1st To, Shri Hardik Shah (Secretary) State Level Expert...
Transcript of 1st To, Shri Hardik Shah (Secretary) State Level Expert...
1st March, 2016
To,
Shri Hardik Shah (Secretary)
State Level Expert Appraisal Committee (Gujarat)
C/o. Gujarat Pollution Control Board,
Paryavaran Bhavan,
Sector-10 A, Gandhinagar – 382 010
Kind Att. : Mr. Hardik Shah (Secretary)
Subject : Submission of additional details for Environmental Clearance of
our proposed manufacturing unit.
Reference : Minutes of the 256th meeting of the State Level Expert Appraisal
Committee held on 16/09/2015
Dear Sir,
Regarding the above mentioned subject and reference we would like to submit here
the desired information. The point wise clarification and details are mentioned and
attached as an Annexure A. We have also enclosed all other supporting documents
for your kind perusal.
We hope the above details are adequate as per the requirements and looking to this
we request you to process our application at the earliest.
We shall be obliged for your above consideration and also assure you of our all
possible efforts for the prevention of pollution and preservation of environment.
Yours faithfully,
For, Ascent Pharma.
(Authorized Signatory)
Encl:
Annexure – A : Point wise Clarification for Additional details
Annexure – 1 : List of Industries in Nearby Area
Annexure – 2 : List of by products & agreement for sale
Annexure – 3 : Membership Certificate for TSDF_CHWIF
Annexure – 4 : Report on Treatability and Adequacy of ETP
Annexure – 5 : Soil Report
Annexure – 6 : Solvent Recovery
Annexure – 7 : Report on Risk and Safety Management
Annexure – 8 : Undertaking by the project proponent and consultant
Annexure – 9 : Project Summary & Conclusion as per the generic structure of
EIA notification
ANNEXURE- A
Point wise Clarification for Additional details
Annexure A
Point wise Clarification for Additional details
1. Reasons for higher concentration of PM10
Reasons for higher concentration of PM
at project site, Ribda and Pipaliya
Pal Village in Baseline study of EIA report.
10
• The proposed project will be carried out in existing industrial premises
located in the Shapar-Veraval Industrial area, which is well-developed
industrial area comprises of more than 80 industries (List of the industries
of nearby area is enclosed as Annexure-1), which are mainly
pharmaceutical, chemical, cement industries,foundries etc. Therefore,
surrounding industrialization is the main reasonfor higher PM
at project site and villagesRibda
and Pipailya Pal are as follows,
10
• Ribda and Pipaliya Pal villages are located in the predominant down-wind
direction from project site as well as fromShapar-Veraval Industrial area.
concentration at project site.
Villages Distance (Km)
Shapar-VeravalIndustrial Area
Project Site
Ribda 0.92 2.67
Pipaliya Pal 4.55 6.27
• Also, Ribda and Pipaliya Pal village are in proximity of NH-8B by 20 m &
100 m respectively, where heavy traffic load is expected during the peak
hours.
2. Characteristics of by products, feasibility of their actual use as raw
material, management plan for By-products to be generated, along with the
name and address of end consumers to whom the by-product/s will be sold.
Copies of agreement / MoU / letter of intent fromthem, showing their
willingness to purchase said by-product/s from the proposed project.
Byproducts generated from the proposed project are Hydrochloric Acid,
Sodium Bisulphite and Phosphorus Acid. All the byproducts are readily
salable in the market.
Details of source of generation,characteristics and end use along with
agreement by end-users for their willingness to purchase byproducts are
enclosed in Annexure-2.
3. Copy of valid membership certificate for Common TSDF/CHWIF.
Membership certificate for common TSDF/CHWIF is given as Annexure-3.
4. Complete details about the characteristics and treatability of the effluent
with mode of disposal. A detailed treatability study vis-à-vis the adequacy
and efficacy of the treatment facilities proposed for the wastewater to be
generated. Give stage wise reduction in important parameters.
There will be no effluent generation from manufacturing process. However,
condensate water generated from process @ 0.4 KLD will be reused for
cooling make up.
Effluent generated from APCE, Cooling, Boiler and Washing @1.7 KLD will
treated in ETP comprising of primary, secondary and tertiary units andtreated
wastewater will be reused for greenbelt development. A detailed treatability
study report is enclosed as Annexure-4.
5. Submit the Soil analysis report of the proposed site. Soil analysis report of
proposed project location at different places covering response level of
contaminants including heavy metals. Ensure that there is no threat to
ground water quality by leaching of heavy metals and other toxic
contaminants.
There will not be any heavy metals and toxic raw materials used for
manufacturing of proposed products. Also, there will be no effluent generation
from proposed manufacturing process. Condensate water generated from
process will be reused for cooling. Therefore, treated wastewater from ETP,
used for greenbelt development, will not pose any threat to soil quality and
ground water contamination. Detailed Soil analysis report is enclosed as
Annexure-5.
6. Treated effluent management plan during monsoon season when utilization
of treated effluent for gardening & plantation purpose is not feasible.
Detailed study report considering Percolation rate of the land available for
gardening &plantation. Ensure that land is suitable for utilization of treated
sewage for plantation & gardening.
As stated above, there will be no effluent generation from manufacturing
process and condensate generated from process will be reused for cooling
make up. Treated effluent from ETP will be utilized for gardening & plantation
purpose.
In reference to the treatability study, existing ETP will be adequate to achieve
the discharge norms prescribed by GPCB. In addition, it is proposed to
provide 5 KL capacity of treated effluent collection tank, which will be
sufficient to store effluent up to 4 days in monsoon season.
Percolation test was carried out site and detailed soil report with the finding of
test carried out is enclosed here as Annexure-5.Percolation test results show
that soil is having high water holding capacity and moderate permeability
(97.5 mm/hr). However considering the effluent generation, greenbelt area
proposed will be more than required allowing water to percolate effectively to
avoid any water logging. Also the total water requirement for the greenbelt
development will be almost double then the wastewater generation from the
proposed project.
7. Name and quantity of each type of solvents to be used for proposed
production. Details of solvent recovery system including mass balance,
solvent loss, recovery efficiency feasibility of reusing the recovered
solvents etc. for each type of solvent. Ensure that Solvent recovery shall
not be less than 95 percent in any case. The unit intends to use various solvents like Mono Chloro Benzene, Acetone,
Methanol and Xylene. The spent solvent generated during the manufacturing
process will be separated and recovered up to 95% on average by two stage
distillation and reused in the process.
Details of solvent requirements & recovery system including measures for
achieving maximum solvent recovery are enclosed in Annexure-6.
During the distillation of spent solvent impurities will be removed along with
distillation residue and recovered solvent will be of 99.9% purity. Further each
lot of solvent will be tested and validate for further use as per Schedule M
Good Manufacturing Practices notified by Ministry Of Health And Family
Welfare, New Delhi. Therefore, it will be feasible to reuse recovered solvent
for the manufacturing.
8. Risk assessment including prediction of the worst-case scenario and
maximum credible accident scenarios should be carried out. The worst-
case scenario should take into account the maximum inventory of storage
at site at any point of time. The risk contours should be plotted on the map
clearly showing which of the facilities and surrounding units would be
affected in case of an accident taking place. Based on the same, proposed
safeguard measures including On-Site / Off-Site Emergency Plan should be
provided. There are total 17 chemicals proposed to use as a raw materials in the
manufacturing. Out of which, 5 nos. of raw materials are solid and non-
hazardous in nature. Out of remaining 12 hazardous chemicals, risk
assessment has been submitted along with EIA report for two of the major
hazardous chemicals considering worst-case scenario and maximum credible
accident scenarios. However, as per your requirement, we have carried out
MCA analysis for additional 9 hazardous chemicals. Detailed risk assessment
report including On-site / Off-site Emergency Plan is enclosed as Annexure-
7.
9. Records of any legal breach of Environmental laws i.e. details of show-
cause notices, closure notices etc. served by the GPCB to the existing unit
in last three years and actions taken then after for prevention of pollution.
There are no instances of any legal breach of Environmental laws in the past.
Unit has maintained full compliance for all the conditionals stipulated in the
CTE and CCA for existing unit and will maintain the same for proposed
expansion.
10. An undertaking by the Project Proponent on the ownership of the EIA
report as per the MoEF&CC OM dated 05/10/2011 and an undertaking by the
Consultant regarding the prescribed TORs have been complied with and
the data submitted is factually correct as per the MoEF&CC OM dated
04/08/2009.
Undertaking by the project proponent and consultant are given in Annexure-8.
11. Summary & Conclusion as per the generic structure given in Appendix III A
of the EIA Notification 2006.
Summary and conclusion as per the generic structure of EIA notification is
enclosed in Annexure-9
Page 1 of 3
Annexure- 1
LIST OF INDUSTRIES IN NEARBY AREA
Sr. No.
Name of Industry Type of Industry
1. Orchev Pharma Pvt. Ltd. Pharmaceutical
2. Endoc Lifecare Pvt. Ltd. Pharmaceutical
3. Espee Formulation Pvt. Ltd. Pharmaceutical
4. SNJ Labs Pvt. Ltd. Pharmaceutical
5. Creative Pharma Industries Pharmaceutical
6. Adani Pharmachem Pvt. Ltd. Pharmaceutical
7. Jagdish Chemicals Chemicals
8. Lamberty Hydro colloid Pvt. Ltd. Chemicals
9. Solgel Film Pvt. Ltd. Chemicals
10. Magpie Chemicals Chemicals
11. Patidar Silica Pvt. Ltd Chemicals
12. Revlovne Industries Chemicals
13. Shree Sadguru Chemicals Industries Chemicals
14. Gold Coin Foam Pvt. Ltd. Chemicals
15. Balaji Laminates Laminate Sheets
16. Decora Laminates Laminate Sheets
17. Vision Laminates Laminate Sheets
18. Advance Laminates Laminate Sheets
19. Decora Coatings Pvt. Ltd. Paints
20. Ideal Paints Paints
21. Kohinoor Paints Paints
22. Shree Krishna Biotech Pvt. Ltd. Agriculture
23. Everest Fertilizer & Chemicals Pvt. ltd. Agriculture
24. Ganesh Bio Control System Agriculture
25. Champion Agro Ltd. Agriculture
26. Ascent Crop Science Agriculture
27. Parmatma Enterprise Agriculture
28. Decora Cement Pvt. Ltd. Cement
29. Dhanraj Cement Pvt. Ltd Cement
30. Kishan Cement Pvt. Ltd. Cement
31. Major Cement Pvt. Ltd Cement
32. Marshal Cement Industries Cement
33. New Kishan Cement Pvt. Ltd Cement
Page 2 of 3
Sr. No.
Name of Industry Type of Industry
34. New Tech Cement Pvt. Ltd. Cement
35. Patel Cement Pvt. Ltd. Cement
36. Swastik Industries Cement
37. Rishi Cast Pvt. Ltd Casting- Foundry
38. Rajan Techno Cast Pvt. Ltd. Casting- Foundry
39. Jagdish Technocast Pvt. Ltd Casting- Foundry
40. Gravity Cast Pvt. Ltd. Casting- Foundry
41. Inovative Techno Cast Pvt. Ltd. Casting- Foundry
42. Rajeshwary Alloy Casting Casting- Foundry
43. Sanjivani Casting Pvt. Ltd Casting- Foundry
44. Gujarat Alloy Cast Pvt. Ltd. Casting- Foundry
45. Shree Rudra Techno Cast Pvt. Ltd. Casting- Foundry
46. Sumangal Casting Pvt. Ltd. Casting- Foundry
47. Wellmake Technocast Pvt. LTd. Casting- Foundry
48. AllwaysTechnocast Pvt. Ltd. Casting- Foundry
49. Uni Tech Casting Casting- Foundry
50. SanduriTechnocast Casting- Foundry
51. Plasma Alloys Pvt. Ltd. Casting- Foundry
52. Precision Technocast Pvt. Ltd. Casting- Foundry
53. Nova Technocast Pvt. Ltd. Casting- Foundry
54. Jay Gayatri Icecream / Dairy Pro Food & Beverages
55. Best Agro Foods Pvt. Ltd. Food & Beverages
56. Empire Floor Mills Pvt. Ltd. Food & Beverages
57. Ganga Agro Food Industries Food & Beverages
58. Max Health Foods & Beverages Co. Food & Beverages
59. Galaxy Cotton & Textile Pvt. Ltd Cotton Ginning Mill
60. Jaydeep Cotton Fibers Pvt. Ltd Cotton Ginning Mill
61. AvadhCotex Pvt. Ltd. Cotton Ginning Mill
62. Amit Cotton Industries Cotton Ginning Mill
63. Madhav Cotton Industries Cotton Ginning Mill
64. Casco International Valve
65. Kishan Soap Factory Soap Detergent & Oil Soap
66. Galaxy Soaps Soap Detergent & Oil Soap
67. Fishfa Rubbers Pvt. Ltd Rubber Product
68. Diamond Rubber Industries Rubber Product
69. Sapphire Reclaim Rubber Pvt. Ltd Rubber Product
Page 3 of 3
Sr. No.
Name of Industry Type of Industry
70. P.S. Plywood Products Pvt. Ltd. Plywood Manufacturers
71. Ajanta Plastic Plastic & Packaging
72. Alidhra Packaging Plastic & Packaging
73. AnupamPlastoEngg Pvt. Ltd. Plastic & Packaging
74. Essen Polybags PVT. Ltd. Plastic & Packaging
75. Rubi Plastics Plastic & Packaging
76. BalsonPolyplast Pvt. Ltd. Pipe & Pipe Fittings
77. Captain Polyplast Limited Pipe & Pipe Fittings
78. Godavari Pipes Pvt. Ltd. Pipe & Pipe Fittings
79. Kaveri Polymers Pvt. Ltd. Pipe & Pipe Fittings
80. Narmada Pipes Pipe & Pipe Fittings
81. Om Irrigation Pipe & Pipe Fittings
82. Jaydeep Oxygen Pvt. Ltd. Gases
83. Tirupati Oxygen Pvt. Ltd. Gases
84. MalwinPharma Pvt. Ltd. (Hadmtala) Pharmaceutical
85. Sam Fine Chem Ltd. (Hadmtala) Pharmaceutical
Page 1 of 3
Annexure-2
DETAILS OF PROPOSED BY-PRODUCTS & CHARACTERISTICS
Sr. No.
Name of By-Product
Quantity (TPM)
Source Characteristic End Use
1. Hydrochloric
Acid (30%) 15.5
APCE-
Oxyclozanide
HCl: 25 %
Water: 75 %
Manufacturing of
Colloidal Silica
2. Sodium Bi-
Sulphite (25%) 26.0
APCE-
Oxyclozanide
NaHSO3Manufacturing of
Sodium Bi-Sulphite
: 25%
NaOH: 1 %
Water: 74 %
3. Phosphorous
Acid Aq.(54%) 3.3
Oxyclozanide
(Route-2; using
PCL3-Stage-I)
H3PO3Manufacturing of DAP
Fertilizer.
: 54 %
Water: 43.95 %
Impurities:0.05 %
Page 2 of 3
AGREEMENT FOR PURCHASE OF BYPRODUCTS FROM END-USERS
Page 3 of 3
Page 1 of 1
Annexure-3
MEMBERSHIP CERTIFICATE FOR COMMON TSDF/CHWIF
ANNEXURE- 4
Report on Treatability and Adequacy of ETP
Report on Treatability Study and Adequacy of ETP
Proposed By,
Ascent Pharma Survey No. 163/9, Nr. Chintan Gas Godown, S. I. D. C. Road,Veraval,
(Shapar)- 360024. Ta: Kotada Sangani, Dist: Rajkot (Guj.). India.
Prepared By:
(QCI-NABET ACCREDITED EIA CONSULTANT
3)
rd
Nr. Parimal Underpass, Paldi, AHMEDABAD-380 007, Gujarat. Floor, Akashganga Complex, B/s. Suvidha Shopping Centre,
Telefax: (079) 2665 0473, 2665 0878; E-mail: [email protected]
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page i
LIST OF CONTENTS
SR. NO. TITLE PAGE
NO.
1.0 Introduction 1
2.0 Aim of Study 1
3.0 Characteristics of Raw Effluent 2
4.0 Treatability Study- Physico Chemical Treatment 2
4.1 Methodology 2
4.2 Details Of Attempts 3
4.3 Summary of Analysis Results 3
4.4 % Reduction Obtained 3
4.5 Details Of Chemical Dosing 4
4.6 Rate of Chemical Dosing 4
5.0 Treatability Study- Biological Treatment 5
6.0 Treatability Study – Tertiary Treatment 6
7.0 Conclusion Of Treatability Study 7
8.0 Design Considerations 7
8.1 Introduction 7
8.2 Design Criteria 8
8.2 [A] Proposed Effluent Treatment Scheme 8
8.2 [B] Details of Proposed Effluent Treatment Units 10
8.2 [C] Schematic Flow Diagram of Proposed Effluent Treatment Plant
11
9.0 Conclusion 11
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page ii
LIST OF TABLES
SR. NO.
TITLE PAGE NO.
Table 1 Characteristics of Composite Effluent 2
Table 2 Details of Attempts 3
Table 3 Summary of Attempts & Results 3
Table 4 Results of % Reduction 3
Table 5 Details of Chemical Dosing 4
Table 6 Rate of Chemical Dosing 4
Table 7 Characteristic of Primary Treated Effluent 5
Table 8 General Details of Study 5
Table 9 Summary of Analysis Results 6
Table 10 Analysis Results after Tertiary Treatment 6
Table 11 Expected Characteristics of Effluent (Stage wise) 7
Table 12(a) Stage wise % Reduction 8
Table 12(b) Cumulative % Reduction 8
Table 13 Design Criteria for Effluent Treatment Scheme 8
Table 14 Hydraulic Flow rate for proposed ETP 10
Table 15 Details of Effluent Treatment Units 10
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 1 of 12
1.0 INTRODUCTION
M/s. Ascent Pharma is an existing small scale unit located at Survey No. 163/9 & 11
on S.I.D.C. Road in Shapar-Veraval Industrial Area of Village Veraval (Shapar) in
Kotada Sangani Taluka of Rajkot District in Gujarat state. At present the unit is
manufacturing various Inorganic Chemicals with the total production capacity of 50
TPM. Now, considering the market demand, the unit intends to manufacture various
Bulk Drugs & Drugs Intermediates (Synthetic Organic Chemicals) with total
production capacity of 55 TPM within the existing premises by utilizing existing
infrastructure facilities with the addition of new machineries. The unit has already
applied for Environmental Clearance and obtained additional ToR from SEAC,
Gujarat.
For detailed treatability study for the effluent, proposed unit has appointed M/s.
Envisafe Environment Consultants, Ahmedabad. The sample of the composite raw
effluent from different streams has been collected and submitted by Ascent Pharma
for the lab scale treatability study.
2.0 AIM OF STUDY
The aim of the treatability study is to find out feasibility of effluent treatment for the
proposed unit to achieve quality as per GPCB norms and to design the adequate
treatment scheme for the proposed effluent generation. GPCB norms are given
below.
pH : 6.5 –8.5
TSS : ≤ 100 mg/L
TDS : ≤2100 mg/L
COD : ≤100 mg/L
BOD : ≤30 mg/L
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 2 of 12
3.0 CHARACTERISTICS OF RAW EFFLUENT
The industrial water consumption will be for Process, Boiler, Washing and Cooling.
