2007-047 BWR Vessel & Internals Project (BWRVIP) · 2012. 11. 29. · 2007-047 BWR Vessel &...

103
-. p>~ rfl. 3 11ELECTRIC POWER RESEARCH INSTITUTE 2007-047 BWR Vessel & Internals Project (BWRVIP) February 21, 2007 Document Control Desk U. S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852 Attention: John Honcharik Subject: Project No. 704 - TR-105696-R9 (BWRVIP-03) Revision 9: BWR Vessel and Internals Project, Reactor Pressure Vessel and Internals Examination Guidelines Enclosed are five (5) CD copies of the report "TR-105696-R9 (BWRVIP-03) Revision 9: BWR Vessel and Internals Project, Reactor Pressure Vessel and Internals Examination Guidelines," EPRI Technical Report 1013394, December 2006. In accordance with NRC requirements, one of enclosed CDs is unprotected and is labeled as such. The other four (4) CDs are protected. This report is being transmitted as a means of exchanging information with the NRC for the purpose of supporting generic regulatory improvements related to inspections of BWR internals. BWRVIP-03 is a living document that is updated periodically as inspection technology evolves. The "History of Changes to this Document Revision 9" section identifies the changes that supersede affected portions of the previous Revision 8. The enclosed CDs contain a complete copy of Revision 9 that is being published on CD only. Please note that the enclosed report contains proprietary information. A letter requesting that the report be withheld from public disclosure and an affidavit describing the basis for withholding this information are provided as Attachment 1. Two paper copies of the non-proprietary report "TR-105696-R9 (BWRVIP-03NP) Revision 9: BWR Vessel and Internals Project, Reactor Pressure Vessel and Internals Examination Guidelines," EPRI Technical Report 1013394, December 2006, are also enclosed. This non- proprietary report is identical to the enclosed proprietary report except that the proprietary information has been deleted and the letters "NP" appear in the BWRVIP report number. Together ... Shaping the Future of Electricity PALO ALTO OFFICE .,.O5R 3420 Hillview Avenue, Palo Alto, CA 94304-1395 USA * 650.855.2000 * Customer Service 800.313.3774 9 www.epri.com

Transcript of 2007-047 BWR Vessel & Internals Project (BWRVIP) · 2012. 11. 29. · 2007-047 BWR Vessel &...

  • -. p>~

    rfl. 3 11ELECTRIC POWERRESEARCH INSTITUTE

    2007-047 BWR Vessel & Internals Project (BWRVIP)

    February 21, 2007

    Document Control DeskU. S. Nuclear Regulatory Commission11555 Rockville PikeRockville, MD 20852

    Attention: John Honcharik

    Subject: Project No. 704 - TR-105696-R9 (BWRVIP-03) Revision 9: BWR Vessel andInternals Project, Reactor Pressure Vessel and Internals Examination Guidelines

    Enclosed are five (5) CD copies of the report "TR-105696-R9 (BWRVIP-03) Revision 9: BWRVessel and Internals Project, Reactor Pressure Vessel and Internals Examination Guidelines,"EPRI Technical Report 1013394, December 2006. In accordance with NRC requirements, oneof enclosed CDs is unprotected and is labeled as such. The other four (4) CDs are protected.This report is being transmitted as a means of exchanging information with the NRC for thepurpose of supporting generic regulatory improvements related to inspections of BWR internals.

    BWRVIP-03 is a living document that is updated periodically as inspection technology evolves.The "History of Changes to this Document Revision 9" section identifies the changes thatsupersede affected portions of the previous Revision 8. The enclosed CDs contain a completecopy of Revision 9 that is being published on CD only.

    Please note that the enclosed report contains proprietary information. A letter requesting that thereport be withheld from public disclosure and an affidavit describing the basis for withholdingthis information are provided as Attachment 1.

    Two paper copies of the non-proprietary report "TR-105696-R9 (BWRVIP-03NP) Revision 9:BWR Vessel and Internals Project, Reactor Pressure Vessel and Internals ExaminationGuidelines," EPRI Technical Report 1013394, December 2006, are also enclosed. This non-proprietary report is identical to the enclosed proprietary report except that the proprietaryinformation has been deleted and the letters "NP" appear in the BWRVIP report number.

    Together ... Shaping the Future of Electricity

    PALO ALTO OFFICE .,.O5R3420 Hillview Avenue, Palo Alto, CA 94304-1395 USA * 650.855.2000 * Customer Service 800.313.3774 9 www.epri.com

  • If you have any questions on this subject please call Chuck Wirtz (FirstEnergy, BWRVIPInspection Focus Group Chairman) at 440.280.7665.

    Sincerely,

    William A. EatonEntergy Operations, Inc.Chairman, BWR Vessel and Internals Project

  • I ELECTRIC POWERRESEARCH INSTITUTE

    Attachment 1February 20, 2007

    Document Control DeskOffice of Nuclear Reactor RegulationU.S. Nuclear Regulatory CommissionWashington, DC 20555-0001

    Subject: Request for Withholding of the following Proprietary Document:

    rIR-105696-R9 (BWRVIP-03) Revision 9: BWR Vessel and Internals Project,Reactor Pressure Vessel and Internals Examination Guidelines," EPRI TechnicalReport 1013394, December 2006

    To Whom It May Concern:

    This is a request under 10 C.F.R. §2.390(a)(4) that the U.S. Nuclear Regulatory Commission("!NRC') withhold from public disclosure the information identified in the enclosed Affidavitconsisting of the proprietary information owned by Electric Power Research Institute, Inc. ("EPRr)and identified above (the "Reorr). Copies of the Report and the Affidavit in support of thisrequest are enclosed.

    EPRI desires to disclose, in confidence, the Report for informational purposes to assist the NRC.The Report is not to be divulged to anyone outside of the NRC or to any of its contractors, nor shallany copies be made of the Report provided herein. EPRI welcomes any discussions and/orquestions relating to the information enclosed.

    If you have any questions about the legal aspects of this request for withholding, please do nothesitate to contact me at (704) 595-2173. Questions on the content of the Report should bedirected to Randy Stark of EPRI at (650) 855-2122.

    Sincerely,

    ELECTRIC POWER RESEARCH INSTITUTE, INC.

    ýW"' - -,;?,D- 07

    Senior Sector Business Operations Manager

  • .. l ELECTRIC POWERRESEARCH INSTITUTE

    AFFIDAVIT

    RE: Request for Withholding of the Following Proprietary Document:

    -TR-105696-R9 (BWRVIP-03) Revision 9: BWR Vessel and Internals Project, ReactorPressure Vessel and Internals Examination Guidelines," EPRI Technical Report 1013394,December 2006

    I, JOHN P. GAERTNER, being duly sworn, depose and state as follows:

    I am a Senior Sector Business Operations Manager of Electric Power Research Institute,Inc. whose principal office is located at 3420 Hillview Avenue, Palo Alto, California (LEPRI") and Ihave been specifically delegated responsibility for the above-listed Report that is sought under thisAffidavit to be withheld (the "Reffot"). I am authorized to apply to the U.S. Nuclear RegulatoryCommission (QNRC") for the withholding of the Report on behalf of EPRI.

