1.Estimating Concrete and Rebars
Transcript of 1.Estimating Concrete and Rebars
-
8/8/2019 1.Estimating Concrete and Rebars
1/8
Estimating Concrete and
Rebar
Course objectives
Correctly setting up an estimate
Calculating the perimeter
Setting up the concrete foundation takeoff
Calculating concrete labor and materialcosts
Concrete takeoff for foundations
3 methods to use building line
center line
sectioning
Provide HO #1
-
8/8/2019 1.Estimating Concrete and Rebars
2/8
Building line estimates
Used for small projects (residential)
fast, easy
problem counts corners twice
Add perimeter (48 + 48 + 26 +26) = 148.0 ft. or 2(L + W)
148.0 ft x 8.0 ft x 0.83 ft = 982.72 cf.
Sectioning
Breaks construction down into smallerpieces
More accurate
More time consuming
Use where large volumes of concreterequired, but unusual angles, etc.
-
8/8/2019 1.Estimating Concrete and Rebars
3/8
Sectioning red 2) 24.33 ft x 8.0 ft x 0.83 ft = 323.10 cf.
blue 2) 48.0 ft x 8.0 ft x 0.83 ft = 637.44 cf. sum = 960.54 cf
Centerline length
Avoids adding corners twice
Most common method in commercial wk
Useful for conc., rebar, walls, etc.
Formula to know:
Outside Building line length or perimeter (4* thickness or width of any given strip)
Complete in-class activity #1calculate the amount of footingconcrete required
SOL = Po (4T)
distance from centerline of theconstruction line to the building line
= 10 inches (0.83 inches)
-
8/8/2019 1.Estimating Concrete and Rebars
4/8
Centerline length method
Building line length = (perimeter) = 148.0 ft
Distance from centerline to bldg. line =
148.0 ft (4*.83) = 144.67 (true perimeter)
144.67 ft * 8 ft * 0.83ft = 960.59 cf.
Centerline length caveat
Only works if all walls and offsets are 90
Quick estimating tip
Short cut for estimating concrete in anyfooting
Multiply the cross-section in square inchesby 0.000257. Gives CY/lineal ft
Multiply that result by number of lineal feetin the footing
-
8/8/2019 1.Estimating Concrete and Rebars
5/8
Quick estimating tip illustrated
Given: A footing 7-in deep and 22-in wideis 160-ft long.
Calculate the yards of concrete reqd.
(7" * 22")*160' * .000257 = 6.33 CY
DO NOT Convert inches to decimals except whenpart of next foot (e.g., 38-7)
Estimating footings (pads)
Estimating footings (pads)
List the description or title from scheduleProvide HO#2
-
8/8/2019 1.Estimating Concrete and Rebars
6/8
Calculating Rebar
Rebar weight perlinear foot
See text (pg. 133 forsplicing req.
Calculating formwork
2 Types Structural (concrete) formwork
Foundations
Walls
Columns
Beams
Flatwork (flat concrete work) Sidewalks
Driveways Slabs
Structural (concrete) formwork
Formwork measured in SFCA
-
8/8/2019 1.Estimating Concrete and Rebars
7/8
Measuring concrete walls
Use centerlinelength * height* 2
Refer to HO#1
Calculate the formworkand concrete required forthe wall
Labor placing concrete infoundations
50- 70 CY/8 hr day(direct from truck tofooting)
How is labor calculated?
Duration =Quantity of Work
Rate of Production
Using HO #1 calculate the duration of the footinginstallation
(0.35 labor hours/CY use a price of 35$/hour/man
-
8/8/2019 1.Estimating Concrete and Rebars
8/8
Course objectives
Correctly setting up an estimate
Calculating the perimeter
Setting up the concrete foundation takeoff Calculating concrete labor and material
costs