The major quantity of wastewater generation will be from APCE, Boiler, Washing and
cooling make up. The composite sample of wastewater stream likely to be at the inlet
of the ETP coming from all section of the plant area is synthesized for lab scale
treatability study. The characteristic of composite raw effluent is given in Table-1.
Table-1: Characteristics of Composite Effluent
Sr. No. Parameters Unit Concentration
1. pH -- 8.5
2. Total Suspended Solid (TSS) mg/L 210
3. Total Dissolved Solid (TDS) mg/L 1250
4. Chemical Oxygen Demand (COD) mg/L 665
5. Biological Oxygen Demand (BOD) mg/L 208
4.0 TREATABILITY STUDY- PHYSICO CHEMICAL TREATMENT
4.1 Methodology
The composite sample was undertaken for the laboratory scale treatability study.
Based on treatment scheme adopted, it was decided to give the effluent Physico
Chemical treatment followed by Biological treatment and Tertiary treatment.
One liter of composite effluent sample was taken into four different beakers and
placed on jar test apparatus.
First, hydrated lime was added into the effluent to neutralize the effluent and
then to raise the pH up to 9.5 - 10.0. Then, inorganic flocculating chemical Alum
or Ferrous Sulfate or Hydrogen Peroxide(H2O2)was added to lower the pH up to
7.0 - 7.5. The addition of PAC powder and Polyelectrolyte was also tried to
accelerate the flocculation and coagulation.
After addition of each treatment chemicals rapid mixing for one minute at 100
RPM was carried out. Then after the addition of all chemicals, slow mixing at 20
RPM for a period of 20.0 minutes was done to facilitate flock formation.
Uniformly mixed and flocculated effluent sample was allowed to settle for 30
minutes and then clear supernatant effluent was taken for analysis.
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 3 of 12
4.2 Details of Attempts
Various attempts were carried out in physicochemical treatment by addition of
various chemicals with different dosage to know the optimum dosing and pollution
reduction. COD & BOD reduction in each attempt during the study is focused. The
details of attempts in first stage are given in Table-2.
Table-2: Details of Attempts
Attempt No. Details
I. : Addition of Lime and Alum
II. : Addition of Lime, FeSO4 and H2O2
III. : Addition of Lime and PAC
IV. : Addition of Lime, Alum and Poly Electrolyte
4.3 Summary of Analysis Results
The Parameters like pH, COD, BOD were analyzed during study in each attempt and
result of all the parameters are summarized in Table-3.
Table-3: Summary of Attempts and results
Sr. No. Parameters Concentration
I II III IV
1. pH 7.2 7.2 7.3 7.1
2. COD 472 518 484 297
3. BOD 165 180 178 97
All parameters are expressed in mg/L except pH
4.4 % Reduction Obtained
The Percentage reduction has been worked out by comparing all the results with raw
effluent for COD, BOD and pH which is given in Table–4.
Table-4: Results of % Reduction
Sr. No. Parameters I II III IV
1. COD 29.0 22.1 27.2 55.3
2. BOD 20.7 13.5 14.4 53.4
From the above table, it can be concluded that maximum % reduction can be
obtained from Attempt–IV and it is the optimum dosing scheme for the primary
treatment.
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 4 of 12
4.5 Details of Chemical Dosing
The desired solution was made for all the chemicals viz. Hydrated Lime, Alum,
Polyelectrolyte, Hydrogen Peroxide (H2O2), PAC Powder and Ferrous Sulphate
(FeSO4).Various trials were conducted by addition of treatment chemical with
different dosage for physicochemical study during treatability study.The details of
chemical dosing in each attempt of first stage are given in Table-5.
Table-5: Details of chemical dosing
Sr. No.
Name of Solution Concentration,
%
Chemical dosing in ml for one liter of effluent
I II III IV
1. Alum 10 1.60 0.00 0.00 1.60
2. Hydrated Lime 10 2.10 2.50 2.10 2.10
3. Polyelectrolyte 0.1 0.00 0.00 0.00 2.20
4. PAC Powder/ Liquid 5 0.00 0.00 1.20 0.00
5. FeSO4 10 0.00 3.10 0.00 0.00
6. H2O2 30 0.00 1.20 0.00 0.00
4.6 Rate of Chemical Dosing
From the solution used for the study and dosing of solution as listed in above table
rate of chemical dosing in mg per liter of effluent has been work out in first stage
which is given in Table-6.
Table-6: Rate of chemical dosing
Sr. No. Name of Chemical Chemical dosing in mg/L of effluent
I II III IV
1. Alum 160.00 0.00 0.00 160.00
2. Hydrated Lime 210.00 250.00 210.00 210.00
3. Polyelectrolyte 0.00 0.00 0.00 2.20
4. PAC Powder/ Liquid 0.00 0.00 60.00 0.00
5. FeSO4 0.00 310.00 0.00 0.00
6. H2O2 0.00 360.00 0.00 0.00
TOTAL 370.00 920.00 270.00 372.00
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 5 of 12
5.0 TREATABILITY STUDY – BIOLOGICAL TREATMENT
To carry out biodegradability study, the effluent sample of about 20.0 Liter was
prepared in laboratory by giving physicochemical treatment, as per Trial-IV, to the
raw composite sample of industrial effluent. The characteristics of primary treated
effluent taken for further biological study is given in Table–7.
Table-7: Characteristics of Primary Treated Effluent
Sr. No. Parameters Unit Concentration
1. pH -- 7.1
2. Chemical Oxygen Demand (COD) mg/L 297
3. Biochemical Oxygen Demand (BOD3 at 270 mg/L C) 97
For the lab scale biological treatability study, 10.0 Liter of primary treated sample was
taken in a laboratory scale acrylic aeration tank and mixed with the adequate quantity
of active biomass, obtained from similar type of industry. Nutrients like Urea and DAP
were also added as per requirement in to the aeration tank.
Oxygen required for the biological activity was supplied by means of aquarium type
aerators and lab scale membrane diffuser to maintain desired level of Dissolved
Oxygen throughout study. The sample from container was collected after several
detention times and analyzed to find out the concentration of COD and BOD. The
general detail of study is given in Table-8.
Table–8: General Details of Study
Sr. No.
Particular Unit Value
1. Sample Taken Liter 10.0
2. Air Supplied CFSTR, Conventional Aeration: 1 kg COD = 1.0 Lit.
Liter/min 1.53
3. MLVSS Level mg/L 2500
The summary of analysis results for the Biological treatment and % reduction
obtained is summarized in Table-9.
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 6 of 12
Table-9: Summary of Analysis Results
HRT in AT, Hrs.
Concentration, mg/L % Reduction
COD BOD COD BOD
0 297 97 0.0 0.0
10 271 84 8.8 13.4
12 245 73 17.5 24.7
18 190 57 36.0 41.2
24 130 39 56.2 59.8
30 102 28 68.0 71.1
36 86 26 71.0 73.2
42 78 24 73.7 75.3
48 72 23 75.8 76.3
From the above table, it can be concluded that optimum reduction can be obtained
for the retention time of 36 hrs in the biological treatment.
6.0 TREATABILITY STUDY - TERTIARY TREATMENT
The supernatant obtained after the end of aeration of 66 hrs from biological treatment
is passed through Sand & Carbon filter on the laboratory scale. Then finally tertiary
treated effluent is taken and analyzed. The details Analysis Result is given here
under in Table- 10.
Table-10: Analysis Result after Tertiary Treatment
Sr. No. Parameters Unit
Concentration %
Reduction Secondary Outlet
Tertiary Outlet
1. COD mg/L 86 78 9.3
2. BODat27 0 mg/L C 26 24 7.7
From the above mentioned table it can be seen that all parameters of finally treated
effluent is well within the limit prescribed by GPCB for disposal in undergraound
drainage system.Thus primary treatment, biological treatment followed by tertiary
treatment is the most optimum line of treatment to treat the industrial effluent likely to
be generated from the unit.
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 7 of 12
7.0 CONCLUSION OF TREATABILITY STUDY
Physico Chemical Treatment
• From Table-4, it can be seen that the percentage organic removal in Attempt-IV
is highest. Finally, it can be concluded that Attempt-IV with addition of Lime,
Alum and Poly Electrolyte shall be adopted for the Physico-Chemical
treatment.
Biological Treatment
• The treatability study shows that the wastewater under consideration is having
biodegradability characteristics. With 36Hours of aeration at 2500mg/L MLVSS,
the maximum COD and BOD removal is obtained of @ 71% and 73.2%
respectively.
Tertiary Treatment
• The treatability study shows that the wastewater passed through Pressure Sand
Filter and Activated Carbon Filter, the maximum COD and BOD removal is
obtained by 9.3% and 7.7% respectively.
8.0 DESIGN CONSIDERATIONS
8.1 Introduction
Looking to the above treatability study, the unit is suggested to give physico-
chemical, biological treatment and tertiary treatment to meet the GPCB Norms. For
the design purpose, hydraulic load of the effluent taken is 2 KL/Day and the COD
concentration in the raw effluent taken is 665 mg/lit considering the shock loading if
any. The expected characteristics of effluent after each stage of treatment are given
in Table–11 and % reduction after each stage of treatment and cumulative %
reduction is given in Table-12(a) & 12(b).
Table-11: Expected Characteristics of Effluent (Stage wise)
Sr. No.
Parameter Unit Composite
Effluent Primary Outlet
Secondary Outlet
Tertiary Outlet
1. COD mg/L 665 297 86 78
2. BOD mg/L 208 97 26 24
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 8 of 12
Table-12(a): Stage wise % Reduction
Sr. No.
Parameter % Reduction
Primary Outlet
Secondary Outlet
Tertiary Outlet
Overall
1. COD 55.34 71.04 9.30 88.27
2. BOD 53.37 73.20 7.69 88.46
Table–12(b): Cumulative % Reduction
Sr. No.
Parameter % Reduction
Primary Outlet
Secondary Outlet
Tertiary Outlet
Overall
1. COD 55.34 87.07 88.27 88.27
2. BOD 53.37 87.50 88.46 88.46
8.2 Design Criteria
Based on the results of the Treatability study and the theoretical assumptions for the
design of ETP units, the basic design criteria were finalized for the proposed effluent
treatment scheme which would to be most adequate to achieve desired norms of
GPCB for discharge of treated effluent. These design criteria are listed in Table–13.
Table–13: Design Criteria for Effluent Treatment Scheme
A Primary Units
1. Collection Cum Equalization Tank : Retention Time: 8 Hours
2. Primary Settling Tank (Hopper Bottom) : Retention Time: 4.0 Hours, SOR:30 m3/m2/Day
B Secondary Units
3. Aeration Tank : Retention Time: 36Hours MLVSS: 2500 mg/L
4. Secondary Settling Tank (Hopper Bottom)
: Retention Time: 4.0 Hours, SOR:12.0 m3/m2/Day
[A] Effluent Treatment Scheme:
The wastewater shall be treated in the following stages:
Collection cum Treatment tank
The wastewater generated from APCE, Boiler, Washing and Cooling will be collected
in the collection tank. Here, effluent will be thoroughly mixed with constant supply of
compressed air through grid aeration pipeline.
Chemical Dosing Tank
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 9 of 12
The chemical dosing tanks are provided for the preparation of chemical solution
required for the physicochemical treatment such as hydrated lime and alum.
Primary Hopper Bottom Settling Tank
The effluent from flocculation tank will be led to Primary Settling Tank. Here the
effluent will be retained for the certain period in a relatively quiescent state. Thus,
chemical flocs having higher specific gravity then the liquid tends to settle to the tank
bottom. The settled sludge at the bottom will be transferred into the sludge drying
bed. The clear supernatant effluent from tank overflow will be taken for the further
treatment.
Aeration Tank
After the primary settling tank, effluent will be taken to the aeration tank. The fix
microbial culture will be developed and maintained by recirculating the active
biomass form the secondary clarifier. The microbes oxidize the organic matter
present into the wastewater and use it as a food and form their own cell mass. Thus
the organic load present in the wastewater in the form of BOD & COD will be
converted in to simple products as CO2 and H2O. The oxygen required for bacterial
growth will be supplied by blowers through means of aeration grid at the bottom of
the aeration tank. The wastewater overflow from aeration tank will be taken to the
secondary settling tank.
Secondary Settling Tank
The mix liquor from aeration tank will be carried to the Secondary settling tank and
retained for the certain period in a relatively quiescent state. Thus microbial mass
having higher specific gravity than the liquid tends to settle to the bottom. The part of
biological sludge settled in to the tank hopper will be recycled to the aeration tank to
maintain desired level of microbial population and excess sludge is drained to the
sludge drying bed. The clear supernatant effluent will be sent for Tertiary treatment.
Sludge Handling
Sludge drained from Primary and Secondary settling tank will be transferred to
sludge drying bed for further treatment. Leachate from sludge drying bed will be
recycled back into collection cum treatment tank. Remaining sludge will be
transferred to designated hazardous waste storage area for safe disposal to TSDF
site.
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 10 of 12
Pressure Sand Filter
The treated wastewater is pumped from the tertiary treatment tank through the
pressure sand filter to remove excess suspended solids. Pressure sand filter is
cleaned periodically to remove accumulated solids. This is done by backwashing the
filter using fresh water in reverse flow sequence. The backwash water flows back to
collection cum equalization tank for treatment.
Activated Carbon Filter
The effluent from the outlet of pressure sand filter is passed through activated
carbon filter where final polishing of the effluent is done to reduce the suspended
solids, colour, odor and other organic impurities. Activated carbon filter is cleaned
periodically to remove accumulated solids. This is done by backwashing the filter
using fresh water in reverse flow sequence. The backwash water flows back to
collection cum neutralization tank for treatment.
[B] Details of proposed Effluent Treatment Units:
The details of proposed effluent treatment plant will be adequate to treat wastewater
generation @ 2.0 KL/day is given in Table-14 and Table-15.
Table-14: Hydraulic flow rate for proposed ETP
Treatment Units Primary
Settling Tank Aeration
Tank Secondary
Settling Tank
Actual Flow rate KL/Day 1.7 1.7 1.7
Design Flow Rate, KL/Day 2.0 2.0 2.0
Operation, Hrs 8 24 8
Design Flow Rate, KL/Hour 0.25 0.083 0.25
Table–15: Details of Effluent Treatment Units
Sr. No.
Units
No
s.
Len
gth
,
m
Wid
th,
m
Liq
uid
Dep
th, m
Liq
uid
Vo
lum
e, m
3
Rete
nti
on
Tim
e, h
rs
Remarks
1. Collection cum Treatment Tank
2 1.10 1.10 1.70 4.11 16.46 --
2. Lime Solution Tank 1 0.75 0.75 0.75 0.42 - --
3. Alum Solution Tank 1 0.75 0.75 0.75 0.42 - --
4. Polyelectrolyte Solution Tank
1 50 Liter 0.05 - --
5. Flocculation Channel 1 1.10 0.50 0.50 0.28 1.10 --
6. Primary Settling Tank (Hopper Bottom)
1 1.00 1.00 2.00 2.00 8.0 SOR = 6 m
3/m
2/hr
(Adequate)
7. Aeration Tank 1 1.50 1.50 2.50 5.63 67.50 MLVSS = 2500 mg/L
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 11 of 12
Sr. No.
Units
No
s.
Len
gth
,
m
Wid
th,
m
Liq
uid
Dep
th, m
Liq
uid
Vo
lum
e, m
3
Rete
nti
on
Tim
e, h
rs
Remarks
(Adequate)
8. Secondary Settling Tank (Hopper Bottom)
1 1.20 1.20 2.00 2.88 11.52 SOR = 4.17 m
3/m
2/hr
(Adequate)
9. Treated Water Collection Tank - 1
1 1.10 1.10 1.70 2.06 8.23 --
10. Treated Water Collection Tank - 2
1 5.0 KL HDPE 20 Proposed Tank
11. Pressure Sand Filter 1 0.3 Dia. X 1.5 HOS --
12. Activated Carbon Filter 1 0.3 Dia. X 1.5 HOS --
13. Sludge Drying Beds 2 1.00 1.00 0.50 1.00 -- --
[C] Schematic diagram of proposed Effluent Treatment Plant
Treatability and Adequacy of ETP Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 12 of 12
9.0 CONCLUSION:
From the above treatability study, it can be seen that the required retention time for
Primary Settling Tank is 4 hrs, for Aeration Tank is 36 hrs and for Secondary Settling
Tank it is 4 hrs. However, the unit has provided retention time of 8 hrs for Primary
Settling Tank, 67.5 hrs for the aeration tank and 11.5 hrs for the Secondary Settling
Tank, which is more than adequate.
In addition to this, the required SOR for primary settling tank is 30 m3/m2/d and for
Secondary Settling Tank it is 12 m3/m2/d. However, the unit has provided SOR of 6
m3/m2/d to the Primary Settling Tank and of 4.17 m3/m2/d to the Secondary Settling
Tank, which is adequate than the desired one.
Treated water collection tank of 5 KL capacity has been proposed in addition to
existing 2 KL treated water collection tank. It will be sufficient enough for storage of
treated water up to 4 days in case if it cannot be utilized for gardening purpose
during monsoon season.
Hence, the existing ETP along with additional treated water collection tank will
be adequate to the handle the total effluent load after proposed expansion and
achieve the desired norms of final discharge.
ANNEXURE- 5
Soil Report
Soil Report
Proposed By, Ascent Pharma Survey No. 163/9, Nr. Chintan Gas Godown, S. I. D. C. Road,Veraval (Shapar)- 360024. Ta: Kotada Sangani, Dist: Rajkot (Guj.). India.
(QCI-NABET ACCREDITED EIA CONSULTANT3rd Floor, Akashganga Complex, B/s. Suvidha Shopping Centre,Nr. Parimal Underpass, Paldi, AHMEDABAD-380 007, Gujarat.Telefax: (079) 2665 0473, 2665 0878; E-mail: [email protected]
)
Prepared By,
Soil Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page i
LIST OF CONTENTS
SR. NO. TITLE PAGE NO.
1.0 Background 1
2.0 Objective 1
3.0 Soil 3
3.1 Logging of soil strata 3
3.2 Soil type in Rajkot District 3
3.3 Physico-Chemical Analysis of Soil 4
3.4 Percolation Test 5
4.0 Ground Water Quality at Project Site 7
5.0 Major Findings 7
6.0 Conclusion and Mitigation Measures 9
LIST OF TABLES
TABLE NO.
TITLE PAGE NO.
Table 1 Physico- Chemical characteristics of soil 4
Table 2 Percolation Test at different Trail Pit 6
LIST OF FIGURES
FIGURE NO.
TITLE PAGE NO.
Figure 1 Location Map of the project site 2
Figure 2 Geological map of Gujarat 3
Figure 3 Soil Map of Gujarat 4
Soil Report Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 1 of 9
Soil Report
Soil Investigation and percolation tests 1.0
M/s. Ascent Pharma is an existing small scale unit located at Survey No. 163/9 &
11 on S.I.D.C. Road in Shapar-Veraval Industrial Area of Village Veraval (Shapar) in
KotadaSanganiTaluka of Rajkot District in Gujarat state and involved in the
manufacturing of various Inorganic Chemicals with the production capacity of 50
TPM. Now the unit proposes to manufacture various Bulk Drugs & Drugs
Intermediates (Synthetic Organic Chemical) with total production capacity of 55
TPM.
