2001 ANNUAL REPORT2001 PL1 ANNUAL REPORT-3- 5.2 Environmental Audits 17 5.3 Safety Audits 17 6.0...
Transcript of 2001 ANNUAL REPORT2001 PL1 ANNUAL REPORT-3- 5.2 Environmental Audits 17 5.3 Safety Audits 17 6.0...
2001 ANNUAL REPORT
OnPipeline Licence 1
MOOMBA TO ADELAIDE PIPELINE
Document NumberJDK-TR-1015-01
April 2002
2001 PL1 ANNUAL REPORT
-2 -
TABLE OF CONTENTS
TABLE OF CONTENTS 2
LIST OF ABBREVIATIONS 4
1.0 SUMMARY 6
2.0 ACTIVITIES UNDERTAKEN IN 2001 7
2.1 Safety and Environmental 7
2.1.1 Incidents 7
2.1.2 Risk Assessments 8
2.2 Maintenance Performance 10
2.2.1 Pipeline 10
2.2.2 Cathodic Protection 11
2.2.3 Electrical and Instrumentation 11
2.2.4 Communications 12
2.2.5 Mechanical 12
2.2.6 Other 13
2.2.6.1 Landholder Contacts 13
2.2.6.2 Pipeline Location Service 13
2.2.6.3 Community Awareness 14
2.3 Training 14
2.4 Emergency Response 15
3.0 COMPLIANCE ISSUES 15
4.0 ACTIONS TO RECTIFY NON-COMPLIANCE 16
5.0 MANAGEMENT SYSTEM AUDITS 16
5.1 Operational Audits 16
2001 PL1 ANNUAL REPORT
-3 -
5.2 Environmental Audits 17
5.3 Safety Audits 17
6.0 REPORTS GENERATED IN 2001 18
7.0 REPORTED INCIDENTS 18
8.0 THREATS TO THE PIPELINE 19
8.1 AS2885 Risk Assessment 19
8.2 Other 19
9.0 OPERATIONS PROPOSED FOR 2002/2003 20
10.0 VOLUME OF PRODUCT TRANSPORTED 20
11.0 STATEMENT OF EXPENDITURE 20
12.0 KEY PERFORMANCE INDICATORS 21
ANNEX A - STATEMENT OF ENVIRONMENTAL OBJECTIVES 23
ANNEX B - ASSESSMENT OF STATED OBJECTIVES 36
ANNEX C - PIPELINE CP DATA AND ON/OFF POTENTIAL PROFILES 38
2001 PL1 ANNUAL REPORT
-4 -
LIST OF ABBREVIATIONSALARP As Low As Reasonably Practicable
AS2885 Australian Standard 2885 – Pipelines- Gas and Liquid Petroleum
CFS Country Fire Service
CP Cathodic Protection
CPU Cathodic Protection Unit
DNV Det Norske Veritas
EMS Environmental Management System
ESD Emergency Shut Down
GJ Giga Joule
GPS Geographical Positioning System
Hazop Hazard Operability
HDD Horizontal Directional Drill
HSE Health, Safety and Environment
KP Kilometre Point
LMS Land Management System
LTI Lost Time Injury
MAOP Maximum Allowable Operating Pressure
MAP Moomba to Adelaide Pipeline
MFS Metropolitan Fire Service
MLV Mainline Valve
2001 PL1 ANNUAL REPORT
-5 -
MTI Medical Treatment Injury
PIRSA Primary Industries and Resources of South Australia
PL1 Pipeline Licence No 1
ROC Remote Operating Controller
SCADA Supervisory Control and Data Acquisition
SEO Statement of Environmental Objectives
SES State Emergency Service
SMS Safety Management System
SWER Single Wire Earth Return
TJ Terra Joule
UHF Ultra High Frequency
VHF Very High Frequency
2001 PL1 ANNUAL REPORT
-6 -
1.0 SUMMARYThis report is submitted in accordance with the requirements of Pipeline Licence 1 andthe South Australian Petroleum Regulations 2000. The Moomba to Adelaide Pipeline isowned, operated and maintained by Epic Energy.The report reviews operations carried out during 2001 and intended operations for2002 and 2003. In accordance with the Petroleum Regulations, a performanceassessment is also provided with regard to the Statement of Environmental Objectivesfor the Moomba to Adelaide Pipeline.The Moomba to Adelaide Pipeline is 781km long and 559mm in diameter, constructedof welded steel wrapped in a protective coating and is buried to depths in excess of800 mm. There are seven gas turbine driven compressor stations located about 100kms apart and mainline valves are installed approximately every 32kms. After-coolersare provided at the compressor stations to reduce the risk of stress fracture or over-temperature of the pipeline coating. The pipeline was designed for the expresspurpose of transporting Natural Gas and operates at a Maximum Operating Pressure of7.3MPa.The MAP has been progressively upgraded to boost capacity and increase security ofgas supplies. This includes a 43km loop line of 510mm diameter between Wasleys theTorrens Island Power Station, where pressure limiting is installed to protect themainline.The design parameters for the Moomba to Adelaide Pipeline are as follows:
Date Constructed 1967/68Date Commissioned 1969Length, km 781Diameter (OD), mm 559Wall Thickness, mm:- Normal 7.92- Special Crossings (eg:
rivers, roads, railways)9.50
- MLV’s 9.50Pipe Grade API 5L X52MAOP, kPa 7,300Coating Plicoflex TapeMain Line Valves 34Actuators 16Compressor Stations 7Meter Stations 28
2001 PL1 ANNUAL REPORT
-7 -
The design parameters for the Wasleys Loopline are as follows:
Date Constructed Sep 1986Date Commissioned Sep 1986Length, km 43Diameter (OD), mm 510Wall Thickness, mm:- Normal 9.00- Special Crossings (eg:
rivers, roads, railways)9.00
- MLV’s 9.00Pipe Grade API 5L X60MAOP, kPa 7,322Coating Fusion Bonded EpoxyMain Line Valves 6Actuators 5Scraper Stations 0Meter Stations
6
2.0 ACTIVITIES UNDERTAKEN IN 2001
2.1 Safety and Environmental
2.1.1 IncidentsThere were 30 Incidents reported for the MAP, consisting of:
• 16 Environmental (4 third party encroachments, 2 oil spills(minor/contained), 5 gas releases and 5 erosions);
• 4 Incidents causing injury (2 LTI, 1 MTI, 1 no medical treatment required);
• 8 Safety (3 hazards, 2 near misses, 3 incident); and
• Unavoidable vehicle incidents.
2001 PL1 ANNUAL REPORT
-8 -
2.1.2 Risk AssessmentsAn AS2885 Risk Assessment was undertaken for the MAP, which included allMAP Laterals (Doc No: TEB-012-0007-01). The draft risk assessment reportwas submitted to PIRSA in December 2001 and the final revision provided inJanuary 2002.Following a review of the location and non-location specific threats to thepipeline, six categories were considered to be credible:
- Corrosion.- External Interference, including: excavation, trenching operations, hole
boring, core sampling and bore drilling, blasting, dam building, road works,HDD operations, quarrying, construction activities, vibration at railway(cased) crossing, maintenance of drains and failure of other pipelines(rupture).
- Operations and Maintenance Threats, including: exceeding MAOP, piggingoperations, incorrect operation of control equipment, bypass of logic andcontrol equipment, inadequate maintenance procedures, inaccurate testequipment and inadequate servicing of pipeline.
