1.Estimating Concrete and Rebars

download 1.Estimating Concrete and Rebars

of 8

Transcript of 1.Estimating Concrete and Rebars

  • 8/8/2019 1.Estimating Concrete and Rebars

    1/8

    Estimating Concrete and

    Rebar

    Course objectives

    Correctly setting up an estimate

    Calculating the perimeter

    Setting up the concrete foundation takeoff

    Calculating concrete labor and materialcosts

    Concrete takeoff for foundations

    3 methods to use building line

    center line

    sectioning

    Provide HO #1

  • 8/8/2019 1.Estimating Concrete and Rebars

    2/8

    Building line estimates

    Used for small projects (residential)

    fast, easy

    problem counts corners twice

    Add perimeter (48 + 48 + 26 +26) = 148.0 ft. or 2(L + W)

    148.0 ft x 8.0 ft x 0.83 ft = 982.72 cf.

    Sectioning

    Breaks construction down into smallerpieces

    More accurate

    More time consuming

    Use where large volumes of concreterequired, but unusual angles, etc.

  • 8/8/2019 1.Estimating Concrete and Rebars

    3/8

    Sectioning red 2) 24.33 ft x 8.0 ft x 0.83 ft = 323.10 cf.

    blue 2) 48.0 ft x 8.0 ft x 0.83 ft = 637.44 cf. sum = 960.54 cf

    Centerline length

    Avoids adding corners twice

    Most common method in commercial wk

    Useful for conc., rebar, walls, etc.

    Formula to know:

    Outside Building line length or perimeter (4* thickness or width of any given strip)

    Complete in-class activity #1calculate the amount of footingconcrete required

    SOL = Po (4T)

    distance from centerline of theconstruction line to the building line

    = 10 inches (0.83 inches)

  • 8/8/2019 1.Estimating Concrete and Rebars

    4/8

    Centerline length method

    Building line length = (perimeter) = 148.0 ft

    Distance from centerline to bldg. line =

    148.0 ft (4*.83) = 144.67 (true perimeter)

    144.67 ft * 8 ft * 0.83ft = 960.59 cf.

    Centerline length caveat

    Only works if all walls and offsets are 90

    Quick estimating tip

    Short cut for estimating concrete in anyfooting

    Multiply the cross-section in square inchesby 0.000257. Gives CY/lineal ft

    Multiply that result by number of lineal feetin the footing

  • 8/8/2019 1.Estimating Concrete and Rebars

    5/8

    Quick estimating tip illustrated

    Given: A footing 7-in deep and 22-in wideis 160-ft long.

    Calculate the yards of concrete reqd.

    (7" * 22")*160' * .000257 = 6.33 CY

    DO NOT Convert inches to decimals except whenpart of next foot (e.g., 38-7)

    Estimating footings (pads)

    Estimating footings (pads)

    List the description or title from scheduleProvide HO#2

  • 8/8/2019 1.Estimating Concrete and Rebars

    6/8

    Calculating Rebar

    Rebar weight perlinear foot

    See text (pg. 133 forsplicing req.

    Calculating formwork

    2 Types Structural (concrete) formwork

    Foundations

    Walls

    Columns

    Beams

    Flatwork (flat concrete work) Sidewalks

    Driveways Slabs

    Structural (concrete) formwork

    Formwork measured in SFCA

  • 8/8/2019 1.Estimating Concrete and Rebars

    7/8

    Measuring concrete walls

    Use centerlinelength * height* 2

    Refer to HO#1

    Calculate the formworkand concrete required forthe wall

    Labor placing concrete infoundations

    50- 70 CY/8 hr day(direct from truck tofooting)

    How is labor calculated?

    Duration =Quantity of Work

    Rate of Production

    Using HO #1 calculate the duration of the footinginstallation

    (0.35 labor hours/CY use a price of 35$/hour/man

  • 8/8/2019 1.Estimating Concrete and Rebars

    8/8

    Course objectives

    Correctly setting up an estimate

    Calculating the perimeter

    Setting up the concrete foundation takeoff Calculating concrete labor and material

    costs