The stated project will be carried out within the existing premises. Location map of
the project site is given in Figure 1.
In order to ensure compliance of the additional TOR obtained from SEAC-
Gandhinagar,here under conducted soil investigation and percolation tests to check
permeability of soil.
BACKGRAOUND
2.0
This report is part of an Environmental Impact Assessment (EIA) report being
prepared for the proposed project. Its main objective is to present the soil conditions
that pertain to the site. The vulnerability to pollution as a consequence of the effluent
discharge from the proposed plant and mitigation measures necessary has also
been suggested.
OBJECTIVE
Soil Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 2 of 9
Figure 1: Location Map of the project site
Soil Report Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 3 of 9
3.0 SOIL
3.1 Logging of soil strata
The soil survey has been done to know soil characteristics of the area. Figure 2
shows that in and around the study area comprises of Deccan Trap Basalts. This
trap rocks appears gently tilted at places, flows comprises massive, hard and tough
Amygdaloidal Basalt, Vesicular fine grained basalts; Porphyritic basalts,Geodes with
Zeolite, Chalcedony, Agate and Calcite are often in Amygdaloidal types. The traps
are invariably jointed by all kinds of joints in Basalt.The area is almost flat and
ground gradients are mild and sloping from West to East.
Figure 2:Geological map of Gujarat
3.2 Soil Type in Rajkot District
The soil strata consist of thin inorganic soil overlaying basaltic layer of varying
degree of weathering.
Soil type in the KotadaSanganiTaluka of Rajkot district is shallow medium black as
shown in Figure 2.
Soil Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 4 of 9
The structure of the soil found in the region is predominantly clayey having high
water holding capacity and moderate permeability.
Figure 3: Soil Map of Gujarat
3.3 Physico- Chemical analysis of soil
To determine the exact impacts of any proposed activity, existing status of soil
quality through a study of soil quality assessment has been done. Considering this,
surface soil samples were collected from two trail pits of project site, which signifies
that the soil of the area is fertile. This is given in below table 1.
Table 1:Physico- Chemical characteristics of soil
Sr.
No. Parameters Unit Trial Pit 1 Trial Pit 2
1 Bulk Density gm/cm 1.19 3 1.14
2 Moisture content % 6.17 5.86
3 Water Holding Capacity % 39 38
4 Specific gravity -- 1.99 2.02
5 Particle Size Distribution
Soil Report Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 5 of 9
Sr.
No. Parameters Unit Trial Pit 1 Trial Pit 2
i Sand % 22 20
ii Clay % 52 54
iii Silt % 26 26
6 Texture Class -- Loamy clay Loamy clay
7 pH (10% Solution) -- 7.20 7.00
8 Electrical Conductivity ms/cm 2.4 2.6
9 Cation Exchange Capacity meq/100 gm 32 36
10 Calcium gm/Kg 1.5 1.3
11 Magnesium gm/Kg 0.5 0.8
12 Sodium gm/Kg 2.3 2.1
13 Potassium gm/Kg 0.6 0.8
14 Chloride gm/Kg 2.2 1.8
15 Phosphorous gm/Kg 0.06 0.10
16 SAR -- 2.30 2.28
17 Available Nitrogen gm/Kg 1.2 1.4
18 Total organic matter % 3.9 4.1
19 Iron as Fe gm/Kg 1.5 1.2
20 Zinc as Zn gm/Kg 0.2 0.2
21 Nickel as Ni gm/Kg 0.18 0.14
3.4 Percolation test
The total greenbelt area of 760 sqmt (existing 340 sqmt+ proposed 420 sqmt) is
investigated to assess the suitability of the proposed mode of effluent disposal. As
the total greenbelt area is 0.076 ha which is less than 4ha, hence only one trail pit is
adequate for the soil study. However, two trial pits were excavated at project site for
the logging of soil strata and percolation test.
1. Trial pit 1 (0. 5m x 0.5m x 0.45m deep)
Soil depth (m) Soil Characteristics
0- 0.15 Topsoil
0.15- 0.35 Completely weathered basalt with inorganic soil layers
0.35- 0.45 Weathered basaltic layer
2. Trial pit 2 (0. 5m x 0.5m x 0.45m deep)
Soil depth (m) Soil Characteristics
0.00- 0.13 Topsoil
0.13- 0.32 Completely weathered basalt with inorganic soil layers
0.32 – 0.45 Weathered basaltic layer
Soil Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 6 of 9
Percolation tests have been design to determine suitability of the soil for a
subsurface effluent disposal system. More specifically, the percolation tastes will
measure the ability of the soil to absorb the effluent discharge. The rate at which the
effluent is absorbed isnot only used to calculate the surface area required for
effective discharge of the effluent, but also indicates the degree of filtration and
hence the degree of treatment achieved.
Two percolation tests were carried out at bottom of each trail pit. The methodology
adopted can be summarized as follows;
a) A hole0.5 x0.5 m square to a depth 0.45 m was excavated for each pit.
b) A 60 mm level of gravel (10-14 mm size) was placed at the bottom of the base.
c) The hole was filled with water and allowed to soak overnight.
d) About 3 hours before carrying out the test the hole was again filled with water
and allowed to drain out to achieve saturated conditions.
e) The test was carried out by filling the hole with water upto 0.3 meter and time
recorded for the water to drain through. This was repeated two times.
Details of the results obtained and the corresponding computation of the soil
permeability is given here under:
Table 2: Percolation Test at different Trail Pit
Sr. No.
Parameters Unit Trial Pit- 1 Trial Pit- 2
PT-1 PT-2 PT-1 PT-2
1 Dimension of trail pit m 0.5 x 0.5 x 0.45 0.5 x 0.5 x 0.45
2 Level of water from bottom of the pit
mm 300 300 300 300
3 Time taken for complete infiltration of water
min 196 163 218 171
4 Percolation rate mm/hr 91.8 110.4 82.6 105.3
5 Average Permeability mm/hr 101.1 93.9
Average Permeability of soil mm/hr 97.5
Soil Report Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 7 of 9
4.0 GROUND WATER QUALITY AT PROJECT SITE
These are hard rock area. Ground water is occurring in the zone of secondary
porosity. Ground water is occurring under unconfined condition. Ground water
sample was also collected and analyzed to assess the present status of ground
water quality. The depth to water level of unconfined aquifer in this area is ranging
from 3.0 to 16.0m. The depth of well in this area is ranging from 16.9 to 21.0 m.
From the ground water development point of view, this area falls in safe category.
Apparently, one may feel that it is not necessary to plan recharge scheme in such
area but it is not so. Ground water quality is good (MAP). The total dissolved solids
content in ground water is ranging from 1,000 to 3,000 ppm.
5.0 MAJOR FINDINGS
1. This area comprises of Deccan Trap Basalt. The weathering of this rock type
gives rise toblack cotton soil.
2. The depth of water level near close proximity of this plant site is about 16.9 to 21
m below ground level.
3. From the ground water development point of view this area falls in safe zone
category. 4. Physico- chemical analysis predicts that soil type is loamy clay and fertile in
nature.
5. Thissoil is having average permeability of 97.5 mm/hr and having characteristics
of high water holding capacity.
6. Considering actual percolation rate exits at project site, Land suitability for
discharge of treated effluent at project site is good.
Average Permeability of soil 97.5 mm/hr (2.34 m/Day)
Effluent Generation 1.7 m3/Day
Land Area Required 0.726 m2
Land Available 760 m2
Land area required is much lesser than the area available for greenbelt
development. Therefore, there are negligible chances of water logging and water
will effectively percolate through the soil.
Soil Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 8 of 9
7. The total water requirement for the greenbelt development will be more than the
total treated effluent generation and will be met from additional freshwater.
Total greenbelt area after proposed project : 760 sqmt
Water requirement for greenbelt development : 4 Lit/sqmt
Total water requirement : 3040 Liter
Treated effluent for greenbelt development : 1700 Liter
Fresh water requirement for greenbelt development : 1340 Liter
Treated effluent generated @ 1.7 KLD and freshwater @ 1.3 KLD will be used for
greenbelt development.
Soil Report Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 9 of 9
6.0 CONCLUSION&MITIGATION MEASURES
• From the above inherent field condition, it appears that there are remote
chances for ground water contamination. However, there are no heavy
metals or toxic chemicals used as raw materials. Also, there will be no
wastewater generation from manufacturing process which may pose threat to
reuse of treated wastewater for greenbelt development. Effluent generated
from APCE, boiler, washing and cooling will be treated in ETP comprising of
Primary, Secondary and Tertiary unit and treated effluent will be reused for
plantation and gardening.
• The total water requirement for the greenbelt development will be almost
double then the wastewater generation from the proposed project. Also
percolation testresults show that soil is having high water holding capacity and
moderate permeability allows water to percolate effectively avoiding any water
logging on proposed greenbelt area.
• Soil analysis report shows that soil quality is good, fertile and adequate for the
utilization of treated effluent for plantation & gardening.
• Over the period of time salinity of soil may increase for which unit will explore
effective chemical treatments by applying Gypsum as and when required.
• However,threat to ground water contamination can be taken careof bygrowing
following high water absorbing trees &plants in green belt area;
1) Tamarixgallica (French tamarisk) 2) Buteamonosperma (Kesudo)
3) Casuarinaequisetifolia (Saru) 4) Ailanthesexcelsa (Arduso)
5) Pongamiapinnata (Karanj) 6) Cocusnucifera (Nariyal)
7) Azadirachtaindica (Neem) 8) Albizzialebbeck (Shirish)
Page 1 of 3
Annexure-6
After the completion of the reaction, the spent solvent/mother liquor will be
separated by centrifuge and pumped to distillation reactor. It will be subjected to
distillation to separate and recover solvent.
SOLVENT REQUIREMENTS & RECOVERY SYSTEM
The industry proposes to manufacture synthetic organic chemicals (Bulk Drugs &
Drugs Intermediates), which require solvents during various unit processes. The unit
intends to use various solvents viz. Mono Chloro Benzene, Acetone, Methanol and
Xylene. The spent solvent generated during the manufacturing process will be
recovered by way of distillation and reused in the process. The process of the
solvent recovery system is described hereunder;
Firstly, the mass will be distilled at required temperature where pure solvents will
be distilled out depending on their boiler points and it will be collected in the
recovered solvent storage tank and reused in the process and then residue will
be sent to TSDF site for the disposal by incineration.
Vacuum will also be applied during distillation.
The overall requirements and mass balance for the solvent based on mass
balance of each product has been worked out. The schematic diagram of the
solvent recovery system is shown in the Figure 1.
The entire manufacturing activities & distillation process will be carried out in the
totally closed system.
Measures for achieving maximum solvent recovery:
Maintenance of the pipeline and valves & fittings will be carried out regularly to
avoid any leakages.
Reactor will be connected with two numbers of condensers where cooling water
and chilled water will be used as media and also equipped with vacuum system
as per requirement.
The condenser will be provided with the sufficient HTA and residence time to
achieve more than 95% recovery.
The fresh solvent requirement will be depended on generation of distillation loss. The
details of solvent consumption and mass balance are given below in Table 1 &
Table 2.
Page 2 of 3
Figure 1: Schematic Diagram of Solvent Recovery System
Table 1: Details of Solvent Requirement and Recovery
Sr. No.
Name of Solvent
Product Group
Fresh, MT/Month Recovered, MT/Month
Product wise
Group Max
Total Product
wise Group Max
Total
1. Acetone I (a/b) 4.00 4.00
9.00 64.43 64.43
144.43 2 5.00 5.00 80.00 80.00
2. Methanol 2 15.00 15.00 15.00 235.00 235.00 235.00
3. Mono Chloro Benzene
I (a) 4.50 4.50 4.50
98.00 98.00 98.00
I (b) 4.50 98.00
4. Xylene 3-A 0.80
0.80 0.80 19.60
21.60 21.60 3-B 0.80 21.60
Page 3 of 3
Table 2: Summary of Solvent Requirement and Recovery
Sr. No.
Name of Solvent
Solvent Requirement, MT/Month
Solvent Requirement,%
Fresh Recovered Total Fresh Recovered Total
1. Acetone 9.00 144.43 153.43 5.87 94.13 100.00
2. Methanol 15.00 235.00 250.00 6.00 94.00 100.00
3. Mono Chloro Benzene
4.50 98.00 102.50 4.39 95.61 100.00
4. Xylene 0.80 21.60 22.40 3.57 96.43 100.00
Total / Average 29.30 499.03 528.33 4.96 95.04 100.00
ANNEXURE- 7
Report on Risk and Safety Management
RISK AND SAFETY MANAGEMENT
Ascent Pharma Survey No. 163/9, Nr. Chintan Gas Godown, S. I. D. C. Road, Veraval (Shapar) -
360024. Ta: Kotada Sangani, Dist: Rajkot (Guj.). India.
(QCI-NABET ACCREDITED EIA CONSULTANT3rd Floor, Akashganga Complex, B/s. Suvidha Shopping Centre,Nr. Parimal Underpass, Paldi, AHMEDABAD-380 007, Gujarat.Telefax: (079) 2665 0473, 2665 0878; E-mail: [email protected]
)
Prepared By,
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page i
LIST OF CONTENTS
SR. NO. TITLE PAGE NO.
1.0 Preamble 1
2.0 Objective, Phylosophy & Methodology 2
2.1 Objective 2
2.2 Phylosophy 2
2.3 Methodology 2
3.0 Hazardous Material, Process and Safety Management 3
3.1 Hazardous Chemicals 3
3.2 Safety Measures for Transportation, Storage & Handling of chemicals
5
3.3 Critical Safety Measures for Process Units 5
3.4 Safety Measures For Preventive Maintenance 7
3.5 Safety measures to prevent spillage / leakage of toxic chemicals
7
4.0 Occupational Health & Safety Program 8
5.0 Risk Assessment Study 9
5.1 Identification of High Risk Areas 12
5.2 Models of Failure 12
5.3 Maximum Credible Accident Analysis and Its Mitigation Measures
13
5.4 Consequences Analysis 14
5.4.1 Definitions & Explanation of Terms Used 15
5.4.2 Possible Accident Scenario 17
6.0 Onsite Emergency Plan and Disaster Management Plan 78
6.1 Pre-emergency activity 79
6.2 Emergency Time Activities 81
6.3 Post – Emergency Activities 83
7.0 Off Site Emergency Plan 83
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page ii
LIST OF TABLES
TABLE NO.
TITLE PAGE NO.
Table 1 Details of Hazardous Chemicals per the MSIHC rules 1989 & 2000
4
Table 2 Storage details of Hazardous Chemicals 14
Table 3 Threshold values of the Hazardous Chemicals 15
Table 4 Atmospheric Conditions Assumed 17
Table 5 Source Strength considered for Methanol 18
Table 6 Threat zone of toxic liquid concentration 19
Table 7 Falmable area of vapor cloud 19
Table 8 Source Strength in case of Methanol escapes (pool fire) 21
Table 9 Threat zone of thermal radiation from BLEVE 22
Table 10 Source Strength considered for Ammonia gas 24
Table 11 Toxic Threat zone 25
Table 12 Flammable area of vapor cloud 26
Table 13 Threat zone of thermal radiation from jet fire 29
Table 14 Threat zone of thermal radiation from BLEVE 31
Table 15 Source Strength considered for Ammonia 32
Table 16 Threat zone of toxic liquid concentration 33
Table 17 Flammable area of vapor cloud 34
Table 18 Source Strength considered for Acetone 35
Table 19 Threat zone of toxic liquid concentration 37
Table 20 Flammable area of vapour cloud 37
Table 21 Threat zone of thermal radiation from pool fire 39
Table 22 Threat zone of thermal radiation from BLEVE 40
Table 23 Source Strength considered for Cyclo Hexyl Isocynate 42
Table 24 Threat zone of toxic liquid concentration 43
Table 25 Flammable area of vapor cloud 45
Table 26 Threat zone of thermal radiation from BLEVE 46
Table 27 Source Strength considered for Formic Acid 48
Table 28 Threat zone of toxic liquid concentration 49
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page iii
Table 29 Flammable area of vapor cloud 50
Table 30 Threat zone of thermal radiation from BLEVE 51
Table 31 Source Strength considered for Hydrazine 52
Table 32 Threat zone of toxic liquid concentration 53
Table 33 Flammable area of vapor cloud 54
Table 34 Threat zone of thermal radiation from BLEVE 56
Table 35 Source Strength considered for Mono Chloro Benzene 58
Table 36 Threat zone of toxic liquid concentration 59
Table 37 Flammable area of vapor cloud 60
Table 38 Threat zone of thermal radiation from pool fire 62
Table 39 Threat zone of thermal radiation from BLEVE 64
Table 40 Source Strength considered for Phosphorus Trichloride 65
Table 41 Threat zone of toxic liquid concentration 66
Table 42 Source Strength considered for Thionyl Chloride 68
Table 43 Threat zone of toxic liquid concentration 69
Table 44 Source Strength considered for Xylene 72
Table 45 Threat zone of toxic liquid concentration 73
Table 46 Flammable area of vapor cloud 73
Table 47 Threat zone of thermal radiation from pool fire 75
Table 48 Threat zone of thermal radiation from BLEVE 76
LIST OF FIGURES
FIGURE NO.
TITLE PAGE NO.
Figure 1 Risk Assessment Methodology 11
Figure 2 Source Strength in case of Methanol escape 18
Figure 3 Isopleths result of Toxic threat at a point for Methanol 20
Figure 4 Source Strength in case of Methanol escapes (pool fire) 21
Figure 5 Thermal radiation at a point in case of Methanol escapes (pool fire)
22
Figure 6 Isopleths result of threat zone of thermal radiation from BLEVE
23
Figure 7 Source Strength in case of ammonia gas escapes 25
Figure 8 Isopleths result of toxic threat zone for Ammonia Gas 26
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page iv
FIGURE NO.
TITLE PAGE NO.
escaping
Figure 9 Isopleths result of flammable threat zone for Ammonia Gas escaping
27
Figure 10 Isopleths result of Toxic threat at a point for Ammonia Gas 28
Figure 11 Source Strength in case of Ammonia Gas escapes (pool fire)
29
Figure 12 Isopleths result of Thermal radiation from jet fire 30
Figure 13 Isopleths result of threat zone of thermal radiation from BLEVE
31
Figure 14 Source Strength in case of Ammonia escape 32
Figure 15 Threat zone of toxic liquid concentration 33
Figure 16 Isopleths result of Toxic threat at a point for Ammonia 35
Figure 17 Source Strength in case of Acetone escape 36
Figure 18 Isopleths result of Toxic threat at a point for Acetone 38
Figure 19 Source Strength in case of Acetone escapes (pool fire) 39
Figure 20 Thermal radiation at a point in case of Acetone escapes (pool fire)
40
Figure 21 Isopleths result of threat zone of thermal radiation from BLEVE
41
Figure 22 Source Strength in case of Cyclo Hexyl Isocynate escape 43
Figure 23 Threat zone of toxic liquid concentration 44
Figure 24 Isopleths result of Toxic threat at a point for Cyclo Hexyl Isocynate
46
Figure 25 Isopleths result of threat zone of thermal radiation from BLEVE
47
Figure 26 Source Strength in case of Formic Acid escape 48
Figure 27 Threat zone of toxic liquid concentration 49
Figure 28 Isopleths result of Toxic threat at a point for Formic Acid 50
Figure 29 Isopleths result of threat zone of thermal radiation from BLEVE
51
Figure 30 Source Strength in case of Hydrazine escape 53
Figure 31 Threat zone of toxic liquid concentration 54
Figure 32 Isopleths result of Toxic threat at a point for Hydrazine 55
Figure 33 Isopleths result of threat zone of thermal radiation from BLEVE
56
Figure 34 Source Strength in case of Mono Chloro Benzene escape 58
Figure 35 Threat zone of toxic liquid concentration 59
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page v
FIGURE NO.