    EPRI requests that the Report be withheld from the public on the following bases:

    Withholding Based Upon Privileged And Confidential Trade Secrets Or Commercial OrFinancial Information:

    a. The Report is owned by EPRI and has been held in confidence by EPRI.All entities accepting copies of the Report do so subject to written agreements imposing anobligation upon the recipient to maintain the confidentiality of the Report. The Report is disclosedonly to parties who agree, in writing, to preserve the confidentiality thereof.

    b. EPRI considers the Report and the proprietary information containedtherein (the "Proprietary Information') to constitute trade secrets of EPRI. As such, EPRI holds theReport in confidence and disclosure thereof is strictly limited to individuals and entities who haveagreed, in writing, to maintain the confidentiality of the Report. EPRI made a substantial economicinvestment to develop the Report, and, by prohibiting public disclosure, EPRI derives an economicbenefit in the form of licensing royalties and other additional fees from the confidential nature of theReport. If the Report and the Proprietary Information were publicly available to consultants and/orother businesses providing services in the electric and/or nuclear power industry, they would beable to use the Report for their own commercial benefit and profit and without expending thesubstantial economic resources required of EPRI to develop the Report.

    c. EPRI's classification of the Report and the Proprietary Information astrade secrets is justified by the Uniform Trade Secrets Act which California adopted in 1984 and aversion of which has been adopted by over forty states. The California Uniform Trade Secrets Act,California Civil Code §§3426 - 3426.11, defines a "trade secret' as follows:

    "'Trade secret' means information, including a formula, pattern,compilation, program device, method, technique, or process, that:

  • _ELECTRIC POWERRESEARCH INSTITUTE

    (1) Derives independent economic value, actual or potential, fromnot being generally known to the public or to other persons whocan obtain economic value from its disclosure or use; and

    (2) Is the subject of efforts that are reasonable under thecircumstances to maintain its secrecy."

    d. The Report and the Proprietary Information contained therein are notgenerally known or available to the public. EPRI developed the Report only after making adetermination that the Proprietary Information was not available from public sources. EPRI made asubstantial investment of both money and employee hours in the development of the Report. EPRIwas required to devote these resources and effort over a period of several years to derive theProprietary Information and the Report. As a result of such effort and cost, both in terms of dollarsspent and dedicated employee time, the Report is highly valuable to EPRI.

    e. A public disclosure of the Proprietary Information would be highly likely tocause substantial harm to EPRI's competitive position and the ability of EPRI to license theProprietary Information both domestically and internationally. The Proprietary Information andReport can only be acquired and/or duplicated by others using an equivalent investment of timeand effort.

    I have read the foregoing and the matters stated herein are true and correct to the best of myknowledge, information and belief. I make this affidavit under penalty of perjury under the laws ofthe United States of America and under the laws of the State of California.

    Executed at 1300 W T Harris Blvd, Charlotte, North Carolina being the premises and place ofbusiness of Electric Power Research Institute, Inc.

    Date ,,,• -9'0

    JohP.Gaertner

    Subscribed and swom before me this Aj-iday ofa 200-"7

    . • Notary Public

    My Commission expires .- .2.oo'

  • RESEARCH INSTITUTE

    TR-105696-R9 (BWRVIP-03NP) Revision 9:BWR Vessel and Internals Project,Reactor Pressure Vessel and InternalsExamination Guidelines

    SE WARNING:Please read the Export Control

    . \ / Agreement on the back cover.ft AlTechnical Report

    NON-PROPRIETARY INFORMATIONNOTICE: This report contains the non-proprietary information that is includedin the proprietary version of this report. The proprietary version of this reportcontains proprietary information that is the intellectual property of BWRVIPutility members and EPRI. Accordingly, the proprietary report is available onlyunder license from EPRI and may not be reproduced or disclosed, wholly orin part, by any Licensee to any other person or organization.I

  • TR-105696-R9 (BWRVIP-03NP) Revision 9:BWR Vessel and Internals ProjectReactor Pressure Vessel and InternalsExamination Guidelines

    1013394NP

    Final Report, December 2006

    EPRI Project ManagerJ. Landrum

    ELECTRIC POWER RESEARCH INSTITUTE3420 Hillview Avenue, Palo Alto, California 94304-1395 * PO Box 10412, Palo Alto, California 94303-0813 * USA

    800.313.3774 * 650.855.2121 * askepri0eprl.com * www.epri.com

  • DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

    THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS ANACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE BWR VESSEL AND INTERNALSPROJECT (BWRVIP) AND ELECTRIC POWER RESEARCH INSTITUTE, INC. (EPRI). NEITHERBWRVIP, EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) BELOW,NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:

    (A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I)WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, ORSIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESSFOR A PARTICULAR PURPOSE, OR (11) THAT SUCH USE DOES NOT INFRINGE ON ORINTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUALPROPERTY, OR (111) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'SCIRCUMSTANCE; OR

    (B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER(INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF BWRVIP, EPRI OR ANY EPRIREPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTINGFROM YOUR SELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS,METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.

    ORGANIZATION(S) THAT PREPARED THIS DOCUMENT

    Electric Power Research Institute (EPRI)

    NON-PROPRIETARY INFORMATIONNOTICE: This report contains the non-propriety information that is included in

    the proprietary version of this report. The proprietary version of thisreport contains proprietary information that is the intellectual propertyof BWRVIP utility members and EPRI. Accordingly, the proprietaryreport is available only under license from EPRI and may not bereproduced or disclosed, wholly or in part, by any Licensee to anyother person or organization.

    NOTE

    For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 ore-mail askepri @epri.com.

    Electric Power Research Institute and EPRI are registered service marks of the Electric PowerResearch Institute, Inc.

    Copyright © 2006 Electric Power Research Institute, Inc. All rights reserved.

  • CITATIONS

    This report was prepared by

    Electric Power Research Institute (EPRI)NDE Center1300 W.T. Harris BoulevardCharlotte, NC 28262

    Principal Investigator

    BWRVIP Inspection Focus Group

    This report describes research sponsored by EPRI and its BWRVIP participating members.

    The report is a corporate document that should be cited in the literature in the following manner:

    TR-105696-R9 (BWRVIP-O3NP) Revision 9: BWR Vessel and Internals Project, ReactorPressure Vessel and Internals Examination Guidelines. EPRI, Palo Alto, CA: 2006. 1013394NP.

    iii

  • PRODUCT DESCRIPTION

    In 1990, a visual examination of the core shroud of a Swiss boiling water reactor (BWR)revealed the presence of intergranular stress corrosion cracking. Since that event, examinationsof other BWR vessel internal components have revealed an industry-wide cracking problem.In 1994, domestic BWR-owning utilities formed the Boiling Water Reactor Vessel & InternalsProject (BWRVIP), which is chartered to support a program addressing the problems of reactorinternals, internal attachments, vessel welds, and vessel nozzles. Most international BWR ownershave become members. This annual report defines inspection standards and documentedinspection techniques for BWR vessel internal components.

    Results and FindingsProcedure standards have been developed for ultrasonic, visual, and eddy current inspection.Many inspection techniques have been demonstrated and documented. In support of thesedemonstrations, realistic mockups of reactor internal components have been manufactured withcontrolled flaws. BWR owners can use these documented techniques to inspect their vesselinternal components in compliance with BWRVIP guidance.

    Challenges and ObjectivesIn-service inspection program managers and BWR vessel internals program managers use thisdocument to ensure that their components are inspected in compliance with BWRVIP guidance.

    Applications, Value, and UseThe information contained in this report is applied by all BWR owners in the preparation for andduring refueling outages. It is updated annually.

    EPRI PerspectiveThis report provides the BWR fleet with inspection options for all of the safety-related vesselinternal components, and provides a stable mechanism for documenting the capability of theevolving inspection technology. It is the sole resource for internals inspection information forBWR owners.

