A
pr-0
9 A
Rem
oval
of S
GB
from
Mic
a 5/
6 E
AO
(App
rove
d)23
17-A
pr-0
9 A
17-A
pr-0
9 A
Obt
ain
BC
UC
App
rova
l22
320
-Apr
-09
A24
-Feb
-10
Impl
emen
tatio
n Ph
ase
976
05-J
un-0
9 A
29-A
pr-1
3
EA
R A
ppro
val f
or IM
P11
05-J
un-0
9 A
15-J
un-0
9 A
ME
PP
I Pro
cure
men
t (P
lace
Hol
der)
784
30-J
un-0
929
-Jun
-12
Aw
ard
Con
tract
for S
witc
hgea
r Bui
ldin
g0
30-J
ul-0
9*S
ubm
it G
as In
sula
ted
Sw
itchg
ear (
GIS
) Det
aile
d D
esig
n S
umm
ary
9511
-Aug
-09
21-D
ec-0
9
Com
plet
e O
vera
ll S
witc
hgea
r Bui
ldin
g - W
eath
er T
ight
6811
-Sep
-09
15-D
ec-0
9
Com
plet
e O
vera
ll S
witc
hgea
r Bui
ldin
g10
816
-Dec
-09
14-M
ay-1
0M
EP
PI G
IS C
ontra
ct S
tage
1 -
Inst
all L
ead
Sha
ft 3
4901
-Oct
-10
08-D
ec-1
0
ME
PP
I GIS
Con
tract
Sta
ge 2
- In
stal
l Sw
itchg
ear &
GIS
Equ
ipm
ent
(U5
& U
6)84
01-O
ct-1
026
-Jan
-11
Pla
nned
Sum
mer
Out
age
2011
Win
dow
109
01-M
ar-1
1*29
-Jul
-11*
ME
PP
I GIS
Con
tract
Sta
ge 3
- U
3 &
U4
GIS
Rep
lace
men
t52
01-M
ar-1
111
-May
-11
ME
PP
I GIS
Con
tract
Sta
ge 4
- Tr
ansm
issi
on L
ine
to R
eact
or @
SG
B51
15-A
pr-1
124
-Jun
-11
ME
PP
I GIS
Con
tract
Sta
ge 5
- Le
ad S
haft
211
102
-Aug
-11
03-J
an-1
2
Pla
nned
Sum
mer
Out
age
2012
Win
dow
109
01-M
ar-1
2*31
-Jul
-12*
ME
PP
I GIS
Con
tract
Sta
ge 6
- U
1 &
U2
GIS
and
SG
B G
IS
Rep
lace
men
t89
01-M
ar-1
203
-Jul
-12
ME
PP
I GIS
Con
tract
Sta
ge 7
- Le
ad S
haft
110
101
-Aug
-12
19-D
ec-1
2
Pro
ject
Com
plet
ion
Doc
umen
tatio
n90
11-D
ec-1
229
-Apr
-13
MJ
Jul
AS
ON
DJ
FM
AM
JJu
lA
SO
ND
JF
MA
MJ
Jul
AS
ON
DJ
FM
AM
JJu
lA
SO
ND
JF
MA
MJ
Jul
2009
2010
2011
2012
2013
24-F
eb-1
0, D
efin
ition
Pha
se
File
BC
UC
App
licat
ion
Rem
oval
of S
GB
from
Mic
a 5/
6 E
AO
(Dra
ft)
Rem
oval
of S
GB
from
Mic
a 5/
6 E
AO
(App
rove
d)
Obt
ain
BC
UC
App
rova
l29
-Apr
-13,
EA
R A
ppro
val f
or IM
PM
EP
PI P
rocu
rem
ent (
Pla
ce H
olde
r)A
war
d C
ontra
ct fo
r Sw
itchg
ear B
uild
ing
Sub
mit
Gas
Insu
late
d S
witc
hgea
r (G
IS) D
etai
led
Des
ign
Sum
mar
y
Com
plet
e O
vera
ll S
witc
hgea
r Bui
ldin
g - W
eath
er T
ight
Com
plet
e O
vera
ll S
witc
hgea
r Bui
ldin
gM
EP
PI G
IS C
ontra
ct S
tage
1 -
Inst
all L
ead
Sha
ft 3
ME
PP
I GIS
Con
tract
Sta
ge 2
- In
stal
l Sw
itchg
ear &
GIS
Equ
ipm
ent (
U5
& U
6)
Pla
nned
Sum
mer
Out
age
2011
Win
dow
ME
PP
I GIS
Con
tract
Sta
ge 3
- U
3 &
U4
GIS
Rep
lace
men
t
ME
PP
I GIS
Con
tract
Sta
ge 4
- Tr
ansm
issi
on L
ine
to R
eact
or @
SG
B
ME
PP
I GIS
Con
tract
Sta
ge 5
- Le
ad S
haft
2
Pla
nned
Sum
mer
Out
age
2012
Win
dow
ME
PP
I GIS
Con
tract
Sta
ge 6
- U
1 &
U2
GIS
and
ME
PP
I GIS
Con
tract
Sta
ge
Pro
ject
Co
MIC
A G
ISLe
vel 1
Sch
edul
eP
rint D
ate:
22-
Jul-0
9
Rem
aini
ng L
evel
of E
ffort
Act
ual L
evel
of E
ffort
Act
ual W
ork
Rem
aini
ng W
ork
Crit
ical
Rem
aini
ng W
ork
Mile
ston
eS
umm
ary
Pag
e 1
of 1
Mica Gas Insulated Switchgear Project Appendix C
Page 1 of 1
Mica Gas Insulated Switchgear Project
Appendix
D
Project Lifecycle and Project Cost Estimating
BC Hydro Standard Project Lifecycle
A standard Project Life Cycle is an essential component of good project management
practice. BC Hydro’s Project Lifecycle is provided as Figure 1.
Figure 1 Project Life Cycle
The Project Life Cycle is composed of phases and stages within those phases. Each
phase results in the development of key deliverables that are subject to checking and
independent review, functional endorsement and financial due diligence before they
receive approval to proceed.
For each of the Project Life Cycle phases, the project initiator and project manager
present the recommendations of the key deliverables to a gateway committee for
approval to proceed. The gate committee is composed of members of the EARG senior
management team. Once the gate committee approves proceeding with the next phase
of the project, the recommendation and results of the financial due diligence are
presented to Chris O’Riley, the project sponsor, for approval. If the project sponsor does
not have the necessary level of delegated financial authority, the decision proceeds to
the level required to make the business decision, which for funding requests greater than
$20 million, is the BC Hydro Board of Directors.
Mica Gas Insulated Switchgear Project Appendix D-1
Page 1 of 3
Initiation Phase
When BC Hydro’s EARG generation operations group identifies a problem or
opportunity, it is entered into BC Hydro’s asset management process. If the project is not
included in BC Hydro’s current Capital Plan it is reviewed by management prior to formal
assignment to the EARG generation project delivery group. If the project is included in
the capital plan, the EARG generation project delivery group assigns a qualified project
manager to the project. The Initiation phase ends when the EARG finance group
approves initial funding for the Identification phase to initiate planning and a project
manager to plan and deliver the project has been assigned.
Identification Phase
During the course of the Identification phase conceptual designs are prepared to identify
solutions to address the problem or opportunity. Subsequently, feasibility studies are
carried out and a preliminary business case is prepared. The Identification phase ends
with the selection of a preferred alternative to address the problem or opportunity. At the
end of the Identification phase, the gate committee decides whether to fund the
Definition phase of the project.
Definition Phase
During the course of Definition phase, field and other studies (preliminary design) are
completed to comply with any regulatory obligations, and to finalize the business case. In
addition, applicable regulatory authorizations1 are sought and the project plans and
business case are revised to incorporate any conditions imposed by regulatory agencies.
The Definition phase ends when the gate committee decides whether to proceed to
implement the project.
1 May include: Water Act, Canadian Environmental Assessment Act and BC Environmental Assessment
Act and the Utilities Commission Act.
Mica Gas Insulated Switchgear Project Appendix D-1
Page 2 of 3
Implementation Phase
During the course of the Implementation phase, detailed design occurs; equipment is
procured2; the work is manufactured, supplied, installed and constructed; and the testing
and commissioning is completed. At this stage, the assets for the project are transferred
from the custody of the project team to the staff in the EARG generation operations
group that will operate and maintain the asset. The project is complete when the project
initiator accepts the project results by signing the project completion report.
Throughout the Project Life Cycle, project monthly reports are issued and reviewed by
senior management, and issues are escalated as required to move forward.
2 Where appropriate, senior management may approve the tendering of equipment in advance of
regulatory approvals to reduce project risk. In such cases the contracts awarded will be subject to regulatory approval and contain termination provisions that limit financial exposure.
Mica Gas Insulated Switchgear Project Appendix D-1
Page 3 of 3
BC Hydro Project Cost Estimating Practices
BC Hydro’s estimating practice for projects expected to cost over $6 million is to
establish a range of possible costs based on a probability analysis to determine
contingency1 allowances, and to include specific possible adverse developments outside
BC Hydro’s control, and potential but uncertain scope expansions. The probability
analysis is carried out by breaking the project cost2 into distinct cost elements, which are
internally similar but statistically independent. For each cost element, BC Hydro makes
an estimate of the range of possible cost outcomes from low to high, as well as a single
best estimate, with the intention that there is only a five per cent probability that the
actual outcome will lie outside the low - high range. This range is intended to cover the
common reasons for estimate differences, including:
Difference in site conditions;
Design refinements as engineering continues;
Labour productivity not as assumed;
Quantity variations; and
Changes in cost or extra costs.
The estimate of the appropriate cost range is determined by experience, professional
judgement, or common industry practice, after review of the project Risk Register and
discussion with key members of the project team about potential risks and uncertainties
in the project. These range estimates are used to create a statistical model of the total
project cost; the output of the statistical model is a probability density function indicating
the probability of a particular aggregate cost outcome – of particular interest are the P50 1 “Contingency – An amount added to an estimate to allow for items, conditions, or events for which the
state, occurrence, and/or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs.” Association for the Advancement of Cost Engineering International; Recommended Practice No 10S-90. A contingency is expected to be expended on items that cannot be identified in advance, but are likely to occur (with varying degrees of confidence) over the course of the project.
2 This analysis includes directs costs and BC Hydro costs, such as Engineering and Project Management, but excludes loadings for overhead or IDC. The range estimates are in constant dollars, which are then increased to reflect anticipated escalation in construction costs.
Mica Gas Insulated Switchgear Project Appendix D-2
Page 1 of 3
and P90 values; the cost estimates at which there is a 50 per cent probability that the
actual outcome will be less than the estimate, and at which there is a 90 per cent
probability that the actual outcome will be less than the estimate. These values are then
“loaded” by including them in a monthly cash-flow schedule over the project life. The
cash flow schedule allows calculation of IDC to reflect the carrying cost of an asset that
has not gone into service, Inflation and Escalation to reflect the nominal dollars to be
expended, and an overhead charge to reflect the burden of administrative and financial
functions that do not make a direct contribution to the project.
The Loaded P50 value is the Expected Cost of the project, representing BC Hydro’s
estimate of the likely project cost: by definition there is an equal chance that the actual
outcome will be above this value or below this value. The P90 value is a reasonable
upper estimate of the cost of the project, except it does not include possible costs
outside the control of BC Hydro, including:
Material changes in exchange rates or general inflation and escalation rates;
Changes in project scope or operating requirements;
Accidents with material cost or schedule implications for the project;
Abnormal weather; and
Changes in governmental policy, environmental standards or regulated working
conditions.
BC Hydro estimates the likelihood of such events and the possible cost impact (on a
Loaded basis), and the project initiator and project sponsor jointly determine whether
they wish to reflect such costs in the project’s Authorized Cost by including them in a
Management Reserve. The decision as to what should be included in a Management
Reserve is based on professional judgement and experience and will reflect the
likelihood and materiality of these uncontrollable risks. The project’s Authorized Cost is
the P90 estimate together with the Management Reserve established by the project
initiator and project sponsor.
Mica Gas Insulated Switchgear Project Appendix D-2
Page 2 of 3
All projects requiring approval of the BC Hydro Board of Directors (BoD), such as this
Project, include a Project Reserve for the Implementation phase. Authority to approve
the use of this Project Reserve is delegated to the Chief Executive Officer, unless
otherwise determined by the BoD. Any cost overruns that are forecast to exceed the
Authorized Cost amount require BoD approval. The project manager is delegated the
authority to spend the Expected Cost amount on the project.
Mica Gas Insulated Switchgear Project Appendix D-2
Page 3 of 3
Mica Gas Insulated Switchgear Project
Appendix
E
Condition Assessment Reports
1
Mica Generating Station
Condition Assessment of 550 kV ITE SF6 Gas Insulated Station (GIS) Equipment in the
Transformer Gallery and Lead Shafts
October 2005
This report was written by
Bjorn Holm International Switchgear Consulting Ltd
14728 Upper Roper Ave White Rock, B.C. Canada, V4B-2C9
The report was reviewed by
Darren Kahl, Electrical Maintenance Engineer Upper Columbia Generation
Mica Gas Insulated Switchgear Project Appendix E-1
Page 1 of 6
2
Introduction The gas insulated switchgear (GIS) at Mica is now about 30 years old. This was the first 550 kV GIS made by ITE. This make has been prone to flash over failures and SF6 leaks. Disconnects are now no longer operated with motor drives and are only switched while being de-energized on both sides. This has reduced flashover failures, but it has also imposed severe operating restrictions. Service Life Considerations Utilities commonly expect a GIS life span of about 40 to 50 years before being faced with refurbishing or replacement. Life limiting materials include seals, epoxy insulation, spring contacts at insulators and current carrying sliding contacts. Most replacement decisions have been made due to insulation flashovers and SF6 leaks, some due to sliding contact failures. Arizona Public Service has replaced their three 230 kV GIS stations. TVA is in the process of replacing their three 550 kV GIS stations. The service life for these stations varies from 20 to 30 years. National Grid, ConEdison and Entergy have all performed extensive repairs and refurbishing, but have not replaced stations yet. Mica Failure History The failures to date have all occurred in the switchgear building, with the exception of one in a lead shaft and one in the transformer gallery. The failure in the lead shaft was likely due to particles or contamination in SF6. The failure in the transformer gallery was due to contamination during an operating rod installation. Most of the failures in the switchgear building have been associated with the circuit breakers. Some have been due to internal disconnect operating rod flash over and some due to particles or contamination. Failures have not yet occurred due to internal flash over within cone insulators or due to insulator insert spring degradation. The onset of such failures would be likely to indicate chronic future problems and a need for GIS replacement. The time required for tendering, manufacturing and installing new GIS is normally up to two years after budget approval. Major refurbishing requirements can develop within this time frame. It is therefore important to take the expected time required for replacement into account in order to avoid major refurbishing. Generator G5 Installation The addition of generator G5 would require new GIS from new transformers T5 to existing disconnects 5D10, and new GIS in lead shaft #3 to the switchgear building. New GIS in lead shaft #3 would provide additional contingencies and thus allow easier replacement of the existing GIS when needed, particularly in lead shafts. It is advantageous to install the GIS for generator G5 before installing the generator in order to reduce risks and consequences of failures in the ITE GIS, as well as to facilitate replacement.
Mica Gas Insulated Switchgear Project Appendix E-1
Page 2 of 6
3
Risk of Two Unit Outage A flash over failure in the transformer gallery GIS would result in two generators being out of service until completion of repairs. The time to repair after operating rod failures has usually taken only a few days. Other types of failures are more likely to take about five to six weeks, provided the technical resources, parts and tools are available at site. A two unit outage after a flash over could be reduced to one unit by installing disconnects to sectionalize the bus. Two sets of two disconnects would be required, one set between lead shaft #1 and transformer T2, and one set between lead shaft #2 and transformer T3. This sectionalizing could be made similar to the existing sectionalizing arrangement at disconnects 5D7/5D8 and disconnects 5D9/5D10. Alternately, the time required to get both units back in service after a flash over could be reduced from a few weeks to a few days by installing a connectable spare phase along the length of the transformer gallery, parallel to the existing bus. This spare phase would need provision for connection to the 12 transformer disconnects and to the 6 lead shaft disconnects. Three sections would be required for temporarily connecting the spare bus in order to bypass the faulted portion. The faulted bus could then be repaired while all units remain in service, and then returned to service during a two unit outage at an opportune time. Equipment Concerns The wire type spring contacts and the age of seals dictated replacement of the GIS at Seven Mile. Disconnect design, surge arrester design and age, age of seals, age of solid insulation, and floating electrode type defects are the critical issues at MCA. Disconnects Flashover failures, test results, and dissections, have shown that disconnect operating rods contain contaminants from manufacture and have too high electrical stress at the end fittings. All rods should be replaced as soon as possible. Motor operators as well as contact configurations need major modifications. The original equipment manufacturer has provided product support for operating rod replacement, but support for major modifications has not been offered. Cone Insulators Internal PD can be present for decades before a flash over failure results. UHF tests have detected partial discharge (PD) in cone insulators. However, there has been no internal flash over within insulators so far. Flash over at surfaces due to contamination have occurred. Spring Contacts at Insulator Insert Wire type contact springs at insulator inserts have contributed to early replacement of several ITE stations, including the 230 kV GIS at Seven Mile. Vibrations have often been associated with the partial discharge at this wire type of spring connection.
Mica Gas Insulated Switchgear Project Appendix E-1
Page 3 of 6
4
The springs at Mica are a flat type that has so far not been associated with failures at this station. However, UHF signatures due to partial discharge, and consistent with floating electrode type defects, have been detected at many locations. Contact springs are a likely source of such partial discharge signals. Surge Arresters The surge arresters in the transformer gallery are gap type arresters using obsolete technology. Counter history can be analyzed. Grading currents can be measured. Spark over voltage can be measured to determine if SF6 has leaked into the nitrogen compartment. Functionality is questionable and cannot be tested. A defective surge arrester would add stress to the bus as well as the transformers. Insulation weaknesses would be likely to result in flash over due to lack of switching surge suppression. SF6 Leaks The bypass piping at Mica has had numerous leaks from the time of installation. Such leaks are normally relatively inexpensive to repair and repairs have been completed in recent years. There are also a number of leaks at bolted flanges. Some of these leaks can be easy to repair, such as at access covers and ground switches but success rate to date has been low due to warped flanges. Some of the flange leaks require extensive dismantling in order to replace O-rings. Temporary repairs are commonly made to defer dismantling until a convenient time. The most serious SF6 flange leaks are in the switchgear building. There are fewer critical flanges in the transformer gallery. Insulation Test Results Partial Discharge Detection Partial discharge degrades SF6 gas as well as solid insulation, and results in insulation flash over at some point in time. Partial discharge produces electromagnetic radiation in the ultra high frequency (UHF) spectrum, acoustic signals of up to about 100 kHz, and chemical decomposition of SF6. UHF signals travel up to about 60’ inside GIS, depending on materials and geometries involved. UHF signals may be detected at disconnect view ports at Mica. Partial discharge inside solid insulators generates UHF signals, but the magnitudes are usually relatively low. Sonic and ultrasonic signals from partial discharge usually travel up to about 6’ depending on materials and geometry involved. Acoustic analysis can detect partial discharge in SF6 but not inside the epoxy insulators, due to damping of signals in epoxy. Vibrations can mask acoustic signals. Partial discharge in SF6 produces gaseous and solid decomposition products. The decomposition gases may be detected on site using chemical analysis. Partial discharge inside solid insulation does not decompose SF6 and cannot be detected. Desiccants adsorb decomposition gases. Sampling lines can affect test results.