TITLE PAGE NO.
Figure 36 Isopleths result of Toxic threat at a point for Mono Chloro Benzene
61
Figure 37 Source Strength in case of Mono Chloro Benzene escapes (pool fire)
62
Figure 38 Thermal radiation at a point in case of Mono Chloro Benzene escapes (pool fire)
63
Figure 39 Isopleths result of threat zone of thermal radiation from BLEVE
64
Figure 40 Source Strength in case of Phosphorus Trichloride escape 65
Figure 41 Threat zone of toxic liquid concentration 66
Figure 42 Isopleths result of Toxic threat at a point for Phosphorus Trichloride
67
Figure 43 Source Strength in case of Thionyl Chloride escape 69
Figure 44 Threat zone of toxic liquid concentration 70
Figure 45 Isopleths result of Toxic threat at a point for Thionyl Chloride 71
Figure 46 Source Strength in case of Xylene escape 72
Figure 47 Isopleths result of Toxic threat at a point for Xylene 74
Figure 48 Source Strength in case of Xylene escapes (pool fire) 75
Figure 49 Thermal radiation at a point in case of Xylene escapes (pool fire)
76
Figure 50 Isopleths result of threat zone of thermal radiation from BLEVE
77
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 1 of 84
1. PREAMBLE
Increasing use of hazardous chemicals as raw materials, intermediates and finished
products has attracted attention of the Government and the public at large in view of
the chemical disasters. The serious nature of the accidents, which cause damage to
the plant, personnel and public, has compelled industries to pay maximum attention
to the safety issues and also to effectively manage the hazardous material and
operations. It is mandatory for the industries handling hazardous chemical to
maintain specified safety standards and generate an on-site emergency plan and
keep it linked with off site emergency plan.
The Risk Assessment Study and safety management for the proposed project of
M/s. Ascent Pharma has been carried out and the details are elaborated in this
chapter. Based on the findings & recommendations of RA report management plan
for the proposed project has also been prepared and included.
Risk Assessment is defined as a continuous and integrated process of identification,
evaluation and measurement of risks, along with their potential impact on the
organization.
The benefits of risk assessment include the following:
• Prevention or reduction in occurance of accidents.
• Mitigation of the severity and/or consequences by way of improved process
techniques, fire protection systems, arrangements of storage, inventory
monitoring to fit production requirements.
• Development of confidences in employees by improving competency.
• Preparedness and prompt response to deal with any accident.
The safety management includes the implementation of preventive methods or
accident prevention methods to avoid incident or accident and handling of
emergency in case of accident.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 2 of 84
2. OBJECTIVE, PHILOSOPHY AND METHODOLOGY OF RISK ASSESSMENT
2.1 Objective
The principle objective of this study is to identify major risks in the manufacturing
process and to evaluate on-site & off-site consequences of identified hazard
scenarios. Pointers are then given for effective mitigation of hazards in terms of
suggestions for effective disaster management, suggesting minimum preventive and
protective measures & change of practices to ensure safety.
2.2 Philosophy
The following aspects and areas have been covered in this study;
• Identification of major risk areas.
• Hazard identification / Identification of failure cases.
• Consequential analysis of probable risks / failure cases;
o Determination of the probable risk by Releasing of chemical due to leakage
of storage tank and catastrophic failure.
o Risk assessment on the basis of the above evaluation & risk acceptability.
o Minimum preventive & protective measures to be taken to minimize risks to
maximum possible extent.
• Giving pointers for effective disaster management.
• Suggesting measures to further lower the probability of risk.
2.3 Methodology
Design data, built in safety systems are studied. Discussions are held with officials.
Safety related individual system is discussed. Hazard identification exercise is
conducted taking into consideration of materials, material handling methods,
operating procedures, built in safety in reactors, operating parameters and safety
measures to be taken in proposed plant. Few areas like process building, storage of
hazardous chemicals, to evaluate safety systems in the event of any abnormalities
occurring. Containment failure scenario related to storage area is considered for
hazard Analysis and consequences of such containment failures are considered in
detail. Thus, this study is mainly oriented towards actual risks rather than chronic
risks.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 3 of 84
3.
The proposed project includes manufacturing of various bulk drugs and drug
intermediates along with the existing products. Manufacturing of these synthetic
organic chemicals required raw materials are listed in Chapter-2, Section-2.8 with
hazardous identification of EIA Report. Physical characteristic as well as hazardous
details of raw materials and products in form of MSDS are enclosed in Appendix-1.
HAZARDOUS MATERIAL, PROCESS AND SAFETY MANAGEMENT
3.1 Hazardous Chemicals
None of the product is defined as hazardous in MSIHC rules but may fall under the
definition of hazardous material/chemicals either due to flammability or toxicity.
Certain raw materials fall under the definition of hazardous chemical. The details of
hazardous chemicals are given in Table 1.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 4 of 84
Table 1: Details of Hazardous Chemicals per the MSIHC rules 1989 & 2000
Sr.
No.
Name of
Chemicals State Colour Odor
Sp.
Gravity
Vapour
Density
Melting
Point ºC
Boiling
Point ºC
Flash
Point ºC
Explosive
limit Solubility in
water
Hazardous
Characteristics LEL UEL
% %
1. Acetone Liquid Colourless Fragrant Mint 0.791 2 -94.7 56.48 -20 2.6 12.8 Miscible Corrosive,
Flammable
2. Ammonia Gas Gas Colourless
gas with sharp
Strong Similar to
smelling Salts
0.59 --- -77.7 -33.4 --- --- --- 0.848 Toxic &
Flammable
3. Caustic Soda
Flakes Liquid
White Flakes
/Pellets Odourless 2.12 --- 318.4 1390 --- --- --- Soluble Corrosive
4. Formic Acid Liquid
Clear
Colourless
Liquid
Characteristic
Pungent Odor. 1.22 1.6 8 101 50 18 57
Infinitely
Soluble ---
6. Hydrochloric
Acid (Gas)
Liquefied
Gas Colourless Pungent --- --- -114 -85 --- --- --- Hydrolyses
Toxic,
Corrosive
7. Methanol Liquid Colourless,
waterly Alcoholic Odour 0.79 1.1 -97.8 64.5 16.1 6 36.5
20°C
(Liu) q
Corrosive,
Flammable
8. Phosphorous
Trichloride Liquid
Colurless to
Light Yellow Pungent, Irritant 1.574 4.75 -112 76 --- --- --- Insoluble Toxic, Explosive
9. Mono Chloro
Benzene Liquid
10. Thionyle
Chloride
Fuming
Liquid
Colurless to
Light Yellow Suffocating 1.638 4.1 -104.5 76 --- --- ---
Insoluble in
Cold Water
Corrosive,
Poisonous
11. Xylene Liquid Colourless Sweet Odour 0.864 --- - 134-140 37.7 --- --- insoluble Corrosive,
Flammable
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 5 of 84
3.2 Safety Measures for Transportation, Storage & Handling of chemicals
Solvent will be received by road tankers / in drums and stored in designated
storage area.
Standard procedure for solvent unloading will be in place and will be
implemented for safe unloading of road tanker.
Static earthing provision will be made for tanker unloading.
Fixed pipelines with pumps will be provided for solvent transfer up to reactors.
NRV provision will be made on all pump discharge line.
Drum handling trolleys will be used for transportation of drums up to plant.
Muffler on the silencer of the tanker during entering in factory premises.
Display Boards will be provided on all storage tanks which includes the name of
the chemicals, storage Material of construction, Calibration of tanks and date of
Painting.
In order to avoid the accident due to spillage or overflow, the level indicators will
be placed which helps to know the exact liquid level inside the tank.
All the storage tanks will be provided with Dyke wall and transferring pumps
which will help to reduce the risk of tank leakages.
Water showering system (Automated sprinkling system) will be provided to the
flammable liquid storage tanks, wherever required to avoid the vaporization due
to increase in atmosphere temperature.
Proper earthing will be provided to all storage tanks to prevent the firing due to
static charges.
Breather Valves and Flame arrestors will be provided on flammable liquid storage
tanks to prevent the firing.
On-site detectors for fire based on heat &/or smoke detection with alarm system
will be provided as required.
Fire fighting system will be provided as required.
First aids boxes will also be provided at prominent places in the plant.
Area will be declared as “NO SMOKE ZONE”.
3.3 Critical Safety Measures for Process Units
Critical safety measures are the most important aspect of selection of process
technology to ensure safety in production unit. For the safety in production area
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 6 of 84
some important critical safety measures will be provided within the process
technology/ equipment itself & will put continue efforts for developing new
technology/equipment. Company will ensure such provision in the technology
/equipment /machineries at time of purchase. The details of the critical safety
measures for process unit are as below;
• Any reaction upsets will be confined to the reaction vessel itself as defined
quantity of raw materials will be issued to the reaction vessel by metering
pumps/load cells.
• Process parameters control will be provided vide Standard Operating
Procedures.
• Materials will be transferred by pumping through pipeline or by vacuum from
drums.
• All reaction vents will be connected to vapor condensers system.
• Hazardous materials will be transferred by pipelines and in control manners.
• Trained person will be engaged for handling of hazardous materials.
• Proper safety precautions will be taken during handling of hazardous materials.
• All solvents and flammable material storage area away from the process plant
and required quantity of material will be charge in reactor by pump or by gravity.
• Further all the vessels will be examined periodically by a recognized competent
person.
• All the vessels and equipments will be well earthed appropriately and well
protected against Static Electricity. Also for draining in drums proper earthing
facilities will be provided.
• Temperature indicators will be provided near all reactor and distillation systems.
• Caution note, safety posters, stickers, periodic training & updation in safety and
emergency preparedness plan will be displayed and conducted.
• Flame proof light fittings will be installed in the plant.
• All the Plant Personnel will be provided with Personal Protection Equipments to
protect against any adverse health effect during operations, leakage, spillages or
splash. PPE like Helmets, Safety Shoes and Safety Glasses will be provided to
the employees.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 7 of 84
• Material Safety Data Sheets of Raw Materials & Products will be kept readily
available at the shop floor.
3.4 Safety Measures For Preventive Maintenance
The safety measures in form of the general Do's & Don'ts for safety in process &
other plant area are as below:
• Do not work on equipments without permission from plant head and maintenance
head.
• Make sure equipment is empty and fluxed with nitrogen and air.
• Check VOC content for flammable and make sure that no flammable vapour
contents.
• Keep proper and adequate fire extinguisher near work area.
• Use proper PPE.
• Do not allow any employment without pre-medical check-up or without checking
fitness.
• Check all motors are disconnected and fuse pulled out before maintenance.
• Work in any equipment must be conducted in presence of supervisor.
• Make sure all process lines are disconnected.
• Additional safety measures in form of the checklist covering Do's & Don'ts of
preventive maintenance, strengthening of HSE, manufacturing utility staff for
safety related measures will be updated timely and will be made available to all
concern department & personnel.
3.5 Safety measures to prevent spillage / leakage of toxic chemicals
The preventive maintenance will be planned and carried out as per plan to avoid the
failure of valve, pipe lines and other component of transferring line. The spillage will
be confined to the dyke area underneath the vessel. The resultant splash of such
chemicals will result in exposure of toxic chemicals to employees. Decontamination
facilities (Safety shower and eye wash fountains) will be provided in the plant area,
which can be used to decontaminate the affected employees.
Suitable decontamination procedure will be used to decontaminate the spilled or
leaked material. The SOP for decontamination will be reared with all related
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 8 of 84
department. The followings are some measures to be taken for handling the toxic
chemicals safely;
• The installation of all the equipment will be as per guidelines of provision of
Gujarat Factories Rule 1963.
• The storage of corrosive and toxic chemicals will be segregated from each other.
• The piping will be examined thoroughly every year for finding out any defects;
and a defect will be removed forthwith. The record of such examination will be
maintained.
• Smoking will be prohibited inside the factory. Train employees will be employed
for handling of toxic and corrosive chemicals.
• All pipe joints will be provided with heavy duty champion gaskets to prevent any
leakage.
• Self breathing apparatus will be provided and workers will be trained about their
use also.
• Dyke wall will be provided to area where hazardous chemicals are stored.
• Spare barrels of sufficient quantity will be kept ready for any emergency spillage
or leakage.
• Drum trolley will be used for the movement of drums of hazardous chemicals.
• VOC detectors will be installed to implement LDAR
4.
The main effects of chemicals especially VOCs are anticipated in proposed project.
No other source of adverse effects on occupation health & safety is likely to occur.
However, MSDS of hazardous chemicals will be made available with the
management as well as concern personnel working with the materials or area likely
to be affected by the materials. In general following are the key safety measure
which has been recommended with the project.
OCCUPATIONAL HEALTH & SAFETY PROGRAM
• Provision of all necessary equipment like portable detector, online detectors and
other laboratory equipments as mentioned above for regular monitoring of
workplace air and other conditions (VOC, Temperature, Humidity and Light
Intensity etc.).
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 9 of 84
• Establish the safety policy.
• Compulsory use of necessary PPES
• Installation of Fire extinguishers at required places.
for all workers.
• Regular work place monitoring.
• Protection of storage area with Dyke wall.
• Separate area provision for container decontamination.
• Provision of part time qualified medical officer as per factories act guidelines.
• Pre-medical checkup at the time of employment and maintain form 33 as per
factories act guidelines.
• Regular medical check of employees by qualified medical officer and maintain
health records in prescribed format.
• Monitoring of occupational hazards like noise, ventilation, chemical exposure
should be carried out at frequent intervals.
• Provision of proximity suits and self-breathing apparatus.
• Display various instruction boards, cautionary notices etc. at different locations.
5.
Chemical process industries have undergone tremendous changes during last five
decades. Process conditions such as Pressure & Temperature have become severe;
concentration of stored energy has increased. The scale of possible fire, explosion,
toxic release, body injuries and occupational diseases has grown considerably.
These factors have greatly increased the risk for major industrial disasters, involving
loss of human lives, plant & property and environmental degradation.
Identification analysis and assessment of hazard and risk are very useful in providing
information to risk management. It provides basis for what should be the type and
capacity of its on-site and off-site emergency plan also what types of safety
measures are required. Risk and consequence analysis is carried out considering
storage and handling of various hazardous raw materials, intermediates and
products as well as manufacturing process. The objectives considered for Risk
Assessment study are as follows;
RISK ASSESSMENT STUDY
• To assess the risk involved in transporting, storing & processing raw material up
to final product.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 10 of 84
• To define Emergencies including risk & Environment impact assessment.
• To evaluate the risk and to get the complete view of the available facilities.
• To take appropriate action to control the incidents.
• To safe guard employees and people in vicinity.
• To minimize damage to property and neighboring environment.
• To inform the employees, general public & Government authority
aboutvarious type of hazards, assessed risk, safe guards provided, residual
riskif any, and role to be played by them in the event of emergency.
• To inform Police, fire brigade, District authority and statutory authority for
providing help during emergency.
• To work out a plan with all provisions to handle emergencies and to provide
training to employees through mock rehearsals.
• To rescue and give treatment to the casualties and to count the number ofinjured
persons.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 11 of 84
Figure 1. Risk Assessment Methodology
Following matrix summarizes methodology adopted for Risk Assement study
START
Facility, process and meteorological data collection
Listing out hazardous operations & storage details
Identification of failure scenarios & quantification of probable hazard associated for risk assessment
Defining parameters for each chemical and each hazard
Defining release type (continuous / instantaneous) & determine release rate
Simulation of different credible scenario for consequence modeling
Prepare Summary of Credible Scenario
Evaluate potential risk associated to the surrounding
Suggest mitigation measures for the risk associated
END
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 12 of 84
5.1 Identification of High Risk Areas
It is observed that the storage areas pose fire/explosion hazards which may lead to
major accident event. In the process areas it is observed that inventories of
chemicals are very low & so there are not deemed to pose major off-site hazards.
Thus, the quantitative risk assessment studies are limited to unit and some extent in
vicinity.
5.2 Modes of Failure
Storages system can fail in different ways depending on the materials stored,
storage conditions & may involve systems in their vicinity. Conditions such as over
filling, over pressure, missile, lightening or bomb attack, earthquake & resultant
replier or release scenarios have been identified. Outcomes of such incidents are
determined by presence of ignition either immediate or delayed. As can be seen
depending upon modes of failure different scenarios are possible viz:
1. Continuous release
2. Instantaneous release
This may be of gas / liquid depending upon type of material stored/released & its
characteristics. More examples, a liquid boiling at ambient conditions, will
immediately be converted to gas upon exposure to atmosphere.
An instantaneous release is any release occurring for a period less than 15 seconds.
Failure mode responsible for instantaneous releases may be catastrophic failure of
road tanker. For an instantaneous gas release important parameters are release
height & quantity released whereas for instantaneous liquid release, important
parameters are amount spilled, spill area & pool temperature, evaporation rate,
vapour mass etc.
Continuous release occurs when the material is released over a period greater than 15 seconds. For a continuous gas release, important parameters include height of leak above ground, emission rate & total time of release. For continuous liquid release important parameters are spill rates, duration, area & pool temperature, evaporation rate and vapor mass or Gas mass.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 13 of 84
5.3 Maximum Credible Accident Analysis and Its Mitigation Measures
A Maximum Credible Accident (MCA) can be characterized as the worst credible
accident. In other words: an accident in an activity, resulting in the maximum
consequence distance that is still believed to be possible. A MCA-analysis does not
include a quantification of the probability of occurrence of the accident. Another
aspect, in which the pessimistic approach of MCA studies appears, is the
atmospheric condition that is used for dispersion calculations.
The Maximum Credible Loss (MCL) scenarios have been developed for the Facility.
The MCL cases considered, attempt to include the worst “Credible” incidents-what
constitutes a credible incident is always subjective. Nevertheless, guidelines have
evolved over the years and based on basic engineering judgment, the cases have
been found to be credible and modeling for assessing vulnerability zones is prepared
accordingly.
The objective of the study is Emergency planning, hence only holistic & conservative
assumptions are used for obvious reasons. Hence, though the outcomes may look
pessimistic, the planning for emergency concept should be borne in mind whilst
interpreting the results.
This has been done for weather conditions having wind speed 1.0 m/s. In
Consequence analysis, geographical location of the source of potential release plays
an important role. Consideration of a large number of scenarios in the same
geographical location serves little purpose if the dominant scenario has been
identified and duly considered.
The Consequence Analysis has been done for selected scenarios by ALOHA
(version 5.4.5) of EPA.The details of software used for MCA analysis are described
below.
A computer based version ALOHA 5.4.5 is used to calculate toxic and explosive
effect of the accidental release of liquid chemicals within the plant area.