    ApproachThe BWRVIP strives to make effective inspection techniques available by developing inspectionstandards that can ensure the structural integrity of the components and providing demonstrated,documented techniques for effectively examining the susceptible components.

    v

  • KeywordsBWRVIPNDEInternalsInspectionUltrasoundVessel

    vi

  • EXECUTIVE SUMMARY

    This document presents findings and products of the Inspection Focus Group of the BoilingWater Reactor Vessel and Internals Project (BWRVIP). An overview of the structure of theBWRVIP is presented, with an outline of the goals and approach of the Focus Group.

    The Inspection Focus Group has developed guideline documents which establish protocols forutilities and nondestructive evaluation (NDE) vendor companies to follow in order to gain accessto BWRVIP-owned mockups; to perform formal demonstrations of NDE techniques usingBWRVIP mockups; and to perform their own demonstrations of NDE techniques or inspectiontooling in a manner acceptable to the Focus Group. These documents are included in theirentirety.

    The Focus Group has conducted extensive investigations and demonstrations of NDE techniquesappropriate for inspection of BWR internals. These efforts have included the design, fabrication,and inspection of a series of realistic mockups containing realistic simulations of the degradationmechanisms of concern. These investigations result in the development of evaluation factors,which are numerical values, related to the uncertainties inherent in delivering and executing anNDE technique in a BWR. These evaluation factors are combined with the actual results of aninspection to form input into a fracture-mechanics assessment of the component's serviceability.

    The Focus Group's activities are ongoing. The various components of BWR vessels and internalsare being addressed in concert with other technical Committee efforts. For componentsaddressed to date, this report includes data on mockup fabrication, NDE uncertaintymeasurements and evaluation factors, and procedure standards for ultrasonic examination, eddycurrent examination, and visual examination.

    This is a living document. Updates to the included data on components that have already beenaddressed, and new report sections on components that have not yet been addressed, will besupplied as they are developed. A history of changes is included within the document.

    vii

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 9

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994, Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and Boiling Water Reactor Pressure Vesseland Internals Examination Guidelines (BWRVIP-03) (EPRI Report TR-105696, October 1995).The changes listed below supersede the affected paragraphs of TR-105696-R8 (BWRVIP-03)Revision 8. Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines(EPRI Report 1011689, December 2005).

    Affected Section(s) Description of Change

    xxvii Updated the Inspection Focus Group roster.

    Chapter 1

    Table 4.4.2-1

    4.4.42-4.4.46

    5.3.2

    Table 6.4.2-1

    6.4.36-6.4.39

    10.4.14

    10.4.15-10.4.17

    Updated to include NEI 03-08 Implementation Requirements.

    Updated to reflect new NDE technique demonstrations.

    New sections: new NDE technique demonstrations.

    Added two new shroud support mockups.

    Updated to reflect new NDE technique demonstrations.

    New sections: new NDE technique demonstrations.

    Corrected errata.

    New sections: new NDE technique demonstrations.

    ix

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 8

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994, Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and Boiling Water Reactor Pressure Vesseland Internals Examination Guidelines (BWRVIP-03) (EPRI Report TR-105696, October 1995).The changes listed below supersede the affected Paragraphs of TR-105696-R7 (BWRVIP-03)Revision 7: Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines(EPRI Report 1009910, December 2004).

    Affected Section(s) Description of Change

    xxv Updated the Inspection Focus Group roster.

    2.5, Para. 4.3

    2.5, Para. 6.3.2

    2.6, Para. 3.1

    2.6, Para. 3.3

    2.6, Para. 7.3

    2.6, Para. 7.5

    2.6, Para. 11.0

    Added guidance for visual examination training, regardingdetection and reporting of unusual crud deposits on the vesselinterior or internals.

    Clarified EVT-1 guidance to require that the resolution targetsmust be seen as a dark object; detection only of the bright, glintingreflection of the lights is not adequate.

    Clarified UT personnel requirements to include CP- 189 in additionto ASNT-TC- IA.

    Corrected errata.

    Clarified discussion of one-sided UT access. This change was alsomade in many report sections documenting individual techniquedemonstrations.

    Clarified requirement for adequate recording of transducer positiondata in ultrasonic examination.

    New paragraph, providing background information on UT withone-sided access.

    xi

  • 2.7, Para. 3.1

    4.4.36, 5.4.21

    4.4.37-4.4.41

    4.7.6-4.4.7

    5.4.37-5.4.39

    5.6.4

    10.3.5

    10.4.1

    10.4.11-10.4.14, 10.5.2

    10.6.4

    Clarified ET personnel requirements to include CP- 189 in additionto ASNT-TC- IA.

    Corrected errata.

    New sections: New NDE technique demonstrations.

    New sections: New delivery system demonstrations.

    New sections: New NDE technique demonstrations.

    New section: New delivery system demonstration.

    Added documentation of new jet pump beam mockups.

    Modified discussion of single-side access, for consistency withsimilar discussions elsewhere in the document.

    New sections: New NDE technique demonstrations.

    New section: New delivery system demonstration.

    xii

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 7

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and Boiling Water Reactor Pressure Vesseland Internals Examination Guidelines (BWRVIP-03) (EPRI Report TR- 105696, October 1995).The changes listed below supersede the affected Paragraphs of TR-105696-R6 (BWRVIP-03)Revision 6: Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines,(EPRI Report 1008061, December 2003).

    Affected Section(s) Description of Change

    xxxiii Updated the Inspection Focus Group roster.

    Chapter 1

    2.5, Para. 3.5

    2.5, Para. 6.2

    2.5, Para. 6.2.2

    2.6, Para. 3.3, 4.1

    2.6, Para. 5.2

    4.3.1.8, 4.3.1.9

    4.4.2

    Replaced all references to Inspection Committee with FocusGroup.

    Removed recording medium, water clarity, and lighting from listof key elements.

    Changed title from Minimum Water Clarity to EnvironmentalConditions.

    Added lighting conditions as an environmental condition, alongwith water clarity.

    Clarified UT qualifications that are required for standby liquidcontrol welds and recognizes the recent availability of qualifiedmanual examiners.

    Clarified acceptability of normal variation in transducer frequency.

    New sections: Added documentation of new mockups BWRVIP-SSC-1 and BWRVIP-H6OH.

    Added new Demonstration References for UT Demonstrations 33and 34.

    xiii

  • 4.4.35,4.4.36 New sections: New NDE technique demonstrations.

    5.3.2

    5.4.21

    5.4.29-36

    10.2

    11.1

    Changed the word six to seven in the first line of the thirdparagraph.

    Corrected an erratum and clarified the description of a technique'sperformance.

    New sections: New NDE technique demonstrations.

    Added a paragraph providing VT- I guidance for viewing jet pumpwedges.

    Updated BWRVIP-27 to BWRVIP-27A where necessary.

    Updated guidance for SLC examination to include all allowableinspection alternatives: volumetric every ten years, surfaceexamination every other outage, or enhanced leakage inspectionevery outage. Enhanced leakage inspection is to be performed withthe insulation removed.

    11.2.3, 11.2.4

    xiv

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 6

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and the October 1995 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03). The changeslisted below supersede the affected paragraphs of TR-105696R5 (BWRVIP-03) Revision 5:Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines, December 2002.

    Affected Section(s) Description of Change

    xix

    5.4.27 - 5.4.28

    5.6.3

    6.4.32 - 6.4.35

    All NDE techniqueand delivery systemdemonstrations

    Many UT demonstrations

    Updated the Inspection Focus Group roster.

    New sections: New NDE technique demonstrations.

    New section: New NDE delivery system demonstration.

    New sections: New NDE technique demonstrations.

    Added the publication date of each demonstration.