Mica Gas Insulated Switchgear Project Appendix E-1
Page 4 of 6
5
UHF Test Results UHF signals from partial discharge have been detected at almost all disconnect view ports. A high portion of the detected UHF signals have originated at contamination inside disconnect operating rods. After rod replacement, signals from other sources may be identified, and some have been characterized further to include floating electrode type partial discharge as well as from voids or contamination. UHF signals characterized as floating electrode have been detected at 4 view ports adjacent to bus section 5BT2T1 B phase. UHF time of flight measurements have been made at these 4 disconnect view ports, where the same signal might be detected at two or more view ports, thus enabling the partial discharge to be located. Results so far indicate one source close to disconnect 5D2B and one source close to disconnect 5D1B. Acoustic Test Results Acoustic signals have provided information about partial discharge in the lead shafts, but not yet in the transformer gallery, due to vibrations caused by operation of the generators and transformers. SF6 Chemical Decomposition SF6 decomposition gases have been detected in gas zone GBT3A. This is a small zone at T3A that includes disconnect 5D3A, which contains desiccant for moisture and SF6 decomposition gas removal. Conclusions A flash over in the transformer gallery is likely to result in two units being out of service for about five to six weeks. If a failure occurs in one of the two lead shafts, the work could take longer, but in this case all Mica output would depend on one lead shaft. One spare phase, connectable to bypass a faulted section in the transformer gallery would reduce the consequences of a failure from two generators being out of service for a number of weeks, to the two generators being back in service within a number of days. Disconnects can only be operated manually while both sides are de-energized. Replacement would allow normal operations to resume. The gap type surge arresters in the transformer gallery are likely to be at, or close, to end of life. Test results have correlated well with GIS condition based on internal inspections at Mica and Seven Mile. Partial discharge has been detected in numerous locations in the transformer gallery GIS. Flash over failures are likely to occur, probably within the next few years. More problems have been detected in the transformer gallery than in the lead shafts, perhaps because of ease of detection, but perhaps also because of lower vibrations.
Mica Gas Insulated Switchgear Project Appendix E-1
Page 5 of 6
6
GIS lead shaft repairs due to flash over or GIS replacement due to end of life would leave Mica output dependent on one lead shaft, perhaps for an unacceptable length of time. Advancing the installation of GIS for G5 in lead shaft #3 would avoid this weakness. The condition, obsolescence and design weaknesses of the ITE GIS indicate that replacement will be necessary, probably within about 8 years. The number of issues involved, as well as the amount of partial discharge that has been detected indicates internal problems that are less costly to solve by replacement. Recommendations Install one spare phase with provisions to temporarily bypass a faulted GIS section in the transformer gallery. Review requirements for parts, tools, equipment and access needed for emergency repairs in the transformer gallery. Perform more frequent UHF, chemical and acoustic tests to locate defects that might require immediate repairs. Install GIS in lead shaft # 3 for the G5 generator position to facilitate GIS replacement. Replace the ITE GIS in stages within about 8 years, starting in the transformer gallery. Whenever the GIS in the transformer gallery is replaced, install two additional sets of sectionalizing disconnects, one set between lead shaft #1 and T2, one set between lead shaft #2 and T3.
Mica Gas Insulated Switchgear Project Appendix E-1
Page 6 of 6
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 1 of 7
PHONE 724-933-0260 FAX 724-933-0266
BC Hydro - Mica Generating Station ITE-GIS
Condition and Risk Assessment
Situation found at Site
Historic operational documentation of the ITE GIS was obtained at Revelstoke and Mica
Power Station. Available data of problems, faults, repairs and leakage was reviewed. A
tour of the transformer gallery and also of the upper GIS building was completed. The
one-line diagram was reviewed. A few key factors appear to dominate the problems
experienced over the years. These factors continue to be the main concern about the
future of the ITE GIS.
1. Much higher than expected leakage rate
2. Partial discharge in several areas
3. Operating rods on disconnect switches.
4. Electric operating mechanisms of disconnect switches
5. Internal leakage of Barrier-Type insulators
6. SF6 Density Monitors
7. Integrity of sliding contacts
8. Arrestors are only spark gap type and not Zink-Oxide
Historic problems from other ITE GIS substations need also to be considered. They are:
9. Aging of all seals and O-rings and associated higher leakage and loss of SF6
10. Electric contact Springs between sliding bus and support insulator’s inserts
(details page 2)
Elaboration on above points.
To 1. The expected leakage rate on a modern GIS is less than 0.5 % per year. (for
instance compare with Revelstoke and Peace Canyon). The loss of SF6 is not only a cost
factor but also a reliability issue. The aging of the seals has also a negative effect on
reliability and the leakage rate will increase continuously and can lead eventually to
catastrophic losses. Additionally, in future BCH faces a possible environmental liability.
The Canadian equivalent of the EPA will eventually issue heavy fines for the usage (loss)
of SF6 gas – we expect it to be similar to what is already in effect in Europe. The total
amount of SF6 used at Mica Generating Station during 2004 was 172.9 kg, during 2005
was 56.8 kg and during 2006 it was 92.9 kg. The reduction of SF6 loss in 2005 was
mainly due to repairing the by-pass piping. The increasing amount for 2006 is an
indication that the repair is only temporary and also most likely the leakages in seals and
O-rings are on the increase. The Green house effect can easily be calculated.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 1 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 2 of 7
PHONE 724-933-0260 FAX 724-933-0266
To 2. Partial discharge will lead sooner than later to internal electrical breakdown with
resulting flash-over and lengthy repair time of the component. The associated
unscheduled outage time can be a few days or a few weeks depending on where the fault
occurs and the availability of spare components. The financial loss of such an
unscheduled outage (measured by multiples of cost per MW hours) can quickly offset the
cost for new GIS.
The severity of PD at Mica has been greatly reduced by replacing some of the disconnect
switch operating rods. However the PD activity as a whole in Mica is still much larger
than in other stations. This indicates that we have to expect in future a higher than normal
failure rate. To predict this failure rate is almost impossible since it depends not only on
normal, in service conditions but also on occurring over-voltages produced by switching
operations (internally) and other network system conditions (externally). Historically and
technically we know that partial discharge inside GIS leads almost always to a failure.
To 3. The old, solid epoxy type operating rods had reliability problems from the very
beginning. Aging of these rods including the associated internal PD has resulted in
premature failures. The detected UHF discharge suggested a fairly quick deterioration of
the insulation properties and triggered the replacement of these operating rods.
The replaced operating rods of the disconnect switches are functioning well and there
seems to be no immediate danger of further failures. The only concern is that we do not
have long time experience on these newly designed rods and therefore there is no
historical data available to evaluate the long term reliability.
To 4. All electrical operating mechanisms of the disconnect switches have been disabled
do to unreliability. The adjustment of the auxiliary switches is extremely difficult and
also unstable. The result is a drifting “start-stop position” for the motor and the switch
position for the remote indicators are some times incorrect. The aux. contacts themselves
have a tendency to corrode. Presently all switching operations are carried out manually.
This can easily lead to human error and is potentially dangerous. A correctly interlocked
disconnect switch can not be operated in the wrong mode. At Mica it is relatively difficult
to gain access to the disconnect switches and associated operating mechanisms. Due to
this fact the writer thinks it is easy possible for the operator to make a mistake and
manually open or close a wrong disconnect switch. Should an operator error occur and a
disconnect switch is opened or closed in the wrong mode, a ground fault at the switch is
unavoidable. The operator will be positioned within 2 or 3 feet of this fault, shielded only
by the enclosure of the GIS. The resulting induced voltages and currents to the platforms
and structures are potentially dangerous, not to mention a possible melt-through of the
enclosure. Additionally these disconnect switches can not be used to de-energize the
transformers and associated bus-works. The manual operation takes substantially more
time than remote control . The extra time to perform the switching and the inability to
switch under live condition increases cost, loses revenue and reduces operational
flexibility.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 2 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 3 of 7
PHONE 724-933-0260 FAX 724-933-0266
To 5. A “Barrier-type” insulator is supposed to be a barrier between two gas
compartments. This condition is designed to allow work to be performed on one side of
the barrier without degassing the other. If an internal leak exists through the barrier, the
SF6 gas can escape during inspection and/or maintenance and can cause a failure if not
detected. The station personnel reported at least one of these incidents at Mica. Aging
has an effect on the integrity of the sealing system of the barrier insulators. This fact will
contribute to future difficulties maintaining the GIS.
To 6. The Density Monitors provide a vital function by constantly checking the
temperature compensated pressure inside the SF6 compartments. If a Density Monitor
should fail to provide the “Low Gas Pressure Alarm” on time, an internal flashover would
result. We have found no history of a Density Monitor failure. Calibration and regular
checks of the Density Monitor’s set points are a requirement. These checks should be a
combination of manufacturer’s recommendations and operational history. In a GIS
installation with a history of many leaks, the function of these Density Monitors becomes
very critical. The station personnel mentioned that they check the internal pressure of
each SF6 compartment manually approx. every two month. A modern GIS has a visible
pressure indicator in combination with the density monitor. This eliminates the manual
task of connecting and disconnection a pressure gauge to each compartment every few
month, reducing the risk of further leaks being introduced.
To 7. The existing UHF PD signatures point to a potential problem on some of the
sliding contacts. Similar signatures where found at burning or welding of sliding contacts
in other stations. At this time the condition of the inspected sliding contacts at Mica
(from the switchgear building) is very good. The remaining sliding contacts in the lead
shafts and transformer gallery bus runs are unknown. They have not caused any failures.
If a life-extension of the ITE GIS at Mica should be considered an inspection of the
sliding contacts would need to be included in this process, especially in areas where UHF
signatures have indicated contact burning.
Other UHF fingerprints / time of flight measurements indicate some PD at or near support
insulators. If the level of PD, based on test results (chemical & UHF), is judged to be
dangerous, then these areas should be inspected and possible corrective action taken.
To 8. The presently installed Surge Arresters are of the Gap-Type design. These
arresters are obsolete. They are installed primarily to protect the 16/550 kV transformers.
The new, much more reliable, design is a Metal-Oxide. The new type arresters provide a
much better protection, especially against faster rising transient over-voltages. Counter
readings indicate that these arresters are in working condition.
To 9. At this moment there are a few leaks on flanged connections. The O-rings and
seals in the rest of these flanges and entering points of operating shafts are aging faster
than other components of this GIS. Historically the leakages on gaskets, seals and O-
rings increase at an accelerating rate. The O-rings, gaskets and seals are getting older.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 3 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 4 of 7
PHONE 724-933-0260 FAX 724-933-0266
The artificial softener imbedded into the rubber evaporates with time. The hardening and
associated shrinkage of these rubber type materials accelerates with age until they loose
all memory and elasticity. To replace these seals and O-rings the switchgear would need
to be dismantled. The leakage rate indicates that this GIS is getting closer to the time
when this work is unavoidable. Newer type of sealing compounds have a longer live
expectancy.
To 10. These springs have been a problem in other ITE GIS installations. This contact
spring provides solid electrical contact between the sliding busbar and the inner metallic
inserts of the support insulator. If the contact spring is displaced and/or looses the contact
pressure the metallic insert becomes a floating potential with partial discharges. The
particular vintage of GIS installed at Mica has a flat contact spring. This flat spring is not
associated with the kind of failures reported at other stations where a round spring was used.
Operational History
By-Pass Piping:
The design of the by-pass piping is not up to present standards. Leakages, even after
repair, can not be totally avoided indicated by increasing leakage rate in 2006 compared
to 2005 after repair of by-pass piping.
Bolted Flanges and Enclosures:
Leakages continue in some areas and will increase with time. Provisions for dismantling
some sections of the GIS-BUS are not part of this design. Therefore the replacement of
O-rings are going to be very time consuming.
Epoxy components:
The conical support and barrier insulators have no history of internal failure and are
actually of a reliable design. Nonetheless there is some evidence of small PD on or near
some insulators. We believe that this PD is not significant enough to cause failures in the
immediate future. Some of the epoxy operating rods of the disconnect switches with PD
have been replaced. Ground-switch insulators are prone to leakage.
Electrical Failures:
Mica GIS operating fault history confirms that most failures were associated with the
disconnect switch operating rods and disconnect switches inability to switch magnetizing
current of transformers and associated GIS bus.
The reason for the reported flash-over in LS1 in November of 1984 could not be clearly
identified. It was speculated that electrical stress from an earlier transformer failure could
have contributed to this flash-over. This failure was not internal to the insulator. This
fact makes us believe that the support and barrier type insulators are actually of sound
design and are not subject to regular failures. However some insulators show signs of
internal PD (small voids or contamination in epoxy). This is not a design but a
Mica Gas Insulated Switchgear Project Appendix E-2
Page 4 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 5 of 7
PHONE 724-933-0260 FAX 724-933-0266
manufacturing defect which was not detectable at time of production due to non
availability of UHF testing. The risk for future failures is relatively small, specially if
UHF testing is done in regular intervals and UHF signal fingerprints are compared.
Inspections
A. We verified that many SF6 leaks are still present at by-pass piping and other
components. The design and age combination of this type of GIS does not
allow many of these leaks to be corrected economically and reliably.
B. During the site visit we had the opportunity to inspect many of the
components removed from the switchgear building. The sliding contacts are
in very good condition. The metallic (Aluminum) portion of the bolted flanges
and enclosures have no signs of corrosion and appear also to be in very good
condition, specially if compared with an outdoor installation.
C. The surge-arresters have been regularly checked and there is no evidence of
SF6 leaking into the Nitrogen compartments. Operating counters show that
the arresters have operated.
Recommendations
I. For the immediate future:
The probability for immediate failures exist mainly at the disconnect switch
operating rods. To secure the operational reliability and safety of the GIS, all of
the remaining disconnect switch operating rods need to be changed. After all
operating rods have been replaced a new UHF survey should be done and
fingerprints compared to previous results. If the operating rods are not replaced,
UHF tests have to be done at least once per year to monitor the condition and
deterioration of these rods.
II. Medium term solution (approx. 5 years –see also VI. below)
a. Repair and stop all SF6 leaks including replace all O-rings in bolted flanges
and all shaft seals.
b. Investigate and repair units with higher level of PD
c. Replace SF6 Monitors, add extra monitors and create smaller gas
compartments. This makes searching for leaks easier.
d. Regular tests and surveys need to be part of the maintenance program.
III. Long term solution (5 to 30 years)
a. Install a GIS bus run in the 3rd
lead shaft
b. Replace all the GIS components in the transformer gallery, including the busbar
c. The existing lead shafts are working adequately at this time. Their
replacement should be determined by future leak rates and other occurring
operational problems. After the installation of the 3rd
lead shaft, an outage of
any lead shaft does not represent any longer a high operational risk.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 5 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 6 of 7
PHONE 724-933-0260 FAX 724-933-0266
IV. Internal inspections can only be recommended as a last step to assist in the
decision making to extend the life of the Mica GIS. In case a life extension
should be considered, internal inspections should be based upon further UHF
survey in combination with chemical analysis of the SF6 and acoustic testing.
This combined process might help to determine if a life extension is justified.
V. The UHF signatures reveal that there are still severe problems at some
locations. It is known that the disconnect operating rods are the single most
failure prone component. We highly recommend to monitor the situation of
the disconnect operating rods very closely and change all of them to the new
design at the first possible opportunity.
VI. Remarks to the recommendations:
How many of the above recommendation can or should be implemented
depends on monetary and philosophical considerations including future plans
for this station. The problems resulting in the complex operating procedures
(manual operation of disconnect and grounding switches and manual checks
for SF6 pressure) can not be resolved without considering the long term plans.
If a replacement GIS is considered than the recommended “Medium Term
Solutions” may be delayed until the new GIS is installed. However some
unscheduled outages, repairs and maintenance will most likely be the result of
this delay.
Summary
The GIS at Mica is 30 years old. Based on the “ pioneer type design” at time of
production, it has survived and served reasonably well. New designs of GIS take
advantage of experience gained during this time frame and also of the availability of new
materials ( gaskets, seals, polymers)
Future reliability and end of life of major components can not be determined very
accurately, however our assumption is that the disconnects and ground switches are at the
end of their reliable live cycle. This is mainly due to the aging of seals, O-rings and
leaking by-pass plumbing. The disconnect switches have never been capable of
switching transformer currents as per original specification. Further, the Motor Operated
Mechanisms of the disconnect switches are non functional and it is almost impossible to
reliably repair these mechanisms.
The bus runs and associated insulators could probably survive some time without too
many failures. The lack of “Dismantling Units” however makes it very hard and time
consuming to do any maintenance; not only on the bus runs but also on the disconnect
switches. Present and increasing leakage rates on by-pass plumbing and bolted flange
seals are limiting the economic long term life extension.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 6 of 7
ROHE INTERNATIONAL, INC.
June 30th
-2007
349 NORTHGATE DRIVE, WARRENDALE, PA 15086 page 7 of 7
PHONE 724-933-0260 FAX 724-933-0266
The lead-shaft bus can not be surveyed using the UHF method due to the fact that there
are no windows or any other ports to access the PD signals. Acoustic surveys provide
only some information about the health of the lead shaft bus insulation.
If no maintenance is done the following could happen.
• SF6 Leaks will increase beyond maintainability
• Disconnect operating rods will fail
• Density monitors will fail
• SF6 will leak into nitrogen filled compartments of surge arresters
• Eventually support (cone) insulators will start to fail internally
• Sliding contacts could eventually deteriorate, even so, present evidence does not
support serious contact problems at many locations.
The writer thinks that the ITE GIS has served its purpose. The availability of newer,
better and more reliable components and bus runs justifies replacement of the existing
GIS. The long term solution is the replacement of the ITE designed GIS; at least all the
GIS in the transformer gallery should be replaced. This would ensure future, very reliable
and flexible operation of Mica Creek Power Plant. The fact that we have a third lead
shaft available and an existing plan to install two additional generators, should aid and
accelerate the decision making process for the renewal of the ITE GIS as recommended
above.
This report has been prepared by
Edgar Heil Rohe International, Inc.