ALOHA (Areal Locations of Hazardous Atmosphere) is a computer program
designed especially for use by people responding to chemical release as well as
for emergency planning and training.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 14 of 84
ALOHA was jointly developed by the National Oceanic and Atmospheric
Administration (NOAA) and the Environment Protection Agency (EPA).
The mathematical model is based on the Emergency Response Planning
Guidelines (ERPGs) which gives Toxic Levels of Concern (LOCs) to predict the
area where a toxic liquid concentration might be high enough to harm people.
ALOHA models key hazards-toxicity, flammability, thermal radiation (Heat), and
over pressure (expansion blast force)-related to chemical releases that result in
toxic gas dispersion, fire and/or explosion.
5.4 Consequences Analysis
From the proposed raw materials Methanol and Ammonia Gas have been taken for
the consequences analysis considering their hazardous nature. Storage condition
and threshold value of these chemicals are mentioned in the Table 2 & 3. MSDS of
these chemicals are enclosed as Appendix-1.
Table 2: Storage details of Hazardous Chemicals
Sr. No.
Hazardous chemicals
Physical form
Type of storage
Size of Storage
Unit
Qty. of Storage
Unit
Maximum Storage
Capacity (MT)
Storage Pressure Kg/cm
2
Storage Temp.
ºC
1. Methanol Liquid HDPE
Barrel 170 Kg 58 10.0 ATM At RT
2. Ammonia
Gas Gas Cylinder 50 Kg 10 0.5 ATM At RT
3. Ammonia
Liquid Liquid
HDPE Barrel
50 Kg 10 0.5 ATM At RT
4. Acetone Liquid HDPE Barrel
170 Kg 58 10 ATM At RT
5. Cyclo Hexyl
Isocynate Liquid
HDPE Barrel
50 Kg 10 0.5 ATM At RT
6. Formic Acid Liquid HDPE Barrel
200 Lit. 10 2.0 ATM At RT
7. Hydrazine Liquid HDPE Barrel
200 Lit. 10 2.0 ATM At RT
8. Mono Chloro
Benzene Liquid
HDPE Barrel
235 Kg 42 10.0 ATM At RT
9. Phosphorus
Tri Chloride Liquid
HDPE Barrel
100 Kg 5 0.5 ATM At RT
10. Thionyl
Chloride Liquid GI Barrel 300 Kg 10 3.0 ATM At RT
11. Xylene Liquid HDPE Barrel
190 Kg 15 3.0 ATM At RT
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 15 of 84
Table 3: Threshold values of the Hazardous Chemicals
Sr. No.
Chemicals Threshold Value (ppm)
ERPG-1 / AEGL-1
ERPG-2 / AEGL-2
ERPG-3 / AEGL-3
1. Methanol 530 2100 7200
2. Ammonia Gas 30 160 1100
3. Ammonia Liquid 30 160 1100
4. Acetone 200 3200 5700
5. Cyclo Hexyl Isocynate - 0.034 0.1
6. Formic Acid 3 25 250
7. Hydrazine 0.1 13 35
8. Mono Chloro Benzene 10 150 400
9. Phosphorus Tri Chloride 0.34 2 5.6
10. Thionyl Chloride - 2.4 14
11. Xylene 130 920 2500
ERPG: Emergency Response Planning Guidelines AEGL: Acute Exposure Guideline Levels
5.4.1 Definitions & Explanation of Terms Used
EPRG-1 : The maximum concentration in air below which it is believed nearly all individuals
could be exposed for up to one hour without experiencing other than mild
transient adverse health effects or perceiving a clearly defined objectionable odor.
EPRG-2 : The maximum airborne concentration below which it is believed that nearly all
individuals could be exposed for up to 1 hour without experiencing or developing
irreversible or other serious health effects or symptoms which could impair an
individual's ability to take protective action.
ERPG-3 : The maximum airborne concentration below which it is believed that nearly all
individuals could be exposed for up to 1 hour without experiencing or developing
life-threatening health effects.
AEGL-1 : The airborne concentration of a substance above which it is predicted that the
general population, including susceptible individuals, could experience notable
discomfort, irritation, or certain asymptomatic nonsensory effects. However, the
effects are not disabling and are transient and reversible upon cessation of
exposure.
AEGL-2 : The airborne concentration of a substance above which it is predicted that the
general population, including susceptible individuals, could experience
irreversible or other serious, long-lasting adverse health effects or an impaired
ability to escape.
AEGL-3 : The airborne concentration of a substance above which it is predicted that the
general population, including susceptible individuals, could experience life-
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 16 of 84
threatening health effects or death.
IDLH : IDLH is an estimate of the maximum concentration in the air to which a healthy
worker could be exposed without suffering permanent or escape-impairing health
effects.
LEL : LEL is the minimum concentration of fuel in the air needed for a fire or an
explosion to occur if an ignition source is present. If the concentration is below
the LEL, there is not enough fuel in the air to sustain a fire or an explosion -- it is
too lean.
UEL : UEL is the maximum concentration of fuel in the air that can sustain a fire or an
explosion if an ignition source is present. If the concentration is above the UEL,
there is not enough oxygen to sustain a fire or an explosion -- it is too rich (much
like an engine that cannot start because it has been flooded with gasoline).
STEL : The concentration to which workers can be exposed continuously for a short
period of time without suffering from (1) Irritation
(2) Chronic or Irreversible tissue damage
(3) Narcosis of sufficient degree to increase injury, impair self-rescue or materially
reduce work efficiency and provide that the daily TLV-TWA is not exceeded.
TWA : The time-weighted average concentration for a normal 8-hour workday and a 40-
hour workweek, to which nearly all workers may be repeatedly exposed, day by
day, without adverse effect.
Source
Strength
: The source strength is either the rate the chemical enters the atmosphere or the
burn rate, depending on the scenario. A chemical may escape very quickly (so
that source strength is high), as when a pressurized container is ruptured, or
more slowly over a longer period of time (so that source strength is low), as when
a puddle evaporates.
Threat zone : It represents the area within which the hazard level (toxicity, flammability, thermal
radiation, or overpressure) is predicted to exceed the Level of Concern (LOC) at
some time after a release begins.
Evaporation
Puddle
: Choose Puddle from the Source submenu under the set up menu to model a
liquid that has spilled and formed a puddle on the ground. ALOHA can model the
puddle either as an evaporating puddle or, if the chemical is flammable, as a Pool
Fire.Choose Puddle when a puddle has already formed on the ground and is not
changing in area. If liquid is continuing to leak from a tank and spilling into a
puddle (so that the puddle's area and volume are increasing) choose Tank from
the Source submenu instead. Check the "Tank source" help topic to learn more
about this option.
Toxic
Threat zone
: A Toxic Level of Concern (LOC) is a threshold concentration of an airborne
pollutant, usually the concentration above which a hazard may exist.
Flammable
Threat zone
: A Flammable Level of Concern (LOC) is a threshold concentration of fuel in the
air above which a flammable hazard may exist. Generally, this LOC will be some
fraction of the Lower Explosive Limit (LEL).
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 17 of 84
Threat zone
of thermal
radiation
from jetfire
: The thermal radiation effects that people experience depend upon the length of
time they are exposed to a specific thermal radiation level. Longer exposure
durations, even at a lower thermal radiation level, can produce serious
physiological effects. The threat zones displayed by ALOHA represent thermal
radiation levels; the accompanying text indicates the effects on people who are
exposed to those thermal radiation levels but are able to seek shelter within one
minute.
Below are some effects at specific thermal radiation levels and durations (on bare
skin):
• 2 kW/(sq m) -- people will feel pain after 45 seconds and receive second-
degree burns after 3 minutes;
• 5 kW/(sq m) -- people will feel pain after 13 seconds and receive second-
degree burns after 40 seconds; and
• 10 kW/ (sq m) -- people will feel pain after 5 seconds and receive second-
degree burns after 14 seconds.
Threat at
point
: It represents the specific information about the hazards at point of interest (such
as schools and hospitals) in and around the threat zones.
5.4.2 Possible Accident Scenario
Different possible ways of occurrence of any accidents due to storage/usage of
above hazardous chemicals are prescribed here below;
Scenario-A: Release of chemical due to leakage and form evaporating puddle (Not
burning)
Scenario-B: Release of chemical due to leakage and form burning puddle (Pool fire)
Scenario-C: Release of chemical due to catastrophic failure (BLEVE)
Atmospheric conditions assumed at the time of accidents are mentioned in Table 4.
Table 4: Atmospheric Conditions Assumed
Particulars Details
Wind (Max) 3.0 meter/second
Ground Roughness Open Country
Cloud Cover 4 tenths
Air Temperature 32° C
Stability Class D
Relative Humidity 50%
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 18 of 84
1)
The possibilities of source strength considered at the time of accidents due to
leackage of Methanol from hole of 0.5 inches diameter at bottom of barrel are
mentioned in Table 5.
METHANOL
Table 5: Source Strength considered for Methanol
Particulars Value
Barrel diameter 0.5 m
Barrel height 1.1 m
Barrel volume 0.22 m3
Opening diameter 0.5 inches
Opening from tank bottom 0 m
Internal temperature 18.2 ºC
a) Source Strength
Scenario-1A: Release of Methanol due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Methanol escape from barrel by a hole of 0.5 inch, then maximum average
sustained release rate will be 874 gms/min and hence approx. 40.7 Kg of methanol
will be released in about 1 hour. Isopleths results are given in Figure 2.
Figure 2: Source Strength in case of Methanol escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 19 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Methanol release is given in Table 6. Threat
zone was not drawn because effects of near-field patchiness make dispersion
predictions less reliable for short distances.
Table 6: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 5000 (ERPG-3) < 10
Orange 1000 (ERPG-2) < 10
Yellow 200 (ERPG-1) 28
Model output of the flammable threat zone for chemical release is given in Table 7.
Flammable threat zone:
Table 7: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone
Horizontal Direction
Vertical Direction
Red 43,800 (60 % LEL) < 10 m
Yellow 7,300 (10 % LEL) < 10 m
Isopleths result of flammable threat zone showing area of vapor cloud at LEL value
was not drawn because effect of near field patchiness make dispersion prediction
less reliable for short distance.
c) Threat at Point
In case of leakage of Methanol from barrel, the significant effects will be upto 28
meter in case of toxic threat zone with concentration of 200 ppm. Effect has been
worked out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Methanol estimated at
described point is 17.9 ppm at outdoor and 2.54 ppm in indoor and Isopleths for the
same is shown in Figure 3.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 20 of 84
Figure 3: Isopleths result of Toxic threat at a point for Methanol
a) Source Strength
Scenario-2B: Release of Methanol due to leakage & form burning puddle (pool
fire)
When methanol escaped from barrel as a liquid and forms a burning puddle,
maximum burn rate in this case will be 5.88 Kg/min considering maximum attentive
time of 33 min. Moreover, puddle will be spread to a diameter of 2.7 m. Isopleths
results are given in Figure 4.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 21 of 84
Figure 4: Source Strength in case of Methanol escapes (pool fire)
b) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from pool fire is given in Table 8.
Table 8: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2
Threat Zone Radial Distance
Red 10 (Potentially lethal within 60 sec.) < 10 m
Orange 5 (2nd < 10 m degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) < 10 m
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. Maximum thermal radiation will be
0.00403 kw/m2. Isopleths results are given in Figure 5.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 22 of 84
Figure 5: Thermal radiation at a point in case of Methanol escapes (pool fire)
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When methanol will be released from barrel as a liquid and forms a fire ball, diameter
of fire ball will be 32 m and burn duration will be 3 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 9 & Figure 6.
Table 9: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance
Red 10 (Potentially lethal within 60 sec.) 53 m
Orange 5 (2nd 76 m degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 120 m
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 23 of 84
Figure 6: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 2.9 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 24 of 84
2)
The possibilities of source strength considered at the time of accidents due to
ammonia gas are mentioned in Table 10.
AMMONIA GAS
Table 10: Source Strength considered for Ammonia gas
Particulars Value
Cylinder Diameter 0.33 m
Cylinder Height 0.955 m
Cylinder volume 0.082 m3
InternalTemperature 18.2° C
Chemical Mass in cylinder 50 Kg
Scenario – A & B
Circular Opening Diameter 0.5 inches
Opening from Drum bottom 0 m
Ground Type Concrete
Scenario – C
Internal Pressure at Failure 1 atm
Percentage of Tank Mass in Fireball 100%
a) Source Strength
Scenario-2A: Release of Ammonia Gas due to leakage and form evaporating
puddle (Not burning)
When ammonia gas will escapes from cylinder as a gas and formed an evaporating
puddle, Maximum average sustained release rate in this case will be 833 gms/sec
considering maximum attentive time of 1 min. Isopleths results are given in Figure 7.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 25 of 84
Figure 7: Source Strength in case of ammonia gas escapes
b) Threat Zone
Model output of the Toxic threat zone and isopleths for chemical release are given in
Table 11 and Figure 8.
Toxic threat zone
Table 11: Toxic Threat zone
Threat Zone Concentration
(ppm)
Threat Zone
Horizontal
Direction
Vertical
Direction
Red 1100 (AEGL-3) 222 m
Orange 160 (AEGL-2) 478 m
Yellow 30 (AEGL-1) 903 m
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 26 of 84
Figure 8: Isopleths result of toxic threat zone for Ammonia Gas escaping
Model output of the flammable threat zone for chemical release is given in Table 12
and isopleths are given in Figure 9.
Flammable threat zone:
Table 12: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone
Horizontal Direction
Vertical Direction
Red 96,000 (60 % LEL) 26 m
Yellow 16,000 (10 % LEL) 67 m
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 27 of 84
Figure 9: Isopleths result of flammable threat zone for Ammonia Gas escaping
c) Threat at point
In case of leakage of ammonia gas, the significant effects will be upto 67 m in case
of toxic threat zone with concentration of 16000 ppm. Effect has been worked out at
a point in downwind direction at about 2.87 km distance (Village Ribda) from the
source. Maximum concentration of Ammonia estimated at described point is 1.14
ppm at outdoor and 0.046 ppm in ondoor and Isopleths for the same is shown in
Figure 10.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 28 of 84
Figure 10: Isopleths result of Toxic threat at a point for Ammonia Gas
a) Source Strength
Scenario-2B: Release of Ammonia Gas due to leakage and form burning
puddle (pool fire)
When ammonia will escape from cylinder as a gas and forms a burning puddle,
maximum burn rate in this case will be 2.36 Kg/sec considering maximum attentive
time of 22 seconds. The chemical will escape from the cylinder and burn as a jet fire.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 29 of 84
Figure 11: Source Strength in case of Ammonia Gas escapes (pool fire)
b) Threat zone of thermal radiation from Jet fire
Model output of the threat zone of thermal radiation from jet fire is given in Table 13
and isopleths results are given in Figure 12.
Table 13: Threat zone of thermal radiation from jet fire
Threat Zone
Thermal Radiation from fire ball, kw/m2
Threat Zone Radial Distance
Red 10 (Potentially lethal within 60 sec.) 10 m
Orange 5 (2nd 10 m degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 14 m
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 30 of 84
Figure 12: Isopleths result of Thermal radiation from jet fire
c) Threat at point
Effect has been worked out at a point in downwind direction at about 2.87 km
distance (at Village Ribda) from the source. There will be no significant concentration
or effect at given distance.
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When ammonia will escape from cylinder as a gas and forms a fire ball, diameter of
fire ball will be 21 m and burn duration will be 2 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 14 & Figure 13.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 31 of 84
Table 14: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance
Red 10 (Potentially lethal within 60 sec.) 34 m
Orange 5 (2nd 50 m degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 78 m
Figure 13: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction at about 2.87 km
distance (At Village Ribda) from the source. The maximum thermal radiation
estimated at point will be 0.00111 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 32 of 84
3)
The possibilities of source strength considered at the time of accidents due to
leackage of Ammonia from hole of 1 cm diameter at bottom of barrel are mentioned
in Table 15.
AMMONIA LIQUOR
Table 15: Source Strength considered for Ammonia
Particulars Value
Puddle Diameter 1 m
Mass in the Puddle 35 kg
Internal temperature 32 ºC
a) Source Strength
Scenario-A: Release of Ammonia due to leakage and form evaporating puddle (Not burning)
In case of Ammonia escape from barell and forms an evaporating puddle, maximum
average sustained release rate will be 320 gm/min and hence approx. 4.15 Kg of
Ammonia will be released in about 1 hour. Isopleths results are given in Figure 14.
Figure 14: Source Strength in case of Ammonia escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 33 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Ammonia release is given in Table 16. Toxic
Threat zone is given in Figure 15.
Table 16: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 1100 (AEGL-3) 14
Orange 160 (AEGL-2) 41
Yellow 30 (AEGL-1) 98
Figure 15: Threat zone of toxic liquid concentration
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 34 of 84
Model output of the flammable threat zone for chemical release is given in Table 17.
Flammable threat zone:
Table 17: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 90,000 (60 % LEL) <10
Yellow 15,000 (10 % LEL) <10
Flammable threat zone was not drawn because effect of near field patichiness
makes the dispersion less reliable for short distance.
c) Threat at Point
In case of leakage of Ammonia from barrel, the significant effects will be upto 98
meter in case of toxic threat zone with concentration of 30 ppm. Effect has been
worked out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Ammonia estimated at
described point is 28.8 ppm at outdoor and 2.53 ppm in indoor and Isopleths for the
same is shown in Figure 16.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 35 of 84
Figure 16: Isopleths result of Toxic threat at a point for Ammonia
4)
The possibilities of source strength considered at the time of accidents due to
leackage of Acetone from hole of 0.5 inch diameter at bottom of barrel are
mentioned in Table 18.
ACETONE
Table 18: Source Strength considered for Acetone
Particulars Value
Barrel diameter 0.55 m
Barrel height 0.85 m
Barrel volume 200 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Acetone due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Acetone escape from barrel by a hole of 0.5 inch, maximum average
sustained release rate will be 4.12 kg/min and hence approx. 157 Kg of Acetone will
be released in about 1 hour. Isopleths results are given in Figure 17.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 36 of 84
Figure 17: Source Strength in case of Acetone escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 37 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Acetone release is given in Table 19. Toxic
threat zone was not drawn because effects of near-field patchiness make dispersion
prediction less reliable for short distances.
Table 19: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 5700 (AEGL-3) <10
Orange 3200 (AEGL-2) <10
Yellow 200 (AEGL-1) 34
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 20.
Table 20: Flammable area of vapour cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 15,600 (60 % LEL) <10
Yellow 2,600 (10 % LEL) <10
Threat zone for flammable area of vapor cloud is not drawn because effects of near-
field patchiness make dispersion predications less reliable for short distances.
a) Threat at Point
In case of leakage of Acetone from barrel, the significant effects will be upto 34
meter in case of toxic threat zone with concentration of 200 ppm. Effect has been
worked out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Acetone estimated at described
point is 28 ppm at outdoor and 8.22 ppm in indoor and Isopleths for the same is
shown in Figure 18.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 38 of 84
Figure 18: Isopleths result of Toxic threat at a point for Acetone
a) Source Strength
Scenario-2B: Release of Acetone due to leakage & burns as a Pool fire
When Acetone escaped from barrel as a liquid and forms a burning puddle,
maximum burn rate in this case will be 5.82 Kg/min considering maximum attentive
time of 28 min. Moreover, puddle will be spread to a diameter of 1.6 m. Isopleths
results are given in Figure 19.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 39 of 84
Figure 19: Source Strength in case of Acetone escapes (pool fire)
b) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from jet fire is given in Table 21.