- Natural Events, including lightning, floods/inundations, movement of sanddunes, erosion, and flotation of pipeline and impact by floating objects.
- Intentional damage.- Other threats, including: powerline breakages, induced voltages and fault
current from parallel powerlines, anchorage, as well as casings shielding thepipeline from adequate Cathodic Protection.
Of those credible threats, existing protection was determined to be adequate for
the majority and they were consequently assessed as being at ALARP. Theremaining threats were then assessed and risk ranked as follows:
River bed level recovery since removalof previous walls higher than originalcrossing area
Water flow looking downstream
2001 PL1 ANNUAL REPORT
-9 -
• Intermediate:• External corrosion (SCC) – All Laterals• General corrosion (CP shielding) – Dry Creek, Taperoo, Burra,
Peterborough, Port Bonython, Whyalla and Angaston Laterals• Trenching operations – MAP, Burra, Peterborough, Whyalla and
Angaston Laterals• Power pole hole boring – MAP; All Laterals, except Osborne and
Quarantine Laterals• Dam building – Angaston Lateral
• Low:• Internal corrosion (CO2) – All Laterals• General corrosion – All Laterals• Bore drilling – Angaston Lateral• Change of land use (Vineyard development) – Angaston Lateral• Excavation of Telstra cable which crosses underneath MAP at KP680.7• Fault current/Powerline breakage from parallel powerlines – MAP and
Laterals• Casing shielding pipe from adequate CP at railway crossings – MAP
and Laterals• Washout of Balcooracana Creek crossing KP351.3 – MAP• Wilpeena Creek crossing KP386.5 – MAP• Creek crossings at KP413.9 and KP547.4 – MAP• Drain crossing at KP646.3 – MAP• Failure of Origin 18inch pipeline at KP0.417 – Dry Creek Lateral• Failure of Epic Energy 20inch Loopline at KP0.02 – Osborne Lateral• Failure of Moomba to Port Bonython Liquids Line at KP68.1 – Port Pirie
to Whyalla Lateral• Failure of Moomba to Port Bonython Liquids Line at KP4.45 – Port
Bonython Lateral• Emergency anchor drop from passing ships at Port River – Taperoo
Lateral• Anchorage damage to both 4 inch steel pipeline and Lateral at Spencer
Gulf crossing – Port Pirie to Whyalla Lateral
• Negligible:• Mulligan Springs Creek crossing• Failure of below ground Santos gathering pipeline where it crosses the
MAP• Failure of above ground Santos gathering pipeline where it crosses the
MAP• Fault currents/Powerline breakage
The risk assessment generated 9 global actions, 20 MAP location Specificactions, 7 Lateral location specific actions, 10 MAP non-location specific actionsand 7 Lateral non-location specific actions.
2001 PL1 ANNUAL REPORT
-10 -
2.2 Maintenance PerformanceIn 2001, 2235 Maintenance Work Orders were produced from Epic Energy’sComputerised Maintenance Management System (Maximo), made up as follows:
• 47 % Preventative Maintenance tasks; and• 53 % Corrective Maintenance tasks.
2.2.1 Pipeline• All routine road and aerial patrols and
above ground facility inspections werecompeted as scheduled.
• Fire extinguisher services werecompleted twice at all facilities inaccordance with Australian Standards.
• MLV and scraper station valves weremaintained in accordance with theMaintenance Program.
• A new 200mm lateral andregulator/meter station wasconstructed and commissioned tosupply the Origin Energy QuarantinePower Station. Epic Energy isresponsible for the operation andmaintenance of those facilities.
A total of three hot taps were carried out on the pipeline system in 2001. A400mm hot tap was carried out on the 500mm diameter Loop Line for theofftake to the new Origin Energy Quarantine Power station. A 200mm hot tapwas carried out on the Angaston Lateral for the offtake to the new Amcor Glassfactory. Finally, a 550mm hot tap was carried out on the Moomba to AdelaidePipeline for the offtake to the new Hallet Power Station.The underground pipework at Compressor Station 6, between the units and theaftercoolers was excavated and inspected as part of the ongoing pipelineintegrity management plan.Approximately 700 new “Pipeline Warning“ signs were installed on the Moombato Adelaide Pipeline to increase line of sight and ensure full compliance withAS 2885.3. The sections between Moomba and Compressor Station 2,Compressor Stations 4 and 5, and Peterborough to Compressor Station 7 wereall upgraded.
2001 PL1 ANNUAL REPORT
-11 -
2.2.2 Cathodic Protection
To mitigate corrosion, all buriedpipelines are covered with aprotective coating which serves toisolate the external pipeline surfacesfrom corrosive elements in thesurrounding environment. Secondaryprotection at coating holidays andimperfections is achieved byapplying cathodic protection.
The effectiveness of the cathodic protection system is monitored by carrying outtwo full line potential surveys annually, once at the end of summer and thenagain at the end of winter. In addition, all cathodic protection units (CPU’s) areinspected for correct operation bi-monthly.Survey results given in Annex C indicate all areas of the pipeline system metthe target performance levels of protection (Refer to Section 13). It should benoted that some of the OFF potentials lower than -0.850 V are from foreigncrossings and do not belong to the MAP. Examples of these include thepotential of the casing in a cased crossing; potential of the foreign pipe and aTelecom shielded cable. Apart from these low points there are genuine lowpotentials on the line that are due to the condition of the coating and nature ofthe local ground. Each year new ground beds are installed to increase the levelof protective current available to the pipe. Through this practice, old groundbeds with increased resistance are also replaced with new ones. In Year 2001two new ground beds were installed at KP 294.66 and at KP 416. These groundbeds were activated very early in 2002.
2.2.3 Electrical & Instrumentation
• All routine Meter Station custodytransfer and Compressor Stationfuel gas accuracy verification testswere completed as per themaintenance plan.
• Compressor station andcompressor unit electrical serviceswere completed in line with themaintenance program.
• Fire and gas detection systemswere serviced in accordance withthe Australian Standard.
2001 PL1 ANNUAL REPORT
-12 -
Cooled recycle valves were installed into the pig trap kicker line pipework atCompressor Stations 1, 2, 4, and 6 to prevent the station shutting down on highdischarge temperature. This project has increased station and unit reliability.The Compressor Station unit valves were overhauled and the valve positionerreplaced with Fisher DVC controllers, increasing fuel efficiencies and unitreliability.Regular inspections and maintenance was performed on the 19Kv SWER lineand solar panel battery powered sites on the Moomba to Adelaide Pipelinesystem.
2.2.4 CommunicationsRoutine maintenance has ensured the reliability of the digital microwavesystem.VHF, UHF, and Telstra telephone communication systems are maintained inaccordance with the maintenance management plan.
2.2.5 Mechanical• Compressor Station 7 had the Centaur
turbine on unit “A” was upgraded toincrease horsepower from 4000 to4700 and increase pipeline capacity.The unit “A” boost compressor wasalso overhauled to increaseefficiencies at the station.
• All scheduled routine filter inspections/changes, MLV maintenance, regulatorinspection/services, relief valve testing,and ESD valve operational checkswere completed on meter andcompressor as scheduled.
The Gas Engine Alternator at Compressor Station 4 was overhauled / rebuiltand the 68D Alternators at Compressor Station 1, 2 and 3 had cooling systemupgrades completed to prevent high shut downs and increase station powerreliability.The Angaston Meter Station relief valve was replaced with a modulating typerelief valve system to reduce gas emissions to atmosphere in the event of aregulator failure or a relief valve operation.