    Where appropriate, added a note stating the need to ultrasonicallyexamine stainless steel and nickel-alloy welds from both directionsif possible. (The same note was already present in generic form inSection 2.6, the UT Standard. This action identifies more clearlywhich UT technique demonstrations it applies to.)

    xv

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 5

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and the October 1995 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03). The changeslisted below supersede the affected paragraphs of TR-105696R4 (BWRVIP-03) Revision 4:Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines.

    Affected Section(s)

    xvii

    2.5, Para. 8.1.2

    2.6 and 2.7, Para. 2.4

    2.6, Para. 3.3

    2.6, Para. 7.3

    4.4.2,6.4.2

    4.4.33-4.4.34

    4.7.5

    6.3.1.4

    6.4.18, 6.4.19 and 6.4.24

    6.4.26-6.4.31

    10.4.10

    Description of Change

    Updated the Inspection Focus Group roster.

    Clarifies documentation of EVT-1 examination coverage torecognize access limitations. Documentation must include anestimate of the percentage of the examination area that wascovered with EVT-1 quality.

    New paragraphs. References ASNT CP-189 in addition to SNT-TC- 1A for qualification and certification of examination personnel.

    Clarifies qualification requirements for personnel performing UT.Provides personnel qualification requirements for examiningstandby liquid control welds, and for determining whether flawshave propagated into the pressure vessel. Deleted Paragraph3.3.3.2, which was made redundant by this change.

    New paragraph. States the need to ultrasonically examine stainlesssteel and nickel-alloy welds from both directions.

    Updated demonstration tables.

    New sections: New NDE technique demonstrations.

    New section: New NDE delivery system demonstration.

    Added documentation of core spray tee box mockup BWRVIP-N.

    Withdrew UT demonstrations for core spray hidden weld P9because of recent findings from a new, more comprehensive set ofmockups.

    New sections: New NDE technique demonstrations.

    New section: New NDE technique demonstration.

    xvii

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 4

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and the October 1995 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03). The changeslisted below supersede the affected paragraphs of TR-105696R3 (BWRVIP-03) Revision 3December 2000: Boiling Water Reactor Pressure Vessel and Internals Examination Guidelines.

    Affected Section(s) Description of Change

    xvii Updated the Committee roster.

    2.6, Para. 3.3

    4.1,5.1, 6.1,7.1, 8.2,9.2, 10.2, 11.2, 12.2, 13.2

    4.4.2,6.4.2

    4.4.29-4.4.32

    5.3.5

    Clarifies prerequisite for UT data analysis personnel: their IGSCCqualification must be on non-overlaid components.

    Clarifies that examination procedures must be appropriate to thespecific configuration of the plant. Previously "utility-specific"procedures were called for. This change of wording is intended toremove any suggestion that the procedures must be tiedadministratively to the specific utility.

    Updated demonstration tables.

    New sections: New NDE technique demonstrations.

    New section: Description of BWR/2 H8/H9 mockups.

    New sections: New NDE technique demonstrations.

    New section: New NDE delivery system demonstration.

    5.4.23-5.4.26

    5.6.2

    6.4.21-6.4.25 New sections: New NDE technique demonstrations.

    New section: New NDE technique demonstration.8.4.4

    TOC, Figure 6.3.1.5-1,11.2.3 Correction of errata.

    xix

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 3

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and the October 1995 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03). The changeslisted below supersede the affected paragraphs of the December 1999 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03) Revision 2.

    Affected Section(s) Description of Change

    Updated the Committee roster.I

    2.5, Para. 8.1.3

    5.3.4

    For EVT-1, recommends that the method of measuring flaw length(estimation or ruler) be recorded.

    Updated the description of shroud support mockups.

    New sections: New NDE technique demonstrations.

    Updates status of hidden welds.

    New section: description of BWR/6 core spray mockup.

    5.4.21, 5.4.22

    6.2.2, 9.2, 10.2

    6.3.1.5

    6.4.20

    10.4.9, 10.5.1

    New section: New NDE technique demonstration.

    New sections: New NDE technique demonstrations.

    Updated the status of control rod guide tube mockup.13.3

    xxi

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 2

    This is a living document. Updates to the included data will be added as they are developed.Minor or editorial changes may not appear in this summary listing of significant changes. Thisdocument supersedes the November 21, 1994 Inspection Committee document BWR-VIP CoreShroud NDE Uncertainty & Procedure Standard and the October 1995 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (B WR VIP-03). The changeslisted below supersede the affected paragraphs of the March 1999 document Boiling WaterReactor Pressure Vessel and Internals Examination Guidelines (BWRVIP-03) Revision 1.

    Affected Section(s) Description of Change

    I Updated the Committee roster.

    2.6, Paragraph 3.3 Modified the personnel qualification requirements for selectedexaminations.

    3.0 Correction: Changed heading numbers to correspond with rest of thedocument.

    4.3.1.7 New section: Description of new mockup BWRVIP-H 1.

    4.4.28 New section: New NDE technique demonstration.

    5.4.20 New section: New NDE technique demonstration.

    6.3.1.2 Correction: Figure 6.3.1.2-4 correct image inserted.

    6.4.18-19 New sections: New NDE technique demonstrations.

    8.4.3 New section: New NDE technique demonstration.

    xxiii

  • HISTORY OF CHANGES TO THIS DOCUMENTREVISION 1

    This is a living document. Updates to the included data on components that had already beenaddressed, and new report sections on components that had not yet been addressed, will be addedas they are developed. Minor or editorial changes may not appear in this listing. This documentsupersedes the November 21, 1994 Inspection Committee document BWR-VIP Core Shroud NDEUncertainty & Procedure Standard and the October 1995 document Boiling Water ReactorPressure Vessel and Internals Examination Guidelines (BWRVIP-03).

    Affected Section(s) Description of Change

    I Updated the Committee roster and Acknowledgments.

    2.1 - 2.4 Changes to administrative procedures, made necessary bydiscontinuation ofreferenced Inspection Committee workinggroups. Revised key elements for visual inspection.

    2.5 New section: "Generic Standards for Visual Examination ofReactor Pressure Vessel Internals, Components, and AssociatedRepairs."

    2.6 New section: "Generic Standards for Ultrasonic Examination ofBWR Vessel Internal Components."

    2.7 New section: "Generic Standards for Eddy Current Examinationof BWR Vessel Internal Components."

    3.0 New section: "Demonstration of Accuracy of Flaw LengthMeasurement by Visual Examination." This section replaces theexisting Section 3.

    3.0 Correction: Changed heading numbers to correspond with rest ofthe document.

    4 Added reference to generic NDE standards, Sections 2.5 - 2.7.

    4.3 Added documentation of new mockups.

    xxv

  • 4.4.19 -4.4.26,4.6.5 - 4.6.6,4.7-3

    4A, 4B, 4C

    5

    5.3

    5.4.10 - 5.4.18

    New sections: Documentation of NDE demonstrationsconducted since issuance of prior documents.

    Deleted. Shroud-specific NDE standards deleted, references togeneric standards in Sections 2.5 - 2.7 added.

    Added reference to generic NDE standards, Sections 2.5 - 2.7.

    Added documentation of new mockups.

    New sections: Documentation of NDE demonstrations conductedsince issuance of prior documents.

    New section: Core Spray Piping and Sparger. These componentshad not been addressed in prior documents, except for Section 6A,"Standards for Visual Inspection of Core Spray Piping, Spargers,and Associated Components."

    Section 6A, "Standards for Visual Inspection of Core SprayPiping, Spargers, and Associated Components," is now deleted andSection 2.5 is referenced instead. New Section 6A: "Investigationof Core Spray Internal Piping Overlay Inspection."

    New section: Top Guide.

    New section: Core Plate.

    6

    6A

    7

    8

    9

    10

    11

    New section: LPCI Coupling.