Table 21: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2
Threat Zone Radial Distance
(m)
Red 10 (Potentially lethal within 60 sec.) < 10
Orange 5 (2nd < 10 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) < 10
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. Maximum thermal radiation will be
0.00323 kw/m2. Isopleths results are given in Figure 20.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 40 of 84
Figure 20: Thermal radiation at a point in case of Acetone escapes (pool fire)
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Acetone will be released from barrel as a liquid and forms a fire ball, diameter
of fire ball will be 130 m and burn duration will be 3 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 22 & Figure 21.
Table 22: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 58
Orange 5 (2nd 83 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 130
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 41 of 84
Figure 21: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 3.42 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 42 of 84
5)
The possibilities of source strength considered at the time of accidents due to
leackage of Cyclo Hexyl Isocynate from hole of 0.5 inch diameter at bottom of barrel
are mentioned in Table 22.
CYCLO HEXYL ISOCYNATE
Table 22: Source Strength considered for Cyclo Hexyl Isocynate
Particulars Value
Barrel diameter 0.3 m
Barrel height 0.7 m
Barrel volume 49.5 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Cyclo Hexyl Isocynate due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Cyclo Hexyl Isocynate escape from barrel by a hole of 0.5 inch, maximum
average sustained release rate will be 35.8 gm/min and hence approx. 2.04 kg of
Cyclo Hexyl Isocynate will be released in about 1 hour. Isopleths results are given in
Figure 22.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 43 of 84
Figure 22: Source Strength in case of Cyclo Hexyl Isocynate escape
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Cyclo Hexyl Isocynate release is given in Table
24. Toxic Threat zone is given in Figure 23.
Table 24: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 0.1 (AEGL-3) 107
Orange 0.034 (AEGL-2) 185
Yellow NA (AEGL-1) No recommended LOC
value
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 44 of 84
Figure 23: Threat zone of toxic liquid concentration
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 45 of 84
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 25.
Threat zone was not drawn because effects of near-field patchiness make dispersion
results less reliable for short distances.
Table 25: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 6,600 (60 % LEL) < 10
Yellow 1,100 (10 % LEL) < 10
c) Threat at Point
In case of leakage of Cyclo Hexyl Isocynate from barrel, the significant effects will be
upto 185 meter in case of toxic threat zone with concentration of 0.034 ppm. Effect
has been worked out at a point in downwind direction within the premises at about
100 meters distance from the source. Maximum concentration of Cyclo Hexyl
Isocynate estimated at described point is 0.114 ppm at outdoor and 0.047 ppm in
indoor and Isopleths for the same is shown in Figure 24.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 46 of 84
Figure 24: Isopleths result of Toxic threat at a point for Cyclo Hexyl Isocynate
The chemical is below its flash point and is unlikely to catch on fire.
Scenario-2B: Release of Cyclo Hexyl Isocynate due to leakage & burns as a
Pool fire)
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Cyclo Hexyl Isocynate will be released from barrel as a liquid and forms a fire
ball, diameter of fire ball will be 94 m and burn duration will be 2 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 26 & Figure 25.
Table 26: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 42
Orange 5 (2nd 60 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 94
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 47 of 84
Figure 25: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 1.76 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 48 of 84
6)
The possibilities of source strength considered at the time of accidents due to
leakage of Formic Acid from hole of 0.5 inch diameter at bottom of barrel are
mentioned in Table 27.
FORMIC ACID
Table 27: Source Strength considered for Formic Acid
Particulars Value
Barrel diameter 0.55 m
Barrel height 0.85 m
Barrel volume 216 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Formic Acid due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Formic Acid escape from barrel by a hole of 0.5 inch, maximum average
sustained release rate will be 1.73 kg/min and hence approx. 78.7 Kg of Formic Acid
will be released in about 1 hour. Isopleths results are given in Figure 26.
Figure 26: Source Strength in case of Formic Acid escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 49 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Formic Acid release is given in Table 28. Toxic
Threat zone is given in Figure 27.
Table 28: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 250 (ERPG-3) 14
Orange 25 (ERPG-2) 75
Yellow 3 (ERPG-1) 227
Figure 27: Threat zone of toxic liquid concentration
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 50 of 84
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 29.
Table 29: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 72,000 (60 % LEL) <10
Yellow 12,000 (10 % LEL) < 10
Threat zone for flammable area of vapor cloud is not drawn because effects of near-
field patchiness make dispersion predications less reliable for short distances.
c) Threat at Point
In case of leakage of Formic Acid from barrel, the significant effects will be upto 227
m in case of toxic threat zone with concentration of 3 ppm. Effect has been worked
out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Formic Acid estimated at
described point is 14.6 ppm at outdoor and 4.95 ppm in indoor and Isopleths for the
same is shown in Figure 28.
Figure 28: Isopleths result of Toxic threat at a point for Formic Acid
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 51 of 84
The chemical is below its flash point and is unlikely to catch on fire.
Scenario-2B: Release of Formic Acid due to leakage & burns as a Pool fire
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Formic Acid will be released from barrel as a liquid and forms a fire ball,
diameter of fire ball will be 32 m and burn duration will be 3 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 30 & Figure 29.
Table 30: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 18
Orange 5 (2nd 34 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 59
Figure 29: Isopleths result of threat zone of thermal radiation from BLEVE
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 52 of 84
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 0.726 kW/m2
7)
.
The possibilities of source strength considered at the time of accidents due to
leakage of Hydrazine from hole of 0.5 inch diameter at bottom of barrel are
mentioned in Table 31.
HYDRAZINE
Table 31: Source Strength considered for Hydrazine
Particulars Value
Barrel diameter 0.55 m
Barrel height 0.85 m
Barrel volume 216 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 53 of 84
a) Source Strength
Scenario-1A: Release of Hydrazine due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Hydrazine escape from barrel by a hole of 0.5 inch, maximum average
sustained release rate will be 494 gm/min and hence approx. 22.9 Kg of Hydrazine
will be released in about 1 hour. Isopleths results are given in Figure 30.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 54 of 84
Figure 30: Source Strength in case of Hydrazine escape
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Hydrazine release is given in Table 32. Toxic
Threat zone is given in Figure 31.
Table 32: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 35 (AEGL-3) 36
Orange 13 (AEGL-2) 65
Yellow 0.1 (AEGL-1) 843
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 55 of 84
Figure 31: Threat zone of toxic liquid concentration
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 33.
Table 33: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 28,020 (60 % LEL) <10
Yellow 4,670 (10 % LEL) <10
Threat zone for flammable area of vapor cloud is not drawn because effects of near-
field patchiness make dispersion predications less reliable for short distances.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 56 of 84
c) Threat at Point
In case of leakage of Hydrazine from barrel, the significant effects will be upto 843 m
in case of toxic threat zone with concentration of 0.1 ppm. Effect has been worked
out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Hydrazine estimated at
described point is 5.93 ppm at outdoor and 2.06 ppm in indoor and Isopleths for the
same is shown in Figure 32.
Figure 32: Isopleths result of Toxic threat at a point for Hydrazine
The chemical is below its flash point and is unlikely to catch on fire.
Scenario-2B: Release of Hydrazine due to leakage & burns as a Pool fire
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Hydrazine will be released from barrel as a liquid and forms a fire ball,
diameter of fire ball will be 34 m and burn duration will be 3 seconds.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 57 of 84
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 36 & Figure 33.
Table 34: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 47
Orange 5 (2nd 68 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 108
Figure 33: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Figure 50: Isopleths result of threat zone of thermal radiation from BLEVE
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 2.33 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 58 of 84
8)
The possibilities of source strength considered at the time of accidents due to
leakage of Mono Chloro Benzene from hole of 0.5 inch diameter at bottom of barrel
are mentioned in Table 35.
MONO CHLORO BENZENE
Table 35: Source Strength considered for Mono Chloro Benzene
Particulars Value
Barrel diameter 0.55 m
Barrel height 0.85 m
Barrel volume 216 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Mono Chloro Benzene due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Mono Chloro Benzene escape from barrel by a hole of 0.5 inch, maximum
average sustained release rate will be 1.17 kg/min and hence approx. 53.5 Kg of
Mono Chloro Benzene will be released in about 1 hour. Isopleths results are given in
Figure 34.
Figure 34: Source Strength in case of Mono Chloro Benzene escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 59 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Mono Chloro Benzene release is given in
Table 36. Toxic Threat zone is given in Figure 35. However, Toxic threat zone was
not drawn for Red and Orange zone because effect of near-field patchiness made
dispersion predictions less reliable for short distances
Table 36: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 400 (AEGL-3) <10
Orange 150 (AEGL-2) <10
Yellow 10 (AEGL-1) 61
Figure 35: Threat zone of toxic liquid concentration
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 60 of 84
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 37.
Threat zone was not drawn because effects of near-field patchiness made dispersion
predictions less reliable for short distances.
Table 37: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 7,800 (60 % LEL) <10
Yellow 1,300 (10 % LEL) <10
a) Threat at Point
In case of leakage of Mono Chloro Benzene from barrel, the significant effects will be
upto 61 meter in case of toxic threat zone with concentration of 10 ppm. Effect has
been worked out at a point in downwind direction within the premises at about 100
meters distance from the source. Maximum concentration of Mono Chloro Benzene
estimated at described point is 4.02 ppm at outdoor and 1.37 ppm in indoor and
Isopleths for the same is shown in Figure 36.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 61 of 84
Figure 36: Isopleths result of Toxic threat at a point for Mono Chloro Benzene
a) Source Strength
Scenario-2B: Release of Mono Chloro Benzene due to leakage & burns as a
Pool fire)
When Mono Chloro Benzene escaped from barrel as a liquid and forms a burning
puddle, maximum burn rate in this case will be 6.9 Kg/min considering maximum
attentive time of 33 min. Moreover, puddle will be spread to a diameter of 1.6 m.
Isopleths results are given in Figure 37.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 62 of 84
Figure 37: Source Strength in case of Mono Chloro Benzene escapes (pool fire)
b) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from pool fire is given in Table
38.
Table 38: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2
Threat Zone Radial Distance
(m)
Red 10 (Potentially lethal within 60 sec.) <10
Orange 5 (2nd <10 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) <10
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 63 of 84
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. Maximum thermal radiation will be
0.00368 kw/m2. Isopleths results are given in Figure 38.
Figure 38: Thermal radiation at a point in case of Mono Chloro Benzene escapes (pool fire)
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Mono Chloro Benzene will be released from barrel as a liquid and forms a fire
ball, diameter of fire ball will be 35 m and burn duration will be 3 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 39 & Figure 39.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 64 of 84
Table 39: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 62
Orange 5 (2nd 89 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 139
Figure 39: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 3.93 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 65 of 84
9)
The possibilities of source strength considered at the time of accidents due to
leakage of Phosphorus Trichloride from hole of 0.5 inch diameter at bottom of barrel
are mentioned in Table 40.
PHOSPHORUS TRICHLORIDE
Table 40: Source Strength considered for Phosphorus Trichloride
Particulars Value
Barrel diameter 0.33 m
Barrel height 0.8 m
Barrel volume 68.4 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 30 ºC
a) Source Strength
Scenario-1A: Release of Phosphorus Trichloride due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Phosphorus Trichloride escape from barrel by a hole of 0.5 inch,
maximum average sustained release rate will be 2.84 kg/min and hence approx. 100
Kg of Phosphorus Trichloride will be released in about 1 hour. Isopleths results are
given in Figure 40.
Figure 40: Source Strength in case of Phosphorus Trichloride escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 66 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Phosphorus Trichloride release is given in
Table 41. Toxic Threat zone is given in Figure 41.
Table 41: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 5.6 (AEGL-3) 122
Orange 2.0 (AEGL-2) 206
Yellow 0.34 (AEGL-1) 515
Figure 41: Threat zone of toxic liquid concentration
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 67 of 84
c) Threat at Point
In case of leakage of Phosphorus Trichloride from barrel, the significant effects will
be upto 515 m in case of toxic threat zone with concentration of 0.34 ppm. Effect has
been worked out at a point in downwind direction within the premises at about 100
meters distance from the source. Maximum concentration of Phosphorus Trichloride
estimated at described point is 8.26 ppm at outdoor and 2.31 ppm in indoor and
Isopleths for the same is shown in Figure 42.
Figure 42: Isopleths result of Toxic threat at a point for Phosphorus Trichloride
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 68 of 84
10)
The possibilities of source strength considered at the time of accidents due to
leakage of Thionyl Chloride from hole of 0.5 inch diameter at bottom of barrel are
mentioned in Table 42.
THIONYL CHLORIDE
Table 42: Source Strength considered for Thionyl Chloride
Particulars Value
Barrel diameter 0.33 m
Barrel height 0.8 m
Barrel volume 68.4 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Thionyl Chloride due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Thionyl Chloride escape from barrel by a hole of 0.5 inch, maximum
average sustained release rate will be 2.84 kg/min and hence approx. 100 Kg of
Thionyl Chloride will be released in about 1 hour. Isopleths results are given in
Figure 43.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 69 of 84
Figure 43: Source Strength in case of Thionyl Chloride escape
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Thionyl Chloride release is given in Table 43.
Toxic Threat zone is given in Figure 44.
Table 43: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 5.6(AEGL-3) 122
Orange 2 (AEGL-2) 206
Yellow 0.34 (AEGL-1) 515
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 70 of 84
Figure 44: Threat zone of toxic liquid concentration
c) Threat at Point
In case of leakage of Thionyl Chloride from barrel, the significant effects will be upto
515m in case of toxic threat zone with concentration of 0.34 ppm. Effect has been
worked out at a point in downwind direction within the premises at about 100 meters
distance from the source. Maximum concentration of Thionyl Chloride estimated at
described point is 8.26 ppm at outdoor and 2.31 ppm in indoor and Isopleths for the
same is shown in Figure 45.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 71 of 84
Figure 45: Isopleths result of Toxic threat at a point for Thionyl Chloride
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 72 of 84
11)
The possibilities of source strength considered at the time of accidents due to
leakage of Xylene from hole of 0.5 inch diameter at bottom of barrel are mentioned in
Table 44.
XYLENE
Table 44: Source Strength considered for Xylene
Particulars Value
Barrel diameter 0.55 m
Barrel height 0.85 m
Barrel volume 202 Lit
Opening diameter 0.5 inch
Opening from tank bottom 0 m
Internal temperature 32 ºC
a) Source Strength
Scenario-1A: Release of Xylene due to leakage from Barrel and form evaporating puddle (Not burning)
In case of Xylene escape from barrel by a hole of 0.5 inch, maximum average
sustained release rate will be678 gm/min and hence approx. 31.8 Kg of Xylene will
be released in about 1 hour. Isopleths results are given in Figure 46.
Figure 46: Source Strength in case of Xylene escape
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 73 of 84
b) Threat Zone
Toxic Threat Zone
Model output of Toxic threat zone for Xylene release is given in Table 45. Toxic
Threat zone is not drawn because effects of near-field patchiness make the
dispersion less reliable for short distances.
Table 45: Threat zone of toxic liquid concentration
Threat Zone Concentration, ppm
Threat Zone, m
Horizontal Direction
Vertical Direction
Red 1000 (PAC-3) <10
Orange 200 (PAC-2) <10
Yellow 150 (PAC-1) <10
Flammable threat zone:
Model output of the flammable threat zone for chemical release is given in Table 46.
Table 46: Flammable area of vapor cloud
Threat Zone
Concentration, ppm
Threat Zone (m)
Horizontal Direction
Vertical Direction
Red 6,600 (60 % LEL) <10
Yellow 1,100 (10 % LEL) <10
Threat zone for flammable area of vapor cloud is not drawn because effects of near-
field patchiness make dispersion predications less reliable for short distances.
c) Threat at Point
In case of leakage of Xylene from barrel, the significant effects will be upto <10 m in
case of toxic threat zone with concentration of 150 ppm. Effect has been worked out
at a point in downwind direction within the premises at about 100 meters distance
from the source. Maximum concentration of Xylene estimated at described point is
2.46 ppm at outdoor and 0.862 ppm in indoor and Isopleths for the same is shown in
Figure 47.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 74 of 84
Figure 47: Isopleths result of Toxic threat at a point for Xylene
d) Source Strength
Scenario-2B: Release of Xylene due to leakage & burns as a Pool fire)
When Xylene escaped from barrel as a liquid and forms a burning puddle, maximum
burn rate in this case will be 6.16 Kg/min considering maximum attentive time of 29
min. Moreover, puddle will be spread to a diameter of 1.3 m. Isopleths results are
given in Figure 48.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 75 of 84
Figure 48: Source Strength in case of Xylene escapes (pool fire)
e) Threat zone of thermal radiation from pool fire
Model output of the threat zone of thermal radiation from pool fire is given in Table
47.
Table 47: Threat zone of thermal radiation from pool fire
Threat Zone
Thermal Radiation from fire ball, kw/m2
Threat Zone Radial Distance
(m)
Red 10 (Potentially lethal within 60 sec.) <10
Orange 5 (2nd <10 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) <10
f) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. Maximum thermal radiation will be
0.00523 kw/m2. Isopleths results are given in Figure 49.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 76 of 84
Figure 49: Thermal radiation at a point in case of Xylene escapes (pool fire)
a) Source Strength
Scenario-2C: Release of chemical due to catastrophic failure (BLEVE)
When Xylene will be released from barrel as a liquid and forms a fire ball, diameter
of fire ball will be 33 m and burn duration will be 3 seconds.
b) Threat Zone of thermal radiation
Model output and Isopleths result of the threat zone of thermal radiation is given in
Table 48 & Figure 50.
Table 48: Threat zone of thermal radiation from BLEVE
Threat Zone
Thermal Radiation from fire ball, kw/m2 Threat Zone Radial
Distance (m)
Red 10 (Potentially lethal within 60 sec.) 72
Orange 5 (2nd 102 degree burns within 60 sec)
Yellow 2 (Pain within 60 sec) 160
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 77 of 84
Figure 50: Isopleths result of threat zone of thermal radiation from BLEVE
c) Threat at point
Effect has been worked out at a point in downwind direction within the premises at
about 100 meters distance from the source. The maximum thermal radiation
estimated at point will be 5.23 kW/m2.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 78 of 84
Risk Mitigative Measures
Layout and location of hazardous chemical storage are will be based on natural
and mechanical ventilation.
For any case of fire emergency, standard type of Fire extinguishers will be
provided in the storage area as well as required places in the plant.
Regular inspection of all barrels/ drums of hazardous chemicals will be carried
out before it will be taken to the storage area and damaged drums will be
separated and disposed to avoid the possibility of catastrophic rupture.
All equipments related to hazardous chemical storage will be maintained and
calibrated regularly.
A trained person will be deployed for handling operation.
First-aid facility and first-aid trained person will be available at the time of
handling operation.
The adequate and suitable personnel protective equipments will be provided to
the operating workers.
SOP for handling will be displayed in local language for safe operating procedure.
6.