2001 PL1 ANNUAL REPORT
-13 -
2.2.6 Other
2.2.6.1 Landholder Contacts
There are 470 landowners and occupiers along the MAP system.
A property owner contact scheme is operated by Epic Energy. The LandManagement Officer personally visits each owner or occupier along the pipelinesystem annually.
Other contacts made by Field Maintenance Officers and Superintendents duringthe course of daily business, or other land related issues that arise occasionallyare recorded in our Land Management System.
Land Management is supported by dedicated LMS software that provides apowerful data base and MapInfo facilities. All property details and notesrelating to discussions or issues with the property owners are recorded in theLMS. Through its MapInfo facility an image of the cadastral boundaries of eachproperty relative to the pipeline route can be displayed for any property. Duringthe year each property owner dwelling has been captured by GPS and will bedisplayed on the pipeline / cadastral plans.
If personal contact cannot be made, the occupier or owner is telephoned ormailed a letter explaining the reason for the visit, the contact officer’s businesscard, an information brochure on pipeline safety and our dial before you digcontact phone number is left at all unattended residences visited. All propertyowners receive our pipeline safety brochure, a complimentary biro, as well as ahigh quality calendar, which is individually mailed out.
These items all contain our "Dial Before You Dig" contact phone number andstrongly reinforce safe working practices near high-pressure gas lines.
A hard file is maintained for each of the 1500 land parcels crossed by pipelines.Each property is flagged with the Land Titles Office who inform Epic Energy ofany changes in ownership or land tenure details, ensuring that our records arealways up to date for mail outs and personal visits.
2.2.6.2 Pipeline Location Service
Epic Energy provides a free service to locate pipelines for which they areresponsible. This service is primarily used by other companies carrying out civilworks in the vicinity of any of the pipelines administered by Epic Energy.There were 190 actual pipe locations carried out for third parties on theMoomba - Adelaide Pipeline in 2001. The majority of the pipeline locationsrequested were as a result of the “One Call“ system, they ranged from newinstallations crossing the pipeline, new fences as a result of subdivisions, andgeneral activities on the pipeline easement. All authorised activities within thepipeline easement are supervised by Epic Energy field officers to ensure thesafety and integrity of the pipeline.
2001 PL1 ANNUAL REPORT
-14 -
2.2.6.3 Community Awareness
• Epic Energy implements a CommunityAwareness Program, which entailsholding awareness meetings withcommunities along the pipeline route.
• The target is to hold meetingsapproximately annually with CFS,MFS, police, ambulance, SES,councils, Earth Moving Contractors,irrigation installation contractors andvarious community members invitedto attend.
In year 2001, 3 public awareness presentations for the Moomba to AdelaidePipeline were made at Burra, Peterborough, and Whyalla. The focus of thepresentation was on the specific nature and characteristics of the productscarried by the Moomba - Adelaide line, the route of the pipeline, basicinformation about the pipeline and its monitoring, control and emergencyprocedures. Additional meetings were held with several utilities, includingTelstra, Origin Energy and ETSA.
2.3 TrainingConsiderable training was carried out in SA for field maintenance personnel, including:
• Base Line (Petroleum Industry) training was completed by all Epic Energy fieldpersonnel;
• Senior First Aid Training (re-certification) was completed by all field staff;
• Health, Safety and Environmental (HSE) Induction training was completed by allEpic Energy field personnel;
• Permit to Work training was completed by all Epic Energy field personnel;
• Remote Operations Controller (ROC) Training for Fisher ROC’s was completedby all Epic Energy electrical and instrumentation staff;
• Water Bath Heater training to accommodate the maintenance to be carried outat the new Quarantine Power Station and Hallet Power Station was carried outby Tomlinson Boilers;
• Bristol Babcock Remote Terminal Unit training was conducted by Bristol;
• Dr Hassan Nabi-Zadeh (Epic Energy Corrosion Control Engineer) conducted inhouse Cathodic Protection training;
• Pipeline Location training in the use of Metrotech 9800 series Pipeline Locatorswas conducted by Corrpro Pty Ltd;
• Confined Space Entry and the use of Breathing Apparatus Course wasconducted by BOC Gases Pty Ltd;
2001 PL1 ANNUAL REPORT
-15 -
• Wasleys Compressor Package training was conducted by Collicutt Pty Ltd(Canada, supplier of Package); and
• Familiarisation training in the maintenance of Gorter and Pietro Fiorentiniregulators was conducted by the suppliers.
2.4 Emergency ResponsePipeline Licence 1 requires emergency drills be held on the pipeline system at leastevery two years.
An emergency exercise was held at Angaston Compressor site on 15 February 2001.The exercise was used as a joint exercise for the Riverland Pipeline system and theAngaston Lateral under Pipeline Licence 1.
A full mobilisation exercise is scheduled for the Moomba to Adelaide Pipeline in 2002.
3.0 COMPLIANCE ISSUESEvery endeavour is made to ensure that design, manufacture, construction, operation,maintenance and testing of all appropriate facilities are carried out in accordance withAS 2885. Any non-compliance identified is logged in Epic Energy’s ComputerisedMaintenance Management System, where they are tracked to conclusion. Significantitems are reported to PIRSA.A copy of the currently gazetted Statement of Environmental Objectives (SEO’s) forPL1 is provided at Annex A. The overall objectives of the SEO’s were achieved in that:
• Environmental damage from activities involved in operation of the Moomba toAdelaide Pipeline was minimised;
• Appropriate consultative processes involving people directly affected by regulatedactivities and the public generally were established; and
• The public was protected from risks inherent in regulated activities involving theMoomba to Adelaide Pipeline.
The specific objectives declared in the SEO’s have been assessed in accordance withthe Goal Attainment Scaling. The results of that assessment are provided in Annex B.
2001 PL1 ANNUAL REPORT
-16 -
4.0 ACTIONS TO RECTIFY NON-COMPLIANCETo mitigate corrosion, all buried pipelines are covered with a protective coating whichserves to isolate the external pipeline surfaces from corrosive elements in thesurrounding environment. Secondary protection at coating holidays and imperfectionsis achieved by applying cathodic protection.
The effectiveness of the cathodic protection system is monitored by carrying out twofull line potential surveys annually, once at the end of winter and then at the end ofsummer. In addition all cathodic protection units (CPU’s) are inspected for correctoperation bimonthly.
Survey results given in Appendix C indicate all areas of the pipeline system met thetarget performance levels of protection. It should be noted that some of the OFFpotentials lower than -0.850V are from foreign crossings do not belong to the MAP.Examples of these include the potential of the casing in a cased crossing; potential ofthe foreign pipe and a Telecom shielded cable. In the next annual report the MAPpotentials only will be presented in the graphs and charts. Apart from these low points,there are genuine low potentials on the line that are due to the condition of the coatingand nature of the local ground.
Each year new ground beds are installed to increase the level of protective currentavailable to the pipe. In this practice old ground beds with increased resistance arealso replaced with new ones. In Year 2001 two new ground beds were installed at KP294.66 and at KP 416. These ground beds will be activated in early 2002.
5.0 MANAGEMENT SYSTEM AUDITS
5.1 Operational AuditsEpic Energy is partially owned by El Paso Corporation, a major North American gastransmission company. The El Paso Corporate Audit Division conducted anoperational audit on Epic Energy in the third quarter of 2001. While that audit focusedon gas pipelines, it included a partial review of the Liquids Pipeline. The only issue ofconcern raised in regard to the Liquids Pipeline related to the upkeep of the burn pits,which are no longer used. This will be addressed in 2002 as a specific exemptexpenditure item.