    New section: Jet Pump Assembly.

    New section: Standby Liquid Control.

    New section: Vessel Attachments.

    New section: Lower Plenum.

    New section: Vessel Penetrations.

    12

    13

    14

    xxvi

  • BWRVIP INSPECTION FOCUS GROUP

    Charles Wirtz, Technical Chairman

    Rich CiemiewiczBunny CrockerPatrick GraedelFred HabibRick HambletonThomas JonesScott LarsonTim McClureTony OliveriGary ParkPorfirio Perez TegedorDouglas RameyRudy SchwammbergerRick SealsTed SieverKevin WhiteNorimichi Yamashita

    Jeff Landrum, EPRI Task Manager

    First Energy Nuclear Operating Company

    Exelon CorporationEntergy Operations, Inc.BKW FMB Energie AG (KKM)PPL Susquehanna, LLCDetroit Edison CompanyNuclear Management CompanyProgress Energy, Inc.Nebraska Public Power DistrictPSEG Nuclear,LLCDuane Arnold Energy CenterIberdrola Generacion, S. A.Energy NorthwestKemkraftwerk Leibstadt AGTennessee Valley AuthorityConstellation Energy GroupSouthern Nuclear Operating CompanyTokyo Electric Power Company

    xxvii

  • ACKNOWLEDGMENTS

    The BWRVIP Inspection Focus Group acknowledges the support of General Electric, VisualInspection Technologies, Imaging and Sensing Technologies, RJ Electronics, and FramatomeTechnologies in providing personnel and equipment for demonstration of visual examinationtechniques.

    The staff of the EPRI NDE Center are acknowledged for their successful completion of thisdocument:

    Mark DennisJeff LandrumGreg SelbyPaul Zayicek

    xxix

  • CONTENTS

    *1 BW RVIP OVERVIEW AND BACKGROUND ........................................................................ 1-1

    1.1 BW RVIP ....................................................................................................................... 1-1

    1.2 BW RVIP Inspection Focus G roup ................................................................................ 1-1

    1.3 G eneral Approach to Inspection Support ..................................................................... 1-2

    1.4 Im plem entation Requirem ent ....................................................................................... 1-3

    2 GENERAL PROCEDURES .................................................................................................... 2-1

    2.1 G uidelines for Use of BW RVIP Mockups ..........................................................................

    1.0 Purpose ........................................................................................................................

    2.0 Reference .....................................................................................................................

    3.0 G uidelines for Usage ....................................................................................................

    4.0 G uidelines for Use Prioritization ...................................................................................

    2.2 Protocol for NDE Technique Demonstrations on BWRVIP Mockups ...............................

    1.0 Purpose ........................................................................................................................

    2.0 Responsibilities ............................................................................................................

    3.0 Prerequisites ................................................................................................................

    4.0 Demonstration Plan ......................................................................................................

    5.0 Dem onstration Process ................................................................................................

    6.0 Results Reporting and Docum entation ........................................................................

    2.3 G uidelines for Determ ining NDE Technique Uncertainty ..................................................

    1.0 Purpose ........................................................................................................................

    2.0 References ...................................................................................................................

    3.0 Responsibilities ............................................................................................................

    4.0 Demonstration Process ................................................................................................

    5.0 Docum entation .............................................................................................................

    2.4 G uidelines for Determ ining Inspection Tool Positioning Uncertainty ................................

    1.0 Purpose ........................................................................................................................

    2.0 References ...................................................................................................................

    xxxi

  • 3.0 Responsibilities ............................................................................................................

    4.0 Guidelines for Uncertainty Measurements ...................................................................

    5.0 Demonstration Plan ......................................................................................................

    6.0 Demonstration Process ................................................................................................

    7.0 Documentation .............................................................................................................

    2.5 Generic Standards for Visual Inspection of Reactor Pressure Vessel Internals,

    Components, and Associated Repairs .......................................................................................

    1.0 Purpose ........................................................................................................................

    2.0 Scope ...........................................................................................................................

    3.0 Definitions ....................................................................................................................

    4.0 Personnel Training/Experience ....................................................................................

    5.0 Equipment Requirements .............................................................................................

    6.0 Inspection Requirements .............................................................................................

    7.0 Evaluation of Indications ..............................................................................................

    8.0 Documentation of Results ............................................................................................

    2.6 Generic Standards for Ultrasonic Examination of BWR Vessel Internal

    Components ...............................................................................................................................

    1.0 Scope ...........................................................................................................................

    2.0 References ...................................................................................................................

    3.0 Personnel .....................................................................................................................

    4.0 Technique Demonstrations ..........................................................................................

    5.0 Equipment ....................................................................................................................

    6.0 Calibration ....................................................................................................................

    7.0 Exam ination .................................................................................................................

    8.0 Recording .....................................................................................................................

    9.0 Evaluation ....................................................................................................................

    10.0 Reporting .....................................................................................................................

    11.0 Examination of Stainless Steel and Nickel-Alloy Welds with Single-Sided Access .........................................................................................................................

    2.7 Generic Standards for Eddy Current Examination of BWR Vessel Internal

    Components ...............................................................................................................................

    1.0 Scope ...........................................................................................................................

    2.0 References ...................................................................................................................

    3.0 Personnel .....................................................................................................................

    4.0 Technique Demonstration ............................................................................................

    5.0 Equipment ....................................................................................................................

    xxxii

  • 6.0 Calibration ....................................................................................................................

    7.0 Exam ination .................................................................................................................

    8.0 Recording .....................................................................................................................

    9.0 Evaluation ....................................................................................................................

    10.0 Reporting .....................................................................................................................

    3 DEMONSTRATION OF ACCURACY OF FLAW LENGTH MEASUREMENT BY

    VISUAL EXAM INATION ............................................................................................................ 3-1

    3.1 Sum mary ..........................................................................................................................

    3.2 Dem onstration ..................................................................................................................

    3.2.1 Vendors ....................................................................................................................

    3.2.2 Mockups ...................................................................................................................

    3.2.3 Flaws ........................................................................................................................

    3.2.4 Cameras ...................................................................................................................

    3.2.5 Measurement Techniques ........................................................................................

    3.3 Sizing Performance ...........................................................................................................

    3.3.1 Estimation ................................................................................................................

    3.3.2 M easurement by Ruler .............................................................................................

    4 SHROUD ................................................................................................................................ 4-1

    4.1 Sum mary ..................................................................................................................... 4-1

    4.2 Inspection Considerations ........................................................................................... 4-1

    *4.3 Applicable Mockups ..................................................................................................... 4-1

    4.3.1 Shroud W eld M ockups ........................................................................................ 4-2

    4.3.1.1 NDE Center's Original H3 Mockup ............................................................... 4-2

    4.3.1.2 Utility H3 and H4 Mockups ............................................................................ 4-2

    4.3.1.3 Shroud Block BW RVIP-A: Ring-to-Cylinder .................................................. 4-2

    4.3.1.4 Shroud Block BW RVIP-B: Ring-to-Cylinder .................................................. 4-4

    4.3.1.5 Shroud Block BW RVIP-C: Cylinder-to-Cylinder ............................................ 4-6

    4.3.1.6 Shroud Mockup BWRVIP-G and H: Ring Segment Welds ........................... 4-8

    4.3.1.7 Shroud Mockup BW RVIP-H1: Shroud W eld H1 ........................................ 4-11

    4.3.1.8 Shroud Mockup BWRVIP-SSC1: Shroud Scallops .................................... 4-11

    4.3.1.9 Shroud Mockup BWRVIP-H6OH: Overhanging Core PlateSupport Ring .............................................................................................................. 4-13

    4.3.2 Special Purpose M ockups ................................................................................. 4-14

    4.3.2.1 Surface Roughness .................................................................................... 4-14

    xxxiii

  • 4.3.2.2 Multiple Parallel Cracks .............................................................................. 4-15

    4.3.2.3 EDM Notches in W eld Toe .......................................................................... 4-16

    4.4 UT Technique Demonstrations for Core Shroud W elds ............................................. 4-17

    *4.4.1 General Findings for UT .................................................................................... 4-17

    *4.4.1.1 Detection of Shallow Reflectors .................................................................. 4-17

    *4.4.1.2 Detection of Skewed Reflectors .................................................................. 4-17

    *4.4.1.3 Effect of M ultiple Parallel Defects ............................................................... 4-18

    *4.4.1.4 Effect of Roughness of Scanning Surface .................................................. 4-18

    4.4.2 UT Demonstration Summary ............................................................................. 4-19

    4.4.3 UT Demonstration 1 .................................................................................................