Mica Gas Insulated Switchgear Project Appendix E-2
Page 7 of 7
Report for the attention of
Mr Owen Williams
Project Manager, Generation
BCHydro
THE PRESENT CONDITION AND FUTURE RELIABILITY OF THE TRANSFORMER GALLERY GIS
AT MICA 500kV SUBSTATION
Prepared by
Brian Hampton
25 June 2007
Mica Gas Insulated Switchgear Project Appendix E-3
Page 1 of 15
1
CONTENTS
1. Objective
2. Review of significant reports
2.1 Operating history
2.2 Diagnostic testing
3. Assessing the future reliability of the Transformer Gallery GIS
3.1 Plant items
3.1.1 Gas leaks
3.1.2 Disconnects
3.1.3 Surge arresters
3.2 Busbar configuration
3.2.1 Transformer bay connections
3.2.2 Lead shafts
4. Failure risk assessment
5. Proposed actions to improve the future reliability of the GIS
5.1 Factors to be considered
5.2 Recommendations
6. Further diagnostic studies
7. Acknowledgements
8. References
Appendix
CV of Brian Hampton
Mica Gas Insulated Switchgear Project Appendix E-3
Page 2 of 15
2
1. Objective
The purpose of the study reported here is to assess the present condition of the 500kV GIS
located in the Transformer Gallery and lead shafts at Mica by reviewing its operating history,
together with the inspections & diagnostic tests made on it, and recommend actions needed to
ensure its long-term reliability and safe operation.
2. Review of significant reports
2.1 Operating history
The generating units were put into service in 1976 [1], and the initial operating experience
revealed significant defects, which included:
Excessive gas leakage – the GIS specification called for a maximum gas loss of 2% per annum,
but the initial leakage was 0.2% per day. This was said to be caused by poor welds and by-pass
piping joints.
Disconnects – which were found to be incapable of breaking the magnetizing current of the
generator transformers, and had problems with their motor-controlled operating mechanisms.
Another report [2], which includes a written update, includes details which indicate a pattern of
failures in some equipment:
Dec 1976 disconnect failure while de-energising a generator transformer
Aug 1978 disconnect failure while de-energising a busbar
Sept 1978 surge arrester failure during a system over-voltage (said to be a not uncommon
event for conventional, gapped arresters)
Aug 1983 damage to a generator transformer and its associated surge arrester following an
operational error in switching
Apr 1985 the operating rod of a disconnect failed soon after the disconnect was energised
Nov 1985 the same disconnect failed when the replacement operating rod failed
1989 disconnect failed when its operating rod flashed over
It will be seen that over this period, five failures occurred in disconnects. These can be attributed
to either their poor design or manufacture. The other two failures involved surge arresters, and
were probably caused by these conventional, gapped arresters being too slow to suppress the
very fast transient over-voltages which occur in GIS. All this points to the failures being caused
by generic defects in the plant, and not by infant mortality. It is therefore likely that further
failures of these items will occur.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 3 of 15
3
2.2 Diagnostic testing
The high failure rate of disconnect operating rods indicated a possible type fault, and to
investigate this surveys were made of the PD activity in the GIS. These were undertaken using
the UHF technique, which enables any source of PD to be recorded, and both the nature of the
defect & its location to be found. This work is documented in [3,4], and will not be explained
here.
The main conclusions of the studies were:
(i) there were high levels of PD activity over most of Mica GIS
(ii) most of the PD signals were of the same type, and were typical of those coming from
discharges either in or on the surface of solid insulation
(iii) many of these discharges were located, and their source found to be at the operating rods of
disconnects
(iv) the high level of these discharges would have masked most other PD signals which might
have been present, but some further PD typical of floating electrodes was seen. It was thought
that this may have arisen from sparking at the flat spring connection between the barrier inner
sleeve and the conductor. Very high levels of PD typical of contact sparking were also seen
briefly.
Further partial discharge and analytical tests on operating rods taken from disconnects were
made for BC Hydro at the Powertech Labs Inc. The results are comprehensively reported [5,6,7],
and showed that the operating rods examined contained embedded metallic particles, together
with signs that they had been discharging. Subsequent to these tests and analysis, the operating
rod was re-designed and so far those in five disconnects have been replaced. PD
measurements made recently at one of these disconnects still indicated a high level of PD, and
further tests including time of flight location of the PD are needed to clarify this.
3. Assessing the future reliability of the Transformer Gallery GIS
The experience gained with operating the GIS to date, together with the results of the diagnostic
investigations made on it, identify weaknesses in plant items which must be addressed before
an acceptable long-term reliability can be expected. In addition, the present busbar configuration
in the GIS is very inflexible and significant benefits would be obtained by upgrading it.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 4 of 15
4
3.1 Plant items
3.1.1 Gas leaks
Gas leaks do not in themselves affect the performance of the GIS unless the gas pressure falls
appreciably, but unless corrective action is taken many outages will be needed over the next
several years when the leaks need to be repaired.
The loss of SF6 to the atmosphere contributes to global warming, especially since the effect of
SF6 on the atmosphere is far greater than that of CO2. Of course we know that against this the
volume of SF6 released is orders of magnitude less than the volume of CO2; but global warming
is a major concern in the West, and governments are seizing every opportunity (real or
imaginary) to be seen to limit the amount of greenhouse gases released to the atmosphere.
The IEC standards presently limit the amount of SF6 that can be lost from a GIS to 0.5% per
annum, and there are proposals to reduce this to 0.1% per annum. It is understood that such
limits do not apply in North America, but there is every chance that similar constraints will be
enforced there before long.The GIS at Mica has always been prone to gas leaks, and records
show that 170kg was used by Generation to replace the losses which occurred in 2005. The
total amount of gas in the Transformer Gallery and lead shafts is 10,521kg, and so the loss rate
for 2005 was 1.6%.
A gas leak survey conducted by EPRI in 2001 revealed 75 leaks in the following locations (note
that this survey included the switchgear floor):
Number of leaks Leak description
36 Bypass pipe assembly
9 Desiccant plugs in cabinet
7 Plumbing fittings in cabinet
4 Ground switch flange
6 Repair site bolted flange leaks
6 Welds
2 Access cover flange view ports
1 Access cover flange
1 Ground switch view port
1 Rupture disk
2 SF6 tank plug
Mica Gas Insulated Switchgear Project Appendix E-3
Page 5 of 15
5
Most leaks were found in the gas by-pass lines, which contain many compression joints made
with what appear to be standard plumbing fittings. Many of the leaking fittings were tightened to
reduce the gas loss, and in a random inspection made now, some six years later, some were still
gas-tight. Against this, leaks were found in other by-pass lines. The instrument used to check the
leakage was a Dilo Leak Detector type 3-033-R002, and it is not known how the sensitivity of the
present measurements compares with those made by EPRI.
However, it is not thought that leaks in the by-pass lines present a major maintenance problem,
because it would not be difficult to replace the lines either by others of welded construction, or
with high quality fittings designed for use with gas. Similarly, leaks found in access cover ports,
or other situations where the O-ring seals are easily accessible, may readily be repaired if the
flanges and O-ring groove are in good condition.
The situation with leaks occurring at bolted flanges between bus chambers is quite different, and
often it would be necessary to dismantle a major part of the bay before the joint could be
separated, or the busbar moved until O-rings could be passed over it. The need to replace these
seals is likely to increase in the future as the present neoprene and ethylene propylene rubber
O-rings age – especially since they have a very much smaller cross-section than the O-rings
commonly used today, and will deform more readily.
It is interesting to note that there are 24 gas seals in the two lead shafts, 20 in the main busbars,
and 240 in the transformer bays. The importance of first sealing the transformer bays is evident.
3.1.2 Disconnects
There are no circuit breakers in the Transformer Gallery, and disconnects are used to isolate
those sections which, for whatever reason, need to be grounded. For example, if a generator is
out of service for maintenance, the generator breaker is opened to isolate it from the low-voltage
winding of the generator transformer. However the high-voltage winding of the transformer
continues to be back energised from the 500kV busbar, from which it draws a magnetising
current. The normal practice would then be to open the bay disconnect so that both the
transformer and surge arrester could be grounded. However, the existing breakers have proved
to be incapable of interrupting the magnetizing current, and may, as in Dec 1976, fail if this is
attempted. Since then the procedure of operating disconnects only when the busbars are de-
energised has been in place, and without this restriction many more failures would have
Mica Gas Insulated Switchgear Project Appendix E-3
Page 6 of 15
6
occurred – although the penalty of doing so has been the loss of the twin generator when the
single busbar is de-energised. This is the first problem with the disconnects.
Second, the motor drives of the disconnects were defective, and have been disabled. This
means that the disconnects and earth switches have to be operated manually, which prevents
any safety interlocking and leads to a higher risk of operator error. These factors lead to an
unwelcome restriction on normal operating practice.
Third, the present disconnect operating rods are faulty, and it has not yet been shown that the
replacement rods being applied on a limited scale have solved the problem. The many studies
made in universities and research laboratories throughout the world have shown that some
types of defect are more likely to cause failure than others. In particular it is recognised that
flashover across an insulating surface can occur quite readily, for example if it is triggered by a
defect on or embedded in its surface. The explanation for this is that the tip of the triggering
discharge deposits charge on the surface as it travels across it, and since the insulating material
has a relatively high permittivity, a high charging current is maintained in the discharge channel.
This results in a low voltage drop along the length of the channel, which maintains the high
electric stress at its tip. The discharge then becomes self-propagating until it reaches the
opposite electrode. Any insulating surface, in this case that of a disconnect operating rod, is
inherently weaker than either the gas in which it is immersed or the solid insulation, and defects
on it are particularly to be avoided.
Fourth, gas leaks are present in at least some disconnects.
In summary, the disconnects are in a poor state and will cause further problems in the future
unless remedial action is taken.
3.1.3 Surge arresters
The gapped type of surge arresters fitted at Mica are of quite complex construction, and contain
both SF6 and nitrogen filled compartments. Bearing in mind that the gas seals in the arresters
are now 30 years old, it seems likely that internal gas leakages will occur in the not-too-distant
future.
SF6 molecules have a high electron attachment coefficient, which gives the gas its excellent
electrical strength. Non-attaching gases such as nitrogen are inherently much weaker, but
Mica Gas Insulated Switchgear Project Appendix E-3
Page 7 of 15
7
adding a proportion of SF6 to them raises their strength markedly. The protective gaps in a surge
arrester are filled with nitrogen, and if even 1 or 2% of SF6 leaked into the nitrogen the sparkover
voltage of the gaps could increase to a level higher than that needed to protect other plant in the
GIS. This could no doubt be prevented if the arresters were stripped down and serviced, but
they would still have the fundamental disadvantage that they operate slowly compared with the
newer metal oxide arresters, and cannot control the very fast voltage transients generated by
switching operations in the GIS.
3.2 Busbar configuration
3.2.1 Transformer bay connections
Transformer bays 1 & 2 are connected to a single busbar, as are bays 3 & 4. If a failure were to
occur in a busbar, then the output from both the generator bays connected to it would be lost.
This would not be the case if an additional busbar was installed to provide a double busbar (1½
disconnect) configuration.
3.2.2 Lead shafts
If a failure occurred at the lower end of a lead shaft, in a gas zone next to the disconnect, it is
understood (discussion with Mr Darren Kahl) that the disconnect would not provide a point of
isolation, and the main busbar would need to be taken out of service while a repair was made.
This would not be the case with a double busbar configuration.
4. Failure risk assessment
The CIGRE Task Force D1.03.09 ‘Risk Assessment of Defects in GIS based on PD Diagnostics’
was set up 5 years ago with the objective of collecting data and developing the procedures to
calculate the risk of a GIS failing due to a particular defect. This has proved to be an impossible
task. In laboratory studies where all the parameters of the defect (size, shape, motion pattern,
etc.) are known, and the applied stress can be varied, it can sometimes be predicted that failure
will occur. In an operational GIS, PD measurements reveal only the type of defect, its
approximate discharge magnitude, and its location – and with only this data a risk assessment
cannot be calculated with any confidence.
For the time being at least, the prediction of failure remains an art based on the considerable
experience gained using UHF measurements in GIS the world over. My previous company, for
example, is presently continuously monitoring the PD data from upwards of 80 GIS rated from
Mica Gas Insulated Switchgear Project Appendix E-3
Page 8 of 15
8
154-800kV, and advising utilities when it seems necessary to intervene and correct a defect.
The characteristics of the UHF signals which allow this judgement to be made are:
(i) the type of defect (a free particle, floating electrode, void in insulation, etc), which is
determined from the PD pattern
(ii) the location of the defect, found using time-of-flight measurements
(iii) the approximate amplitude of the signal
(iv) whether the signal is constant or intermittent
(v) whether the characteristics of the signal are changing with time (trend analysis)
In truth, there is more experience than science in this, but the results are convincing – over all
the GIS being monitored, only 3 in-service failures have occurred during the past 10 years. With
my own knowledge gained during this time, I have no doubt at all that there is a 99% probability
of Mica GIS failing during the next 10 years unless some action is taken.
5. Proposed actions to improve the future reliability of the GIS
5.1 Factors to be considered
The Transformer Gallery GIS at Mica has proved to be exceptionally reliable over the 30 years in
which it has been in service, and there is a temptation to leave well alone. However there are
signs that it is ageing – discharging disconnect operating rods, discharges in the vicinity of cone
insulators, gas leaks – and it is unwise to assume that the good record will be maintained. With
the present configuration some failures of the GIS could result in a major reduction in output
over periods of some months, and long-term remedial action is needed.
The ways in which the reliability of the GIS could be improved have been examined. The
sections of the GIS most in need of attention are the transformer bays, made up of the
disconnect & surge arrester, and the bus chambers connecting them to the generator
transformer and main busbar. There are three such bays for each generator, and twelve in total.
Consideration was given to refurbishing the bays. For this each bay would need to be
dismantled up to the disconnect flange nearest to the main busbar, so that all the O-ring seals in
the bay could be replaced. The by-pass piping would be renewed at this time. Although the
seals and the operating rod in the disconnect would be replaced, it would still not be possible to
operate it remotely, nor restore its capacity to break the transformer magnetizing current.
The surge arrester is of the gapped type, which was the only one available when the GIS was
built. It too needs refurbishing but even then would not protect the GIS adequately. For this, the
faster-operating metal oxide arrester is needed. In all, the effort required to refurbish the bay in
this way is not commensurate with the benefits obtained.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 9 of 15
9
5.2 Recommendations
The objective of this report is to recommend actions needed to ensure the long-term reliability
and safe operation of the Transformer Gallery GIS. However these recommendations are based
solely on a technical assessment, and whether or not they are adopted will depend on other
factors such as weighing the cost of the remedial work against the financial losses which would
be incurred should a failure occur. Without knowledge of the commercial aspects, several
options (Phases 1-3, below) are presented for evaluation.
In these, Phase 1 is the essential work needed to keep the substation in operation; the addition
of Phase 2 adds operational flexibility such that if a failure were to occur in a main busbar, no
longer would half the generating capacity of the station be lost for some weeks; and Phase 3, in
which the reliability of the lead shafts is considered, should also be undertaken. These three
phases naturally follow each other – for example, the condition and probability of a failure in the
main busbars (Phase 2) cannot be properly assessed until the high levels of PD currently arising
in the transformer bays have been eliminated (Phase 1). From a technical point of view, the
highest reliability of the GIS will be achieved by implementing all three of these phases.
Phase 1
Replace the present disconnects by those of a newer design and improved performance, and
the surge arresters by a metal oxide type. Since all the O-ring seals of the chambers would also
need to be replaced, and adaptor plates fitted, it is simpler to replace the complete bay and this
is the recommended course.
It is common practice in many utilities to install UHF couplers into new GIS, for use both during
commissioning tests on the new plant and later when it is in service. Fitting new chambers will
enable internal couplers to be specified, and all major switchgear manufacturers are able to
supply these mounted on a suitable port. (The existing disconnects are fitted with large windows
on which UHF couplers can be mounted, but it is unlikely that any present-day disconnect will
have windows of sufficient size for this purpose).
Mica Gas Insulated Switchgear Project Appendix E-3
Page 10 of 15
10
To increase the long-term reliability of the GIS, this needs to be followed by Phase 2. Provision
should be made to install a second main busbar, and changes needed to the present bay are
illustrated in Fig 1.
Fig 1 Layouts of the existing and new transformer bay allowing for Phase 2 (for illustration only)
Phase 2
The transformer bays will now be substantially free of PD, although the operating rods in the
inter-tie and lead shaft disconnects may still be discharging. If this interference is not too high, it
should now be possible to detect and locate any PD activity in the busbar. Should the busbar be
reasonably discharge-free, it could be retained. Whether or not to replace it is essentially a
commercial decision, which would no doubt take into account the number of adaptor flanges
which would need to be fitted to the present busbar.
A second busbar will be installed to improve the operational flexibility of the GIS. The
disconnects at the bottom of the lead shafts will be replaced by separate disconnects for each
busbar. The existing inter-tie disconnects will also be replaced (if the present busbar is to be
retained), and others installed in the new busbar.
disconnect 2 disconnect 1
generator transformer
generator transformer
surge arrester
surge arrester
busbar
busbar 1
provision for busbar 2
disconnect
Mica Gas Insulated Switchgear Project Appendix E-3
Page 11 of 15
11
Phase 3
The discharge levels in lead shafts 1 and 2 will be measured, using both UHF and acoustic
technology. Unless a specific problem is found, they will not be replaced until the third lead shaft
is commissioned in 2014.
6. Further diagnostic studies
The reliability of the cone insulators in the busbars has so far been excellent, with only one
failure being reported (lead shaft 1, C phase, 1983). The UHF surveys made in 1999 and 2000
showed a very high level of PD activity throughout the whole GIS, and many of the PD sources
were traced to the disconnect operating rods. Some of these have been replaced by others of a
new design, but the few UHF measurements made subsequently still do not show the GIS to be
completely discharge free. This needs to be investigated further before the operating rods in
other disconnects are replaced.
In the previous surveys, other PD sources were largely masked by the high signals from the
disconnects, but some appeared to be associated with cone insulators. Once the signals from
the disconnects have been eliminated – or at least much reduced – any discharges then found
at the cones should be examined. It is reported in [8] that insulators in sound condition do not
exhibit any ageing mechanisms which might cause an increase in their failure rate with time, and
lifetimes much longer than 30 years are expected. However if the insulators were not
manufactured to a high standard, or have manufacturing defects, their lifetime may be reduced.
The object of this survey is to establish whether any cones are developing internal PD indicative
of degradation.
While the UHF technique is in general the most sensitive method of detecting defects in GIS, it
may lack sensitivity along the lead shafts because no UHF couplers can be fitted there. In this
location further acoustic measurements, such as those reported in [9], may be needed.
Other techniques, notably chemical analysis, have given useful results in the past and may also
be required.
7. Acknowledgement
The assistance given by Mr Bjorn Holm in preparing the technical documents for review, and for
calling on his expert knowledge of the GIS to answer detailed questions, is gratefully
acknowledged.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 12 of 15
12
8. References
1. ‘Comparative review of GIS installations in BC Hydro generating stations and their
operating experience’, R F Cleven, CEA SF6 Insulation Coordination Committee, March
1989.