As emergency is said to have risen when operators in the plant are not able to cope
with a potential hazardous situation i.e. loss of an incident causes the plant to go
beyond its normal operating conditions, thus creating danger. When such an
emergency evolves, chain of events which affect the normal working within the
factory area and / or which may cause injuries, loss of life, substantial damage to
property and environment both inside and around the factory takes place and a
DISASTER is said to have occurred.
Various steps involved in Disaster Management Plan can be summarized as follows:
ONSITE EMERGENCY PLAN AND DISASTER MANAGEMENT PLAN
1. Minimize risk occurrence (Prevention)
2. Rapid Control (emergency response)
3. Effectively rehabitate damaged areas (Restoration)
Disaster Management Plan is evolved by careful scrutiny and interlinking of
a. Types and causes of disaster
b. Technical know-how
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 79 of 84
c. Resource availability
Types of Disaster:
a. Due to Fire and Explosion
b. Due to Vapour Cloud
c. Due to Toxic Gas Release from:
i. Within the Unit
ii. External Sources
d. Hurricane, Flood, Cyclone and other Natural Calamities
This plan is developed to make best possible use of resources to:
• Reduce possibilities of accident.
• Contain the incident and control it with minimum damage.
• Safeguard others
• Rescue the victims and treat them suitable.
• Identify the persons affected/ dead.
• Inform relatives of the causalities.
• Provide authorative information to the news media.
• Preserve relevant records and equipment needed as evidence incase of any
inquiry.
• Rehabilitate the affected areas.
The primary purpose of the on-site emergency plan is to control and contain the
incident and so as to prevent from spreading to nearby plant. It is not possible to
cover every eventuality in the plan and the successful handling of the
emergency will depend on appropriate action and decisions being taken on the spot.
Following three staged activities are suggested as they are co-related and
provide better points for emergency preparedness, emergency action and
subsequent follow up.
6.1 Pre-emergency activity
The following are the details of Pre-emergency plan:
Internal Safety Survey
It is conducted by Safety department.
To identify various hazards in plant area.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 80 of 84
To check protective equipment of workability.
To check various Safety installations.
To check fire system, fire water pumps, water shower etc.
To suggest extra modification required.
Third Party Survey
Experts of consultants conduct Third Party Survey.
To identify various hazards inside the factory.
To conduct survey on available Safety equipments.
To check built in safety system for its efficiency.
To suggest modification/new additions in the system.
Non-Destructive Testing (NDT)
To prepare a list of equipments/pipe lines for non-Destructive testing.
To prepare a plan for replacements/repairs as per testing reports.
To maintain Plant wise record to compare with the last period.
Safety valve Testing
To prepare a list in the plant.
To prepare a periodic schedule for their testing & maintaining record.
To prepare a plan for replacements/repairs.
Fire Fighting system Testing
To prepare a list of fire hydrants, Fire Fighting appliances, Fire water pumps and
other available appliances and maintain the record.
To plan for testing schedule.
To replace defective equipments/accessories.
To check fire water pumps capacity.
To check all fire fighting equipments/appliances under fire services for operability.
Mock drills
To conduct Internal mock drill for training the workers.
To conduct drills to check the performance of workers and equipments.
To know the draw backs/defects of the system and its corrective actions.
Training
To operate regular training of employees for handling various safety equipments.
To train workers for fire emergency.
To educate workers for different type of emergency.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 81 of 84
Personal Protective Equipments (PPE)
To arrange for sufficient quantity of personal protective equipments.
To train workers to use each PPE.
To maintain them in good condition.
Communication
To maintain internal/external communication system in good working condition.
To modify the siren sound for emergency.
To install wind-sacks to indicate wind direction.
Emergency Lights
To check and maintain the emergency lights in control room and selected areas.
To keep sufficient number of torches in supervisor’s cabin/plant and in each
department.
Emergency Control Room
To identify the place of emergency control room.
To identify the alternative emergency control room.
To keep sufficient quantity of PPE in control rooms.
To provide proper telephone system in emergency control room.
To provide plan of the factory showing hazardous points and emergency control
point in emergency control room.
Assembly Points
To identify the location for assembling the plant emergency staff and co-ordinate
in case of emergency
To utilize the services of others to fix assembly points for non essential workers
and to assemble in case of emergency.
Liaison with State Authorities
To keep liaison with police, fire brigade, Factory Inspector, Collector, local
hospital and keep them informed.
To inform them about the requirement in advance.
To keep them informed about mock drills.
6.2 Emergency Time Activities
Under these activities, the staff in the plant at various levels with pre-assigned duties
is expected to work in a coordinated manner to meet emergency situation, remove
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 82 of 84
the emergency conditions and bring the plant to normal with the help of resources
available within and out side the plant. Availability and correct use of different means
of communication and control is an important time activity. Sequence of action in
case of various types of emergencies (Fire and Leakage of chemicals):
Any person noticing fire or explosion or leakage of chemicals from pipeline or
other equipment, should attract attention of nearby personnel by using or siren
available within premises.
The area should be checked clear of people and organize emergency shut down
of the plant/ equipment.
The total quantity of chemical leaked should be ascertained and discharge of Air
pollutants through stack should be stopped.
Other persons in the area will help the injured persons to go out of the
place i.e. at open area and immediately arrange for first aid.
Simultaneously by Telephone he will contact the emergency control centre.
He will inform the Incident controllers and key personnel depending upon the
nature of emergency.
He will also guide the out side agency emergency aid services till the Incident
Controller/ Site Main Controller reaches to the site of Incident.
As soon as Incident controller/Site Main Controller reaches to the site of incident
he will take charge of the situation and guide/advice in tackling the emergency.
It is necessary to know that every one on the site should be accounted for and
that the relatives of causalities will be informed. It is necessary to have an up
dated list of the names of people at site on Holidays and weekly off days.
If the situation is not likely to be controlled by the available sources incident
controller/Site Main controller will assess the situation and declare the emergency
as “OFF SITE EMERGENCY”.
The incident controller/Site Main Controller will continue to do the available
resources to control and contain the emergency till the outside authorities and aid
services reaches to the incident site.
After District Authority reaches to the site, he will extend all the necessary help,
assistance and give required information/data as when required to control &
contain the emergency.
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 83 of 84
6.3 Post – Emergency Activities
A post-emergency base activity of steps taken after the emergency is over so as to
establish the reasons of the emergency and preventive measures to be taken.
The main steps involve:
Collection of records
Conducting inquiries and preventive measures.
Making Insurance claims
Inquiry reports and suggestions Implementations
7.
The Off site emergency plan is made based on events, which could affect people
and Environment out side the premises. The off site plan is largely a matter of
ensuring the co-ordination of proposed services and their readiness as far as
possible, for the specific hazards and problems, which may arise in as incident.
Briefly two main purposes of the plan are as under:
OFF SITE EMERGENCY PLAN
To provide the local district authorities, police, fire brigade, doctors etc. the basic
information of risk and environmental impact assessment and to appraise them of
the consequences and the protection / prevention measures and control plans
and to seek their help to communicate with the public in case of major
emergency.
To assist the district authorities for preparing the off site emergency plan for the
district or particular area. We have made our key personnel and other fully aware
about this aspect. The function of the off site plans are as under:
Structure of the off site emergency plan includes the following:-
Organizational set up-Incident controller /Site main controller, Key personnel, etc
Communication facilities - List of important telephones
Specialized emergency equipment - Fire fighting equipment
Specialized Knowledge - Trained people
Voluntary Organization - Details of organization
Chemical information - MSDS of hazardous substances
Meteorological information - Weather condition, Wind velocity etc
Humanitarian arrangement - Transport, First aid, Ambulance
Risk and Safety Management Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page 84 of 84
Role of the factory management
The on site and off site plans are come together so that the emergency services are
call upon at the appropriate time and are provided with accurate information and a
correct assessment of situation.
Role of local authority
Generally the duty to prepare the off-site plan lies with the local authority. They may
have appointed an emergency planning officer (EPO) to prepare whole range of
different emergency within the local authority area.
Role of fire authority
The control of a fire is normally the responsibility of the senior fire brigade officer who
would take over the handling of fire from the Incident Controller on arrival at the site.
Role of police
The overall control of an emergency is normally assumed by the police with a senior
officer designated as emergency coordinating officer. Formal duties of the police
during emergency include protection of life and property and controlling traffic
movements.
Role of health authorities
Health authorities, including doctors, surgeons, hospitals, ambulances etc. have a
vital role to play following a major accident and they should form an integral part of
the emergency plan. Major off site incidents are likely to require medical equipments
and facilities in addition to those available locally.
Role of the “mutual aid” agencies
Some types of mutual aids are available from the surrounding factories, as per need,
as a part of the on site and off site emergency plan.
The role of the factory inspectorate
In the event of an accident, the factory inspector will assist the District Emergency
Authority for information and help in getting mutual aid from surrounding factories.
Unit maintains the records of details of emergency occur, corrective preventive
measures taken and in future the same practice will be continue. Unit has displayed
the details like list of assembly points, name of the persons involve in the safety
team like site controller, incident controller etc.
ANNEXURE- 8
Undertaking by the project proponent and consultant
REGO. OFF.: 3rd Floor, Aka8h Ganga Complex, B/8. Suvidha Shopping Centre, EnvisafeNr. Parimal Underpass, Paldi, Ahmedabad-380 007. Gujarat, INDIA. Tele/Fax: +91 7926650878, 26650473 E·mail : [email protected] Environment Consultants
Environmental Consultancy & laboratory
UNDERTAKING
I THE UNDERSIGNED; PUSHPIN V. SHAH AS A PROPRIETOR OF MIS. ENVISAFE
ENVIRONMENT CONSULTANTS HAVING OFFICE AT 3rd Floor, AKASH GANGA COMPLEX,
BESIDES SUVIDHA SHOPPING CENTRE, NEAR PARIMAL UNDERPASS, PALDI,
AHMEDABAD-380007; DO HEREBY UNDERTAKE AS FOLLOWS;
(1) OURS IS AN ORGANIZATION ACCREDITED AS AN EIA CONSULTANT
ORGANIZATION BY NATIONAL ACCREDITATION BOARD FOR EDUCATION AND
TRAINING, QUALITY COUNCIL OF INDIA (NABET/QCI), NEW DELHI.
(2) WE HAVE BEEN ASSIGNED RESPONSIBILITY AS AN EIA CONSULTANT TO CARRY
OUT EIA STUDY FOR PROPOSED PROJECT OF MIS. ASCENT PHARMA LOCATED
AT SURVEY NO. 163/9 & 11 ON S.I.D.C. ROAD IN SHAPAR-VERAVAL INDUSTRIAL
AREA, TALUKA KOTADA SANGANI, DISTRICT RAJKOT.
(3) THE EIA STUDY IS CARRIED OUT AS PER THE GUIDELINES OF THE MINISTRY OF
ENVIRONMENT, FOREST AND CLIMATE CHANGE (MoEF&CC), NEW DELHI AND
THE EIA REPORT IS PREPARED CONSIDERING THE GENERIC STRUCTURE
PROVIDED IN THE APPENDIX III AND lilA OF THE EIA NOTIFICATION, 2006
(4) TORs ISSUED BY MOEF VIDE LETTER NO. J-11011/210/2013-IA-1I (I) DATED
07/11/2013 HAVE BEEN ADDRESSED AND INCORPORATED IN ALL RESPECTS IN
THE EIA REPORT SUBMITTED HEREWITH.
(5) ALL THE DATA SUBMITTED IN THIS ENVIRONMENTAL IMPACT ASSESSMENT
REPORT IS FACTUALLY CORRECT.
I SOLEMNLY AFFIRMED THAT THE ABOVE STATED DETAILS ARE TRUE TO THE BEST
OF MY KNOWLEDGE AND BELIEF.
DATE: Oi \ O~ 12-016' w· NAME: PUSHPIN V. SHAHPLACE: AHMEDABAD
Branch: 27, Akash Villas, Near 500 Quarters, G.I.D.C, New Colony, ANKLESHWAR - 393 002. Dist : Bharuch Mob. : +91 9328961241
Annexure-8
Undertaking by Proponent
ANNEXURE- 9
Project Summary & Conclusion as per the generic structure of EIA notification
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.1
PROJECT SUMMARY & CONCLUSIONS
11.1
M/s. Ascent Pharma is an existing small scale unit located at Survey No. 163/9 & 11 on
S.I.D.C. Road in Shapar-Veraval Industrial Area of Village Veraval (Shapar) in Kotada
Sangani Taluka of Rajkot District in Gujarat state. At present the unit is manufacturing
various Inorganic Chemicals with the total production capacity of 50 TPM. Now, considering
the market demand, the unit intends to manufacture various Bulk Drugs & Drugs
Intermediates (Synthetic Organic Chemicals) with total production capacity of 55 TPM within
the existing premises by utilizing existing infrastructure facilities with the addition of new
machineries.
PROJECT DESCRIPTION
Unit has applied for grant of EC for the proposed expansion at MoEF under 5(f)-A category
since the project site is located outside the notified industrial area. Hence, ToR was issued
by MoEF vide file no. J-11011/210/2013-IA.II (I) dated 7th November 2013. Public Hearing
for the proposed project was conducted by Gujarat Pollution Control Board on 15th October
2014 and EIA report was submitted on 10th
Now, as per the amendment to EIA Notification 2006 vide SO 1599 (E) dated 25
November 2014.
th June
2014, small scale units are categorized under Category B projects. Meeting the criteria of
water consumption less than 25 m3/day, fuel consumption less than 25 TPD and not covered
in the category of MAH units as per MSIHC Rule, 1989, MoEF has transferred the
application vide file no. J-11011/108/2013-IA II (I) dated 23rd February 2015 to SEIAA,
Gujarat which was received on 9th
The EIA Study has been carried out by M/s. Envisafe Environment Consultants,
Ahmedabad, Gujarat which is based on one season field data collected from the study area
during December 2013 to February 2014 (Winter Season) and the same data has been used
in assessment of impacts due to the proposed project.
March 2015 by SEIAA.
Status
DETAILS OF PROPOSED PROJECT
: Small Scale Unit; Proposed Project for manufacturing
of various Bulk Drugs & Drugs Intermediates within
the existing premises
Product & Capacity :
Sr. No.
Name of Product Capacity TPM
Existing Proposed Total
Products
1 Potassium Nitrate 10.0 Nil 10.0
2 Potassium Sulphate 10.0 Nil 10.0
3 Magnesium Hydroxide 10.0 Nil 10.0
4 Potassium Chloride 10.0 Nil 10.0
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.2
5 Potassium Iodide 10.0 Nil 10.0
6 Oxyclozanide Nil 25.0 25.0
7 Glibenclamide Nil 20.0 20.0
8 A. 1,2,4 Triazole
Nil 10.0 10.0 B. 4-Amino -1,2,4 Triazole
Total 50.0 55.0 105.0
By-Product
1 Hydrochloric Acid (30%) Nil 15.5 15.5
2 Sodium Bi-Sulphite Nil 26.0 26.0
3 Phosphorous Acid Aq. Nil 3.3 3.3
Use of Products : The products are widely used in pharmaceutical
industries for manufacturing of medicines and drugs.
Land Type & Availability
General Information:
: Proposed project will be carried out within the
existing industrial premises having an area of 2,292
sq.m. and no additional land will be required for the
proposed project.
Capital Investment, (Lacs) : Existing: 48.57, Proposed: 36.50 & Total: 85.07
Capital Investment for EMP, Lacs
: Proposed: 5.5
Recurring Cost for EMP, Lacs/Annum
: Existing: 2.10, Proposed: 4.65 & Total: 6.75
CSR Cost, Lacs/Annum : 0.5
Raw materials
Resources requirements:
: After proposed project, about 18 raw materials will be
required including 5 solvents. All the raw materials
are available in the local market.
Source of water supply : Water supply by Veraval (Shapar) Gram Panchayat
through tanker OR private water supply through
tanker
Fresh Water Requirement, KLD
:
Existing: 1.7, Proposed: 6.51, Total: 8.21
Industrial:
Existing: 0.5, Proposed: 1.5, Total: 2.0
Domestic:
Existing: 0.5, Proposed: 0.8, Total: 1.3
Gardening:
Power Source : Pashchim Gujarat Vij Company Ltd. (PGVCL)
Power Requirement : Existing:45 KVA, Proposed: 15 KVA, Total: 60 KVA
Fuel Requirement : FO/ LDO (KL/Month)
Existing:1.5; Proposed:1.5 ; Total: 3.0
:
Manpower Requirement, Nos.
: Existing: 11; Proposed: 27 & Total: 38
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.3
11.2 POLLUTION POTENTIAL & CONTROL MEASURES
Effluent Generation &
Management
Water Pollution:
: Source of Effluent
Process, APCM, Boiler, Cooling, Washing
:
Existing: Industrial: Nil; Domestic: 0.40
Effluent Generation (KLD)
Proposed: Industrial: 1.70; Domestic: 1.20
Total: Industrial: 1.70; Domestic: 1.60
Presently there is no effluent generation form the
existing unit and unit maintains the Zero Effluent
Discharge. The industrial effluent generation from
the proposed project will be @ 2.10 KLD, from which
0.40 KLD of condensate water from process will be
recovered & reused in cooling make-up and for
remaining 1.7 KLD effluent, the unit has proposed to
install an effluent treatment plant (ETP) comprising
of primary, secondary & tertiary treatment which will
be adequate to achieve the discharge norms
prescribed by GPCB. After treatment into ETP, the
total quantity of effluent will be used for gardening
and plantation within the premises.
Management:
The Domestic wastewater after the proposed project
will be increased from 0.40 KLD to 1.60 KLD, which
will be discharged in to soak pit through septic tank
as per the current practice.
Flue gas emission
control
Air Pollution:
: Unit has installed steam boiler of 0.8 TPH wherein
LDO/Furnace Oil is used as fuel. The same boiler
will be utilized after the proposed project.
Existing fuel requirement is 1.5 KL/month which will
be increased upto 4.5 KL/month after the proposed
project.
Adequate stack height of 12 m is provided for proper
dispersion of pollutant from the steam boiler. Hence,
there will be no requirement to provide any
additional air pollution control system for flue gas
emission for the proposed project.
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.4
Process gas emission
control
: There is no any process emission from the existing
manufacturing unit. The only source of process gas
emission from the proposed manufacturing activity
will be HCl & SO2 gas generated from the
manufacturing of Oxyclozanide. Hence, The
adequate water scrubber followed by alkali scrubber
will be provided for the control of process gas
emission
: Hazardous Waste
Management:
All the hazardous waste will be collected, stored,
handled, transported and disposed as per the
Hazardous Waste (Management, Handling
&Transboundary Movement) Rules, 1989 as
Amended in 2008.
The unit has obtained membership of GPCB
approved TSDF/ CHWIF of M/s. Saurashtra Enviro
Projects Pvt. Ltd. for the disposal of hazardous
waste.
: Noise & Vibration: There is no major source of noise and vibration from
the existing as well as proposed manufacturing
activity. Also, there is no D.G. set in existing unit and
will not provided after proposed project and no other
source of noise and vibration from the proposed
project. However, adequate precautionary measure
for noise and vibration control measures as
described below will be taken by the unit.