    4.4.4 UT Demonstration 2 .................................................................................................

    4.4.5 UT Demonstration 3 .................................................................................................

    4.4.6 UT Demonstration 4 .................................................................................................

    4.4.7 UT Demonstration 5 .................................................................................................

    4.4.8 UT Demonstration 6 .................................................................................................

    4.4.9 UT Demonstration 7 .................................................................................................

    4.4.10 UT Demonstration 8 .................................................................................................

    4.4.11 UT Demonstration 9 .................................................................................................

    4.4.12 UT Demonstration 10 ...............................................................................................

    4.4.13 UT Demonstration 11 ...............................................................................................

    4.4.14 UT Demonstration 12 ...............................................................................................

    4.4.15 UT Demonstration 13 ...............................................................................................

    4.4.16 UT Demonstration 14 ...............................................................................................

    4.4.17 UT Demonstration 15 ...............................................................................................

    4.4.18 UT Demonstration 16 ...............................................................................................

    4.4.19 UT Demonstration 17 ...............................................................................................

    4.4.20 UT Demonstration 18 ...............................................................................................

    4.4.21 UT Demonstration 19 ...............................................................................................

    4.4.22 UT Demonstration 20 ...............................................................................................

    4.4.23 UT Demonstration 21 ...............................................................................................

    4.4.24 UT Demonstration 22 ...............................................................................................

    4.4.25 UT Demonstration 23 ...............................................................................................

    4.4.26 UT Demonstration 24 ...............................................................................................

    4.4.27 UT Demonstration 25 ...............................................................................................

    xxxiv

  • 4.4.28 UT Dem onstration 26 ...............................................................................................

    4.4.29 UT Dem onstration 27 ..............................................................................................

    4.4.30 UT Dem onstration 28 ...............................................................................................

    4.4.31 UT Dem onstration 29 ...............................................................................................

    4.4.32 UT Dem onstration 30 ...............................................................................................

    4.4.33 UT Demonstration 31 ...............................................................................................

    4.4.34 UT Dem onstration 32 ...............................................................................................

    4.4.35 UT Dem onstration 33 ...............................................................................................

    4.4.36 UT Dem onstration 34 ...............................................................................................

    4.4.37 UT Dem onstration 35 ...............................................................................................

    4.4.38 UT Dem onstration 36 ...............................................................................................

    4.4.39 UT Dem onstration 37 ...............................................................................................

    4.4.40 UT Dem onstration 38 ...............................................................................................

    4.4.41 UT Dem onstration 39 ...............................................................................................

    4.4.42 UT Dem onstration 40 ...............................................................................................

    4.4.43 UT Dem onstration 41 ...............................................................................................

    4.4.44 UT Dem onstration 42 ...............................................................................................

    4.4.45 UT Dem onstration 43 ...............................................................................................

    4.4.46 UT Dem onstration 44 ...............................................................................................

    4.5 VT Technique Demonstrations for Core Shroud W elds ............................................. 4-20

    *4.5.1 VT General Findings ......................................................................................... 4-20

    4.5.1.1 Training ....................................................................................................... 4-20

    *4.5.2 VT Dem onstration 1 .......................................................................................... 4-20

    4.6 ET Technique Dem onstrations for Core Shroud W elds ............................................. 4-23

    4.6.1 ET General Findings ......................................................................................... 4-23

    4.6.1.1 Detection of Skewed Reflectors .........................................................................

    4.6.1.2 Effect of Scanning on a Rough Surface .............................................................

    4.6.1.3 Scan Pattem ......................................................................................................

    *4.6.2 ET Dem onstration 1 .......................................................................................... 4-26

    4.6.2.1 Crack Length Measurem ent ........................................................................ 4-26

    4.6.2.2 O ptim um Param eters for ET Imaging ......................................................... 4-26

    *4.6.3 ET Demonstration 2 .......................................................................................... 4-29

    4.6.4 ET Demonstration 3 .......................................................................................... 4-30

    xxxv

  • 4.6.4.1 Data Acquisition .................................................................................................

    4.6.4.2 Data Evaluation ..................................................................................................

    4.6.5 ET Demonstration 4 .......................................................................................... 4-31

    4.6.6 ET Demonstration 5 .......................................................................................... 4-32

    4.7 Delivery System Demonstrations for Core Shroud W elds ......................................... 4-36*4.7.1 Delivery System Demonstration 1 ..................................................................... 4-37

    *4.7.2 Delivery System Demonstration 2 ..................................................................... 4-38

    4.7.3 Delivery System Demonstration 3 ..................................................................... 4-39

    4.7.4 Delivery System Demonstration 4 ..................................................................... 4-40

    4.7.5 Delivery System Demonstration 5 ..................................................................... 4-41

    4.7.6 Delivery System Demonstration 6 ..................................................................... 4-42

    4.7.7 Delivery System Demonstration 7 ..................................................................... 4-43

    4.7.7.1 Flaw Length Measurement W ithin a Single Scan .................................................

    4.7.7.2 Flaw Length Measurement Using More Than One Scan ......................................

    *4.8 References ................................................................................................................ 4-44

    5 SHROUD SUPPORT .............................................................................................................. 5-1

    5.1 Summary ..........................................................................................................................

    5.2 Inspection Considerations ................................................................................................

    5.2.1 Chicago Bridge & Iron/CBI Nuclear Shroud Supports ..............................................

    5.2.2 Babcock & W ilcox Shroud Supports ........................................................................

    5.2.3 Combustion Engineering Shroud Supports ..............................................................

    5.2.3.1 Gusset Supports ................................................................................................

    5.2.3.2 Cone Skirt Support .............................................................................................

    5.2.3.3 Heavy Steel Baffle Plate ....................................................................................

    5.2.4 Inspection Access ....................................................................................................

    5.3 Applicable Mockups ..........................................................................................................

    5.3.1 Shroud Support Mockup BW RVIP-D: W eld H7 .......................................................

    5.3.2 Shroud Support Mockups BWRVIP-E, BWRVIP-El, and BWRVIP-E2:W eld H9 .................................................................................................................................

    5.3.3 Shroud Support Mockup BW RVIP-F: W eld H8 ........................................................

    5.3.4 Shroud Support Mockups BWRVIP-P, BWRVIP-Q1, BWRVIP-Q2 .........................

    5.3.5 Shroud Support Mockups BWRVIP-B2SS1 and BWRVIP-B2SS2 ..........................

    5.4 UT Technique Demonstrations for Core Shroud Support W elds ......................................

    5.4.1 General Findings for UT ...........................................................................................

    xxxvi

  • 5.4.1.1 Effect of Alloy 82/182 W eld Material ..................................................................