2. ‘Mica Gas Insulated Switchgear – Problems’, Appendix, File 211-1517.16.0, February
1986.
3. ‘Partial Discharge Survey of Mica 500kV GIS’, Brian Hampton, Report to BC Hydro, 30
March 1999.
4. ‘Identifying and Locating Partial Discharges in Mica 500kV Substation’, Brian Hampton,
Report to BC Hydro, 25 May 2000.
5. ‘Failure Analysis on 500kV SF6 Operating Rod from Mica Generating Station’, Powertech
Labs Inc., Project No 12474-27, July-August 2000.
6. ‘Partial Discharge Test on 500kV SF6 Operating Rods from Mica Generating Station’.
Powertech Labs Inc., Project No 12722-27, December 2000.
7. ‘Partial Discharge Test on 500kV SF6 Operating Rods from Mica Generating Station’.
Powertech Labs Inc., Project No 13536-27, February-March 2002.
8. ‘Long-term Performance of SF6 Insulated Systems’, Paper 15-301, Study Committee 15,
CIGRE Session 2002.
9. ‘Detection of Flaws using the Acoustic Insulation Analyser Type AIA-1’, Report No. TN-
40.400.527.1, May 2000.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 13 of 15
13
APPENDIX: CURRICULUM VITAE of BRIAN HAMPTON 1951-1954 Undergraduate at Imperial College of Science and Technology, London.
Degree of BSc (Eng) with 1st class hons awarded.
1954-1957 Postgraduate research in the Electrical Engineering Dept. of IC, on the study of
particle tracks in a cloud chamber.
Degree of Doctor of Philosophy awarded.
Associate of the City & Guilds Institute awarded.
Diplomate of Imperial College awarded.
Membership of professional institutions:
Fellow, Institution of Electrical Engineers
Fellow, Institute of Physics
Chartered Engineer
Membership of CIGRE:
UK member, Study Committee 15 ‘Insulating Materials’ 1986-1998
UK member, Working Group 15-03 ‘Gaseous Insulation’ and its WG Task Forces, 1986-
present
Employment:
1958-1988 Research Laboratories of the UK utility Central Electricity Generating Board,
London. Responsible for research into failures in transformers, overhead lines
& gas insulated substations, and for technical collaboration with the Research
Departments of the utilities EDF (France) and ENEL (Italy).
1988-1997 Manager, Diagnostics Laboratory of the Centre for Electrical Power
Engineering, University of Strathclyde, Glasgow. Developed the (then) novel
UHF technique, and its practical application in EHV substations.
1997- 2001 Managing Director, Diagnostic Monitoring Systems, Glasgow, a new spin-out
company from the University. DMS designs and manufactures UHF monitoring
equipment for EHV substations.
2001 –2007 President, Diagnostic Monitoring Systems.
Jan 2007 Retired
Mica Gas Insulated Switchgear Project Appendix E-3
Page 14 of 15
14
Experience particularly relevant to the present report:
In 2001 DMS was ready for rapid growth, and I took responsibility for promoting sales. I visited
several of the major utilities many times to discuss the problems they were experiencing with
their GIS, and demonstrate how the UHF technique could help them. Those utilities I came to
know best were in countries where the industry was undergoing the strongest growth, or where
problems with ageing GIS were developing. They were:
Far East: Japan, Korea, Hong Kong, China, Taiwan, Malaysia, Singapore
Middle East: Bahrain, Saudi Arabia, Dubai, Jebel Ali, Sharja
Europe: UK, Germany, France, The Netherlands, Italy
Americas: Canada, USA, Brazil, Paraguay
My experience with GIS in these places has been gained using either portable or installed
monitoring equipment, both during commissioning tests and with GIS in service. Very many
defects were found and corrected during this time, and this has provided the background on
which some of the opinions in my report are based.
Mica Gas Insulated Switchgear Project Appendix E-3
Page 15 of 15
Mica Gas Insulated Switchgear Project
Appendix
F
Mica Gas Insulated Switchgear Capital Expenditures
Mic
a G
IS R
epla
cem
ent P
roje
ct -
Sche
dule
of A
utho
rized
Exp
endi
ture
s -
$Mill
ion
Tota
lF2
008
F200
9F2
010
F201
1F2
012
F201
3F2
014
Expe
cted
Aut
horiz
edId
entif
icat
ion
and
Def
initi
on
Dire
ct0.
53.
02.
25.
75.
7O
verh
ead
0.1
0.4
0.1
0.6
0.6
IDC
0.0
0.1
0.2
0.3
0.3
0.3
1.2
1.2
Tota
l 0.
63.
52.
50.
30.
30.
37.
57.
5
Impl
emen
tatio
n C
osts
Dire
ct -
Exp
ecte
d C
osts
33.9
30.6
17.0
12.8
0.4
94.7
94.7
Man
agem
ent &
Eng
inee
ring
3.5
4.6
4.7
4.8
1.1
18.8
18.8
Exp
ecte
d C
ost C
ontin
genc
y2.
12.
82.
82.
90.
711
.311
.3In
flatio
n0.
92.
22.
32.
60.
38.
48.
4S
ubto
tal
40.5
40.2
26.8
23.1
2.4
133.
113
3.1
Dis
man
tling
and
Rem
oval
0.2
0.2
0.3
0.3
0.1
1.0
1.0
Ove
rhea
d - E
xpec
ted
5.4
5.3
3.6
3.1
0.3
17.7
17.7
IDC
- E
xpec
ted
1.2
4.8
6.4
7.2
1.7
21.3
21.3
Dire
ct -
Incr
ease
to A
utho
rized
2.3
3.0
3.1
3.2
0.7
12.4
Ove
rhea
d - I
ncre
ase
to A
utho
rized
0.3
0.4
0.4
0.4
0.1
1.7
IDC
- In
crea
se to
Aut
horiz
ed0.
10.
30.
50.
80.
32.
0S
ubto
tal
9.4
14.1
14.4
15.0
3.2
40.0
56.1
Pro
ject
Cos
ts b
efor
e M
anag
emen
t Res
erve
50.0
54.3
41.2
38.2
5.6
173.
218
9.2
Man
agem
ent R
eser
ve (L
oade
d)3.
53.
5
Tota
l Im
plem
enta
tion
Pro
ject
Cos
ts50
.054
.341
.238
.29.
117
3.2
192.
7
Tota
l Pro
ject
Cos
ts
0.6
3.5
52.5
54.6
41.5
38.5
9.1
180.
620
0.2
Mica Gas Insulated Switchgear Project Appendix F
Page 1 of 1
Mica Gas Insulated Switchgear Project
Appendix
G
Most Severe Single Contingency
July 13, 2009
Owen Williams, M.Eng, P.Eng, PMP Project Manager, Generation BC Hydro
Re: BCTC’s review of the proposed Mica switchyard configuration:
Dear Owen, Mica GS is one of the largest generation stations in the BC electric system and plays a critical role in system reliability. A high level of reliability is expected from Mica 500 kV GIS switchgear from a system planning perspective. Presently, the Most Severe Single Contingency (MSSC) in the BCTC / BC Hydro system is 1000MW. This represents the largest possible loss of generation as a result of the outage of a single element, a lead shaft at Revelstoke. Once Revelstoke unit 5 is commissioned, the MSSC will increase from 1000MW to 1500MW as three 500MW generating units will be connected to a single lead shaft. Studies for the integration of Revelstoke unit 5 concluded that this increase in MSSC was acceptable. 1500MW was determined to be an upper limit for the MSSC that could be managed by relying on generation reserves within BC and the North West Power Pool without negatively affecting system reliability or transfer limits. BCTC notes that while the proposed designs for Mica units 5 and 6 incorporate the addition of a third lead shaft, there may be switching configurations that allow more than two units connected to a single lead shaft. BCTC will require BC Hydro to limit the amount of generation that may end up being connected to a single Mica lead shaft to 1500MW in order to respect the MSSC limit. Sincerely,
Paul Choudhury
Manager, System Planning & Performance Assessment
c.c. K. Zhang, G. Kehl, G. Wang, BCTC File: STN:MCA
Paul Choudhury P.Eng
Manager, System Planning & Performance Assessment
Suite 1100, Four Bentall Centre
1055 Dunsmuir Street
P O Box 49260
Vancouver, B.C. V7X 1V5
Phone: (604) 699-7374
Fax: (604) 699-7452
e-mail: [email protected]
Mica Gas Insulated Switchgear Project Appendix G
Page 1 of 1
Mica Gas Insulated Switchgear Project
Appendix
H
Lead Shaft Requirements for Mica with Four to Six Units
Lead Shaft Requirement for Mica with Four to Six Units In evaluating replacement options and how the Project can best meet the long term
needs of Mica, an understanding of the number of lead shafts required for different
generating capacities is required. Engineering practice is to design wherever possible, to
ensure the maximum power from Mica can continue to be transmitted in the event of a
single contingency (i.e. a failure of one major piece of equipment). While each lead shaft
is capable of conducting the power of all six units, BC Hydro is restricted to transferring a
maximum of 1500 MW. This restriction is imposed to ensure system wide operating
stability. A sudden drop in generation of 1500MW or more has the potential to impacts
the stability of the electric grid.
Table 1 shows that with the existing four unit Mica and two lead shafts, 500MW of power
cannot be transferred during a planned or forced outage of a lead shaft. Three lead
shafts for a four unit Mica would provide more flexibility and reduce the need for planned
outages for some maintenance and replacement work. Additionally, with three lead
shafts, the capacity at risk in the event of a single GIS equipment failure is nil for Mica
regardless of whether it had four, five or six units.
The addition of one or two more units (estimated at 500 MW each) requires an additional
lead shaft for Mica as otherwise 800 MW or 1300 MW of capacity is at risk in during a
planned or forced outage of a lead shaft GIS.
Table 1 - Capacity at Risk
Description Formula Measure Number of Units
Number of Generating Units Units 4 5 6
Approximate Capacity of incremental Unit MW 500+ 500+
Mica Capacity A MW 1800 2300 2800
Transfer capacity of each Lead Shaft B MW 1500 1500 1500
2 lead shafts in-service Capacity at risk in event of planned or forced outage of one of the two lead
C=A-B MW 300 800 1300
3 lead shafts in-service Capacity at risk in event of planned or forced outage of one of the three lead shafts
D = (B X 2) - A Nil Nil Nil
Mica Gas Insulated Switchgear Project Appendix H
Page 1 of 1
Mica Gas Insulated Switchgear Project
Appendix
I
GIS Replacement Alternative Assumptions
GIS Replacement Alternatives Assumptions
1. Introduction
The purpose of this appendix is to explain the basis for the PVs provided in Tables 4-2 and 4-4
of the Application.
Section 2 of this appendix provides the assumptions used for the PV calculations. Section 3
explains the basis for the range of outage consequences at Mica from $6 million to $19 million
shown in Table 4-2. Section 4 shows how, by combining the outage consequences with outage
probabilities the "Range of Outage costs" shown in Table 4-2 are determined. Section 5
provides the breakdown of the major Project components (i.e., lead shaft 1, lead shaft 2 etc.)
which are used for calculating the PVs of the alternatives and options shown in Tables 4-2 and
4-4. Section 6 provides the construction schedule and cost assumptions used in determining the
PVs for the alternatives in Table 4-2. Section 7 provides the construction schedule and cost
assumptions used for determining the PVs of the options in Table 4-4.
2. Key Assumptions
• The GIS must be replaced by 2025 in all scenarios. This was the original life expectancy of
the asset before considering the actual condition of the asset.
• The discount rate applied for PV analysis is 8 per cent nominal or 6 per cent real.
• $134 million is used as the base case project cost consisting of the implementation phase
project cost (direct) (excluding inflation) of $130.6 million (refer to Table 4) plus $3 million for
planning and engineering (refer to Table 5).
• The estimated costs are based on an ISD of 2013.
• If the Project schedule or staging is changed such that portions of the Project are deferred
cost increases were assumed due to:
tendering and procuring lower quantities;
incremental engineering, planning and design for Identification, Definition and
Implementation phases;
additional interfaces;
Mica Gas Insulated Switchgear Project Appendix I
Page 1 of 10
higher mobilization costs due to multiple mobilizations as a result of piecemeal
approach; and
fixed project costs which would not be reduced due to changes in scope.
• References to lead shaft 3 include the cost of the switchgear building extension, installing
bus in lead shaft 3, circuit breakers, disconnect switches and bus to connect new GIS to
existing GIS. These components are combined due to assumed dependencies. For
example, it is assumed that the switchgear building extension would not occur without
installing GIS in lead shaft 3;
• Escalation rates used range from 0.9 per cent to 3 per cent with cumulative escalation of
25.5 per cent over 15 years or 1.7 per cent average per year. Escalation is an estimate of
the expected incremental inflation on certain cost of materials and labour not included in
estimates of average annual inflation rates. The cost of alternatives which defer a portion or
all of the Project costs to later years are escalated based on these rates; and
• Where GHG offsets are included, the estimated value applied is $23 per tonne of CO2
equivalent. This is based on the 2008 LTAP average cost of the low scenario forecast for
GHG offsets for the period 2013 to 2027.
3. Range of Outage Consequences
This section describes how, for the purpose of this application, the range of outage
consequences at Mica is determined. This range of outage consequences is, as described in
section 4 below, combined with various probabilities of outages to come up with the “range of
outage costs” for each alternative in Table 4-2 of the Application.
Mica represents 16 per cent of BC Hydro’s capacity and all of the units have an annual average
utilization factor of 45 per cent. Maintenance is usually performed in the April to July period of
each year, with planned outages on two units. During winter peak periods and in late July to
September the utilization factor is higher due to domestic load and trade opportunities.
The opportunity cost of capacity and energy vary significantly due to domestic load
requirements, trade opportunities, and variances in water conditions and stream flows in the
Pacific Northwest. If a one unit forced outage were to occur during the winter peak the
opportunity cost is estimated to be about $2 million per week based on:
Average import price net of transmission cost = $40/MWh
Mica Gas Insulated Switchgear Project Appendix I
Page 2 of 10
Capacity per unit = 450 MW
Winter Load = 69 per cent
Opportunity Cost = $2 million 1 per week.
The cost of outages at Mica can be significantly reduced because, in most cases, the water can
be held in the reservoir for future generation and future revenue earning opportunities. However,
depending on reservoir levels and stream flow conditions, situations could occur where water
would have to be spilled at Mica to maintain water flows downstream for Revelstoke and for
water license requirements. Although less likely to occur, the consequence of spilling are costly.
GIS failures can result in extended forced outages. Failures of GIS in a lead shaft could take
ten weeks to repair as access and repair is challenging. Combined with the lack of spare parts
for the equipment, outages of two days to 12 weeks are considered likely. The cost of
purchasing replacement parts on an emergency basis can be two to three times more than the
cost to purchase on a planned basis. Depending on the cause and location of a GIS failure in
Mica, two unit outages are also possible. Table 1 provides examples of potential outage
consequences, with a range in value of $2 million to $36 million.
Table 1 Potential Outage Consequences (in $000’s)
Outage Scenario Opportunity Cost Energy
Capacity Reservation
Labour and Material
Total Outage cost
Assumption
A Forced outage in spring
Nil Nil $2,000-6,000 $2,000-6,000 Forced outage occurs between April to July
B 6 week of 2 Unit forced outage
$1,740 $850 $2,000 $4,590 Valuation based on equal chance of outage throughout year, Opportunity cost of energy at $43.25/MWh, Capacity Reservation cost at $17/MW winter
C 12 weeks of 2 units forced outage
$4,080 $1,700 $4,000 $9,780 Same assumption as B
D 4 weeks of 4 units forced outage
$8,210 $2,620 $6,000 $16,830 Same assumption as B
1 450MW x $40/MWh X 24 hours/day x 7 days/week x 69 per cent = $2 million per week.
Mica Gas Insulated Switchgear Project Appendix I
Page 3 of 10
Outage Scenario Opportunity Cost Energy
Capacity Reservation
Labour and Material
Total Outage cost
Assumption
E 6 week of 2 Unit forced outage
$3,480 $1,060 $2,000 $6,540 Validation based on equal chance of outage throughout the year. Opportunity cost of energy based on 2006 Call for Tender price of $83/MWh net of transmission, Capacity Reservation cost at $34/MW
F 12 weeks of 2 units forced outage
$8,160 $2,125 $4,000 $14,285 Same assumption as E
G weeks of 4 units forced outage
$16,420 $3,275 $6,000 $25,695 Same assumption as E
H 300 MW loss resulting from single lead shaft failure, 8 weeks
$7,260 $3,000 $10,260 300 MW outage, Opportunity cost of energy estimated at $40 MWh; 45 per cent plant utilization of all units.
I 300 MW loss resulting from single lead shaft failure, 8 weeks
$23,090 $6,000 $29,090 300 MW outage, Opportunity cost of energy estimated at $83 MWh and 69 per cent winter plant utilization.
J 450 MW unit out 8 weeks outage
$10,890 $1,000 $11,890 450 MW outage, Opportunity cost of energy estimated at $40 MWh; 45 per cent average plant utilization.
K 450 MW unit out 8 weeks outage
$34,640 $2,000 $36,640 450 MW outage, Opportunity cost of energy estimated at $83MWh and 69 per cent winter plant utilization.
Table 1 illustrates outage costs depending on time of year, market prices, plant utilization and
water conditions for some probable outage scenarios. To reduce the number of scenarios for
financial analysis, the range of potential outage consequences is reduced to probable low,
moderate and high consequences. Outage values provided in Table 2 below are used as
proxies for the outage costs of Mica.
Mica Gas Insulated Switchgear Project Appendix I
Page 4 of 10
Table 2 Range of Outage Consequence Costs used in Financial Analysis
Outage Consequence Scenario Total Cost
($ million)
Low Consequence $6
Moderate Consequence $12
High Consequence $19
In 2009, a review of the consequence of extending a planned four month (April to July) two unit
outage by one month through August was estimated to cost between $3 million and $20 million.
Given that prolonged planned two-unit outages during this period are common, the study
supports the range of values in Table 2 being used in the financial analysis in Table 4-2 of the
Application.
4. Probability and Cost of Outages
This section describes how the range of outage consequences in Table 2 is combined with the
probability of a failure at Mica to determine the PV of outage costs. The PV of outage costs are
then used to determine the “range of outage costs” in Table 4-2 of the Application.
One of the independent GIS experts who assessed the Mica GIS concluded that there was a
99 per cent chance of a GIS failure within ten years or, in other words, there is a 33 per cent
chance2 of failure in each of the next ten years. The risk of a GIS failure is expected to increase
over time as the GIS ages.
Table 3 provides a summary of the PV of the potential cost of outages if BC Hydro deferred the
replacement for ten years. The PV of outage costs is shown for the three outage consequence
scenarios from Table 2 and a range of annual failure probabilities.
2 A 99 per cent failure in ten years can be translated to a 33 per cent failure per annum by applying the Bernoulli
formula as follows: [Probability of Failure in x = 1 - (1 - Probability of failure/year)x ].