5.2 Environmental AuditsAs the owner of the Moomba to Adelaide Pipeline, Epic Energy is required to have inplace an Environmental Management System. A complete review of that EMS wascarried out in 2001, following the development of SEO's for operating pipelines in SA.The Audit looked at the effectiveness and system structure relating to the SEO's.Modifications were carried out on the Aspects Register and included an update of theObligations Register.PPK Environmental & Infrastructure Pty Ltd were commissioned to undertakeenvironmental monitoring works at several sites along the Moomba to AdelaidePipeline. These sites included Compressor Stations 1 - 7, the Mintaro Meter Station,Peterborough Depot and Torrens Island Meter Station. The objectives of the programare part of ongoing environmental monitoring and walk through inspections to identifysignificant environmental issues.Groundwater monitoring was carried out at selected sites to determine the extent ofhydrocarbon plume beneath the site and whether this has changed since the previous
2001 PL1 ANNUAL REPORT
-17 -
round of monitoring. The 2001 survey provided evidence of natural degradation of theplume. The program is to ensure that any significant breach in the integrity of thescrubber tanks on the above sites is identified, to enable a response strategy to beimplemented if required. Monitoring of previously identified hydrocarbon contaminationwithin the groundwater at the Torrens Island site was carried out to determine themigration of contaminant and assess the potential for natural attenuation. A generalreduction in the hydrocarbon concentration since previous monitoring round hasoccurred with evidence of natural biodegradation of hydrocarbons. Groundwatermonitoring at the Torrens Island Meter Station will continue, to assess the migration ofthe petroleum hydrocarbon contamination within the groundwater and provide evidenceof natural attenuation of the hydrocarbon plume beneath this site.Due to presence of a localised area of phase separated hydrocarbon product in thevicinity of the former soakage pit at Compressor Station 7, a passive skimminggroundwater remediation system was installed in 2001. The objective was to removeas much phase-separated hydrocarbon (PSH) product as practicable from thegroundwater. This reduces the spread of the contamination plume within thegroundwater. The passive skimming unit has been operating effectively and hasreduced the thickness of phase-separated hydrocarbons to a thin film. It has beenrecommended that the unit remain in operation until the rate of PSH recovery becomesnegligible.Existing areas of “African Rue”, an exotic weed along the Right Of Way in the vicinity ofCS5, were monitored and sprayed at appropriate intervals.
5.3 Safety AuditsEpic Energy has developed and implemented a Safety Management System (SMS) forall operations and pipeline systems. An internal audit of the SMS was conducted in2001. Further to this, Det Norske Veritas (DNV) undertook an external review inaccordance with our Western Australia Safety Case requirements.Housekeeping inspections are conducted monthly at all facilities in accordance with ourSMS requirements.
6.0 REPORTS GENERATED IN 2001The following reports were generated and forward to PIRSA during 2001:
• PL1 Annual Report for 2000 submitted to PIRSA 11 April 2001.
• AS 2885 Risk Assessment for the Moomba to Adelaide Pipeline submitted 20December 2001.
7.0 REPORTED INCIDENTSA total of 30 safety and environmental incidents were reported on the Moomba toAdelaide Pipeline, including:
• Unauthorised activity in the Easement:A new fence was erected within one metre of the pipeline on Taylors Road,Anglevale. The landowner drilled a hole 300mm deep within one metre of thepipeline. This work was unauthorised and unsupervised.A new fence was installed on the pipeline easement at Kp 581.2Burra Council removed 400mm of ground cover from the pipeline easement forroad repairs without notifying Epic Energy.
2001 PL1 ANNUAL REPORT
-18 -
Heathgate Resources bogged a grader on the pipeline easement within one metreon the pipeline near Compressor Station 3.
• ErosionWashouts occurred after heavy rains at Muligans Creek on two occasions, eachtime exposing the top of the pipeline for a short distance.Heavy rains caused Moorowie Creek to flow just south of Compressor Station 6and expose the top section of the pipeline.The Balcoracana Creek immediately north of Compressor Station 4 flooded onseveral occasions and twice exposed the top of the pipeline for several metres.
• Relief valves ventingFour relief valves operated in 2001 - Torrens Island Meter Station, Symes RoadMeter Stations, Compressor Station 1 fuel gas skid and Compressor Station 4 fuelgas skid. The largest amount of gas vented was at Compressor Station 1 withapprox 14 TJ of gas vented to atmosphere.
• Pipeline leaksThere was an incident at MLV 24 when the sealant injection nipple dislodged fromthe sealant line, venting gas to atmosphere until repairs were completed. Anestimated 6.9 GJ of gas was vented in this incident.
• Oil SpillsThere was a minor oil spill at Wasleys compressor station when the undergroundoil collection tank allowed a mixture of oil and gas to vent via the breather pipe andcontaminated the ground.The contractor cleaning the meter tubes at Gepps Cross meter station allowedcontaminated water from the cleaning process to spill to ground with the potentialto enter the storm water drains.
2001 PL1 ANNUAL REPORT
-19 -
• Injuries:An employee injured his knee while alighting from the back of a vehicle. Thisrequired surgery and resulted in a roster cycle off work.An employee inadvertently used oxygen instead of nitrogen when testing a reliefvalve. Oil within the valve exploded, resulting in shrapnel injuries to the employee.That employee had several days off work recovering from his injuries.An employee required stitches in his leg after hitting his leg on a protrusion duringroutine maintenance.
8.0 THREATS TO THE PIPELINE
8.1 AS2885 Risk Assessment• The Risk Assessment was commenced in 2001 and was completed in February
2002. This assessment included the Moomba to Adelaide Pipeline, all lateralsand the 500mm Loop Line from Wasleys to Torrens Island.
8.2 Other• Third party activity has is identified as the greatest risk to cause damage to the
Moomba to Adelaide Pipeline. Unauthorised activity on the pipeline easementis the greatest concern.
• The risks identified are from landowners erecting fences or establishing newvineyards and changing the land use, utilities and councils installing newservices and unauthorised use of heavy machinery and earth movingequipment on the easement.
• Natural events such as erosion, flooding of pipeline and impact from floatingobjects, have the potential to cause pipeline and coating damage.
• Epic Energy ensures the pipeline safety through regular and frequent road andaerial patrols, and pipeline warning signs. The risk assessment to be completedin 2002 will give a clearer understanding of any additional risks and supportingactions to rectify potential hazards.
2001 PL1 ANNUAL REPORT
-20 -
9.0 OPERATIONS PROPOSED FOR 2002/2003• Intelligent pigging of the 550mm Moomba to Adelaide pipeline including the
500mm Loop Line form Wasleys to Torrens Island is scheduled for May 2002.
• An investigation on the condition of the un-piggable sections of the pipeline incompressor stations will be conducted in 2002.
• An investigation on the situation of the earthing systems will be conducted in allcompressor stations and metering stations on the pipeline in 2002.
• Interference from overhead power lines crossing and going parallel to thepipeline and the adequacy of pipeline AC mitigation facilities will be investigatedin 2002.
• A modulating type relief valve is to be installed at Port Pirie meter station.
• Communications tower maintenance is carried out every three years and isscheduled for 2002.
• Projects have been raised to replace all rusted carbon steel fittings withstainless steel and all obsolete and antiquated equipment will be replaced andupgraded.
