1.Budget and Cash Flow

download 1.Budget and Cash Flow

of 10

Transcript of 1.Budget and Cash Flow

  • 7/30/2019 1.Budget and Cash Flow

    1/10

    Budget and Cash Flow

    For preparing the budget the following should be

    prepared.

    2601771

    Program for Completion of the Project

    This is a bar chart to be prepared by planning

    engineer in consultation with Project Manager and

    all section engineers. This should be based oncontinual improvement theme and with the help of

    NET WORK. This will be evaluated by SBU heads.

    The assumption to be considered is Release of

    Drawings, Finalization of Design/Approval, and

    Release of work fronts and Mobilization of major

    equipment.

    The critical assume, the non achievement of which

    may impact the whole budget, should be

    highlighted with a special covering note by PM.

    Time cycle for cyclic nature activities.

    Achieved Vs Projected for Balance work.

    Production achieved for major activities.

    Achieved Vs Projected for Balance work.

    Support required from HO department wise.

  • 7/30/2019 1.Budget and Cash Flow

    2/10

    THE TURNOVER STATEMENT

    The list of BOQ should be brief. Major BOQ itemshould be 80 to 90% and 10 to 20% should be

    considered for miscellaneous bead. Site has to give

    miscellaneous grouped items. The out of scope

    work (OOSW) should be indicated separately as

    shown in formats.

    ESCALATION

    Escalation working should be for the total job (JTD

    + Balance), latest indices to be considered and the

    month of indices to be mentioned. Provisional

    indices if considered should be highlighted.

    MONTHLY COST BUDGET

    Abstract sheet of planned revenue (income) and

    expenses. JTD cost should be in line with the cost

    booked in FA. Income with WIP.

    Certified Turnover JTD

    Uncertified Turnover JTD

    (NBTR)-WIP / Deferment of installation cost.

  • 7/30/2019 1.Budget and Cash Flow

    3/10

    Site WIP

    Work done billable but not billed. Cut and bentbars at site at BOQ rate.

    Full length bars lying at yard (Issued from stores)

    less wastage.

    Materials

    The abstract of month wise cost of materialsrequired based on Turnover sheet. The backup

    sheet of month wise quantities of materials based

    on T.O.sheet. This sheet shall form the basis of

    procurement of HO controlled material.

    Major Construction Material

    Mix Design & JMF authenticated by HO QA/QC, unitmaterial price considered authenticated by HO

    purchase department. Based on this the

    construction materials to be calculated including

    wastage.

    Subcontractor Cost

    Abstract sheet of subcontractor /PRW/labour supply

    cost monthwise. The backup sheet monthly B.O.Q

    items as per turnover statement & non BOQ

    requirement support from subcontractor

  • 7/30/2019 1.Budget and Cash Flow

    4/10

    /PRW/labour supply for arriving monthly cost.

    Approved existing rates to be considered. New

    rates if applicable, that should be highlighted to

    HO. 80 to 90% of subcontractor / PRW/ laboursupply quantities rate and amount must be given.

    Balance can be added to miscellaneous items.

    Plant and Machinery Cost

    Abstract sheet of Plant and machinery cost Month

    wise Backup sheet Turnover statement for BOQ &

    Non BOQ items for arriving at Monthly cost.

    Production per hour should be match with time

    cycle. Fuel norms and spares norms as per

    authenticated by CPE department. Plant required

    for establishments like Offices, Stores, Labour

    camps, Workshops etc., duration must be

    conjunction with work programme.

    Hire Charges:

    Internal hire charges should be 2.35% of purchase

    value per month and the external hire charges

    details should be given. The commissioning data

    and duration of usages should be mentioned.Installation Cost

    Breakup installation costs incurred till date under

    varies heads as indicated in the formats.

  • 7/30/2019 1.Budget and Cash Flow

    5/10

    Installation costs to be incurred for balance works

    should be substantiated with the work programme.

    Installation cost is to be worked out on the basis of

    estimation and drawings. Under each items thedetailed break up of cost which constitute 80 to 90

    % of the overall cost should be given.

    Allocable expenses

    The cost is basically divided into two parts

    1)Shuttering, staging, sheet piles etc

    2)Capital expenditures

    Shuttering, staging, sheet piles etc

    The cost is to be tracked separately for transfer

    from other sites and new purchases.

    For the Project specific shuttering such as Steel

    form work of special shape, steel liners, Plywood

    etc the entire cost is to be charged off to the

    Project and only scrap values is to be considered in

    other income.

    For Doka sheet piles and other standard form works

    and staging materials which can be repeatedly

    used from Project to Project 25% of the purchased

    value per annum. Quarterly should be charged to

  • 7/30/2019 1.Budget and Cash Flow

    6/10

    the cost for the new purchases all fabrication done

    at site.

    For the materials transferred from other sites 25%

    per annum of the original cost incurred elsewhere

    in other Projects to be charged quarterly to the

    cost. The period to be reckoned will be from the

    time of Purchase / receipt of materials upto the

    date on which the items are declared surplus and

    taken outside.

    Capital expenditures

    These are the expenses for the items fabricated /

    manufactured in the sites such as launching

    stress, EOT, Barges, Bridge builders / or the

    capital repairs carried out at sites as approved byCPE. For such items if the entire amount is

    capitalized then the internal hire charges are to

    be considered in Plant and Machinery cost.

    Manpower cost

    The cost should be prepared month wise. The

    cost is bifurcated under the needs salaries and

  • 7/30/2019 1.Budget and Cash Flow

    7/10

    wages. Salary comprises of Management Salaries

    and Non Management salaries like supervisory

    and staffs. The wages comprises the salaries of

    Operators, Mechanics, Welders and Electricians.The salary should be done individual wise. This

    can be group based as Management, Non

    management, Supervisory staffs, Operators,

    Helpers, Mechanics, Welders and Electricians etc

    under different categories such as HO monthly,

    local monthly and local daily. The man powercost should be authenticated by HR department.

    Other cost

    This should be made month wise which are to

    worked out on the basis of estimation / trends of

    costs for the last three months. The major items

    such as royalties, Insurances, Guarantees,

    Interest detail should be given. Finance cost

    apart from BG charges, Bank charges and

    interest on advances to clients, the interest on

    funding from / to corporate offices is also to be

  • 7/30/2019 1.Budget and Cash Flow

    8/10

    included. The other cost to be authenticated by

    HO finance department.

    Cash flow

    Cash flow consists of Cash inflow, Cash outflow

    and Net in flow. This is to be prepared month

    wise.

    Cash In flow

    The assumptions to be considered for Cash

    inflow are as follows.

    1) Payment / Recovery of advance2) Release of retention

    3) Income tax % considered

    4) Release of withheld / Uncertified payments

    5) Payments of monthly RA bills etc (Lead

    period)

    Cash Out flow

  • 7/30/2019 1.Budget and Cash Flow

    9/10

    The assumptions to be considered for Cash Out

    flow are as follows.

    1) Credit period for the payment of major

    construction materials.

    2) Stock level of major materials.

    For working out of cash flow the following steps

    are to be followed.

    1) Monthly consumption (as worked out in the

    cost budget)

    2) Monthly stock level - To be assessed for the

    balance period.

    3) Monthly purchase = Monthly consumption

    + Closing stock Opening stock

    4) Monthly creditors To be assessed for the

    balance period.

    5) Cash Out flow = Opening Creditors +

    Purchase Closing Creditors.

    Conclusion:

    It is so necessary to know about the

    calculations the cash inflow, Cash Out flow

  • 7/30/2019 1.Budget and Cash Flow

    10/10

    and Budget preparations to control the Profit

    and loss of the particular Project.