1.Budget and Cash Flow
Transcript of 1.Budget and Cash Flow
-
7/30/2019 1.Budget and Cash Flow
1/10
Budget and Cash Flow
For preparing the budget the following should be
prepared.
2601771
Program for Completion of the Project
This is a bar chart to be prepared by planning
engineer in consultation with Project Manager and
all section engineers. This should be based oncontinual improvement theme and with the help of
NET WORK. This will be evaluated by SBU heads.
The assumption to be considered is Release of
Drawings, Finalization of Design/Approval, and
Release of work fronts and Mobilization of major
equipment.
The critical assume, the non achievement of which
may impact the whole budget, should be
highlighted with a special covering note by PM.
Time cycle for cyclic nature activities.
Achieved Vs Projected for Balance work.
Production achieved for major activities.
Achieved Vs Projected for Balance work.
Support required from HO department wise.
-
7/30/2019 1.Budget and Cash Flow
2/10
THE TURNOVER STATEMENT
The list of BOQ should be brief. Major BOQ itemshould be 80 to 90% and 10 to 20% should be
considered for miscellaneous bead. Site has to give
miscellaneous grouped items. The out of scope
work (OOSW) should be indicated separately as
shown in formats.
ESCALATION
Escalation working should be for the total job (JTD
+ Balance), latest indices to be considered and the
month of indices to be mentioned. Provisional
indices if considered should be highlighted.
MONTHLY COST BUDGET
Abstract sheet of planned revenue (income) and
expenses. JTD cost should be in line with the cost
booked in FA. Income with WIP.
Certified Turnover JTD
Uncertified Turnover JTD
(NBTR)-WIP / Deferment of installation cost.
-
7/30/2019 1.Budget and Cash Flow
3/10
Site WIP
Work done billable but not billed. Cut and bentbars at site at BOQ rate.
Full length bars lying at yard (Issued from stores)
less wastage.
Materials
The abstract of month wise cost of materialsrequired based on Turnover sheet. The backup
sheet of month wise quantities of materials based
on T.O.sheet. This sheet shall form the basis of
procurement of HO controlled material.
Major Construction Material
Mix Design & JMF authenticated by HO QA/QC, unitmaterial price considered authenticated by HO
purchase department. Based on this the
construction materials to be calculated including
wastage.
Subcontractor Cost
Abstract sheet of subcontractor /PRW/labour supply
cost monthwise. The backup sheet monthly B.O.Q
items as per turnover statement & non BOQ
requirement support from subcontractor
-
7/30/2019 1.Budget and Cash Flow
4/10
/PRW/labour supply for arriving monthly cost.
Approved existing rates to be considered. New
rates if applicable, that should be highlighted to
HO. 80 to 90% of subcontractor / PRW/ laboursupply quantities rate and amount must be given.
Balance can be added to miscellaneous items.
Plant and Machinery Cost
Abstract sheet of Plant and machinery cost Month
wise Backup sheet Turnover statement for BOQ &
Non BOQ items for arriving at Monthly cost.
Production per hour should be match with time
cycle. Fuel norms and spares norms as per
authenticated by CPE department. Plant required
for establishments like Offices, Stores, Labour
camps, Workshops etc., duration must be
conjunction with work programme.
Hire Charges:
Internal hire charges should be 2.35% of purchase
value per month and the external hire charges
details should be given. The commissioning data
and duration of usages should be mentioned.Installation Cost
Breakup installation costs incurred till date under
varies heads as indicated in the formats.
-
7/30/2019 1.Budget and Cash Flow
5/10
Installation costs to be incurred for balance works
should be substantiated with the work programme.
Installation cost is to be worked out on the basis of
estimation and drawings. Under each items thedetailed break up of cost which constitute 80 to 90
% of the overall cost should be given.
Allocable expenses
The cost is basically divided into two parts
1)Shuttering, staging, sheet piles etc
2)Capital expenditures
Shuttering, staging, sheet piles etc
The cost is to be tracked separately for transfer
from other sites and new purchases.
For the Project specific shuttering such as Steel
form work of special shape, steel liners, Plywood
etc the entire cost is to be charged off to the
Project and only scrap values is to be considered in
other income.
For Doka sheet piles and other standard form works
and staging materials which can be repeatedly
used from Project to Project 25% of the purchased
value per annum. Quarterly should be charged to
-
7/30/2019 1.Budget and Cash Flow
6/10
the cost for the new purchases all fabrication done
at site.
For the materials transferred from other sites 25%
per annum of the original cost incurred elsewhere
in other Projects to be charged quarterly to the
cost. The period to be reckoned will be from the
time of Purchase / receipt of materials upto the
date on which the items are declared surplus and
taken outside.
Capital expenditures
These are the expenses for the items fabricated /
manufactured in the sites such as launching
stress, EOT, Barges, Bridge builders / or the
capital repairs carried out at sites as approved byCPE. For such items if the entire amount is
capitalized then the internal hire charges are to
be considered in Plant and Machinery cost.
Manpower cost
The cost should be prepared month wise. The
cost is bifurcated under the needs salaries and
-
7/30/2019 1.Budget and Cash Flow
7/10
wages. Salary comprises of Management Salaries
and Non Management salaries like supervisory
and staffs. The wages comprises the salaries of
Operators, Mechanics, Welders and Electricians.The salary should be done individual wise. This
can be group based as Management, Non
management, Supervisory staffs, Operators,
Helpers, Mechanics, Welders and Electricians etc
under different categories such as HO monthly,
local monthly and local daily. The man powercost should be authenticated by HR department.
Other cost
This should be made month wise which are to
worked out on the basis of estimation / trends of
costs for the last three months. The major items
such as royalties, Insurances, Guarantees,
Interest detail should be given. Finance cost
apart from BG charges, Bank charges and
interest on advances to clients, the interest on
funding from / to corporate offices is also to be
-
7/30/2019 1.Budget and Cash Flow
8/10
included. The other cost to be authenticated by
HO finance department.
Cash flow
Cash flow consists of Cash inflow, Cash outflow
and Net in flow. This is to be prepared month
wise.
Cash In flow
The assumptions to be considered for Cash
inflow are as follows.
1) Payment / Recovery of advance2) Release of retention
3) Income tax % considered
4) Release of withheld / Uncertified payments
5) Payments of monthly RA bills etc (Lead
period)
Cash Out flow
-
7/30/2019 1.Budget and Cash Flow
9/10
The assumptions to be considered for Cash Out
flow are as follows.
1) Credit period for the payment of major
construction materials.
2) Stock level of major materials.
For working out of cash flow the following steps
are to be followed.
1) Monthly consumption (as worked out in the
cost budget)
2) Monthly stock level - To be assessed for the
balance period.
3) Monthly purchase = Monthly consumption
+ Closing stock Opening stock
4) Monthly creditors To be assessed for the
balance period.
5) Cash Out flow = Opening Creditors +
Purchase Closing Creditors.
Conclusion:
It is so necessary to know about the
calculations the cash inflow, Cash Out flow
-
7/30/2019 1.Budget and Cash Flow
10/10
and Budget preparations to control the Profit
and loss of the particular Project.