• A Technical Audit was carried out in 2001. Remediation work arising from thataudit will continue through 2002 and 2003.
10.0 VOLUME OF PRODUCT TRANSPORTEDApproximately 100,807 TJ of natural gas were transported through the Moomba toAdelaide Pipeline in 2001.
11.0 STATEMENT OF EXPENDITURECommercial-in-confidence
2001 PL1 ANNUAL REPORT
-21 -
12.0 KEY PERFORMANCE INDICATIONSThe following key performance indicators have previously been established to monitorperformance of operations and maintenance activities on the Moomba to AdelaidePipeline.
2001
target
2001actual
2001Comment
Cathodic Protection
1. % of pipeline that has an offpipe to soil potential greaterthan - 850mV (WINTER)
97% 97%
2. % of pipeline that has an offpipe to soil potential greaterthan - 850mV (Summer)
75% 95%
Third Party Incident
1. Number of times pipeline isdamaged
0 0
2. Number of near misses (diggingwithin 1m of pipeline)
1 1 A new fence was erected over the pipelineon Taylors road, Anglevale, a fence postwas excavated 300mm deep within onemetre on the pipeline
3. Unauthorised activity oneasement
5 3 A fence was installed over the pipeline atKP 581.2. Nearest fence post was notwithin one metre of the pipeline.
The Burra Council graded the road nearBoobarowie removing approx 400mm of topsoil from the pipeline easement withoutnotifying Epic Energy.
Heathgate Resources bogged a grader onthe pipeline easement near CompressorStation 3.
4. Exposure of pipeline due towashout and wind erosion
6 5 Washouts occurred after heavy rains atMulligans Creek on two occasions, eachtime exposing the top section of the pipelinefor a short distance.
Heavy rains caused the Moorowie Creek toflow just south of Compressor Station 6 andexposed the pipeline.
The Balcoracana Creek near CompressorStation 4 flooded on several occasionsexposing the top of the pipeline for severalmetres on two occasions.
Unplanned Gas Release
1. Number of Relief valve/ventdischarges
5 4 Four relief valves operated in 2002 :
• Torrens Island Meter Station
• Compressor Station 1
• Compressor Station 4
• Symes Road Meter Station
The largest was approx 14 TJ from CS1vent relief valve
2001 PL1 ANNUAL REPORT
-22 -
2001
target
2001actual
2001Comment
2. Number of pipeline leaks (morethan 200 m3/hr)
0 2 There was an incident at MLV 24 when thesealant injection nipple dislodged from thesealant line venting gas to atmosphere untilrepairs were completed. An estimated6.9 GJ of gas was vented in this incident.
There was a minor gas leak from the bodyof the Beverley meter station regulator, theamount of gas released was minor
SCADA and Leak Detection
1. Reliability of SCADA 99.5% 99.8%
Environmental
1. Number of oil or otherhydrocarbon spills
2 2 There was a minor oil spill at the WasleysCompressor Station when the undergroundoil collection tank allowed a mixture of gasand oil to vent via the breathing pipeworkand contaminate the ground.
The contractor cleaning the meter tubes atGepps Cross Meter Station allowedcontaminated water from the cleaningprocess to spill to ground with the potentialto enter the storm water drains.
2. Gas unaccounted for 0 0.01% Marginally off target
3. Total methane discharged 34.5 TJ This includes gas vented from unit startsand stops, as well as gas vented duringroutine maintenance on scrubbers, pig trapsand filter vessels. This figure was higherthan target, due to the vent valve mentionedabove and MAP upgrade work.
2001 PL1 ANNUAL REPORT
-23 -
ANNEX A
2001 PL1 ANNUAL REPORT
DATED APRIL 2002
STATEMENT OF ENVIRONMENTAL OBJECTIVES
2001 PL1 ANNUAL REPORT
-24 -
MMoooommbbaa ttoo AAddeellaaiiddee
GGaass PPiippeelliinnee
STATEMENT OF ENVIRONMENTAL
OBJECTIVES
APRIL 2001
2001 PL1 ANNUAL REPORT
-25 -
Table of Contents
1 OBJECTIVES 28
2 ASSESSMENT CRITERIA 29
3 REPORTING REQUIREMENTS 29
4 GLOSSARY 30
5 REFERENCES 30
2001 PL1 ANNUAL REPORT
-26-
INTRODUCTIONThis Statement of Environmental Objectives (SEO) has been prepared in accordancewith the requirements of Section 99 of the Petroleum Act 2000.
Licence Pipeline Licence 1
Licence description Moomba to Adelaide
Location Refer to Figure 1.
Activities covered bythis CEP/SEO.
All regulated activities relating to the operation of the Moombato Adelaide Pipeline.
This SEO does not apply to de-commissioning of the pipeline.A separate SEO will be required prior to de-commissioning.
This SEO does not apply to pipeline construction projects.
The objectives developed in this SEO are in keeping with the objectives of thePetroleum Act 2000, which include:
• To minimise the environmental damage from the activities involved in theconstruction or operation of transmission pipelines for transporting petroleum;
• To establish appropriate consultative processes involving people directly affected byregulated activities and the public generally;
• To protect the public from risks inherent in regulated activities.This document is based on Statements of Environmental Objectives/Codes ofEnvironmental Practice (SEO/CEP) developed for the following recent pipelineprojects:
• Pipeline Licence No 1 – Moomba to Adelaide Pipeline Looping Project
• Pipeline Licence No 4 – South East Pipeline – Nangwarry Lateral ProjectIn each case, the SEO/COP was developed in accordance with both the existinglegislation (Petroleum Act 1940) and the proposed legislation (Petroleum Bill 1999).This included an assessment of the projects in accordance with the SignificanceAssessment Criteria (PIRSA 1999), and in each case the proposals were assessed asbeing of LOW environmental significance. Public consultation on the SEO's was notrequired. Under the terms of draft Memoranda of Understanding with DEHAA andPlanning SA, these SEO’s were developed in consultation with both organisations.
2001 PL1 ANNUAL REPORT
-27-
Figure 1 – Map of Pipeline Route
2001 PL1 ANNUAL REPORT
-28-
This SEO also takes account of previous Declarations of Environmental Factors andCodes of Environmental Practice approved under the Petroleum Act 1940, and makesreference to the Australian Pipeline Industry Association code of EnvironmentalPractice : Part B – Onshore Pipeline Operations.
It should be noted that the major environmental impacts associated with a pipelineproject are associated with construction, while operational impacts are negligible incomparison. As stated above, this SEO applies to pipeline operations only.
OBJECTIVESOBJECTIVE GOAL(S)
1. To avoid significant disturbance to landuse or damage to infrastructure.
1.1 To minimise disturbance to land use anddamage to infrastructure
2. To promote and maintain soil stability 2.1 To ensure there is no erosion on theeasement.
3. To promote and maintain vegetationcover on the ROW.
3.1 To ensure that the easement remainsfree of weeds and pathogens.
3.2 To maintain regrowth of nativevegetation
4. To minimise noise due to operations. 4.1 To ensure operations comply with noisestandards.
5. To minimise the potential for emissionsthat may cause public concern.
5.1 To ensure that uncontrolled emissionsare reported and acted uponimmediately
6. To minimise the risks to public healthand safety.
6.1 To adequately protect public safetyduring normal operation.
6.2 To adequately reduce the likelihood offire.
6.3 To adequately protect public safetyduring maintenance.
7. To ensure the environmentalmanagement and rehabilitation of dig-ups is carried out in accordance withthe APIA Code of EnvironmentalPractice Part B – Onshore PipelineOperations.