Mica Gas Insulated Switchgear Project Appendix I
Page 5 of 10
Table 3 PV Cost of GIS Failures at Different Probabilities of Failure for 10 years
Model Parameters
Real discount rate 6.00%
Number of useful years of service 10 Annual Probability of Failure
Outage Cost Predicted
Scenario Parameters ($2009 $000) 15.0% 20.0% 33.0% 40.0%
Case 1 - Low Consequence $6,000 ($000) ($000) ($000) ($000)
Annual Outage Costs
($6000xAnnual Probability of Failure) $900 $1,200 $1,980 $2,400
PV of Outage Costs for 10 years $6,624 $8,832 $14,573 $17,664
Case 2 - Moderate Consequence $12,000
Annual Outage Costs
($12000xAnnual Probability of Failure) $1,800 $2,400 $3,960 $4,800
PV of Outage Costs for 10 years $13,248 $17,664 $29,146 $35,328
Case 3 - High Consequence $19,000
Annual Outage Costs
($19000xAnnual Probability of Failure) $2,850 $3,800 $6,270 $7,600
PV of Outage Costs for 10 years $20,976 $27,968 $46,148 $55,937
5. Project Cost
In order to determine the PV of the alternatives and options in Table 4-2 and Table 4-4 of the
Application, the costs of the components of the Project (i.e. lead shaft 1, lead shaft 2 etc) were
determined. This section provides the component costs.
Table 4 is the breakdown of total Project costs. The $2009 Implementation phase direct capital
cost of the Project is used for the financial analysis. The direct cost represents the incremental
cost to BC Hydro before, inflation, IDC and overhead. The breakdown of Implementation phase
direct costs by component is shown in Table 5.
Mica Gas Insulated Switchgear Project Appendix I
Page 6 of 10
Table 4 Project Cost
PROJECT COST AMOUNT ($ million)
Direct Construction Cost 94.6
Project Management and Engineering 18.8
Sub-total: Construction Cost before Contingency $113.4
Contingency on Expected Cost 11.3
Dismantling and Removal 1.0
Escalation 4.9
Implementation Phase Cost (Direct Capital) $2009 $130.6
Inflation 3.5
Sub-total: Implementation Phase Cost (Direct Capital) $134.1
Capital Overhead 17.7
Interest During Construction 21.3
Sub-total: Implementation Phase Cost (Loaded) $173.1
Identification and Definition Phase (Loaded) 7.5
Total Expected Cost $180.6
Project Reserve 19.6
Total Authorized Cost $200.2
Mica Gas Insulated Switchgear Project Appendix I
Page 7 of 10
Table 5 Allocated Implementation Phase Direct Cost by Major Component
Component Cost ($2009 millions)
Replacement of existing GIS in transformer gallery 31
Replacement of existing GIS in switchgear building 14
Lead shaft 2 13
Lead shaft 1 13
Lead shaft 3, switchgear building extension, and all new GIS required in the transformer chamber and switchgear building
60
Total Implementation Phase (Direct) Project cost $131 Identification and Definition Planning and Engineering (Direct) 3
Total Direct Cost $134
The cost of implementing a different scope of work in the future is not expected to be equivalent
to the allocated component cost shown in Table 4. The cost to design, engineer and procure a
smaller scope of work is not proportionally reduced by the scope of the Project. To provide a
comparison of the alternatives in Table 4-2 and options in Table 4-4, the total direct cost
($2009) for the Project of $134 million is compared to the alternatives of Table 4-2 in Table 6
and compared to the options of Table 4-4 in Table 7 below.
6. Alternative Analysis
Table 6 provides a summary of the direct costs ($2009) for the alternatives of Table 4-2 along
with the construction schedule and cost assumptions used to determine the cost of the
alternatives. All alternatives assume that Identification and Definition phase Project costs will be
$3 million for the Project undertaken in full and for components of the Project that are deferred.
The costs are escalated to reflect the cost that is likely to be incurred if deferred but exclude
general inflation increases. Cash flows are discounted by 6 per cent.
Mica Gas Insulated Switchgear Project Appendix I
Page 8 of 10
Table 6 Cost of Replacement Alternatives
Description of Alternative Construction Schedule and Cost Assumptions
Percent change in cost from
Base (%)
Direct Cost ($2009 millions)
Alternative 1: Implement Full Project Scope by 2013
Base Case, lead shaft 3 (2010/11), lead shaft 2 (2012) and lead shaft 1 (2013).
Base 134
Alternative 2a: Implement lead shaft 3 by 2013, defer replacement of existing GIS by 5 years
Lead shaft 3 (2011/12), replacement costs deferred (2017 or 5 years) Base Case plus additional $3 million for duplicate planning costs as Project segmented.
2 136
Alternative 2b: Implement lead shaft 3 by 2013, defer replacement of existing GIS by 10 years
Lead shaft 3 (2011/12), replacement cost deferred (2021 or 10 years). Base Case plus additional $3 million for duplicate planning costs as Project segmented.
2 136
Alternative 3: Implement lead shaft 3 by 2013, piecemeal replacement of existing
Lead shaft 3 (2011/12) replacement of existing GIS in 4 separate projects over next 10 years. Additional costs incurred for planning, procurement and mobilization
15 153
Alternative 4: Implement lead shaft 3 by 2013, defer replacement of Lead shaft 1 and 2
Lead shaft 3 (2011/12), transformer gallery and switchgear building GIS (2012/2013), lead shaft 2 (2020) and lead shaft 1 (2021) Additional costs incurred for higher procurement and mobilization.
9 146
7. Option Analysis
Table 7 provides a summary of the direct costs ($2009) for the options of Table 4-4 along with
the construction schedule and cost assumptions used to determine the cost of each option.
Since the ISD for Mica Unit 5 is uncertain, the dates and hence the timing of the investment in
the lead shafts 1, 2 and 3 have been varied. However for all alternatives it has been assumed
all Project components would be in-service before Mica Unit 5. Options 2, 3 and 4 are
implemented before 2018 while option 5, 6 and 7 are implemented before 2025. It is assumed
that certain planning and engineering, mobilization and procurement costs would not decline
proportionately if portions of the Project were deferred. All alternatives assume that Identification
and Definition phase Project costs will be $3 million for the Project undertaken in full and for
Mica Gas Insulated Switchgear Project Appendix I
Page 9 of 10
components of the Project that are deferred. The costs are escalated to reflect the cost that is
likely to be incurred if deferred but exclude general inflation increases. Cash flows are
discounted by 6 per cent.
Table 7 Cost of Options
Description of Alternative Construction Schedule and Cost Assumptions
Percentage change in cost
from Base (%)
Direct Cost ($2009 millions)
Option 1: Implement Full Project Scope by 2013
Base Case, lead shaft 3 (2010/11), lead shaft 2 (2012) and lead shaft 1 (2013).
Base $134
Options 2: Replace existing GIS by 2013, defer lead shaft 2 and 1
Lead shaft 3 (2010/11), existing in transformer gallery and switchgear (2012/2013), lead shaft 2 (2017), lead shaft 1 (2018). Estimated of increase based on fixed procurement, planning and mobilization costs.
9 146
Options 3: Replace existing GIS by 2013, defer lead shaft 3
Existing in transformer gallery and switchgear building (2010/2011), lead shaft 2 (2012), Lead shaft 1 (2013) lead shaft 3 (2016/17) Estimated of increase based on fixed procurement, planning and mobilization costs.
17 157
Options 4: Replace existing GIS and implement lead shaft 3, defer lead shaft 1
All existing and lead shaft 3 by 2013 except lead shaft 1 (2018) Estimated of increase based on fixed procurement, planning and mobilization costs.
4 139
Options 5: Replace existing GIS by 2013, defer lead shaft 2 and 1
Lead shaft 3 (2010/11), existing in transformer gallery and switchgear (2012/2013), but Lead shaft 2 (2023), Lead shaft 1 (2024) Estimated of increase based on fixed procurement, planning and mobilization costs.
9 146
Option 6: Replace existing GIS by 2013, defer lead shaft 3
Existing in transformer gallery and switchgear building (2010/2011), lead shaft 2 (2012), lead shaft 1 (2013) lead shaft 3 (2023/2024) Estimated of increase based on fixed procurement, planning and mobilization costs.
17 157
Option 7: Replace existing GIS and implement lead shaft 3, defer lead shaft 1
All existing and lead shaft 3 by 2013 except lead shaft 1 (2025) Estimated of increase based on fixed procurement, planning and mobilization costs.
4 139
Mica Gas Insulated Switchgear Project Appendix I
Page 10 of 10
Mica Gas Insulated Switchgear Project
Appendix
J
First Nations Consultation Record
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 1
of 2
7
2009
-Sep
t-17
Ktu
naxa
Nat
ion
Cou
ncil
Site
Vis
it B
CE
AO
N
/A
KNC
B
CE
AO
B
C M
inis
try o
f E
nviro
nmen
t C
olum
bia
Shus
wap
R
egio
nal
Dis
trict
Tour
of M
CA
GS
and
the
loca
tion
of th
e ex
istin
g an
d pr
opos
ed e
xten
sion
of t
he s
witc
hgea
r bui
ldin
g.
2009
-Sep
t-17
Littl
e S
husw
ap
Site
Vis
it B
CE
AO
N
/A
LSIB
B
CE
AO
B
C M
inis
try o
f E
nviro
nmen
t C
olum
bia
Shus
wap
R
egio
nal
Dis
trict
Tour
of M
CA
GS
and
the
loca
tion
of th
e ex
istin
g an
d pr
opos
ed e
xten
sion
of t
he s
witc
hgea
r bui
ldin
g.
2009
-Sep
t-17
Oka
naga
n N
atio
n Al
lianc
e S
ite V
isit
BC
EA
O
N/A
ON
A
BC
EA
O
BC
Min
istry
of
Env
ironm
ent
Col
umbi
a Sh
usw
ap
Reg
iona
l D
istri
ct
Tour
of M
CA
GS
and
the
loca
tion
of th
e ex
istin
g an
d pr
opos
ed e
xten
sion
of t
he s
witc
hgea
r bui
ldin
g.
2009
-Sep
t-17
Spl
atsi
n S
ite V
isit
BC
EA
O
N/A
Spl
atsi
n B
CE
AO
B
C M
inis
try o
f E
nviro
nmen
t C
olum
bia
Shus
wap
R
egio
nal
Dis
trict
Tour
of M
CA
GS
and
the
loca
tion
of th
e ex
istin
g an
d pr
opos
ed e
xten
sion
of t
he s
witc
hgea
r bui
ldin
g.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 1 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 2
of 2
7
2009
-Feb
-19
Adam
s La
ke
Lette
r BC
H (R
yan
McF
adde
n)
Adam
s La
ke
(Chi
ef N
elso
n Le
on)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Bon
apar
te
Lette
r BC
H (R
yan
McF
adde
n)
Bon
apar
te (C
hief
Te
rry
Por
ter)
N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Col
umbi
a La
ke
Lette
r BC
H (R
yan
McF
adde
n)
Col
umbi
a La
ke
(Chi
ef W
ilfre
d Te
nese
e)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-1
Page 2 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 3
of 2
7
will
look
like
with
the
exte
nsio
n;
a
diag
ram
sho
win
g an
arc
hite
ctur
al v
iew
of h
ow
the
lead
shaf
ts c
onne
ctin
g th
e sw
itchg
ear b
uild
ing
to th
e un
derg
roun
d po
wer
hous
e; a
nd
P
ower
Poi
nt p
rese
ntat
ion
on th
e G
IS P
roje
ct w
as
give
n at
the
Janu
ary
29, 2
009
Cor
e C
omm
ittee
.
2009
-Feb
-19
Kam
loop
s Le
tter
BCH
(Rya
n M
cFad
den)
Kam
loop
s (C
hief
Sh
ane
Got
tfrie
dson
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
KN
C
Lette
r BC
H (R
yan
McF
adde
n)
KN
C (B
ill G
reen
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 3 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 4
of 2
7
2009
-Feb
-19
Lhei
dli T
’enn
eh
Lette
r BC
H (R
yan
McF
adde
n)
Lhei
dli T
’enn
eh
(Chi
ef D
omin
ic
Fred
eric
k)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Littl
e S
husw
ap
Lette
r BC
H (R
yan
McF
adde
n)
Littl
e Sh
usw
ap
(Chi
ef F
elix
Ar
nous
e)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Low
er K
oote
nay
Lette
r BC
H (R
yan
McF
adde
n)
Low
er K
oote
nay
(Chi
ef C
hris
toph
er
Luke
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-1
Page 4 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 5
of 2
7
will
look
like
with
the
exte
nsio
n;
a
diag
ram
sho
win
g an
arc
hite
ctur
al v
iew
of h
ow
the
lead
shaf
ts c
onne
ctin
g th
e sw
itchg
ear b
uild
ing
to th
e un
derg
roun
d po
wer
hous
e; a
nd
P
ower
Poi
nt p
rese
ntat
ion
on th
e G
IS P
roje
ct w
as
give
n at
the
Janu
ary
29, 2
009
Cor
e C
omm
ittee
.
2009
-Feb
-19
Low
er
Sim
ilkam
een
Lette
r BC
H (R
yan
McF
adde
n)
Low
er
Sim
ilkam
een
(Chi
ef J
osep
h D
enni
s)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Nes
konl
ith
Lette
r BC
H (R
yan
McF
adde
n)
Nes
konl
ith (C
hief
Ju
dy W
ilson
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 5 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 6
of 2
7
2009
-Feb
-19
Oka
naga
n Le
tter
BCH
(Rya
n M
cFad
den)
O
kana
gan
(Chi
ef
Fabi
an A
lexi
s)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
ON
A
Lette
r BC
H (R
yan
McF
adde
n)
Oka
naga
n N
atio
n Al
lianc
e (E
xecu
tive
Dire
ctor
Pau
line
Terb
aske
t)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Oso
yoos
Le
tter
BCH
(Rya
n M
cFad
den)
O
soyo
os (C
hief
C
lare
nce
Loui
e)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-1
Page 6 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 7
of 2
7
will
look
like
with
the
exte
nsio
n;
a
diag
ram
sho
win
g an
arc
hite
ctur
al v
iew
of h
ow
the
lead
shaf
ts c
onne
ctin
g th
e sw
itchg
ear b
uild
ing
to th
e un
derg
roun
d po
wer
hous
e; a
nd
P
ower
Poi
nt p
rese
ntat
ion
on th
e G
IS P
roje
ct w
as
give
n at
the
Janu
ary
29, 2
009
Cor
e C
omm
ittee
.
2009
-Feb
-19
Pen
ticto
n Le
tter
BCH
(Rya
n M
cFad
den)
P
entic
ton
(Chi
ef
Ste
war
t Phi
llip)
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Shus
wap
Le
tter
BCH
(Rya
n M
cFad
den)
Sh
usw
ap (C
hief
P
aul S
am)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 7 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 8
of 2
7
2009
-Feb
-19
Sim
pcw
Le
tter
BCH
(Rya
n M
cFad
den)
S
impc
w (C
hief
K
eith
Mat
thew
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Ske
etch
estn
Le
tter
BCH
(Rya
n M
cFad
den)
Ske
etch
estn
(C
hief
Ric
k D
enea
ult)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
SN
TC
Lette
r BC
H (R
yan
McF
adde
n)
SN
TC (D
irect
or
Bob
Moo
dy)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-1
Page 8 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 9
of 2
7
will
look
like
with
the
exte
nsio
n;
a
diag
ram
sho
win
g an
arc
hite
ctur
al v
iew
of h
ow
the
lead
shaf
ts c
onne
ctin
g th
e sw
itchg
ear b
uild
ing
to th
e un
derg
roun
d po
wer
hous
e; a
nd
P
ower
Poi
nt p
rese
ntat
ion
on th
e G
IS P
roje
ct w
as
give
n at
the
Janu
ary
29, 2
009
Cor
e C
omm
ittee
.
2009
-Feb
-19
Spl
atsi
n Le
tter
BCH
(Rya
n M
cFad
den)
S
plat
sin
(Chi
ef
Way
ne C
hris
tian)
N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
St.
Mar
y's
Lette
r BC
H (R
yan
McF
adde
n)
St.
Mar
y's
(Chi
ef
Sop
hie
Pie
rre)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 9 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 10
of 2
7
2009
-Feb
-19
Toba
cco
Pla
ins
Lette
r BC
H (R
yan
McF
adde
n)
Toba
cco
Plai
ns
(Chi
ef M
ary
Mah
seel
ah)
N/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Upp
er N
icol
a Le
tter
BCH
(Rya
n M
cFad
den)
Upp
er N
icol
a (C
hief
Tim
M
anue
l) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Upp
er
Sim
ilkam
een
Lette
r BC
H (R
yan
McF
adde
n)
Upp
er
Sim
ilkam
een
(Ric
hard
Hol
mes
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-1
Page 10 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 11
of 2
7
will
look
like
with
the
exte
nsio
n;
a
diag
ram
sho
win
g an
arc
hite
ctur
al v
iew
of h
ow
the
lead
shaf
ts c
onne
ctin
g th
e sw
itchg
ear b
uild
ing
to th
e un
derg
roun
d po
wer
hous
e; a
nd
P
ower
Poi
nt p
rese
ntat
ion
on th
e G
IS P
roje
ct w
as
give
n at
the
Janu
ary
29, 2
009
Cor
e C
omm
ittee
.
2009
-Feb
-19
Wes
tban
k Le
tter
BCH
(Rya
n M
cFad
den)
W
estb
ank
(Chi
ef
Rob
ert L
ouie
) N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
2009
-Feb
-19
Whi
sper
ing
Pin
es
Lette
r BC
H (R
yan
McF
adde
n)
Whi
sper
ing
Pin
es
(Chi
ef M
icha
el
LeB
ourd
ais)
N
/A
Sw
itchg
ear P
roje
ct N
otifi
catio
n Le
tter i
ndic
atin
g B
C H
ydro
w
ould
be
initi
atin
g m
aint
enan
ce a
nd re
furb
ishm
ent w
ork
to
exte
nd th
e sw
itchg
ear b
uild
ing
to a
ccom
mod
ate
the
inst
alla
tion
of n
ew a
nd re
plac
emen
t sw
itchg
ear.