    5.4.1.2 Effect of Mismatch in the Fit-up of W eld H7 .......................................................

    5.4.2 UT Demonstration 1 .................................................................................................

    5.4.3 UT Demonstration 2 .................................................................................................

    5.4.4 UT Demonstration 3 .................................................................................................

    5.4.5 UT Demonstration 4 .................................................................................................

    5.4.6 UT Demonstration 5 .................................................................................................

    5.4.7 UT Demonstration 6 .................................................................................................

    5.4.8 UT Demonstration 7 .................................................................................................

    5.4.9 UT Demonstration 8 .................................................................................................

    5.4.10 UT Dem onstration 9 .................................................................................................

    5.4.11 UT Demonstration 10 ...............................................................................................

    5.4.12 UT Dem onstration 11 ...............................................................................................

    5.4.13 UT Dem onstration 12 ...............................................................................................

    5.4.14 UT Dem onstration 13 ...............................................................................................

    5.4.15 UT Demonstration 14 ...............................................................................................

    5.4.16 UT Dem onstration 15 ...............................................................................................

    5.4.17 UT Demonstration 16 ...............................................................................................

    5.4.18 UT Dem onstration 17 ...............................................................................................

    5.4.19 UT Dem onstration 18 ...............................................................................................

    5.4.20 UT Dem onstration 19 ...............................................................................................

    5.4.21 UT Demonstration 20 ...............................................................................................

    5.4.22 UT Dem onstration 21 ...............................................................................................

    5.4.23 UT Dem onstration 22 ...............................................................................................

    5.4.24 UT Dem onstration 23 ...............................................................................................

    5.4.25 UT Demonstration 24 ...............................................................................................

    5.4.26 UT Dem onstration 25 ...............................................................................................

    5.4.27 UT Dem onstration 26 ...............................................................................................

    5.4.28 UT Dem onstration 27 ...............................................................................................

    5.4.29 UT Demonstration 28 ...............................................................................................

    5.4.30 UT Dem onstration 29 ...............................................................................................

    5.4.31 UT Dem onstration 30 ...............................................................................................

    5.4.32 UT Dem onstration 31 ..............................................................................................

    5.4.33 UT Dem onstration 32 ...............................................................................................

    xxxvii

  • 5.4.34 UT Demonstration 33 ...............................................................................................

    5.4.35 UT Demonstration 34 ...............................................................................................

    5.4.36 UT Demonstration 35 ...............................................................................................

    5.4.37 UT Demonstration 36 ...............................................................................................

    5.4.38 UT Demonstration 37 ...............................................................................................

    5.4.39 UT Demonstration 38 ...............................................................................................

    5.5 ET Technique Demonstrations for Core Shroud Support W elds ......................................

    5.5.1 General Findings for ET ...........................................................................................

    5.5.2 ET Demonstration 1 .................................................................................................

    5.6 Delivery System Demonstrations for Core Shroud Support W elds ...................................

    5.6.1 Delivery System Dem onstration 1 ............................................................................

    5.6.2 Delivery System Demonstration 2 ............................................................................

    5.6.3 Delivery System Demonstration 3 ............................................................................

    5.6.4 Delivery System Demonstration 4 ............................................................................

    6 CORE SPRAY PIPING AND SPARGER ............................................................................... 6-1

    6.1 Summary ..........................................................................................................................

    6.2 Inspection Considerations ................................................................................................

    6.2.1 Downcomer Sleeve ..................................................................................................

    6.2.2 Tee Box Assembly ...................................................................................................

    6.2.3 Shroud Connection Region ......................................................................................

    6.3 Applicable Mockups ..........................................................................................................

    6.3.1 Core Spray Mockups ................................................................................................

    6.3.1.1 Downcomer Sleeve Joint Mockup (BW RVIP-J) .................................................

    6.3.1.2 BW R/2 Shroud Penetration Mockup (BW RVIP-K) .............................................

    6.3.1.3 BW R/3-5 Shroud Penetration Mockup (BW RVIP-L) ..........................................

    6.3.1.4 BWR/3-5 Core Spray Header Tee Box Mockups (BWRVIP-M and -N) .............

    6.3.1.5 BWR/6 Core Spray Pipe Coupling Assembly Mockup (BWRVIP-CS6) .............

    6.4 UT Technique Demonstrations for Core Spray W elds ......................................................

    6.4.1 General Findings for UT ...........................................................................................

    6.4.1.1 Detection and Sizing of Flaws Parallel to the W eld ...........................................

    6.4.1.2 Detection of Flaws Transverse to the W eld .......................................................

    6.4.1.3 Effect of Roughness of Scanning Surface .........................................................

    6.4.2 UT Demonstration Summary ....................................................................................

    6.4.3 UT Demonstration 1 .................................................................................................

    Xxxviii

  • 6.4.4 UT Demonstration 2 .................................................................................................

    6.4.5 UT Demonstration 3 .................................................................................................

    6.4.6 UT Demonstration 4 .................................................................................................

    6.4.7 UT Demonstration 5 .................................................................................................

    6.4.8 UT Demonstration 6 .................................................................................................

    6.4.9 UT Demonstration 7 .................................................................................................

    6.4.10 UT Demonstration 8 .................................................................................................

    6.4.11 UT Demonstration 9 .................................................................................................

    6.4.12 UT Demonstration 10 ...............................................................................................

    6.4.13 UT Demonstration 11 ...............................................................................................

    6.4.14 UT Demonstration 12 ...............................................................................................

    6.4.15 UT Demonstration 13 ...............................................................................................

    6.4.16 UT Demonstration 14 ...............................................................................................

    6.4.17 UT Demonstration 15 ...............................................................................................

    6.4.18 UT Demonstration 16 ...............................................................................................

    6.4.19 UT Demonstration 17 ...............................................................................................

    6.4.20 UT Demonstration 18 ...............................................................................................

    6.4.21 UT Demonstration 19 ...............................................................................................

    6.4.22 UT Demonstration 20 ...............................................................................................

    6.4.23 UT Demonstration 21 ...............................................................................................

    6.4.24 UT Dem onstration 22 ...............................................................................................

    6.4.25 UT Demonstration 23 ...............................................................................................

    6.4.26 UT Demonstration 24 ...............................................................................................

    6.4.27 UT Demonstration 25 ...............................................................................................

    6.4.28 UT Demonstration 26 ...............................................................................................

    6.4.29 UT Demonstration 27 ...............................................................................................

    6.4.30 UT Demonstration 28 ...............................................................................................

    6.4.31 UT Demonstration 29 ...............................................................................................

    6.4.32 UT Demonstration 30 ...............................................................................................

    6.4.33 UT Demonstration 31 ...............................................................................................

    6.4.34 UT Demonstration 32 ...............................................................................................

    6.4.35 UT Demonstration 33 ...............................................................................................

    6.4.36 UT Demonstration 34 ...............................................................................................

    6.4.37 UT Demonstration 35 ...............................................................................................

    xxxix

  • 6.4.38 UT Demonstration 36 ...............................................................................................

    6.4.39 UT Demonstration 37 ...............................................................................................

    6 A INVESTIGATION OF CORE SPRAY INTERNAL PIPING OVERLAY INSPECTION..... 6A-1

    6A.1 Materials ...........................................................................................................................

    6A.1.1 Probes .....................................................................................................................

    6A.1.2 Ultrasonic Instrument ..............................................................................................

    6A.1.3 Mockups ..................................................................................................................

    6A.2 Surface Condition .............................................................................................................

    6A.3 Exam ination Results .........................................................................................................

    6A.4 Conclusions ......................................................................................................................

    6A.5 References .......................................................................................................................