7.1 To minimise the impact as a result of anemergency situation.
2001 PL1 ANNUAL REPORT
-29-
ASSESSMENT CRITERIAThe objectives identified above are subject to an assessment to measure the level ofachievement. The assessment criteria for each objective will be one of the following:
• Defined conditions - objectives for construction and operation activities that can onlybe managed through the prevention of unacceptable actions (eg no remnantvegetation shall be cleared);
• Defined requirements - the achievement of an objective can be assessed againstthe implementation of specific procedures or actions required for an activity (eg thedesign and construction of the pipeline must meet the requirements of AS 2885.1—1997 Pipelines—Gas and liquid petroleum);
• Goal Attainment Scaling (GAS) criteria - the objectives are assessed against a setcriteria to determine the level of goal achievement (ie goal exceeded, achieved ornot achieved).
Appendix A tabulates the objectives and the appropriate assessment criteria. The GAScriteria are detailed in Appendix B.
REPORTING REQUIREMENTSDEFINITIONS
It is a requirement under Section 85 of the Petroleum Act 2000 that any incidents thatare determined to be ‘serious’ or ‘reportable’ incidents must be reported to the Minister.The following descriptions have been provided to help clarify and elaborate on thedefinitions given in Section 85(1) of the Petroleum Act 2000 and Regulation 32(1) ofthe Petroleum Regulations 2000.
Serious IncidentsThe incidents listed below are considered to be to be serious incidents under Section85(1) of the Petroleum Act 2000:
• Loss of containment incident resulting in :
• Serious injury or death,
• Imminent risk to public health or safety, or
• Serious environmental damage or imminent risk of serious environmentaldamage, or
• Interruption or imminent risk of interruption of the natural gas supply.
• Unauthorised activity on the pipeline where the pipeline is actually contacted.
2001 PL1 ANNUAL REPORT
-30-
Reportable IncidentsThe incidents listed below are considered to be reportable incidents under Section85(1) of the Petroleum Act 2000:
• Unauthorised activity on the pipeline easement where the pipeline is not contacted.
• Oil or hazardous material spill that adversely impacts on an area not specificallydesigned to contain such spills.
A range of KPI’s must be reported in the annual report.
REPORTING REQUIREMENTS
Serious Incidents must be reported to the PIRSA Minister as soon as practicable afterthe occurrence, as per Section 85 of the Petroleum Act 2000 and Section 32 of thePetroleum Regulations 2000.
Reportable Incidents must be reported to PIRSA on a quarterly basis within 1 monthof the end of the quarter, as per Section 32 of the Petroleum Regulations 2000.
GLOSSARYALARP As Low As Reasonably Practical
APIA Australian Pipeline Industry Association
DEF Declaration of Environmental Factors
DHEAA Department of Environment, Heritage and Aboriginal Affairs
EPA Environment Protection Agency
EIR Environmental Impact Report prepared in accordance with Section 97 ofthe Petroleum Act 2000 and Regulation 10.
PIRSA Primary Industries and Resources, South Australia
Planning SA Department of Transport, Urban Development and the Arts
ROW Right of Way
SEO Statement of Environmental Objectives prepared in accordance withSection 99 and 100 of the Petroleum Act 2000 and Regulations 12 and13.
REFERENCESMcDonough, R. 1999. Goal attainment scaling: a tool for evaluating pipelineenvironmental performance. Primary Industries and Resources of South Australia,Adelaide.
Petroleum Group (PIRSA) 2000. Criteria for Classifying the Level of EnvironmentalImpact of Regulated Activities: Requirements under Part 12 Petroleum Act 2000.Primary Industries and Resources of South Australia, Adelaide.http://www.pir.sa.gov.au
2001 PL1 ANNUAL REPORT
-31-
APPENDIX AOBJECTIVES AND ASSESSMENT CRITERIA
Goal Goal/ Comment Criteria1. To avoid significant
disturbance to land use ordamage to infrastructure.
1.1 To minimise disturbanceto land use and damageto infrastructure
Refer to GAS criteria AppendixB.
2. To promote and maintainsoil stability.
2.1 To ensure there is noerosion on the easement.
Refer to GAS criteria AppendixB.
3. To promote and maintainvegetation cover on theROW.
3.1 To ensure that theeasement remains free ofweeds and pathogens.
3.2 To maintain regrowth ofnative vegetation
Refer to GAS criteria AppendixB.
4. To minimise noise due tooperations.
4.1 To ensure operationscomply with noisestandards.
The requirements of theEnvironment Protection Act1993 and EPA IS No 9 April1998 Noise Control are met.(Refer to Epic EnergyObligation Register)
5. To minimise the potential foremissions that may causepublic concern.
5.1 To ensure thatuncontrolled emissionsare reported and actedupon immediately.
Refer to GAS criteria AppendixB.
6. To minimise the risks topublic health and safety.
6.1 To adequately protectpublic safety duringnormal operation.
6.2 To adequately reduce thelikelihood of fireassociated withmaintenance activities.
6.3 To adequately protectpublic safety duringmaintenance.
Risk assessment reportdemonstrates that the pipelinerisks are Negligible, Low orALARP, in accordance with AS2885 Section 2.
Adherence to AS 2885.3 1997demonstrated via annualreports, emergency responsereports and fitness for purposereports (refer to PetroleumRegulations 2000)
Refer to GAS criteria AppendixB.
7. To ensure the environmentalmanagement andrehabilitation for emergencydig-ups will be carried out inaccordance with the APIACode of EnvironmentalPractice: Part B – OnshorePipeline Operations.
7.1 To minimise the impactas a result of anemergency situation.
In the event of an emergency,stockpiling of topsoil andvegetation etc is not aconsideration. Appropriaterehabilitation action should betaken once the emergency hasbeen dealt with.
Adherence to APIA CEPSection 4.2.
(Refer to Section 5 of EpicEnergy’s EMP Operations).
REFER TO EPIC’S EMP OPERATIONS FOR DETAILS OF THE ENVIRONMENTALCONTROL MEASURES TO BE IMPLEMENTED IN ORDER TO ACHIEVE THE STATEDOBJECTIVES.
2001
PL
1 A
NN
UA
L R
EP
OR
T
-32-
APPE
NDIX
BGO
AL A
TTAI
NMEN
T SC
ALIN
G
Goa
l sig
nific
antly
exce
eded
Goa
l exc
eede
dG
oal a
chie
ved
Min
or s
hort
fall
Sign
ifica
nt s
hort
fall
Obj
ectiv
eG
oal p
aram
eter
+2+1
0-1
-2
1.
To a
void
sign
ifica
ntdi
stur
banc
e to
land
use
or
dam
age
toin
frast
ruct
ure.
1.1
To m
inim
ise
dist
urba
nce
tola
nd u
se a
ndda
mag
e to
infra
stru
ctur
e.
No
dist
urba
nce
toin
frast
ruct
ure.
No
acce
ss to
priv
ate
land
.
Dis
turb
ance
toin
frast
ruct
ure
occu
rsle
ss th
an o
nce
ever
yte
n ye
ars.
Acce
ss to
priv
ate
prop
erty
occ
urs
on a
nan
nual
bas
is in
acco
rdan
ce w
ithla
ndow
ner
agre
emen
ts.