A
ttach
men
ts a
nd e
nclo
sure
s in
clud
ed a
pho
to o
f Mic
a D
am
show
ing
switc
hgea
r bui
ldin
g;
a
phot
o of
the
exis
ting
switc
hgea
r bui
ldin
g;
a
rend
erin
g sh
owin
g w
hat t
he s
witc
hgea
r bui
ldin
g w
ill lo
ok li
ke w
ith th
e ex
tens
ion;
a di
agra
m s
how
ing
an a
rchi
tect
ural
vie
w o
f how
th
e le
adsh
afts
con
nect
ing
the
switc
hgea
r bui
ldin
g to
the
unde
rgro
und
pow
erho
use;
and
Pow
erP
oint
pre
sent
atio
n on
the
GIS
Pro
ject
was
gi
ven
at th
e Ja
nuar
y 29
, 200
9 C
ore
Com
mitt
ee.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 11 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 12
of 2
7
2009
-Mar
-23
Adam
s La
ke
Emai
l B
CE
AO
(Bria
n M
urph
y)
Adam
s La
ke
(Chi
ef N
elso
n Le
on)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Bona
parte
Em
ail
BC
EA
O (B
rian
Mur
phy)
B
onap
arte
(Chi
ef
Mik
e R
etas
ket)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Can
im L
ake
Emai
l B
CE
AO
(Bria
n M
urph
y)
Can
im L
ake
(C
hief
Mik
e A
rchi
e)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Can
oe C
reek
Em
ail
BC
EA
O (B
rian
Mur
phy)
Can
oe C
reek
(C
hief
Han
k A
dam
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 12 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 13
of 2
7
2009
-Mar
-23
Esk
etem
c E
mai
l B
CE
AO
(Bria
n M
urph
y)
Esk
etem
c (C
hief
C
harle
ne B
elle
au)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Hig
h B
ar
Emai
l B
CE
AO
(Bria
n M
urph
y)
Hig
h B
ar (C
hief
Le
nora
Fle
tche
r) Te
ena
Sella
rs
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Kam
loop
s Em
ail
BC
EA
O (B
rian
Mur
phy)
Kam
loop
s (C
hief
Sh
ane
Got
tfrie
dson
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
KNC
Em
ail
BC
EA
O (B
rian
Mur
phy)
K
NC
(Bill
Gre
en)
Chr
is B
eers
S
ophi
e P
ierre
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 13 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 14
of 2
7
2009
-Mar
-23
Lhei
dli T
’enn
eh
Emai
l B
CE
AO
(Bria
n M
urph
y)
Lhei
dli T
’enn
eh
(Chi
ef D
omin
ic
Fred
eric
k)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Littl
e Sh
usw
ap
Emai
l B
CE
AO
(Bria
n M
urph
y)
LSIB
(Chi
ef F
elix
Ar
nous
e)
Rec
eptio
n
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Low
er K
oote
nay
Em
ail
BC
EA
O (B
rian
Mur
phy)
LK
oot (
Chi
ef
Chr
isto
pher
Luk
e)
Rec
eptio
n
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Low
er
Sim
ilkam
een
Emai
l B
CE
AO
(Bria
n M
urph
y)
LSIM
(Chi
ef J
oe
Den
nis)
N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 14 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 15
of 2
7
2009
-Mar
-23
Nes
konl
ith
Emai
l B
CE
AO
(Bria
n M
urph
y)
Nes
konl
ith (C
hief
Ju
dy W
ilson
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Nor
ther
n Sh
usw
ap T
ribal
C
ounc
il Em
ail
BC
EA
O (B
rian
Mur
phy)
N
STC
(Gor
don
Ste
rritt
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Oka
naga
n Em
ail
BC
EA
O (B
rian
Mur
phy)
O
KIB
(Chi
ef
Fabi
an A
lexi
s)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
ON
A
Em
ail
BC
EA
O (B
rian
Mur
phy)
ON
A (E
xecu
tive
Dire
ctor
, Pau
line
Terb
aske
t) Ja
y Jo
hnso
n H
eidi
McG
rego
r Ad
die
Veda
n
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 15 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 16
of 2
7
2009
-Mar
-23
Oso
yoos
E
mai
l B
CE
AO
(Bria
n M
urph
y)
Oso
yoos
(Chi
ef
Cla
renc
e Lo
uie)
N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Pen
ticto
n E
mai
l B
CE
AO
(Bria
n M
urph
y)
PIB
(Chi
ef S
tew
art
Phill
ip)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Soda
Cre
ek
Emai
l B
CE
AO
(Bria
n M
urph
y)
SC
RE
EK
( Chi
ef
Lenn
y S
ella
rs)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Sim
pcw
E
mai
l B
CE
AO
(Bria
n M
urph
y)
Sim
pcw
(Chi
ef
Kei
th M
atth
ew)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 16 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 17
of 2
7
2009
-Mar
-23
Ske
etch
estn
E
mai
l B
CE
AO
(Bria
n M
urph
y)
Ske
e (C
hief
Ric
k D
enau
lt)
Rec
eptio
n
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
SNTC
Em
ail
BC
EA
O (B
rian
Mur
phy)
SN
TC (T
ribal
D
irect
or B
ob
Moo
dy)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Spl
atsi
n E
mai
l B
CE
AO
(Bria
n M
urph
y)
Spl
atsi
n (C
hief
W
ayne
Chr
istia
n)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
St.
Mar
y's
Em
ail
BC
EA
O (B
rian
Mur
phy)
S
TM
(RS
ebas
tian)
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 17 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 18
of 2
7
2009
-Mar
-23
Toba
cco
Plai
ns
Emai
l B
CE
AO
(Bria
n M
urph
y)
TAB
P (C
hief
Mar
y M
ahse
elah
) A
dmin
istra
tion
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Upp
er N
icol
a Em
ail
BC
EA
O (B
rian
Mur
phy)
U
PN
IC (C
hief
Tim
M
anue
l) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Upp
er
Sim
ilkam
een
Emai
l B
CE
AO
(Bria
n M
urph
y)
UP
SIM
(Chi
ef
Ric
hard
Hol
mes
) N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
Wes
tban
k E
mai
l B
CE
AO
(Bria
n M
urph
y)
WB
AN
K (C
hief
Jo
nath
an K
ruge
r) C
Clo
ugh
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 18 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 19
of 2
7
2009
-Mar
-23
Whi
sper
ing
Pine
s Em
ail
BC
EA
O (B
rian
Mur
phy)
W
PIN
ES
(Chi
ef
Mic
hael
Le
Bou
rdai
s)
N/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-23
McD
onal
d an
d C
o.
Lega
l Cou
nsel
Emai
l B
CE
AO
(Bria
n M
urph
y)
Mic
hael
McD
onal
d N
/A
BC
EA
O (B
M) i
ndic
ated
BC
H h
ave
requ
este
d an
am
endm
ent t
o th
e A
ppro
ved
Term
s of
Ref
eren
ce (A
TOR
) an
d S
ectio
n 11
Ord
er to
rem
ove
the
rem
ove
the
switc
hgea
r bu
ildin
g ex
tens
ion
wor
k fro
m th
e sc
ope
of th
e B
CE
AA
pr
oces
s. F
irst N
atio
ns a
nd T
ribal
Cou
ncils
wer
e as
ked
to
cont
act t
he B
CE
AO
prio
r to
Apr
il 3,
200
9 w
ith a
ny
com
men
ts o
r spe
cific
con
cern
s.
2009
-Mar
-31
Adam
s La
ke
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Adam
s La
ke
(Chi
ef N
elso
n Le
on)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a m
essa
ge o
n W
hisp
erin
g P
ines
Chi
ef 's
(NL)
voi
cem
ail a
skin
g if
Chi
ef N
L
had
rece
ived
the
Sw
itchg
ear P
acka
ge, c
ompr
ised
of
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pr
esen
tatio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 20
09. J
anic
e as
ked
Chi
ef N
L to
con
firm
that
it w
as re
ceiv
ed
and
let h
er k
now
if h
e ha
d an
y qu
estio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear R
epla
cem
ent.
2009
-Mar
-31
Bona
parte
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) B
onap
arte
(Chi
ef
Terr
y P
orte
r)
N/A
BC
H (J
F) s
poke
with
Bon
apar
te R
ecep
tioni
st a
nd a
sked
if
Bon
apar
te C
hief
(TP
) had
rece
ived
Sw
itchg
ear P
acka
ge,
com
pris
ed o
f Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
P
ower
Poi
nt p
rese
ntat
ion
date
d an
d se
nt o
ut F
ebru
ary
23,
2009
. Rec
eptio
nist
con
firm
ed S
witc
hgea
r pac
kage
had
be
en re
ceiv
ed. J
F le
ft a
voic
emai
l for
Chi
ef T
P a
skin
g if
Chi
ef T
P h
ad a
ny q
uest
ions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r Rep
lace
men
t pro
ject
.
2009
-Mar
-31
Bona
parte
Te
leph
one
Cal
l B
onap
arte
(Chi
ef
Terr
y P
orte
r)
BCH
(Jan
ice
Fost
er)
N/A
Te
leph
one
call
from
Bon
apar
te C
hief
(TP
) to
BC
H (J
F) le
ft JF
a m
essa
ge a
skin
g th
at S
witc
hgea
r pac
kage
be
re-s
ent t
o hi
s at
tent
ion.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 19 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 20
of 2
7
2009
-Mar
-31
Col
umbi
a La
ke
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Col
umbi
a La
ke
(Chi
ef W
ilfre
d Te
nese
e)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a m
essa
ge fo
r Col
umbi
a La
ke's
Chi
ef (W
T) w
ith C
olum
bia
Lake
(Rec
eptio
nist
) ask
ing
if C
hief
WT
had
rece
ived
the
Sw
itchg
ear P
acka
ge,
com
pris
ed o
f Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
P
ower
Poi
nt p
rese
ntat
ion
that
was
dat
ed a
nd s
ent o
ut
Febr
uary
23,
200
9. J
anic
e as
ked
Chi
ef W
T to
con
firm
that
it
was
rece
ived
and
let h
er k
now
if h
e ha
d an
y qu
estio
ns o
r co
ncer
ns re
gard
ing
the
Sw
itchg
ear R
epla
cem
ent.
2009
-Mar
-31
Kam
loop
s Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Kam
loop
s (C
hief
Sh
ane
Got
tfrie
dson
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a vo
icem
ail a
nd in
quire
d if
Kam
loop
s C
hief
(SG
) had
rece
ived
the
Sw
itchg
ear
Pac
kage
whi
ch w
as c
ompr
ised
of t
he S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt p
rese
ntat
ion
that
as
date
d an
d se
nt o
ut F
ebru
ary
23, 2
009.
Kam
loop
s (R
ecep
tioni
st) c
onfir
med
the
Sw
itchg
ear p
acka
ge h
ad b
een
rece
ived
. JF
requ
este
d C
hief
(SG
) to
cont
act h
er w
ith a
ny
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r R
epla
cem
ent p
roje
ct.
2009
-Mar
-31
KNC
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
KN
C (F
inan
cial
A
dmin
istra
tor
Jaim
e C
hris
tale
s)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith K
NC
(JC
) and
in
quire
d if
KN
C (B
ill G
reen
) had
rece
ived
the
Sw
itchg
ear
Pac
kage
whi
ch w
as c
ompr
ised
of t
he S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt p
rese
ntat
ion
that
as
date
d an
d se
nt o
ut F
ebru
ary
23, 2
009.
JC
sta
ted
she
wou
ld
chec
k w
ith B
G a
nd le
t JF
know
. JF
also
ask
ed J
C to
che
ck
with
BG
if h
e ha
d an
y qu
estio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear p
roje
ct.
2009
-Mar
-31
Lhei
dli T
’enn
eh
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Lhei
dli T
’enn
eh
(Chi
ef D
omin
ic
Fred
eric
k)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a m
essa
ge w
ith L
heid
li T'
enne
h's
Chi
ef (D
F) R
ecep
tioni
st a
skin
g if
Chi
ef D
F ha
d re
ceiv
ed th
e S
witc
hgea
r Pac
kage
, com
pris
ed o
f Sw
itchg
ear
lette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pre
sent
atio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 200
9. J
F as
ked
Chi
ef D
F to
con
firm
that
it w
as re
ceiv
ed a
nd le
t her
kno
w if
he
had
any
que
stio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear
Rep
lace
men
t.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 20 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 21
of 2
7
2009
-Mar
-31
Littl
e Sh
usw
ap
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Littl
e Sh
usw
ap
(Lan
d an
d R
esou
rces
M
anag
er S
tew
art
Ada
mso
n)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a vo
icem
ail a
nd in
quire
d if
Littl
e S
husw
ap (S
A) h
ad re
ceiv
ed th
e S
witc
hgea
r Pac
kage
w
hich
was
com
pris
ed o
f the
Sw
itchg
ear l
ette
r, at
tach
men
ts
(7 p
hoto
s) a
nd P
ower
Poi
nt p
rese
ntat
ion
that
as
date
d an
d se
nt o
ut F
ebru
ary
23, 2
009.
JF
requ
este
d (S
A) c
onta
ct h
er
with
any
que
stio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear
Rep
lace
men
t pro
ject
.
2009
-Mar
-31
Low
er K
oote
nay
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Low
er K
oote
nay
(Chi
ef C
hris
toph
er
Luke
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r Lo
wer
Koo
tena
y C
hief
(CL)
and
ask
ed if
Chi
ef C
L ha
d re
ceiv
ed th
e S
witc
hgea
r Pac
kage
, com
pris
ed o
f Sw
itchg
ear
lette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pre
sent
atio
n da
ted
and
sent
out
Feb
ruar
y 23
, 200
9. T
he R
ecep
tioni
st
conf
irmed
the
Sw
itchg
ear p
acka
ge h
ad b
een
rece
ived
. JF
left
a vo
icem
ail f
or C
hief
CL
requ
estin
g he
con
tact
her
with
an
y qu
estio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear
Rep
lace
men
t pro
ject
.
2009
-Mar
-31
Low
er
Sim
ilkam
een
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Low
er
Sim
ilkam
een
(Chi
ef J
osep
h D
enni
s)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r Lo
wer
Sim
ilkam
een
Chi
ef (J
D) a
nd a
sked
if C
hief
JD
had
re
ceiv
ed S
witc
hgea
r Pac
kage
, com
pris
ed o
f Sw
itchg
ear
lette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pre
sent
atio
n da
ted
and
sent
out
Feb
ruar
y 23
, 200
9. R
ecep
tioni
st
conf
irmed
Sw
itchg
ear p
acka
ge h
ad b
een
rece
ived
. JF
left
a m
essa
ge re
ques
ting
that
Chi
ef J
D c
onta
ct h
er w
ith a
ny
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r R
epla
cem
ent p
roje
ct.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 21 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 22
of 2
7
2009
-Mar
-31
Nes
konl
ith
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Nes
konl
ith (C
hief
Ju
dy W
ilson
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
a vo
icem
ail a
nd in
quire
d if
Nes
konl
ith C
hief
(JW
) had
rece
ived
the
Sw
itchg
ear
Pac
kage
whi
ch w
as c
ompr
ised
of t
he S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt p
rese
ntat
ion
that
as
date
d an
d se
nt o
ut F
ebru
ary
23, 2
009.
JF
requ
este
d C
hief
JW
con
tact
her
with
any
que
stio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear R
epla
cem
ent p
roje
ct.
2009
-Mar
-31
Oka
naga
n Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Oka
naga
n (T
errit
oria
l St
ewar
dshi
p D
ivis
ion
Man
ager
C
olle
en
Mar
chan
d)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith O
kana
gan
(CM
) an
d as
ked
if O
kana
gan
had
rece
ived
the
Sw
itchg
ear
Pac
kage
whi
ch w
as c
ompr
ised
of t
he S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt p
rese
ntat
ion
that
w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 200
9. C
M c
onfir
med
th
e pa
ckag
e w
as re
ceiv
ed a
nd th
at O
kana
gan
did
not h
ave
any
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
2009
-Mar
-31
ON
A
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Oka
naga
n N
atio
n Al
lianc
e (E
xecu
tive
Dire
ctor
Pau
line
Terb
aske
t)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r O
NA
(PT)
and
ask
ed if
PT
had
rece
ived
Sw
itchg
ear
Pac
kage
, com
pris
ed o
f Sw
itchg
ear l
ette
r, at
tach
men
ts (7
ph
otos
) and
Pow
erP
oint
pre
sent
atio
n da
ted
and
sent
out
Fe
brua
ry 2
3, 2
009.
Rec
eptio
nist
con
firm
ed th
e S
witc
hgea
r pa
ckag
e ha
d be
en re
ceiv
ed. J
F le
ft a
mes
sage
requ
estin
g th
at P
T co
ntac
t her
with
any
que
stio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear R
epla
cem
ent p
roje
ct.
2009
-Mar
-31
Oso
yoos
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) O
soyo
os (C
hief
C
lare
nce
Loui
e)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
mes
sage
with
R
ecep
tioni
st fo
r Oso
yoos
Chi
ef (C
L), a
skin
g hi
m to
con
firm
th
at h
e ha
d re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as
com
pris
ed o
f the
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
an
d P
ower
Poi
nt p
rese
ntat
ion
that
was
dat
ed a
nd s
ent o
ut
Febr
uary
23,
200
9. J
F al
so re
ques
ted
Chi
ef C
L co
ntac
t her
if
he h
ad a
ny q
uest
ions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 22 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 23
of 2
7
2009
-Mar
-31
Pen
ticto
n Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) P
entic
ton
(Rec
eptio
nist
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st, w
ho
coul
d no
t con
firm
Pen
ticto
n re
ceiv
ed th
e S
witc
hgea
r pa
ckag
e an
d as
ked
that
the
pack
age
be re
-sen
t. JF
sai
d th
at s
he w
ould
re-s
end
the
pack
age.
2009
-Mar
-31
Shus
wap
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) Sh
usw
ap (C
hief
P
aul S
am)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
mes
sage
for S
husw
ap
Chi
ef (P
S),
aski
ng h
im to
con
firm
that
he
had
rece
ived
the
Sw
itchg
ear P
acka
ge w
hich
was
com
pris
ed o
f the
S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt
pres
enta
tion
that
was
dat
ed a
nd s
ent o
ut F
ebru
ary
23,
2009
. JF
als
o re
ques
ted
Chi
ef P
S c
onta
ct h
er if
he
had
any
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
2009
-Mar
-31
Sim
pcw
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) S
impc
w (R
efer
rals
D
epar
tmen
t) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith S
impc
w
(Ref
erra
ls D
epar
tmen
t) w
ho re
mem
bere
d se
eing
the
Sw
itchg
ear p
acka
ge, b
ut c
ould
not
loca
te it
. RD
ask
ed th
at
JF re
-sen
d th
e le
tter,
atta
chm
ents
and
Pow
erP
oint
el
ectro
nica
lly, w
hich
JF
did
and
copi
ed S
impc
w C
hief
(Kei
th
Mat
thew
). R
D s
tate
d he
wou
ld fo
llow
up
with
Chi
ef K
M a
nd
cont
act J
F if
ther
e w
ere
any
ques
tions
or c
once
rns.