11.3
The baseline environmental quality of air, water, soil, noise, socioeconomic status
and ecology has been assessed in the winter season (December 2013 to February
2014). For the EIA study, the area falling within 10 km radial distance from project
site has been selected for preparing the site map along with infrastructure setup and
administrative map, land use/land cover map and socio-economic study whereas the
area falling within 5 km was considered to monitor the base line environment quality.
Baseline study was conducted as per the approved TORs issued by MoEF and
guidelines of MoEF/CPCB.
BASELINE ENVIRONMENT, IMPACTS ASSESSMENT & MITIGATION MEASURES
11.3.1 Topography & Geology
The area is almost flat. The ground gradients are mild and sloping from West to
East. In and around the study area comprises of Deccan Trap Basalts. This trap
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.5
rocks appears gently tilted at places. This Deccan Trap flows comprises massive,
hard and tough Amygdaloidal Basalt, Vesicular fine grained basalts; Porphyritic
basalts, Geodes with Zeolite, Chalcedony, Agate and Calcite are often in
Amygdaloidal types. In and around the study area is covered by thick Mantle of soil.
11.3.2 Seismology
Study area falls in Zone III as per IS 1893 (Part-I):2002, which is referred as
Moderate Damage Risk Zone. The area is liable to earthquakes of Modified Mercalli
Intensity Scale VII.
11.3.3 Micro Meteorology
The site-specific micrometeorological data was collected continuously during the
study period by installing automatic weather station at project site. During the study
period wind was blowing mostly from NNW with average speed of 0.85 m/s and
maximum speed of 7.1 m/s. Average temperature recorded was 20.1°C with
maximum temperature of 34.3°C and minimum of 12.1°C. The average relative
humidity was recorded as 46% and maximum as 83%.
11.3.4 Ambient Air
Baseline Scenario
The ambient air samples were collected from six locations and analyzed for PM
:
10,
PM2.5, SO2, NOx, HCl, NH3, CO & VOC. All the parameters are well within the
NAAQS except PM10 at three locations including project site. HCl concentration at
project site was also well within the GPCB norms prescribed for industrial area. It
was below detectable limit at other locations. VOC and NH3
PM
concentration (as
isobutylene) was below detectable limit (BDL) at all locations.
10 concentration at project site was higher due to surrounding industrialization in
Shapar-veraval industrial estate. Also, villages Ribda and Pipaliyapal are located in
predominant downwind direction from project site & Shapar-Veraval industrial area
and proximity to the NH 8B being the main reason for higher PM10 concentration.
• The maximum 24-hourly average ground level concentration for pollutants due to
proposed project calculated using mathematical model (ISCST3) for PM
Impacts Assessment:
10, SO2,
NOx and HCl. Maximum Incremental concentration for PM10, SO2, NOx and HCl
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.6
is 0.0798, 0.2786, 0.2778 and 0.0004 respectively even for the worst case
scenario.
• There will be the fugitive dust emissions due to the manufacturing activities, raw
materials handling, loading and unloading of raw materials and finished goods,
conveying and feeding point, vehicular movements, etc.
• An adequate stack height of 12.0 meter is provided for proper dispersion of
pollutant, which will also be adequate after proposed expansion.
Mitigation Measures to be Adopted:
• The adequate scrubbing system like water scrubber followed by alkali scrubber is
proposed to control the process gas emission of SO2
• In addition to the above, unit will take adequate measures for the control of
fugitive emissions after the proposed expansion.
and HCl from
manufacturing activity after the proposed project.
11.3.5 Water Environment
• Ground water samples were collected from the five locations and pipe water was
collected from project site once during the study period. TDS was higher than the
permissible limit at Pardi Village. Total Hardness was found higher than the
permissible limit at Pardi, Veraval (Shapar) and Ribda Village. Heavy metals and
other parameters except specified above were well within the permissible limit at
all locations and water collected from all the location is fit for the drinking
purposes except the ground water of Pardi Village.
Baseline Scenario:
• Presently the entire water requirement of unit is met through water supply by
Veraval (Shapar) Gram Panchayat through tanker and same source will be
utilized after proposed expansion. Unit also sources water from Private water
supplier through tankers in case of non-availability of main source. After
proposed expansion also, this will be kept as stand by source. Hence, there will
not be any direct impact envisaged on the ground water.
Impacts Assessment:
• There may be risk of ground water and surface water contamination due to
wastewater generation, handling and treated wastewater utilization for Greenbelt
development.
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.7
• The unit will explore the opportunities for rainwater harvesting and groundwater
recharge. Hence, there will not be any adverse impact on water environment due
to water availability and water requirement of the proposed activity.
Mitigation Measures to be Adopted:
• For effective treatment; safe handling and disposal of effluent, the unit has
proposed to install their own effluent treatment plant (ETP) comprising of primary,
secondary & tertiary treatment which will be adequate to treat proposed effluent
load.
• Treated effluent after confirming norms prescribed by GPCB, will be used for
gardening and plantation within the premises.
• Domestic wastewater will be discharged through septic tank into soak pit.
• Thus, there will not be any adverse impact on water environment.
11.3.6 Noise
Noise level monitoring has been conducted at project site and 6 surrounding villages.
The monitored noise levels have been compared with the standards prescribed by
MoEF which indicates that Noise levels at project site were found well within the limit
for day & night time. Noise levels at surrounding villages were found slightly higher
during day time.
Baseline Scenario:
Due to proximity of NH-8B to the surrounding villages, traffic load is observed high
during day as well as night time being the reason for increasing level of Noise.
During operation phase of the proposed project, the impact on noise environment will
be due to manufacturing activities, utilities and transportation activities
(transportation of raw materials and finished products).
Impacts Assessment
The noise pollution management will be taken up by selecting low noise generating
equipment, Isolating the noise generating equipments and working area and by
administrative & safety measures, providing noise level monitoring, remedial
measures, providing noise safety appliances to the working personnel.
Mitigation Measures to be adopted
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.8
11.3.7 Soil Quality
Soil samping has been carried out for project site and surrounding 5 villages. Water
Holding Capacity of soil samples were in range of 32% (Veraval (Shapar) Village) to
40% (Gundasara Village). The texture of soil is observed mainly Sandy Clay Loam in
the study area. The concentration of available Nitrogen, Phosphorous and
Potassium were in the range of 0.3 to 1.2 gm/Kg, 0.04 to 0.1 gm/Kg and 0.5 to 1.0
gm/Kg respectively, which signifies that the soil of the area is fertile. The organic
matter in the soil ranged from 1.2 to 3.9 mg/Kg.
Baseline Scenario:
• During operation activity the impact of air, water and hazardous waste pollution
will cause direct / indirect effect on soil.
Impacts Assessment
• In operational phase there will be chances of soil contamination due to improper
working of machineries or during transportation of raw materials or finished
products.
• Soil quality may be affected by use of treated wastewater for gardening purpose.
• Effluent treatment plant with primary, secondary and tertiary units is proposed for
adequate treatment of effluent generated. Treated effluent meeting GPCB
prescribed norms will be utilized for greenbelt development.
Mitigation Measures to be adopted
• An adequate stack height of 12.0 meter is provided for proper dispersion of
pollutant to avoid any soil contamination by air pollutants.
• Regular maintenance of plants and machineries will be carried out and proper
care taken while loading, unloading and transfer of materials to avoid any soil
contamination.
11.3.8 Land Use Pattern
Classification of land use/land cover was derived using GIS software from satellite
image. About 68.96% of the study area is covered under agricultural land. There is
3.55% land acquired for the industrial purposes in the study area. 0.96 % area is
water body consists of lake/pond and river.
Baseline Scenario:
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.9
Also, there is no protected area notified under the Wild Life (Protection) Act (1972) &
Eco - sensitive area notified under Section 3 of the Environment (Protection) Act-
1986 exists within 10 Km radius areas from the Plant Site. As per census 2001,
Naranka Reserve Forest falls within the study area and unit has obtained No
Objection Certificate from the Forest Department, Rajkot for the proposed project.
As the proposed project will be carried out within the existing premises, there will not
be any change in land use pattern, forest cover or vegetation in surrounding area.
Impacts Assessment:
11.3.9 Socio-Economic Study
As per the 2011 census, the study area of 10 km from the project site comprises of
total four Talukas of Rajkot District namely Rajkot, Kotada Sangani, Gondal and
Lodhika. There are 41 villages falling within the study area having total population of
around 1,06,313 indicating that the area is sparsely populated with scattered
settlements. Overall literacy rate in the study area is 68.6%, which show that literacy
rate in the study area is comparatively high. The overall employment ratio for the 41
villages in the study area is 44.0%, which shows that employment ratio is low.
Baseline Scenario:
• The proposed project will help to improve the economical status in the study area
by providing more employment opportunities. The area is well developed in terms
of education, communication, health services and banking facilities.
Impacts Assessment
• Unit will increase in employment from existing 11 to 38 workers, based on the
requirement the local people will be given priority.
• Unit will allocate fund up to Rs. 50,000/- for carrying out various CSR activities.
11.3.10 Biological Environment
It is observed during site visit that all flora and fauna species encountered are quite
common and found everywhere. No endangered and rare species were observed.
Also, there are no zoological parks or sanctuaries in the study area.
Baseline Scenario:
Pollutants of air, water and hazardous waste can interfere with the biotic and abiotic
components of the ecosystem and may include injurious effects when concentrations
Impacts Assessment
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.10
exceed permissible limits. All necessary pollution control measures will be provided
and operated efficiently for proposed expansion. Hence, there will not be any
adverse impact of pollution potentials on the surrounding ecology after
commissioning of the proposed project.
Also, existing and proposed green belt area will help in inviting small birds & animals
and other creatures to proliferate.
11.3.11 Greenbelt Development
Unit has already developed green belt in 340 m2 within the premises and this will be
increased up to 760 m2 (33.16% of total area) after the proposed project.
Green belt will not only improve the soil condition but will also prevent soil erosion
and the landscape & give slight beneficial impact on the land usage.
Impacts Assessment
11.4
The environmental management plan is proposed with respect to the all proposed activities
considering affected environmental attributes and impact zone which is summarized here
under:
ENVIRONMENTAL MANAGEMENT PLAN
Sr. No.
Activity Management Plan
1. Manufacturing
activities and
operations of
utilities
Ensure provision of Environmental Management system (EMS) as
proposed / committed for environmental pollution control.
Ensure the efficient operations of provided EMS.
Ensure proper treatment and reuse of treated effluent for greenbelt
development.
Regular monitoring w.r.t. EMS, ambient air quality, work area,
noise, water quality as per the monitoring program.
Review the monitoring reports and take corrective measures as
required.
Ensure the submission of monitoring reports to the concerned
authority as per the norms.
Ensure compliance of stipulated conditions by concerned
authorities.
Ensure optimum use of resources.
Regular monitoring of water consumption.
Maintain proper record of resources utilization.
Ensure the close manufacturing systems in order to minimize
fugitive emissions.
Ensure the regular maintenance of reactors and other process
equipments.
Ensure regular usage of proper PPE's by workers in the plant.
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.11
Sr. No.
Activity Management Plan
Ensure the collection, storage, handling, transportation & disposal
of all the hazardous wastes as per the Hazardous Waste
(Management, Handling & Transboundary Movement) Rules, 1989
as Amended in 2008.
Proper and timely oiling, lubrication, preventive maintenance of all
plant machinery & equipments.
Explore the technology for cleaner production, waste minimization,
treatment/ reuse / recycle / co-incineration of wastes.
2. Storage &
handling of
hazardous
chemicals and
hazardous
waste
Ensure the storage and handling of all the chemicals in a proper
manner to avoid any spillages and also to prevent runoff
contamination in monsoon.
Ensure collection & treatment of spillages, if any ensure good
housekeeping to maintain clean and orderly working environment.
Provide training to the persons handling chemicals & hazardous
wastes.
Ensure the provision of designated hazardous waste storage area
with proper roofing and leachate collection.
Ensure the disposal of hazardous wastes at approved TSDF with
manifest only.
Ensure availability of MSDS of all the Hazardous materials to the
on-site emergency team.
3. Domestic
activities
Regular monitoring of water consumption and ensure optimum use
of water.
Ensure proper discharge of sewage to soak pit through septic
tank.
4. Green belt
development
Maintain existing green belt by regular watering, soil enrichment
work (applying manure) weeding and provide proper protection.
Ensure the further development of greenbelt as proposed.
5. CSR activities Give preference to local people for the recruitment.
Ensure to carry out CSR activities as proposed.
6. Transportation
of hazardous
chemicals and
hazardous
waste
Vehicles must be PUC certified.
Ensure vehicular movement only during day time.
Ensure the transportation only by covered vehicles.
Ensure availability of manifest/TREM card with driver during the
transportation of Hazardous Waste / hazardous chemicals.
Ensure regular maintenance and optimum use of the vehicles.
Educate driver about the characteristics of wastes/ chemicals and
immediate actions in case of any spillage or accident.
Ensure availability of MSDS of all the Hazardous materials to the
Off-site Emergency team.
11.5
From the monitoring point of view, the important components are air, water, soil,
noise and occupational health & safety. Regular monitoring will be carried out after
ENVIRONMENTAL MONITORING PROGRAMME
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.12
the proposed project as per the monitoring program. Unit will establish a small scale
laboratory at ETP area for regular wastewater monitoring. Untreated and treated
wastewater of ETP will be daily analysed with respect to pH, TDS and COD. Flow
meters will be provided at the outlet of ETP for regular monitoring of wastewater
quantity. Unit has already made necessary tie-up with nearby hospitals for the
medical assistance in case of any emergency. Unit will establish a well organized
Environmental Management Cell (EMC) which will perform all the environmental
management activities.
Unit will also prepare EHS policy to adhere with standard operating process in order
to comply with the statue and bring into focus any infringement of any norms and
directives with regards to the Environment, Health & Safety and to take further
corrective actions. Voluntary reporting of environmental performance with reference
to EMP will be undertaken. Plant In-charge will co-ordinate all monitoring programs
at site and data generated will be submitted regularly to the statutory agencies.
Frequency of reporting shall be as per the requirement of GPCB and MoEF.
11.6
The proposed project will be carried out within the existing premises and existing
infrastructure facilities will also be utilized with the addition of new machinery for the
proposed project. Thus, no alternative for the site was considered due to the
availability of infrastructure, land, water sources, fuel transportation, power etc.
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
For the proposed products i.e. various Bulk Drugs & Drugs Intermediates (Synthetic
Organic Chemical), unit will adopt latest and best technology available so far in the
market. Moreover, the unit is very concerns and conscious about the product quality
and equally about the environmental protection and resource conservation; and
hence they put their efforts for replacing/upgrading their existing plant and
machineries from time to time with the best available technology.
11.7
The unit is very much aware of their obligation to protect all persons at work and
others in the neighborhood that may be affected by an unfortunate and unforeseen
incidence occurring at the works. Unit has provided all the adequate safety
measures in the existing plant. After proposed project also, any hazard either to
RISK AND SAFETY MANAGEMENT
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.13
employees or others arising from activities at the plant site shall as far as possible,
be handled by the personnel of the company and prevented from spreading any
further. In the case of eventuality the on-site and off-site emergency plan proposed
by the unit will be adequate and may be able to control the situation. After the
proposed project all the required safety measures will be taken and unit will also
carry out safety audit through authorized agency/organization.
11.8
Unit has contributed reasonably as part of their CSR and carried out various
activities in nearby villages. Unit is spending annually about Rs. 25,000 for such
activities. In addition to this employment opportunity for 27 persons and for many
other skilled-unskilled labors during construction and other ancillary activities during
operation will be generated after the proposed project. Unit has planned to carry out
various activities for the upliftment of poor people, welfare of women & labors,
education of poor students as part of Corporate Social Responsibility (CSR) in the
nearby villages and therefore unit will make additional provision of Rs. 25,000.
Therefore, after proposed project, unit will spent at least Rs. 50,000 every year
towards CSR activities.
PROJECT BENEFITS
11.9
It can be concluded on a positive note that after the implementation of the mitigation
measures and environmental management plans, the proposed project activities
during the construction and operation phase would have manageable & largely have
reversible impacts on the environment and on balance the project would be
beneficial to surrounding communities and the region.
CONCLUSION
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.12
the proposed project as per the monitoring program. Unit will establish a small scale
laboratory at ETP area for regular wastewater monitoring. Untreated and treated
wastewater of ETP will be daily analysed with respect to pH, TDS and COD. Flow
meters will be provided at the outlet of ETP for regular monitoring of wastewater
quantity. Unit has already made necessary tie-up with nearby hospitals for the
medical assistance in case of any emergency. Unit will establish a well organized
Environmental Management Cell (EMC) which will perform all the environmental
management activities.
Unit will also prepare EHS policy to adhere with standard operating process in order
to comply with the statue and bring into focus any infringement of any norms and
directives with regards to the Environment, Health & Safety and to take further
corrective actions. Voluntary reporting of environmental performance with reference
to EMP will be undertaken. Plant In-charge will co-ordinate all monitoring programs
at site and data generated will be submitted regularly to the statutory agencies.
Frequency of reporting shall be as per the requirement of GPCB and MoEF.
11.6
The proposed project will be carried out within the existing premises and existing
infrastructure facilities will also be utilized with the addition of new machinery for the
proposed project. Thus, no alternative for the site was considered due to the
availability of infrastructure, land, water sources, fuel transportation, power etc.
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
For the proposed products i.e. various Bulk Drugs & Drugs Intermediates (Synthetic
Organic Chemical), unit will adopt latest and best technology available so far in the
market. Moreover, the unit is very concerns and conscious about the product quality
and equally about the environmental protection and resource conservation; and
hence they put their efforts for replacing/upgrading their existing plant and
machineries from time to time with the best available technology.
11.7
The unit is very much aware of their obligation to protect all persons at work and
others in the neighborhood that may be affected by an unfortunate and unforeseen
incidence occurring at the works. Unit has provided all the adequate safety
measures in the existing plant. After proposed project also, any hazard either to
RISK AND SAFETY MANAGEMENT
Project Summary & Conclusion Proposed Project for Manufacturing of Synthetic Organic Chemicals
Page | 11.13
employees or others arising from activities at the plant site shall as far as possible,
be handled by the personnel of the company and prevented from spreading any
further. In the case of eventuality the on-site and off-site emergency plan proposed
by the unit will be adequate and may be able to control the situation. After the
proposed project all the required safety measures will be taken and unit will also
carry out safety audit through authorized agency/organization.
11.8
Unit has contributed reasonably as part of their CSR and carried out various
activities in nearby villages. Unit is spending annually about Rs. 25,000 for such
activities. In addition to this employment opportunity for 27 persons and for many
other skilled-unskilled labors during construction and other ancillary activities during
operation will be generated after the proposed project. Unit has planned to carry out
various activities for the upliftment of poor people, welfare of women & labors,
education of poor students as part of Corporate Social Responsibility (CSR) in the
nearby villages and therefore unit will make additional provision of Rs. 25,000.
Therefore, after proposed project, unit will spent at least Rs. 50,000 every year
towards CSR activities.
PROJECT BENEFITS
11.9
It can be concluded on a positive note that after the implementation of the mitigation
measures and environmental management plans, the proposed project activities
during the construction and operation phase would have manageable & largely have
reversible impacts on the environment and on balance the project would be
beneficial to surrounding communities and the region.
CONCLUSION