    7TOP GUIDE ............................................................................................................................ 7-1

    7.1 Sum m ary ..........................................................................................................................

    7.2 Inspection Considerations ................................................................................................

    7.2.1 Aligner Pin Assemblies ............................................................................................

    7.2.2 Hold-Down Assem blies ............................................................................................

    7.2.3 W edges ....................................................................................................................

    7.2.4 BW R/6 Hold-Down Studs .........................................................................................

    7.2.5 Rim -to-Bottom Plate W eld ........................................................................................

    7.2.6 G rid Beams ..............................................................................................................

    7.3 Applicable Mockups ..........................................................................................................

    7.3.1 Top Guide Grid Mockup BW RVIP-I ..........................................................................

    7.4 UT Technique Demonstrations for Top Guide Com ponents .............................................

    7.4.1 General Findings for UT ...........................................................................................

    7.4.1.1 G rid Beams ........................................................................................................

    7.4.2 UT Demonstration 1 .................................................................................................

    8 CORE PLATE ......................................................................................................................... 8-1

    8.1 Sum m ary ..........................................................................................................................

    8.2 Inspection Considerations ................................................................................................

    8.2.1 Rim Hold-Down Bolt Locations ................................................................................

    8.3 Applicable Mockups ..........................................................................................................

    8.4 UT Technique Demonstrations for Core Plate Rim Hold-Down Bolts ...............................

    X1

  • 8.4.1 UT Demonstration 1 .................................................................................................

    8.4.2 UT Demonstration 2 .................................................................................................

    8.4.3 UT Demonstration 3 .................................................................................................

    8.4.4 UT Demonstration 4 .................................................................................................

    9 LPCI CO UPLING .................................................................................................................... 9-1

    9.1 Summary ..........................................................................................................................

    9.2 Inspection Considerations ................................................................................................

    9.3 Applicable Mockups ..........................................................................................................

    9.4 UT Technique Demonstrations for LPCI Coupling W elds .................................................

    10 JET PUM P ASSEM BLY ..................................................................................................... 10-1

    10.1 Summary ..........................................................................................................................

    10.2 Inspection Considerations ................................................................................................

    10.3 Applicable Mockups .........................................................................................................

    10.3.1 Mockup BW RVIP-U ..................................................................................................

    10.3.2 Mockup BW RVIP-V ..................................................................................................

    10.3.3 Mockup BW RVIP-Z3 ................................................................................................

    10.3.4 Mockup BW RVIP-Z4 ................................................................................................

    10.3.5 Jet Pump Beam Mockups ........................................................................................

    10.4 UT Technique Demonstrations .........................................................................................

    10.4.1 General Findings for UT ...........................................................................................

    10.4.2 UT Demonstration 1 .................................................................................................

    10.4.3 UT Demonstration 2 .................................................................................................

    10.4.4 UT Demonstration 3 .................................................................................................

    10.4.5 UT Demonstration 4 .................................................................................................

    10.4.6 UT Demonstration 5 .................................................................................................

    10.4.7 UT Demonstration 6 .................................................................................................

    10.4.8 UT Demonstration 7 .................................................................................................

    10.4.9 UT Demonstration 8 .................................................................................................

    10.4.10 UT Demonstration 9 .................................................................................................

    10.4.11 UT Demonstration 10 ...............................................................................................

    10.4.12 UT Demonstration 11 ...............................................................................................

    10.4.13 UT Demonstration 12 ...............................................................................................

    10.4.14 UT Demonstration 13 ...............................................................................................

    xli

  • 10.4.15 UT Demonstration 14 ...............................................................................................

    10.4.16 UT Demonstration 15 ...............................................................................................

    10.4.17 UT Demonstration 16 ...............................................................................................

    10.5 ET Technique Demonstrations .........................................................................................

    10.5.1 ET Demonstration 1 .................................................................................................

    10.5.2 ET Demonstration 2 .................................................................................................

    10.6 Delivery System Demonstrations .....................................................................................

    10.6.1 Delivery System Demonstration 1 ............................................................................

    10.6.2 Delivery System Demonstration 2 ............................................................................

    10.6.3 Delivery System Demonstration 3 ............................................................................

    10.6.4 Delivery System Demonstration 4 ............................................................................

    11 STANDBY LIQUID CONTROL ........................................................................................... 11-1

    11.1 Sum m ary ..........................................................................................................................

    11.2 Inspection Considerations ................................................................................................

    11.2.1 Nozzle-to-Vessel W eld .............................................................................................

    11.2.2 Penetration-to-Vessel W eld .....................................................................................

    11.2.3 Nozzle-to-Safe-End W eld .........................................................................................

    11.2.4 Penetration-to-Safe-End Extension W eld ................................................................

    11.3 Applicable Mockups .........................................................................................................

    11.3.1 Mockup BW RVIP-X1 ................................................................................................

    11.3.2 Mockup BW RVIP-X2 ................................................................................................

    11.3.3 Mockup BW RVIP-Y3 ................................................................................................

    11.3.4 Mockup BW RVIP-Y4 ................................................................................................

    11.3.5 Mockup BW RVIP-Y5 ............................................................................................

    11.4 UT Technique Demonstrations for SLC Com ponents ................................................

    11.4.1 General Findings for UT ...........................................................................................

    11.4.2 UT Demonstration 1 .................................................................................................

    11.4.3 UT Dem onstration 2 .................................................................................................

    12 VESSEL ATTACHM ENTS ................................................................................................. 12-1

    12.1 Sum m ary ..........................................................................................................................

    12.2 Inspection Considerations ................................................................................................

    12.3 Applicable Mockups .........................................................................................................

    12.4 UT Technique Demonstrations for Vessel Attachment W elds .........................................

    xlii

  • 13 LOW ER PLENUM .............................................................................................................. 13-1

    13.1 Sum m ary ..........................................................................................................................

    13.2 Inspection Considerations ................................................................................................

    13.3 Applicable M ockups .........................................................................................................

    13.4 UT Technique Dem onstrations for Lower Plenum W elds ................................................

    14 INSTRUM ENT PENETRATIO NS ....................................................................................... 14-1

    14.1 Sum m ary ..........................................................................................................................

    14.2 Inspection Considerations ................................................................................................

    * This section, its subsections, and all associated figures and tables are not proprietary.

    All sections that are NOT marked with an asterisk, their subsections, and associated figuresand tables, are proprietary.

    xliii

  • LIST OF FIGURES

    Figure 4.3.1.3-1. Design of Shroud Mockup BWRVIP-A ........................................................... 4-3

    Figure 4.3.1.3-2. Cross Section of Weld in Mockup BWRVIP-A ................................................ 4-4

    Figure 4.3.1.4-1. Design of Shroud Mockup BWRVIP-B ........................................................... 4-5Figure 4.3.1.4-2. Cross Section of Weld in Mockup BWRVIP-B ................................................ 4-6Figure 4.3.1.5-1. Design of Shroud Mockup BWRVIP-C ........................................................... 4-7

    Figure 4.3.1.5-2. Cross Section of Weld in Mockup BWRVIP-C ................................................ 4-8Figure 4.3.1.6-1. Mockup BWRVIP-G and BWRVIP-H, Representing the Ring

    S egm ent W eld .................................................................................................................... 4-9Figure 4.3.1.6-2. Cross Section of Mockup BWRVIP-G and BWRVIP-H ................................. 4-10Figure 4.3.1.6-3. Shroud Ring Segment Weld ......................................................................... 4-10Figure 4.3.1.7-1. Mockup BWRVIP-H1: Shroud Weld HI ....................................................... 4-45

    Figure 4.3.1.8-1. Mockup BWRVIP-SSC1 ............................................................................