Dis
turb
ance
toin
frast
ruct
ure
(eg.
such
as
fenc
ing
orac
cess
trac
ks) o
ccur
sle
ss th
an o
nce
ever
yfiv
e ye
ars.
Acce
ss to
priv
ate
prop
erty
occ
urs
mor
eof
ten
than
onc
e a
year
in a
ccor
danc
e w
ithla
ndow
ner
agre
emen
ts.
Dis
turb
ance
toin
frast
ruct
ure
occu
rsle
ss th
an o
nce
ever
ytw
o ye
ars.
Acce
ss to
priv
ate
prop
erty
occ
urs
mor
eof
ten
than
twic
e a
year
in a
ccor
danc
e w
ithla
ndow
ner
agre
emen
ts.
Dis
turb
ance
toin
frast
ruct
ure
occu
rs m
ore
ofte
n th
an o
nce
ever
y tw
oye
ars.
Acce
ss to
priv
ate
prop
erty
occu
rs m
ore
ofte
n th
anfo
ur ti
mes
and
was
not
inac
cord
ance
with
land
owne
r agr
eem
ents
.
2.
To p
rom
ote
and
mai
ntai
n so
ilst
abilit
y.
2.1
To e
nsur
eth
ere
is n
oer
osio
n on
the
ease
men
t.
Ther
e w
as n
oev
iden
ce o
f ero
sion
.Th
e ex
tent
of s
oil
eros
ion
on th
eea
sem
ent w
asco
nsis
tent
with
surro
undi
ng la
nd.
Ther
e w
as e
vide
nce
ofm
ore
exte
nsiv
eer
osio
n th
an o
nsu
rroun
ding
land
for
up to
1%
of t
heea
sem
ent.
Ther
e w
as e
vide
nce
ofex
tens
ive
eros
ion
onm
ore
than
1%
of t
heea
sem
ent.
3.
To p
rom
ote
and
mai
ntai
nve
geta
tion
cove
ron
the
RO
W.
3.1
To e
nsur
e th
atw
eeds
and
path
ogen
s ar
eco
ntro
lled
at a
leve
l tha
t is
atle
ast c
onsi
sten
tw
ith a
djac
ent
land
.
No
noxi
ous
wee
ds o
rpa
thog
ens
wer
eev
iden
t on
the
right
-of-
way
.
Ther
e w
ere
less
wee
ds a
nd p
atho
gens
than
on
adja
cent
land
.
The
pres
ence
of
wee
ds a
nd p
atho
gens
on th
e ea
sem
ent w
asco
nsis
tent
with
adja
cent
land
.
Wee
ds a
nd p
atho
gens
wer
e sl
ight
ly m
ore
abun
dant
than
on
adja
cent
land
.
Ther
e w
as a
gre
ater
abun
danc
e an
d di
vers
ityof
wee
d an
d pa
thog
ensp
ecie
s th
an o
n ad
jace
ntla
nd.
2001
PL
1 A
NN
UA
L R
EP
OR
T
-33-
Goa
l sig
nific
antly
exce
eded
Goa
l exc
eede
dG
oal a
chie
ved
Min
or s
hort
fall
Sign
ifica
nt s
hort
fall
Obj
ectiv
eG
oal p
aram
eter
+2+1
0-1
-2
3.2
To m
aint
ain
regr
owth
of
nativ
eve
geta
tion.
Rev
eget
atio
n w
asin
dist
ingu
isha
ble
from
the
surro
undi
ngs.
Spec
ies
abun
danc
ean
d di
strib
utio
n w
asco
nsis
tent
with
the
surro
undi
ngs.
Spec
ies
abun
danc
ean
d di
strib
utio
n in
such
are
as w
asco
nsis
tent
with
the
surro
undi
ngs.
Follo
w-u
p re
stor
atio
nw
ork
was
und
erta
ken
as n
eces
sary
.
75%
of s
peci
espr
esen
t in
surro
undi
ngar
eas
have
esta
blis
hed
and
cove
rw
as c
onsi
sten
t.
Som
e fo
llow
-up
rest
orat
ion
wor
k w
asun
derta
ken.
Less
than
75%
of s
peci
espr
esen
t in
surro
undi
ngar
eas
have
est
ablis
hed
and
cove
r was
less
than
adja
cent
land
.
No
follo
w-u
p re
stor
atio
nw
ork
was
und
erta
ken.
4.
To m
inim
ise
nois
e du
e to
oper
atio
ns
4.1
Ope
ratio
nsco
mpl
y w
ithno
ise
stan
dard
s.
Ope
ratio
nal a
ctiv
ities
com
ply
with
noi
sere
gula
tions
, und
er th
eEn
viro
nmen
tPr
otec
tion
Act 1
993.
No
com
plai
nts
wer
ere
ceiv
ed.
Ope
ratio
nal a
ctiv
ities
exce
ed n
oise
regu
latio
ns o
n on
e or
two
occa
sion
s pe
rye
ar.
Com
plai
nts
wer
ere
ceiv
ed.
Ope
ratio
ns fr
eque
ntly
exce
ed n
oise
regu
latio
ns.
Num
erou
s co
mpl
aint
sw
ere
filed
.
5.
To m
inim
ise
the
pote
ntia
l for
emis
sion
s th
atm
ay c
ause
publ
ic c
once
rn.
5.1
To e
nsur
e th
atun
cont
rolle
dem
issi
ons
are
repo
rted
and
acte
d up
onim
med
iate
ly.
Emis
sion
s w
ere
kept
to a
n ac
cept
able
leve
lfo
r the
life
of t
hepi
pelin
e. N
oco
mpl
aint
s w
ere
rece
ived
from
the
publ
ic
Emis
sion
s w
ere
repo
rted.
Com
plai
nts
from
the
publ
ic w
ere
acte
d up
onim
med
iate
ly.
Emis
sion
s w
ere
repo
rted
and
com
plai
nts
wer
e no
tac
ted
upon
.
6.
To m
inim
ise
the
risks
to p
ublic
heal
th a
ndsa
fety
.
6.1
To a
dequ
atel
ypr
otec
t pub
licsa
fety
dur
ing
norm
alop
erat
ion.
The
pipe
line
ease
men
tw
as c
lear
ly id
entif
ied
by s
igns
that
had
bee
nin
stal
led
in a
ccor
danc
ew
ith A
S288
5.
A co
mpr
ehen
sive
land
owne
r lia
ison
prog
ram
was
impl
emen
ted.
An E
mer
genc
yR
espo
nse
Plan
was
inpl
ace
and
staf
f wer
ead
equa
tely
trai
ned.
The
pipe
line
ease
men
tw
as c
lear
ly id
entif
iabl
efo
r mos
t of t
he ro
ute.
Mos
t lan
dow
ners
wer
eco
nsul
ted
on a
regu
lar
basi
s.
An E
mer
genc
yR
espo
nse
Plan
was
inpl
ace
and
som
e st
aff
wer
e tra
ined
.
The
pipe
line
ease
men
tw
as p
oorly
mar
ked
bysi
gns
and
diffi
cult
toid
entif
y fo
r mor
e th
an 5
0%of
the
ease
men
t.
No
land
owne
r lia
ison
was
cond
ucte
d.
No
Emer
genc
y R
espo
nse
Plan
was
in p
lace
.