2009
-Mar
-31
Sim
pcw
Em
ail
BCH
(Jan
ice
Fost
er)
Sim
pcw
(Chi
ef
Kei
th M
atth
ew);
cc: S
impc
w
(Ref
erra
ls
Dep
artm
ent)
N/A
Em
ail f
rom
BC
H (J
F) to
Sim
pcw
Chi
ef (K
M) r
espo
nded
to
requ
est f
rom
Sim
pcw
(Ref
erra
ls D
epar
tmen
t) th
at B
CH
re
send
info
rmat
ion
rega
rdin
g S
witc
hgea
r Rep
lace
men
t pr
ojec
t ele
ctro
nica
lly; B
CH
(JF)
atta
ched
the
Sw
itchg
ear
Pro
ject
Not
ifica
tion
Lette
r, ph
oto
atta
chm
ents
and
the
Pow
erP
oint
pre
sent
atio
n se
nt to
Sim
pcw
on
Febr
uary
23,
20
09.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 23 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 24
of 2
7
2009
-Mar
-31
Sim
pcw
Em
ail
BCH
(Jan
ice
Fost
er)
Sim
pcw
(Chi
ef
Kei
th M
atth
ew);
cc: S
impc
w
(Ref
erra
ls
Dep
artm
ent)
N/A
Em
ail s
ent f
rom
BC
H (J
F) to
Sim
pcw
Chi
ef (K
M) s
tate
d th
at
prev
ious
atte
mpt
by
JF to
sen
d th
ree
atta
chm
ents
my
emai
l w
as u
nsuc
cess
ful,
and
that
she
wou
ld re
-sen
d th
em o
ne
emai
l at a
tim
e. S
witc
hgea
r Pro
ject
Not
ifica
tion
Lette
r was
at
tach
ed.
2009
-Mar
-31
Sim
pcw
Em
ail
BCH
(Jan
ice
Fost
er)
Sim
pcw
(Chi
ef
Kei
th M
atth
ew);
cc: S
impc
w
(Ref
erra
ls
Dep
artm
ent)
N/A
E
mai
l sen
t fro
m B
CH
(JF)
to S
impc
w C
hief
(KM
) atta
ched
S
witc
hgea
r Rep
lace
men
t Pow
erP
oint
pre
sent
atio
n.
2009
-Mar
-31
Ske
etch
estn
Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Ske
etch
estn
(C
hief
Ric
k D
enea
ult)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
mes
sage
for S
keet
ches
tn
Chi
ef (R
D),
aski
ng h
im to
con
firm
that
he
had
rece
ived
the
Sw
itchg
ear P
acka
ge w
hich
was
com
pris
ed o
f the
S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s) a
nd P
ower
Poi
nt
pres
enta
tion
that
was
dat
ed a
nd s
ent o
ut F
ebru
ary
23,
2009
. JF
als
o re
ques
ted
Chi
ef R
D c
onta
ct h
er if
he
had
any
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
2009
-Mar
-31
SN
TC
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
SN
TC (D
irect
or
Bob
Moo
dy)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r S
NTC
(BM
); R
ecep
tioni
st c
onfir
med
that
BM
had
rece
ived
th
e S
witc
hgea
r Pac
kage
whi
ch w
as c
ompr
ised
of t
he
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pr
esen
tatio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 20
09.
JF re
ques
ted
BM
con
tact
her
if h
e ha
d an
y qu
estio
ns
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 24 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 25
of 2
7
2009
-Mar
-31
Spl
atsi
n Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Spl
atsi
n (E
xecu
tive
Secr
etar
y Th
eres
a W
illiam
)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
mes
sage
for S
plat
sin
(TW
), as
king
her
to c
onfir
m th
at s
he h
ad re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as c
ompr
ised
of t
he
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pr
esen
tatio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 20
09.
JF a
lso
requ
este
d TW
con
tact
her
if s
he h
ad a
ny
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
2009
-Mar
-31
St.
Mar
y's
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
St.
Mar
y's
(Chi
ef
Sop
hie
Pie
rre)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
left
mes
sage
for S
t. M
ary'
s C
hief
(SP
), as
king
her
to c
onfir
m th
at s
he h
ad re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as c
ompr
ised
of t
he
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pr
esen
tatio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 20
09.
JF a
lso
requ
este
d C
hief
MM
con
tact
her
if s
he h
ad
any
ques
tions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r pro
ject
.
2009
-Mar
-31
Toba
cco
Plai
ns
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Toba
cco
Plai
ns
(Rec
eptio
nist
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r To
bacc
o P
lain
s C
hief
(Mar
y M
ahse
elah
) and
ask
ed if
the
Chi
ef h
ad re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as
com
pris
ed o
f the
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
an
d P
ower
Poi
nt p
rese
ntat
ion
that
was
dat
ed a
nd s
ent o
ut
Febr
uary
23,
200
9. J
F w
as a
sked
to c
all b
ack
as th
e pe
rson
man
agin
g th
e in
com
ing
mai
l was
off
sick
.
2009
-Mar
-31
Upp
er N
icol
a Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Upp
er N
icol
a (C
hief
Tim
M
anue
l) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r U
pper
Nic
ola
Chi
ef (T
M);
Rec
eptio
nist
con
firm
ed th
at C
hief
TM
had
rece
ived
the
Sw
itchg
ear P
acka
ge w
hich
was
co
mpr
ised
of t
he S
witc
hgea
r let
ter,
atta
chm
ents
(7 p
hoto
s)
and
Pow
erP
oint
pre
sent
atio
n th
at w
as d
ated
and
sen
t out
Fe
brua
ry 2
3, 2
009.
JF
requ
este
d C
hief
TM
con
tact
her
if h
e ha
d an
y qu
estio
ns o
r con
cern
s re
gard
ing
the
Sw
itchg
ear
proj
ect.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 25 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 26
of 2
7
2009
-Mar
-31
Upp
er
Sim
ilkam
een
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Upp
er
Sim
ilkam
een
(Rec
eptio
nist
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith R
ecep
tioni
st fo
r To
bacc
o P
lain
s an
d as
ked
if th
ey h
ad re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as c
ompr
ised
of t
he
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pr
esen
tatio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 20
09.
JF w
as a
sked
to c
all b
ack
as th
e pe
rson
man
agin
g th
e in
com
ing
mai
l was
not
in th
e of
fice
that
day
.
2009
-Mar
-31
Wes
tban
k Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
)
Wes
tban
k (In
terg
over
nmen
tal
Affa
irs M
anag
er
Rap
hael
D
eGue
vara
)
N/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
that
left
a m
essa
ge fo
r W
estb
ank
Chi
ef (R
D) a
skin
g if
Chi
ef R
D h
ad a
ny q
uest
ions
or
con
cern
s re
gard
ing
the
Sw
itchg
ear p
acka
ge s
ent o
n Fe
brua
ry 2
3, 2
009.
2009
-Mar
-31
Wes
tban
k Te
leph
one
Cal
l BC
H (J
anic
e Fo
ster
) W
estb
ank
(Chi
ef
Rob
ert L
ouie
) N
/A
Tele
phon
e ca
ll fro
m B
CH
(JF)
spo
ke w
ith E
xecu
tive
Ass
ista
nt to
Wes
tban
k C
hief
(RL)
and
ask
ed if
Chi
ef R
L ha
d re
ceiv
ed th
e S
witc
hgea
r Pac
kage
whi
ch w
as c
ompr
ised
of
the
Sw
itchg
ear l
ette
r, at
tach
men
ts (7
pho
tos)
and
P
ower
Poi
nt p
rese
ntat
ion
that
as
date
d an
d se
nt o
ut
Febr
uary
23,
200
9. A
ssis
tant
sta
ted
the
Sw
itchg
ear
pack
age
had
been
rece
ived
and
pas
sed
JF o
ver t
o W
estb
ank
(Rap
hael
DeG
ueva
ra).
2009
-Mar
-31
Whi
sper
ing
Pin
es
Tele
phon
e C
all
BCH
(Jan
ice
Fost
er)
Whi
sper
ing
Pin
es
(Chi
ef M
icha
el
LeB
ourd
ais)
N
/A
Tele
phon
e C
all f
rom
BC
H (J
F) w
ith W
hisp
erin
g Pi
nes
(Rec
eptio
nist
) for
and
ask
ed if
Whi
sper
ing
Pin
es C
hief
(ML)
ha
d re
ceiv
ed S
witc
hgea
r Pac
kage
, com
pris
ed o
f Sw
itchg
ear
lette
r, at
tach
men
ts (7
pho
tos)
and
Pow
erP
oint
pre
sent
atio
n th
at w
as d
ated
and
sen
t out
Feb
ruar
y 23
, 200
9.
Rec
eptio
nist
con
firm
ed th
e Sw
itchg
ear p
acka
ge h
ad b
een
rece
ived
. JF
left
a m
essa
ge w
ith th
e R
ecep
tioni
st fo
r Chi
ef
ML
to c
onta
ct h
er w
ith a
ny q
uest
ions
or c
once
rns
rega
rdin
g th
e S
witc
hgea
r Rep
lace
men
t pro
ject
.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 26 of 27
Switc
hgea
r Fi
rst N
atio
n Lo
g –
Mar
ch 3
1, 2
009
Dat
e (y
yyy,
mm
,dd)
Fi
rst N
atio
n M
etho
d of
C
omm
unic
atio
n In
itiat
ed b
y R
ecip
ient
Pa
rtic
ipan
ts
Key
Dis
cuss
ion
Pag
e 27
of 2
7
2009
-May
-26
Ktu
naxa
Nat
ion
Cou
ncil
Site
Vis
it BC
H (R
yan
McF
adde
n)
N/A
7 m
embe
rs o
f th
e K
tuna
xa
Land
s an
d R
esou
rces
C
omm
ittee
(K
LRC
) M
CA
GS
P
lant
Sta
ff B
C H
ydro
A
R&
N
Vie
wed
the
maj
or c
ompo
nent
s of
the
Mic
a G
S, l
ead
shaf
ts
1-3
and
flang
e se
ctio
ns, p
ower
hous
e, e
xist
ing
switc
hgea
r bu
ildin
g, a
nd th
e si
te o
f the
pro
pose
d sw
itchg
ear b
uild
ing
exte
nsio
n to
asc
erta
in if
ther
e w
ere
any
appa
rent
en
viro
nmen
tal c
once
rns.
Mica Gas Insulated Switchgear Project Appendix J-1
Page 27 of 27
The attached letter was sent to the First Nations and Tribal Councils
indentified in Table 5-1 of the Application.
The contact information has been
redacted for privacy.
Mica Gas Insulated Switchgear Project Appendix J-2
Page 1 of 17
hydro WI ·
FOR GENERATIONS
Ryan McFadden Sr. Aboriginal Relations Coordinator BC Hydro Aboriginal Relations & Negotiations 6911 Southpoint Drive - 16th Floor, Burnaby, BC, V3N 4X8
February 23, 2009
Dear :
Re: Switchgear Replacement Project
This is to advise you that in 2009-2010 BC Hydro will be extending the Switchgear Building located at Mica Dam as part of a project to replace aging switchgear1 that has reached end-of-life and is affecting generation and transmission system reliability.
The following Attachments are provided to assist your understanding of the work:
Attachment A: Attachment B: Attachment C: Attachment D:
Attachment E:
Google Earth Photo of Mica Dam Showing Switchgear Building Photo of the existing Switchgear Building Photo showing what the building will look like with the extension Architectural view of how the lead shafts connect the switchgear building to the underground powerhouse Photos (3) of Mica Switchgear Building Extension Site
The Switchgear Building is attached to the office tourist centre structure at located on the west side of the Mica. The structure will be extended by 124 feet or roughly 1/3 of its current length to accommodate the commissioning of a third lead shaft needed to conduct replacement work on the conductors in the two lead shafts lead shafts currently in use. The excavation for the third lead shaft has been in place since the original construction of the dam. Commissioning involves the installation of the gas insulated
1 Switchgear refers to the combination of electrical disconnects, fuses and/or circuit breakers used to isolate electrical equipment. Switchgear is used both to de-energize equipment to allow work to be done safely, and to clear faults downstream.
II!
~ - BC hydro m • FOR GENERATIONS
,. ~ vancouver 2010 vancouver 2010 OFFICIAL ,..uu.lYMtlCGAMES
QSe9 '[\IX rAMLYMnQVES SUPPORTER
ltv
REDACTED
REDACTED
Mica Gas Insulated Switchgear Project Appendix J-2
Page 2 of 17
Chgd .. o WI
FOR GENERATIONS
conductors used to bring power from the underground generators to the above-ground transmission system.
The third conductor will serve two purposes. Because two conductors are required to reliably operate the four existing generating units, the third conductor will be used while each of the existing two conductors is being replaced. The third conductor is also needed for the operation of all six generating units once units 5 and 6 are added.
The extension of the Switchgear Building will occur on a previously disturbed site within the BC Hydro generating station yard. See Attachment E for photos of the site. BC Hydro assessed the site and no potential wildlife, vegetation, or heritage impacts were identified. The site was pointed out during a site visit attended by regulatory agencies, stakeholders, and some First Nations on September 17, 2008.
It is anticipated that an Application will be submitted to the BCUC in June/July 2009, with a decision expected before 2010. For more information about the BCUC process, please visit their website at www.bcuc.com.
For additional information on the Mica Switchgear Building Project, please find enclosed a presentation that was shared at the most recent Core Committee meeting in Revelstoke held on January 29th, 2009. So far no concerns have been raised.
Should you require further information, capacity funding, or should you have any concerns that the proposed Project may affect the rights or interests of
please do not hesitate to contact me at 604-528-2833 or [email protected], and/or
Deb Bisson, Regulatory, Environmental, and Stakeholder Manager, BC Hydro Project Delivery, Upper Columbia, [email protected], 604-528-1913
Respectfully,
Ryan McFadden Sr. Aboriginal Relations Coordinator Aboriginal Relations and Negotiations
Enclosures (1)
Ii! -,. vancouver 2010
Q5e9
~ BChydro m FOR GENERATIONS
~ vancouver 2010 OFFICIAL 'AAAlYWICGA.LllS
IEUX PAMl.YM"QUES SUPPORTER il-...;
Mica Gas Insulated Switchgear Project Appendix J-2
Page 3 of 17
B hydro au
FOR GENERATIONS
Attachment A: Google Earth Photo of Mica Dam Showing Planned Switchgear . Building Extension
Dam face
.i
3 I! t= - BC hydro m • FOR GENERATIONS
.. ~ vancouver 2010 vancouver 2010 OFFICIAL 'AMlntPICGAMU
Q%) 'WX 'AMLYMI'IQVES SUPPORTER ((---.I
Mica Gas Insulated Switchgear Project Appendix J-2
Page 4 of 17
BC hydro FOR GENERATIONS
Attachment B Photo of Switchgear Building
4 I!
~ .. BC hydro m • FOR GENERATIONS
-" ~ vancouver 2010 vancouver 2010 OFFICIAL PAkAlYWIC GAMlS
QSe9 IEUX rMAlYMr1Qun SUPPORTER ((....;
Mica Gas Insulated Switchgear Project Appendix J-2
Page 5 of 17
BC hydro m FOR GENERATIONS
Attachment C - Rendering of Switchgear Building Extension
Mica GIS Switchgear Building Addition
5
Building extension on right side of yellow line
• -• ,. ~ ~ vancouver 2010 vancouver 2010 I'AMlVUPIC GAMES
QSe9 IEUX I'AMlYMPIQUU
ll,-,
BC hydro m FOR GENERATIONS
OFFICIAL SUPPORTER
Mica Gas Insulated Switchgear Project Appendix J-2
Page 6 of 17
BC hudro m FOR GENERATIONS
Attachment D Architectural View of Lead Shafts
I, <>-\ife. f'"r.5 ' OQ~ \ r,'O,.,s h UI::HO/l 'I\ ~cei $
T~"n~1 .~;
!.lron l u l1~ (; O I~' Chomhc r
G f,I'!f:M~ l~~I()!3 _t.1·\T IO!'l
l,Y.~;<> Jjf~() Eill.Q.,I!,t,fI/6.1J911 .? ; l!.~ 'Os\' 18;~ 1A.~: -\~Z[t~,~.LE.YAII~!I, 1~<:tO ~o IILl lif.AP 'IlOO',O' po",! ii;;[)I,lSC-t~~911 ' "f'i~·. o·
Utplh • I ,i~·.() · ' " I,jlll . 8.(1'.0'
vC!l}rOr~Ks <ti,i,'~~~ i"~"!,,, ; Sf.! , '.t'l' TAl1.flM.f;S 1,;1. 1100',1)'
tif?:,. i~O'.t:r
6 I! -vancouver 2010
C&9
P.~ti;' t "C~
~ ~I
MICA PROJ f'Cl lllQMlllllC . .
\JrHI~rHHI UNO flO',lt(l l'LMt' QM -104 '
~ BChydro en FOR GENERATIONS
~ vancouver 2010 OFFICIAL PAltALYMI'IC G.U.lU
JEUX PAMLYM"QVES SUPPORTER
ll-...l
Mica Gas Insulated Switchgear Project Appendix J-2
Page 7 of 17
BChydro FOR GENERATIONS
Attachment E - Photos of Site for Switchgear Building Expansion
7 I!
~ - BC hydro m • FOR GENERATIONS
.. -.; vancouver 2010 vancouver 2010 OFFICIAL PAMlYJ.4PICGA.MES
C&9 ,RlX I'AMl.YM'IQvn SUPPORTER (-...;
Mica Gas Insulated Switchgear Project Appendix J-2
Page 8 of 17
BC hudro m FOR GENERATIONS
8 II!
~ - BChydro m • FOR GENERATIONS
' " ~ vancouver 2010 vancouver 2010 OFFICIAL PAAAlYJ.4!'1C GAMES
QS{9 JEUX rAMLTM"Qun SUPPORTER
1--....1
Mica Gas Insulated Switchgear Project Appendix J-2
Page 9 of 17
hydro m FOR GENERATIONS
9 • ~ - BChydro m • FOR GENERATIONS
~ vancouver 2010 vancouver 2010 OFFICIAL rAMl'f'MMCCAM(S
Q%) InlX rAIW.YMrlQUU SUPPORTER
l(v
Mica Gas Insulated Switchgear Project Appendix J-2
Page 10 of 17
Mica Generating Unit 5 and Unit 6 and
Mica Switchgear Project
Switchgear Building Extension
Switchgear Building For Units 1 to 4
• Existing building located on west side of the dam
• Houses high voltage switchgear at the terminal of the two SF6 conductors .
• SF6 conductors bring power from the . underground powerhouse transforms (twelve
transformers, three per unit) through two shafts to the switchgear building
1
Mica Gas Insulated Switchgear Project Appendix J-2
Page 11 of 17
2
Mica Gas Insulated Switchgear Project Appendix J-2
Page 12 of 17
Reason for Switchgear Building Extension
• Building is being extended to accommodate the switchge"ar that will terminate the conductor to be installed in the third empty shaft
• Switchgear and conductor to be installed in the third shaft so that: a) It can be used while the conductors in the first and second
shafts are being maintained or replaced; and b) To provide the required reliability for six units once Unit 5
" and Unit 6 are operational
'-! IC A PFl!')J I:: Cl ! 1,.\1 ... r.I;> ( i '~:"l!H 1I1.!;to;' r'O '4 r.." 'L,u.: 1: ( II I ~';
3
Mica Gas Insulated Switchgear Project Appendix J-2
Page 13 of 17
. Switchgear Building Extension
• Switchgear building extension is· included in the "Scope" of the Mica 5 Project environmental assessment because part of the reason for the extension relates to the reliable delivery of power from the additional units
• Switchgear building extension is planned to be constructed as part of a separate BCH project - the Mica Switchgear Project
• Switchgear building extension is included in the "Scope" of the Mica 5 Project environmental assessment .