2001
PL
1 A
NN
UA
L R
EP
OR
T
-34-
Goa
l sig
nific
antly
exce
eded
Goa
l exc
eede
dG
oal a
chie
ved
Min
or s
hort
fall
Sign
ifica
nt s
hort
fall
Obj
ectiv
eG
oal p
aram
eter
+2+1
0-1
-2
6.2
To a
dequ
atel
yre
duce
the
likel
ihoo
d of
fire
asso
ciat
ed w
ithpi
pelin
em
aint
enan
ceac
tiviti
es.
Fuel
load
on
the
ease
men
t was
cons
iste
nt w
ithad
jace
nt la
nd.
All o
pera
tions
pers
onne
l wer
e tra
ined
in fi
re s
afet
ypr
oced
ures
.
No
proj
ect r
elat
ed fi
res
have
occ
urre
d.
Fuel
load
on
the
ease
men
t gre
ater
than
on a
djac
ent l
and.
Som
e op
erat
ions
pers
onne
l wer
e tra
ined
in fi
re s
afet
ypr
oced
ures
.
No
proj
ect r
elat
ed fi
res
have
occ
urre
d.
Fuel
load
on
the
ease
men
t sig
nific
antly
grea
ter t
han
on a
djac
ent
land
.
No
oper
atio
ns p
erso
nnel
wer
e tra
ined
in fi
re s
afet
ypr
oced
ures
.
Proj
ect r
elat
ed fi
res
have
occu
rred.
6.3
To a
dequ
atel
ypr
otec
t pub
licsa
fety
dur
ing
mai
nten
ance
.
All a
ffect
ed a
ndad
jace
nt la
ndow
ners
wer
e ad
vise
d of
the
natu
re a
nd s
ched
ule
ofm
aint
enan
ce a
ctiv
ities
.
All p
oten
tially
haza
rdou
s ar
eas
wer
esi
gnpo
sted
or m
arke
dw
ith b
untin
g.
Adeq
uate
traf
ficm
anag
emen
t pra
ctic
esw
ere
impl
emen
ted.
Ther
e w
ere
no in
jurie
sor
nea
r mis
ses
invo
lvin
g th
e pu
blic
.
Mor
e th
an 7
5% o
f the
land
owne
rs w
ere
advi
sed
of th
e na
ture
and
sche
dule
of
mai
nten
ance
act
iviti
es.
Mos
t pot
entia
llyha
zard
ous
area
s w
ere
sign
post
ed o
r mar
ked
with
bun
ting.
No
spec
ific
traffi
cm
anag
emen
tpr
oced
ures
wer
e in
plac
e.
At le
ast o
ne n
ear m
iss
invo
lvin
g th
e pu
blic
occu
rred.
Less
than
75%
of t
hela
ndow
ners
wer
e ad
vise
dof
the
natu
re a
ndsc
hedu
le o
f mai
nten
ance
activ
ities
.
No
pote
ntia
lly h
azar
dous
area
s w
ere
sign
post
ed o
rm
arke
d w
ith b
untin
g.
No
spec
ific
traffi
cm
anag
emen
t pro
cedu
res
wer
e in
pla
ce.
At le
ast o
ne in
jury
invo
lvin
g th
e pu
blic
occu
rred.
2001 PL1 ANNUAL REPORT
-35-
ANNEX B
2001 PL1 ANNUAL REPORT
DATED APRIL 2002
ASSESSMENT OF DECLARED OBJECTIVES
2001
PL
1 A
NN
UA
L R
EP
OR
T
-36-
ASSE
SSME
NT O
F DE
CLAR
ED O
BJEC
TIVE
SO
BJE
CTI
VEG
OA
L(S)
ASS
ESSM
ENT
CO
MM
ENT
1.To
avo
id s
igni
fican
t dis
turb
ance
to la
ndus
e or
dam
age
to in
frast
ruct
ure.
1.1
To m
inim
ise
dist
urba
nce
to la
nd u
se a
ndda
mag
e to
infra
stru
ctur
e.-2
Seve
ral e
xcav
atio
ns w
ere
carri
ed o
ut o
nth
e rig
ht o
f way
to a
ccom
mod
ate
fore
ign
cros
sing
s an
d ne
w o
fftak
es.
2.To
pro
mot
e an
d m
aint
ain
soil
stab
ility.
2.1
To e
nsur
e th
ere
is n
o er
osio
n on
the
ease
men
t.-1
Ther
e w
as s
ome
evid
ence
of e
rosi
on,
prim
arily
in c
reek
bed
s.
3.To
pro
mot
e an
d m
aint
ain
vege
tatio
nco
ver o
n th
e R
OW
.3.
1To
ens
ure
that
wee
ds a
nd p
atho
gens
are
cont
rolle
d at
a le
vel t
hat i
s at
leas
tco
nsis
tent
with
adj
acen
t lan
d.
0Th
e pr
esen
ce o
f nox
ious
wee
ds o
rpa
thog
ens
on th
e rig
ht o
f way
was
cons
iste
nt w
ith th
e su
rroun
ding
envi
ronm
ent.
3.2
To m
aint
ain
regr
owth
of n
ativ
e ve
geta
tion.
+2R
eveg
etat
ion
was
indi
stin
guis
habl
e fro
mth
e su
rroun
ding
s.
4.To
min
imis
e no
ise
due
to o
pera
tions
.4.
1To
ens
ure
oper
atio
ns c
ompl
y w
ith n
oise
stan
dard
s.0
Ope
ratio
nal a
ctiv
ities
com
ply
with
noi
sere
gula
tions
, und
er th
e En
viro
nmen
tPr
otec
tion
Act 1
993.
No
com
plai
nts
wer
e re
ceiv
ed.
5.To
min
imis
e th
e po
tent
ial f
or e
mis
sion
sth
at m
ay c
ause
pub
lic c
once
rn.
5.1
To e
nsur
e co
ntro
lled
emis
sion
s ar
e re
porte
dan
d ac
ted
upon
imm
edia
tely
.-1
Inci
dent
s w
ere
repo
rted
and
rem
edia
lac
tion
was
und
erta
ken
prom
ptly
.
6.To
min
imis
e th
e ris
ks to
pub
lic h
ealth
and
safe
ty.
6.1
To a
dequ
atel
y pr
otec
t pub
lic s
afet
y du
ring
norm
al o
pera
tion.
0R
isk
asse
ssm
ent
repo
rt de
mon
stra
tes
that
the
pip
elin
e ris
ks a
re N
eglig
ible
,Lo
w o
r AL
ARP,
in a
ccor
danc
e w
ith A
S28
85.
6.2
To a
dequ
atel
y re
duce
the
likel
ihoo
d of
fire
asso
ciat
ed w
ith m
aint
enan
ce a
ctiv
ities
.0
Ris
k as
sess
men
t re
port
dem
onst
rate
sth
at t
he p
ipel
ine
risks
are
Neg
ligib
le,
Low
or
ALAR
P, in
acc
orda
nce
with
AS
2885
.
6.3
To a
dequ
atel
y pr
otec
t pub
lic s
afet
y du
ring
mai
nten
ance
.0
All m
aint
enan
ce a
ctiv
ities
wer
eco
nduc
ted
in a
con
trolle
d m
anne
r.
2001 PL1 ANNUAL REPORT
-37-
ANNEX C
2001 PL1 ANNUAL REPORT
DATED APRIL 2002
PIPELINE CATHODIC PROTECTION DATA AND ON/OFFPOTENTIALS PROFILES
2001 PL1 ANNUAL REPORT
-38-
Main Gas Line Full Line Surveys
500600700800900
100011001200130014001500
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Kilometres
mV
Feb 01 Sep 01