• . The site for the extension is adjacent to the existing building on previously disturbed ground
• Environmental assessment includes; - Wildlife - Vegetation - Archeology
4
Mica Gas Insulated Switchgear Project Appendix J-2
Page 14 of 17
Mica Switchgear Project
• Project replaces aging SF6 equipment units 1 to 4 • Plant requires two conductors in service to ensure reliable
delivery of power to the high voltage grid • Switchgear building expansion included in Mica Switchgear
project so that an existing conductor can be de-energized and replaced while maintaining reliability for existing four units
• In addition to replacing existing SF6 equipment for Units 1 to 4, Mica GIS Project includes installing new conductor in the third lead shaft, termina'l switchgear for the third conductor as well as the construction of the switChgear building extension
Existing Gas Insulated Switchgear
5
Mica Gas Insulated Switchgear Project Appendix J-2
Page 15 of 17
• Starts late 2009 or early 2010 - complete early 2013 • Estimated cost range $90 million to $229 million (June 2008
estimate) • Work at site under CHC Agreement • Work about 85 persons years
- 201029 person years, peal< about 30 - 2011 26 person years, peak about 40 - 2012 25 person years, peak about 40 - 2013 5 person years, peak about 16
• Separate contract for switchgear building extension - Concrete building - 1000 cubic yards of concrete - About 40 feet wide, 130 feet long, 40 feet high - Start late 2009 or early 2010 after receipt of the Mica 5
Environmental Approval Certificate
Mica Switchgear Building - Rendition of Extended Building
Mica GIS Swllc.hgear Building Addition
6
Mica Gas Insulated Switchgear Project Appendix J-2
Page 16 of 17
Mica Switchgear Building Extension
- Questions
7
Mica Gas Insulated Switchgear Project Appendix J-2
Page 17 of 17
Mic
a G
ener
atin
g U
nit 5
and
Uni
t 6
and
Mic
a Sw
itchg
ear P
roje
ct
Sw
itchg
ear B
uild
ing
Ext
ensi
on
Mica Gas Insulated Switchgear Project Appendix J-3
Page 1 of 13
Switc
hgea
r Bui
ldin
g Fo
r Uni
ts 1
to 4
Exi
stin
g bu
ildin
g lo
cate
d on
wes
t sid
e of
the
dam
Hou
ses
high
vol
tage
sw
itchg
ear a
t the
te
rmin
al o
f the
two
SF6
con
duct
ors
SF6
con
duct
ors
brin
g po
wer
from
the
unde
rgro
und
pow
erho
use
trans
form
s (tw
elve
tra
nsfo
rmer
s, th
ree
per u
nit)
thro
ugh
two
shaf
ts to
the
switc
hgea
r bui
ldin
g
Mica Gas Insulated Switchgear Project Appendix J-3
Page 2 of 13
Mic
a Sw
itch
Bui
ldin
g an
d Ex
tens
ion
Mica Gas Insulated Switchgear Project Appendix J-3
Page 3 of 13
Mic
a Sw
itchg
ear B
uild
ing
Mica Gas Insulated Switchgear Project Appendix J-3
Page 4 of 13
Rea
son
for S
witc
hgea
r Bui
ldin
g Ex
tens
ion
Bui
ldin
g is
bei
ng e
xten
ded
to a
ccom
mod
ate
the
switc
hgea
r tha
t will
term
inat
e th
e co
nduc
tor t
o be
in
stal
led
in th
e th
ird e
mpt
y sh
aft
Sw
itchg
ear a
nd c
ondu
ctor
to b
e in
stal
led
in th
e th
ird
shaf
t so
that
:a)
It
can
be u
sed
whi
le th
e co
nduc
tors
in th
e fir
st a
nd s
econ
d sh
afts
are
bei
ng m
aint
aine
d or
repl
aced
; and
b)
To p
rovi
de th
e re
quire
d re
liabi
lity
for s
ix u
nits
onc
e U
nit 5
an
d U
nit 6
are
ope
ratio
nal
Mica Gas Insulated Switchgear Project Appendix J-3
Page 5 of 13
Shaf
ts
Mica Gas Insulated Switchgear Project Appendix J-3
Page 6 of 13
Switc
hgea
r Bui
ldin
g Ex
tens
ion
Sw
itchg
ear b
uild
ing
exte
nsio
n is
incl
uded
in
the
“Sco
pe” o
f the
Mic
a 5
Pro
ject
en
viro
nmen
tal a
sses
smen
t bec
ause
par
t of
the
reas
on fo
r the
ext
ensi
on re
late
s to
the
relia
ble
deliv
ery
of p
ower
from
the
addi
tiona
l un
its
Sw
itchg
ear b
uild
ing
exte
nsio
n is
pla
nned
to
be c
onst
ruct
ed a
s pa
rt of
a s
epar
ate
BC
H
proj
ect –
the
Mic
a S
witc
hgea
r Pro
ject
Mica Gas Insulated Switchgear Project Appendix J-3
Page 7 of 13
Mic
a 5
Proj
ect a
nd th
e Sw
itchg
ear
Bui
ldin
g Ex
tens
ion
Sw
itchg
ear b
uild
ing
exte
nsio
n is
incl
uded
in th
e “S
cope
” of t
he M
ica
5 P
roje
ct e
nviro
nmen
tal
asse
ssm
ent
The
site
for t
he e
xten
sion
is a
djac
ent t
o th
e ex
istin
g bu
ildin
g on
pre
viou
sly
dist
urbe
d gr
ound
Env
ironm
enta
l ass
essm
ent i
nclu
des;
– W
ildlif
e–
Veg
etat
ion
– A
rche
olog
y
Mica Gas Insulated Switchgear Project Appendix J-3
Page 8 of 13
Mic
a Sw
itchg
ear P
roje
ct
Pro
ject
repl
aces
agi
ng S
F6 e
quip
men
t uni
ts 1
to 4
Pla
nt re
quire
s tw
o co
nduc
tors
in s
ervi
ce to
ens
ure
relia
ble
deliv
ery
of p
ower
to th
e hi
gh v
olta
ge g
rid
Sw
itchg
ear b
uild
ing
expa
nsio
n in
clud
ed in
Mic
a S
witc
hgea
r pr
ojec
t so
that
an
exis
ting
cond
ucto
r can
be
de-e
nerg
ized
and
re
plac
ed w
hile
mai
ntai
ning
relia
bilit
y fo
r exi
stin
g fo
ur u
nits
In a
dditi
on to
repl
acin
g ex
istin
g S
F6 e
quip
men
t for
Uni
ts 1
to 4
, M
ica
GIS
Pro
ject
incl
udes
inst
allin
g ne
w c
ondu
ctor
in th
e th
ird
lead
sha
ft, te
rmin
al s
witc
hgea
r for
the
third
con
duct
or a
s w
ell a
s th
e co
nstru
ctio
n of
the
switc
hgea
r bui
ldin
g ex
tens
ion
Mica Gas Insulated Switchgear Project Appendix J-3
Page 9 of 13
Exis
ting
Gas
Insu
late
d Sw
itchg
ear
Mica Gas Insulated Switchgear Project Appendix J-3
Page 10 of 13
Mic
a Sw
itchg
ear P
roje
ct
Sta
rts la
te 2
009
or e
arly
201
0 –
com
plet
e ea
rly 2
013
Est
imat
ed c
ost r
ange
$90
mill
ion
to $
229
mill
ion
(Jun
e 20
08
estim
ate)
Wor
k at
site
und
er C
HC
Agr
eem
ent
Wor
k ab
out 8
5 pe
rson
s ye
ars
– 20
10 2
9 pe
rson
yea
rs, p
eak
abou
t 30
– 20
11 2
6 pe
rson
yea
rs, p
eak
abou
t 40
– 20
12 2
5 pe
rson
yea
rs, p
eak
abou
t 40
– 20
13 5
per
son
year
s, p
eak
abou
t 16
Sep
arat
e co
ntra
ct fo
r sw
itchg
ear b
uild
ing
exte
nsio
n–
Con
cret
e bu
ildin
g –
1000
cub
ic y
ards
of c
oncr
ete
– A
bout
40
feet
wid
e, 1
30 fe
et lo
ng, 4
0 fe
et h
igh
– S
tart
late
200
9 or
ear
ly 2
010
afte
r rec
eipt
of t
he M
ica
5 E
nviro
nmen
tal A
ppro
val C
ertif
icat
e
Mica Gas Insulated Switchgear Project Appendix J-3
Page 11 of 13
Mic
a Sw
itchg
ear B
uild
ing
- Ren
ditio
n of
Ext
ende
d B
uild
ing
Mica Gas Insulated Switchgear Project Appendix J-3
Page 12 of 13
Mic
a Sw
itchg
ear B
uild
ing
Exte
nsio
n
– Q
uest
ions
Mica Gas Insulated Switchgear Project Appendix J-3
Page 13 of 13
Mica Gas Insulated Switchgear Project
Appendix
K
B.C. Environmental Assessment Act Order
Ken R. McKenzie, P.Eng., M.B.A. Project Director Generation Engineering 6911 Southpoint Drive, Floor B02 Burnaby, B.C. V3N 4X8
12 March 2009
Task Number: S600 Mr. Brian Murphy Environmental Assessment Office 1st Floor 836 Yates Street PO Box 9426 Stn Prov Govt Victoria, BC V8W 9V1 Dear Mr. Murphy:
Mica Generating Station Unit 5 Project Requested Amendment Regarding the Switchgear Building
I am writing to request an amendment to the Terms of Reference and Section 11 Order for the Mica Generating Station Unit 5 Project to remove the switchgear building extension work from the scope of the project. Currently the Section 11 Order for Mica Generating Unit 5 “Scope of the Project”, Section 3.1, includes the switchgear building extension because this work is needed to accommodate installation of the 500 kV conductor in shaft #3 and circuit breakers, which will be needed to bring power from Mica Unit 5 to the transmission system. The following (as bolded) is the relevant scope provision in the Terms of Reference, and the Section 11 Order,
• Bank of three single phase 16kV/500kV generator transformers. The switchgear
building will be extended to accommodate the new 500 kV circuit breakers;
At the Mica Generating Station, BC Hydro is scheduled to proceed with the Mica Switchgear Replacement (Mica GIS) project which involves replacement of the original and aging Mica GIS (Gas Insulated Switchgear) equipment for the existing four generating units. This equipment is now in poor condition and poses an unacceptable outage risk at Mica Generating Station. Recent significant outages caused by the failure of this equipment have proved costly because they render Mica generation inaccessible to the grid. BC Hydro needs to prevent the risk and costs of further outages by replacing this equipment as soon as practicable. The replacement of this equipment, including the conductors in shafts #1 and #2, cannot reasonably commence until the conductor in shaft #3 has been commissioned because there must be two conductors in operation at any given time to service four generating units. Therefore, BC Hydro wants to move forward with the site preparation work on the switchgear building extension in the fall of 2009. With the recent BC Hydro extension to the pre-application phase of the Mica Generating Unit 5 project Environmental Assessment process to allow for additional First Nation consultation and stakeholder engagement, the earliest the environmental certificate could be issued is March 2010. For these reasons BC Hydro is requesting that the
British Columbia Hydro & Power Authority, B02, 6911 Southpoint Drive, Burnaby, BC V3N 4X8 www.bchydro.com
Mica Gas Insulated Switchgear Project Appendix K-1
Page 1 of 4
- 2 -
British Columbia Hydro & Power Authority, B02, 6911 Southpoint Drive, Burnaby, BC V3N 4X8 www.bchydro.com
switchgear building extension be removed from the Mica Generating Station Unit 5 Terms of Reference and Section 11 Order.
The size of the switchgear building extension is approximately 40 feet wide, 130 feet long and 40 feet high. It will be a concrete structure with a steel roof. The building is located adjacent to the existing switchgear building (see attached photographs). The area has been previously disturbed and is currently used for parking and equipment storage. As part of the preparation of the Mica Generating Unit 5 EA Application, studies were undertaken on wildlife, vegetation, and archeology at the site. No potential impacts were found. As well, during a site visit this past fall, and a presentation at the last Core Committee meeting, no concerns were raised about the switchgear building extension. Given that,
• the building extension is required in the public interest to reliably operate the existing Mica generation and transmission system, and
• no potential environmental or heritage impacts were found, and • no concerns have been raised through consultation and engagement to date, and • BC Hydro voluntarily opted into the BCEA process with the Mica Generating Station Unit 5
project, we trust that you will be able to grant our request to remove the above noted (bolded) wording from the Mica Generating Station Unit 5 Terms of Reference and Section 11 Order, through a section 13 amendment order, or otherwise. Thank you for your consideration of this matter. Yours sincerely, Ken McKenzie Project Director KRM/kc Attachments c. Peter Northcott – BCH David Wilson – BCH Ryan McFadden - BCH Owen Williams – BCH
Mica Gas Insulated Switchgear Project Appendix K-1
Page 2 of 4
- 3 -
British Columbia Hydro & Power Authority, B02, 6911 Southpoint Drive, Burnaby, BC V3N 4X8 www.bchydro.com
Photo of Current Site and Switchgear Building
Mica Gas Insulated Switchgear Project Appendix K-1
Page 3 of 4
- 4 -
British Columbia Hydro & Power Authority, B02, 6911 Southpoint Drive, Burnaby, BC V3N 4X8 www.bchydro.com
Rendering of Proposed Switchgear Building Extension
Mica Gas Insulated Switchgear Project Appendix K-1
Page 4 of 4
From: Murphy, Brian EAO:EX Sent: Monday, March 23, 2009 8:32 AM To: '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; XT:Johnson, Jay Okanagan Nation Alliance; '[email protected]'; XT:Osoyoos Indian Band EAO:IN; '[email protected]'; XT:Chief, Westbank First Nation EAO:IN; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]'; XT:Terbasket, Pauline Okanagan Nation Alliance EAO:IN; '[email protected]'; '[email protected]'; '[email protected]'; '[email protected]' Cc: Darling, May Y EAO:EX; Murphy, Brian EAO:EX Subject: Mica Generating Station Unit 5 - Section 11 order and Approved Terms of Reference
Mica Generating Station Unit 5 First Nations:
British Columbia Hydro and Power Authority (Proponent) wrote to me requesting (see attached) an amendment to the Approved Terms of Reference (ATOR) (section 4.3.1, page 24) and the section 11 order (section 3.1, bullet 3) to remove the switchgear building extension work. The switchgear building extension is needed to accommodate the installation of the 500 kV conductor in shaft #3 and circuit breakers to bring power from the proposed Mica Generating Station Unit 5 Project to the transmission system. As part of the request letter there is a photo of the current site and switchgear building and a second photo that includes a rendering of the proposed building extension. The size of the switchgear building extension is approximately 40 feet wide, 130 feet long and 40 feet high. It will be a concrete structure with a steel roof. The extension will be located adjacent to the existing building, as shown in the rendering. I have also attached additional photos of the area.
At the Mica Generating Station, the original Mica GIS (Gas Insulated Switchgear) equipment that services the existing four generating units is now in poor condition and poses an unacceptable outage risk. I understand that recent significant outages were caused by the failure of this equipment and resulted in the Mica Generating Station being unable to connect to the grid. In order to prevent further outages, the Proponent is proposing to replace the original and aging Mica GIS equipment. The replacement of the equipment will include the conductors in shafts #1 and #2. However, the replacement cannot begin until the conductor in shaft #3 is commissioned because there must be two conductors in operation at any given time to service four generating units. Shaft #3 is, at this time, excavated but not in use. The Proponent wants to move forward with the site preparation work on the switchgear building extension to the fall of 2009. The area proposed for the extension has been previously disturbed and it is currently used for parking and equipment storage. As part of the review process for the Mica Generating Station Unit 5 Application for an Environmental Assessment certificate, studies were undertaken by the Proponent on wildlife, vegetation and archaeology at the site; no potential impacts were found. Also, during a site visit in the fall of 2008, and
Mica Gas Insulated Switchgear Project Appendix K-2
Page 1 of 2
a presentation at the January, 2009 Core Committee meeting, no concerns were raised about the switchgear building extension.
I have attached the draft section 13 order. If you have any specific concerns about the removal of the switchgear building extension work from the ATOR and the section 11 order, please contact me with your concerns prior to April 3, 2009. Thank you.
Mica Gas Insulated Switchgear Project Appendix K-2
Page 2 of 2
IN THE MATTER OF THE ENVIRONMENTAL ASSESSMENT ACT S.B.C. 2002, c.43 (the Act)
AND
THE ENVIRONMENTAL ASSESSMENT OF THE
MICA GENERATING STATION UNIT 5 PROJECT (the Project)
ORDER UNDER SECTION 13
WHEREAS:
A. On March 4, 2008 British Columbia Hydro and Power Authority (Proponent) applied in writing to the Executive Director of the Environmental Assessment Office (EAO) and requested that the Project be designated a reviewable Project under section 7 of the Act;
B. The Executive Director, EAO, granted this application under section 7(3)(a) by return mail dated March 31, 2008;
C. The Executive Director has delegated to the undersigned powers and functions under the Act, including the power to issue orders under section 10, 11 and 13 of the Act;
D. On April 18, 2008, under section 10(1 )(c) of the Act, the Project Assessment Director issued an order to the Proponent stating that the Project requires an Environmental Assessment Certificate, and that the Proponent may not proceed with the Project without an assessment;
E. On October 28, 2008, the Project Assessment Director issued an order under section 11 of the Act, determining the scope of the required environmental assessment and the procedures and methods for conducting the assessment;
F. On December 19, 2008, Schedule B of the section 11 order was amended to include additional First Nations whose asserted traditional territories the Project lies within; and,
G. On March 12, 2009, the Proponent requested an amendment to the section 11 order to remove the switchgear building extension work. The existing equipment is now in poor condition and poses an unacceptable outage risk at Mica Generating Station. The Proponent is scheduling to replace the existing switchgear equipment, in the fall of 2009, to ensure reliable operation of the existing Mica generation and transmission system.
1
Mica Gas Insulated Switchgear Project Appendix K-3
Page 1 of 2
NOW THEREFORE:
Pursuant to section 13 of the Act, I order that:
Section 3.1, bullet 3, of the section 11 order issued on October 28, 2008 is varied by removing the following sentence:
• The switchgear building will be extended to accommodate the new SOOkV circuit breakers;
irector ion Unit 5 Project
Dated April 17, 2009 at VictOria , British Columbia
2
Mica Gas Insulated Switchgear Project Appendix K-3
Page 2 of 2